1. What is planning?
2. Nature of Planning
3. Procurement Planning
3.1 Importance of Planning
3.2 Preparing the PPMP
3.3 Preparing the APP
Government Procurement Policy Board – Technical Support Office 2
Assess Review studies Post/Advertise Procure
Consolidate into APP opportunity
Decide procurement Open and evaluate
method bids
Approve APP Post-qualify
Determine readiness Award and enter into
contract
Identify Cost-benefit analysis Oversee Implement
Feasibility study implementation
Market study Inspect and accept
PPMP deliveries
Release payment
refers to predetermined course/s
of action to achieve a desired
end/goal.
“Process of identifying which
project needs can be best met by
procuring products and services
outside the project organization
and should be accomplished
during the project planning
effort”
Procurement Planning ensures that the overall goal of a particular
project will be effectively and efficiently achieved.
Precludes occasions for unnecessary government purchases and
circumventions of the prescribed procurement procedures
- advance deliveries
- suki system
- unwarranted resort to alternative methods procurement
However, it must be done within budgetary context
Procurement Planning and Budgeting Linkage
Within approved budget of procuring entity
Judiciously done
Consistent with government fiscal measures
Considered crucial to the efficient discharge of governmental functions
o Required for the day-to-day operations
o In pursuit of the principal mandate of the procuring entity concerned
The APP shall include provisions for foreseeable emergencies based on
historical records.
No procurement unless in accordance with the Annual Procurement Plan
(APP)
Approval of the APP by the Head of Procuring Entity (HoPE) or designated
second-ranking official is mandatory
Source: Budget Operations Manual for Local Government Units
END BUDGET TECHNICAL
USER OFFICE WORKING GROUP
BIDS AND AWARDS COMMITTEE (BAC) & APPROVING
BAC SECRETARIAT AUTHORITY/HoPE
Source: Budget Operations Manual for Local Government Units
A guide document in the procurement and contract
implementation process, as well as a vital reference
in procurement monitoring.
Tool allowing the PE the flexibility to optimize the
utilization of scarce resources.
Minimize the practice of doing short-cuts
Each end-user unit shall prepare the PPMP during the budget preparation to
support the cost estimates in the budget proposal.
The end-user or implementing units shall be responsible for the preparation
of all documents necessary for the procurement activity, including but shall
not be limited to, the technical specifications, scope of work, or terms of
reference
During Budget Preparation/Budget Call
HOPE/Approving
Body
BAC &
Secretariat
Budget Submit Indicative
Office Consolidation of
APP and budget
proposal to
PPMPs to
HOPE/oversight
Indicative APP by
body for approval
Submit to BAC Sec and
End-User Budget Office recommendation
for evaluation by BAC of modality
Unit
Prepare Project
Procurement
Management
Plan (PPMP)
Source: Budget Operations Manual for Local Government Units
Downloadable at [Link]
Contracting
Arrangement
Estimated Type and
budget Objective
PPMP
Time
Extent/size
schedule
Procurement
Methods
Suggested basis for identifying needs:
1. Core functions of the end-user unit in the organization, i.e
Accounting, Legal etc.
2. Historical data/Foreseen contingencies;
3. Identified purpose/goals/MFOs;
4. P.E’s Strategic Plans;
5. Current supply inventory;
6. Other maintenance and operating needs.
Consult Stakeholders
In developing the project requirements and TS/SOW/TOR, the Procuring
Entity may engage the services of technical experts, whether in-house or
consultants, to ensure that the requirements and the TS/SOW/TOR are
adequate to achieve the objectives of the particular procurement.
Set CLEAR Specifications:
- Generic and flexible
- Clear and unambiguous
- Reminder on Reference to Brand Names (Section 18)
- Updated, where technology is taken into account
- Fits the actual requirements of the PMO/End-user
REQUIREMENT SPECIFICATION
Every purchase requires some form of requirement
specification no matter how simple.
• A requirement specification is a condition or
capability that must be met or possessed by a
system, product, service, result or component to
satisfy the end-user’s requirements.
