EIA Report for Noor Mahal Project
EIA Report for Noor Mahal Project
AT
VILLAGE:- PHUSGARH,
DISTT. KARNAL, HARYANA.
BY
ENVIRONMENT CONSULTANT
OCEAO-ENVIRO Management Solutions (India) Pvt. Ltd.
QCI – NABET Certificate No: NABET/EIA/1821/IA 0033
217, 1st Floor, Sector 12, Vasundhara, Ghaziabad, U.P 201012
www.oceaoenviro.com | [email protected]
Compliance to Terms of Reference (ToR) Points Hotel, Restaurant & banquet Hall
“Noor Mahal” Village Phusgarh, Distt. Karnal, Haryana.
S. No. Compliance
1. The State Government/SPCB to take action HSPCB has initiated Credible action
against the project proponent under the against M/s Jewel Classic Hotels
provisions of the section 19 of the Environment Pvt. Ltd. under section 19 of the
(Protection) Act, 1986, and further no Consent to Environment (Protection) Act, 1986.
Operate or Occupancy Certificate to be issued Notice Copies from special
till the project is granted EC. environment Kurukshetra enclosed
as Appendix I.
2. The Project Proponent shall be required to Noted.
submit a bank guarantee equivalent to the
amount of remediation plan and natural and
community resource augmentation plan with the
SPCB prior to the grant EC. The quantum shall
be recommended by the SEAC and finalized by
the regulatory authority. The bank guarantee
shall be released after successful implementation
of the EMP, followed by recommendations of
the SEAC and approval of the regulatory
authority.
Specific TOR points for EIA/ EMP Study
3. The PP should submit an affidavit from the Complied. The project proponent
Director of the Company giving graphical details has submitted an affidavit giving
of Construction and utility services already done. graphical details of construction and
utility services already done
enclosed as Appendix II.
4. The PP Should submit approved building plan Complied. The project proponent
along with service plan. has submitted the approved plan
along with service plan
5. The PP should submit NOC from the Forest Complied. The project proponent
Department. has submitted NOC from the Forest
Department.
6. The NOC from the Airport Authority of India. Complied.
7. The PP should submit the permission from the Complied.
Fire Department.
8. The PP should provide the details of internal and Complied.
external developments.
Additional TOR points for EIA/ EMP Study
9. Latest status report of the project verified by the Latest petition copy verified by RO
RO, MoEF & CC/RO, HSPCB to be included. is being enclosed as Appendix III.
10. Confirmation of the land – use as per the Complied. The confirmation of the
“Master-Plan” of the area from DTCP. land-use plan has been submitted.
11. Approval of Air Port Authority of India Complied. Approval of Air Port
regarding the present height of the building Authority of India regarding the
wherever applicable. present height of the building is
granted.
Compliance to Terms of Reference (ToR) Points Hotel, Restaurant & banquet Hall
“Noor Mahal” Village Phusgarh, Distt. Karnal, Haryana.
7. Details on flora and fauna and socio- Details are given in Chapter 3 of
economic aspects in the study area EIA/EMP Report
Details given in section 3.12 (table 10)
of chapter 3 of EIA/EMP Report
CHAPTER-1
INTRODUCTION
1.1 Preamble
EIA is a technical exercise, to predict environmental impacts, assess their significance, and
provide recommendations for their mitigation. This assessment covers construction and
operation of the development. The report covers a wide range of technical disciplines and
covers areas such as noise, air quality, ecology, contamination, water quality & hydrology,
local architecture, landscape, sustainability and socio-economics.
Identification and characterization of critical environmental impacts allow the public and
government to form a view about the environmental acceptability of a developmental
project and what conditions should apply to mitigate or reduce those risks and impacts.
This report has been prepared as per the EIA Notification, 2006 and its amendments thereof
i.e. based on MoEF & CC notification dated 14.03.2017. EIA Guidance Manual for
Building Construction, Township and Area Development based on the Terms of Reference
(ToR) approved by the SEIAA, Haryana and additional & Specific ToR points suggested
by them vide letter no. HR/SEAC/ 18/ 946 dated 09.08.2018.
The project is under violation of EIA notification 2006, although after being a Category B,
schedule 8(a) project which does not require EIA/EMP report a detailed EIA/EMP study
has been carried out as per the guidelines issued by MoEF & CC for the violation projects.
M/s Jewel Classic Hotels Pvt. Ltd. has constructed their project i.e. “Hotel, Restaurant &
banquet Hall “Noor Mahal” at village Phusgarh, Dist- Karnal, Haryana, as per OM dated
14.03.2017
• M/s Jewel Classic Hotel Pvt. Ltd. had already constructed “Noor Mahal” project having
Hotel, Restaurant, Banquet Hall, Recreational Park & Health Club.
• The total area for Hotel, Restaurant, Banquet Hall as per CLU is 12,140.46 sqm and as
per part Occupational Certificate the area developed is 12,685.30 sqm & sanction plan
is 18,210.69 sq.m.
• The total area for Health Club as per CLU is 7,284.28 sqm and as per Part Occupational
Certificate the area developed is 1,521.55 sqm & sanction plan is 7284.28 sqm
• The total area for Recreational Park as per CLU is 9,204.22 sqm and as per Part
Occupational Certificate the area developed is 231.253 sqm & sanction plan is 920.42
sqm
• M/s Jewels Classic Hotels Pvt. Ltd., had already constructed built-up area which was
less than 20,000 sqm to meet the validity of CLU & OC as per T&CP, Haryana.
Construction was done after obtaining Consent to Establish (CTE).
• Further, when expansion of the project was done as per sanctions the built-up area
increased to 24,671.106 sqm which attracts Environment Clearance under EIA
notification, 2006.
• As the plan was approved having built-up area 24,671.106 sqm but area developed was
19,537.296 sqm. After expansion of the project proponent went to for Environment
Clearance for the whole built-up area (24,671.106 sqm). In which we comes to know
our project comes under violation case as they have constructed the project prior to
Environment Clearance.
• Hence, the project comes under the violation case as per the EIA notification, 2006 and
its amendments.
• The case was earlier applied on September 2013.
• Further as per new guidelines, on 13.04.2018 we applied for Environment Clearance in
which we have applied under the violation case as per OM 14.03.2017
• On 09.08.2019 we received the TOR vide no. - HR/SEAC/ 18/ 946.
• On the basis of TOR and detailed project study we preferred this report containing
EIA/EMP, Remediation and Augmentation Plan.
The basic information about the project is as given below the Table 1.1.
The project proponent for the Hotel, Restaurant & Banquet Hall project “Noor Mahal” is
M/s Jewel Classic Hotels Pvt. Ltd. The Company has its registered office at:
Hotel Jewels, Kunjpura Road, Karnal, Haryana- 132001.
The project site M/s Jewel Classic Hotels Pvt. Ltd. of Hotel, Restaurant & Banquet Hall
“Noor Mahal” located at Village Phusgarh, Dist- Karnal, Haryana. The plot area measuring
28,628.96 m2 (or 7.07 acres) built up area is increase to 24,671.106 sq.m. The project has
access through the 24 m wide Sector road connecting the NH-1.
• On-site monitoring of environmental parameters viz. soil, water, ambient air and ambient
noise and within 10 km radius from project site sample having total 5 location of each
parameters;
• Secondary data collection of land use pattern, topography, geological setting,
meteorology, flora & fauna of the area and socio-economic environment
• Compilation of baseline environmental monitoring of environment parameter and social
scenario of the study area within a radius of 10 km around the project site based on field
studies covering one month (February 2019) and secondary data collection;
• Identification, prediction and evaluation of potential environmental impacts expected
during the construction and operation phase of the project;
• Preparation of environmental monitoring programme in construction and operation
phases
• Preparation of pollution control and mitigation measures, Environmental Management
Plan (EMP) and approximate environmental budget allocation for the project.
• Incorporation of Terms of Reference (TOR) points
• Preparation of Damage assessment, budgetary plan with Remediation plan & natural
augmentation for the project site.
• Collection, collation and analysis of regional and local environmental status for various
environmental attributes (like topography, geology, ambient air quality, meteorology, water
quality, noise level, soil characteristics and land use, transport, settlement status and socio
economic aspects etc.).
Stage–III
• Compilation of environmental baseline data of the study area generated through primary field
survey, monitoring of environmental parameters and secondary data collected from literature
review, research institutions and Govt. departments.
Stage–IV
• Assessment of Environmental Impacts by predicting the scale and extent of changes associated
with the project and their subsequent effects on environment against the baseline
environmental condition, and evaluating the significance of such impacts against accepted
criteria.
Stage-V
• Preparation of measures to mitigate significant impacts (evaluated from the impact prediction
process) by proposing applicable alternatives and control measures.
• Finally, development of appropriate Environmental Management and Monitoring Plan to
ensure that suitable mitigation measures are proposed to minimize the environmental impact
both during construction and operation stage of the project.
• Assessment of damage caused to Environment by considering the mitigation measures
adopted & preparation of Remediation & Damage assessment plan.
1.9 Categorization of the Project & Environmental Clearance Process
As per EIA Notification, 2006, the “Building and Construction” project covering built-up
area 24671.106 sqm greater than 20,000 sq.m but less than 150,000 sq.m area listed in
Category B in the item 8(a) of the Schedule and requires prior Environmental Clearance from
the Ministry of Environment and Forests (MoEF)/ State Level Environmental Impact
Assessment Authority (SEIAA). The project will be appraised by the Expert Appraisal
Committee on the basis of Form 1, Form 1A, and conceptual Plan and no Environmental
Impact Assessment (EIA) report but we are preparing EIA Report due to violation.
S. No. Permission Departmen Permissible FAR as per CLU & Sanction FAR as per Sanction
t Plan
CLU Sanction Area
Plan
Memo. No. K- Sanctioned 12140.46 12140.46 Sqm
669-10DP- Vide No. Sqm
CLU & T&CP 2006/2488 1329
1. Sanction (Ann. 1(a))
Plan for the Memo. No. K- Sanctioned 9204.22 9204.22 Sqm
project site 737-JE(B)- Vide No. Sqm
2009/1028 4431
(Ann. 1(b))
Memo. No. K- Sanctioned 7284.28 7284.28 Sqm
738-JE(B)- Vide No. Sqm
2009/1031 4834
(Ann. 1(c))
Prosecution HSPCB The unit has already prosecuted under Air & Water act (EPA 1986)
2. (Credible in 2015 by HSPCB as per guidelines of EIA notification 2006.
Action)
Memo. No. 4189 12685.30 sqm 12685.30 sqm
dated 30-09-2010
Part Memo. No. 202 231.253 sqm 231.253 sqm
3. Occupation T&CP dated 11-01-2012
Environmental Clearance
Under the Environment Impact Assessment Notification, 2006, the project will obtain
environment clearance. The project shall abide by all applicable provisions of the Environment
Protection Act, 1986 and Rules formed there under.
Consent to Establish & Consent to Operate
The unit had already obtained CTE & CTO before start of construction. As the project is a
violation case and project has been prosecuted. Therefore, CTE/CTO are null & void and
project proponent will obtain a fresh after obtaining Environment Clearance (EC).
The unit has already prosecuted under Air & Water act (EPA 1986) in 2015 by HSPCB as per
guidelines of EIA notification 2006.
Gives the names of the technical team involved in the report preparation along with
Accreditation of the consultant from the quality council of India.
Chapter 12: Corporate Environmental Responsibility
The chapter describes certain role and activities which are to be carried out as a corporate
practice for environmental compliance and safe guard to the environment.
Chapter 13: Remediation & Natural Augmentation Plan
This chapter describes about the methods that has to taken to cover up the damage made by the
construction and operation phase of the project
This present report is prepared based on scientific principles and professional judgment with
resultant subjective interpretation. Professional judgments expressed herein are based on the
available data and information collected from primary and secondary sources.
CHAPTER-2
PROJECT DESCRIPTION
The project is over an area of 7.07 acres (28,628.96 m2) with ground coverage of 7,904.92 m2.
The salient features of the project are given in the Table 2.1 below.
The master site layout plan of the project showing plot boundary, location of various building
blocks, internal & external roads, landscape & some other features is enclosed as Annex 2(b).
The various land use, FAR and ground coverage permitted as per the zoning plan vis-a-vis
achieved & permissible is given below in the Table 2.2. Total plot area is 7.07 acre (28,628.96
m2) is to be developed for this Hotel, Restaurant & Banquet Hall, Recreational Park and Health
Club.
Table 2.2 Permitted Land use Details of Hotel, Restaurant & Banquet Hall, Recreational
Park and Health Club Scheme
The project is Hotel, Restaurant & banquet Hall, Recreational Park & Health Club developed by
M/s Jewel Classic Hotels Pvt. Ltd. consisting of Hotel, Restaurant & Banquet Hall, Recreational
Park and Health Club namely “Noor Mahal” located at Village Phusgarh, Dist- Karnal, Haryana.
The total plot area of the project is 7.07 acre (28,628.96 m2). The land is earmarked for
commercial development as per the local development/ zoning plan issued by Town & Country
Planning (T&CP). The project had been developed as Lower Ground Floor, Mezzanine Floor,
Upper Ground Floor, 3 Floors & basement. The total Built-up area is 24,671.106 sqm. & since it
has been constructs without obtaining Environment Clearance therefore, it amounts to violation
of EIA notification of 2006. As per OM 14.03.2017 issued by MoEF&CC, GOI.
The primary purpose of hotels is to provide travelers with shelter, food, refreshment, and similar
services and goods, offering on a commercial basis things that are customarily furnished within
households but unavailable to people on a journey away from home. Historically hotels have also
taken on many other functions, serving as business exchanges, centers of sociability, places of
public assembly and deliberation, decorative showcases, political headquarters, vacation spots,
and permanent residences. The basic purpose is to cater the local functions, marriage in Banquet
Hall and provide world class recreational services in the health club & yoga club.
The project site is located at Village Phusgarh, Dist- Karnal, Haryana. The geographical location
of the project site is shown in Table 2.3:
The location of project site is shown in the map below at Figures 2.1.
The project has access through the 60 m wide Sector road connecting the NH-1 and SH-7. The
project area is well connected to network of roads leading to various parts of NCR and railway
by New Delhi-Jaipur section of rail network. The distance and direction of nearest highway,
railway station and airport are given below:
6 m wide roads are kept for car/vehicles parking within the commercial development project.
The parking details for the project are illustrated below:
Parking Facilities
Adequate parking (404 ECS) provision is provided for vehicles parking in the project. Besides
this, internal road of 6 m width within the project is being facilitated smooth traffic movement.
Parking Provided:
Area for Basement parking = 4293.40m2
Area required for 1 ECS of Basement parking = 35 m²
Parking provided for Basement parking = 122 ECS
The project complex is connected through the existing 60 m wide Sector road connecting the
NH-1. Internal roads of adequate width and separate entries and exits will be provided for
smooth and one-way movement of traffic. The increase in traffic due to the project is marginal
compared to the existing high volume of traffic in the area, and therefore the impact is marginal.
The power supply is being supplied by Uttar Haryana Bijli Vitran Power Nigam (UHBVN). The
connected load for the Commercial Project is approx. 1500 KVA. There are 3 no. of DG sets of
total capacity 1500 KVA (3 X 500) for power back up in the Project. 1 DG set of 500 kVA is
taken as standby & 2 DG sets of 500 kVA each are operational. The DG sets is equipped with
acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion.
In operation phase, total water requirement for the project is 155 KLD. Details of water
requirement and its breakup, source of water and water balance are given in Table below. Out of
total water requirement, 110 KLD will be domestic water met from the Ground Water supply.
The sewage generated during operation phase (96 KLD) is treated in STP of SAFF technology of
150 KLD capacity. The treated sewage will be recycled/ reused for toilet flushing horticulture in
the project site. Therefore, during normal operations, there will be zero discharge, as the entire
treated sewage will be recycled. The item wise break-up of water requirement is given in the
Table 2.6 and source of water and reuse of treated sewage is given in the Table 2.7 below.
@ 100%
5 KLD
FLUSHING (5 KLD)
RESIDENT STAFF
@ 90 %
86 KLD
7 KLD
HVAC COOLING (7 KLD)
@ 100%
FLUSHING (5 KLD)
5 KLD @ 90 %
RESIDENT STAFF
85 KLD
The details of quantity of sewage and sewage collection, treatment, reuse and disposal are given
in the Table 2.8. Location of the common STP “Noor Mahal” is shown in Annex 2(c).
Proposed storm water system consists of pipe drain, catch basins and seepage pits at regular
Intervals for rain water harvesting and ground water recharging. For basement, the rainwater
from ramps will be collected in the basement storm water storage tank. This water will be
pumped out to the nearest external storm water drain. The storm water disposal system for the
premises shall be self-sufficient to avoid any collection/ stagnation and flooding of water.
Maximum harvesting will be done within the site. Therefore, it has been decided to provide
sufficient rain water harvesting at selected locations, which are liable to catch the maximum run-
off from the area.
The rainwater collected from the rooftop and other paved areas within the project area will be
conveyed into the rainwater harvesting system consisting of Desilting-cum-filter chamber, Oil &
grease separator and Recharge pit with bore well for recharge into the groundwater.
Rainwater harvesting plan is as per the design approved in the manual issued by the Government
of India. The plan & section of rainwater harvesting pit & recharge well is enclosed in Annex
2(d). The layout plan showing drainage and location of RWH pits is enclosed as Annex 2(e).
Details of rainwater harvesting calculation are given in Table 2.9 below:
The rainwater will be collected through piped drains and conveyed into rainwater harvesting
system. All storm water drains have been designed for adequate size and slope such that there
shall not be any flooding in the site. It shall be ensured that no wastewater shall enter into storm
water drainage system.
The topsoil was preserved separately and has been reused for horticultural purpose. Waste
construction materials has been recycled and waste construction material had been sold to the
authorized recyclers wherever applicable and surplus excavated earth is disposed as per norm
after using it for filling of vacant low lying lands of project.
The details of collection recycle and disposal of solid wastes are given in the Table 2.10 below.
The management of solid wastes during operation phase is shown through the following Figure
2.4 & 2.5 respectively.
Nature and quantity Hotel, Restaurant 255 kg/day( Guest + Banquet Hall + Staff)
& Banquet Hall
Restaurant 40 kg/day
Landscape waste 31.8 kg/day
Collection and disposal Solid wastes generated is segregated into biodegradable and
non-biodegradable components and collected in separate bins.
Both the biodegradable & non-biodegradable/ recyclable wastes
will be sold to authorized vendors for recycling of non-
Solid Waste
Construction
Waste Food Waste
As per MSW
Rules, 2000 and
amended Rules,
2008
Construction Empty Excavated
waste, Cement Soil
Broken Bricks, Bags
Waste Plaster
Solid Waste
Inert Hazardous
Total green area measuring 8,588.69 m2 i.e. 30 % of the total area had been provided within
project site. 10.5% of the total area (3,000 sq. m) will be dedicated for green belt development &
19.5% (5582.65 sq. m) of project area is being developed as organized greens. The list of
existing trees is shown below in Table 2.11.
Adequate fire protection facilities is installed including fire detectors, fire alarm and fire fighting
system to guard the building against fires. All fire protection facilities are designed as per the
latest National Building Code. The approvals in this regard will be obtained prior to installation
of the fire protection equipments. Fire NOC is enclosed.
• Fire extinguishers
• Hose reel and wet riser
• Yard hydrants
• Automatic sprinkler system in the building
• Manually operated electric fire alarm system
• Automatic detection and alarm system
• Underground and terrace level fire water storage tanks
• Electric and diesel driven fire pumps
The following drawings had been prepared at project design stage separately for layout, building
elevation, traffic circulation and surface parking, basement plan showing parking & services,
landscape and greenery development, rainwater harvesting, plumbing services, fire-fighting,
lightening earth pits & arresters etc. as per specifications and building codes.
CHAPTER 3
DESCRIPTION OF ENVIRONMENT
The present chapter covers baseline environmental condition of the study area. In order to get an
idea about existing state of environment and to set-up baseline environmental condition of the
project area various environmental parameters such as meteorology, air-quality, water quality,
soil quality, noise level, ecology and socio-economic environment have been studied/ monitored.
• 500 m radius from the project boundary for land-use pattern and environmental primary survey
viz tree survey, vegetation type etc.
• 2 km radius from the project site for monitoring of environmental parameters such as soil,
water, air and noise and socio-economic condition
• Baseline environmental study has been done at 5 locations within 10 km as per TOR given.
• The environmental sensitive features are identified within 15 km of the project site.
The methodologies adopted for carrying out the environmental study and set-up the baseline
environmental condition are as follows:
• Site visit & identification of environmental features within 500 m radius of project site
• Site survey and collection of primary data from project site and surroundings
• Selection of monitoring locations and monitoring & analysis of environmental parameters viz.
soil, water, air and noise
• Secondary data collection from literature review, district and state departments
• Brief idea about the socio-economic condition of the people of the study area
• Data compilation
The Google image of the project site and its surroundings is shown at Figure 3.1 and the project
vicinity map is presented at Figure 3.2. The features within 500 m surrounding the project site is
shown the vicinity map enclosed as Annex 3(a).
