248 Chapter?
Chapter 7
Construction Contracts
Related standard: PFRS 15 Revenue from Contracts with Customers
Learning Objectives
1. Apply PERS 15 to account for revenues from, and. costs oj,
construction contracts.
2. Account for onerous construction contracts.
3. Account for changes in the transaction price of a construction
contract.
4. Account for uncertainty in the collectability of contrac
revenue.
Introduction
An entity applies PFRS 15 Revenue from Contracts with Customers to
account for revenues from contracts with customers. PFRS 15
supersedes PAS 11 Construction Contracts.
e Revenue — is “income arising in the course of an entity's
ordinary activities.” (PFRS 15. Appendix A)
© Contract - is “an agreement between two or more parties that
creates enforceable rights and obligations.” (PFRS 15.Appendix A)
Customer - is “a party that has contracted with an entity te
obtain goods or services that are an output of the entity's
ordinary activities in exchange for consideration.” (FR
15. Appendix A)
Core principle under PFRS 15
An entity recognizes revenue to depict the transfer of promised
goods or services to customers in an amount that reflects the
consideration to which the entity expects to be entitled i"
exchange for those goods or services.
atte ll
||
i]
J
oon oeConstruction Contracts
_ fl Summary of the Revenue recognition Principles wader PERS 15:
[Step 1: Identify the contract with
the customer
The contract is with a customer and
| (among others) the collectability of
the consideration is probable.
Step 2: Identify the performance
obligations in the contract
Each promise to deliver a distinct
good or service in the contract is
treated as a separate performance
obligation
A promised good or service is
distinct if:
a. The customer cai benefit from the
good or service either on its own
or together with other resources
that are readily available to the
customer; and
b. The promise to transfer the good
‘or service is separately identifiable
from other promises in the
contract.
Step 3: Determine the transaction
price
‘The transaction price is the amount
that the entity expects to be entitled
to in exchange for satisfying a
performance obligation.
Step 4: Allocate the transaction
price to the performance
obligations
The transaction price is allocated to
the performance obligations based
on the relative stand-alone prices of the
distinct goods or services.
Step 5: Recognize revenue when
(or as) a performance obligation
is satisfied
~ For a performance obligation
satisfied over time, revenue is
recognized as the entity
progresses towards the complete
satisfaction of the performance
obligation.
- For a performance obligation
satisfied at a point in time,
revenue is recognized when the
entity completely satisfies thealge
performance obligation,
Revenue is measured a)
amount of transaction price alllog
to the performance
satisfied.
ai |
Obligatig,
Definition of Construction contract
Construction contract — is a contract specifically negotiated fo, the
construction of an asset or a combination of assets that are lose
interrelated or interdependent in terms of their design, technology
and function or their ultimate purpose or use.
Construction contracts include:
a. Contracts for the rendering of services that are directly related
to the construction of an asset, e.g, those for the services of
Project managers and architects; and
b.
Contracts for the destruction or restoration of assets, and the
restoration of the environment following the demolition of
assets.
Construction contracts are generally long-term. The dete
at which the contract is entered into and the date the contract is
completed normally fall on different financial reporting perils
The primary issue in the accounting for construction contracts,
therefore, is the timing of recognition of contract revenue and
contract costs.
Application of the Basic Principles of PFRS 15
Step 1: Identify the contract with the customer
A contract with a customer is accounted for only when all of tk
following criteria are met: .
a. The contracting parties have approved the contract (in writin
orally or implied in customary business practices) and
committed to perform their Tespective obligations;
alcConstruction Contracts
p. The entity can identify each party’s rights regarding the goods
or services to be transferred;
c. The entity can identify the payment terms for the goods or
services to be transferred;
d, The contract has commercial substance (i.e., the risk, timing or
amount of the entity’s future cash flows is expected to change
ag a result of the contract); and
e. The consideration in the contract is probable of collection.
When assessing collectability, the entity considers only the
customer's ability and intention to pay the consideration on due
date.
No revenue is recognized on a contract that does not meet
the criteria above. Any consideration received from such contract
is recognized as a liability and recognized as revenue only when
either of the following has occurred:
a. The entity has no remaining obligation to transfer goods or
services to the customer and all, or substantially all, of the
consideration has been received and is non-refundable; or
b. The contract has been terminated and the consideration
received is non-refundable.
Combination of contracts
Each contract is accounted for separately. However, two or more
contracts entered into at or near the same time with the same
customer (or related parties of the customer) are combined and
accounted for as a single contract if:
a The contracts are negotiated as a package with a single
commercial objective;
b. The amount of consideration to be paid in one contract
depends on the price or performance of the other contract; or
c. Some or all of the goods or services promised in the contracts
are a single performance obligation.
Negotiating multiple contracts at the same time is not
sufficient evidence to demonstrate that the contracts represent a
single arrangement.252 Chapter?
AAS?
Step 2: Identify the performance obligations in the contrac,
Each promise to transfer the following is a performance obligayi,,
that is accounted for separately:
a. A distinct good or service (or a distinct bundle of goods 4,
services); or
b. A series of distinct goods or services that are substantially th,
same and have the same pattern of transfer to the customer
A promised good or service is distinct if:
a. The customer can benefit from the good or service either on its
own or together with other resources that are readily available
to the customer; and
b. The promise to transfer the good or service is separatey
identifiable from other promises in the contract.
Customer can benefit:
A customer can benefit from a good or service if the good or service
could be used, consumed, sold for an amount that is greater than
scrap value or otherwise held in a way that generates economic
benefits. The fact that the entity regularly sells a good or service
separately indicates that a customer can benefit from the good ot
service on its own or with other readily available resources.
Separately identifiable:
A promise to transfer a good or service is separately identifiable if
the good or service: |
i. is mot an input to a combined output specified by the |
customer. |
ii. does not significantly modify another good or service |
promised in the contract.
iii, is not highly interrelated with other goods or servic
promised in the contract. For example, the customer’ —
decision of not purchasing a good or service does not affect
the other promised goods or services in the contract.ruction Contracts 253
Construct
A promised good or service that is not distinct is combined
with other promised goods or services until a bundle of goods or
services that is distinct is identified. In some cases, this may result
to treating all the promised goods or services in a contract as a
single performance obligation.
Series of distinct goods or services
A series of distinct goods or services that are substantially the
same and have the same pattern of transfer to the customer are
accounted for as a single performance obligation if each good or
service in the series represents a performance obligation that
would be satisfied over time if each was accounted for separately;
and the entity would use the same measure of progress toward the
satisfaction of the performance obligation for each of those goods
or services.
Performance obligations include only activities that involve the
transfer of a good or service to a customer. Performance
obligations do not include administrative tasks to set up a
contract.
Example: Determining whether goods and services are distinct
Entity A, a contractor, enters into a contract to build a resort hotel
fora customer. Entity A is responsible for the overall development
and identifies various goods and services to be provided,
including design, engineering, site preparation, procurement,
Construction, piping and wiring, installation of uninterruptible
Power supply system, swimming pools and Jacuzzi, and finishing.
The entity, and its competitors, regularly sells many of these
800ds and services separately to customers.
Analysis:
The Promised goods and services are capable of being distinct
Under criterion (a). The customer can benefit from the goods and
Services either on their own or together with other readily
Available resources. This is evidenced. by the fact that the goods
[Saae Chapter 7
and services are regularly sold to customers. In addition, th,
customer could generate economic benefit from the individ
goods and services by using, consuming, selling or holding them, |
However, the goods and services are not distinct unde,
crilerion (b) because they are not separately identifiable from each)
other. This is evidenced by the fact that the entity Provides 4
significant service’ of integrating the goods and services (the |
inputs) into the hotel resort (the combined output) for which the |
customer has contracted. |
Conclusion:
Because both criteria are not met, the goods and services are not
distinct. The entity accounis for all the goods and services in the
contract not separately but as a single performance obligation.
Satisfaction of performance obligations
At contract inception, the entity shall determine whether the
identified performance obligations will be satisfied either:
a. Over time; or
b. Ata point in time
A performance obligation is satisfied over time if one of
the following criteria is met:
a. The customer simultaneously receives and consumes the benefits
provided by the entity's performance as the entity performs.
Example: If the contract with the customer is
discontinued and the customer enters into a contract with
another entity to fulfill the remaining performance obligation.
the other entity would not need to substantially re-perform
the work that the entity has completed to date.
b. The entity's performance creates or enhances an asset (8
work in progress) that the customer controls as the asset is
created or enhancedConstruction Contracts
Rss eee
¢ The entity's performance does not create an asset with an
alternative use to the entity and the entity has an enforceable right
to payment for performance completed to date.
Alternative use:
i. An asset does not have an alternative use to the entity if
the entity is restricted contractually from directing the
asset for another use during or after the asset’s
completion, or in the absence of a contractual restriction,
the entity would incur significant costs of rework before
it can direct the asset for another use, or the entity could
only sell the asset at a significant loss.
Enforceable right to payment for performance completed to date:
ii, Anentity has an enforceable right to payment for performance
completed to date if the entity is entitled to compensation
for the completed performance if the contract is
terminated for reasons other than the entity’s failure to
perform as promised, and the compensation is sufficient
to cover the costs incurred in satisfying the performance
obligation plus a reasonable profit margin. A reasonable
profit margin need not equal the profit margin expected
if the contract was fulfilled as promised.
For many construction contracts, it is likely that the
performance obligation is satisfied over time. However, an entity
should consider all available information to determine whether
one of the criteria above is met.