22
REQUIREMENT SPECIFICATION
The specification is the “heart” of the procurement
transaction
• It defines client’s needs
• It tells buyer what to buy
• It tells supplier what is required
• It sets standards for quality
23
TYPES OF SPECIFICATIONS
1. Functional
• Purpose, duty, role or function
2. Performance
• Capability, input/output criteria, performance characteristics
3. Technical
• Detailed physical characteristics
24
FUNCTIONAL DESCRIPTION
description of the functions for which the Goods are to be utilized
EXAMPLE:
The ballpen is expected to write 1.5 km
of straight, continuous lines.
PERFORMANCE DESCRIPTION
refers to the manner that the Goods are required to perform the
functions expected of them
EXAMPLE:
A ballpen that writes at 1.5 km
continuously and smoothly.
ENVIRONMENTAL INTERFACE
refers to the environment in which the required functions are
performed at the desired level
EXAMPLE:
The ballpen should write continuously for
1.5km on a notebook, but not necessarily
on a white board.
DESIGN
refers to the technical design or drawing of the goods being
procured
EXAMPLE:
The ballpen should be comfortable to use
by left-hand writers.
The ABC reflected in the APP and PPMP shall be consistent with the
appropriations for the project authorized in the GAA, continuing and
automatic appropriations, the corporate budget, and the Appropriations
Ordinance, as the case may be.
For multi-year contracts, for which a Multi-Year Obligational Authority (MYOA)
or an equivalent document is required, the ABC shall be that incorporated in
the project cost reflected in the MYOA or equivalent document
For Foreign-funded Procurement, the ABC refers to the cost estimate
prepared by the PE and approved by the foreign government/foreign or
international financing institution as specified in the Treaty or
International or Executive Agreement
End user to conduct market study
Market price, inflation and cost of money related to the procurement time
table must also be considered.
In determining the ABC, the end-user unit, with the assistance of the TWG
(when necessary), must consider the different cost components.
Cost Components which may be considered:
Cost or market price of the product or service itself;
Freight, insurance, taxes, and other incidental expenses (For goods only);
Cost of money, to account for government agencies usually buying on
credit terms;
Inflationary factor (For goods only);
Quantities, considering that buying in bulk usually means lower unit
prices;
Supply of spare parts and/or maintenance services, if part of the
contract package (For goods only);
Factors to consider in identifying procurement timelines:
1. Budget rules, i.e. CSE – every quarter;
2. Nature of Procurement Projects, whether simple or complex
3. For shopping/small value procurement, give at least two weeks
4. Foreseen/Unforeseen Contingencies, i.e. frequent change in
specifications, etc.
5. Availability in the market.
As a general rule, all procurement
should be through Public Bidding
The selection of the method of
procurement is dependent on the
presence or absence of specific
conditions of other methods of
procurement in Sections 48 to 54 of
the revised IRR
Purchase Request (PR) – Request for purchase or requisition of
supplies, materials and equipment or its equivalent shall be duly
approved by proper authorities. (Source: Training Handbook on
Government Expenditures)
In no way that the End-user Unit submit their P.R. ahead of the
approved PPMP item.
Legal Basis: Section 7 of the revised IRR of RA 9184
Refers to the entirety of the procurement activities that will be
undertaken by the procuring Entity within the calendar year using the
prescribed format issued by the GPPB.
Shall be consolidated by the BAC Secretariat from the PPMPs of end-
user units. The BAC shall take into consideration the following factors:
One year planning perspective
Emergency or Contingency Fund
Schedule of Activities
No procurement shall be undertaken unless in accordance with the
approved APP
All procurement should be meticulously and judiciously planned by
procuring entity
APP should be maintained and updated regularly
In the consolidation of PPMPs, the BAC may adopt a strategy through
where similar items of procurement are packaged into one
procurement undertaking.
A review and updating of the individual PPMPs and the APP shall be
done regularly, at least once every 6 months or as often as necessary.
The end-user or implementing units shall be responsible for the
changes to the PPMPs, while the BAC Secretariat shall be responsible
for the consolidation of these PPMPs into an APP.