Figure 3.1: Google Image of the Project Site and its Surroundings
Figure 3.2: Vicinity Map and Surrounding Features of 10 km of the Project Site
The environmental sensitive features nearest to the project site are given in the Table 3.1.
3.4 Topography
The project area possesses slightly undulating terrain. The Contour plan of the project site and
Contour Map of 10 Km of project are enclosed as Annex 3(b) and 3(b 1 ) respectively. Highest
contour level is 802.30 m & the lowest level is 800.50 m. Difference between the highest &
lowest level is 1.8 m.
There is no vulnerability of subsidence. Proper greening & paving of area did not caused soil
erosion problem recorded during construction.
3.4.3 Seismicity
The area under study falls in Zone-IV, according to the Indian Standard Seismic Zoning Map.
Suitable design will be made to mitigate the seismic impacts.
The project site for M/s Jewel Classic Hotels Pvt. Ltd. of Hotel, Restaurant & Banquet Hall
“Noor Mahal” located at Village Phusgarh, Dist- Karnal, Haryana. The total plot area of the
project is 7.07 acre (28,628.96 m2) & built up area is 24,671.106 m2.
The project site is earmarked for commercial project as per the Change of Land Use from Town
& Country Planning, Haryana is enclosed as Annex 3(c). The land is earmarked for commercial
project as per the local development/ zoning plan (the Occupational Certificate of the project is
enclosed as Annex 3(d). The project is planned and designed as per the regulations and
procedures laid down by the Director of Town & Country Planning (DTCP), Haryana. The
photographs of the project site are enclosed in Annex 3(e) and shown below:
Sandy & Loamy soil is present within the Project site. Irrigation facility is not up-to the mark and
thus the agriculture is almost rainfed. The land environment is described by landuse/ landcover
of the study area within 500 m radius.
The classification of landuse/ landcover pattern of the study area is mainly dominated by the
Agriculture land. The agriculture land covers the majority of the land which is about 91.8 % of
the study area. The land use data are presented in Table 3.3, the pie chart of the landuse is given
below in Figure 3.2 and the landuse/ landcover map is presented in Figure 3.4 and Annexure
3(f)
Area (Ha)
0% 0%
2%
6%
Open Land
Forest
Water Bodies
Settlement
Agriculture
92%
Soil is formed almost entirely of alluvium; the state is situated towards the depressions of the
rivers Ganges and Indus. It is a broad level plain standing nearly on the watershed between the
basins of the two rivers. It is a vast ground of moist land. In the whole of the region except the
flood plains of the Yamuna and the Ghaggar, the alluvium is of the old type containing sand,
clay, silt and hard calcareous concentrations about the size of nuts known as 'Kankars'.
In order to get the characteristics of the soil in the project area, soil analysis was carried out
during study. The frequency and methodology of soil quality sampling process is given in Table
3.3. The soil quality sampling monitoring locations are depicted in Table 3.4 and map showing
the soil quality monitoring results in the study area is given in figure 3.5 and Annexure 3(g)
Table 3.3 Frequency and Methodology for Soil Sampling & Monitoring
Particulars Details
Frequency One *grab sample from each station– once during the Study Period
Methodology
The soil samples were collected in the month of April 2019 from 5 locations as given in Table
3.4 and Figure 3.5. At each of these locations 5 sub-locations were identified randomly from
where soil was collected from 30 cm below the surface. The final 5 samples represent
homogenously mixed soil from these 5 sub-locations for each location. The samples were filled
in polythene bags, labeled in the field with number and site name and sent to laboratory for
analysis.
Physical characteristics of soil were characterized through specific parameters viz pH, electrical
conductivity and texture. Soil pH plays an important role in the availability of nutrients. Soil
microbial activity as well as solubility of metal ions is also dependent on pH. In the study area,
variations in the pH of the soil were found to be slightly alkaline (6.51 to 6.81). Electrical
conductivity (EC) is a measure of the soluble salts and ionic activity in soil. In the collected soil
samples the conductivity ranged from 569 to 594 μmhos/ cm. The soil analysis results is given
below in the Table 3.5
The project does not intersect any natural drainage route. No perennial or non-perennial drainage
system is found to exist in the project area or being obstructed by the project. The surroundings
comprise an urbanized stretch and well planned storm water drainage has been designed for
internal storm water drainage.
Water quality assessment is one of the essential components of EIA study. Such assessment
helps in evaluating the existing health of water body and suggesting appropriate mitigation
measures to minimize the potential impact from development projects. Water quality of
groundwater has been studied in order to assess proposed water-uses in construction, drinking,
cooling and horticulture purpose. The water quality at site and other locations within a radius of
10 km was monitored in April 2019
Parameters for analysis of water quality were selected based on the utility of the particular source
of water as per MoEF guidance. Hence quality of ground water was compared with IS:
10500:1991(Reaffirmed 1993 With Amendment No-3 July 2010) for drinking purposes.
Drinking Water quality meets the standards (IS: 10500)
Ground water quality and surface water quality was monitored at project site and surrounding
area. The ground water quality and surface water quality monitoring stations are given in the
Table 3.6 and Figure 3.6 below and Annexure 3(h). One groundwater and surface water sample
from each station respectively was taken on April 2019. Sampling was done by standard
sampling technique as per the Standard Methods. Necessary precautions were taken for
preservation of sample.
The water quality in the study area was assessed through physico-chemical and bacteriological
analysis of ground and surface water samples. The results were compared with drinking water
quality standards specified in IS: 10500. It was observed that all the physico-chemical
parameters and heavy metals from surface and ground water samples are below stipulated
drinking water standards. Hence, the ground water samples analyzed can be considered fit for
drinking purpose in the absence of alternate sources. The groundwater and surface water analysis
results are given in Table 3.7 (a, b, c) and Table 3.8 (a, b) respectively below
Table 3.7 (a) Ground Water Quality April 2019 (On site)
Table 3.7 (b) Ground Water Quality April 2019 (Adarsh Nagar)
Table 3.8 (a) Surface Water Quality April 2019 (Yamuna River Upstream)
Table 3.8 (b) Surface Water Quality April 2019 (Yamuna River Downstream)
Preliminary survey was carried out to identify ground water sampling location, considering its
uses for domestic and drinking purposes and other activities. Based on this survey, three different
locations were selected for ground water sampling. The results obtained for ground water quality
and surface water quality are given in the 3.9 (a), 3.9 (b) & 3.9 (c) and 3.10 (a) & 3.10 (b)
respectively.
• The total dissolved solids were observed in the range 386 to 1345 mg/l
• The total hardness, as CaCO3 was observed in the range of 169 to 792 mg/l.
• The concentrations of calcium observed in the range 49 to 220 mg/l, which is not within
the limit of 200 mg/l and the concentrations of magnesium was observed in the range
10.9 to 58.80mg/l.
• The concentration of chloride was observed in the range 37 to 432 mg/l.
• The concentrations of sulphate were observed in the range 2.8 to 19.1 mg/l, which is
below the desirable limit of 200 mg/l.
• The concentrations of nitrate were observed in the range 1.6 to 15.2 mg/l.
It is, therefore, concluded that the ground water at the site is safe for use as potable water. All the
parameters are within the permissible limit. There is no alternative source of drinking water. So
this water can be used as drinking purpose.
3.9.1 Climate
The climate of the area is moderate and tropical characterized by a hot and dry summer
from March to middle of June, a humid monsoon or rainy season stretching from middle of
June to September, a short pleasant post-monsoon concentrated during October and
November, and a cool and dry winter spanning between December and February.
3.9.2 Temperature
May is observed as the hottest month during summer having mean daily temperature of
40.5 ºC and January was the coldest month mean daily temperature having 5.0 °C as per
Indian Meteorological Data during the period 1965 to 1980.
3.9.3 Rainfall
June to September is the monsoon session in Karnal. The weather condition is almost dry
during the month of October to March. The annual average rainfall in Karnal is 766 mm
and average number of rainy days 32.
It is observed that the pollutant concentration decreases with increase in wind speed and
dispersion of pollutants both gaseous and particles are good when the wind speed is high,
thus minimizing the pollution affect on surface level. The relationship between ground
level pollutant concentration and wind speed is inversely proportional. The prominent wind
speed in Gurgaon is from west direction to east. The wind-rose diagram for the monitoring
period is given in the Figure 3.7.
However in spite of the above meteorological data collected from secondary sources a
meteorological study has been carried out from the project premises. Meteorological data
was generated on February 2019. The following parameters were recorded at hourly
intervals during the study period:
• Wind Speed
• Wind Direction
The meteorological data recorded at project site for the study period February 2019 is
summarized in the Table 3.9 below and the wind-rose diagram for the monitoring period is given
in the Figure 3.7.
Ambient air quality monitoring was carried in a month with a frequency of 24 hours for 4
weeks. Fine particulate Sampler was used for monitoring PM 2.5 and Respirable Dust sampler is
used for monitoring PM 10 . Gaseous pollutants like SO 2 , and NO 2 was collected by Gaseous
Pollutant Sampler and CO was analyzed as per CPCB guidelines.
Method for measurement of Particulate Matter (PM10) in ambient air is done by Cyclonic Flow
Technique. Particles with aerodynamic diameter less than the cut-point of the inlet are collected
by a filter. Ambient air at the monitoring location is sucked through a cyclone. Coarse and non-
reparable dust is separated from the air stream by centrifugal forces acting on the solid particles
and these particles fall through the cyclone's conical hopper and get collected in the sampling
cap placed at the bottom. The fine dust (<10 microns) forming the particulate matter (PM10)
passes the cyclone and is retained on the filter paper The mass of these particles is determined
by the difference in filter weights prior to and after sampling. The concentration of PM10 in the
designated size range is calculated by dividing the weight gain of the filter by the volume of air
sampled. A tapping is provided on the suction side of the blower to provide suction for sampling
air through a set of impinges for containing absorbing solutions for SO2 and NO2. Samples of
gases are drawn at a flow rate of 0.2 liters per minute. FPS is used for PM2.5. This system is a
manual method for sampling fine particles (PM2.5 fraction) and is based on Impactor designs
standardized by USEPA for ambient air quality monitoring.
PM 2.5 have been estimated by gravimetric method and PM 10 is analyzed as per IS: 5182, Pt-23,
2006. Improved West and Gaeke method (IS-5182 part-2, 2006) has been adopted for
estimation of SO 2 and Modified Jacobs-Hochheiser method (IS-5182 part-VI, 2006) has been
adopted for the of NO 2 .
Method for Measurement of Carbon monoxide – NDIR Method (IS:5182, Pt-10, 1999,
Reaffirmed 2003)
This method is used to measure CO in ambient air, in the range of 0-200 ppm (220 mg/m3) to a
sensitivity of 0.05 ppm (55μg/m3).
Annual average: annual arithmetic mean of minimum 104 measurements in a year at a particular
site taken twice a week 24 hourly at uniform intervals.
24 hours average: 24 hourly or 01 hourly monitored values for CO, as applicable, shall be
compiled with 98% of the time in a year. 2% of the time, they may exceed the limits but not on
two consecutive days of monitoring.
Note: whenever and wherever monitoring results on two consecutive days of monitoring exceed
the limits specified above for the respective category, it shall be considered adequate reason to
institute regular or continuous monitoring and further investigation
Table 3.12 (a) Ambient Air Quality with respect to PM 2.5 (24 Hourly Average)
As per
Location 98
Location Min Max Average CPCB
Code Percentile
Standards
AAQ1 On site 59 70 63.75 69.72 60
AAQ2 Kalwa Heri 42 76 60.87 75.16 60
Adarsh 60
AAQ3 42 81 62 80.72
Nagar
AAQ4 Budha Khera 39 75 62.13 74.44 60
AAQ5 Phoosgarh 41 73 59.13 72.58 60
The values of Particulate Matter (size less than 2.5 μm) in study area are presented in Table
3.12 (a). The seasonal minimum, maximum, average and 98 percentile values within the study
area ranged between 39-59 μg/m3, 70-81 μg/m3, 59.13-63.75 μg/m3 and 69.72-80.72 μg/m3
respectively.
Chart Title
90
80
70
60 Min
50 Max
40 Average
30 98 Percentile
20
As per CPCB Standards
10
0
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Fig 3.9 (a) Charts of Ambient Air Quality Monitoring with respects to PM 2.5 (24 Hourly
Average)
Table 3.12 (b) Ambient Air Quality with respects to PM 10 (24 Hourly Average)
PM 10 μg/m3
As Per
Location 98
Location Min Max Average CPCB
Code Percentile
Standards
AAQ1 On site 126 154 143.875 153.58 100
AAQ2 Kalwa Heri 72 178 149 176.74 100
Adarsh 100
AAQ3 75 184 146.38 182.32
Nagar
AAQ4 Budha Khera 68 182 148.63 180.88 100
AAQ5 Phoosgarh 82 172 138.63 171.02 100
The values of Particulate Matter (size less than 10μm) in study area are presented in Table
3.12(b). The seasonal minimum, maximum, average and 98 percentile values within the study
area ranged between 68-126 μg /m3, 154-184 μg/m3, 138.63-149 μg/m3 and 153.58-182.32
μg/m3 respectively.
Chart Title
200
180
160
140
Min
120
Max
100
Average
80
98 Percentile
60
As Per CPCB Standards
40
20
0
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Fig 3.9(b) Charts of Ambient Air Quality Monitoring with respects to PM 10 (24 Hourly
Average)
Table 3.12 (c) Ambient Air Quality with respect to SO 2 (24 Hourly Average)
SO 2 μg/m3
Location 98 CPCP
Location Min Max Average
Code Percentile standards
AAQ1 On site 16 21 19.25 21.86 80
AAQ2 Kalwa Heri 12 22 17.25 21.72 80
AAQ3 Adarsh Nagar 14 20 17.75 20 80
AAQ4 Budha Khera 12 23 17.25 22.72 80
AAQ5 Phoosgarh 12 22 17.75 21.72 80
The values of Sulfur dioxide in study area are presented in Table 3.12(c). The seasonal
minimum, maximum, average and 98 percentile values within the study area ranged between
12-16 μg/ m3, 20-23 μg/ m3, 17.25-19.25 μg/ m3 and 20-22.72 μg/m3 respectively.
Chart Title
90
80
70
60
Min
50
Max
40
Average
30
CPCP standards
20
10
0
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Fig 3.9(c) Charts of Ambient Air Quality Monitoring with respects to SO 2 (24 Hourly
Average)
Table 3.12 (d) Ambient Air Quality with respect to NO 2 (24 Hourly Average)
NO 2 μg/m3
Location 98 CPCP
Location Min Max Average
Code Percentile standards
AAQ1 On site 25 31 27.88 30.86 80
AAQ2 Kalwa Heri 20 31 24 30.72 80
Adarsh 80
AAQ3 23 31 26.75 30.72
Nagar
AAQ4 Budha Khera 24 30 25.63 29.58 80
AAQ5 Phoosgarh 19 31 26.25 30.86 80
The values of oxides of nitrogen in study area are presented in Table 3.12 (d). The seasonal
minimum, maximum, average and 98 percentile values within the study area ranged between
19-25 μg/m3, 30-31 μg/m3, 24-27.88 μg/m3 and 29.58-30.86 μg/m3 respectively
Chart Title
90
80
70
60 Min
50 Max
40 Average
30 98 Percentile
20 CPCP standards
10
0
AAQ1 AAQ2 AAQ3 AAQ4 AAQ5
Fig 3.9 (d) Charts of Ambient Air Quality Monitoring with respects to NO 2 (24 Hourly
Average)
From the summarized monitoring results it is clear that, in all cases, the 24-hourly average
levels of SO 2 and NO 2 were observed to be within the limit of 80 µg/m3 for commercial, rural
& other areas as stipulated in the National Ambient Air Quality Standards.
A preliminary survey was undertaken to identify the major noise generating sources in the area.
The noise monitoring was conducted to assess the background noise levels in different zones.
Methodology
The intensity of sound energy in the environment is measured in a logarithmic scale and is
expressed in a decibel, dB (A) scale. In a sophisticated type of sound level meter, an additional
circuit (filters) is provided, which modifies the received signal in such a way that it replicates
the sound signal as received by the human ear and the magnitude of sound level in this scale is
denoted as dB (A). The sound levels are expressed in dB (A) scale for the purpose of
comparison of noise levels, which is universally accepted by the international community.
4 numbers of sampling locations were selected for sampling of noise levels which are basically
in residential areas. The sampling locations are given in Table 3.13 and map showing the
monitoring location is given in Figure 3.10 and Annexure 3(j). The day noise levels have been
monitored during 6.00 am to10.00 pm and night noise levels, during 10.00 pm to 6.00 am at all
the 5 locations.
Ministry of Environment & Forests (MoEF) has notified the noise standards vide. Gazette
notification dated February 14, 2000 for different zones under the Environment Protection Act
(1986). These standards are given in Table 3.14.
Note: Daytime is from 6.00am to 10.00 pm and Night time is from 10.00 pm to 6.00 am.
Silence zone is defined as area up to 100 meters around premises of hospitals, educational
institutions and courts. Use of vehicle hours, loud speakers and bursting of crackers are banned
in these zones.
The noise level monitoring results are given in the following Table 3.15.
80
70
60
50
40 Day Time*
Night Time*
30
20
10
0
NQ1 NQ2 NQ3 NQ4 NQ5
Literally environment stands for the totality of surrounding conditions. Animals and plants form
a vital part of this sum total. Flora and fauna of an area are inter-related to each other and have a
very crucial impact on human life. With changes in environmental conditions, structure, density
and composition of plants and animals undergo changes as well. The present study was carried
out in two separate headings for floral and faunal community. The information on flora and
fauna were collected based on field survey, literature review.
The prevailing vegetation cover over the area is mainly of tropical dry deciduous forest as per the
Champion and Seth (1968) “Classification of forest type of India”. There was no vegetation
within the project site except few bushes and only a few species of Azadirachta indica, Delonix
regia and Bauhinia purpurea were seen and the rest is a part consists mainly of agricultureal
crops. Project site does not fall in forest land. The vegetative community of the area is mainly
under open scrub forest and because of urbanization the study area. The major species are
Azadirachta indica, Delonix regia, Bauhinia purpurea etc. The prominent grass is Delonix
pulcherima, Plumeria alba. No threatened, rare, endangered or endemic species were observed
during the survey. Data on local plant species were also collected from secondary sources. The
list of plants species is given in Table 3.16.
The common trees found along the roadside of the study area are Axel Erlandson, Hyophorbe
lagenicaulis, Livistona chinensis, Aegle marmelos L., Mangifera indica, Kinnow, Lychee,
Psidium guajava, Arecaceae, Fiscus, Alstonia scholaris, Arecaceae etc.
Near villages the vegetation pattern changes from rest of the area. The common species grown
near villages are Axel Erlandson, Hyophorbe lagenicaulis, Livistona chinensis, Aegle marmelos
L., Mangifera indica, Kinnow, Lychee, Psidium guajava, Arecaceae, Fiscus, Alstonia scholaris,
Arecaceae etc.
Field survey was conducted to identify the fauna species in the study area. Few common
mammal species such as cow, dog, cat, rat, and squirrel were reported in the study area. No
threatened, rare, endangered or endemic species were observed during the survey in study area.
Information was also collected from secondary sources. The list of faunal species in the study
area is given in Table 3.17. There is no displacement of fauna– terrestrial and aquatic or creation
of barriers of their movement.
Protected Areas
Baragaon Protected Forest lies at distance of 7.53 km in North-East direction from project site.
The major portion of the study consists of agricultural field and human settlements which do not
support wildlife habitat.
Baragaon Protected Forest lies at distance of 7.53 km in North-East direction from project site.
3.13 Agriculture
The Irrigation facility is not proper in the study area, rainwater is the main source of irrigation
and wheat is the main crop grown in the area. Other crops, which are grown, are Moong, Arhar,
til, etc. Where watering facility is available seasonal vegetables are also grown. Land at some
places is used for agriculture purpose. The main crops are wheat, maize, bajra, cotton and
vegetables.
The project has access through the 60 m wide Sector road connecting the NH-1 and SH-7. The
project area is well connected to network of roads leading to various parts of NCR and railway
by New Delhi-Jaipur section of rail network. The distance and direction of nearest highway,
railway station and airport are given below:
Public transport facility, like, buses, autorikshaw, cab and minibuses are easily available in the
area as transport linkage. All the Sectors in the study area are well connected with pacca roads.
There have been rapid developments of roads in the area due to increasing colonization as part of
urbanization.
In order to get the ideas of socio-economic status of people living in the study area of Hotel,
Restaurant & Banquet Hall, Recreational Park and health club. Secondary data were collected
and analyzed. Considering the various Quality of Life (QoL) indicators, and satisfaction level of
the residents of the study area, an attempt was made for developing the QoL of a family and the
community as well.
According to Census 2011, the total population of the area is 4830 of which 52 (2522) percent
are male and the remaining 48 (2308) percent are female.
(Source - http://www.census2011.co.in/data/village/59309-phusgarh-haryana.html)
Phusgarh village has lower literacy rate compared to Haryana. In 2011, literacy rate of Phusgarh
village was 74.01 % compared to 75.55 % of Haryana. In Phusgarh Male literacy stands at 81.78
% while female literacy rate was 65.64 %.