If the entity cannot
obligation is satisfied over time,
Performance obligation is satisfied at a point in time.
demonstrate that a performance
it is presumed that the256
Chapter 7
tere eeeceneee
Example 1.1: Alternative use
%
Entity A énters into
1
a contract with a customer to builg ,
el. Entity A customizes solar panels for |
ch solar panel can differ substantially on the |
basis of each customer's needs. If the customer cancels the Contrag |
for reasons other than Entity A’s failure to perform, Entity A g), |
|
|
|
Customized solar pan
|
|
various customers, Ea |
all
keep the solar panel. However, due to its specialized naty
Significant: modificatio
sold to another custom
Te,
n is needed before the solar panel Can be
er,
Analysis;
At contract inception, Entity A assesses whether its Performance
obligation to bu
ild the solar panel is a performance obligation that
is satisfied over time using the criteria in (a) to (c) above,
As part of that assessment, Entity A considers whether the
solar panel has an alternative use to Entity A. (See criterion ‘¢’
Although Entity A is not contractually restricted from
directing the solar Panel to another customer, the customer.
Specific design of the solar power limits Entity A’s practical ability
to readily direct it to another customer without incurring
significant costs of rework. Consequently, the solar panel has 10
alternative use to Entity A.
However, before Entity A can conclude that its
performance obligation is satisfied over time, Entity A shall also
assess if it has an enforceable right to Payment for performance
completed to date. See Example 1.2 below,
Example 1.2; Enforceable right to payment |
(Continuation of Example 1.1)
The customer is required to make a 15% adv,
contract inception. Subsequent payments are |
| Progress on the contract, after proportionate deductions for the)
| advance payment and 10% retention. The 10% retention is due)
| when the solar panel is completed and has passed the prescribed
performance tests. The payments are non-refundable unless Enti
| A fails to periorm ag=promised:If ane Neugiomer cancel
ance payment a
based on Entity 4's)
j
ale:struction Contracts ~
Constr _ 257
| contract, Entity A retains any payments received but has no right
“| to further compensation.
; —— a _
Analysis:
Entity A considers whether it has an enforceable right to payment for
performance completed to date if the customer were to terminate the
contract for reasons other than Entity A’s failure to perform as
promised. (Gee criterion’c’)
Entity A has an enforceable right to payment for performance
completed to date because the payments are non-refundable and are
based on Entity A’s progress on the contract. The cumulative
amount of the payments is expected, at all times throughout the
contract, to sufficiently cover Entity A’s costs plus a reasonable profit
margin.
Accordingly, in Examples 1.1 and 1.2, Entity A can conchide
that its performance obligation to build the solar panel is a
performance obligation that is satisfied over time.
Example 1.3: Enforceable right to payment
(Continuation of Example 1.1 and Variation of Example 1.2)
The customer is required to make a 15% advance payment at
contract inception, periodic payments equal to 40% throughout
the estimated construction period, and the remaining 45% when
the solar panel is completed and has passed the prescribed
performance tests. The payments are non-refundable unless Entity
A fails to perform as promised. If the customer cancels the
contract, Entity A retains any payments received but has no right
to further compensation
Analysis:
Entity A does not have an enforceable right to payment for
performance completed to date because even though the
payments are non-refundable, the cumulative amount of those
payments is not expected, at all times throughout the contract, to
compensate Entity A’s performance completed to date.oN
as Chapter 7
For example, if the customer cancels the contract y
100% completion, Entity A would only be entitled to 55% Paymen,
(15% advance + 40% periodic payments) and that would p,
insufficient to cover Entity A’s costs plus a reasonable Profit
margin.
Accordingly, in Examples 1.1 and 1.3, Entity 4,
Performance obligation to build the solar panel is a performance
obligation that is satisfied at a point in time.
Example 1.4: Enforceable right to payment
(Continuation of Example 1.1 and Variations of Examples 1.2 & 1.3)
The customer is required to make a 15% advance payment a
contract inception. The balance is payable when the solar panel is |
completed and has passed the prescribed performance tests. The |
payment is refundable only when Entity A fails to perform as|
promised.
Analysis:
Entity A does not have an enforceable right to payment for
performance completed to date (same reason as with Ex. 1.3).
Step 3: Determine the transaction price
The transaction price is “the amount of consideration to which an
entity expects to be entitled in exchange for transferring promised
goods or services to a customer, excluding amounts collected ot
behalf of third parties (e.g., some sales taxes).” (PFRS 15.Appdx. A)
In a construction contract, the transaction price normally
consists of the following: |
a. The contract price; and |
b, Any subsequent variations in the contract price to the extent
that it is probable that they will result in revenue and they af |
capable of being, measured reliably, |
However, the transaction price may not be equal to the |
contract price if the consideration in the contract is affected by a
of the following:
wee eaeConstruction Contracts
Variable consideration;
Constraining estimates of variable consideration;
The existence of a significant financing component in the
contract;
d. Non-cash consideration; or
e. Consideration payable to a customer.
oP
Aconstruction contract may be either:
1. Fixed price contract - a construction contract in which the
contractor agrees to a fixed contract price or a fixed rate per
‘unit of output, which in some cases is subject to cost escalation
clauses.
2. Cost plus contract - a construction contract in which the
contractor is reimbursed for allowable or defined costs, plus a
fee. The two types of cost-plus contracts are:
a. Cost-plus-variable-fee contract ~ the contractor is reimbursed
for the costs plus a percentage of those costs. The contract
price is the sum of the costs and the variable fee.
b. Cost-plus-fixed-fee contract - the contractor is reimbursed
for'the costs plus a fixed amount. The contract price is the
sum of the costs and the fixed fee.
Some construction contracts may contain characteristics of
both a fixed price contract and a cost plus contract, such as in the
case of a cost plus contract with a ceiling price.
Example: ;
You contracted Mr. Architect Engineer Contractor to build a house
for you.
Case 1: The contract states a price of POM for the house. |
Analysis: The contract is a fixed price contract. The transaction price
is P6M,260
er
o 2: The contract states that you shall reimburse Mr. Contragj>)
€ total construction costs plus 15% thereof. " |
Analysis: The contract is a cost-plus-a-variable-fee contract, The
transaction price is equal to the reimbursable costs plus 15,
thereof,
Case 3: The contract states that you shall reimburse Mr. Contractor
the total construction costs plus P2M.
Analysis: The contract is a cost-plus-a-fixed-fee contract. The
transaction price is equal to the reimbursable costs plus P2M.
Cost-plus pricing is used in cases where it is difficult for
the contractor to quote the contract price because either
a. itis not possible to accurately estimate the scope of the project;
or
b. there have been no precedent similar projects that can be used
as basis for price quotation.
The cost-plus-variable-fee, which is common in government
contracts, has the following disadvantages:
a. Disadvantage to the contractor: The contractor's recovery of
overhead costs depends on the cost of materials, which can be
affected by significant price fluctuations. There can be a tisk
that the agreed percentage may prove to be too low for the
contractor to recover overhead costs and eam a profit.
b. Disadvantage to contractee: There is no incentive for the
contractor to be cost-efficient. Instead, the contractor ®
tempted to increase the cost because the greater the cost, the
greater will be the profit. Accordingly, the contractee may end
up paying an outrageously overstated contract price.onstruction Contracts 5
a 261
Step 4: Allocate the transaction price t
Sr tions pl io the performance
The transaction price is allocated to the performance obligations
based on the relative stand-alone prices of the distinct goods or
services.
The stand-alone selling price is the price at which a
promised good or service can be sold separately to a customer
If there is only one performance obligation in a contract,
the transaction price is allocated only to that single performance
obligation.
Step 5: Recognize revenue when (or as) a performance
obligation is satisfied
If the performance obligation in the contract is satisfied over time,
revenue is recognized over time as the entity progresses towards
the complete satisfaction of the obligation.
If the performance obligation in the contract is satisfied at
a point in time, the entity recognizes revenue when the
performance obligation is satisfied.
Revenue is measured at the amount of the transaction price
allocated to the satisfied performance obligation.
Performance obligations satisfied over time
An entity recognizes revenue from a performance obligation that
is satisfied over time based on the entity’s measurement of its
progress towards the complete satisfaction of the obligation in the
contract. For example, if the performance obligation is 70%
completed, revenue is recognized equal to 70% of the transaction
price.
Methods of measuring progress ;
An entity shall use a single method of measuring progress
consistently for each performance obligation satisfied over time
and shall remeasure its progress at the end of each reporting
period. Appropriate methods of measuring progress include:
a. Output methods
b. Input methods262 g Chapter 7
Input methods
Inputs methods recognize revenue on the basis of efforts or inp),
expended relative to the total expected inputs needed to fully
satisfy a performance obligation. Examples of efforts or inputs
include:
a. Costs incurred
b. Resources consumed
c. Labor hours expended
d. Machine hours used
e. Time elapsed
Cost-to-cost
The most common application of the input methods is the “cost-
cost” method.
Cost-to-cost method refers to the estimation of stage of
completion by reference to the proportion that contract costs
incurred for work performed to date bear to the estimated total
contract costs.
In other words, the percentage of completion is
determined as the ratio of total costs incurred to date over the
estimated total contract costs.
Formula #1:
Percentage of Total costs incurred to date
completion Estimated total contract costs
> Total costs incurred to date represent the cumulative costs
incurred from contract inception up to the current reporting
date.
> Estimated tolal contract costs (Estimated total costs at completion
pertain to the forecasted total costs of completing the contract
This can also be determined as the sum of total costs incurred
date and estimated costs to complete.suction Contracts
263
Estimated costs t ele pert
> Ee ted ‘0 complete pertain to the anticipated additional
costs required to fully complete the contract.
