1. Coal target ( April 2019 to September 2019 ) 11.
84 lakh te, coal production
achievement 12.42 lakh te %achievement- 104.90%
2. Mine development activities such as construction of month urimari railway siding,
R&R development activities, construction of C/D type quarters etc are in progress as
per the scheduled
3. Rehabilitation of 10 PAEs of Boartola, Jojotola completed, shifting of 20 such PAE’s
is in process
4. No production loss due to IR problem
5. Despatch of coal April 2019 to September 2019 14.43 lakh te despatch of coal
achievement is more than target
6. Vocational training is being given to the employees and contractor workers as per the
schedule
7. Necessary action has been taken to comply the DGMS violations
8. Co-ordination meetings are held time to time with the villagers PAP’s to resolve their
issues for the progress of the mine working
9. Activities related with production and safety is in the process as per the production
programme. It is assured that production target is achieved