In Phusgarh village out of total population, 1439 were engaged in work activities. 89.85 % of
workers describe their work as Main Work (Employment or Earning more than 6 Months) while
10.15 % were involved in Marginal activity providing livelihood for less than 6 months. Of 1439
workers engaged in Main Work, 262 were cultivators (owner or co-owner) while 334 were
Agricultural labourers. The Table 3.18 below indicates categorization of workers on the basis of
occupation.
The study area is well provided with medical facility, drinking water, communication, approach
roads and irrigation. Gurgaon is an important business center close to NCR Delhi. It has well-
developed infrastructural facilities.
• Drinking water
Drinking water facility is available in all the habitations located in the study area. CGWA supply
water is the most common form of source of drinking water.
• Electricity
Electricity has reached all the Sectors. In the study area electricity is used for domestic lighting,
industrial use and energizing pumps. The demand for electricity for industrial uses is fast
growing due to rapid industrialization.
• Communication facilities
The study area is provided with Post offices and Land line phone connections. Due to rapid
industrialization and urbanization these facilities are increasing at a faster rate. Besides the study
area is well connected to all over parts of the country through road and railway networks.
• Education
The Study area has good educational facility and good network of Schools, Colleges.
• Public health
Available medical facilities in the study area are hospitals, dispensaries, health centers, public
health sub centers; maternity homes etc. within a range of 1-10 km.
CHAPTER 4
4.1 Introduction
Generally, the environmental impacts can be categorized as either primary or secondary. The
construction and operation phase of the project comprise various activities, each of which may
had some impact on environmental parameter. This chapter discusses identification, assessment
of various environmental impacts due to development of Hotel, Restaurant & Banquet Hall
“Noor Mahal” located at Village Phusgarh, Dist- Karnal, Haryana and their suitable mitigation
measures
The project is in operational phase as it has already the facilities for proper and assessment of the
environmental impacts understanding to the various activities associated with the Hotel,
Restaurant & Banquet Hall. The environmental impact assessment had been made as the built-up
area is increased. The impact identification and prediction process aims to:
For each category of environmental parameter (such as, ambient air quality, water quality, soils,
land, etc,) the potential impacts of activities during construction and operation phases had been
identified. Pollution sources & its characteristics, the potential impacts and magnitude of the
impacts had been assessed and discussed in detail in following sub sections. In each case,
cognizance had been already taken to mitigation measures inherited in the construction and
operation phase.
The pollutants likely to be generated both during construction and operation phase of the Hotel,
Restaurant & Banquet Hall project are solid, liquid and gaseous in nature. Also the generation of
pollutants could be continuous, periodic or accidental. Sources of pollutants and their
characteristics during construction and operation phase are given below in Table 4.1.
Table 4.1 Sources of Pollutants, their Characteristics during Construction & Operation
Phase
• Physical change in landscape due to earth work excavation and related activities.
• Soil erosion caused due to loss of vegetation and other construction activities.
• Generation, storage and disposal of construction wastes;
• Noise pollution due to plant, machinery, equipments and vehicle movement;
• Air pollution due to plant, machinery, equipments and vehicle movement;
• Generation and disposal of wastewater;
• Impact on ecology;
• Consumption of resources such as water, electricity, and diesel.
Impacts identified during operation of the project include major concerns such as:
The areas of environmental concerns for which the impacts and their predictions are taken into
consideration are mainly:
• Topography
• Landuse pattern
• Soil Quality
• Water Environment
• Air Environment
• Noise Environment
• Biological Environment–Ecological Flora and fauna
• Agricultural Pattern
• Socio economic Environment
• Transport Infrastructure and Traffic Management
• Solid waste Management
• Infrastructure facilities (Drinking water, Electricity, Communication, Public health etc.)
The impacts can be further categorized as positive impacts and negative impacts depending upon
their nature, potential and magnitude in construction phase and in operation phase.
4.5.1 Topography
Anticipated Impacts
The project area possesses slightly undulating terrain. Highest contour level is 802.30 m & the
lowest level is 800.50 m. Difference between the highest & lowest level is 1.8 m. There is no
vulnerability of subsidence. Proper greening & paving of area had not cause soil erosion
problem. The area under study falls in Zone-IV, according to the Indian Standard Seismic
Zoning Map.
Mitigation Measures
Since there is no significant impact is anticipated on the topography and physiographic from the
project. It was maintain 30 % of the plot areas as green through plantation of various local and
aesthetic species to improve the vegetation cover of the area. Suitable structural design had been
made to mitigate the seismic impacts.
Anticipated Impacts
The existing landuse of the project site is vacant barren land with spurse vegetative cover. The
land is earmarked for Hotel, Restaurant & Banquet Hall, Recreational Park and Health Club as
per the local development/ zoning plan. Hence, no significant impact is expected from the project
which had been developed after obtaining all necessary permissions.
4.5.3 Soil
Anticipated Impacts
Soil would be excavated at project site for foundations of project. The soil excavated during
construction was first temporarily stored in a designated area earmarked and then used to fill up
low lying area in and around the project site.
Mitigation Measures
Few shrubs & small vegetation covers were, removed from the site while leveling and allowing
minimal disturbance to vegetation in adjacent areas. Land clearing activities had only is confined
to necessary areas. The top soil was stripped from constructional areas and stored for later reuse
in landscaping. The number, frequency and area of movement of heavy machinery were
restricted. Moreover tree plantation and greenery at completion stage of the project had resisted
the soil erosion.
Anticipated Impacts
The project does not intersect any natural drainage route. No perennial or non-perennial drainage
system is found to exist in the project area or being obstructed by the project. The surroundings
comprise an urbanized stretch. The construction activities had been confined to the project site
and not altered the drainage pattern of the area.
Mitigation Measures
The construction activities were confined within the project site which was vacant almost plain
terrain plot. Development of the project had not disturbed the natural drainage pattern during
rainfall in construction phase. However, during construction storm water/ had been managed
through temporary arrangements and storing in the temporary pits so that natural flow pattern
had not be affected.
Anticipated Impacts
The primary concerns relating to surface water quality associated with construction activities are
pointed out below:
• Run-off related to unpaved and excavated areas during the rain shower.
• Sediments transported to run-off from the construction site.
• Run-off related to area where lubricant, fuel other materials are stored, handled and disposed-
off.
Surface water quality may be affected with the discharge of the runoff from the project site. The
impact to the surface water bodies could arise from the increased soil erosion from excavated site
only causing increase in the suspended particles and turbidity of run-off water from the site.
However, this impact had been temporary in the nature and would be observed in first rain only
and as soon as rain is over excavated soil at site would be stabilized. Therefore, the surface water
quality during rains had been impacted marginally for very short duration.
Mitigation Measures
During the construction phase, surface water quality is likely to be affected due to soil erosion
during first rain and generation of wastewater mainly from construction labour camp. However,
this phenomenon had been a temporary thing and restricted to close vicinity of construction site.
The impact on surface water quality is minimized by adopting following measures;
• Proper management of excavated soils
• Clearing all surplus excavated earth from site as soon as construction is over
• Suitable storage of top-soil for use in landscaping at completion stage of the project
• By providing proper hutment and toilet facilities for construction labour
• Construction wastewater properly disposed into soak pit & through septic tank
Anticipated Impacts
Water requirement during construction phase depending upon construction activities and was
met by private water tanker. As an estimate about 345.40 KLD water was required for site
preparation activities dust settlement, consolidation, compaction and curing as well as building
construction and drinking water requirement. The requirement of construction water did not put
pressure on the available ground water recourses of area. No groundwater had been used for
construction purposes. No hazardous chemical and material was used in the construction phase
of project. Debris and wastes generated during this phase were collected and backfilled in the
site. Since, there is no dumping of any hazardous materials. Therefore, contamination of ground
water is negligible. Hence, no impact is anticipated on the ground water quality during the
construction phase.
During operation stage fresh water had been sourced from ground water and as the provision of
HUDA has been started we will switch over to the source i.e., HUDA water and sewerage
facility. The wastewater generated during operation of the project had been treated into the
sewage treatment plant of 150 KLD capacity in the project. The treated water had been recycled
and re-used for cooling, horticulture purpose within the project site and surplus treated sewage
had been used for irrigation in Green Area. Dual-plumbing plan enclosed Annex 4 (a).
Mitigation Measures
Although no significant impact is anticipated on the groundwater regime, the following measures
were used further minimize the demand on freshwater resources:
• Curing water had been sprayed on concrete structures and free flow of water not allowed
• Concrete structures had been covered with thick cloth/gunny bags and then water sprayed on
them to avoid water rebound and ensure sustained and complete curing.
• Ponds had been made using cement and sand mortar to avoid water flowing away from the flat
surface while curing.
• Water ponding had been done on all sunken slabs. This had also highlighted the importance of
having an impervious formwork.
• Proper drainage system had been provided to deal with the storm water and rainwater
harvesting system to recharge the groundwater.
The potential sources of air emissions during the construction and development phase of the
project were as follows:
• Dust from earth works (during site clearance and preparation);
• Emissions from power generator at site;
• Emissions from the operation of construction equipment and machines;
• Fugitive emissions from vehicles running to site;
• Fugitive emissions during the unloading of material at the site;
• Fugitive emissions during mixing of cement with other building materials during development
and construction activities;
• Air emissions other than dust arise from combustion of hydrocarbons. The pollutants of
concerns are NO2, SO2, CO, particulate etc.
Anticipated Impacts
Ambient air quality effects were normally assessed in relation to their potential to cause;
Health deterioration and nuisance in local communities
Health deterioration amongst onsite workers
stacks had been provided to the DG set as per guidelines of CPCB to facilitate the dispersion of
flue gases into the atmosphere.
Mitigation Measures:
• Construction material had been kept at temporary storage yard. Loading and unloading
activities had been carried out at certain places near the storage yard.
• Dust suppression had been carried out by water sprinkling
• Adequate stack height for DG sets were provided during construction phase so that the stack
emission get dispersed properly at certain height and not affect the working population at
construction site.
• Monitoring of emissions from DG sets and ambient air quality had been carried out as per
norms.
All the above-mentioned sources of development and construction activities at project site were
intermittent and experienced occasionally. It may also be noted that the most of the construction
activities were carried out only during the daytime. The expected noise levels from various
activities are given hereunder:
Where: Lp1, Lp2 and Lp3 are noise pressure level at a point due to different sources in dB(A).
The resultant maximum noise level for the above sources as calculated using equation (1) is 89.3
dB (A). For an approximate estimation of dispersion of noise in the ambient air from the sources
point, a standard mathematical model for sound wave propagation is used. The sound level
generated by noise source decrease with increasing distance from the source due to wave
divergence. An additional decrease in sound pressure level from the source is expected due to
atmospheric effect or its interaction with objects in transmission path.
For hemispherical sound wave propagation through homogenous loss of free medium, noise
levels at various locations can be calculated due to different sources using model based on the
first principles as per the following, equation:
Lpx2 = Lpx1-20 log10 (x2/x1) ………. (2)
X2 =Unknown
X1 = Known
Where: Lpx2 and Lpx1–Sound Pressure Level (SPLs) at points located at sources and at distance
of x2 from the source respectively in dB (A).
Assuming no environmental attenuation factors, noise modeling had been done, which shows
that noise level had been mingle with baseline noise level with in short distance.
The noise produced during, construction phase had temporary impacts on the existing, ambient
noise levels at project site but restricted to small distance and only during daytime. Therefore,
the impact of noise levels on surrounding area had been insignificant during the development and
construction phase.
Mitigation Measures
• To minimize impacts of noise generation from construction activities, the workers were
provided with ear muffs.
• Enclosed type DG sets or DGs with proper acoustic enclosure for controlling noise were
installed during construction.
• The construction machinery and equipment had been monitored and maintenance were carried
out at regularly.
• Monitoring of noise level was carried out as per norms.
Anticipated Impacts
There is no forest area in this zone. The vegetative community of the area is mainly under open
scrub forest and because of urbanization area is usually surrounded with planted varieties. The
dominant species are Delonix pulcherima, Plumeria alba, Ervatamia divaricata, Yellow Duranta,
Saraca indica, Ficus retusa, Bassia Latifoliaetc, etc. The prominent grass is Cynodon dactylon.
No threatened, rare, endangered or endemic species were observed during the survey in the study
area.
Mitigation Measures
The project had not had any major negative ecological impact. There is no forest near the project
site. However, it developed extensive green areas in the project site to improve the aesthetics of
the area which had also help in reduction of air pollution, noise pollution and provide suitable
habitat for local birds and animal species.
Anticipated Impacts
The major part of the study area lies under agriculture field and human settlements which
restricted the wildlife habitat significantly.
Most of the mammalian species reported in the study area are cow, goat, dog, cat etc. There is no
information regarding migratory movement of birds in the study area. There is neither any
wildlife sensitive area nor any corridor for the movement of wildlife present in the study area.
No threatened, rare, endangered or endemic species were observed during the survey
Mitigation Measures
The major part of the study area lies under agriculture field and human settlements which
restricted the wildlife habitat significantly. Project had no adverse impact on the faunal species.
Anticipated Impacts
The project had been built on the land earmarked for commercial project as per the Change in
Land use plan, hence no agricultural land had been acquired for the project and the post project
development also had not affect the cropping pattern of the study area.
Mitigation Measures
No adverse impact on agricultural pattern due to this project is envisages. Hence mitigation
measures are not required. Due to the project development the socio-economic condition of the
surrounding area had had positive impact.
Anticipated Impacts
The project site is located in the developed area of the City Karnal where road network and
transport infrastructure facilities already exist. The project area is well connected to network of
roads leading to various parts of National Capital Region. Public transport facility, like, buses,
auto-rickshaw, cab and minibuses are easily available in the area as transport linkage. During
construction phase, some impact is anticipated on the transport linkage of the area, however
increase in traffic had not adversely affect the local traffic pattern since the site is well connected
by wide road and present traffic load on these road are not significant.
Mitigation Measures
• Proper planning, for the movement of the heavy vehicles to reduce load on existing traffic such
that the peak hours are avoided.
• Ensure that the vehicles bringing the building construction material must had Pollution under
Check (PUC) certificate and are in good condition.
• The vehicles had been temporarily parked inside the project premises for loading unloading
activities of building materials during construction phase and also ensure that all the vehicles
to the site had been provided with parking space such that there is no waiting time along the
access roads.
• No public place had been used for parking of vehicles.
Anticipated Impacts
The quantity of excavated earth had been about 15,286 m3, a part of which had been used for
backfilling and leveling of project site. The topsoil had been preserved separately and had been
reused for horticultural purpose. Waste construction materials had been recycled. The excess
construction debris & excavated earth had been disposed at vacant low lying lands of Hotel,
Restaurant & Banquet Hall for filling & leveling, if required. Besides, the surplus earth had been
disposed off in the areas designated by the local authority. The surplus earth would only be the
construction waste and had not caused any health hazards; hence no such adverse impact is
anticipated.
Mitigation Measures
During construction phase after solid wastes segregation, recyclable wastes had been sold to
government authorized vendors and the biodegradable waste has been disposed to the local
municipal solid wastes collection point for further disposal by local authority. Hazardous wastes
had been disposed off as per the provisions of the Hazardous Wastes (Management, Handling
and Trans-boundary Movement) Rules, 2008 and as amended.
Anticipated Impacts
The construction activities had been confined within the project premises and project boundary
without affecting / involving the surrounding public places.
During construction phase, about 300 skilled and semiskilled and unskilled workers had been
hired from local nearby areas. No temporary labour hutment was proposed. The project is a
commercial project. Thus, no influx of people is envisaged.
Noticeable, flow-on economic impacts had been experienced in other sectors of economy as a
result of purchase of construction materials and employment opportunity to the personnel
engaged in the development and construction.
Mitigation Measures
Suitable measures had been taken at the construction site to keep the place clean. On-site
drinking water and sanitation facilities had been provided to the workers during construction
phase. Other safety precautions to be maintained at work site including provision of PPEs,
guarding of dangerous machine parts, maintenance of equipments as hoists and lifts etc, and
adequate provision of different types of fire extinguishers had been made. All applicable rules
and regulations pertaining to workplace health and welfare of workers had been adhered to.
Anticipated Impact
The project had not brought any adverse impact due to its development during construction stage
in terms of infrastructure facilities and amenities. The project had been developed in the area
earmarked for commercial project as per the Change in Land use plan and the construction
activities had not disrupt any of the public services and amenities such as water supply,
electricity and public transport facilities, public health and education. Due to the transport of
building construction material traffic movement had been increase insignificantly and public
place had not been occupied for parking of the vehicle.
Mitigation Measures
As the project development had no such adverse impact during its construction phase no such
mitigation measures are required. However, care had been taken to look after the drainage and
water supply line if any adjacent to the project plot so that those remain uninterrupted. Adequate
space had been provided for parking of vehicles transporting the building construction material
4.6 Assessment of the Environmental Impacts and Mitigation Measures during Operation
Phase
4.6.1 Topography
Anticipated Impacts
The project area possesses slightly undulating terrain. Highest contour level is 802.30 m & the
lowest level is 800.50 m. Difference between the highest & lowest level is 1.8 m. There is no
vulnerability of subsidence. Proper greening & paving of area had not cause soil erosion
problem. The area under study falls in Zone-IV, according to the Indian Standard Seismic
Zoning Map.
Mitigation Measures
No significant impact is anticipated on the topography and physiographic from the project.
Moreover, landscaping and greenery development had improved the aesthetics of the
surroundings. Suitable structural design had been made to mitigate the seismic impacts.
Mitigation Measures
No change in land-use pattern and no adverse impact are anticipated. The tree plantation,
landscaping and greenery development had improve the air environment and aesthetics of the
area
4.6.3 Soil
Anticipated Impacts
During the operation phase of the project, the soil may get polluted/ contaminated from littering
of various kinds of wastes generated within the site such as food items, paper, wood pieces,
paints, pesticides, oil & grease etc. However, owing to the solid waste management system, no
significant impact is anticipated.
The post project development had no any adverse impact on the soil quality. During operation
phase there no requirement of site clearance and removing of vegetative cover. Hence no adverse
impact is anticipated.
Mitigation Measures
The tree plantation and greenery at completion stage of the project had resisted the soil erosion.
Moreover the solid waste generated at operation phase had been properly management properly
and treated. Used oil from operating DG sets had been handled as per the Hazardous wastes
Management, Handling and Trans-boundary Movement Rules 2008. Therefore there was no
chance of soil contamination.
Anticipated Impacts
The project does not intersect any natural drainage route. No perennial or non-perennial drainage
system is found to exist in the project area or being obstructed by the project. The surroundings
comprise an urbanized stretch and well planned storm water drainage had been designed for
internal storm water drainage. No storm water of the project site had been discharged outside.
Thus, no impact on the natural drainage system is anticipated.
Mitigation Measures
Most of the storm water produced on site had been harvested for ground water recharge. Thus
proper management of this resource is a must to ensure that it is free of contamination. A
detailed Storm Water Management Plan had been developed which had consider the sources of
storm water. The plan had incorporated best management practices which had include the
following:
• Regular inspection and cleaning of storm drains.
• Installation of clarifiers or oil/ water separators system of adequate capacity around
parking areas and garages as per requirement.
• Cover waste storage areas.
• Avoid application of pesticides and herbicides before wet season.
• Conducting routine inspections to ensure cleanliness.
• Preparation of spill response plans, particularly for fuel and oil storage areas.
• Provision of silt traps in rain water harvesting system.
• Good housekeeping in the above areas.
Anticipated Impacts
There was no low-lying area and wetland in the vicinity of the project site. There was no
diversion of water from the other users.
The wastewater generated from the Hotel, Restaurant & Banquet Hall had been collected through
the sewer line network provided and treated in a Sewage Treatment Plant (STP) of capacity 150
kld. No discharges from the project site had been made to any surface water body. The project
had zero discharge units.
Mitigation Measures
As no impact was anticipated on the water bodies of the region, no mitigation measures are
suggested.
Anticipated Impacts
In operation phase, total water requirement for the project is 155 kld. The fresh water
requirement 110 kld has been met from Ground water supply supplemented by groundwater
withdrawal through 1 no. of on-site and existing registered bore well. The ground water
withdrawal had been done as per actual requirement and had not been wasted.
The sewage generated during the operation phase (96 kld) had been treated in the existing
Sewage Treatment Plant (STP) of 150 kld capacity in Hotel, Restaurant & Banquet Hall “Noor
Mahal”. The treated sewage had been recycled/ reused for cooling, toilet flushing and
horticulture in the project site and irrigation of golf course. Therefore, during normal operations,
there had been zero discharge, as the entire treated sewage had been recycled. Hence, no adverse
impact was anticipated on the groundwater quality form the project.
Mitigation Measures
The wastewater generated at site had been treated and reuse/ recycle within the project and
irrigation of green area. There had been no discharge of treated sewage. Moreover, the storm
water from the site had been used for recharging groundwater resources after adequate treatment
of the storm water through oil and grease traps and filtration. The wastewater from the site was
to be used for landscaping only after adequate treatment in Sewage Treatment plant.
The Hotel, Restaurant & Banquet Hall had been well maintained. Solid waste management
practices had been adopted and followed to prevent groundwater pollution through leaching.