Formula #2: Variation
A variation of the formula above is presented below:
ral costs incurred to date _
= Total costs incurred to date +
Estimated costs to complete
Percentage of
completion
Illustration 1: Cost-to-cost
In 20x1, ABC Construction Co. enters into contact to construct a
building for a customer. The contract price of P6M will be billed to
the customer periodically based on ABC’s progress on the
construction.
| Case 1: Estimated total contract costs
| The estimated total contract costs are PAM. The actual costs incurred
in 20x1 are P1.2M. ss
Requirement: How much revenue is recognized in 20x1?
Solution:
Step 1: Identify the contract with the customer :
The contract is a construction contract, i.e, a contract specifically
negotiated for the construction of an asset.
Step 2: Identify the performance obligations in the contract
The performance obligation is to construct a building. This is
satisfied over time because:
a. The entity's performance creates an asset (e.g., work in progress)
that the customer controls as the asset is created.
b. The entity’s performance does not create an asset with an
alternative.use to the entity and the entity has an enforceable right to
payment for performance completed to date:264 Chapter 7
Step 3: Determine the transaction price
The transaction price is the contract price of POM.
Step 4: Allocate the transaction
The whole of the P6M transaction price is allocated to the single
performance obligation of constructing @ building.
Step 5: Recognize revenue when (or as) a performance obligation
is satisfied
Because the performance obligation is satisfied over time, ABC
shall recognize revenue over time as it progresses towards the
complete construction of the building.
ABC shall measure its progress by, in this case, using the
‘cost-to-cost’ method, an application of the input method.
Revenue in 20x] is computed as follows:
Percentage of Total costs incurred to date
completion Estimated total contract costs
Percentage of completion = 1.2M + 4M
Percentage of completion = 30%
Revenue in 20x1 = Contract price x Percentage of completion
Revenue in 20x1 = 6M x 30%
Revenue in 20x1 = P1,800,000
Case 2: Estimated costs to complete |
The actual costs incurred in 20x1 are P1.2M. The estimated costs # |
complete as of Dec. 31, 20x1 are P2.8M
Requirement: How much revenue is recognized in 20x1?
Solution.ruction Contracts
N
a
Total costs incurred to date
Total costs incurred to date +
Estimated costs to complete
percentage of == ————
completion
Percentage of completion = 1.2M + (1.2M+ 2.8M)
percentage of completion = 1.2M = 4M
percentage of completion = 30
Revenue in-20x1 = Contract price x Percentage of completion
Revenue in 20x] = 6M x 30%
Revenue in 20x1 = P1,800,000
Illustration 2: Estimated costs to complete - Subsequent period
information on an entity’s contract costs is as follows:
20x1 20x2
Total costs incurred to date 400,000 1,500,000
Estimated costs to complete 1,600,000 375,000.
Requirement: Compute for the following:
a. Percentage of completion as of Dec. 31, 20x1
b. Percentage of completion as of Dec. 31, 20x2
c. Percentage completed in 20x2.
Solutions:
Total costs incurred to date
= Total costs incurred to date + Estimated costs
to complete
Percentage of
completion
Requirement (a): Percentage of completion as of Dec. 31, 20x1
Percentage of completion = 400,000 + (400,000 + 1,600,000)
Percentage of completion = 400,000 + 2,000,000
Percentage of completion as at Dec. 31, 20x1 = 20%
Requirement (b): Percentage of completion as of Dec. 31, 20x2
Percentage of completion = 1,500,000 = (1,500,000 + 375,000)
Percentage of completion = 1,500,000 + 1,875,000 *
Percentage of completion as at Dee: 31, 20x2 = 80%266 Chapter?
Requirement (c): Percentage of progress made in 20x2
The computed percentages above are the cumulative percentage,
of completion at the end of each year. Meaning, the 80,
completion as at Dec. 31, 20x2 includes the 20% completed in 29.3,
Therefore, the perceniage completed in 20x2 is 60% (80% minus 20%)
Efforts-expended (labor hours-based) method
Another application of the inputs method is the efforis-expende,
(labor hours-based) method. Under this method, the percentage of
completion is based on “efforts expended” in. completing the
contract — normally in direct labor hours, rather than on costs. This
method is most commonly used by general contractors who
profits are directly related on how they manage subcontractors
rather than from the value of the subcontracts themselves.
The percentage of completion is computed as follows:
Percentage of _ Total labor hours to date
completion ~ "Estimated total contract Labor hours
OR
Percentage Total labor hours to date
of = Total labor hrs. to date + Estimated labor hrs. to
completion complete
Illustration: Efforts-expended method
Information on an entity's labor hours on a contract is as follows:
20x1 20x2
Total direct labor hours to date 400 1,500
Estimated direct labor hrs. to complete 1,600 375
Requirement: Compute for the percentages of completion as of Dec
31, 20x1 and 20x2.
Soltttion:construction Contracts 267
Percentage Total labor hours to date
of = Total labor hrs. to date + Estimated labor hrs. to
completion complete
20rd
Percentage of completion = 400 = (400 + 1,600)
Percentage of completion = 400 = 2,000
Percentage of completion as at Dec. 31, 20x1 = 20%
20x2
Percentage of completion = 1,500 + (1,500 + 375)
Percentage of completio: 500 + 1,875
Percentage of completion as at Dec. 31, 20x2 = 80%
> The percentage completed in 20x2 is 60% (80% minus 20%).
Contract costs
Contract costs include:
a. Incremental costs of obtaining a contract
b. Costs to fulfill a contract
Incremental costs of obtaining a contract
Incremental costs of obtaining a contract - are costs incurred in
obtaining a contract with a customer that the entity would not
have incurred had the contract not been obtained (e.g, sales
commission).
® Such costs are recognized as asset if the entity expects to
recover them.
Cosis that would have been incurred regardless of whether
the contract was obtained are recognized as expense, unless
those costs are explicitly chargeable to the customer regardless
of whether the contract is obtained.
>268 . Chaptery |
at ae es i ae peg Tm
remental costs of obtainjn,
hen incurred if the expect
or less.
As a practical expedient, inc
contract are recognized as expense W!
amortization period of the asset is one year
Costs to fulfill a contract wae
Costs incurred in fulfilling a contract that are within the scope
other standards (e.g., PAS 2 Inventories, PAS 16 PPE, or PAS
Intangible Assets) are accounted for in accordance With thos
standards.
Costs incurred in fulfilling a contract that are outside the
scope of other standards are recognized as asset if all of the
following criteria are met:
a. The costs are directly related to a contract or specifically |
identifiable anticipated contract.
b. The costs generate or enhance resources that will be used in
satisfying performance obligations in the future; and
cc. The costs are expected to be recovered.
Examples of costs that are directly related to a contract:
a. Direct materials (e.g., costs of materials used in construction).
b. Direct labor (e.g, site labor costs, including site supervision).
c. Other costs that are incurred only because the entity entered
into the contract. Examples:
i, Payments to subcontractors
ii Costs of moving plant, equipment and materials to and
from the contract site
iii, Costs of hiring plant and equipment
iv. Costs of design and technical assistance that are direct!’
related to the contract
d. Costs that are explicitly chargeable to the customer under the
contract (eg., estimated costs of rectification and guarante®
work, including expected warranty costs, and claims ffo™
third parties).
e. Allocations of costs that relate directly to the contract of?
contract activities! Examples?Construction Contracts 260
i. Insurance
ii, Depreciation of plant and equipment used on the
contract
iii, | Costs of design and technical assistance that are not
directly related to a specific contract
iv. Costs of contract management and supervision
vy. Borrowing costs capitalized in accordance with PAS 23
Borrowing Costs
vi. Other construction overheads
The following costs are expensed when incurred:
a. General administration costs for which reimbursement is not
specified in the contract
b. Costs of wasted materials, labor or other resources that were
not reflected in the price of the contract
c. Selling costs
d. Research and development costs for which reimbursement is
not specified in the contract
e. Depreciation of idle plant or equipment that is mot used on a
particular contract
{. Costs that relate to satisfied or partially satisfied performance
obligations in the contract (i.e, costs that relate to past
performance)
8. Costs for which an entity cannot distinguish whether the costs
relate to unsatisfied performance obligations or to satisfied or
partially satisfied performance obligations
Any incidental income derived from the construction that
is not included in contract revenue is accounted for as reduction of
contract costs, e.g., income from the sale of excess/scrap materials.
Amortization and impairment
Contract costs recognized as asset are amor!
basis that is consistent with the transfer of the related goods or
Services to the customer.
tized on a systematic270
carrying amount of the asset exceeds:
a
Chapter 7
Oa caer a
Impairment loss is recognized to the extent that the
a. the remaining amount of consideration that the entity expegs
to receive in exchange for the goods or services to Which the
asset relates; less
b.
the costs that relate directly to providing those goods o,
services and that have not been recognized as expenses,
(PFRS 15.101)
Illustration:
A contractor uses the “cost-to-cost” method in determining its
Progress on a contract. The estimated total contract cost is P10M.
The following costs were incurred in the first year of the
construction:
Costs of negotiating the contract (immediately expensed)
Costs of materials used in construction
Costs of materials purchased but not yet used.
Site labor costs
Site supervision costs
Depreciation of equipment used in construction
Depreciation of idle equipment not used in the contract
Costs of moving equipment to and from the contract site
Costs of hiring equipment
100,000
|
|
|
|
|
3,000,000
500,000
1,000,000
200,000
120,000
60,00)
40,000
140,000
Requirement: Compute for the percentage of completion.
Solution
Costs of materials used in construction
Site labor costs
Site supervision costs
Depreciation of equipment used in construction
Costs of moving equipment to and from the contract site
Costs of hiring equipment
Total costs incurred to date
3,000,000
1,000,000
200,000
120,000
40,000
ume,
we
ae
aYr
Construction Contracts =
& percentage of - Total costs incurred to date
completion Estimated total contract costs
& percentage of completion = 4, 500,000 + 10,000,000
Percentage of completion =
Adjustments to the measure of progress
Aweakness of the input methods is that there may not be a direct
relationship between the inputs and the transfer of control of the
asset to the customer. In such cases, the inputs used in measuring
the entity’s progress are adjusted.