1 2 3 4 5 6 7 8
Per GPPB Circular 07-2015
• Column 1 - Code (UACS/PAP)
• Column 2 - Procurement Program/Project
• Column 3 – PMO/End-user
• Column 4 – Mode of Procurement
• Column 5 – Schedule of Each Stage of the Procurement Activity
• Column 6 - Source of Funds
• Column 7 - Estimated Budget
• Column 8 - Remarks (Brief Description of the P/A/P)
D o w n l o a d a b l e a t h tt p : / / w w w. g p p b . g o v. p h / d o w n l o a d a b l e s / S a m p l e Fo r m s . h t m l
GAA, Corporate Budget or Appropriation
Ordinance Becomes Final HOPE/Approving
Body
BAC &
Secretariat
End-User
Unit
Approval of APP
by HOPE/
Consolidation of oversight body
Budget PPMPs to APP by
Office Finalize Project BAC Sec and
Procurement recommendation by
Management BAC of modality
Plans (PPMPs)
Provide
comments on
Indicative
PPMPs to end-
users
Checking of Recommendation
procurement of procurement
methods methods by the BAC
Propose
procurement
methods (End-user)
Update/
Supplement End-User
PPMP
Consolidate
PPMP/s to BAC &
Updated/
BAC Secretariat
Supplemental
APP
Approve
Updated/
Supplemental HOPE
APP
Procurement Short of Award
To facilitate the immediate implementation of procurement, even
pending approval of the GAA, corporate budget or appropriations
ordinance, the PE may undertake the procurement activities short of
award
For a contract with a period not exceeding one (1) year, the ABC shall
be based on the amount in the approved indicative APP as included in
the proposed national budget (NEP) submitted by the President to
Congress; or on budget levels as proposed to the governing board for
GOCCs or in the executive budget for LGUs
No award of contract shall be made until the GAA or corporate budget
has been approved
APP being referred to in the IRR of RA 9184 is different from the APP-
CSE
APP-CSE serves as basis of DBM – PS in projecting its inventory
requirements, scheduling of activities, and over-all management of the
central procurement of common-use goods (DBM Circular Letter 2011-
6 & 2011-6a)
Common-use supplies – refers to those supplies and materials and
equipment included in the price list of the PS which are necessary in
the transaction of the official business of the procuring entity and
consumed in its day-to-day operations
Sort by Type of Procurement
Goods Infra Consulting
Check for Items which can be merged
i.e: IT Equipment, Design and Build projects, Office Furniture, etc
Common Use Supplies
CSE NON-CSE
Mode of Procurement
Sources of Funds
Value for Money Source
Time/ Quantity
Delivery
PROCUREMENT
Price Quality
3.2. Annual Procurement Plan (APP) – the requisite document that the
agency must prepare to reflect the entire procurement activity (i.e.,
goods, services, civil works to be procured) that it plans to undertake
within the calendar year. This document contains the following
information:
3.2.1. Name of the procurement program/project;
3.2.2. Project management office or end-user unit;
3.2.3. General description of the procurement;
3.2.4. Procurement method to be adopted;
3.2.5. Time schedule for each procurement activity;
3.2.6. Source of fund; and
3.2.7. Approved Budget for the Contract.
1. To verify if the procuring entity has an Annual Procurement Plan (APP)
2. To verify if the APP is approved by the HOPE or by a second-ranking
official designated by the HOPE to act on his behalf
3. To verify if the APP contains the following information:
a. name of the procurement program/ project;
b. project management office or end-user unit;
c. general description of the procurement;
d. procurement method to be adopted;
e. time schedule for each procurement activity;
f. source of fund;
g. approved budget for the contract.
4. To verify if the APP is supported by PPMPs prepared by the respective
end-user units
5. To verify if the items in the approved APP were included in the PPMPs
6. To verify if the APP matches the budget per GAA, corporate budget,
appropriation ordinance, as the case may be
1. Possible COA AOMs/Disallowances
2. Wastage of Government Funds
3. Suspension of Officials
4. Possible administrative/criminal liabilities
5. Project Delays
6. Project Failures