Water meters conforming to ISO standards should be installed at the inlet point of water uptake
and at the discharge point to monitor the daily water consumption. To further lower the water
consumption, options of Low flow flushing systems, sensor based fixtures and tap aerators etc
had been explored
Anticipated Impacts
During the post construction phase, cars, scooter/motorcycle had been owned by the population
of Hotel, Restaurant & Banquet Hall. Vehicular emissions had been major source of air pollution
in addition to DG set. Quantum and dispersion of pollutants form vehicular emission had
depended upon the following:
• Volume of traffic on the roads,
• Meteorological conditions.
• Emission sources from DG sets.
From vehicular emissions, PM, NO 2 and CO is the pollutants of primary concern. The dispersion
of vehicular emissions would be confined within 100 m from the road and concentration had
decrease with the increase in distance from road. It was anticipated that the contribution of
vehicular emissions in ambient air quality had been marginal but well within the stipulated
National Ambient. At higher wind speed dispersion had been faster
There was provision of 3 no. of DG sets of total capacity 1500 KVA (3 X 500) for power back
up in the Project. 1 DG set of 500 kVA had been taken as standby & 2 DG sets of 500 kVA each
were operational. The DG sets was equipped with acoustic enclosure to minimize noise
generation and adequate stack height for proper dispersion. The stack characteristics are given in
the Table 4.3 below. This had cause emission of PM, SO 2 , NO 2 and CO. However, since the DG
sets had been operational only during power failure and low sulphur diesel had been used;
therefore, pollutants incremental load in the ambient air environment had been expected to be
minimal. However, an adequate stack height of DG Sets had been provided as per the stipulated
guidelines of Central Pollution Control Board (CPCB) to facilitate proper dispersion of exhaust
gases as given below considering height of the building:
Atmospheric dispersion modeling of pollutants from DG sets was carried out using the USEPA
approved air quality model ISCST3. Hourly meteorological data as monitored at site was used
for impact assessment study. Mixing height data are taken from publication of IMD “Atlas of
Hourly Mixing Height in India, 2008”. The GLC was predicted on the impact zone of 2 km x 2
km at grid spacing 100 x 100 m. The predicted GLCs of PM 10 , CO and SO 2 are found
insignificant. The resultant GLC in the form of isopleths for NO 2 is given in Figure 4.2. Based
on the observed meteorological condition, the 24-hours average maximum predicted GLC of
NO 2 is to be 07.69 μg/ m3 and to be occurred at (700,300) m from the DG sets location. GLC of
NO 2 is less than the permissible limit of 80 μg/ m3 (As per CPCB guidelines). N0 2 is the worst
pollutant in the study had maximum emission in compare to SO 2 , PM 10 , CO and HC. The
meteorological data for 24-hours average maximum predicted concentration is presented in the
Table 4.4. The wind rose diagram showing the wind direction from west to east is given below
in Figure 4.1 and also enclosed in Annex 4(b).
2019 2 1 9 112.5 5
2019 2 1 10 112.5 7
2019 2 1 11 137 7
2019 2 1 12 157.5 7
2019 2 1 13 247.5 7
2019 2 1 14 270 9
2019 2 1 15 270 12
2019 2 1 16 270 9
2019 2 1 17 270 8
2019 2 1 18 270 7
2019 2 1 19 270 8
2019 2 1 20 292.5 8
2019 2 1 21 270 9
2019 2 1 22 270 8
2019 2 1 23 270 9
2019 2 1 24 0 0
Mitigation Measures
• Back up DG sets had complied with the applicable emission norms.
• Adequate stack height for DG sets had been provided as per norms.
• Back up DG sets had been used only during power failure.
• Monitoring of emissions from DG sets and ambient air quality had been carried out as per
norms.
• Plantation and greenery development had work as barrier for the movement of pollutants and
help in pollution control.
Anticipated Impacts
During operation vehicular movement and operation of DG sets are the major sources of noise
pollution and Vibration. But, both these activities DG set and vehicular movement had no any
significant impact on the people residing in the area since DG set had not be operational
continuously and had been kept in the acoustically treated DG room on vibration isolators.
Hence no or minimal impact had been anticipated. It was envisaged that the movement of the
motor vehicles had been restricted to designated carriageways only. Hence, during this phase, no
major impact on noise environment was anticipated.
Mitigation Measures
• DG sets had been installed in the basement to minimize the impact on ambient noise.
• DG room had been provided with acoustic lining/ treatment to insure 25 dB (A) insertion
loss as per the regulations.
• Adequate exhaust mufflers had been provided as per norms to limit the noise.
• DG sets had been installed on vibration isolators
Anticipated Impacts
The project site was a piece of vacant land earmarked for commercial development and had very
sparse vegetative cover. Therefore, there had been no major impact on the local environment.
Any loss of vegetation in the project site had been compensated through landscaping.
Mitigation Measures
A combination of evergreen and ornamental flowering trees, palms, shrubs and ground covers,
mostly indigenous/ local plants, had been planted along the sides of the roads and in open spaces
& along the boundary wall within the complex under the landscape plan. The landscape plan
showing green area, tree species is enclosed as Annex 4(c) and the list of existing tree species is
also given below. Total green area including tree cover is 8,588.69 m2.
Anticipated Impacts
The project site is part of the Karnal. There had not been any threat to biodiversity of the area
due to project. All the project activities during construction had been confined within the
premises of the commercial complex. There was no displacement of fauna – terrestrial and
aquatic or creation of barriers of their movement.
Mitigation Measures
The project had no any direct or indirect adverse impacts on the fauna and avifauna of the area.
However, planting of trees in the project had been an attraction to the local bird population.
Anticipated Impacts
There had been increase in number of vehicles during operation phase of the project. The
increase in traffic due to the project was marginal compared to the existing high volume of traffic
in the area, and therefore the impact had been marginal.
Mitigation Measures
• Provision made for parking space of 404 ECS as against the mandatory requirement of 390
ECS.
• The project complex had had access through the existing 60 m wide Sector road connecting the
NH-1 and SH-7.
• Internal roads of adequate width and separate entries and exits had been provided for smooth
and one-way movement of traffic (Traffic circulation, entry and exits are shown in the
enclosed Traffic Circulation Plan Annex 4(d)).
• Adequate traffic management measures were managed the traffic within and outside the site.
Anticipated Impacts
During operation phase biodegradable solid wastes such as waste vegetables and foods (327 kg/
day) and non-biodegradable solid wastes viz. papers, cartons, thermocol, plastics, glass etc.
(130.8 kg/ day) are likely to be generated from the Hotel, Restaurant & banquet Hall. The solid
wastes are mainly domestic in nature and also suitable management of the solid wastes had been
done. Hence no such adverse impact was anticipated on environment.
Mitigation Measures
The solid wastes generated had been segregated into bio-degradable and non-biodegradable/
recyclable components and collected in separate bins. Both biodegradable and non-
biodegradable wastes had been sold to authorized vendors for recycling of non-biodegradable
wastes and disposal of biodegradable waste. Dewatered/ dried sludge from STP had been used as
manure in horticulture.
Anticipated Impacts
The project site is located in the development area under the development plan of Karnal. The
area is earmarked for Hotel, Restaurant & banquet Hall establishments. All sorts of social
infrastructure like transportation facilities, water supply & sanitation facilities, communication
facilities, educational institutions, hospitals, markets, banks, cultural amenities etc. already exist
in the Karnal City.
In operation phase due to the project development, the surrounding area had positive impact in
terms of increase in land value, public transport facilities and employment opportunities.
Mitigation Measures
Construction had no adverse effects on local communities. Since the project related activities be
confined within the premises, no adverse impacts on surrounding features are envisaged.
Moreover, the project had added to the infrastructure development of the surrounding area and
job opportunity of the local worker during construction.
Anticipated Impact
Once the development and construction of Hotel, Restaurant & banquet Hall had complete, there
had been some long-term positive impact on the economic structure of the area. People in the
area had got direct and indirect employment opportunities. Transport linkages and public
transport facility may be developed due to the operation of the project. There had been increase
in land value of the surrounding due to such development.
Various activities from the Hotel, Restaurant & banquet Hall “Noor Mahal” are likely to had
some impact on the environmental constituents during its construction as well as operational
phase. The impact assessment matrix given in Table 4.5 reveals the impact associated with each
activity of the project on various environmental parameters during construction and function
phase respectively before any mitigation measures are implanted. To assess the severity of the
impacts, they are categorized as follows:
CHAPTER 5
ANALYSIS OF ALTERNATIVES
This chapter discusses the assessment of various options that may be available for different
components of the project in terms of environmental suitability. Lately, there are a number of
options available for the use of building materials, means of energy conservation and methods of
transportation. The various applicable options are thus evaluated for their suitability to project
and environment.
Project site is located in the developed area of the City Karnal where road network and
infrastructure facilities already exist. The project area is well connected to network of roads
leading to various parts of National Capital Region and railway by Karnal Station of rail
network. The distance and direction of nearest highway, railway station and airport are given
below:
It has been ensured during construction phase that the vehicles bringing building construction
material must have Pollution under Check (PUC) certificate and are in good condition. The
vehicles had been temporarily parked inside the project premises for loading unloading activities
of building materials. No public place is used for parking of vehicles.
Parking Provided:
Area proposed for Basement parking = 4293.40m2
Area required for 1 ECS of Basement parking = 35 m²
Parking provided for Basement parking = 122 ECS
5.2.1.1 Wall
Conventionally, sun burnt clay bricks are cemented in the construction of walls. The strength of
these construction materials cannot be compromised which had otherwise pose a threat to the life
and property of the occupants. However, presently, materials with similar properties are easily
available that are made of waste products, thereby reducing the waste burden and conserving
natural resources.
Though most of the construction materials to be used are conventional, energy efficient building
materials, if available locally, has been used as specified in the Energy Conservation Building
Code. The major materials required for construction of the project were steel, cement, bricks,
metal, flooring tiles/stones, sanitary and hardware items, electrical fittings, water, etc.
Following low-energy/ recycled material based finishes/products were used in the exteriors
(paving etc.) and interiors (flooring, doors/ windows, frames, interior wood finishes, paneling,
false ceiling etc.), which use low-energy materials and products and industrial waste/ recycled
products and minimize the use of wood as a natural resource.
• Use of ready mix concrete containing fly ash or PPC which contains fly ash
• Use of PPC (which contains minimum 15% of fly ash) in mortar and plaster
• Use of PPC or fly ash based paving blocks/ tiles and pre-cast elements
• Composite wood products such as hardboards, block-boards, plywood etc. made from recycled
wood scrap & dusts.
• Fibrous gypsum plaster boards made from industrial wastes
• Finished concrete flooring, ceiling tiles, ceramic tiles etc. which are made from low embodied
energy products & recycled materials or from resource efficient finishes
5.2.1.2 Roof
The conventional material used for roofing is RCC, as it is suitable for longer spans. The
constituents of RCC, i.e. cement, sand, aggregate and steel are energy intensive materials and
high embodied energy content.
Alternately, it is proposed to use lightweight synthetic aggregates such as fly ash based
aggregates, which is suitable for manufacture of brick, blocks, and is good substitute for clinker
and natural aggregates. When pre-cast/aerated cellular concrete walling blocks and roofing slabs
are used in multi- storied structures, they reduce the weight, resulting in a more economical
design. They have high rating to fire resistance and provide better insulation and thus improved
energy efficiency. These are manufactured by the aerated cellular concrete manufacturing
process.
5.2.1.3 Superstructure
Structural frame of building comprises of footing, columns, beams and lintels, over which the
envelope of building is supported. A variety of metals are used in buildings, but the major
building material used structurally is steel. Steel has a high-embodied energy and recyclable
content, as well as scrap value. Aluminum forms the second most common material used for
roofing sheets, window frames, and cladding systems, which has the highest recyclable content.
Hence, bulk of the metal needs for the building should be met by steel and aluminum.
• Permeable (porous) paving had been provided wherever feasible to control surface water run-
off by allowing storm water to infiltrate the soil and return to the ground water. The traffic
areas is however continue to be impermeable.
• Use of suitable material fencing, grills, tree covers and benches and even in internal road lights
and green landscaped areas.
5.2.2 Technologies
The area under study falls in Zone-IV, according to the Indian Standard Seismic Zoning Map.
Suitable design was made and modern technologies were adopted while strengthening the
structure to mitigate the seismic impacts. All applicable guidelines have also been followed in
this regard to ensure safety of the building and its residents. The project had used updated
technology in the plant, machineries, equipments both during construction and operation of the
project.
All the machinery were of highest standard of reputed make and had comply with
national/international standards that take care of air and noise pollution control/ vibration
control. Therefore, no significant impact due to operation of machinery is anticipated. The DG
set were enclosed type to comply with the noise level standard and were provided with suitable
stack height as per norm during construction.
During construction, all construction workers were provided with personal protective equipment
(PPE) by the contractors as required under the health & safety norms. Training and awareness
about the safety norms was provided to all involved in construction activities.
At operation stage, DG room has been provided with acoustic lining / treatment to insure 25 dB
(A) insertion loss as per the regulations. Adequate exhaust mufflers had provided as per norms to
limit the noise. Monitoring of emissions from DG sets and ambient air quality has been carried
out as per norms.
Adequate fire protection facilities has been installed including fire detectors, fire alarm and fire
fighting system to guard the building against fires. All fire protection facilities are designed as
per the latest National Building Code. The approvals in this regard had obtained prior to
installation of the fire protection equipments. Layout plan showing location of yard hydrants in
enclosed as Annex 5(b) and Fire NOC enclosed as Annex 5 (c).
To reduce the ecological footprint of the proposed development, use of recycled material for
construction and conserving natural resources is of primary importance. In this light, the use of
recyclable building materials has been proposed for various building materials. It is also
proposed to reuse building components, minimization of construction wastes etc.
The project is also committed towards conservation of water. This includes use of treated
wastewater, rainwater harvesting, provision of low water flow fixtures and raising awareness on
means of water conservation. The need for water conservation in the face of impending water
crisis cannot be overemphasized. The project had followed a three pronged management for
water resource viz: water resource development, minimize use of water and recycle wastewater
generated within the site. Dual plumbing has provided to reduce the freshwater demand of the
project. The wastewater from site is treated in the existing common STP and recycled for toilet
flushing, DG set cooling and landscaping / greenery.
The water demand is proposed to be brought down by the use of water efficient fixtures,
implement best management practices for water in both group housing and horticultural
activities. An important means for achieving this is spreading awareness to the occupants for
generating water conservation awareness. Various types of sensor based technologies along with
low flow devices have been used for urinals, taps in wash basins.
In order to conserve the water resources from surface run off a detailed storm water drainage
system is designed to collect the storm water / rainwater and rainwater harvesting is proposed to
recharge the groundwater. The rainwater collected from the rooftop and other paved areas within
the project area had been conveyed into the rainwater harvesting system consisting of Desilting-
cum-filter chamber, Oil & grease separator and Recharge pit with bore well for recharge into the
groundwater. 8 number of rainwater harvest pits have been provided for recharge of
groundwater. Rainwater harvesting plan is as per the design approved in the manual issued by
the GOI. The plan & section of rainwater harvesting pit & recharge well is enclosed in Annex
2(c). The layout plan showing drainage and location of RWH pits is enclosed as Annex 2(d).
The solid wastes generated in the project building is segregated at source into biodegradable and
non-biodegradable components and collected in separate bins: Both biodegradable and non-
biodegradable wastes are sold to authorized vendors for recycling of non-biodegradable wastes
and disposal of biodegradable waste. Dewatered/ dried sludge from STP is used as manure in
horticulture.
The concept of passive solar design emphasizes architectural design approaches that minimize
building energy consumption by integrating conventional energy-efficient devices, such
mechanical and electrical pumps, fans, lighting fixtures, and other equipment, with passive
design elements, such as building sitting, an efficient envelope, appropriate amounts of
fenestration, increased day lighting design, and thermal mass. The basic idea of passive solar
design is to allow daylight, heat, and airflow into a building only when beneficial.
Efforts had been taken for energy conservation using passive solar architecture wherever it is
possible. Passive solar design refers to use/ prevent the sun’s energy for the heating and cooling
of living spaces. Projections etc. has been provided for shading of summer sunlight to reduce the
heat influx into the building and thus reduce the air conditioning loads. Shading options
wherever available has been used for energy saving. The Energy Efficient Features for the
project are as given below:
• Maximum utilization of natural light
• Use of solar lights in street and landscaping
• Energy efficient motors and pumps
• Appropriate design to reduce heat gain and loss
• Roof-top thermal insulation
• Glazing Glass to reduce the U value as far as possible.
1. CFC Free Equipment, A.C units with CFC Free environment friendly refrigerant should be
installed to protect ozone layer.
2. Building envelope was designed to reduce heat intake from outside. Wall, Roof & Glass
U value should be as per the ECBC guide lines to save energy.
3. Lighting power densities was 20% less than the IGBC base line to save energy compared to
base building.
4. Energy metering should be provided at any four of the below mentioned load for continuous
monitoring and enhance the performance of the building. This adds one credit point in IGBC
Certification.
• Air conditioning
• Internal lighting
• External lighting
• Grey water pumping
• Landscape water pumping
5. Captive Power Generation: DG set should be ISI Rated and certified by Central Pollution
Control Board (CPCB) for emission and noise compliance. (One credit point in IGBC
Certification).
6. Energy saving measures in other appliances & equipment.
• Level controllers in over head water tank should be provided to avoid overflow of water
and waste of energy.
• All pumps should be ISI rated and should be of minimum 60% efficiency.
• LED lamps should be provided in all display /exit sign boards to save energy.
• 20% Solar PV panel with LED Street lighting for the external area with 50% based on
conventional LED Street lighting would result in possible savings.
• Use of regenerating motors for lifts would result in 5% to 10% in energy saving
The project further proposes tree plantations and landscaping development. The plants not only
serve various direct environmental facilities, but also have indirect positive environmental
impacts such as reduction in overall energy use in buildings.
CHAPTER 6
6.1 Introduction
The purpose of the monitoring programme is to ensure that the specified mitigative measures
defined in the EMP are complied with and leads to the desired benefits for the target area and its
population. To ensure the effective implementation of the EMP and gauge the efficiency of the
mitigative measures, monitoring should be undertaken both during the construction and
operation period of the project.
The physio-chemical components are of particular significance to the project to compare with the
surrounding environment on pre-project and post project development. The parameters are as
listed below:
• Air quality
• Water quality
• Noise levels
• Solid waste Management
Of these, the following are selected as the Performance Indicators (PIs) and should be monitored,
since these are well known and comparative data series exist:
• Air Quality
• Noise levels
• Water Quality
• Flora
CHAPTER 7
ADDITIONAL STUDIES
This chapter broadly looks at various aspects related to disaster management and natural
resource conservation.
Hotel, Restaurant & banquet Hall project encompasses the lives of a large number of people. It
also involves installation of various structures and machineries that meet the comfort and needs
of its population but may also pose serious threat to the occupants in case of an accident. It is
thus considered necessary to carry out a risk assessment and disaster management plan for the
project.
It is attempted to plan and construct the buildings following all safety norms. However, it is not
always possible to totally eliminate such eventualities and random failures of equipment or
human errors. An essential part of major hazard control has therefore, to be concerned with
mitigating the effects of such emergency and restoration of normalcy at the earliest. A detailed
table showing activities during construction and operation phase along with mitigation measures
are given in Table 7.1.
Display of carrying capacity i.e. load (No. of correctly slung/ secured loads, lifting
person) incorrectly slung, defective lifting equipment good condition-use of proper hand
equipment, unsecured loads, craning in close signals-falls while unloading controlled.
proximity to building people and plant-falls-
falling materials.
Visitors Presence at site Sufficient hoarding-fencing and barricades-
Falls-struck by-dropped materials-road safe pedestrian access past site traffic
accidents-insufficient hoarding or fencing- management for loading and delivery-
pedestrian access past site-mechanical plant construction separated from occupied areas of
movement on and off site. projects.
Apart from above mitigation measures, first aid facility is available at the construction site. First
aid is being provided immediately after an accident to injure. Nearby hospital are Rama Super
Speciality Hospital (3.51 km, W), Life Care Hospital (2.34 km, SW) and Amar Hospital (2.75
km, SW). Nearest Police station is Sector-6 Police Chowki (3.10 km, SW).
The overall objective of an Emergency Response Plan (ERP) is to make use of the combined
resources at the site and outside services to achieve the following:
The ERP is therefore related to identification of sources from which hazards can arise and the
maximum credible loss scenario that can take place in the concerned area. The plan takes into
account the maximum credible loss scenario-actions that can successfully mitigate the effects of
losses/ emergency need to be well planned so that they would require less effort and resources to
control and terminate emergencies, should the same occur.
Standards and codes used in building construction to minimize the risk of natural calamities like
wind load, seismic load (earthquake), thunder storm/ lightning etc, as per NBC 2016 are given
below:
Design Standards
● IS: 456-2000 - Code of Practice for Plain and Reinforced Concrete
● IS: 875 (Part 1 to 5)-1987 - Code of Practice for Design Loads (Other Than Earthquake) for
Buildings and Structures.