' When using the “cost-to-cost” method, an entity excludes
"the following when measuring its progress on a contract:
a. Costs that do not contribute to the entity's progress in
i satisfying the performance obligation, e.g., costs of significant
i inefficiencies, such as wasted materials, labor and other
ji tesources that were not reflected in the contract price.
yb. Costs incurred that are not proportionate to the entity’s
K progress in satisfying the performance obligation. Examples:
i i, Advance payments to subcontractors for which the
t subcontracted work has not yet been started.
t ii, Materials acquired but not yet used on the contract
However, the entity may adjust the input method to
tecognize revenue only to the extent of that cost incurred if
the entity expects at contract inception that all of the following
conditions would be met:
| 1. The good is not distinct;
2. The customer is expected to obtain control of the good
significantly before receiving services related to the good;
3. The cost of the transferred good is significant relative to
the total expected costs to completely satisfy the
performance obligation; and
4. The entity procures the good from a third party and is not
significantly involved in designing and manufacturing the
good (but the entity is acting as principal)
| =e272 Chapter 7
Ilustration 1: Revenue to the extent of cost incurred
On Sept. 1, 20x1, ABC Co. enters into a contract with a customer j.
remodel a plant's electrical wirings and install a new generator fg,
a total consideration of PI2M. The remodeling and the installation
are treated as a single performance obligation satisfied overtime, |
The expected contract costs are as follows:
|
Generator 4,000,000
Other costs 5,000,000
Expected total contract costs 9,000,000
Additional information:
© ABC Co. uses the cost-to-cost method in measuring its progress,
© ABC Co. incurs total costs of P6,000,000 in 20x1, including the
cost of the generator.
© The customer obtains control of the generator when it is
delivered to the site in December 20x1. However, the
generator will not be installed until March 20x2.
e ABC Co. regards the cost of the generator as significant in |
relation to the expected total contract costs (i. 4M > 9M = 44.44%).
e Although ABC Co. acted as a principal in procuring the |
generator, ABC Co, is not involved in designing o
manufacturing the generator.
Requirements:
a. How much revenue is recognized in 20x1?
b. How much profit is recognized from the contract in 20x1?
Solutions.
Analysis:
> The costs incurred to date include the cost of an uninstallel
material, i.e., generator.
+ Because all the conditions listed above (#’s.1.to.4) are met. th”
cost of the generator is excluded from when computing
|construction Contracts 73
applying the percentage of completion. Instead, the cost of the
generator is recognized both as revenue and cost of goods
sold. Consequently, no profit is recognized from the generator
in 20x1,
Percentage of
= ———_Total costs incurred to date _
completion
Estimated total contract costs
= (6M total costs incurred - 4M cost of generator) ~ (9M expected total
contract costs — 4M cost of generator)
=2M+5M
Percentage of completion = 40%
Requirement (a): Revenue in 20x1
Total contract price 12,000,000
Less: Cost of generator (4,000,000)
Total i 8,000,000
Multiply by: Percentage of completion 40%
Total 3,200,000
Add back: Cost of generator 4,000,000
Revenue > 7,200,000
Requirement (b): Profit in 20x1
Expected total contract cost 9,000,000
Less: Cost of generator (4,000,000)
Total 5,000,000
Multiply by: Percentage of completion 40%
Total . 2,000,000
Add back: Cost of generator , 4,000,000.
Cost of goods sald 6,000,000
Revenue ~ : 7,200,000
Cost of goods sold (6,000,000)
Profit 1,200,000274 Chapter 7
Illustration 2: Adjustments to the input method yt
» ABC Co. uses the “cost-to-cost” method in measuring its Progres.
on a construction contract. The estimated total contract cost s
PI0M. Actual costs incurred during the year totaled Poy,
including ?2M advance payment to a subcontractor (the
subcontracted work is not yet started) and 200,000 cost o;
materials not yet installed. The unused materials are no}
significant in relation to the expected total contract costs,
Moreover, ABC Co. retains control over the unused materials
because it can use them on contracts with other customers.
Requirement: Compute for the percentage of completion in 20x1,
Solution:
Because the conditions listed above (ie, #’s 1 to 4) are not met, the
P2M advance payment to the subcontractor and the P200K unused
materials are simply eliminated when measuring ABC’s Progress.
Percentage of _ Total costs incurred to date
completion Estimated total contract costs
Percentage of completion = (6M - 2M — 200K) = 10M
Percentage of completion = (3.8M + 10M) = 38%
Presentation
When either party to a contract has performed, the contract is
Presented in the statement of financial position as a conirac
liability or a contract asset. An unconditional right to consideration
is presented separately as a receivable,
Contract liability ~ is “an entity’s obligation to transfer goods of
services to a customer for which the entity has receined consideratio"
(or the amount is due) from the Customer.” (PrRsis.appendix A)
4Construction Contracts
7 7 275
A contract liability is recognized at the earlier of the date:
a, The entity teceives consideration before the good or service is
transferred to the customer (i.e., advance payment). :
b. The entity has an unconditional right to the consideration before
the good or service is transferred to the customer (e.g., a non-
cancellable contract requires payment in advance). ‘
Contract asset — is “an entity's right to consideration in exchange
for goods or services that the entity has transferred to a customer
when that right is conditioned on something other than the passage
of time (e.g., the entity’s future performance).” (PFRS 15. Appendix A)
A contract asset (excluding amounts recognized as a
receivable) is recognized when the good or service is transferred
to the customer before the consideration is received or becomes
due.
Receivable - is an entity’s right to consideration that is
A right to consideration is unconditional if only the
before payment of that consideration is
ject to refund in the future.
unconditional.
passage of time is required
due, even if the amount is sul
On initial recognition, any difference between the
the receivable in accordance with PFRS 9 and the
measurement of
ognized is presented as an
corresponding amount of revenue rec
expense (e.g., a5 an impairment loss).
liability and Receivable
ers into a contract to install a gate for
fabricated in ABC’s place of business
and will be assembled and installed in the customer's premises on
Mar. 31, 20x1. The contract requires the customer to pay a
consideration of P1,000 in advance on Jan. 31, 20x1. The customer
pays the consideration on Mar. 1, 20x1. ABC installs the gate on
Mar, 31, 20x1.
Illustration 1: Contract
On Jan. 1, 20x1, ABC Co. enti
a customer. The gate will be276 Caples
Requirement:
Provide the journal entries under each of
following sce
narios: (a) the contract is cancellable and ©) the
contract is non-cancellable. (Ignore contract costs)
Solutions:
Scenario A: Canceilable Scenario B: Non-cancellable
liek ot
No entry No entry
© No entry because neither party has performed its obligation,
Scenario A: Cancellable
Jan. 31, 20x1
lan. 2
No entry Receivable... 1,000
Contract liability... ss... 1,000
A receivable is recognized under Scenario B because ABC Co,
has an unconditional right to consideration (i.c., the contract is
non-cancellable and it requires payment on this date). ABC Co,
is entitled to the consideration whether the customer pursues
or cancels the contract. A corresponding contract liability is
recognized for ABC’s obligation to install the gate.
Scenario B: Non-cancellable
ca
® No receivable is recognized under Scenario A because ABC Co.
does not have an unconditional right to consideration (ie, the
contract is cancellable),
_
[Scenario A: Cancellable Scenario B: Non-cancellable _|
Casi 1,000 |
Receivable .......:se:s:01+-1,000_|
# Under Scenario A, contract liability is credited when the
advanced payment is received.
” Under Scenario B, receivable is credited. The contract liability
is recognized on Jan. 31, the earlier of the date th
unconditional right to the consideration is obtained (Jan. 3!)
and the date the advanced payment is received (Mar. 1).
eee ieConstruction Contracts a
Scenario A: Cancellable | cancellable
Mar 31.2081 1 i = icellable _
Contract liability......1,000 | Contract liability......1,000
Revenue... 1,000 Revenue... eeeed,000
r Reverie is recognized only on Mar. 31 when the performance
obligation is satisfied (i.¢., the gate is installed).
Illustration 2: Contract asset
On Dec. 1, 20x1, ABC Co. enters into a contract with a customer
for the installation of roof tiles. The expected number of roof tiles
to be installed is 1,000 units. The contract price is P100 per roof tile
installed. However, the customer pays the total consideration only
when all of the 1,000 roof tiles have been installed.
ABC assesses its performance obligation to be satisfied over time
because the customer simultaneously receives and consumes the
benefits provided by ABC’s performance as ABC performs; and
ABC's performance enhances an asset that the customer controls
as it is enhanced.
As of Dec. 31, 20x1, 800 roof tiles have been installed. The
remaining 200 tiles have been installed on Jan. 7, 20x2. The
customer pays the consideration on Jan. 9, 20x1.
Requirement: Provide the journal entries. Ignore contract costs.
Solution:
Dec. 1,
201 No entry
Dec. 31,] Contract asset (800 units x P100) 80,000
sa Revenue : 80,000
Jin.7, | Receivable (1,000 units x P100) 100,000
ee Contract asset 80,000
Revenue (200 units x P10) 20,000
Jen 9, | Cash 100,000
2 x
tnt | Receivable 100,000278
* Notes:
* Contract asset
TOOf tiles are installed),
is recognized on Dec. 31 (rather
‘receivable’) because ABC Cos right to consideratio
conditioned upon the full installation of the 1,000 roof tiles,
Revenue is recognized as ABC Co. progresses toward;
complete satisfaction of the performance obligation
Receivable is recognized on Jan. 7 because ABC Co. ob:
Ss
Ste ey
mn
thay
is
IS the
(Le, as the
tains an
unconditional tight to consideration as all the roof tiles have
been installed.