Part-1 Dead Loads- Unit Weights of Building Materials and Stored Materials
Part-2 Imposed Load
Part-3 Wind Loads
Part-4 Snow Loads (Not relevent in this case)
Part-5 Special Loads and Combinations
● IS: 1893 (Part 1)-2002 - Criteria for Earthquake Resistant Design of Structures
● IS: 4326- Earthquake resistant design and construction of building
● IS: 13920-1993-Code of Practice for Ductile Detailing of Reinforced Concrete Structures
subjected to Seismic Forces
● IS: 3370 (Part I, II & IV)- 1965: Code of practice for concrete structure for the storage of
liquids
● IS: 2950 (Part I) Code of practice for design and construction of raft foundations
● IS: 1904- Code of practice for design and construction of foundations in soils
● IS: 800-2007–General construction in steel-code of practice.
Main hazards identified for the project include hazards pertaining to fires in buildings and fire in
diesel storage areas, earthquake and LPG leakage and an ERP pertaining to these is described in
the following section.
If indoors:
• Take cover under a piece of heavy furniture or against an inside wall and hold on.
• Stay inside: The most dangerous thing to do during the shaking of an earthquake is to try to
leave the building because objects can fall on you.
If outdoors:
Move into the open, away from buildings, streetlights, and utility wires. Once in the open, stay
there until the shaking stops.
If in a moving vehicle:
Stop quickly and stay in the vehicle. Move to a clear area away from buildings, trees, overpasses,
or utility wires. Once the shaking has stopped, proceed with caution. Avoid bridges or ramps that
might have been damaged by the quake.
• Personnel in the nearby buildings to close all doors and windows to prevent entry of the leaked
gas.
• Source of leakage to be traced and isolated from all the other areas. And if required use
pedestal fans to bring down the gas concentration.
• In case of a fire follow the instructions in case of fire.
with automatic fire detection and alarm system. Nearest fire station to the site is Transport Nagar
fire station at a distance of 5.69 km in SW direction from the project site.
The project is as per the Change in Land-Use Plan. Drinking and domestic water is abstracted
from ground water and as the provision of HUDA has been started we will switch over to the
source i.e., HUDA water and sewerage facility.
There is a dual plumbing system for using recycled treated sewage, which save the consumption
of fresh water. There are two pipe lines, one supplying freshwater for drinking, washing, cooking
etc. and other for supply of recycled treated sewage for flushing, landscape irrigation and cooling
etc. This result in saving fresh water demand and life of existing sewerage is being improved.
Various types of sensor based technologies along with low flow devices (solenoid self-operating
valves) are being used for urinals, taps in wash basins. There is low flush cisterns working on 3
& 6 litres/ flush instead of conventional 12.5 litres.
Awareness is also being spread amongst the residents on the following lines:
• Timely detection and repair of all leakages;
• Turning off the main valve of water while going outdoor;
• Watering of lawn or garden during the coolest part of the day (early morning or late evening,
hours) when temperature and wind speed are lowest. This reduces losses due to evaporation.
• Planting of native and/or drought tolerant grasses, ground covers, shrubs and trees. Once fully
grown, they need not to be watered frequently.
• Avoiding over watering of lawns. Good rains eliminate the need for watering for more than a
week.
• Setting sprinklers to water the lawn or garden only, not the street or sidewalk;
• Avoiding installation or use of ornamental water features unless they recycle the water and
avoiding running them during drought or hot weather;
• Installation of high-pressure, low-volume nozzles on spray washers;
• Replacement of high-volume hoses with high-pressure, low-volume cleaning systems
• Equipping spring loaded shutoff nozzles on hoses;
• Installation of float-controlled valve on the make-up line, closing filling line during operation,
provision of surge tanks for each system avoid overflow;
• Washing vehicles less often,
The increased hard surface of Commercial complex increases the rainwater/storm water runoff as
compared to the otherwise barren land. It is proposed to harvest this rainwater run-off that is
recharge the groundwater resource while reducing the burden of storm water management of the
area and eventually natural water bodies. Apart from the open spaces, it is proposed to harvest
the roof top rainwater. The storm water is treated through an oil and grease trap and allowed to
flow through layers of sand and gravel for filtration prior to reaching the water table, to avoid
any possibility of groundwater contamination.
The following management measures are suggested to protect the water quality during
construction phase.
• Avoid excavation during monsoon season.
• Care would be taken to avoid soil erosion.
• Community toilets were constructed on the site during construction phase and the wastewater
was channelized to the septic tank in order to prevent wastewater from entering the water
bodies.
• To prevent surface and ground water contamination by oil/grease, leak proof containers would
be used for storage and transportation of oil/grease. The floors of oil/grease handling area
would be kept effectively impervious.
• Collection and settling of storm water, prohibition of equipment wash downs, and prevention of
soil loss and toxic release from the construction site was adhered to minimize water pollution.
Most of the storm water produced on site is harvested for ground water recharge. Thus proper
management of this resource is a must to ensure that it is free of contamination. A detailed Storm
Water Management Plan is developed which consider the sources of storm water. The plan
incorporate best management practices which include the following:
• Regular inspection and cleaning of storm drains.
• Installation of clarifiers or oil/ water separators system of adequate capacity around parking
areas and garages as per requirement.
• Cover waste storage areas.
• Avoid application of pesticides and herbicides before wet season.
• Conducting routine inspections to ensure cleanliness.
• Preparation of spill response plans, particularly for fuel and oil storage areas.
• Provision of silt traps in rain water harvesting system.
• Good housekeeping in the above areas.
• Use of ready mix concrete containing fly ash or PPC which contains fly ash
• Use of PPC (which contains minimum 15% of fly ash) in mortar and plaster
• Use of PPC or fly ash based paving blocks/ tiles and pre-cast elements
• Composite wood products such as hardboards, block-boards, plywood etc. made from recycled
wood scrap & dusts.
• Fibrous gypsum plaster boards made from industrial wastes
• Finished concrete flooring, ceiling tiles, and ceramic tiles etc. which are made from low
embodied energy products & recycled materials or from resource efficient finishes.
The principles of energy conservation is also being embedded in the buildings through use of
energy efficient fixtures, maximum availability of natural light, ventilation and use of solar
energy for partly open area lighting.
CHAPTER 8
PROJECT BENEFITS
8.1 General
The project site for Hotel, Restaurant & Banquet Hall, Recreational Park and health club “Noor
Mahal” located at Village Phusgarh, Dist- Karnal, Haryana. The project was developed on a total
plot area of 7.07 acres (28,628.96 m2) with ground coverage of 7,904.92 m2.
8.5.2 Soil
Soil environment was temporarily affected due to activities like site preparation; excavation,
material handling & storage etc. during construction phase but the activity was not result in any
significant land disturbance causing soil erosion, subsidence and instability.
There is sufficient parking space for the vehicles in operation phase as per the norms. The project
has parking space of 404 ECS as against the mandatory requirement of 390 ECS. No public
place was used for parking of vehicles reducing traffic jam and less vehicular pollution. Wide
internal road and separate entry and exits are provided for the smooth traffic movement within
the project complex. The project has roads on the periphery that facilitate the movement of
traffic. Internal roads, ramps for basement with suitable width had also been provided. Adequate
lighting arrangement had been provided covering all corners. The vehicular traffic was around
the periphery of the project without disturbing the landscaped areas and organized open spaces.
The design of the building is such that maximum use of natural lighting can be achieved. The
walls, roofs and opening are being designed to achieve minimum influx of heat. Few energy
efficient features proposed are:
• CFL & T-5 lighting in common areas and True-lite fluorescent lamps in basements
• Use of solar lights partly in common areas
• Energy efficient water cooled chillers for HVAC system
• Energy efficient motors
• Variable frequency drives for secondary chilled water recirculation pumps
• Appropriate design to reduce heat gain and loss
• Roof-top thermal insulation.
• Glazing glass: to maintain the U value as far as possible.
• External glazing is below 60% of the total vertical surface as per ECBC.
The rainwater collected from the rooftop and other paved areas within the project area is being
conveyed into the rainwater harvesting system consisting of Desilting-cum-filter chamber, Oil &
grease separator and Recharge pit with bore well for recharge into the groundwater. Thus the
rainwater collected from paved area and roof top is treated and only clear treated water is
recharge in to ground through 7 number of rainwater harvest pits.
No natural water body exits near the site so; no water pollution on surface water quality due to
the construction of the project is envisaged.
• DG sets was installed in the basement to minimize the impact on ambient noise.
• DG room is being provided with lining/ treatment to insure 25 dB (A) insertion loss as per the
regulations.
• Adequate exhaust mufflers are being provided as per norms to limit the noise.
• The DG sets was built in damper for anti-vibration.
• Use of ready mix concrete containing fly ash or PPC which contains fly ash
• Use of PPC (which contains minimum 15% of fly ash) in mortar and plaster
• Use of PPC or fly ash based paving blocks/ tiles and pre-cast elements
• Composite wood products such as hardboards, block-boards, plywood etc. made from recycled
wood scrap & dusts.
• Fibrous gypsum plaster boards made from industrial wastes
• Finished concrete flooring, ceiling tiles, ceramic tiles etc. which were made from low embodied
energy products & recycled materials or from resource efficient finishes
• Waste such as steel, iron rods etc. from construction activities was recycled and reused as far as
possible.
• The wastewater was treated in the STP and was reused for toilet flushing, cooling, and
horticulture purpose making the unit as zero discharge during operation phase of the project.
Dewatered/ dried sludge from STP is used as manure in horticulture.
• Recyclable/ non-biodegradable solid wastes comprising paper, plastic, glass etc., is being sold
to authorized recyclers for reuse.
CHAPTER 9
INTRODUCTION
Identification and prediction of impacts further needs to suggest the mitigation measures which
would play a vital role in prevention of environmental degradation during operational phase of
the project. This leads to preparation of Environmental Management Plan (EMP), therefore EMP
forms an imperative part of EIA process.
The Environmental Management plan is a site specific plan developed to ensure that the project
is implemented in an environmentally sustainable manner where all contractors and
subcontractors, including consultants if any, understand the potential environmental risks arising
from the project and take appropriate actions to minimize those risks. EMP also ensures that the
project implementation is carried out in accordance with the planned design and by taking
appropriate mitigates actions to reduce adverse environmental impacts during project’s life cycle.
The project is being created certain inevitable impacts, mainly during construction phase,
although within permissible limits as mentioned in Chapter 4 and can be reduced significantly
with the help of effective implementation of a well-designed EMP. The potential environmental
impacts, which need to be regulated, are as mentioned below:
• Air pollution due to the emission of particulate matter and gaseous pollutants from operation
of D.G. Sets during power failure and vehicular movement;
• Noise pollution due to various noise generating equipment as well as vehicular movement;
• Water resource management to ensure continuous water supply.
• Wastewater generation from sanitary/domestic activities; and
• Generation of municipal solid wastes from occupants, maintenance of roads, parks, common
areas including electrical and plumbing wastes.
• Energy conservation methods
• Maintenance of Building Management Systems and emergency aids.
To ensure better environment in & around the project site, effective EMP needs to be developed
separately for operational phase.
Environmental Management Plan (EMP) is the key to ensure a safe and clean environment. The
desired results from the environmental mitigation measures proposed in the project may not be
obtained without a management plan to assure its proper implementation & function. The EMP
envisages the plans for the proper implementation of mitigation measures to reduce the adverse
impacts arising out of the project activities. EMP has been prepared addressing the issues like:
• Pollution control / mitigation measures for abatement of the undesirable impacts caused during
the construction and operation stage
• Institutional set up identified/recommended for implementation of the EMP
• Post project environmental monitoring program to be undertaken
• Expenditures for environmental protection measures and budget for EMP
The construction phase monitoring and post project monitoring plan including areas, number and
location of monitoring stations, frequency of sampling and parameters to be covered is
summarized. The monitoring will be the responsibility of Facility Manager.
The post operational monitoring program is being under the supervision of the Facility Engineer
at the project site. Monitoring is being get carried out by recognized laboratories.
CHAPTER 10
10.1 Introduction
The Project is spread over an area of 7.07 acres (28,628.96 m2) with ground coverage of
7,904.92 m2 and Built-up area is 24,671.106 m2. Total green area including tree cover which is
8,588.9 m2; 30% of total plot area.
For this study, the impact zone shall confine within an angular radius of 10 km from the project
boundary. For the purpose of certain environmental components, the radius has extended up to 5
km as well. The EIA is conducted to establish the baseline environmental setting in the study
area, assessment of potential impacts on different environmental components, design of
mitigation measures so as to keep impacts within acceptable limits and strengthen the positive
impacts.
The summary highlights the baseline environmental status, key environmental issues and their
likely impacts and also lists the major recommended mitigation measures to attenuate the
impacts. It describes the findings of the EIA study to aid in decision making and provides project
related information and environmental impacts.
The project is located in Village Phusgarh, Dist- Karnal in the state of Haryana and
approximately 5.95 km, from Karnal Railway Station. The site was a barren land and was
designated for development into a Hotel, Restaurant & banquet Hall, Recreational Park and
Health Club development as per the Change in Land-Use Plan. The site falls under earthquake
sensitive zone IV on the MSK Scale indicating moderate intensity.
tallest building
No. of floors & Lower Ground Floor + Mezzanine Floor + Upper Ground Floor + 3
basement Floors + Basement
Populations Hotel – 429, Banquet Hall – 525, Restaurant - 80
Area utilization 1st -3rd floor; Basements: Parking & Services
Parking Facilities Total 404 ECS (Basement:122 + Parking Area Under Ramp: 19 +
Surface:263)
Power requirement & 1,500 kVA by Uttar Haryana Vitran Power Nigam
source
Power Backup 3 nos. of back-up DG sets of total capacity 1,500 kVA (3 x 500 kVA). 1
DG set of 500 kVA was taken as standby & 2 DG sets of 500 kVA are
operational.
Water requirement & Fresh Water: 110.34 KLD (From ground water)
source
Sewage treatment & Sewage treatment facility: STP of 150 KLD.
disposal Sewage discharge: Zero Discharge, 100% recycle of treated sewage
Solid wastes 327 kg/day
generation
Green-area 8,588.9 m2 including tree cover (i.e. 30% of plot area)
Project cost Rs. 56 Crores
The baseline environmental status was assessed based on primary and secondary data collected
either through in-site field observation or obtained from agencies such as Irrigation Department,
India Meteorological Department (IMD), Central Ground Water Board, Geological Survey of
India, State Ground Water Department, State Pollution Control Board, Census of India and Local
Forest Department, Non-Governmental Agencies. The baseline status established from analysis
of secondary and primary data and predicted impacts are discussed below. The mitigation
measures are also provided along with.
Land use
The project site is at Village Phusgarh, Dist- Karnal, Haryana. The total plot area 7.07 acres
(28,628.96 m2). As per zoning plan, the land was earmarked for development of Hotel,
Restaurant & Banquet Hall, Recreational Park and Health Club.
The project site is earmarked for Hotel, Restaurant & Banquet Hall, Recreational Park and
Health Club development as per the Change in Land-Use Plan (enclosed as Annex 1(b)).The
land was earmarked for Commercial complex as per the Change in Land-Use plan. Project was
planned and designed as per the regulations and procedures laid down by the Central Ground
Water Authority (CGWA) and Director of Town & Country Planning (DTCP), Haryana.
There was no land disturbance resulting in erosion, subsidence and instability as it was a flat
land. The quantity of excavated earth was about 15,286 m3, a part of which was used for
backfilling and leveling of project site. The topsoil was preserved separately and was reused for
horticultural purpose. Waste construction materials was recycled and excess construction debris
& excavated earth was disposed at vacant low lying lands of green area for filling & leveling.
Slope Analysis:
The project area possesses slightly undulating terrain. The Contour plan of the project site is
enclosed as Annex 3 (a). Highest contour level is 802.30 m & the lowest level is 800.50 m.
Difference between the highest & lowest level is 1.8 m.
Erosion/ Subsidence:
There was no vulnerability of subsidence. Proper greening & paving of area was not cause soil
erosion problem.
Seismicity:
The area falls under the Zone IV according to the Indian Standard Seismic Zoning Map. The
project is earthquake resistant taking into account the latest provisions of Indian Standards
Codes. Suitable design was made to mitigate the seismic impacts.
Soil Quality
Karnal region is occupied by quaternary alluvium and Precambrian meta-sediments of Delhi
System. Delhi super group is represented by Alwar quartzite, and pegmatite intrusive of the
Alwar series and slates of phyllites and quartzite of the sub-recent alluvium and sand dunes. The
soils in the region are sand to loamy sand in sandy plain areas, sandy loam to clay loam / silty
clay loam in alluvial plains, loam sand to loam, calcareous in salt affected plains; silty loam to
loam in low lands and loamy sand to loam, calcareous in hills. In the study area, variations in the
pH of the soil were found to be slightly alkaline (6.51 to 6.81). Electrical conductivity (EC) is a
measure of the soluble salts and ionic activity in soil. In the collected soil samples the
conductivity ranged from 569 to 594 μmhos/ cm. The physico-chemical characteristics of the soil
of the project site, as obtained from the analysis of the soil sample, are presented in Chapter 3.
Total Water
Total Rate of water Requirement
S. No. Description
Occupancy demand (lpcd) (KLD)
A. Hotel
1. Guest 244 320 78
2. Visitor Staff 150 15 2.25
3. Resident Staff 35 135 4.72
B. Banquet Hall 525 15 7.8
C. Restaurant
Guest 80 70 5.6
D. Make up water for 70*40*4 12
swimming pool (Volume)
110 KLD
Total Domestic water Requirement
Horticulture and
E. 8,588.69 m2 4.5 liter /sqm 38
Landscape development
F. HVAC Cooling @ 0.9xTRx12 hours 7
(660 TR) for 12 hrs
@ 100%
FLUSHING (5 KLD)
5 KLD
RESIDENT STAFF
@ 90 %
86 KLD
7 KLD
HVAC COOLING (7 KLD)
The details of quantity of sewage and sewage collection, treatment, reuse and disposal are given
in the Table 10.3. Location of the STP for project is shown in Annex 2 (b).
Reuse / recycle and Disposal During normal operations, there is zero discharge, as the entire
of treated sewage (100%) treated sewage is being reused and recycled for cooling,
horticulture and toilet flushing.
Location of STP Inside the project premises.
The rainwater collected from the rooftop and other paved areas within the project area were
conveyed into the rainwater harvesting system consisting of Desilting-cum-filter chamber, Oil &
grease separator and Recharge pit with bore well for recharge into the groundwater.
Monitoring of all the five locations had been done and results of all the parameters were found
not within the permissible standards of NAAQS. The levels of PM 2.5 , PM 10 , NO 2 , SO 2 and CO
at all five locations were found not within the standards prescribed by NAAQS at all the five
locations. Thus dust emissions from construction activities were require comprehensive
mitigation measures and best construction practices.
Adequate stack heights as per norm for DG set to provide for sufficient dispersion of pollutants.
Water sprinklers were used to suppress dust during construction. During the operation phase,
green belt and green area development is to restrict and absorb air pollutants.
Noise levels were observed at five locations within the study area. Noise monitoring has been
done and results of noise monitoring are within the permissible limits of ambient noise quality
standards at 65 dB (A) and 55 dB (A) for daytime and night time respectively.
The noise emitted from construction equipments during construction period was high and
required occupational preventive measures and temporary noise barriers for noise attenuation.
The construction period been about three year (approx.) duration, was require significant
mitigation measures such as restricted loud noise activities to daytime, provision of PPEs and
acoustic enclosures for DG set. In the operation phase, noise pollution has been checked through
acoustic enclosures of DG sets and green belt plantation.
The population of the Phusgarh district is around approximately 4830 as per Census 2011 data
(Source - http://www.census2011.co.in/data/village/59309-phusgarh-haryana.html).
As most of the worker in construction was from the local villages, no significant change in the
local demographic structure was envisaged for the project. The project site is located in the
development area under the development plan of Karnal. The area is earmarked for Hotel,
Restaurant & banquet Hall, Recreational Park and Health Club establishments. All sorts of social
infrastructure like transportation facilities, water supply & sanitation facilities, communication
facilities, educational institutions, hospitals, markets, banks, cultural amenities etc. already exist
in the Karnal City.
The construction was not having adverse effects on local communities. Since the project related
activities be confined within the premises, no adverse impacts on surrounding features were
envisaged.
Moreover, the project add to the infrastructure development of the surrounding area and job
opportunity of the local worker during construction
The project is proposed to have parking space of 404 ECS against the mandatory requirement of
390 ECS. The details of parking facilities proposed are given in Table 10.7 below.
Parking Provided:
Area proposed for Basement parking = 4293.40m2
Area required for 1 ECS of Basement parking = 35 m²
Parking provided for Basement parking = 122 ECS
The power supply is being supplied by Uttar Haryana Bijli Vitran Power Nigam (UHBVN). The
connected load for the Commercial Project is approx. 1500 KVA. There are 3 no. of DG sets of
total capacity 1500 KVA (3 X 500) for power back up in the Project. 1 DG set of 500 kVA was
taken as standby & 2 DG sets of 500 kVA each are operational. The DG sets is equipped with
acoustic enclosure to minimize noise generation and adequate stack height for proper dispersion.
Efforts are being taken for energy conservation using passive solar architecture wherever it was
possible. Passive solar design refers to use/ prevent the sun’s energy for the heating and cooling
of living spaces. Projections etc. provided for shading of summer sunlight to reduce the heat
influx into the building and thus reduce the air conditioning loads. The energy efficiency features
of the project are:
As a part of energy conservation measures energy efficient building material is used for
construction of the project and few of them are:
Total quantity of solid waste likely to be generated in the project during operation is 327 kg/ day.
The solid wastes generated was segregated into bio-degradable and non-biodegradable/
recyclable components and collected in separate bins. Both biodegradable and non-
biodegradable wastes are sold to authorized vendors for recycling of non-biodegradable wastes
and disposal of biodegradable waste. Dewatered/ dried sludge from STP used as manure in
horticulture.
condition with low noise & emission is being used and engines were
turned off when not in use.
Noise Level • Protective gears of such as ear mufflers etc. were provided to
construction personnel exposed to high noise levels.
Solid Waste • Waste construction materials were recycled and excess construction
debris was being disposed at designated places in tune with the local
norms.
Landscape • Appropriate landscape including plantation of evergreen and
ornamental flowering trees, palms, shrubs and ground covers at open
spaces within the complex was done, which would serve the dual
purpose of controlling fugitive dust and improving the aesthetics of
the area.
Safety • Adequate safety measures complying with the occupational safety
manuals were adopted to prevent accidents/hazards to the
construction workers.
Operation Stage:
Air Quality • Sewage is treated in the existing STP.
• Entire treated sewage is reused for cooling, toilet flushing and
horticulture.
• Regular monitoring of STP effluent quality is being carried out as per
norms.
Water Quality • Back up DG sets are complied the applicable emission norms.
• Adequate stack height for DG sets is provided as per norms.
• Back up DG sets is used only during power failure.
• Regular monitoring of emissions from DG sets and ambient air quality
is carried out as per norms.
Noise Level • DG sets was installed in the basement to minimize the vibration and
impact on ambient noise.
• DG room was treated acoustically as per norms to control the noise
from DG sets.
• Pumps, STP, Compressors, DG sets etc. is being properly maintained
for fuel efficiency and noise control.
• Personal protective equipment is provided to the maintenance staff
working in high noise areas.
Solid Waste • Solid wastes are segregated into organic and inorganic components.
• Both biodegradable and non-biodegradable wastes are sold to
authorized vendors for recycling of non-biodegradable wastes and
disposal of biodegradable waste
• Dewatered / dried sludge from STP is used as manure in horticulture.
Hazardous Wastes • Used oil from DG sets is sold to registered recyclers.
Rain Water • 8 rainwater harvesting are provided by means of recharge into the
Harvesting groundwater.
Fire Protection • Adequate fire protection facilities is being installed including fire
detectors, fire alarm and fire fighting system as per National Building
Code of India.
landscape • Proper maintenance of landscape round the year including replacement
of the decayed plants.
Safety • Adequate safety measures complying with the occupational safety
manuals to prevent accidents/hazards to the maintenance workers.
Others • The building is provided with disabled-friendly design, timber-free
construction, energy efficient lighting & ventilation, and control of
indoor environment.
• Undertaking all necessary pollution control measures to maintain the
emissions and discharges within the prescribed/stipulated limits.
10.5 Conclusion
Based on the environmental assessment, the associated potential adverse environmental impacts
can be mitigated to an acceptable level by adequate implementation of the measures as stated in
the EIA and the EMP.
Hence, it may be concluded through the EIA study that the project have very negligible
environmental impact and significant positive economic and social impact on the local
community.
CHAPTER-11
11.3 Under the guidance of following Coordinator & Functional Area Experts:
Cordinator/FAE Name Signature
EIA Coordinator Mr. Himanshu Goel
FAE-WP Mr. Himanshu Goel
CHAPTER 12
M/s Jewel Classic Hotel Pvt. Ltd. has standard operating procedures to identify and bring into
focuses any infringement/ deviation/ violation of the environmental/ forest norms and conditions.
The details of procedures are given in the Table 12.1 below.
Table 12.1 Applicable Compliance under various Environmental Acts & Rules:
M/s Jewel Classic Hotels Pvt. Ltd has adequate organizational structure to deal with the
environmental issues and for ensuring compliance with the conditions of environmental
approvals. The organization structure is shown in the following chart at Figure 12.2.
• Facility Manager, Planning Manager and legal managers reports to General Manager
• General manager reports to Managing Director of the
Managing Director
General Manager
CHAPTER-13
13.1 Introduction:
M/s Jewel Classic Hotels Pvt. Ltd. Of Hotel, Restaurant & Banquet Hall “Noor Mahal”
located at Village Phusgarh, Dist- Karnal, Haryana. The plot area measuring 28,628.96 m2
(or 7.07 acres). After expansion plot area will be increased to 28,628.96 sq.m. by acquiring
more land & built up area is increase to 24,671.106 sq.m.
The total built-up area of the project will be 24,671.106 sqm. Hence, the project falls under
Category “B” Schedule 8 (a) of EIA notification, 2006. However, as per the notification
vide S.O. 804(E) dated 14.03.2017 the project was submitted to MoEF&CC under
violation category. Subsequently, it was considered in SEAC meeting dated 02.05.2018
and thereafter, TOR was granted by MoEF&CC vide its letter no. SEIAA/HR/19/946
dated August, 2018.
Now as per amendment in notification vide S.O. 1030(E) dated 8th March, 2018 & OM
no. Z11013/22/2017-IA. II (M) dated 15.03.2018 & 16.03.2018, the project falls under
category ‘B’, of Schedule 8(a) & is exempted from Public Hearing and will be appraised
by SEAC/SEIAA, Haryana.
Hence, in view of the aforesaid notification, a Damage Assessment and Remediation plan
is required to explain the extent of damage done due to construction.
Assessment of ecological damage with respect to air, water, land and other environmental
attributes has been done and EMP has been prepared comprising remediation plan and
natural and community resource augmentation plan corresponding to the ecological
damage assessed and economic benefits derived due to violation.
Project Details:
Project Name M/s Jewel Classic Hotels Pvt. Ltd. of Hotel, Restaurant &
Banquet Hall “Noor Mahal” located at Village Phusgarh, Dist-
Karnal, Haryana.
Location Village Phusgarh, Dist- Karnal, Haryana.
Type of Project Hotel, Restaurant & Banquet Hall
Plot Area 7.07 acre (28,628.96 m2)
Built-up Area 24,671.106 m2 (FAR + Basement area)
Ground Coverage 7,904.92 m2
Floor & basement area Floor Area:- 19,482.35 m2 , Area of basement :- 4,293.40 m2
Building height of 27.31m
tallest building
c
M/s Jewel Classic Hotels Pvt. Ltd. 134
Hotel, Restaurant & Banquet Hall,
Recreational Park & Health Club “Noor Mahal”
Village Phusgarh,
Distt. Karnal, Haryana.
No. of floors & Lower Ground Floor + Mezzanine Floor + Upper Ground Floor +
basement 3 Floors + Basement
Populations Hotel – 429, Banquet Hall – 525, Restaurant - 80
Area utilization 1st -3rd floors: Flats; Basements: Parking & Services
Parking Facilities Total 468 ECS (Basement:115 + Parking Area Under Ramp:4 +
Surface:349)
Power requirement & 1,500 kVA by Uttar Haryana Vitran Power Nigam
source
Power Backup 3 nos. of back-up DG sets of total capacity 1,500 kVA (3* 500
kVA). 1 DG set of 500 kVA will be taken as standby & 2 DG
sets of 500 kVA are operational.
Water requirement & Fresh Water: 110.34 KLD (From ground water)
source
Sewage treatment & Sewage treatment facility: STP of 150 KLD.
disposal Sewage discharge: Zero Discharge, 100% recycle of treated
sewage
Solid wastes generation 327 kg/day
Green-area 8,588.9 m2 including tree cover (i.e. 30% of plot area)
Project cost Rs. 56 Crores
13.1 (a) Chronological details of the project with its legal approvals.
c
M/s Jewel Classic Hotels Pvt. Ltd. 135
Hotel, Restaurant & Banquet Hall,
Recreational Park & Health Club “Noor Mahal”
Village Phusgarh,
Distt. Karnal, Haryana.
pollution) Act and Air (Prevention & Control of pollution) Act, 1981 and Environment
protection act 1986. A copy of the same is attached as Annexure III.
xi. Further, we had submitted the letter subject: Issue of Environment Clearance for
expansion of Hotel Noor Mahal, Karnal to Member Secretary State Level Environment
Impact Assessment Authority Haryana, Panchkula. A copy of the same is attached as
Annexure IV.
xii. Further, Gazette notification S.O. 804 (E) dated 14/03/2017 issued by MOEF&CC, GoI.
We had submitted the application for Environment Clearance under violation to
MOEF&CC proposal no. IA/HR/NCP/69957/2017 dated 29.9.2017. Acknowledgment is
attached as Annexure V.
xiii. Thereafter, TOR was granted by MoEF&CC vide its letter no. SEIAA/HR/19/946 dated
August, 2018.
Hotel, Restaurant & Banquet Hall, Recreational Park and Health Club name as “Noor
Mahal” is operation and all the buildings, services & utilities have been laid down by the
project proponent and are being managed by the project proponent.
As per notification vide S.O. 804(E) dated 14.03.2017 it has been notified that the violation
cases/non-Compliance will involve the assessment of ecological damage, remediation plan
and natural and community resource augmentation plan.
We have collected and analyzed the data, for assessment of ecological damage, preparation
of remediation plan and natural and community resource augmentation plan and following
methodology will be adopted.
The overall impact on air, water, noise, soil and land environment will be assessed. In
addition, it will be weighed against the positive impact created on the socioeconomic
scenario. To estimate the impact produced, a framework has been designed as given ahead:
• The place of activity is permissible for the purpose (like it should not fall in eco-sensitive
zones etc.)
• Environmental Sensitivity to be clearly defined
• Status of work done till date
• Status of activities (in quantitative terms) undertaken during violation period and extent of
damage
c
M/s Jewel Classic Hotels Pvt. Ltd. 136
Hotel, Restaurant & Banquet Hall,
Recreational Park & Health Club “Noor Mahal”
Village Phusgarh,
Distt. Karnal, Haryana.
Score Rating
3 Major
2 Moderate
1 Minor
0 None
-1 Minor
-2 Moderate
-3 Major
Damage Scale
Particulars Score Range
Extremely Damaging -41 to -60
Damaging -21 to -40
Minutely Damaging -11 to -20
Not Damaging Significantly <-10
Damage Scale
Particulars Score Range
Extremely Damaging -59 to -87
Damaging -30 to -58
Minutely Damaging -16 to -29
Not Damaging Significantly <-15
• To suggest control measures for preventing deterioration of air quality along with
approximate cost
• To suggest control measures for preventing deterioration of noise quality along with
approximate cost
• To suggest control measures for preventing deterioration of water quality along with
approximate cost
• Remediation plan of loss of top soil, loss of vegetation including trees and their
approximate cost
• To suggest control measures for keeping community safe from adverse effects of activity
approximate cost
• Plan and suggest Development of shelter of green belt to improve environment
• To suggest control measures for preventing deterioration of Environmental characteristics
like Air, water, Noise, Soil, biodiversity & social environment.
c
M/s Jewel Classic Hotels Pvt. Ltd. 137
Hotel, Restaurant & Banquet Hall,
Recreational Park & Health Club “Noor Mahal”
Village Phusgarh,
Distt. Karnal, Haryana.
• To propose and suggest the approximate cost required against the recommended control
measures to be adopted.
• To overall enhance environmental features like vegetation, top soil management etc.
Augmentation plan will include various activities to be taken for augmentation of Natural
Resources like water, land vegetative cover in a time bound manner and estimation of
financial implication.
The score calculated based on the above criteria along with the conditions given in TOR will
be used for damage assessment for estimation of the penal amount to be provided against
creating impact under violation.
To assess these environmental parameters team has been deputed to assess preliminary
assessment of damage to environment. Based on site inspection and the documentary
evidences the environmental aspects vs activity has been filled.
The Construction has been done by the contractor M/s Jewel Classic Hotels Pvt. Ltd. The
Damage Assessment and Remediation of environmental parameters along with Cost basis is
explained in the table No. 13.4:
c
M/s Jewel Classic Hotels Pvt. Ltd. 138
Hotel, Restaurant & Banquet Hall,
Recreational Park & Health Club “Noor Mahal”
Village Phusgarh,
Distt. Karnal, Haryana.
c
M/s Jewel Classic Hotels Pvt. Ltd. 139
Hotel, Restaurant & Banquet Hall,
Recreational Park & Health Club “Noor Mahal”
Village Phusgarh,
Distt. Karnal, Haryana.
S. Project Phase Environment Environment Damage assessed Remediation / Mitigation Measures already
No. Aspects Impacts adopted
1 Construction Air Environment Air Pollution & Dust deposition, resulting in the a. Site was enclosed with barricade along
Phase Air quality soiling of surfaces; the project boundary.
degradation Impact on ecology/vegetation b. Water sprinkling was done.
Impact on human health c. Transportation of construction material
Mineral transportation and excavated earth was done through
Impact on quality of air covered
trucks.
d. Roads leading to project site were paved.
e. Speed of the vehicles was restricted (20
kmph) within project site.
f. Tree plantation initiated from construction
phase.
g. Proper Maintenance of construction
equipment/ machineries, etc.
2 Construction Water Water 1. Impact on human health a. Site was supplied by the fresh water from
Phase Environment Pollution & 2. Impact on nearby drinking source.
Water quality ecology/vegetation b. STP water treating the IS standards for
degradation 3. Water quality degradation at construction was used for curing and
the discharge points other construction purposes
4. Ground water/surface water c. Pits were made to store the RW during
contamination due to seepage construction and used for construction
or leeching of any hazardous d. Storage of bituminous material on the
leachate. hard paved surface so that nothing can
form leachate
e. Septic tanks with soak pits formed for the
labour camps
3 Construction Noise Noise 1. Impact on human health a. Site was enclosed with barricade along
Phase Environment Pollution 2. Impact on the project boundary.
ecology/vegetation b. PPEs were provided to labor exposed to
high intensity noise level.
c. Acoustically enclosed DG sets were used.
d. Tree plantation initiated from construction
phase.
4 Construction Soil Soil Pollution 1. Top soil degradation a. Construction yards were provided for
Phase Environment 2. Impact on vegetation storage of construction material within
3. Impact on Landuse site.
b. Top soil was stored at site and used for
landscape development.
c. Excavated soil (23,562.22 MT) was
utilized for refilling at project site.
Erosion controls have been adopted
5 Construction Ecological Ecological 1. Impact on the local Flora & a. No forest land involved & tree cutting is
Phase Environment damage or Fauna involved -NOC,s obtained
imbalance 2. Impact on the Forest land or b. No Eco-sensitive area present nearby the
any eco-sensitive area project site
involved c. Site was agricultural land and CLU was
obtained by the TCP Haryana.
6 Construction Socio Socio- 1. Health & safety a. Local 50 labours and 90Ouside labours
Phase economic economic 2. Social & physical status of provided
environment status the workers b. Hutments ,cooking facilities ,electricity,
3. Loss of habitation water ,sewerage, medical and crèche
4. Immigration/ Emigration of facilities provided
workers c. No accidents happened during
5. Loss/gain of culture and construction of the building
religion d. All the labour compliances were fulfilled
by the contractor
7 Construction Topography Natural flow 1. Change in Natural contour a. No natural water body present at the site
Phase and Natural of water b. Leveling was done to maintain the
Drainage disturbance gradient of the flow of the storm water
and the wastewater inline to the natural
slope to minimize the energy
consumption.
1 Operation Air Air Pollution 1. Dust deposition, resulting in a. Use of low sulphur diesel
phase Environment & Air quality the soiling of surfaces; b. Paved roads
degradation 2. Impact on c. Green belt with pollution abating trees
ecology/vegetation d. Use of best available technique for Air
3. Impact on human health pollution control measures.
e. Proper maintenance of DG sets.
f. A good housekeeping and proper
maintenance will be practiced which will
help in controlling pollution
g. DG sets had been kept at the appropriate
distance from the working staff beyond
the MGLC.
2 Operation Water Water 1. Land and water stream a. Sewage treatment plant installed of 150
phase Environment Pollution & contamination. KLD capacity of SAFF technology to
Water quality 2. Ground water quality meet the desired discharge standards.
degradation degradation. b. Treated water is completely reused for the
3. Use of ground water for irrigation and DG tower cooling.
domestic purposes c. Dual Plumbing had been proposed for
4. Impact on health and safety wastewater line and treated water line to
of people. minimize the fresh water requirement.
5. Impact on local ecology d. Separate storm water line has been laid to
divert all the storm water to the rainwater
harvesting pits.
e. Outlet discharges are regularly monitored
by wastewater testing by NABL
accredited laboratories.
f. Cleaning and maintenance of the STP by
dedicated cleaner to maintain the
efficiency.
6 Operation Aesthetics Natural beauty 1. Obstruction of any The project site was agricultural land and as per
phase damage important view the land acquisition. TCP Haryana had granted
2. Impact on other existing CLU for the project to get the converted
buildings agricultural land to commercial project.
3. Archeological buildings
nearby
7 Operation Socio Socio- 1. Result in change in During the operation phase almost 185. No. of
phase economic economic population the people are hired and employed on
environment status 2. existing social infrastructure permanent basis and 30 No. of people are
proposed around the project contractual hired
3. any adverse effect on the
local population and
community
8 Operation Energy Climate 1. Overall increase in carbon a. Power requirement is 1500 kVA, Backup
phase Conservation Change & footprint given by DG sets (Auto changing) are
other 2. Consumption/Exploitation 1500 kVA which will be used only in
unsustainable of the natural resources case of power failure.
conditions 3. Change in Microclimates b. Minimization of energy is done by
following:
1.> 3.177 = U value Characteristics of
the glass used in the building design to
reduce the heat transmittance.
c. Use of Renewable sources of energy is
done by installation of solar water
heaters of 6 KW capacity to minimize
the requirement of the required power.
d. Shading done for reducing the unwanted
heat gain. Energy efficient fixtures like
solar water heater, Low flow fixtures
equipments for saving the energy is done
9 Operation Waste Land, Air and 1. Impact on air, water and a. Segregation of waste is being done into
phase management water pollution land wet waste & dry waste
2. Impact on human health b. Separate designated area for waste
3. Impact on occupational collection storage and disposal
health and safety
4. Hazardous waste
management
1) Land Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Top soil degradation - - √ - - - - None
Impact of vegetation - - - √ - - - Negative
Impact on Landuse - - √ - - - - Negative
Change in Natural contour - - √ - - - - Negative
2) Water Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
√
Impact on surface water quality - - - - - - Negative
3) Air Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Impact on quality of air √ - √ - - - - Negative
Mineral transportation - - √ - - - - Negative
Dust emission - √ - - - - - Negative
Human health - - √ - - - - Negative
4) Noise Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Impact of noise - - √ - - - - Negative
Human health - - √ - - - - Negative
5) Ecological Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Impact on the local Flora &
- - - √ - - - None
Fauna
Impact on the Forest land
or any eco-sensitive area - - - √ - - - Positive
involved.
6) Socio-Economic Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Loss of habitation - - - √ - - - None
Immigration/ Emigration of
- - - - - √ - Positive
workers
Health impacts - √ - - √ - - Negative
Loss/gain of culture and
- - - - - - - None
religion
1. Land Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Top soil degradation - - - - - √ - None
Impact of vegetation - - - - - √ - Negative
Impact on Landuse - - √ - - - - Negative
Change in Natural contour - - √ - - - - None
2. Water Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Land and water stream
- - - √ - - - None
contamination
Ground water quality -
- - - √ - - Negative
degradation
Use of ground water for
- √ - - - - - Negative
domestic purposes
Impact on human health - - - √ - - - Positive
Impact on local ecology - - - - - √ - None
3. Air Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Impact on quality of air - √ - - - - - Negative
Dust emission - - √ - - - - Negative
Human health - - - √ - - - None
4. Noise Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Impact of noise - - - √ - - - Negative
Impact on Human health &
- - - √ - - - Negative
local fauna
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Impact on air, water and land - - √ - - - - Negative
Impact on human health - - √ - - - - Negative
Hazardous waste management - - √ - - - - Negative
Impact on occupational health
- - √ - - - - Negative
and safety
6. Ecological Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Impact on the local Flora &
- - - - - √ - Positive
Fauna
Impact on the Forest land or
- - - √ - - - None
any eco-sensitive area involved.