£2 Rementter the following:
Scenario
» Consideration is received or
becomes due before goods or
Services are transferred to the
Accounting
- — |
© Recognize a contract lability |
customer,
> Goods or services are
transferred to the customer
before consideration is received:
a. Right to consideration is
conditional.
b. Right to consideration is
unconditional.
@ Recognize a contract asset.
7 Recognize a receivable.
PERS 15 does not prohibit the use of alternative terms for
“contract asset” and “contract liability” so long as sufficient
information is provided to enable users of the financial statements
to distinguish between “receivables” and “contract assets.”
For example, the “Advances from customers” account may
be used in lieu of contract liability when the consideration
received in advance. However, this account cannot be used if te
consideration becomes due (rather than received) before the goo
ion E
or services are transferred to the customer (see Ilustratiot
Scenario B; Jan.31, 20x1 above).
71
|
|
|
|
|
|
|
}
|
iConstruction Contracts
279
Accounting for Construction Contracts
Asummary of the old and current accounting is provided belo
PAS 11 (old standard)
‘An asset is recognized for “unbilled”
accounts receivable when the entity
recognizes revenue that is not yet
billed. Once the customer is invoiced,
the unbilled receivable is reclassified
ag a “billed” accounts receivable. On
the other hand, billings in excess of
costs are recognized as liabilities
PERS 15 (current standard)
Contract asset is recognized when the
entity performs but its right to
consideration is still conditional.
Once the entity's right — to
consideration becomes unconditional
(such as when none but the passage
of time is required before payment is
due), the contract asset is reclassified
as receivable.
More specifically, PAS 11 requires
the entity to present:
a. the gross amount due from
customers for contract work as an
asset; and
b, the gross amount due to customers
for contract work as a liability.
Contract liability is recognized if the
consideration is received or becomes
due before the entity performs.
The excess of (1) costs incurred and
recognized profits, net of losses, over
(2) progress billings represents gross
amount due from customers. The excess
of (2) over (1) represents gross amount
due to customers.
Illustration: Percentage of completion
On Jan. 1, 20x1, ABC enters into a contract to construct a building
for a customer. ABC identifies its performance obligation to be
satisfied over time. ABC uses the input method based on costs to
Measure its progress on the contract. The contract price is POM.
Information on the construction is provided below:
20x1 20x2_| 20x3
ed per year | 2,760,000 | 3,540,000 | 500,000 |
- per year? _ 50% | 30% 20%
£_ Collections on billings per year 90% | balance
d. Estimated costs to complete
4,140,000 | 700,000 2
(at each yr.-end)280 Chapter 7
~~
© The billings per year are stated as percentages of the contract price. The contract,
non-cancellable.
10% retention. “Retention” is
20x2 are net of
at the end of the
d payable to the contractor
cepted.
© The collections on billings in 20x and
an amount withheld by the contractee an
contract when the project is completed and acc
Requirements:
a. Compute for the gross pro!
construction in 20x1, 20x2 and 20x3,
b. Provide the journal entries.
c. Determine the amounts presented in #
fits, revenues and costs of
respectively.
he financial statements.
Solutions:
Requirement (a):
> _Gross profits
20x1 20x2 20x3
9,000,000 _9,000,000° _ 9,000,000
2,760,000 6,300,000 6,800,000
4,140,000 __700,000
6,900,000 _7,000,000__6,800,000
2,100,000 2,000,000 2,200,000
40% 90% 100%
840,000 1,800,000 2,200,000
- (849,000) _(1,800,000)
400,006,
Total contract price
Ya) Costs incurred to date”
Estimated costs to complete
(b) Estimated total contract costs
Expected gross profit
Multiply by: % completion (@) + @
Gross profit earned to date
Less: Gross profit in prior yrs.
Gross profit for the year 840,000 __960,000
“Costs incurred to date’ is the sum of costs incurred in the current year and
previous years. In 20x?, the costs incurred to date is computed as (2 76M
costs in 20x] + 3.54M costs in 20x2) = 6.3M.
y Revenues
20x1 20x2 20x3
Total contract price 9,000,000 9,000,000 9,000,000
Multiply by:% of completion __40%__—90%_W0
Revenue to date 3,600,000 8,100,000 9,00000
“Less: Revenue recognized in prior yrs. = (3,600,000) (8,100,000.
Revenue for the year 3,600,000 4,500,000 9000"
00) (9540,000)_ 60010"
Cost of construction *
“Gross profit for the year — _ 1900 960,000 LE=
nstruction Contracts ve
a _ ; ‘
+ Under the ‘cost-to-cost’ method, the ‘cost of construction’ (contract costs
amortized to expense) is equal to the contract costs incurred in that period.
Alternatively, this can also be ‘squeezed’ after computing the revenue and
gross profit for the year.
4 Notice that billings and collections do not affect revenue, cost of
construction and gross profit.
Requirement (b): Journal entries
> 20x1
a) _Incurrence of cost
Traditional accounting PERS 15
Construction in progress 2.76M Contract costs 2.76M
Cash (orother accounts) __2.76M Cash (or other accounts) __2.76M
“Construction in progress” is an account used to accumulate contract costs
incurred and profits (less losses) recognized to date.
b)_Billing
Traditional accounting PFRS 15
Accounts receivable 45M Receivable 4.5M
Progress billings (9Mx 50%) _4.5M. Contract liability 45M.
“Progress billings” is an account used to record amounts billed for work
Performed on a contract.
©) Collection
Traditional accounting PERS 15
Cash (4.5m x 90%) 4.05M Cash 4.05M
Accounts receivable 4.05M | __Receivable 4.05M
d) Revenue recognition
Traditional accounting PFRS 15
Cost of construction. 2.76M Contract liability 3.6M
Construction in progress 840K® Revenue 3.6M
Revenue 3.6M
Cost of construction 2.76M®
Contract costs 2.76M.282
Chapter 7
a Nas ae ee,
‘equal to the gross profit
As the progress is measured using the ‘cost-to-cost’ method, all Costs incurred ay,
amortized.
> _20x2
Traditional accounting PERS 15)
Construction in progress 3.54M Contract costs 3.54M |
Cash (or other secourts) 354M Cash (orcthereccourts)__3.54M
Accounts receivable 2.7M Receivable oa
Progress billings (Mx 30%|_2.7M Contract liability 2™M
Cash 27M x 90%) 243M Cash 243M
Accounts receivable 2.43M Receivable 243M |
Cost of construction 354M Contract liability 45M ~|
Construction in progress 960K Revenue 45M |
Revenue 45M. |
Cost of constru 354M
Contract costs M
20x3
Traditional accounting PERS 15 |
Construction in progress 5M Contract costs 5M |
Cash (or other accounts) 5M Cash (or other accounts) 5M
‘Accounts receivable 18M Receivable 18M |
Progress billings (9M x20%) 18M. Contract liability 18M |
Cash 252M ©) Cash 252M
Accounts receivable. 2.52M Receivable 252M
Cost of construction 500K Contract liability 900K
Construction in progress 400K Revenue 900K
Revenue 900K
Progress billing OM
Construction in progress
to eliminate the accounts
9M
Cost oF construction 500K
Contract costs 500k
bt:
{10% 01 45M billing in 201) + (10% of 27M billing in 20:2) + 8M billing in 2003 = 252MConstruction Contracts
~ = - 7 283
Requirement (c): Financial statements
Traditional Accounting
Construction in PERS 15
in progress _ ___ Contract costs
2.760.000 [
sit — 3,600,000
Dee
—— 340.000, 3,540,000
— eee poue = |
rain 8,100,000
500,000
400,000
9,000,000
liability
= eats 75,500,000
tees 900,000 22731/x1
4,500,000 e121
7,200,000 12/312
1,800,000
9,000,000
© See ‘Requirement (a)' for revenues and costs of construction.
© The debit balance in the contract liability account on 12/31/x2 is presented as asset.
The year-end adjusting entry is as follows:
Contract asset
Contract liabili
made to simplify the recording in 20x3.
0x2 may also be recorded as follows:
PFRS 15
Contract liability (900K +36M) 3.6M
Contract asset 900K
Revenue
Areversing entry would be:
Alternatively, the revenue in
4.5M_450,000 1,620,000
(Current babies:
Constnction in progress 3,600,000 is
Less: Progress bilings _ 4,500,000
Gross amt due to cust 900,000 =
Total 900,000 =
20x1 2x2 Ud ed + thet tog
Revenue 3,600,009 4,500.00 960,000 |} Reverse 3600,000 4,500,000 21010)
Cost ot construction
[email protected],000) (3.540.000) (500,000) |] Cost of constan. _(2.760,000) (3,540,000) (Stax
Gros prot 0,70) 360000 400,000 || Gree profit 540,000 _ 260,000 a8
OX Shortcut: Under the ‘cost-o-cost’ method, the balance of the CIP account is equa
to the revenue recognized to date
Output methods
Output methods recognize revenue on the basis of direct
measurements of the value to the customer of the goods or services
transferred to date relative to the remaining goods or services
promised under the contract. Examples of output methods:
a. Surveys of performance completed to date
b. Appraisals of results achieved, milestones reached, time
elapsed and units produced or units delivered
The disadvantages of output methods are that the outputs
used to measure progress may not be directly observable and the
information required to apply them may be costly.