7. Socio-Economic Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Loss of habitation - - - √ - - - None
Immigration/ Emigration of
- - - - - - √ Positive
workers
Health impacts - - - - - √ - Positive
Loss/gain of culture and
- - - √ - - - None
religion
8. Other Environment
Scale of Matrix Major Moderate Minor None Minor Moderate Major Remark/
Parameters (-3) (-2) (-1) 0 (+1) (+2) (+3) Impact
Obstruction of any important
- - - - - √ - Positive
view
Impact on other existing
- - - √ - - - None
buildings
Archaeological buildings
- - - √ - - - None
nearby
Overall increase in carbon
- - √ - - - - Negative
footprint
Changes in Microclimates - - - √ - - - Negative
Damage Assessment
S. Impact on Base Scale Type of
No. Environmental Impact
Component
(Percentage (Negative /
%) Positive)
1. Land Pollution -3 Negative
2. Water Pollution 0 None
3. Air Pollution -5 Negative
4. Noise Pollution -2 Negative
5. Ecological 0 None
6. Socio-Economic 1 Positive
Damage Assessment
S. No. Impact on Environmental Base Scale Type of
Component Impact
(Percentage (Negative /
%) Positive)
1. Land Pollution 0 None
2. Water Pollution 0 None
3. Air Pollution -3 Negative
4. Noise Pollution 0 None
5. Solid Waste/Hazardous waste -4 Negative
Management
6. Ecological 2 Positive
7. Socio-Economic 5 Positive
8. Other 1 Positive
laboratories.
f. Cleaning and
maintenance
of the STP by
dedicated
cleaner to
maintain the
efficiency.
Since, no
discharge is
there to any
water course
hence no
requirement of
adopting any
measures.
g. The surplus
treated water
in the
monsoon
season will be
diverted to the
nearby
agricultural
lands for
irrigation /or
will be given
to any other
nearby
construction.
h. 6 RWH pits
had been
constructed
5 Operation Ecological Green belt Land was an 150 more trees Cost already NIL NIL
phase Environment development agricultural land are proposed for included in Air
and by planting the next five section
trees and years.
developing
greenbelt the
vegetation will be
restore the local
habitation of the
flora & Fauna.
6 Operation Aesthetics Scenic The project site Project had been NIL NIL NIL
phase views/Orientation was agricultural designed
of the project land and as per beautifully to
w.r.t local area the land increase the
acquisition. TCP aesthetic value
Haryana had of that area. The
granted CLU for project includes
the project to get state of art
7 Operation Socio Demographics of During the For maintenance NIL NIL 2nd year
phase economic the local region operation phase & Other in-
environment Existing social almost 185 No. house jobs - 1- 15000/ 360000/-
infrastructure of the people are employment of Skilled month for 2
effect on local hired and 4 more people in years
communities employed on upcoming year. 1 12000/ 288000/-
permanent basis This will semi- month for 2
and 30 No. of increase the skilled years
people are employment 3rd year
contractual hired status of the area
and improve the 2 12000/ 288000/-
socioeconomic semi- month for 1
conditions of skilled year
them. Total Wage of labour –
9,36,000/-
8 Operation Energy 1. Use of a. Power SRI paints will 1. SRI Paints 1,46,250/-
phase Conservation Renewable and requirement be done to the @ Rs 585 /Litre
non renewable is 1500 kVA, fully exposed to x 250 Litres =
energy Backup given open sky paved 1,46,250/-
2. Energy by DG sets surfaces which
savings with (Auto do not have any
different changing) are partial shading
technologies 1500 kVA to reduce the
3. Other which will be heat
sustainable used only in transmission
practices case of power load.
failure.
b. Minimization
of energy is 2. Provision 25 KW * Maintenance of solar
done by of solar panels 50,000 = panels and solar street
following: and street 12,50,000/- lighting 25,000/- for 2
1.> 3.177 = lighting i.e., years.
U value Cost of Solar
Characteristic panels and solar
street lighting
heater, Low
flow fixtures
equipments
for saving the
energy is
done
13.5 Summary
Hotel, Restaurant & Banquet Hall, Recreational Park and Health Club named as Project
“Noor Mahal” is located at Village Phusgarh, Distt.- Karnal, Haryana. It is a state of art
project equivalent to a multiple star rated facility.
The developer has erroneously carried violation of EIA notification 2006. EIA notification,
2006 and its amendments defines the built up area based on which the Environment
Clearance is to be obtained was not clear to the developer and due to the lack of knowledge
and awareness they compounded the built up area more than 20,000 sq.m.(developer
considered built-up area excluding basement)
After the inception of the mistake, they proactively took up the application to SEIAA as per
the applicable guidelines at that time related to violation projects and got the credible action
initiated against the unit.
Now, as per the current applicable guidelines related to the violation projects TOR had been
issued by SEIAA, Haryana and it is compiled with the EIA/EMP report.
The study area has been considered as per TOR conditions and the ecological damage
analysis has been through an NABL accreditated Laboratory. The same has been compiled
in the detailed EIA/EMP study carried out for the project by a QCI-NABET accreditated
consultant.
Based on the damage assessment, after considering the control parameters already
implemented, the remediation plan, Natural and community augmentation plan has been
designed for three years for the project along with its budgetary proposal thus recommended
under chapter 13 in detail.
As per the regulations SEIAA/SEAC shall approve the proposed budget and Bank
Guarantee of the same amount will be submitted to HSPCB. After successful
implementation of the remediation measures the Bank guarantee shall be redeemed by the
project Proponent.
GATE 16'-6"
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
WIDE SLOPING GREEN BELT 5'-0" WIDE BOUNDARY WALL 4'-9" HIGH
RAIN
PARAPET WALL
3'-6" HIGH WATER PIT
Lvl. -0'-4" SCOOTER
19'-8"
SERVICE ROAD 20'-0" WIDE
PARAPET WALL 3'-6" HIGH
PARKING
DN Lvl. +3'-6"
ZONING LINE ZONING LINE Lvl. +3'-0"
Lvl. +3'-6"
DN
1 DRAIN 6" WIDE
W = 3'-0"
T = 1'-1"
SUNKEN
R = 0'-6" SHOWER
AREA
5
CHANGING l.-3
'-0"
Lvl.+2'-9"
Lv DN
SERVICE RAMP
ROOM Lvl.-3'-0"
SWIMMING POOL Lvl.-2'-0"
Lvl.-6'-10 12" LVL.-21'-0" PARAPET WALL 3'-6" HIGH 20'-4" WIDE ELECTRIC
ELECTRICSUBSTATION
SUBSTATION
DRAIN 6" WIDE
(SLOPE 1:9) COOLING
1 15 30
TOWERS
WATCH AND X
POOL
BAR
Lvl.-4'-6" Lvl.-4'-6" Lvl.-4'-6" Lvl.-3'-0" KIDS
B
W = 5'-7"
T = 1'-0" UP CONC.COL.
1'-0"x1'-0"x2'-6"
SUNKEN SERVICE AREA R = 0'-5.65"
PARAPET WALL
POOL
LVL.-21'-0"
-0"
3'-6" HIGH
WARD STAFF
L.-3
PARAPET WALL
LV
3'-6" HIGH
Lvl.-2'-0"
EA
2'-10 12" C/C
LVL. -21'-0" PARAPET WALL
E AR
3'-0" HIGH
IC
BLOCK 9" TH. WALLAS
PER DESIGN
V
SE
R
IDE
4'-0"W
LEGEND
CREEPERS TO MATCH CREEPERS TO MATCH
B. WALL HEIGHT B. WALL HEIGHT
SUNKEN
SHOWER
AREA
RAIN
WATER PIT
BELOW
DRAIN 6" WIDE
SEWERAGE
COLLECTION TANK
Lvl.-6'-10 12"
LAWN-A WITH PUMP
RM.35000 Lt.cap.
ZONING LINE
GREEN AREA
D1
HOTEL
Lvl. +3'-0" BOUNDARY
Lvl.-6'-10 12 " RAMP
HOTEL UP
13'-6" WIDE
W = 10'-0"
BOUNDARY T = 1'-0"
Lvl. +3'-6"
13 1 R = 0'-5.89"
BUILDING
Lvl. +3'-6"
ZONING LINE
SERVICES
RESTAURANT
T = 1'-0"
HOTEL BUILDING
PROJECTION 2'-0" WIDE
Lvl. +59'-2"
Lvl.-6'-1012"
LAWN-B PARKING AREA
170'-112" X 145'-5"
SERVICE ROAD 15'-4" WIDE
Lvl.-6'-112"
WATER PIT
ZONING LINE
UG WATER TANK
PROJECTION 5'-3" WIDE
PLANTERS
Lvl.-6'-1012" PROJECT :-
HOTEL
BOUNDARY
MUMPTY
MUMPTY VISITOR
PROPOSED HOTEL NOOR MAHAL
VISITOR
TOILET 27
Lvl. +59'-2"
27
TOILET AT KARNAL
PA
Lvl. +2'-0"
SS
14 14
TITLE :-
AG
Lvl. +3'-6"
Lvl.-6'-10 12" Lvl.-6'-10 12"
E1
5"4"
6-6
Lvl. +8'-6 12 " STONE JALLI 3'-6" (9"x9") 3'-6" HIGH (9"x9") 3'-6" HIGH
Lvl.-3'-6" HIGH AS PER DETAIL
HIGH AS PER DETAIL
SITE PLAN
IDE
4"5"
Lvl. +6'-0 12 " Lvl. +6'-0 12 "
ROAD 16-6" WIDE
PATHWAY 3'-3" WIDE Lvl. +2'-9" PATHWAY 3'-3" WIDE Lvl. +2'-9"
SS
DN
RAMP 7'- 12 "
AG
GREEN BELT 5'-0" WIDE Lvl. +4'-8" UP PROJECTION 10'-0" WIDE Lvl. +4'-8" GREEN BELT 5'-0" WIDE
"W
UP
IDE
Planter
Lvl. +1'-6" Lvl. +2'-0" Lvl. +1'-6" Lvl. +2'-0"
TEMPORARY
Lvl. +1'-9" Lvl. +1'-9" METER
ROOM
METER
ROOM
SERVICE GATE SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6"
16'-9 12 " WIDE
ROAD 16'-6" WIDE IN OUT SERVICE GATE
16'-9 12 " WIDE
GATE 30'-0" WIDE GATE 30'-0" WIDE
GREEN BELT GREEN BELT
GREEN BELT
ENTRY/EXIT ENTRY/EXIT
SLOPE=1:150
SLOPE=1:300 SLOPE=1:150
SLOPE=1:300 SLOPE=1:300 SLOPE=1:150 SLOPE=1:150 SLOPE=1:150 SLOPE=1:150
SLOPE=1:300 SLOPE=1:300 SLOPE=1:150
SLOPE=1:300 SLOPE=1:150
L=15MTRS L=28MTRS L=15MTRS L=22.5MTRS L=22.5MTRS L=15MTRS L=15MTRS L=15MTRS L=15MTRS L=22.5MTRS L=22.5MTRS L=15MTRS L=30MTRS L=15MTRS
GATE 16'-6"
WIDE SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" BOUNDARY WALL 4'-9" HIGH
E
L=22MTRS VALVE CHAMBER
0" WID
LVL.-20'-9"
DMH-A5 POOL
2'- 6"
PARAPET WALL PARAPET WALL
1 15
GL=-2050
30
l. + 16'-
W = 6'-4"
3'-7" HIGH 3'-7" HIGH UP
T = 1'-0"
IL=-2500
GL=+600 R = 0'-5.45"
Lv AD
DMH
SUNKEN SERVICE AREA
O
SMH SMH
DMH
R
IL=-590 LVL. -20'-9" PARAPET WALL
E
VIC
3'-7" HIGH
DMH-B5
EFH
EFH
R
STP
SE
SUNKEN SERVICE AREA
REFER DETAIL'A' LVL. -20'-9" SLOPE=1:150 GL=+600
SLOPE=1:200 L=25MTRS IL=(-4550)
Lvl.-6'-1012" IL=-600
Lvl. -2'-1012
DRWG. NO. PL-HWS-01 L=13MTRS
SMH-14
DMH-A10
Lvl. +3'-6"
IL=-2100
SLOPING GREEN BELT 5'-0" WIDE
SMH
SMH-12 SLOPE=1:300
GL=-1650 GL=-1650 GL=-1650 GL=(-2050) L=24.5MTRS
IL=-2325 IL=-2250 IL=-2175
SLOPE=1:200 SLOPE=1:200 SLOPE=1:200
EFH
EFH
L=30MTRS
SMH-2 SLOPE=1:200
IL=(-4050)
DMH-A11 IL=(-3040)
GL=+600 SLOPE=1:150 SLOPE=1:200 SMH SLOPE=1:150
L=20.5MTRS L=15MTRS L=15MTRS
HOTEL BUILDING
IL=(-365)
GREEN BELT 3'-0" WIDE
Lvl. +59'-0"
DMH-A7 SLOPE=1:200 GL=-2050
DMH GL=-1650 L=14MTRS IL=-2715 SLOPE=1:300
GL=+600 IL=-2475 Lvl.-6'-1012" GL=-1650 L=24.5MTRS
IL=-740 2WAY FIRE BRIGADE IL=-2250
DMH LAWN INLET CONN.
Lvl. +2'-0"
4 WAY FIRE BRIGADE IL=-2640
LAWN
DRAW OFF CONN.
SLOPE=1:150
SLOPE=1:150 L=16MTRS
SMH-4 SLOPE=1:300
L=7.5MTRS SMH-9 L=26MTRS
EFH
EFH
GL=(-2050) SLOPE=1:200
GL=(-2050) ZONING LINE L=15MTRS
SLOPE=1:200 MUMPTY
L=15MTRS IL=(-3250) SMH
DRAINAGE SUMP
GL=-2050 IL=(-3815)
SLOPE=1:150 Lvl.-6'-1012" SIZE=2.5x2.5X2.5
L=15MTRS DRAINAGE SUMP IL=-2740 SMH
DMH-A12 L=15MTRS IL=-2925 L=15MTRS IL=-2850 L=11.5MTRS L=19MTRS SLOPE=1:150 GL=-1650 L=17.5MTRS GL=-1650 L=17.5MTRS IL=-3100 L=17.5MTRS
ING
L=8MTRS
EE
GREEN BELT 3'-0" WIDE PROJECTION 5'-3" WIDE GREEN BELT 3'-0" WIDE
EL
IL=-840 14
Lvl. +3'-6"
Lvl.-6'-1012"SMH
T5
DMH DMH
SMH Lvl.-6'-1012" SMH PROJECTION 5'-3" WIDE SMH
'-0
"W
Lvl.-6'-1012" SMH-5 SMH-6 SMH-7 SMH-8 L=17.5MTRS L=17.5MTRS L=17.5MTRS L=17.5MTRS DMH-B8
Lvl
1
GL=(-2050) GL=(-2050)
DN DN
GL=+600
3'-
GL=+600 DRAW OFF CONN. CLU OBTAINED AREA = 3.00 ACRE GL=+600 GL=+600 GL=+600
CL=(-500) IL=-300 IL=-375 IL=-475
DMH IL=(-392)
DMH DMH-B9
DMH DMH DMH DMH DMH GL=+600
Lvl. +3'-6" SLOPE=1:400 IL=-900
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" L=17MTRS
SERVICE GATE SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
16'-6" WIDE IN OUT SERVICE GATE
16'-6" WIDE
1.300
CP 1:4
F.S.L.
.340
.450
HOLE FOR RAIN WATER HARVESTING SYSTEM
8.250
.120 7.050
.030 .110.340
1.500
C.C. 1:5:10
.600
GRAVEL 10-20 MM(0.50M)
GRAVEL 5-10 MM SIZE(0.50M)
COURSE 1.5-2.0 MM SIZE(0.50M)SAND
100M
8.250
7.050
PVC SLOTTED PIPE
.120
SPRING SPRING PLAN
WATER WATER
SECTION A-B
CONSULTANTS
TITLE:-
A.P.ASSOCIATES INC.
PROPOSED HOTEL RANGEELO SCALE:-N.T.S. DATE:- INT.,ARCH. & SPACE PLANNING
JEWELS AT KARNAL SCO.196,SECOND FLOOR
DRG.NO:- DEALT BY:- SEC-16,PANCHKULA.
PH.3201046
NOTES :-
SLOPE=1:150 Lvl.+2'-9"
L=15MTRS ELECTRIC SUBSTATION
CHANGING Lvl
.-3'
-0"
SERVICE RAMP
DN
Lvl.-2'-0"
ROOM SWIMMING POOL
Lvl.-6'-10 12 " LVL.-21'-0" PARAPET WALL 3'-6" HIGH 20'-4" WIDE GL=-1650 SLOPE=1:200 GL=-1650 SLOPE=1:200 GL=-1650
Lvl.-3'-0" SLOPE=1:80 L=14MTRS L=14MTRS
(SLOPE 1:9)
L=22MTRS IL=-2240 IL=-2170 IL=-2100
GL=-2050
WATCH AND X
POOL
BAR
Lvl.-4'-6" Lvl.-4'-6" Lvl.-4'-6" Lvl.-3'-0" KIDS
B
W = 5'-7"
T = 1'-0" UP
1 15 30
IL=-2500
DMH
WARD STAFF POOL
LVL.-21'-0" SUNKEN SERVICE AREA R = 0'-5.65"
3- 0"
L.-
DMH
LV
Lvl.-2'-0"
EA
2'-10 21" C/C
LVL. -21'-0" PARAPET WALL
AR
BLOCK E 3'-0" HIGH
C
VI
9" TH. WALLAS ER
ES
PER DESIGN ID W
4'-0 "
Lvl. +3'-6"
13 1 R = 0'-5.89"
IL=-2100
GL=-1650 GL=-1650 GL=-1650
IL=-2325 IL=-2250 IL=-2175
Lvl. +3'-6"
ZONING LINE
SLOPE=1:150
SLOPE=1:200 SLOPE=1:150
RESTAURANT L=15MTRS
GL=-2050
L=15MTRS
SLOPE=1:150
L=15MTRS
HOTEL BUILDING
PROJECTION 2'-0" WIDE
Lvl. +59'-2"
SLOPE=1:200 GL=-2050
DMH GL=-1650 L=14MTRS IL=-2715
IL=-2475
DMH
SERVICE ROAD 15'-4" WIDE
GL=-2050
IL=-2640
LEGEND
RAJA BAGH LAWN PROJECTION 5'-3" WIDE
SLOPE=1:150
L=15MTRS GL=-1650
IL=-2550
L=20MTRS
GL=-1650
IL=-2325
STP LOCATION
PLANTERS
HOTEL
BOUNDARY
MUMPTY
SLOPE=1:200
L=15MTRS
STORM WATER LINE
SLOPE=1:200
L=15MTRS DRAINAGE SUMP
GL=-2050 SIZE=2.5x2.5X2.5
SLOPE=1:150 IL=-2740
L=15MTRS DRAINAGE SUMP
SLOPE=1:200 MUMPTY VISITOR
GL=-1650
SLOPE=1:150
SIZE=2.5x2.5X2.5
GL=-1650
VISITOR L=22MTRS Lvl. +59'-2" GL=-2050
IL=-2840
SLOPE=1:200
IL=-3190
TOILET
CL=-2400
DMH STORM WATER MANHOLE
L=15MTRS IL=-3000TOILET
27 27
DMH
Lvl. +2'-0"
SS
14 14
AG
Lvl. +3'-6"
GREEN BELT 3'-0" WIDE
DMH
Lvl.-6'-10 12" Lvl.-6'-10 12 "
DMH
E 16
1 1
SLOPE=1:150 SLOPE=1:150
:-
R = 0'-4" R = 0'-4"
AT KARNAL
Lvl. +5'-6 " Lvl. +5'-6 "
PA
DN
RAMP 7'- 12"
AG
UP
RAMP 30'-0" WIDE RAMP 30'-0" WIDE
E
TITLE :-
84
STONE KERB SLOPED PARKING L=15MTRS
STONE
AREA
SLOPE=1:150
L=15MTRS WATERBODY
PARKING
Lvl. +2'-2 12" Lvl. +2'-2 12" PARKING DMH
DMH
Planter
Lvl. +1'-6" Lvl. +2'-0" Lvl. +1'-6" Lvl. +2'-0" Lvl. +1'-6"
TEMPORARY
Lvl. +1'-9" Lvl. +1'-9" METER
ROOM
METER
ROOM
SERVICE GATE SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6"
ROAD 16'-6" WIDE IN OUT SERVICE GATE
16'-921" WIDE
GREEN BELT
GATE 30'-0" WIDE
SLOPE=1:150 SLOPE=1:150
GATE 30'-0" WIDE
SLOPE=1:150 SLOPE=1:150 SLOPE=1:150
GREEN BELT
16'-9 12" WIDE
DRG. NO :- REV. :- SCALE :-
GREEN BELT
L=15MTRS L=15MTRS L=8MTRS L=15MTRS L=8MTRS
ENTRY/EXIT ENTRY/EXIT
FOUNDATIONS
ARCHITECTS, INTERIOR DESIGNERS,
& DESIGN CONSULTANTS
W-143, G.K.-1, NEW DELHI-48
E mail - [email protected]
* This drawing is the property of M/S FOUNDATIONS and it should not be altered,
SLOPING GREEN
BELT 5'-0" WIDE
802.
800.6
80 3
801.
80
801.
2.3
0.
800.4
00
0
00
9
80
0
101.02
101.02
801.
9
MAXIMUM CONTOUR
LAVEL:- 800.50M
802.
00
801.
98.50
5
800.9
801.
98.50
00
800.50
800
802.
30
800.6
800.4
800.3
98.10
700
98.10
LEG
800.5
0
PROJ
MINIMUM CONTOUR
LAVEL:- 50.99M
TITLE
800
DRG. N
DLT BY
802.
800
800.50
800.6
800.4
30
800.3
800.9
801.
00
801.
802.