The ‘cost-to-cost’ method (input method) of estimatité
stage of completion is the most commonly tested method in
past CPA board examinations. However, in practice, many entitie®
use the output methods. This is normally the-case~in.t
Ue:285
construction of “high-rise” buildings", dams, bridges, and other
structures wherein the incurrence of costs is not necessarily
proportionate to the entity’s progress on the contract. The input
method is more commonly used for non-complex structures, suich
ag roads.
sGeverslly, a “high-rise” building is one that is taller than the maximum height which peo
wiling to walk up; it normally requires an elevator. The threshold for distinguishing, a high
puilding (€.g, number of floors and vertical measurement) varies from country to country. A
alg taller than a high-cse building is called a “skyscraper”
Making the direct measurements under some output
methods require a considerable degree of expertise. In practice,
these are generally determined by experts (e.g., engineers and
architects). A CPA is not expected to be proficient in making those
measurements. A CPA applying an output method would rely on
the expert’s direct measurements.
The different methods of measuring progress result to
different amounts of revenue, costs and profit. Accordingly, PFRS
15 requires the consistent application of a single method for each
performance obligation satisfied over time.
Illustration 1: Output method - Survey of work
Information on an ongoing construction contract with a fixed
contract price of P1M is shown below:
Cost of construction (contract casts recognized as expense) 500,000
Percent complete (based on a survey by a professional) 80%
Requirement: Compute for the gross profit for the year.
Solution:
Total contract price 1,000,000
Multiply by: Percentage of completion 80%
Revenue to date 800,000
Less: Revenue recognized in prior YTS. 2
Revenue for the year 800,000
Cost of construction for the year (given) ____ (600,000)
300,000
Gross profit for the year iMlustration 2: Physical proportion of the contract work
In 20x1, ABC Co. was subcontracted to construct the first Portion,
of a 94.5-kilometer, four-lane expressway. Construction started jy
20x1 and it was expected that the expressway will be opened t,
the public in three years’ time.
Per House Resolution, the total contract price for the first portion
of the expressway consisting of 41 kilometers is P13B. ABC uses
the output method based on physical proportion of contract work
in estimating the stage of completion of a project. Additional
information on the project is shown below:
Costs incurred Estimated costs No. of kilometers
Year each year to complete completed during the year
20x1 2.3B 7.7B 10.25
20x2 5.5B 24B 22.55
Requirement: Compute for the revenue and the cost of construction
recognized as expense in 20x2, respectively.
Solution:
20x1 20x2
No. of kilometers completed to date 10.25 32.80
Divide by: Total kilometers to be completed 41 41
Percentage of completion to date 25% 80%
> Profits:
20x1 2072
Total contract price 13B 138
_Estimated total contract cosis* (108) 2028)
Expected total profit from construction 3B 2.6B
Multiply by: %ofcompletion | 25% OH
"Profit to date 0.738 2248
Profit for the year 0.75B 1.498
a online’ |construction Contracts : 287
* Estimated total coniract costs are equal to the costs incurred to date plus
estimated costs to complete at each year-end. These are computed as follows:
- 20x1: (2.3B + 7.7B) = 10B
= 2032: (2.38 + 5.5B + 2.48) = 10.28
» Revenues and Costs of constructio
20x1 20x2
Total contract price s 13B 13B
Multiply by: % of completion 25% 80%
Contract revenue to date 3.258104
Contract revenue recognized in prior years : (3.25B)
Contract revenue for the year 3.25B 7.15B
Cost of construction (squeeze) (Q2.5B)___(5.66B)
Profit for the year 0.75B 1.49B
4 Unlike the cost-to-cost method, under the output method, the cost of
construction is not equal to the actual costs incurred in that period.
Changes in the measure of progress
The measure of progress is updated as circumstances change over
time to reflect any changes in the outcome of the performance
obligation. Changes are accounted for prospectively as changes in
accounting estimate in accordance with PAS 8 Accounting Policies,
Changes in Accounting Estimates and Errors.
Reasonable measures of progress
Revenue for a performance obligation satisfied over time is
tecognized only if the progress towards the complete satisfaction
of the performance obligation can be reasonably measured.
If the outcome of a performance . obligation cannot be
Teasonably measured, revenue is recognized only to the extent of
costs incurred that are expected to be recovered.
This accounting method is traditionally called the “zero-
profit” method. There is zero profit because the revenue recognized
is equal to the costs incurred,Illustration: Zero-profit method
Information on a construction contract with a contract price of
POM is provided be!
pam ET els
| 20x17 | 2032 20x3
a. Contract costs incurred per y' { 2,760,000 | 3,540,000 500,00)"
b. Estimated costs to complete | jap measurable | not measurable,
(at each yr.-end) | |
Requirements:
a. Compute for the 20x1, 20x2 and 20x3 revenues.
b. Provide the journal entries in 20x1 assuming billings were 50%,
of the contract price and collections were 90% of the billings.
Solutions: |
Requirement (a):
20x1 20x2 20x3
Revenue 2,760,000 3,540,000 — 2,700,000
Contract costs incurred per yr. (2,760,000) (3,540,000) (500,000)
Gross profit for the year * > 2,200,000
& Notes:
® Prior to completion (ie, 20x1 and 20x2), the revenues
recognized are equal to the contract costs incurred.
Accordingly, no gross profits are recognized during these
years.
On completion (ic, 20x3), the revenue recognized. is the
excess of the contract price over the revenues recognized it
prior years: (9M contract price - 2.76M revenue in 20xl -
3.54M revenue in 20x2 = 2.7M).
* Gross profit is recognized only in the year of completion.
Requirement (b): Journal entries ~20x1 only
Traditional accountin PERS 15
Construction in progress 2.76M | Contract costs 276M
| __Cash (or other account 276M | Cash (orother accounts) 276+
Accounts receivable Receivable 45M
Progress billings OM@sO%)PE5M=| (= /Contractliability ass
latesConstruction Contracts 89
Cash (45x 90%) 4.05M Cash 4.05M
Accounts receivable 4.05M Receivable 4.05M.
Cost of construction —_2.76M Contract liability -2.76M
Revenue 2.76M Revenue 2.76M
Cost of construction 2.76M
Contract costs 2.76M
The 20x1 financial statements will show the following:
Statement of financial position
PFRS 15
Current assets: 20x41
Receivable
Total , Total 450,000
Current liabilities: Current liabilities:
Construction in progress 2,760,000 |} Contract liability 1,740,000
Less: Progress billings 4,500,000
Grossamt. due to cust. 1,740,000
Total
Onerous contract (Expected losses)
PAS 11 (old standard) PERS 15 (current standard)
When it is probable that total | As soon as a contract ‘becomes,
contract costs will exceed total | onerous, an entity recognizes a
contract revenue, the expected loss is provision for the loss it expects to
recognized immediately as expense. incur on the contract in accordance
with PAS 37 Provisions, Contingent
Liabilities and Contingent Assets.
An onerous contract is “a
contract in which the unavoidable
cosis_of_meeting the obligations290 _—_Shapters
eo s
under the contract exceed” jo
economic benefits expected to 4,
received under it.” (PAS 37 Appas.a,
" ity’ ate
‘The amount of loss is determined irrespective of the entity’s progress on ih.
contract,
Illustration 1: Onerous contract .
In 20x1, ABC Co, started work on a PIM fixed price contrag,
Information on the construction is shown below:
20x1 20x2
> S
Costs incurred to date 200,000 825,000
Estimated costs to complete 600,000 275,000
Requirement: Compute for the loss in 20x2.
Solution:
The contract is analyzed as follows:
: 20x1 20x2
Total contract price 1,000,000 1,000,000
Costs incurred to date 200,000 825,000
Estimated costs to complete 600,000 275,000.
Estimated total contract costs 800,000 1,100,000
Expected total profit (loss) on completion 200,000 (200,000)
The contract becomes onerous in 20x2 as the estimated
total contract costs exceed the contract price. The loss recognized
in 20x? is determined as follows:
20x17 20x2
Total contract price 1,000,000 1,000,000
Estimated total contract costs (800,000) (1,100,000)
Expected total profit (loss) on completion 200,000 (100,000)
Multiply by: percentage of completion 25% 0) NIA
Profit (loss) to date 50,000 (100,000)
Profit (loss) recognized in prior yrs. = (60,000)
Profit (loss) for the year 50,000 (150,000)
( @O00K costs incurred to date + 800K estimated total contract costs) = 25%E
struction Contracts =
onsracio Conaeg
«NIA = the progress in 20x2 is ignored so that the P100,000 loss is
recognized in full.
‘The P50,000 profit recognized in 20x1 not restated. Thus, to reflect the
expected total loss on the contract of P100,000, P150,000 loss is
recognized in 20x2 (ie, 50K profit in 20x1 - 150K loss in 20x2 = 100K loss to
date).
The amounts recognized in profit or loss are computed as follows:
20x1 20x2
Total contract price 7,000,000 1,000,000
Multiply by: percentage of completion 25% 75%
Revenue to date 250,000 750,000
Revenue in prior years sk (250,000)
Revenue for the year 250,000 500,000
Costs of construction (200,000) (625,000) ®
Gross profit (loss) for the year 50,000 (125,000)
Loss on onerous contract = + (25,000)
Profit (loss) for the year 50,000 _(150,000)
©) 26x2: (825K costs incurred to date ~ 1.1M estimated total contract costs) = 75%
©) 20%2: (825K costs incurred to date ~ 200K costs incurred in 20x1) 625,000
squeezed’ (150K loss for the year - 125K gross loss) = 25K loss provision
> Journal entries: (Billings and Collections are ignored)
20x1 *
Traditional accounting -___PFRS 15
Construction in progress 200K Contract costs 200K
Cash (or other accounts) 200K Cash (or other accounts) 200K
Cost ofconstruction 200K Contract asset 250K
Construction in progress 50K Revenue 250K
Revenue 250K
Cost of construction 200K
Contract costs 200K
ue
re _ Traditional accounting PFRS 15,
| Construction in progress 625K Contract costs 625K
res (or ther accounts) 625K Cash (or other accounts) 625K
le of construction 625K Contract asset 500K
eston a Revenue 500K
aqe ees, Pe Rem sr ae
292
Chapter
So,
oe Sean?