* This draw
9
00
SLOPING GREEN
BELT 5'-0" WIDE
copied,or u
* Dimension
* The contra
SITE PHOTOGRAPHS
BYE PASS 60 MT. WIDE
GATE 16'-6"
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
WIDE SLOPING GREEN BELT 5'-0" WIDE BOUNDARY WALL 4'-9" HIGH
RAIN
PARAPET WALL
3'-6" HIGH WATER PIT
Lvl. -0'-4" SCOOTER SERVICE ROAD 20'-0" WIDE
PARAPET WALL 3'-6" HIGH
PARKING
DN
Lvl. +3'-6"
ZONING LINE ZONING LINE Lvl. +3'-0"
Lvl. +3'-6"
DN
1 DRAIN 6" WIDE
W = 3'-0"
T = 1'-1"
SUNKEN
R = 0'-6" SHOWER
AREA
5
SERVICE RAMP
DN
ROOM Lvl.-3'-0"
SWIMMING POOL Lvl.-2'-0"
Lvl.-6'-10 12" LVL.-21'-0" PARAPET WALL 3'-6" HIGH 20'-4" WIDE
DRAIN 6" WIDE
(SLOPE 1:9) COOLING
TOWERS
WATCH AND X
POOL
BAR
Lvl.-4'-6" Lvl.-4'-6" Lvl.-4'-6" Lvl.-3'-0" KIDS
B
W = 5'-7"
T = 1'-0" UP
1 15 30
CONC.COL.
1'-0"x1'-0"x2'-6"
0"
.-3-
SMH SMH
VL
PARAPET WALL
3'-6" HIGH
AL
Lvl.-2'-0"
2'-10 21" C/C
LVL. -21'-0" PARAPET WALL
RE
BLOCK
EA
C 3'-0" HIGH
VI
9" TH. WALLAS ER
ES
PER DESIGN ID
4'-0"W
UNDER DECK
D.G SET ROOM
WIRE FENCING WITH
CREEPERS TO MATCH
WIRE FENCING WITH
CREEPERS TO MATCH
BAR STORE
3'-0"x4'-0"x2'-0"
SLOPE=1:150
B. WALL HEIGHT B. WALL HEIGHT
SUNKEN
SHOWER
AREA
BELOW L=25MTRS
DRAIN 6" WIDE
SEWERAGE
LAWN-A Lvl.-6'-1012"
COLLECTION TANK
Lvl. +3'-6"
13 1 R = 0'-5.89"
SMH
SMH-12
GL=(-2050)
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
IL=(-4150)
Lvl.-6'-1012"
SMH
W = 7'-0"
GL=(-2050)
IL=(-3040)
SLOPE=1:150
UNDERGROUND WATER
LEG
Lvl. +59'-2"
Lvl.-6'-1012"
SERVICE ROAD 15'-4" WIDE
IL=(-3920) SLOPE=1:150
SMH-3
R = 0'-5.11"
ZONING LINE
L=30MTRS
GL=(-2050) PROJECTION 5'-3" WIDE
IL=(-3200) SMH
SLOPE=1:150
PLANTERS
IL=(-3815)
SMH
MUMPTY VISITOR
VISITOR Lvl. +59'-2"
TOILET
SMH
TOILET 27 27
SLOPE=1:150 SLOPE=1:150
69 70 71 72 73
L=11.5MTRS L=19MTRS SLOPE=1:150
L=9.5MTRS
WIRE FENCING WITH
CREEPERS TO MATCH SLOPE=1:150 SLOPE=1:150
B. WALL HEIGHT
L=24MTRS L=30MTRS
PA
Lvl. +2'-0"
S
SA
14 14
Lvl. +3'-6"
GREEN BELT 5'-0" WIDE GREENGREEN
BELT 5'-0"
BELT WIDE
3'-0" WIDE
Lvl.-6'-10 12"
GE
1
PROJECTION 5'-3" WIDE SMH Lvl.-6'-10
SMH
2" PROJECTION 5'-3" WIDE
Lvl.-6'-10 12"
SMH SMH
Lvl.-6'-10 12" Lvl. +2'-6"
16-
PROJE
WI
:-
R = 0'-4" R = 0'-4"
Lvl. +6'-9 12 " IL=(-3325) IL=(-3485) PORCH IL=(-3625) IL=(-3750) Lvl. +6'-9 12"
GREEN BELT 3'-0" WIDE 39'-0" x 39'-0"
Lvl. +8'-2" Lvl.+14'-4" Lvl.+14'-4" Lvl. +8'-2"
PARKING Lvl. +7'-3 12 "
Lvl.+ 45'-6 12'' Lvl. +7'-3 12 "
PARKING
Lvl. +6'-5" Lvl. +6'-5"
STONE LAMP STONE LAMP Lvl. +7'-9 12 "
STONE JALLI 3'-6" (9"x9") 3'-6" HIGH (9"x9") 3'-6" HIGH STONE JALLI 3'-6"
Lvl. +5'-11" Lvl. +6'-11" HIGH AS PER DETAIL Lvl. +6'-11" Lvl. +5'-11"
HIGH AS PER DETAIL
ROAD 16-6" WIDE
SLOPE=1:150
27
72 Lvl. +5'-2" Lvl. +5'-2"
70 71 73 74 75 76 77 78 79 80
PATHWAY 3'-3" WIDE Lvl. +2'-9" PATHWAY 3'-3" WIDE Lvl. +2'-9"
SS
DN
RAMP 7'- 12" L=30MTRS
AG
PLANTER
Lvl. +2'-412" PLANTER
WIDE
E1
GREEN BELT 5'-0" WIDE PROJECTION 10'-0" WIDE GREEN BELT 5'-0" WIDE
"
WI
UP
DE
TITLE
84
STONE KERB SLOPED PARKING
STONE
AREA
WATERBODY
PARKING
Lvl. +2'-212" Lvl. +2'-212" PARKING SMH
SECURITY ROOM
16'-9" x 11'-8"
DU
93 94 95 96 97 98 Lvl.+ 12'-3'' 42 43 44 45 46 47 48 49 50
50 51 52 53 54
Planter
Lvl. +1'-6" Lvl. +2'-0" Lvl. +1'-6" Lvl. +2'-0" Lvl. +1'-6"
TEMPORARY
Lvl. +1'-9" Lvl. +1'-9" METER
ROOM
METER
ROOM
SERVICE GATE SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6"
ROAD 16'-6" WIDE IN OUT SERVICE GATE
16'-9 12" WIDE
GREEN BELT
GATE 30'-0" WIDE GATE 30'-0" WIDE
16'-9 12" WIDE
DRG. N
GREEN BELT GREEN BELT
ENTRY/EXIT ENTRY/EXIT
DLT BY
WIND ROSE PLOT: DISPLAY:
NORTH
30%
24%
18%
12%
6%
WEST EAST
WIND SPEED
(Knots)
>= 22
SOUTH
17 - 21
11 - 17
7 - 11
4-7
1-4
Calms: 17.71%
GATE 16'-6"
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
WIDE SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" BOUNDARY WALL 4'-9" HIGH
PARAPET WALL
3'-6" HIGH
Lvl. -0'-4" SCOOTER
PARKING Lvl. +3'-6"
PARAPET WALL 3'-6" HIGH DN
ZONING LINE ZONING LINE Lvl. +3'-0"
Lvl. +3'-6"
DN
1 DRAIN 6" WIDE
W = 3'-0"
T = 1'-1"
SUNKEN
R = 0'-6" SHOWER
AREA
5
CHANGING .- 3'-0
" Lvl.+2'-9"
Lvl DN
SERVICE RAMP
ROOM Lvl.-3'-0"
SWIMMING POOL Lvl.-2'-0"
Lvl.-6'-1012" LVL.-21'-0" PARAPET WALL 3'-6" HIGH 20'-4" WIDE ELECTRIC
ELECTRICSUBSTATION
SUBSTATION
DRAIN 6" WIDE
(SLOPE 1:9) COOLING
1 15 30
TOWERS
WATCH AND X
POOL
BAR
Lvl.-4'-6" Lvl.-4'-6" Lvl.-4'-6" Lvl.-3'-0" KIDS
B
W = 5'-7"
T = 1'-0"
R = 0'-5.65"
UP CONC.COL.
1'-0"x1'-0"x2'-6"
LVL.-21'-0" SUNKEN SERVICE AREA
PARAPET WALL
POOL
.-3-0"
3'-6" HIGH
WARD STAFF
VL
PARAPET WALL
3'-6" HIGH
AL
Lvl.-2'-0"
2'-10 12" C/C
LVL. -21'-0" PARAPET WALL
RE
EA
3'-0" HIGH
IC
BLOCK 9" TH. WALLAS
PER DESIGN
RV
SE
DE
4'-0"W
I
SEWERAGE
COLLECTION TANK
D1
ZONING LINE HOTEL
Lvl. +3'-0" BOUNDARY
Lvl.-6'-10 12" RAMP
HOTEL UP
13'-6" WIDE
W = 10'-0"
BOUNDARY T = 1'-0"
Lvl. +3'-6"
13 1 R = 0'-5.89"
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
RESTAURANT
PLANTERS
T = 1'-0"
R = 0'-5.11"
Lvl.-6'-1012"
LAWN-B
170'-112" X 145'-5"
92'-4" X 192'-2"
ZONING LINE
Lvl.-6'-1012"
HOTEL
BOUNDARY
MUMPTY
MUMPTY VISITOR
VISITOR Lvl. +59'-2" TOILET
TOILET 27 27
PA
Lvl. +2'-0"
SS
14 14
AG
5"4"
5"4"
STAGE
6-6
4"5"
4"5"
Lvl. +6'-0 12 " Lvl. +6'-0 12 "
PATHWAY 3'-3" WIDE Lvl. +2'-9" PATHWAY 3'-3" WIDE Lvl. +2'-9"
SS
DN
RAMP 7'- 12"
AG
PLANTER
Lvl. +2'-4 12" PLANTER
WIDE
E 16-
GREEN BELT 5'-0" WIDE Lvl. +4'-8" UP PROJECTION 10'-0" WIDE Lvl. +4'-8" GREEN BELT 5'-0" WIDE
6"
WI
UP
DE
SECURITY ROOM
16'-9" x 11'-8"
Lvl.+ 12'-3''
Planter
Lvl. +1'-6" Lvl. +2'-0" Lvl. +1'-6" Lvl. +2'-0"
TEMPORARY
Lvl. +1'-9" Lvl. +1'-9" METER
ROOM
METER
ROOM
SERVICE GATE SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" Lvl. +3'-6"
16'-9 12" WIDE
ROAD 16'-6" WIDE IN OUT SLOPING GREEN BELT 3'-0" WIDE SERVICE GATE
16'-9 12" WIDE
GATE 30'-0" WIDE GATE 30'-0" WIDE
GREEN BELT GREEN BELT
GREEN BELT
ENTRY/EXIT ENTRY/EXIT
0.91 HIGH
PROPOSED BUILDING PLAN OF HOTEL,
PARAPET
RESTAURANT , BANQUET HALL , ON THE
LAND FALLING IN RECT/KILL NO 6//9
MIN,10 MIN, 11,12 IN THE REVENUE
ESTATE OF VILLAGE PHUSGARH
RAMP IN & OUT MEASURING 12140.46 SQ. MTRS. M/S
RAMP 8.00 WIDE
(SLOPE 1:10) JEWEL CLASSIC HOTELS PVT. LTD.
VILLAGE PHUSGARH, SECTOR-32, DISTT.
KARNAL
KHURRA
COVERED AREA OF BASEMENT FLOOR
SERVICE AREA
22.46 x 4.66 =(66.06 x 62.17) + 2x (1.98 x19.65)
+ 2x (1.98 x 15.77 ) +4 x (4.17 + 7.38)*
SUNKEN SERVICE AREA
46.40x 11.13
Lvl - 6.23
= 4106.95 + 77.81+ 62.44 + 46.20
R.W.HODI
= 4293.40 Sq.m
UP
1 14 24
ARCH ITECTURAL W = 1.00 m
FEATURE 0.60 WIDE T = 0.30 m
R = 0.15 m
PARKING AREA DETAIL IN BASEMENT
R.W.HODI LVL. -2.28
= AREA OF BASEMENT - (G+H+I+J)
R.W.HODI
SERVICE IC
=4293.40 -{[(7.87x 7.88)+(7.38+4.17)]+
EXIT W10 W10 ENTRY
6" W/S W10/PV C-2
(11.27x9.37)+(9.77x8.11)+(4.11x5.34)]}
C-2 C-2 C-2 C-2 C-2
IC
C-2 R/S DW2
F.T F.T
SUMP WITH C-2 = 4293.39 - [62.01+11.55 + 105.59 + 79.23 +
KHURRA
W10 ENTRY W10
W10
6" RWP
KHURRA
W10
15.33 x 1.98 48
FIRE
2.13 HIGH
PARTITION
WALL D1
6" S/S
KHURRA MOTOR
FROM SUMP 21.94]
W10 W10
C-2
C-2 C-2 C-2 C-2 C-2 C-2 EXTINGUISHERS
D1
C-2 6" RWP C-2 C-2 C-2
= 4293.40 - 280.32
ELECTRIC SUBSTATION &
G R/S
30 31
L. TOILET
3.65 x 4.89 F.T
C-2 C-2
= 4013.08 Sq.m
14 16 49
GENERATOR ROOM Lvl - 5.77
F.T
D2 J AREA FOR PARKING PER CAR IN
C-2 C-2
C-1 C-4
C-2 BASEMENT = 35.00 Sq.m
29 32 50 FIRE
EXTINGUISHERS
C-4
52 53 54 55 57 58 THEREFORE TOTAL NO. OF
51 56
CAR PARKING IN BASEMENT
1 29 = 4013.08 / 35 = 115 P.C.U
UP
W = 1.83 m 28
33
T = 0.29 m D4
R = 0.13 m C-2
D4
C-4
9 *NOTES :-
SHAFT
C-2
C-1 C-4 C-4
1.86 x 1.51 (1) AREA OF SHAFTS IS 2.80 Sq.m, WITH MIN.
WIDTH OF 1.25 MT.
27 34
FIRE (2) THIS BUILDING IS CENTRALY
EXTINGUISHERS
1 AIRCONDITIONED , MECHANICALY
C-2
VENTILATED AND HAS 100% STANDBY
C-2 C-2 C-2
C-1 PARKING GENERATORS
26 Lvl - 6.08
C-1 C-2
C-2
35 C-2 C-2
(3) SPRINKLER SYSTEM PROVIDED IN
LIFT LIFT LIFT BUILDING AS PER NBC
2.95x 2.20 2.95x 2.20 2.95x 2.20
(4) ALL FLOOR TRAPS SHALL DISPOSE
2 64 63 W = 2.45 m
THROUGH 150 MM WASTE STACK PIPE
25 65 62 D4 61
T = 0.27 m D4 59
36 ALL DISPOSAL OF ENGLISH W.C SHALL BE
11
SERVICE CORE
R = 0.13 m UP 60
(5) THROUGH 150MM SOIL STACK PIPES
C-1 SHAFT C-1
1.51 x 1.86 C-4 28 9.31 x 5.22 1
Lvl - 6.08
C-2
C-4
66
I C-2 (6) ALL DOWN PIPES OF W.C SHALL BE
THROUGH 1 2" I/D FROM WATER TANK
24 23 15 6 INSTALLED ON TERRACE
3
37
(7) AL DISPOSAL OF RAIN WATER THROUGH
67 C-2 HODIS WITH 200MM RCC PIPE TO BE
C-1
CONNECTED WITH RAIN WATER
23 C-2 C-2 C-2
C-2
C-2
HARVESTING WELL
C-2 38 C-2
C-1
FIRE
4 69 EXTINGUISHERS
68 71 73 74 75
70 72 76
22 39
C-1
C-1
C-2 C-4 C-2
21 40
5 FIRE
EXTINGUISHERS
6
19 41
C-1 C-1
77 C-2
C-2 32 C-2
43 SHAFT
1.51 x 1.86
C-1 C-4
8
44
17 C-2
C-2 PARKING
Lvl - 6.08
C-4
C-1
FIRE
9
EXTINGUISHERS
C-2
88 91
16 45 89 90 92 93 94 95 96
10
C-2
14 47 C-2
C-2
C-1
C-3 C-1 C-1 C-1 C-2 C-2 C-2 C-2 C-2
C-1
SHAFT
C-2 SIGNATURE OF ARCHITECT
SHAFT 2.25 x 1.25
1.51 x 1.86 37
C-2 C-3
21 24 9
LIFT
2.61 x 2.45
LIFT
FIRE
EXTINGUISHERS
BASEMENT PLAN
2.61 x 2.45
12 13
32 1
C-2 ( LVL. -6.08)
C-3 UP C-3 107 C-3 C-3 110 111 C-3 112 C-3 113 C-3 114 C-3 C-3
C-2 C-3 106 C-3 108 109 C-3 C-3 115 116
H LIFT LOBBY W = 2.45 m
T = 0.36 m
Lvl - 6.08
R = 0.11 m D4 DATE :- DRWNG. NO. :-
FIRE Lvl - 6.08
EXTINGUISHERS
C-2 C-2
C-2
C-2 C-2 C-2 C-2 C-2 C-2 C-2 C-2 C-2 C-2 C-2 C-2 C-2 C-2
C-2
FIRE
EXTINGUISHERS
C-2 C-2
GATE 16'-6"
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
WIDE SLOPING GREEN BELT 5'-0" WIDE BOUNDARY WALL 4'-9" HIGH
PARAPET WALL
3'-6" HIGH
Lvl. -0'-4" SCOOTER SERVICE ROAD 20'-0" WIDE
PARAPET WALL 3'-6" HIGH
PARKING
DN Lvl. +3'-6"
ZONING LINE ZONING LINE Lvl. +3'-0"
Lvl. +3'-6"
EFH EFH DN
1 DRAIN 6" WIDE
W = 3'-0"
T = 1'-1"
SUNKEN
R = 0'-6" SHOWER
AREA
5
SERVICE RAMP
DN
Lvl.-6'-1012"
Lvl.-2'-0"
ROOM Lvl.-3'-0"
SWIMMING POOL LVL.-21'-0" PARAPET WALL 3'-6" HIGH 20'-4" WIDE
(SLOPE 1:9)
DRAIN 6" WIDE
LVL.-21'-0"
-0"
L .-3
PARAPET WALL
V
3'-6" HIGH
AL
Lvl.-2'-0"
2'-10 12" C/C
LVL. -21'-0" PARAPET WALL
RE
BLOCK
A
3'-0" HIGH
CE
VI
9" TH. WALLAS
EFH
EFH
ER
PER DESIGN ES
WI D
4'-0"
LAWN-A Lvl.-6'-1012"
D1
ZONING LINE
Lvl. +3'-0" EFH EFH
Lvl.-6'-10 12" RAMP
HOTEL UP
13'-6" WIDE
W = 10'-0"
BOUNDARY T = 1'-0"
Lvl. +3'-6"
13 1 R = 0'-5.89"
SLOPING GREEN BELT 5'-0" WIDE Lvl. +3'-6"
EFH
RESTAURANT
PLANTERS
EFH
EFH
CREEPERS TO MATCH
B. WALL HEIGHT
HOTEL BUILDING
EFH
EFH
MUMPTY ZONING LINE
MUMPTY VISITOR
VISITOR Lvl. +59'-2" TOILET
TOILET 27 27
Lvl. +2'-0"
SS
14 14
AG
Lvl. +3'-6"
EFH EFH EFH GREEN BELT 3'-0" WIDE
Lvl.-6'-1012" Lvl.-6'-1012"
E1
EFH EFH
Lvl. +5'-6 12" Lvl. +5'-6 12"
PA
69 70 71 72 73 74 75 76 77 78 79 80
Lvl. +5'-2" Lvl. +5'-2" 16 17 18 19 20 21 22 23 24 25 26 27
PATHWAY 3'-3" WIDE Lvl. +2'-9" PATHWAY 3'-3" WIDE Lvl. +2'-9"
SS
DN
RAMP 7'- 21"
AG
PLANTER
Lvl. +2'-4 12" PLANTER
WIDE
E 16-
GREEN BELT 5'-0" WIDE Lvl. +4'-8" UP PROJECTION 10'-0" WIDE Lvl. +4'-8" GREEN BELT 5'-0" WIDE
6"
WI
UP
DE
SECURITY ROOM
16'-9" x 11'-8"
93 94 95 96 97 98 Lvl.+ 12'-3'' 42 43 44 45 46 47 48 49 50
50 51 52 53 54
Planter
Lvl. +1'-6" Lvl. +2'-0" Lvl. +1'-6" Lvl. +2'-0" Lvl. +1'-6"
TEMPORARY
Lvl. +1'-9" Lvl. +1'-9" METER
ROOM
METER
ROOM
SERVICE GATE SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6" SLOPING GREEN BELT 3'-0" WIDE Lvl. +3'-6"
16'-9 12" WIDE
ROAD 16'-6" WIDE IN OUT SERVICE GATE
16'-9 12" WIDE
GATE 30'-0" WIDE GATE 30'-0" WIDE
GREEN BELT GREEN BELT
GREEN BELT
ENTRY/EXIT ENTRY/EXIT