Pet OS eS lt ee
Revenue BOOK ~
Construction in progress 150K
Cost of construction 625K
Contract costs 625K |
Loss on onerous contract 25K} |
Provision 2K
> Financial statements
Statement of financial position
i
i
|
)
|
Gross amt. due o cut. 250000 7255000.
Toe 250,000 725,000. || Total
Current liabilities:
Revere
‘Cost of construction,
Cro low
Loss on uncompleted contract
Profit (los) for the yeer
Illustration 2: Reversal of provision (Continuation of Illustration 1)
The contract is completed in 20x3.
20x1 20x2 20x3
Costs incurred to date 200,000 825,000 1,020,000
Estimated costs to complete 600,000 275,000 -
Requirement: Compute for the profit (loss) in 20x3.
Solution:
The contract is analyzed as follows:
20x1 20x2 20x3
“ Costs incurred to date 200,000 825,000 1,020,000
Estimated costs to complete. 600,000 275,000 .
veal-
Cons!
rruction Contracts 293
Estimated total contract costs 300,000 1,100,000 1,020,000
“Exped pected tel profit loss) on completion 200,000 __ (100,000) _ (20.000)
The actual total loss on the contract is P20,000. The profit
recognized in 20x3 is determined as follows:
20x1 20x2 20x3
Total contract price 1,000,000 1,000,000 1,000,000
Estimated total contract costs (800,000) (1,100,000) _ (1,020,000)
Expected total profit (loss) 200,000 (100,000) (20,000)
Multiply by: % of completion 25% N/A 100%
Profit (loss) to date 50,000 (100,000) (20,000)
Profit (loss) in prior yrs. ¥ (50,000) 100,000
Profit (loss) for the year 50,000 __(150,000) 80,000
@ The profit and loss recognized in 20x1 and 20x2 are not restated. Instead,
{o reflect the total loss on the contract of P20,000, P80,000 profit is
recognized in 20x3 (.,50K profit in 20x1.- 150K loss in 20x2 + 80K profit in 203
+= 20K total loss on contract).
The amounts recognized in profit or loss are computed as follows:
20x1 20x2 20x3
Total contract price 1,000,000 1,000,000 1,000,000
Multiply by: % of completion 25% 75% 100%
Revenue to date 250,000 750,000 1,000,000
Revenue in prior years - (250,000) (750,000)
Revenue for the year 250,000 500,000 250,000.
Costs of construction (200,000) (625,000) (195,000) »
Gross profit (loss) for the year 50,000 (125,000) 55,000
Loss on onerous contract és (25,000) -
Gain on reversal of provision 25,000
Profit (loss) for the year 50,000 (150,000) 80,000
102M costs incurred to date in 20x3 - 825K costs incurred to date in 20x2 = 195K
> Journal entries: (Billings and Collections are ignored)
203
| Traditional accounting
| Construction in progress 195K
La Cash ther acon
bhCost of construction 198K] Contract asset
Construction in Progress 80K Revenue 0K |
Revenue 250K |
Gain on completed contract 25K i
Cost of construction 195K 1
Contract costs 195K
Provision 25K |
Gain on reversal of provision 25,
Mlustration 3; Onerous contract: Zero-profit method
In 20x1, ABC Co. started work on a PIM fixed price contract,
Information on the construction is shown below:
20x1 202 20x3
Costs incurred to date 200,000 825,000
1,020,000
© In 20x1, ABC Co. cannot reasonably measure the outcome of
the performance obligation but expects to recover all contract
costs.
© In 20x2, ABC estimates the total contract Costs to be P1,100,000.
* The contract is completed in 20x3 for a total cost of P1,020,000.
Requirement: Compute for the profit (loss) in 20x1, 20x2 and 200,
respectively.
Solution:
The contract is analyzed as follows: |
20x1 20x2 20:3
Contract price 1,000,000 1,000,000 1,000,000
Contract costs N/A 1,100,000 1,020,000.
Expected profit (loss) N/A 200,000} (20,000),
The contract becomes onerous in 20x2. The profits (losses)
are determined as follows:
20x1 20x2 20x3
Revenue 200,000 625,000 175,000
_Contract costs incurred per yr. (200,000) (625,000) (195,000.
Gross profit for the year : - (20,000)
aletruction Contracts -
Cons itracts: +05
Loss on onerous contract (100,000)
Gain on reversal of provision
Profit (loss) for the year (100,000)
& Notes:
@ The revenues recognized in 20x1 and 20x2 are equal to the
contract costs incurred in those periods.
# The revenue recognized in 20x3 is computed as: 1M contract
price ~ 200K revenue in 20x] ~ 625K revenue in 20x2 = 175,000.
© Reconciliation: 0 profit in 20x1 - 100K loss in 20x2 + 80K profit in 20x3 =
-20K total loss on contract
Variable consideration
If the consideration includes a variable amount, the entity shall
estimate the amount to which it will be entitled in exchange for
transferring the promised goods or services to the customer.
The amount of consideration can vary because of discounts,
rebates, refunds, credits, price concessions, penalties, incentives,
performance bonuses, or other similar items. It can also vary if the
entity’s entitlement to the consideration is contingent on the
occurrence or non-occurrence of a future event.
The variability of consideration may be explicitly stated in
the contract or implied by the entity's customary business
practices, published policies, specific statements, or by other facts
and circumstances.
The amount of variable consideration is estimated using
either of the following methods, depending on which method is
expected to better predict the amount to which the entity will be
entitled:
a. Expected value
range of possible amount
entity has a large nu
characteristics. | ;
che single most likely amount in a range of
b. Most likely amount ~ 1 a
possible amounts. This may be appropriate when there are
— the sum of probability-weighted amounts in a
ts. This may be appropriate when the
mber of contracts with similaraM
Chapter
296
ll.
only two possible outcomes (for example, an entity ithe
achieves a performance bonus or does not).
Constraining estimates of variable consideration
The estimated amount of variable consideration is included jn the
transaction price only to the extent that it is highly probable that,
significant reversal in the amount of cumulative revenue
Tecognized will not occur when the uncertainty associated with
the variable consideration is subsequently resolved.
Example 1: Penalty
A construction contract states a Price of PIM. However, a penalty
of P100,000 will be charged if the construction is not completed
Within two months from the agreed date of completion.
* Analysis:
The consideration includes a fixed amount of 900,000 and a
variable amount of P100,000.
Constraining estimates of variable consideration:
‘The entity determines the probability of the Penalty being charged
and includes the variable consideration (and thus a transaction
price of PIM) only if itis highly probable that the penalty will not
be charged.
Example 2: Estimating variable consideration
A construction contract states a price of PIM. However, for each
day that completion is delayed after the deadline, the contract
price decreases by P1,000, whereas for each day that the
completion is earlier than the deadline, the contract price increas?
by P1,000.
In addition, upon completion, a third party will inspect the asset
and assign a rating based on metrics defined in the contract. If 4 |
specified rating is met, the entity will receive a bonus of P20,000._J
age.
Construction Contre
297
Analysis:
The consideration includes a fixed amount of PIM and a variable
amount, which the entity needs to estimate using the methods
described earlier. The entity makes separate estimates for each of
the components of the variable amount. For example, the entity
uses:
a. the expected value method to estimate the variable consideration
associated with the daily penalty or incentive because there
can be a range of possible amounts (i.e, P1M plus or minus
P1,000 per day); and
b. the most likely amount to estimate the variable consideration
associated with the incentive bonus because there can only be
two possible outcomes (i.e., +P20,000 or +P0)
After making the estimate, the entity considers the
requirements on constraining estimates of variable consideration to
determine whether all or part of the estimate should be included
in the transaction price.
Incentive payments.
Incentive payments are additional amounts paid to the contractor
if specified performance standards are met or exceeded. For
example, a contract may allow for an incentive payment to the
contractor for early completion of the contract.
Incentive payments are inchided in the transaction price,
and consequently to contract revenue when, in applying the
constraining estimates of variable consideration principle, it is
highly probable that a significant reversal in the amount of
cumulative revenue recognized will mot occur when the
Uncertainty associated with the variable consideration is
Subsequently resolved.
Mlustration: Incentive payment
ABC Co. started work on a construction contract in 20x1. The
“ontract provides for a P400,000 bonus if the building is completed
ae298
el
_ Chapte
within 4 years. ABC Co. uses the ‘cost-to-cost’ Methog i
. in
measuring its progress on the contract. Information on the Projeq,
is as follows:
Pere hl ttc es
20x1 2032393
Costs incurred to date 1,000,000 1,960,000 4,160 p99
Estimated costs to complete 4,000,000 2,940,000 — L,04g 09) |
* In 20x1 and 20x2, it is not highly probable that the |
Construction will be completed within the 4-year limit, j
* In 20x3, ABC Co, acquired new equipment and employed
additional Personnel. This has fast-tracked construction work,
ABC Co. now believes it is highly probable that the
construction will be completed within the 4-year limit.
Case 1: Fixed price contract |
Compute for the revenues in 20x1, 20x2 and 2
0x3, respectively,
assuming the contract price is P6M.
Solution:
20x1 20x2 20:3
Total contract price @ 6,000,000 6,000,000 _ 6,400,000 I
Costs incurred to date 1,000,000 1,960,000 4,160,000
Estimated costs to complete 4,000,000 2,940,000 1,040,000
Estimated total contract costs 5,000,000 4,900,000 5,200,000
Expected gross profit 1,000,000 1,100,000 _ 1,200,000
Multiply by: % of completion @ 20% 40% 80%
Gross profit earned to date 200,000 440,000 960,000
Less: Gross profit in prior yrs, (200,000) _ (440,000)
Gross profit for the year 200,000 240,000 520,000
‘2 The bonus is included in the transaction price only in 20x3 when i
that the bonus will be received: (5M contract price + 400,000 bowne
400,000).
2% of completion = Costs incurred to date « Estimated total contract costs
20x14 20x2 20x3
Total contract price 6,000,000 6,000,000 6,400,000
Multiply by: % of completion 20% 40% Ee
Revenue to date 1,200,000.2,400,000.25,120.00Y
onstruction Contracts soo
comiratinmimets
eer the yer 1,200,000 1,200,000 2,720,000
Cost of construction (qweze) (1,000,000) (960,000) (2,200,000)
Gross profit for the year M00) es) Bann)
Case 2: Cost-plus-variable fee
Compute for the revenues in 20x1, 20x2 and 20x3, respectively,
assuming the contract price is set as ‘cost plus 20%’. |
Solution:
20x1 20x2 20x3
Costs incurred to date 1,000,000 1,960,000 4,160,000
Estimated costs to complete 4,000,000 2,940,000 __ 1,040,000
Estimated total contract costs 5,000,000 4,900,000 5,200,000
Multiply by: Cost + Variable fee 120% 120% 120%
Total 6,000,000 5,880,000, 6,240,000
Incentive payment 400,000
Estimated total contract price 6,000,000 5,880,000 6,640,000
Multiply by: % of completion 20% 40% 80%
Revenue to date 1,200,000 2,352,000 5,312,000
Less: Revenue in prior yrs = (1,200,000) _ (2,352,000)
Revenue for the year 1,200,000 1,152,000 2,960,000
Cost of construction &! (1,000,000) (960,000) (2,200,000)
Gross profit for the year 200,000 __192,000___760,000
equal to costs incurred per yr.: (20x1: 1M); (20x2: 1.96M - 1M = .96M); (20x3: 4.16M —
196M =2.2M)
Additional concept:
Under a “cost plus a certain percentage of costs,” the gross profit rate based on
Cost remains relatively constant from period to period.
20x1 20x2 20x3
aE
Gross, profit 200,000 192,000 440,000
ess profit rate 20% 20% 20%
“TOOK gross profit including bonus ~ (400K bonus x 80% completion) = 440,000
a300 oe ee ta
following reconciliation:
we can make the Fe a:
Using the concept above,
dee ___
4,900, 5,2
Estimated total contract costs Soe pest i 0
Multiply by: Gross profit rate = rs
Total 1,000,000 980,000 1,040.97
. 4000 |
Incentive payment 00 |
000,
Estimated total gross profit 1,000,000 os 440,00 |
Multiply by: % of completion 20% b 809,
Gross profit to date 200,000 392,000 1152000
|
Less: Gross profit in prior yrs. ~__ (200,000) (392.000) |
200,000, 192,000 760,000
Gross profit for the year
Cost of construction 1,000,000 960,000 2,200,009 |
Revenue for the year 1,200,000 1,152,000 2,960,000 |
Case 3: Cost-plus-fixed fee if
Compute for the revenues in 20x1, 20x2 and 20x3, respectively, |
assuming the contract price is set as ‘cost plus PIM’. |
Solution:
20x1 20x2 20x3
Costs incurred to date 1,000,000 1,960,000 4,160,000
Estimated costs to complete 4,000,000 2,940,000 _ 1,040,000
Estimated total contract costs 5,000,000 4,900,000 5,200,000 |
Fixed fee 1,000,000 1,000,000 1,000,000
Incentive payment 400,006
Estimated total contract price 6,000,000 5,900,000 6,600,000
Multiply by: % of completion 20% 40% 80%
Revenue to date 1,200,000 2,360,000 5,280,000
Less: Revenue in prior yrs = (1,200,000) _ (2,360,000)
Revenue for the year 1,200,000 1,160,000 2,920,000
Cost of construction (1,000,000) (960,000) _ (2,200,000)
Gross profit for the year 200,000 200,000 720,000, |
Optional reconciliation: |
ae
Fixed fee 1,000,000 1,000,000 1,000,"
Incentive payment _ sont |
Estimated total gross profit 1,000,000 1,000,000 7,400,008 |
Ke|
syuttiply by: % of completion 20% 40% 80% _
fit to date 200,000 1,120,000
(Gross pro! 400,000
_ tas Gross profitin prior yrs. __00,0n0)_{ann.eer
Gross profit for the year 200,000 200,000 720,000
costo‘ construction _1.000,000__990,000_2,200600.
Revenue for the year 1,200,000 1,160,000 __2,920,00
Cost escalations
‘A cost escalation is a contractual provision that stipulates an
increase in the contract price in the event of an increase in certain
costs. For example, an escalation clause may specify that the
contract price will increase with inflation to safeguard the
contractor from price changes in materials and labor. Escalation
dauses are normally expressed as a percentage of an originally
contracted amount. The opposite of an escalation clause is de-
escalation clause. .
‘An escalation is included in (or a de-escalation is excluded
from) the transaction price when, in applying the constraining
estimates of variable consideration principle, it is highly probable
that a significant reversal in the amount of cumulative revenue
recognized will not occur when the uncertainty associated with
the variable consideration is subsequently resolved.
Illustration: Cost escalation
ABC Co. started work on a construction contract in 20x1. The
contract price is PIM; however, this will increase by 5% if the
cumulative inflation rate exceeds 6%. Information on the project is
as follows: 5
et Pees AO a as
Costs incurred to date 224,000 518,000
Estimated costs to complete 476,000 222,000
Cumulative inflation rate 4.95% 6.73%
Requirement: Compute for the gross profit recognized in 20x2.
Solution:302
— ee ee ee
(@) Costs incurred to date 224,000 518,009
——Estimated costs to complete _476,000_222,09)
(b) Estimated total contract costs 700,000 )
Expected gross profit (loss) 300,000 310,009
—Multiply by: % of completion «+ _32% _7vy |
Gross profit (loss) to date 96,000 217,009 >
Gross profitin prioryears = (96,000)
Gross profit (loss) for the year 96,000___ 127,00) ~
“1M initial contract price x 105% = 1,050,000
Contract modifications
A contract modification is a change in the scope and/or price of :
contract that is approved by the contracting parties, in writing
orally or implied by customary business practices. Similar term;
are “change order,” “variation” and “amendment.”
If the contract modification is not approved, the entity
shall continue to apply PFRS 15 to the existing contract until the
modification is approved.
A contract modification may exist even though the
contracting parties have a dispute about the scope and/or priceo!
the modification or the change in the scope has been approved but
the corresponding change in price is not yet determined. In the
latter case, the entity shall estimate the change to the transaction
price arising from the modification.
A contract modification is accounted for as a separat?
contract if both of the following conditions are met:
a. The scope of the contract increases because of the addition & |
promised goods or services that are distinct; and
b. The contract price increases by an amount that reflects
stand-alone selling prices of the additional promised goods”
services.truction Contracts
a 303
A contract modification that is not accounted for as a
separate contract is accounted for as follows:
» Ifthe additional goods or services are distinct but the increase
in the contract price does not reflect the stand-alone selling
price, the contract modification is accounted for as if it were a
termination of the existing contract and the creation of a new
contract.
Accordingly, the sum of (a) the consideration from the
original contract that is not yet recognized as revenue and (b)
the consideration from the contract modification shall be
allocated to all of the remaining performance obligations.
> If the additional goods or services are not distinct, they are
essentially a part of a single performance obligation that is
only partially satisfied. Therefore, the contract modification is
accounted for as if it were a part of the existing contract.
Accordingly, the effect of the contract modification on
the transaction price, and on the entity’s measure of progress
towards complete satisfaction of the performance obligation,
is recognized as an increase or decrease in revenue at the date of
the contract modification. The adjustment to revenue is made
ona cumulative catch-up basis.
2 Summary of concepts:
A contract modification is accounted for:
a. Asa separate contract if the modification results to additional goods or
services that are distinct and the modified contract price reflects the
stand-alone selling prices of those additional goods or services.
nt for the existing contract “as is” and
The entity continues to accou!
as a new and separate contract.
accounts for the modification
termination of the existing contract and the
¢ the additional goods or services are distinct
does not reflect the stand-alone selling
b. As if the modification is a
creation of a new contract i}
but the modified contract price
prices of those additional goods or services.
on-prive from the original_contract plus the
%_ ‘The batan/
Chapter
‘ation from the modification is
Performance obligations.
allocated 10 the tema
© AS if the modification is a part of the existing contract if the Addition,
00d or services are not distinct.
3 The effect of the modification is accounted for as a prospectiyy catch
up adjustment to revenue.
(
Variations on the contract (Change orders)
A variation is an instruction by the customer for a change in the
Scope of the work to be performed under the contract.
Examples of variations;
1. Changes in the specifications or design
2. Changes in the scope of work
3. Changes in the duration of the contract
4. Renegotiations on the originally agreed contract price
Changes in the transaction Price
After contract inception, the transaction Price can change for
various reasons, including the resolution of uncertain events.
A subsequent change in the transaction Price, arising from
other than a contract modification, shall be allocated to the
performance obligations based on the relative stand-alone prices
of the distinct goods at contract inception. Accordingly,
subsequent changes in stand-alone selling prices are ignored.
Amounts allocated to a satisfied performance obligation shall be
recognized as revenue, or as a reduction of revenue, in the period
in which the transaction price changes. :
A subsequent change in the transaction price shall be
allocated to all of the performance obligations in the contra¢
unless it is clear that it relates only to a specific part of the
contract.
A change in the transaction Price after a contrat
modification is accounted for as follows: