Volume-2a Roads Work Specifications (Final)
Volume-2a Roads Work Specifications (Final)
REPUBLIC OF TANZANIA
PROJECT – PHASE 4
FOR
BIDDING DOCUMENT
VOLUME II-A
MAY, 2021.
Section VI. Works Requirements
Contents
Section VI 1 Scope of Works
Section VI 2 Specifications
Section VI 3 Drawings Bound In Separate Volumes i.e. 3A – 3D
Section VI 4 Suplementary Information
Section VI (1) - Scope of Works
The Government of the United Republic of Tanzania has received loans from the WB to
finance the Dar es Salaam Bus Rapid Transit (BRT) System Project – Phase 4. The
Tanzania National Roads Agency (TANROADS), an Agency of the Ministry of Works,
Transport and Communication intends to apply a portion of the proceeds of this loan to
eligible payments under the contract for which this Invitation for Bids is issued.
The project involves the construction of BRT infrastructure along Bibi Titi Mohamed road
from Maktaba Street junction to Ohio Street junction (0.23km), Ali Hassan Mwinyi road
(from the junction of Ohio Street to Mwenge) (10.22 km), New Bagamoyo Road from
Mwenge -Tegeta (DAWASA Daladala Bus Station) (16 km) and a spur on Sam Nujoma
Road from its junction with New Bagamoyo Road to Ubungo junction (4 km).
The works in all stretches will involve constructing two BRT lanes in the right of way
provided in the center of existing mixed traffic lanes with, bicycle lanes and pedestrian
walkways and service roads will be constructed in some sections where the road corridor
is sufficient.
The entire Phase 4 trunk system of 30.45 kilometres will be built along the middle of
existing roads. The average distance between bus stops will be 300m to 800m and
system users will be encouraged to either walk or bicycle to the bus stops (privately
operated bicycle parking facilities are planned at each bus stop).
Scope of work
Construction of 30.45 km of BRT Phase 4 roads and non-motorized lanes on the
periphery of the motor lanes, together with associated storm water sewer system:
BRT Phase 4 infrastrcure 30.45km cover the following;
• Bibi Titi Mohamed road from Maktaba Street junction to Ohio Street junction
(0.23km),
• Ali Hassan Mwinyi road (from the junction of Ohio Street to Mwenge) (10.22 km),
• New Bagamoyo Road from Mwenge -Tegeta (DAWASA Daladala Bus Station)
(16 km) and
• A spur on Sam Nujoma Road from its junction with New Bagamoyo Road to
Ubungo junction (4 km).
• Construction of 43 bus stations, 3 Deport, 2 Terminals and 21 feeder stations
along the project roads.
Construction of 4 Pedestrian Bridge (pedestrian flyover)
Solar street lighting
Solar traffic signals at intersections
Widening of existing cross drainage structures
18 Kerbs m 366,000
20 Piling m 4,104
22 Feeder Stations No 21
Figure 1: Location of BRT Phase 4 System
i
Specifications
The Standard Specifications shall be those forming the “Standard Specification for
Road Works 2000” prepared by the Ministry of Works (now the Ministry of Works,
Transport and Communication), Tanzania. The Standard Specifications are subject to
the variations and additions set out in Part 2, hereto entitled “Special Specifications”.
ii
Section VI: 2A-1 :Standard Specifications for Roadworks
The Standard Specifications shall be the "Standard Specification for Road Works
2000" as published by the Ministry of Works of the United Republic of Tanzania in
June 2000.
These Standard Specifications are not reproduced in this Volume, as they are
protected by copyright. However, a copy may be obtained from:
iii
Section VI: 2A-2: Special Specifications for Roadworks, Street lighting and
traffic signs
iv
TABLE OF CONTENTS
............................................................................................................................................................. 1
Section VI: 2A-1: Standard Specifications for Roadworks ........................................... ii
Section VI: 2A-2Special Specifications for Roadworks, Street lighting and
traffic signs ........................................................................................... ii
Section VI: 2A-3: Specifications for Relocation of Water pipelines along BRT 4 ......... ii
Section VI: 2A-4: Specifications for Duct PVC And Duct Jointing Compound
and ..................................................... Polyethylene Cables for External Use ii
Section VI: 2A-5: Technical Field Requirements and Specifications for
Relocation of ..................................................................................... Powerlines ii
Section VI: 2A-6 Specifications for Building Works (Bus and Feeder stations) ......... ii
Section VI: 2A-1 :Standard Specifications for Roadworks ........................................... iii
Section VI: 2A-2: Special Specifications for Roadworks, Street lighting and
traffic signs .......................................................................................... iv
1100 DEFINITIONS AND TERMS .............................................................. 25
1167 ADDENDUM ...................................................................................... 25
1168 DITCH OR OPEN DRAIN .................................................................. 25
1169 EMPLOYER ....................................................................................... 25
1170 ABBREVIATIONS .............................................................................. 25
1200 GENERAL REQUIREMENTS AND PROVISIONS ............................ 30
1202 SERVICES ......................................................................................... 30
1204 PROGRAMME OF WORKS AND TEMPORARY WORKS ................ 30
1207 NOTICES, SIGNS AND ADVERTISEMENTS .................................... 30
1209 METHODS OF PAYMENT ................................................................. 30
1224 THE HANDING OVER OF THE SITE ................................................ 31
1227 ACCESS TO CONTRACTOR'S RECORDS, MONTHLY SITE
MEETINGS AND PROGRESS PHOTOGRAPHS .............................. 31
SS12.21 Provision of As-Built drawings:........................................................... 32
SS12.40 Dispute Board (DB): ........................................................................... 33
1300 CONTRACTOR'S ESTABLISHMENT ON SITE AND GENERAL
OBLIGATIONS ................................................................................... 33
1302 GENERAL REQUIREMENTS ............................................................ 33
1303 CONTRACTOR'S OFFICES, STORES, WORKSHOPS,
CAMPS ETC. ..................................................................................... 34
1400 ENGINEER'S ACCOMMODATION AND ATTENDANCE UPON
ENGINEER AND HIS SITE PERSONNEL ......................................... 35
1402 FACILITIES FOR THE ENGINEER.................................................... 35
1403 HOUSES FOR THE ENGINEER ....................................................... 35
1404 OFFICE FOR THE ENGINEER ......................................................... 35
v
1407 VEHICLES FOR THE ENGINEER ..................................................... 41
1409 PROVISION OF SURVEY EQUIPMENT ........................................... 42
1410 LABORATORY FOR THE ENGINEER .............................................. 43
1412 MEASUREMENT AND PAYMENT .................................................... 48
1500 ACCOMMODATION OF TRAFFIC .................................................... 50
1502 GENERAL REQUIREMENTS ............................................................ 50
1503 TEMPORARY TRAFFIC-CONTROL FACILITIES.............................. 50
1504 CONSTRUCTION OF DEVIATIONS.................................................. 50
1507 GRAVELLING OF DEVIATIONS OR EXISTING ROADS USED
AS DEVIATIONS ............................................................................... 51
1510 RIDING QUALITY AND MAINTENANCE OF DEVIATIONS
AND EXISTING ROADS USED AS DEVIATIONS ............................. 51
1512 ACCOMMODATION OF TRAFFIC WHERE THE ROAD IS
CONSTRUCTED IN HALF WIDTHS .................................................. 51
1600 OVERHAUL ....................................................................................... 52
1700 ENVIRONMENTAL PROTECTION AND WASTE DISPOSAL ........... 52
1700.01 Restriction on Depth and Spacing of Borrow Pits and Quarry
site ..................................................................................................... 52
1702 GENERAL .......................................................................................... 53
1703 LANDSCAPE PRESERVATION ........................................................ 53
1704 TEMPORARY SOIL EROSION CONTROL ....................................... 54
1705 PRESERVATION OF TREES AND SHRUBBERY ............................ 54
SS1715 OCCUPATIONAL HEALTH AND SAFETY HSMP ............................. 54
vi
2602 MATERIALS....................................................................................... 69
2603 CONSTRUCTION OF GABION CAGES ............................................ 71
3000 EARTHWORKS & PAVEMENT LAYERS OF GRAVEL OR
CRUSHED STONE ............................................................................ 71
3100 CLEARING, GRUBBING AND REMOVAL OF TOPSOI .................... 71
3102 DESCRIPTION OF WORKS .............................................................. 71
3400 BORROW PIT AND QUARRY ACQUISITION AND
EXPLOITATION ................................................................................. 71
3402 NEGOTIATIONS WITH LANDOWNERS, AUTHORITIES AND
LEGAL OCCUPANTS OF LAND ....................................................... 71
3404 OBTAINING BORROW OR QUARRIED MATERIALS ...................... 71
3405 OPENING AND WORKING BORROW PITS ..................................... 72
3500 SELECTING AND UTILISING MATERIAL FROM BORROW
PITS AND CUTTINGS ....................................................................... 72
3506 COMPACTION OF MATERIALS ....................................................... 72
3600 EARTHWORKS ................................................................................. 74
3601 SCOPE .............................................................................................. 74
3602 MATERIALS....................................................................................... 75
3604 PREPARATION OF ROADBED ......................................................... 75
3605 EMBANKMENTS ............................................................................... 75
3610 MEASUREMENTS AND PAYMENT .................................................. 75
3700 PAVEMENT LAYERS OF NATURAL GRAVEL ................................. 76
SS.3705 Maintenance of Existing Roads .......................................................... 76
3800 STABILISATION ................................................................................ 76
3802 MATERIALS....................................................................................... 76
3803 CONSTRUCTION .............................................................................. 79
3804 CONSTRUCTION TOLERANCES ..................................................... 86
3805 MEASUREMENT AND PAYMENT .................................................... 88
3900 CRUSHED AGGREGATE BASE COURSE ....................................... 89
3901 SCOPE .............................................................................................. 89
3902 MATERIALS....................................................................................... 89
3903 CONSTRUCTION .............................................................................. 90
4000 BITUMINOUS LAYERS AND SEALS ................................................ 91
4102 MATERIALS....................................................................................... 91
4105 PREPARATION OF THE LAYER TO BE PRIMED OR TO
RECEIVE A CURING MEMBRANE ................................................... 92
4106 APPLICATION OF THE PRIME COAT OR CURING
MEMBRANE ...................................................................................... 92
4107 MAINTENANCE AND OPENING TO TRAFFIC ................................. 93
vii
4108 TOLERANCES ................................................................................... 93
4110 MEASUREMENT AND PAYMENT .................................................... 93
4200A BITUMINOUS BASE COURSE AND ASPHALT CONCRETE
SURFACING ...................................................................................... 93
4201A SCOPE .............................................................................................. 93
4202A MATERIALS....................................................................................... 94
4203A COMPOSITION OF MIXTURES FOR BITUMINOUS BASE
COURSE AND SURFACING ............................................................. 98
4204A PLANT AND EQUIPMENT............................................................... 100
4205A GENERAL LIMITATIONS AND REQUIREMENTS AND THE
STOCKPILING OF MIXED MATERIAL ............................................ 101
4206A PRODUCING AND TRANSPORTING THE MIXTURE .................... 101
4207A SPREADING THE MIXTURE ........................................................... 102
4208A JOINTS ............................................................................................ 102
4209A COMPACTION ................................................................................. 103
4211A LAYING TRIAL SECTIONS ............................................................. 103
4213A TESTING ......................................................................................... 105
4214A MEASUREMENT AND PAYMENT .................................................. 106
4200B RIGID PAVEMENT .......................................................................... 107
4201B SCOPE ............................................................................................ 107
4202B MATERIALS FOR CONCRETE ....................................................... 108
4203B PREPARING THE UNDERLYING LAYERS .................................... 121
4204B PREPARING THE UNDERLYING LAYERS .................................... 123
4205B SIDE-FORMS, RAILS AND GUIDE WORES ................................... 125
4207B PLACING, COMPACTING AND FINISHING WITH SLIPFORM
EQUIPMENT .................................................................................... 129
4208B PLACING, COMPACTING AND FINISHING WITH HAND
EQUIPMENT .................................................................................... 130
4209B STEEL REINFORCEMENT ............................................................. 131
4210B SURFACE TEXTURE ...................................................................... 134
4211 B CURING ........................................................................................... 136
4212 B TRANSVERSE JOINTS ................................................................... 137
4213 B LONGITUDINAL JOINTS ................................................................. 139
4214 B LONGITUDINAL JOINTS ................................................................. 140
4215B THE BARS AND DOWELS .............................................................. 142
4218B CONSTRUCTION TOLERANCES ................................................... 148
4219 B PROCESS CONTROL ..................................................................... 148
4220B QUALITY CONTROL AND WORKMANSHIP .................................. 148
4221B REMEDIAL WORK........................................................................... 150
viii
4222B OPENING TO TRAFFIC .................................................................. 154
4223B MEASUREMENT AND PAYMENT .................................................. 154
5000 ANCILLARY ROADWORKS ............................................................ 157
5100 MARKER AND KILOMETRE POSTS .............................................. 157
5106 MEASUREMENT AND PAYMENT .................................................. 157
5200 GUARDRAILS .................................................................................. 157
5202 MATERIALS..................................................................................... 157
5400 ROAD SIGNS .................................................................................. 158
5403 MATERIALS..................................................................................... 158
5404 CONSTRUCTION ............................................................................ 158
5409 MEASUREMENT AND PAYMENT .................................................. 159
5500 ROAD MARKINGS........................................................................... 159
5501 SCOPE ............................................................................................ 159
5502 MATERIALS..................................................................................... 159
400 Poise at 160 °C ................................................................................ 160
100 Poise at 190 °C ................................................................................ 160
5503 WEATHER LIMITATIONS................................................................ 161
3.1 Graded Glass Beads: ....................................................................... 162
3.2 Pigments: ......................................................................................... 162
3.3 Heating indicators: ........................................................................... 163
3.4 Skid Resistance: .............................................................................. 163
3.5 Thickness: ........................................................................................ 163
3.6 Versatility: ........................................................................................ 163
3.7 Environmental Resistance: .............................................................. 163
3.8 Retroreflectivity: ............................................................................... 163
3.9 Asphalt ............................................................................................. 164
4.0 Portland Cement Concrete:.............................................................. 164
5504 MECHANICAL EQUIPMENT FOR PAINTING ................................. 165
5507 APPLYING THE THERMOPLASTIC PAINT .................................... 165
5509 ROAD STUDS ................................................................................. 166
5513 PROTECTION ................................................................................. 166
5514 MEASUREMENT AND PAYMENT .................................................. 166
5600 SOLAR STREET LIGHTING AND TRAFFIC SIGNALS ................... 167
5601 SOLAR STREET LIGHTING ............................................................ 167
5602 SCOPE ............................................................................................ 167
5603 MATERIALS..................................................................................... 168
5604 SOLAR STREET LIGHTING TECHNICAL SPECIFICATIONS ........ 168
5605 CONSTRUCTION ............................................................................ 176
5606 TESTING AND COMMISSIONING .................................................. 178
ix
5606 DOCUMENTATION ......................................................................... 183
5607 SPARE PARTS ................................................................................ 183
x
6113.02.01 Provisional Number of Piles............................................................. 226
6113.02.02 Other ................................................................................................ 227
6113.03 Contractor to Acquaint Himself with the Site of Work ...................... 227
6113.04 Subsoil Data .................................................................................... 227
6113.05 Unexpected Ground Conditions ....................................................... 228
6113.06 Systems and Nature of Neighbouring Buildings .............................. 229
6113.07 Site Access ...................................................................................... 230
6113.08 System of Piles Foundation ............................................................. 230
6113.09 Alternative Design by Contractor ..................................................... 233
6113.10 Piles Group ...................................................................................... 235
6113.11 Underground Services ..................................................................... 235
6113.12 Equipment and Labour .................................................................... 235
6113.13 Programme of Works ....................................................................... 236
6113.14 Method Statements for Construction Operations ............................. 236
6113.15 Engineer's Inspection Program ........................................................ 238
6113.15.01 Adequate Notice of Supervision ...................................................... 238
SS 6113.16 Setting Out ....................................................................................... 239
6113.17 Emphasis on Dimensional Accuracy ............................................... 239
6113.18 Pile Position Tolerance .................................................................... 240
6113.19 Forcible Corrections .......................................................................... 240
6113.20 Adjacent Piles .................................................................................... 241
6113.21 Faulty Piles ...................................................................................... 241
6113.22 Stripping or Cutting of Piles to Cut-Off Levels ................................... 241
6113.23 Cleaning Up ....................................................................................... 244
6113.24 Pile Length ......................................................................................... 244
6113.25 Marking of Piles ................................................................................. 244
6113.26 As-Built Drawings .............................................................................. 244
6113.27 Piling Records.................................................................................... 245
6113.28 Wastages ........................................................................................... 246
6400 CONCRETE FOR STRUCTURES ................................................... 246
6401 SCOPE ............................................................................................ 246
6404 MATERIALS.................................................................................... 246
6900 REHABILITATION OF EXISTING CONCRETE AND MASONRY
STRUCTURES ................................................................................ 247
6901 SCOPE ........................................................................................... 247
6902 WORKMANSHIP ............................................................................ 247
6903 MATERIALS.................................................................................... 247
6905 PATCHING ..................................................................................... 250
6906 POINTING....................................................................................... 252
xi
6907 COPING .......................................................................................... 253
6908 EXTENSION OF EXISTING CONCRETE STRUCTURES ............. 254
6909 MEASUREMENT AND PAYMENT ................................................. 255
7000 TOLERANCES, TESTING AND QUALITY CONTROL .................... 257
7100 TESTING OF MATERIALS AND WORKMANSHIP ......................... 257
7109 TAKING AND SUBMITTING SAMPLES .......................................... 257
7110 TESTING METHODS....................................................................... 258
7114 (b) FIELD DENSITY TESTING .............................................................. 258
7114 (d) FIELD DENSITY TESTING ........................................................ 259
7115 TESTS OF SURFACE REGULARITY, LEVELS AND
THICKNESS .................................................................................... 260
7200 QUALITY CONTROL ....................................................................... 260
7204 GENERAL REQUIREMENTS .......................................................... 260
7205 PROCEDURES ................................................................................ 261
xii
3.8 Inspection......................................................................................... 272
3.9 Excavation below required depths ................................................... 273
3.10 Filling................................................................................................ 273
3.11 Return, fill in and ram ....................................................................... 273
3.12 Levelling ........................................................................................... 274
3.13 Soil sterilisation ................................................................................ 274
3.14 Disposal of surplus excavated material ............................................ 275
3.15 Disposal of water ............................................................................. 275
3.16 Planking and strutting....................................................................... 275
3.17 Hardcore .......................................................................................... 276
3.18 Rates for excavations....................................................................... 276
3.19 Rates for Disposal ............................................................................ 277
3.20 Dampproof Membrane ..................................................................... 277
3.21 Cutting down trees ........................................................................... 277
4.0 CONCRETE WORK ......................................................................... 278
4.1 Materials and workmanship generally .............................................. 278
4.2. Materials generally ........................................................................... 278
4.3 Cement ............................................................................................ 278
4.4 Aggregate generally ......................................................................... 278
4.5 Fine Aggregate ................................................................................ 279
4.6 Coarse aggregate ............................................................................ 279
4.7 Water ............................................................................................... 279
4.8 Admixtures ....................................................................................... 280
4.9 Steel reinforcement .......................................................................... 280
4.10 Bending and fixing of reinforcement ................................................. 280
4.11 Formwork to produce a fair face board finish(wrought formwork) .... 281
4.12 Construction and Movement joints ................................................... 282
4.13 Concrete grades .............................................................................. 282
4.14 Concrete Production, Supervision and Tests ................................... 282
4.15 Preliminary cube tests ...................................................................... 282
4.16 Work cube tests ............................................................................... 283
4.17 Quality control requirements ............................................................ 285
4.17.1 Supervision ...................................................................................... 285
4.17.2 Batching and mixing plant ................................................................ 285
4.18 Workmanship ................................................................................... 285
4.18.1 Placing of reinforcement .................................................................. 285
4.18.2 Formwork generally.......................................................................... 286
4.18.3 Mixing of Concrete ........................................................................... 287
4.18.5 Distribution of Concrete.................................................................... 289
xiii
4.18.6 Placing of Concrete .......................................................................... 289
4.18.7 Vibration ........................................................................................... 290
4.18.8 Working joints .................................................................................. 290
4.18.9 Protection of Concrete ..................................................................... 290
4.18.10 Concrete in Excavation. ................................................................... 290
4.18.11 Removal of formwork. ...................................................................... 291
4.18.12 Surface finishes ............................................................................... 291
4.19. Precast Concrete ............................................................................. 292
4.20 Sub-contractors work Incorporated in the Structure ......................... 292
4.21 General ............................................................................................ 293
4.22 Movements and Separation Joints ................................................... 293
4.23 Mortise and Pockets......................................................................... 293
4.24 Pricing concrete work ....................................................................... 294
5.0 WATERPROOFING ......................................................................... 295
5.1 General ............................................................................................ 295
5.1.1 Description ....................................................................................... 295
5.3 Waterproofing Mortar, ...................................................................... 298
5.3.1 Slurry,............................................................................................... 298
5.3.2 Fibre Reinforced Mortar, .................................................................. 298
5.3.3 Complementary products for joint sealing and waterproofing .......... 298
5.3.3.1 Waterstops, ...................................................................................... 298
5.3.3.2 Sealants and Profiles ....................................................................... 298
6.1 Water ............................................................................................... 300
6.3. Fine Aggregate ................................................................................ 300
6.4 Coarse Aggregate ............................................................................ 300
6.5 Lime ................................................................................................. 300
6.8 Concrete Blocks ............................................................................... 300
6.9 Stone................................................................................................ 301
6.10 Fair face work .................................................................................. 301
6.11 Wall reinforcement ........................................................................... 301
6.12 Wall ties ........................................................................................... 301
6.13 Chasing ............................................................................................ 302
6.14 Mortar............................................................................................... 302
6.15 Workmanship ................................................................................... 302
6.16 Setting out ........................................................................................ 302
6.17 Bonding walling ................................................................................ 302
6.18 Laying and Jointing .......................................................................... 303
6.19 Putlog holes ..................................................................................... 303
6.20 Damp proof course........................................................................... 303
xiv
6.21 Prices to include ............................................................................... 303
7.0 FIBERCEMENT REINFORCED PANEL .......................................... 304
8.0 ROOFING ........................................................................................ 312
8.1 Vermiculite lightweight screed.......................................................... 312
8.2 Roof waterproofing ........................................................................... 312
8.3 Bitumen felt roofing .......................................................................... 312
8.3.1 Generally.......................................................................................... 312
8.3.2 Materials .......................................................................................... 312
8.3.3 Fixing of Bitumat Polyframe Waterproofing ...................................... 312
8.3.4 Fixing of Sarnafil Waterproofing Systems ........................................ 313
8.3.5 Guarantee ........................................................................................ 313
8.4. Aluminium sheet roofing................................................................... 313
8.4.1 Materials .......................................................................................... 313
8.4.2 Fixing ............................................................................................... 313
8.5 Zicalume roofing sheet ..................................................................... 313
8.5.1 Materials .......................................................................................... 313
8.5.2 Fixing ............................................................................................... 313
9.0 JOINERY ......................................................................................... 314
9.1 General ............................................................................................ 314
9.2 Hardwood Facia Board .................................................................... 314
9.3 Workmanship ................................................................................... 314
9.4 Flush doors ...................................................................................... 315
9.5 Plywood ........................................................................................... 315
9.6 Blockboard ....................................................................................... 315
9.7. Chipboard ........................................................................................ 315
9.8 Plugging ........................................................................................... 315
9.9 Protection ......................................................................................... 316
9.10 Ironmongery ..................................................................................... 316
9.11 Prices to include ............................................................................... 316
10.0 STRUCTURAL STEEL WORKS ...................................................... 317
10.1 Generally.......................................................................................... 317
10.2 Shop drawings ................................................................................. 317
10.3 Submittals ........................................................................................ 317
10.4 Bolts ................................................................................................. 317
10.5 Welding ............................................................................................ 317
10.6 Painting ............................................................................................ 317
10.6.1 Shop painting ................................................................................... 317
10.6.2 Field painting .................................................................................... 317
11.0 METALWORK .................................................................................. 318
xv
11.1 Mild steel .......................................................................................... 318
11.2 Galvanised work .............................................................................. 318
11.3 Aluminium ........................................................................................ 318
11.4 Smithing, welding and cutting .......................................................... 318
11.5 Bolts ................................................................................................. 318
11.6 Anchor bolts ..................................................................................... 318
11.7 Perforated Aluminium Facade Sheet ............................................... 318
11.8 Louvre windows ............................................................................... 319
11.9 Metal doors ...................................................................................... 319
11.10 Roller Shutter Door .......................................................................... 319
11.11 Burglar bars ..................................................................................... 320
11.12 Structural hollow sections ................................................................ 321
11.13 Mild steel tubing ............................................................................... 321
11.14 Shop inspection ............................................................................... 321
11.15 Marking ............................................................................................ 321
11.16 Storage ............................................................................................ 321
11.17 Erection ............................................................................................ 321
12.0 PLUMBING AND ENGINEERING INSTALLATION ......................... 322
12.1 Execution of Works .......................................................................... 322
12.2 Extent of Works ................................................................................ 322
12.3 Extent of Contractor’s duties ............................................................ 323
12.4 Quality of Materials and Workmanship............................................. 324
12.4.1 Materials and workmanship generally .............................................. 324
12.4.2 Tubing Generally .............................................................................. 324
12.4.3 Galvanized Mild Steel Tubing .......................................................... 327
12.4.4 Black Steel Tubing ........................................................................... 327
12.4.5 Cooper Tubing ................................................................................. 328
12.5 Geberit Mepla .................................................................................. 328
12.5.1 PVC, HDPE and PE Pipes ............................................................... 329
12.5.2 Pipework Ancillaries ......................................................................... 329
12.6 Valves, Cocks, Taps, Etc ................................................................. 329
12.7 Waste Traps..................................................................................... 331
12.8 Galvanized Mild Steel Water Mains ................................................. 331
12.9 Sanitary and Other Appliances ........................................................ 331
12.10 Floor Gully........................................................................................ 332
12.11 GRP Water Storage Tank ................................................................ 332
12.12 Commissioning and Testing ............................................................. 332
13.0 FLOOR, WALL AND CEILING FINISHINGS .................................... 333
13.1 Sand................................................................................................. 333
xvi
13.2 Aggregate ........................................................................................ 333
13.3 Cement ............................................................................................ 333
13.4 Lime ................................................................................................. 333
13.5 Workmanship ................................................................................... 333
13.6 In-situ pavings generally .................................................................. 333
13.6.1 Cement and sand paving ................................................................. 334
13.6.2 Concrete paving ............................................................................... 334
13.6.3 Internal plaster ................................................................................. 334
13.6.4 "Sandtex" finish ................................................................................ 335
13.7 Floor tiles ......................................................................................... 335
13.8 Tactile Walking Surface Tile Resilient .............................................. 335
13.8.1 Construction ..................................................................................... 335
13.8.2 Styles ............................................................................................... 336
13.8.3 Product Performance and Technical Data ....................................... 336
13.8.4 Installation ........................................................................................ 336
14.0 GLAZING ......................................................................................... 337
14.1 General ............................................................................................ 337
14.2 Putty ................................................................................................. 337
14.3 Workmanship ................................................................................... 337
14.4 Cleaning and protection ................................................................... 337
15.0 PAINTING ........................................................................................ 338
15.1 Colour range .................................................................................... 338
15.2 Materials .......................................................................................... 338
15.3 Preparation ...................................................................................... 338
15.4 Plastered surfaces ........................................................................... 338
15.5 Woodwork preparations ................................................................... 339
15.6 Metalwork......................................................................................... 339
16.0 DRAINAGE ...................................................................................... 340
16.1 Generally.......................................................................................... 340
16.2 PVC drain pipes ............................................................................... 340
16.3 Cast iron drainpipes ......................................................................... 340
16.4 Concrete drain pipes ........................................................................ 340
16.5 Pitch impregnated fibre drainpipes ................................................... 341
16.6 Manholes ......................................................................................... 341
16.7 Concrete beds etc ............................................................................ 342
16.8 Trenches and manhole excavation and back filling .......................... 342
16.9 Pipe laying and jointing generally ..................................................... 343
16.9.1 Jointing PVC Drainpipes .................................................................. 343
16.9.2 Jointing precast concrete pipes ........................................................ 344
xvii
16.10 Position of floor gullies etc. .............................................................. 345
16.11 Testing ............................................................................................. 345
17.0 ELECTRICAL INSTALLATION ........................................................ 346
17.1 GENERAL SPECIFICATION ........................................................... 346
17.1.1 Scope of work .................................................................................. 346
17.1.1.1 Working drawings ............................................................................ 346
17.1.1.2 Record drawings .............................................................................. 347
17.1.1.3 As Built Drawings ............................................................................. 347
17.1.1.4 Shop drawings ................................................................................. 347
17.1.1.10 Workmanship ................................................................................... 349
17.1.1.11 Codes, Standards and Regulations ................................................. 349
17.1.1.12 Safety and Property Protection ........................................................ 350
17.1.2.1 General ............................................................................................ 351
17.1.2.2 Noise criteria .................................................................................... 351
17.1.3 Drawings, Data and documentation ................................................ 351
17.1.3.1 Drawings .......................................................................................... 351
17.1.3.2 Operator’s Instruction and Facility manuals ..................................... 352
17.1.3.3 Service and maintenance manuals .................................................. 352
17.1.3.4 Language, Measurement and format ............................................... 352
17.1.4 Equipment registration .................................................................... 353
17.1.4.1 Certificate and registration of Equipment ......................................... 353
17.1.4.2 Plant and Equipment ........................................................................ 353
17.1.4.3 Electrical Equipment ........................................................................ 353
17.1.4.4 Materials .......................................................................................... 353
17.1.4.5 Site Testing ...................................................................................... 353
17.1.5 Tagging and identification ................................................................ 354
17.1.6 Painting ............................................................................................ 354
17.1.7 Spare parts ...................................................................................... 354
17.1.8 Use of Site ....................................................................................... 354
17.1.7 Procurement, Inspection and Expediting.......................................... 355
17.1.7.1 Contractor’s responsibility ................................................................ 355
17.1.8 General requirement for commissioning .......................................... 357
17.2: PARTICULAR SPECIFICATIONS................................................... 359
17.2.1.0 General ............................................................................................ 359
17.2.1.1 Scope of Works ................................................................................ 359
17.2.1.2 Codes, Standards and Specifications .............................................. 360
17.2.2 Supply of Electricity .......................................................................... 361
17.2.3.0 Supply and Distribution .................................................................... 361
17.2.3.1 Sub Main Lv Switchboard ................................................................ 361
xviii
17.2.3.2 MCB Distribution Boards .................................................................. 362
17.2.4.0 Electrical Installations Related to Mechanical Plants ....................... 362
17.2.4.1 Scope ............................................................................................... 362
17.2.4.2 Motor Control Centres ...................................................................... 362
17.2.4.2.1 Scope ............................................................................................... 362
17.2.4.2.2 Mechanical Plants ............................................................................ 363
17.2.5.0 Lighting Installation .......................................................................... 363
17.2.5.1 Lighting Fittings ................................................................................ 363
17.2.5.2 Emergency Lighting ......................................................................... 364
17.2.5.3 Internal Lighting ............................................................................... 364
17.2.5.4 External Lighting .............................................................................. 364
17.2.6 Fire Alarm System........................................................................... 364
17.2.6.1 Voice and Data Installation .............................................................. 365
17.2.8 Earthing Systems ............................................................................ 366
17.2.8.1 Types of Earth Termination Networks .............................................. 366
17.2.8.2 Earthing and Equipotential Connections .......................................... 366
17.2.8.3 Earthing and Protective Conductors ................................................ 367
17.2.8.4 Principal Earth Continuity Conductors and Joints ............................ 367
17.2.8.5 Branch Protective Conductors and Bonding .................................... 368
17.2.8.6 Earth Terminations ........................................................................... 368
17.2.8.7 Earthing Conductor and Connections .............................................. 369
17.2.8.8 Earth Resistance .............................................................................. 370
17.2.8.9 Soil Resistivity .................................................................................. 370
17.2.8.10 Conductor Type and Size................................................................. 370
17.2.8.11 Depth of Burial of Earth Grid ............................................................ 370
17.2.8.12 Duration of Fault Current.................................................................. 370
17.2.8.13 Magnitude of Fault Current .............................................................. 370
17.2.8.14 Test Points ....................................................................................... 371
17.2.9 Emergency Power Supply ................................................................ 371
17.2.9.1 Stand by Generators ........................................................................ 371
17.2.9.1.1 General ............................................................................................ 371
17.2.9.1.2 Scope of Supply ............................................................................... 371
17.2.9.1.3 Technical Requirements .................................................................. 374
17.2.9.1.3.1 Diesel Engine ................................................................................... 374
17.2.9.1.3.2 Coupling and Bearing Arrangement ................................................. 374
17.2.9.1.3.3 Foundations ..................................................................................... 375
17.2.9.1.3.4 Pumps .............................................................................................. 375
17.2.9.1.3.5 Governor .......................................................................................... 375
17.2.9.1.3.6 Charge Air System ........................................................................... 376
xix
17.2.9.1.3.7 Cooling System ................................................................................ 376
17.2.9.1.3.8 Lubrication Oil Cooler....................................................................... 376
17.2.9.1.3.9 Exhaust System ............................................................................... 376
17.2.9.1.3.10 Service Tank .................................................................................... 376
17.2.9.1.3.11 Starting System ................................................................................ 377
17.2.9.1.3.12 Automatic Change-over Switch ........................................................ 378
17.2.9.1.4 Control and Supervisory System ...................................................... 378
17.2.9.1.4.1 Control Panel ................................................................................... 378
17.2.9.1.4.2 General Protection Features ............................................................ 378
17.2.9.1.4.3 Protective Features, Warning ........................................................... 379
17.2.9.1.4.4 Protective Features, Alarm............................................................... 379
17.2.9.1.4.5 Instruments ...................................................................................... 379
17.2.9.1.4.6 Alarms and Indicators ...................................................................... 380
17.2.9.1.4.7 Controls............................................................................................ 380
17.2.9.1.5 Operation ......................................................................................... 381
17.2.9.1.5.1 Starting Sequence ........................................................................... 381
17.2.9.1.5.2 Engine Shutdown Sequence ............................................................ 381
17.2.10 POWER CABLES ............................................................................ 381
17.2.10.1 GENERAL ........................................................................................ 381
17.2.10.2.1 PVC, SWA, PVC Cables .................................................................. 385
17.2.10.2.2 LV Cables ........................................................................................ 385
17.2.10.2.3 Wiring ............................................................................................... 385
17.2.11 Conduits, Trunking and Associated Fittings ..................................... 386
17.2.11.1 General ............................................................................................ 386
17.2.11.2 Steel Conduits - Steel Trunking ....................................................... 388
17.2.11.3 Non Metallic Conduits - Trunkings ................................................... 390
17.2.11.4 Flexible Connections ........................................................................ 392
17.2.12 Testing and Inspection ..................................................................... 392
17.2.12.1 Site Tests ......................................................................................... 393
17.2.12.1.1 Verification of Polarity ...................................................................... 393
17.2.12.1.2 Earthing............................................................................................ 393
17.2.12.1.3 Insulation.......................................................................................... 394
17.2.12.1.4 Continuity ......................................................................................... 394
17.2.12.1.4 MCB’s and Overload settings ........................................................... 394
17.3 ELECTRICAL EQUIPMENT SPECIFICATIONS FOR TYPE A –
BUS STATIONS ............................................................................... 396
17.3.1 EARTHING SYSTEM ...................................................................... 396
17.3.1.1 30x3.5 mm Galvanized Steel Strip ................................................... 396
17.3.1.2 D20 mm, 1,5m Galvanized Rod ....................................................... 396
xx
17.3.1.4 Earthing Bare, 50x10x500 mm ......................................................... 396
17.3.1.5 Earthing Cable, 1x25mm² Yellow-Green Insulated Cable ................ 396
17.3.1.6 Bonding Cable, 1x16mm² Yellow-Green Insulated Cable ................ 396
17.3.2 LIGHTING, SOCKET OUTLET, POWER DIST., VANTILATION
SYSTEM .......................................................................................... 396
17.3.2.1 Downlight Lighting Fitting, IP65, 160W LED Lamp .......................... 396
17.3.2.2 Battery Pack for emergency lighting (1 hour) ................................... 397
17.3.2.3 60 W LED Lamp for Hand Rail ......................................................... 397
17.3.2.4 2x36W Weather-Proof Fluorescent Lighting Fixture ........................ 397
17.3.2.5 Lighting Fitting, 60 W Incandescent Lamp ....................................... 397
17.3.2.6 Single Pole One Gang lighting switch .............................................. 398
17.3.2.7 Grounded Socket (1 phase) ............................................................. 398
17.3.2.8 Data Socket ..................................................................................... 398
17.3.2.9 0.6/1 kV, 3x2.5 mm2 N2XH Cable ................................................... 398
17.3.2.10 0.6/1 kV, 5x2.5 mm2 N2XH Cable ................................................... 398
17.3.2.11 0.6/1 kV, 4x4+4 mm2 N2XH Cable .................................................. 399
17.3.2.12 0.6/1 kV, 4x6+6 mm2 N2XH Cable .................................................. 399
17.3.2.13 Ventilation Fan, 220V, 300W ........................................................... 399
17.3.2.14 Air Condation, 1000W ...................................................................... 400
17.3.3 Pipe and Cable Tray System .......................................................... 400
17.3.3.1 D:100mm, PE Pipe........................................................................... 400
17.3.3.2 Galvanized Steel Cable Trays, Cable Ladders And Their
Accessories...................................................................................... 400
17.3.4 Distribution Boards .......................................................................... 401
17.3.4.1 415V/240V, 25A, 10kA(1 sec) Normal Lighting Distribution
Board ............................................................................................... 401
17.3.4.2 415V/240V, 25A, 10kA(1 sec) Emergency Lighting Distribution
Board ............................................................................................... 402
17.3.4.3 415V/240V, 50A, 16kA(1 sec) Main Distribution Board .................... 403
17.3.4.4 415V/240V, 40A, 16kA(1 sec) UPS Main Distribution Board ......... 405
17.3.5 STAND-BY AND EMERGENCY SYSTEM...................................... 406
17.3.5.1 10kVA or 15 kVA, 6 hours UPS System, including all parts and
accessories ...................................................................................... 406
17.4 ELECTRICAL EQUIPMENT SPECIFICATIONS FOR TYPE B –
BUS STATIONS ............................................................................... 407
17.4.1 EARTHING SYSTEM ...................................................................... 407
17.4.1.1 30x3.5 mm Galvanized Steel Strip ................................................... 407
17.4.1.2 D20 mm, 1,5m Galvanized Rod ....................................................... 407
17.4.1.3 Thermo Welding ............................................................................... 407
xxi
17.4.1.4 Earthing Bare, 50x10x500 mm ......................................................... 407
17.4.1.5 Earthing Cable, 1x25mm² Yellow-Green Insulated Cable ................ 407
17.4.1.6 Bonding Cable, 1x16mm² Yellow-Green Insulated Cable ................ 408
17.4.2 LIGHTING, SOCKET OUTLET, POWER DIST. SYSTEM .............. 408
17.4.2.1 Downlight Lighting Fitting, IP65, 160W LED Lamp .......................... 408
17.4.2.2 Battery Pack for Emergency Lighting (1 hour) ................................. 408
17.4.2.3 60 W LED Lamp for Hand Rail ......................................................... 408
17.4.2.4 2x36W Weather-Proof Fluorescent Lighting Fixture ........................ 409
17.4.2.5 Lighting Fitting, 60 W Incandescent Lamp ....................................... 409
17.4.2.6 Single Pole One Gang lighting switch .............................................. 409
17.4.2.7 Grounded Socket (1 phase) ............................................................. 409
17.4.2.8 Data Socket ..................................................................................... 409
17.4.2.9 0.6/1 kV, 3x2.5 mm2 N2XH Cable ................................................... 409
17.4.2.10 0.6/1 kV, 5x2.5 mm2 N2XH Cable ................................................... 410
17.4.2.11 0.6/1 kV, 4x6+6 mm2 N2XH Cable .................................................. 410
17.4.2.12 0.6/1 kV, 4x10+10 mm2 N2XH Cable .............................................. 410
17.4.2.13 0.6/1 kV, 4x16+16 mm2 N2XH Cable .............................................. 411
17.4.2.14 Ventilation Fan, 220V, 300W ........................................................... 411
17.4.2.15 Air Condation, 1000W ...................................................................... 412
17.4.3 PIPE AND CABLE TRAY SYSTEM ................................................ 412
17.4.3.1 D:100mm, PE Pipe........................................................................... 412
17.4.3.2 Galvanized steel cable trays, cable ladders and their
accessories. ..................................................................................... 412
17.4.4 Distribution Boards .......................................................................... 413
17.4.4.1 415V/240V, 40A, 10kA(1 sec) Normal Lighting Distribution
Board ............................................................................................... 413
17.4.4.2 415V/240V, 32A, 10kA(1 sec) Emergency Lighting Distribution
Board ............................................................................................... 414
17.4.4.3 415V/240V, 80A, 16kA(1 sec) Main Distribution Board .................. 415
17.4.4.4 415V/240V, 40A, 16kA(1 sec) UPS Main Distribution Board ......... 416
17.4.5 Stand-By and Emergency System .................................................. 418
17.4.5.1 15 kVA, 180 min.UPS System, including all parts and
accessories ...................................................................................... 418
18.0 Specifications for ICT Installations .................................................. 419
18.1 Description. ...................................................................................... 419
18.18 Payment and Measurement ............................................................. 421
xxii
PREAMBLE
These Special Specifications and the Standard Specifications may contain cross
references to other Sections and Clauses in these Special Specifications or to the
Drawings and other parts of the Contract Documents which shall likewise be
construed as Specifications for the Item of Work involved.
In the Bill of Quantities reference may have been made to certain Section(s) or
Clause(s) in these Special Specifications or the Standard Specifications
corresponding to the main type of Works involved, but this shall not be construed as
limiting the specifications for such item of work only to the Section(s) or Clause(s)
xxiii
referred to. All relevant requirements of these Special Specifications and the
Standard Specifications for the particular Item of Work shall be complied with.
The apparent silence of these Special Specifications, the Drawings or other Contract
Documents as to any detail or the apparent omission from them of a detailed
description concerning any Works or requirements, shall be regarded as meaning
that good engineering practice shall apply and shall be to the approval of the
Engineer.
xxiv
1000 GENERAL
1167 ADDENDUM
Amendment of or revision to any of the Contract Documents issued to
Tenderers, and which is deemed to form part of the Contract
Documents.
1169 EMPLOYER
The Employer is the Chief Executive, Tanzania National Roads Agency
(TANROADS).
1170 ABBREVIATIONS
Wherever the following abbreviations of titles, terms and units of
measurement are used in the Standard and Special Specifications or on
the Drawings, the intent and meaning shall be interpreted as described
hereunder.
25
ABBREVIATION
% percent
A amperes
A.C. Alternate Current
AADT Aannual Average Daily Traffic
AASHTO American Association of State Highway and Transportation Officials
AC10, AC14, AC20 Asphalt concrete (max. particle size 10 / 14 / 20mm)
ACV Aggregate Crushing Value
AIV Aggregate Impact Value
ALD Average Least Dimension
ASTM American Society for Testing and Materials
av. Average
BEMIX Bitumen emulsion mix
bit. Bitumen/bituminous
BoQ Bill of Quantities
BS British Standard
C Celsius (Centigrade)
C1, C2 cemented material layer (UCS minimum 1 MPa and 2 MPa)
CBR California Bearing Ratio
CKS Standard Coordination Specification
CM cemented material (modified to UCS minimum 0.5 MPa)
cm centimetre(s)
CML Central Materials Laboratory (TANLAB)
conc. concrete
CRR crushed aggregate base with enhanced requirements
CRS crushed aggregate base
CSS-1hr Cationic Slow Setting-1 hour
Cst centistoke(s)
cu.m or m3 cubic metre(s)
D.C. direct current
dB decibel(s)
DBM30, DBM40 dense bituminous mix (max. particle size 30 / 40mm)
DBSD double bituminous surface dressing
DR dump rock
equiv. equivalent
ESA Equivalent Standard Axles
EVA plastomerpolymer
FBMIX foamed bitumen mix
FI Flakiness Index
26
g gram(s)
G25, G45, G60,G80 natural gravel with CBR value min. 25 / 45 / 60 / 80% for
pavement layers
G3, G7, G15 natural gravel with CBR value min. 3 / 7 / 15% for earthworks
GM Grading Modulus (GM = (300 - %pass2mm - %pass0.425mm -
%pass0.075mm) / 100
GVM gross vehicle mass
GW gravel wearing course
ha hectare(s)
HP horsepower
hr/hrs hour(s)
Hz Hertz (Frequency)
i.a. inter alia
kg kilogram
kl kilolitre
km kilometre(s)
km/hr kilometres per hour
kN kilo Newtons
kPa kilo Pascal
kW or kVA kilowatt
LAA Los Angeles Abrasion
LAMBS large aggregate mixes for base (hot-mixed bituminous base)
LCD liquid crystal display
lin.m linear metre(s)
LL Liquid Limit
LS Linear Shrinkage
ltr. litre(s)
m metre(s)
max. maximum
MC moisture content
MC-30, MC-70 medium curing cut-back bitumen
MDD Maximum Dry Density
min minute(s)
min. minimum
ml millilitre(s)
mm millimetre(s)
MoI DMinistry of Infrastructure Development
MoW Ministry of Works
MPa mega Pascal
27
N Newtons
N/A Not applicable
Ndes Design Number of Gyrations
Nini Initial Number of Gyrations
Nmax Maximum Number of Gyrations
no. number
OMC Optimum Moisture Content
OPC Ordinary Portland cement
Pa Pascal(s)
PBFC Portland blast-furnace cement
PI Plasticity Index
PL Plastic Limit
PM Plasticity Modulus (PM = PI x %pass0.425mm)
PM30/PM60/PM80 Penetration Macadam
ppm parts per million
PSV Polished Stone Value
pts. points
PVC polyvinyl chloride
R&B ring and ball softening point test
RC reinforced concrete
ROW right-of-way
rpm revolutions per minute
SABITA Southern African Bitumen and Tar Association
SABS South African Bureau of Standards
SATCC Southern African Transport Coordinating Commission
SBR styrene-butadiene rubber
SBS styren-butadiene-styrene
SBSD single bituminous surface dressing
SE Sand Equivalent
sec seconds
SG Specific Gravity
SP 12.5 Super pave
SP Shrinkage Product (SP = LS x %pass0.425mm)
sq.cm or cm2 Square centimetre(s)
sq.m or m2 square metre(s)
sq.mm or mm2 square millimetre(s)
SSS Sodium Sulphate Soundness
St. Station (location along the designed road centreline)
TANROADS Tanzania National Roads Agency
28
TFOT Thin Film Oven Test
TFV Ten Percent Fines Value
TLA Trinidad Lake Asphalt
ton metric ton (1,000 kg)
TRL Transport Research Laboratory (previously TRRL)
TSR Tensile Strength Ratio
UCS Unconfined Compressive Strength
UPS uninterrupted power supply
V volt(s)
VFA Voids Filled with Asphalt
VMA Voids in Mineral Aggregates
W Watt
29
1200 GENERAL REQUIREMENTS AND PROVISIONS
1202 SERVICES
Replace the first sentence of the third paragraph of Sub-clause 1202(a)
of the Standard Specifications by the following:
The Contractor shall use Microsoft Project as his software for planning
purposes or as otherwise agreed with the Engineer. Detailed time
programmes submitted to the Engineer shall be in both hard copy and
digital copy.
Delete the entire text of paragraph "(e) Materials on the Site" of Clause
1209 of the Standard Specifications, and replace with the following:
30
(e) Materials on Site
Payment in respect of Materials on Site for subsequent incorporation
into the Permanent Works will be in accordance with Clause 14.5 of the
Conditions of Contract, subject to such payment being allowable in said
Clause.
Item Unit
31
The cost shall be inclusive of all materials necessary for the erection of
the board on timber poles as instructed by the Engineer, and the
replacement of the board if damaged."
Item Unit
Item Unit
32
SS12.40 Dispute Board (DB):
(a) Provisional sum to cover the Employer's obligation to pay the DB
provisional sum
(b) Allow for Contractors' overheads and profits as a percentage of
sub-item SS12.40 (a) percentage (%)
Before choosing the sites for work camps it must be assured that waste
and sewage can not pollute the local water resources for instance by
placing the work camps away from human habitation and under no
circumstances upstream to such. Preferably work camps should be
located in small water catchment areas more than 500 metres from
rivers and larger watercourses (more than 1 m wide in the rainy
season). Sufficient sanitation must be provided. According to Tanzania
law it is not permitted to build anything closer than 200 m from rivers.
33
Delete the first sentence of Sub-Clause 1302 (c) of the Standard
Specifications and replace with:
“The Contractor shall provide and erect 6 sign boards (one at each
entrance of the road sections). In addition, the Contractor shall provide
and erect signboards at the site camps, where directed by the Engineer.
Suitable inscription shall include the logos of the respective entities, and
both text and logo shall be in colours to be approved by the Engineer.
The contractor will have to make his own arrangements for a suitable
site for his offices, stores, workshops, camps and other services at his
own expenses pursuant sub- clause 1303 (a) and (e) of standard
Specifications.
34
1400 ENGINEER'S ACCOMMODATION AND ATTENDANCE UPON
ENGINEER AND HIS SITE PERSONNEL
1402 FACILITIES FOR THE ENGINEER
Insert the following text at the end of Sub-clause 1402(e):
35
Adequate electric lighting shall be provided in each room of the office
building together with sufficient power points to supply the office
equipment.
The office building shall be provided with a Subscriber Trunk Dial (STD)
telephone line with Internet connection and extensions to all offices. A
separate dedicated telefax line shall also be provided. The telephone
lines shall be completely independent of the Contractor's. If STD line is
unavailable, provision of telecommunication facilities including Internet
connection may be by mobile phone and/or data operators through
monthly subscription.
The Contractor shall pay all charges associated with connecting and
establishing electricity supply and telephone and power lines, and shall
further pay all electricity and telephone consumption by the Engineer for
the duration of the Contract.
The Contractor shall provide and erect for the duration of the Contract a
site office for the exclusive use of the Engineer’s staff.
The office building shall comprise an area of approximately 160 m2 with
internal access to the following rooms:
The office building shall in addition be equipped with two flush toilets,
changing room and kitchen facilities.
36
The kitchen area shall be provided with a fixed table for hot plates,
sockets for hot plates and refrigerator and a steel sink with running
water.
The Drawings include an acceptable layout plan for the Site Office, but
the Contractor may propose modified layout of the office building for the
approval by the Engineer.
37
Steel drawing cabinets suitable for storing all contract drawings 2
Filing trays 12
Desktop Computers 27” All In One Touch Screen 7760 UHD 4K 10
with Articulating Stand with 8th Gen Intel Core i7-6700, Memory 32GB / 1TB
PCIe SSD / Touch / AMD R9 M485X 4GB GDDR5. At least 5 USB ports, with
HDMI out, SD car, Thunderbolt 3, 10/100/1000 Ethernet, and Operating System
– Windows 10 Business or latest supplied with UPS (Uninterruptible Power
Supply) Unit 1 kVA with surge protector, capable to support and back-up each
PC.
Laptop computer (space gray colour) Intel Core i7 (2.9 GHz Turbo boost up to 4
3.9GHZ), with minimum 512 GBPCLe-based onboard SSD configurable to 2TB
SSD, 16GB RAM of 2133 MHZ LPDDR3 onboard memory, Fullsize backlit
keyboard with Force Touch trackpad, 802.11ac Wi-Fi networking, Etrhernet,
Bluetooth 4.2 wireless technology, HD camera, Thunderbolt 3 digital video
output, USB-C to (1.USB, 2.Digital AV, 3.VGA and 4.Gigabit Ethernet
adapters), up to 30 days standby time,15.4" LG Ultrafine 4K display, wireless
blue tooth, Gigabit Ethernet and
WLAN. At least 3 USB ports, macOS High Sierra,
Office2013 or latest versionandBlack leather carryingbackpack for use by the
Employer
38
Laptop computer 8th Gen Intel Core i7 (2.7 GHz), with minimum 512 SSD, 2
16GB Memory, DDR4 RAM Dual Layer DVD +/- RW Drive,
15.4" wide screen LED, wireless blue tooth, Thunderbolt, Gigabit Ethernet, built
in HD webcam with four microphones and
802.11a/g/n WLAN. At least 3 USB 3.0 & 2.0 ports, Windows 10 professional,
Office2013 or latestandcarryingcase. (1 for the Employer)
The tendered amount shall include for the maintenance of the desk top and
Laptop computers throughout the Contract period.
All desktop and laptop computers shall be supplied with one latest version of
the following software:
MS windows 10 or higher or mac OS Sierra or higher
MS office professional. (Latest Version)
MS Project and/or Primavera licences (latest versios), one for Windows and the
other for macOS
Approved virus detection software with update support.
Lap link for windows with associated cable
Microstation SS3 or AutoCAD 2019/2021 with corporate licences for Windows
and macOS with mínimum of 20 users for each operating software.
Road design software compatible with the design or as approved by the
Engineer e.g. Civil3D (Autodesk) appropriate for supplied MS Windows and
macOS with (2 corporate licenses for mínimum of 20 Users for each operating
system)
Software package for downloading and processing of survey data compatible
with the surveying instrument.
Laser printerwith speed of 22 / 11 pages per minute for A4 / A3 and a resolution 3
of 1200x1200 dpi with paper tray for both A4 and A3 including stationery for the
duration of the Contract.
Colour laser printer, with speed of 28 / 14 pages per minute for A4 / A3 and a 1
resolution of 1200x1200 dpi with paper tray for both A4 and A3 including
stationery for the duration of the Contract.
Photocopier, with speed of 35 pages per minute, resolution 1200 x 1220 dpi 1
including paper and other supplies for the duration of the Contract.
Facsimile transmitting machine (approved by the Engineer) 1
Plotter, HP DesignJet 750 or approved similar type, including provision of 1
paper, inks and maintenance of the machine for the duration of the Contract.
Digital flatbed scanner, including USB cable. 1
Electronic calculators 12
Handheld GPS (Garmin eMap) or latest (1 for the Employer) 3
39
Digital camera, min. 20.1 mega pixels and min. 64 GB SDXC memory card, 2
Dual Battery Kit plus full accessory bundle (1 for Employer personnel)
Powerpoint overhead projector, wireless, full HD 1080p, 2500 lumens color 2
brightness, 2500 lumens white brightness (white colour light output), 2xHDMI
(1MHL), Miracast, 3LCD projector with SXGA (1280 x 1024), contrast ratio
60,000:1 (1 for Employer)
Binding machine (1 for the Employer) 2
Paper punches i(1 heavy duty and 11 standard size punch machine) 12
Paper staplers (2 heavy duty and 10 standard size) 12
Paper shredder (heavy duty), 1 for the Employer 2
Rain gauges 3
Thermometer (max/min) 2
First aid and snake bit kit 2
Fire extinguishers (dry type) 4
Ceiling fans or portable fans as agreed with the Engineer 9
Air conditioners, 12,000 BTU/hr 9
Safe, min. size approx. 0.8 m x 0.5 m x 0.4 m, to be concreted in place (either 1
wall or floor mounted) complete with lock and keys.
Refrigerator (minimum 200 litres), one for the Employer’s personnel 2
Twin hot plates 1
Microwave Oven combi Sage or similar Turntable, 34 litre, outer Dim 2
305x515x445mm, interior Dim 206x325x333mm, crisp pan, weight 15kg, 900W
power, convection oven/grill, push dials and buttons (1 for the Employer)
Electric kettle, Cuisnart CPK-17 or equivalent, 1500W (1 for Employer) 2
Water dispenser with hot cold functions (heating ≥ 90°C and cooling ≤10°C) and 3
rated voltage frequency 220-224~50HZ (1for the Employer)
Thermos jugs, 4.5 litres capacity (1 for Employer) 3
Set of plates, cups and glasses for 24 persons plus cutlery 1
40
The Contractor shall supply all other necessary office equipment including
stationery, A4 and A3 size papers and consumables for the Engineer’s printers
in a quantity sufficient to complete the contract. The Contractor shall also
supplythe Engineer’s office with potable wáter.
The site office shall be connected to a sufficient water and electricity supply.
The Contractor shall be responsible for cleaning and maintaining the offices
and toilets and shall provide soap, towels and all necessary fittings and
cleaning materials.
- 4nos. 4 Wheel Drive Station Wagon with Minimum Engine Capacity 3.0
litre diésel, Gear box 6 speed manual, Fuel Tank Capacity Minimum 80
litre or similar approved by the Engineer made from a Country
acceptable by the Employer.
- 7nos. 4 Wheel Drive Double Cab Pickups (Minimum Engine Capacity
2.8 litre diésel, 5 speed Manual Transmission, Fuel tank Capacity
minimum 76 litres or similar approved by the Engineer)
41
1409 PROVISION OF SURVEY EQUIPMENT
Replace the second paragraph of Sub-clause 1409 of the Standard
Specification with following:
42
1410 LABORATORY FOR THE ENGINEER
Delete the first and second paragraph under Sub-clause 1410(a) of the
Standard Specifications and replace by the following:
The Contractor shall operate and maintain his own laboratory during the
Contract Period, whereas the Engineer will operate the independent separate
laboratory, but the Contractor shall maintain the laboratory and provide the
necessary unskilled and skilled labourers including experienced laboratory
technicians as required for the Engineer’s independent testing. All costs
necessary for the provision and upkeep of these labourers (unskilled and
skilled) shall be the full responsibility of the Contractor.
The Contractor shall submit a proposed layout of the laboratory for the
approval of the Engineer.
The laboratory for the Engineer shall be complete with following furnishings
and equipment:
43
- Table lamps 2
- Swivel type desk chairs 2
- Visitors chairs 2
- Waste paper baskets 1
- Filing trays 2
- Wall boards 2.4 x 1.2 m 1
- Steel cupboard with shelves 1
- Steel filing cabinet with 4 lockable drawers 1
- Shelves, 2 m long 2
- Air conditioner, 12,000 BTU/hr 2
- Portable fan 1
- Work benches 3
- Curing tanks 1
- Stools, 1 m high 4
- Stools, 0.4 m high 4
44
Table 1402/1: Applicable Standard Tests for Soils, Gravel and Cement
Treated Materials
45
Table 1402/2: Applicable Standard Tests for Aggregates and Concrete
CML Name of Test Test Method
2.1
No. Moisture Content of Aggregates BS562:Part 109:1990
2.2 Relative Density and Water BS562:Part 2:1975
2.3 Sieve Tests on Aggregates
Absorption BS562:Part 103.1:1985
2.4 Flakiness Index (FI) and Average BS562:Sect. 105.1:1989
2.5 Elongation Index (ALD)
Least Dimension BS562:Sect. 105.2:1990
2.7 Ten Percent Fines Value (TFV) BS562:Part 111:1990
2.9 Los Angeles Abrasion Test (LAA) ASTM C535-89
2.10 Sodium Soundness Test (SSS) * ASTM C88-90
2.11 Slump Test BS1856:Part 102:1983
2.12 Making of Concrete Test Cubes BS1856:Part 108:1983
2.13 Concrete Cube Strength BS1856:Part 116:1983
Quality of Water to be used in * BS3148
Polished
Concrete Stone Value * BS562:Part 114
Soluble Chloride Content * BS562:Part 117
Organic Impurities in Sands for AASHTO T 21
Clay Lumps and Friable Particles
Aggregate AASHTO T 112
Sand Equivalent
in Aggregates AASHTO T 176
Cement Content AASHTO T211
Washable Particles ASTM C 117
46
CML No. Name of Test Test Method
3.9 Density and Water Absorption of ASTM C127-88
Aggregates Retrieved on a 4.75
mm Sieve
3.10 Density and Water Absorption of ASTM C128-88
Aggregates Passing the 4.75 mm
Sieve
3.11 Calibration of Glass Pycnometers NPRA 014 test 14.5922
(0.5-1 litre)
3.23 Effect of Water on Bituminous ASTM D3625-96
Coated Aggregates, Boiling Test
Sand Equivalent AASHTO T 176
Distillation of Cut-back Asphaltic AASHTO T 78 and
Products ASTM D 402
Moisture and Volatile Distillates AASHTO T 110 and
ASTM D 1461
Superpave PG Characterisation, * PP6-93
all relevant tests
Short Term Ageing PP2-94
Gyratory Compaction TP4-93
Recovery of Asphalt AASHTO T 170
Kinematic Viscosity of Asphalts * AASHTO T 201 and
ASTM D 2170
Viscosity of Asphalts by Vacuum * AASHTO T 202 and
Capillary Viscometer ASTM D 2171
Degree of Pavement Compaction AASHTO T 230
Wheel Tracking Test * Hamburg-standard
TV62/652.010-10
Stripping and Coating * See Sub-clause
4202(d)(i) of these
Specifications
47
Costs associated with performance of the above special tests in asterix
(including transportation of samples and Engineer’s and Employer’s personnel
and upkeep during witnessing of testing) are assumed to be built in the
Contractor’s rates.
The Contractor shall within thirty (30) days of the date of the order to
commence submit to the Engineer for his approval a detailed lay-out plan of
the laboratory building together with a complete listing of all the equipment,
apparatus and supplies he proposes to furnish for the laboratories.
Only those costs that are covered by pay items listed in Bill No.1 - General will
be paid for separately and in accordance with Clause 1412 of the Standard
Specifications. All other applicable costs related to Clause 1400 of the
Standard Specifications shall be deemed included in the General Obligations
of the Contractor.
48
In clarification to Pay items 14.05 & 14.06 of the Standard Specifications the
following applies:
Payment for operating and maintaining vehicles under ITEMS 14.05 and
14.06, SUBITEMS (b) and (c) above, for the Engineer, his staff and the
Employer’s, will be made as follows:
(i) By rates per vehicle month, SUBITEM (b). Such rates shall include for the
first 4,500 km per vehicle travelled in any calendar month. Should a vehicle be
used for less than 4,500 km in a particular month, then the unused distance
shall be offset against months when the distance travelled exceeds 4,500 km.
(ii) By a rate per km, SUBITEM (c), over and above the first 4,500 km per
vehicle travelled in any one calendar month, subject to the condition
mentioned in (i) above.
The rates bid by the Contractor shall include for provision of the vehicle all
licensing, insurance, fuel, lubricants, maintenance and repairs, drivers salaries
and allowances and replacement of the vehicles should this be considered
necessary by the Engineer.
49
1500 ACCOMMODATION OF TRAFFIC
1502 GENERAL REQUIREMENTS
Replace the text in Sub-clause 1502(a) of the Standard Specifications
with the following:
50
If deviations for certain sections of the project road are proposed by the
Contractor, the cleared width of the deviations accommodating two-way
traffic shall be not less than 9 m and they shall be constructed to a
formation width of 7 m. Where diversions consist of two separate one-
way lanes, the minimum cleared width and formation width of each lane
shall be 7 m and 4 m respectively.
51
qualified flagmen and portable STOP and GO signs. Traffic lights shall
be used for longer sections unless otherwise agreed to by the Engineer.
Unless clear vision can be maintained at all times between the staff
operating the traffic control, communication shall be established through
radio systems (walkie-talkies).
1600 OVERHAUL
Delete Section 1600 in its entirety.Overhaul will not be measured and
paid for separately. The tendered rates for other items involving
haulage shall be deemed to include the cost of all haulage
requirements.
The final depth of any borrow pit shall not exceed 3m and the Engineer
shall have discretion to restrict the spacing of borrow pits to minimize
environmental degradation. Furthermore, all new borrow pits should be
established outside the 60m wide corridor of the Right of Way (RoW).
According to the Environmental Code of Practice for Road Works
(2009) prepared by the Ministry of Works, all borrow pits must be
established to a distance of at least 100m from centreline of the road.
So this requirement must be observed by Contractor.
The quarry site must be established far away from the major settlement
to a distance or periphery of at least 500m. Where necessary to
establish the quarry site near the major settlement all properties found
within the area of 500 m periphery must be evaluated for compensation
and ensure all affected persons have moved from the area before
excavation starts.
52
1702 GENERAL
In minimising adverse environmental impacts, the Contractor shall
perform his duties strictly in accordance with the Site-specific
Environmental and Social Management and Monitoring Plan (ESMP),
which shall be approved by the Engineer and is to be prepared by the
Contractor following Contract award. The ESMP shall also be submitted
to the Employer for review and comments prior to implementation. The
ESMP shall reflect the present social and physical situation on the
project site, and shall be based on these Technical Specifications and
Conditions of the Environmental Impact Assessment Certificate (EIAC).
53
1704 TEMPORARY SOIL EROSION CONTROL
Add after the first paragraph of Sub-clause 1704(a) of the Standard
Specifications the following:
Special care with soil erosion control must be exercised, not only for
works within the road reserve, but also in opening and working borrow
pits, quarries, work camps and access roads. Operations in highly
erodible areas must be avoided.
Where trees or shrubs are obtained from selected areas on site and
transplanted to designated locations, such plants shall be maintained as
specified.
No separate pay ítem for 1703 – 1704 except Item 1705 with pay item
17.05 (c) and 57.09(b)(i). 50% of Payment for ítem 57.09(b)(i) should be
made upon planting the trees to be specified by the Engineer
(preferably Dodoma Tree) and 50% of the payment for this particular
ítem shall be released at the end of DLP.
54
obtain a good occupational health and safety standard at the working
sites before the start of construction. The HSMP should be approved by
the Engineer.
The plan must include but not limited to the following items:
Building of new road bed. Exposure to noise, vibration and dust should
be reduced as best possible. Methods should be described in the plan;
55
Handling of hydrated lime and other activators and additives. Meas ures
to avoid skin contact and to minimise manual handling must be
described;
All quarries and borrow pits shall be drained and kept drained and,
where they have been excavated so that they will not drain naturally,
they shall be kept pumped dry and back filled after work has finished;
and Responsibilities for health and safety on the site must be described
in the plan.
56
through-out the Works, and the Contractor shall erect conspicuous
notice boards directing where these are situated and provide all
requisite transport. The Contractor shall comply with the Government
medical or labour requirements at all times and provide, equip and
maintain base dressing stations where directed and at all times have
experienced first-aid men and dressers available throughout the Works
for attending minor injuries.
Reporting
The Contractor will produce the following reports to be submitted to the
Consultant and TANROADS/Engineering Monitoring Consultant.
57
Add the following new Pay items
ITEM DESCRIPTION UNIT
Provide for Compliance with provisions for Environmental and Social
Management Plans (ESMP's) for compliance with the general
SS 17.01 requirements of Clause 1700 of the Standard Specification (Payment
shall be based on the proportion of certified value of executed works
on each certificate)
To cover for compliance with the provisions for temporary soil
(a) Months
erosion control during construction period (Section 1704)
To cover for compliance with the provisions for prevention of water
(b) Months
pollution during construction period (Section 1706)
To cover compliance with the provisions for dust abatement during
(c) Months
construction period (Section1708)
Allow for contractor's overhead and profits as a percentage of
(d) %
subitem 17.01 (a) to ( c )
2) HIV/AIDS CONSIDERATIONS
Given the increasing seriousness of the HIV/AIDS problem and the
perception that roads and personnel involved in road works serve as
one of the principal means of the virus moving from one part of the
country to another, the Employer is integrating HIV/AIDS issues into all
of its activities.
58
The Contractor shall keep detailed records of the number of condoms
issued, copies of which shall be submitted to the Engineer on a weekly
basis.
3) GENERAL REQUIREMENTS
HIV/AIDS, STIS and STDS Prevention and Awareness Programs
The Contractor shall institute an HIV/AIDS, STIs and STDs prevention
and awareness campaigns amongst his workers for the duration of the
contract.
The sexual abuse and exploitation of children will form part of this
campaign.
HIV/AIDS Training
Introduction
HIV/AIDS is having a significant and increasing impact in Tanzania.
Interventions that stimulate the movement of people are likely to
increase both exposure to the HIV virus and the spread of the virus.
Road construction has been identified as one such intervention.
59
during the construction period. This specification provides details of
these requirements.
Objective
The objective is to reduce the risk of exposure to and spread of the HIV
virus in the area of the construction. The target group will be local
labourers and their supervisors employed by the works contractors. The
wider community will benefit indirectly through their normal day-to-day
interaction with the target group.
Scope of activities
Activities for HIV/AIDS awareness and prevention will be broad based
targeting both individuals and groups. They may consist of:
(i) Information posters in public places both on and off site (eating
places, bars, guest houses, etc.)
(ii) Availability of socially marketed condoms for purchase
(maximum 100 Shillings each).
(iii) Peer educators (reference people) drawn from the local labour
and trained in HIV/AIDS issues for discussions with colleagues
(estimate 1 per 100 employees).
(iv) Small focus group discussions and information covering key
issues.
(v) Theatre groups and video presentations.
(vi) Promotional events (such as football matches) to encourage
openness and discussion of HIV/AIDS issues.
(vii) Promotional bill boards to raise awareness of the integration of
road construction and HIV/AIDS activities.
(viii) Inclusion of HIV/AIDS activities at site meetings, other
discussions, and with the Community Liaison Committee.
(ix) Availability of promotional materials such as T-shirts, caps,
bumper stickers, key rings, etc.
60
Education will cover:
• Preventive behaviours including partner reduction, condom use, and
awareness and importance of treatment of stis
• skills including negotiating safer sex, correct condom use, purchase
without embarrassment; and
• Referral to local health centres and services available.
Collaboration
Representatives of local health authorities will be invited to attend training
and communication activities.
61
duplication. In addition, these links will assure the target group access to
continued information after the end of the construction period.
Contractor Responsibilities
The Contractor and implementing organization will work closely together to
support the HIV/AIDS awareness and prevention activities. This will ensure
maximum effectiveness and integration with construction activities. Specific
but not exclusive issues are:
Inputs
An organization experienced in the provision of HIV/AIDS awareness and
prevention activities will be selected as a subcontractor to provide the
above scope of activities on behalf of the main Contractor.
Reporting
The implementing organization will produce the following reports to be
submitted to the Contractor, Consultants, and TANROADS/Engineering
Monitoring Consultants.
➢ monthly progress briefs for inclusion in site meetings.
➢ quarterly reports detailing activities carried out, issues, follow up, etc.
➢ a review report of activities in the road construction sector.
➢ a review report of existing IEC materials with recommendations for
development of materials specifically for the road sector.
62
➢ a final report detailing the methodology and activities carried out under
this project including lessons learnt, impact, liaison with the Contractor
and other parties, etc.
Timing
Activities will commence at the start of the construction period and
continue throughout the 36 months to ensure a sustained impact.
DESCRIPTION UNIT
SS18.01 Institute and Maintain HIV/AIDS Awareness Month
Campaign
The unit of measurement shall be the calendar month or part
thereof, measured over the duration of the campaign. The tender
rate shall include for providing a Health Officer to deal with HIV/AIDS
together with his/her transport requirements. The payment shall be
made monthly, pro-rata for parts of a month, from the date of
appointment of the officer until the completion of the Works or
substantial demobilization of the local workforce, whichever comes
first.
63
ITEM DESCRIPTION UNIT
SS18.02 Institute and Maintain HIV/AIDS Prevention PS
Campaign
Payment shall include the cost of providing a clinic or make alternative
suitable arrangements, running the clinic, providing condoms as per the
specifications.
2000 DRAINAGE
2100 DRAINS
2102 OPEN DRAINS
Add at the end of the first paragraph of Clause 2102 of the Standard
Specifications the following:
Open drain excavation shall also include excavating open drains to direct
runoff into and out of the drainage structure within the right of way or as
instructed by the Engineer. The open drains on downstream side shall be
to the lowest point. The excavation on the upstream side drainage structure
shall be made to ensure smooth flow to the inlet. Earthworks for
Longitudinal open drains excavated within road prism covered by Clause
3601.
64
Pipes for subsoil drainage shall be 125/112 mm diameter slotted corrugated
unplasticised PVC pipes complying with SABS 791 or equivalent.
65
2107 MEASUREMENT AND PAYMENT
Change Pay Item 21.01(a)(i) and 21.03(a)(i) to read:
(i) 0.0 m up to 1.5 m cubic metre (m3)
Replace the first and second paragraph under Pay Item 21.02 by the following:
The unit of measurement shall be the linear metre of side drains cleared and
shaped.
The bid rate shall include full compensation for excavating soil material and
any vegetation to facilitate proper run-off and will generally involve deepening
the drains up to a maximum of 0.20 m including the disposal and haulage of
the excavated material and vegetation as directed.
Add Pay Item 21.19 at end of Clause 2107 of the Standard Specification as
follows:
ITEM UNIT
21.19 Synthetic-fibre filter fabric, square metre (m2)
150 g/sq.m.
The unit of measurement shall be the square metre of area covered with
synthetic-fibre filter fabric.
The bid rate shall include full compensation for procuring, furnishing and
installing the synthetic-fibre filter fabric, including wastage and overlap.
66
2200 PREFABRICATED CULVERTS
2204 CONSTRUCTION METHODS
Replace the second and third paragraph of Clause 2204 of the Standard
Specifications by the following:
The duct marker block shall be constructed by Class 30 concrete with cross
sectional dimensions of 100 x 100mm and total length of 750mm.
Add at the end of second paragraph under Pay Item 22.03 in the Standard
Specifications the following:
The bid rate shall also include for jointing with existing pipes where culverts
have to be extended. Any concrete required for the jointing or for bedding,
haunching and surround will be paid for separately under Item 22.07.
Add Pay Item 22.07(f) at end of Pay Item 22.07 of the Standard Specification
as follows:
67
ITEM UNIT
(f) Precast concrete end unit for 600 mm number (no.)
diameter access culvert including
reinforcement in accordance with the
Drawings
Add at the end of the penultimate paragraph of Pay Item 22.12 in the Standard
Specifications the following:
Plain concrete shall, for the purpose of this item, be deemed to include stone
masonry and brickwork.
Delete entire Pay Item 23.06 of the Standard Specification and substitute by:
ITEM Unit
23.06 Inlet, outlet, transition and similar concrete
structure for slope drains
(a) Concrete Class 25 including formwork cubic metre (m3)
Add Pay Item 23.16 at end of Clause 2307 of the Standard Specification as
follows:
ITEM UNIT
23.16 Slope drain of 300 mm diameter reinforced metre (m)
concrete pipe
The bid rate per metre shall include full compensation for procuring, furnishing
and installing the completed slope drain as specified and all excavation and
the preparation of bedding, backfilling, formwork and finishing required.
68
2500 PITCHING, STONEWORK AND PROTECTION AGAINST EROSION
2508 MEASUREMENT AND PAYMENT
Add at the end of Pay Item 25.03 under Clause 2508 of the Standard
Specifications the following:
Add Pay Item 25.08 at end of Clause 2508 of the Standard Specification as
follows:
ITEM UNIT
25.08 Reinforced concrete erosion cubic metre (m3)
checks including reinfircement
and formwork
The bid rate per metre shall include full compensation for procuring, furnishing
and installing the completed slope drain as specified and all excavation and
the preparation of bedding, backfilling, formwork and finishing required.
2600 GABIONS
2602 MATERIALS
Replace entire Sub-clause 2602(d) of the Standard Specifications by the
following:
69
Table 2602/2: Zinc coating
Nominal diameter of coated Mass of coating (g/m2 surface area)
wire(mm)
Below 2.2 245
2.2-2.9 260
3.0-3.6 275
3.7-4.0 290
The adhesion of the zinc coating to the wire shall be such that when the wire is
wrapped six turns round a mandrel of four times the diameter of the wire, it
shall not flake nor crack to such an extent that any zinc can be removed by
rubbing with the bare fingers.
Wire mesh shall comply with the requirements of SABS 1580 or equivalent.
The wire mesh shall be hexagonal-woven mesh wherein the joints are formed
by twisting each pair of wires through the three half turns. The tightness of the
twisted joints shall be such that a force of not less than 1.7 kN is required
when pulling on one wire in order to separate it from the other wire provided
each wire is prevented from turning the applied forces and the wire are all kept
in the same plane.
The diameter of the wire and the size of mesh used shall be as follows:
Table 2602/3: Mesh size and wire diameter
The shorter dimensions of the mesh shall be taken from centre to centre of the
twisted joints, and the larger dimensions shall be between the inside ends of
twisted joints.
70
2603 CONSTRUCTION OF GABION CAGES
Replace first paragraph of Sub-clause 2603(b) of the Standard Specifications
by the following:
The cut edges of all mesh used in the construction of gabions, except the
bottom edge of diaphragms and end panels, shall be selvedge with wire as
specified in Table 2602/3 above.
Such timber shall not be used by the Contractor and shall remain the property
of the owner or legal occupants of the land unless otherwise agreed on with
the Engineer.
Borrow pit and quarry plans are included in the Soils and Materials Report,
that has been issued for information purposes only and do not form part of the
Contract Documents. The purpose of borrow pit and quarry site information
given in the Soils and Materials Report is to illustrate the availability and
71
quality of potential materials sources. Any assessment and conclusions made
by the Contractor based on the information provided is at his own risk.
Full-scale laying and compaction of site trials shall be carried out by the
Contractor on all earthworks and pavement materials to be incorporated into
the Works, using the construction plant and methods proposed by the
72
Contractor. The trials shall be carried out with the agreement, and in the
presence of the Engineer's Representative.
The trials shall be carried out to enable the Contractor to demonstrate the
suitability of his mixing and compaction equipment to provide, lay and compact
the material to the specified density and level, and to confirm that the other
specified requirements of the completed earthworks and layers can be
achieved.
Each trial area shall be at least 100 metres long unless otherwise specified
and to the full construction width (half road width where appropriate) and shall
be laid to the specified depth for the material. It may form part of the
permanent works provided it complies with the Specifications. Any areas that
do not comply with the Specifications shall be reworked or removed.
The Contractor shall allow in his programme for conducting site trials and for
carrying out the appropriate tests on them. The trial on each pavement layer
shall be undertaken at least 21 days ahead of the Contractor's intended date
for commencing full-scale work on the particular pavement layer.
The Contractor shall compact each section of trial by the range of compactive
effort, which the Contractor is proposing and if appropriate, the following data
shall be recorded for each level of compactive effort at site trial:
The composition and grading of the material before the site trial;
The composition and grading of the material including stabilising agent, if any;
The moisture content at the time of compaction and the optimum moisture
content for the specified compaction;
The type, size, type pressures, frequency of vibration and the number of
passes of the compaction equipment;
73
At least eight sets of tests shall be made by the Contractor and the Engineer
on each 100 metres for each level of compactive effort. Provided all eight sets
of results over the range of compactive effort proposed by the Contractor meet
the specified requirements for the material, the site trial shall be deemed
successful. The above data recorded in the trial shall become the agreed basis
on which the particular material shall be provided and processed to achieve
the specified requirements.
If during the execution of the Works, the construction control tests indicate that
the requirements for the material are not being consistently achieved, then
work on the layer shall stop until the cause is investigated by the Contractor.
Such investigation may include effect of using other compaction methods,
further laboratory tests and site trials on the material to determine a revised set
of data, as above, which when agreed shall be the basis on which all
subsequent material will be provided and processed to achieve the specified
requirements.
Agreement by the Engineer to a set of data recorded in a site trial shall not
relieve the Contractor of any responsibility to comply with the requirements of
the Specifications.
3600 EARTHWORKS
3601 SCOPE
Replace the first paragraph of Clause 3601 of the Standard Specifications by
the following:
This Section covers work in connection with the construction of cuts and fills,
the removal to spoil of material unsuitable for use or surplus materials not
required for fill or improved subgrade construction, the construction and
compaction of fills and improved subgrade layers with cut material from the
road prism or borrow material from approved borrow pits, the compaction of
the roadbed and finishing of cuts and fills, up to the stage where fills are ready
for the placing of the pavement layers.
74
3602 MATERIALS
Add at the beginning of Clause 3602 of the Standard Specifications the
following:
The applicable climatic zone, as referred to in Table 3602/1, shall be the wet
climatic zone.
3605 EMBANKMENTS
Replace the first sentence of Sub-clause 3605(c) of the Standard
Specifications by the following:
Where the natural cross fall of the roadbed or the existing or already
constructed embankments exceeds 30%, the fills shall be bonded to the
roadbed by means of benches excavated in the roadbed or existing
embankment.
75
Measurement of common excavation to spoil shall exclude any quantity of
material already paid for under other bill items and shall only be applicable for
either material deemed by the Engineer to be unsuitable for the Works or
surplus material not required for fill or improved subgrade construction.
The Contractor shall soon after been given possession of Site carryout
a general repair of the existing roads as shall always be instructed by
the Engineer. This work shall be paid from Items 37.03 and 37.04 as
appropriate. The Contractor shall also comply with requirement of
Clause 1500 of the Standard Specifications for the entire duration of the
Project execution.
3800 STABILISATION
3802 MATERIALS
In Clarification to what provided in Article 3802 (a) and (b), the most suitable
type of stabilizer is Portland cementwith ordinary early strenght (EN 197-CEM1
32.5N)
Replace Ordinary Portland Cement with Protland Cement; and TZS 177:1999
and BS 12 in Clause 3802(a) (ii) by TZS 727:2002 and EN 197:2000
respectively.
76
Replace Note 1 in Table 3802/2 of the Standard Specifications by the
following:
Note 1:
The unconfined compressive strength (UCS) shall be measured after 7 days
airtight curing and 4 hours soaking in water.
(e) Water
Water shall be clean and free from injurious concentrations of acids, alkalis,
salts, sugar and other organic or chemical substances harmful to the finished
soil-cement mix. The water shall have a pH-value between 6 and 8.
If the water used is not obtained from a public drinking water main, tests shall
be required to prove its suitability.
The Contractor shall plan and execute all mix design testing in due course
prior to the planned use of the material in the Permanent Works. The results of
the job mix testing shall be submitted to the Engineer for approval minimum
77
fourteen days before the intended commencement of the Trial Section or the
Works as applicable.
The Contractor is reminded that the compaction of the stabilised material shall
be delayed approx. 4 hours after the mixing-in of the stabiliser and water as
per standard.
The sets of specimens shall be cured for 7 days airtight followed by 4 hours
soaking in water before the Unconfined Compressive Strength is tested.
Each set of specimens shall meet the minimum strength requirement of Table
3802/2.
78
These shall be crushed after 7 days curing and 4 hours soaking. The total
content of stabiliser to be used for in-place stabilisation depends on the
application method. Where manual or mechanical "dry in advance spreading"
methods of cement are employed, the total cement content shall exceed the
nominal design content by 1%-point. Should the effect of this 1%-point
additional cement be considered detrimental, adjustment of the nominal design
content shall be made as approved by Engineer.
3803 CONSTRUCTION
Add at the beginning of Clause 3803 of the Standard Specifications the
following:
79
Replace Sub-clause 3803(a) of the Standard Specifications by the following:
Preparatory works shall be initiated at such time that it will be completed well
in advance of the programmed stabilisation operations. The preparatory works
shall comprise material testing and investigations, excavation and replacement
of unsuitable materials or other works as instructed by the Engineer.
The Contractor shall include adequate time in his construction programme for
execution of such type of investigations and any pre-stabilisation work that
may be needed. Sufficient equipment for execution of the preparatory works
shall be available to match the capacity of the stabilisation operations.
The preparatory works shall be carried out daily by the Contractors soil
investigation team and shall in addition to the above operations include soil
investigations at intervals detailed in Table 3804/1 to classify the material to be
stabilised according to AASHTO M145 (Sieve Analysis, Atterberg Limits and
Free Swell). The Engineer may instruct new mix design investigations should
the soil classification differ from the approved mixes.
80
The moisture content of the stabilised material shall after mixing-in the cement
and water be such that the specified compaction level can be reached. Any
section where the moisture content of the mixed material is too high to obtain
the specified compaction shall be rejected and immediately removed.
The Contractor shall not mix in the cement and water on a larger area than he
will be able to complete and compact within the specified time limit.
Construction Joints
The Works shall be planned and executed in a way that will minimise the
number of longitudinal and transverse construction joints.
Full width working, without longitudinal joints shall generally be preferred. Half-
width working may be accepted by the Engineer where this is required to
maintain traffic on the other half-width.
The free edge of the first half shall be provided with sufficient over-width from
the theoretical edge of the stabilised area to provide confinement for the
compaction of the stabilised material.
Great care shall be exercised when constructing joints to ensure that all
material along a joint is stabilised, but also to avoid double-dosing along the
joint. Overlap into stabilised material more than 4 hours old will require
additional cement whereas the need for additional moisture may be less in the
overlap zone as compared to the untreated material.
Longitudinal Joints
To ensure complete reworking across the full width of the road, longitudinal
joints between successive cuts shall overlap by minimum 200 mm. The
overlap shall be larger if required to reach sound, well-compacted cement
treated material having correct level, crossfall and thickness. The overlap shall
be marked-out with cut lines.
The Contractor shall pre-mark cut-lines on the surface and the soil stabiliser
machine shall be steered so as to accurately follow the cut lines. All cut lines
81
shall be approved by the Engineer prior to commencement of the cut. Any
deviation in excess of 50 mm from the cut lines by the soil stabiliser machine
shall be rectified immediately by reversing to where the deviation commenced
and reprocessing along the correct line, without the addition of any further
water or stabilising agent.
The location of longitudinal joints should avoid the wheel paths of slow-moving
heavy vehicles.
The Contractor shall prepare a cut plan detailing each overlap where the
overlap shall be subtracted from the drum width to determine the effective
stabilising width for each cut. This in turn will govern the quantity of water and
cement to be added.
Transversal Joints
Overlap shall be made between transverse joints in successive cuts by the soil
stabiliser machine. The previously laid material shall be treated again. The
overlap measured from the centre of the milling drum shall be minimum 0.75m,
but larger if required to reach sound, well-compacted cement treated material
having correct level, crossfall and thickness. All cut lines shall be approved by
the Engineer prior to commencement of the cut. Care shall be taken to ensure
that the material at the overlap length is not becoming excessively moist thus
hindering proper compaction of the material.
Trial Section
The Contractor shall perform a trial section and submit a detailed Trial Section
Report with his observations and recommendations based on the trial. The
Contractor shall not be allowed to commence construction of the permanent
work until trial sections have been finished and the Trial Section Report
approved by the Engineer.
82
Determine the need for pre-pulverising passes in addition to the passes
required to mix-in of cement and water;
Determine the effect on the grading of the natural gravel materials by varying
the forward speed of the mixing machine and the rate of rotation of the mixing
drum;
Determine the sequence and manner of rolling to comply with the minimum
compaction requirement. This shall be confirmed by at least 4 in-situ
compaction tests for each roller pattern;
Each trial section shall be at least 50 m in length of full-road width and include
longitudinal and transversal joints. The transversal joints shall be both "fresh"
and "hardened". Should the Contractor make any alterations in the methods,
processes, equipment or materials used, or if he is unable to comply
consistently with the Specifications due to changes in the in-situ materials, or
any other reason, he may be required to undertake further demonstrations
before continuing with the permanent work.
Should the trial section not be satisfactory, the Contractor shall demonstrate
his capability to satisfactorily construct the pavement in subsequent trials
without additional payment.
The trial sections shall be carried out at locations approved by the Engineer.
The Contractor shall prepare the subgrade and underlying layers in a way that
will resemble the actual conditions. The trial sections shall be removed and the
area restored unless otherwise directed by the Engineer.
83
The trial section shall be constructed at least 14 days in advance of the
proposed start of the work. At least 14 days prior to the construction of the trial
section, the Contractor shall submit for the Engineer's approval a detailed
Method Statement.
Construction methods for transverse and longitudinal joints of each type (full-
width/half-width construction) that are to be included in the permanent work;
Quality control programme.
Approval of the Trial Section Report shall be given when a trial section
complies with the Specification. The Contractor shall not proceed with normal
working until the trial section has been approved and any earlier defective trial
sections have been removed, if so instructed by the Engineer.
When approval has been given, the materials, plant, equipment and
construction methods shall not thereafter be changed, except for normal
adjustments and maintenance of plant, without the approval of the Engineer.
Any changes in materials, plant, equipment, and construction methods shall
entitle the Engineer to require the Contractor to lay a further trial section as
described in this Clause to demonstrate that the changes will not adversely
affect the permanent works.
84
Add after the first paragraph of Sub-clause 3803(c) of the Standard
Specifications the following:
The target moisture content of the stabilised material should be the OMC, but
trial sections with the actual material might indicate that a somewhat drier mix
is preferable.
The mass and/or pressures of the rollers shall be adequate to ensure proper
full-depth compaction to comply with the specifications or surface finish and
density.
The curing method shall be method (ii) of the Standard Specifications i.e.
protection by covering the stabilised surface with the specified crushed
aggregate base course material, which shall be placed, compacted and kept
wet or damp until the prime coat for the asphalt layer is placed.
The Contractor shall protect and maintain the completed layer until the next
layer is applied. In addition to frequent light watering to prevent drying-out,
maintenance shall include the immediate repair of any damage to or defects in
the layer and shall be repeated as often as necessary. Repairs shall be made
so as to assure that an even and uniform surface is restored after completion
of the repair work. The cost of such repairs shall be borne by the Contractor
even when damaged by early trafficking.
85
Over-watering shall be avoided so as not to disturb the subgrade or cause
segregation to either the stabilised material or the protective layer, should the
protective layer form part of the next layer.
Plant used for application of water, dumping and spreading material on top of
the stabilised surface and any other work operations shall not damage the
stabilised layer. Any such damages shall be repaired to the satisfaction of the
Engineer who may instruct that the damaged section be removed and
completely re-worked.
Where the underlying layer does not meet the specified requirements;
When the moisture content of the material to be stabilised exceeds its
optimum moisture content;
When rain is imminent;
After sunset;
When at any location the moisture content of the material to be stabilised is
too high or too low to allow compaction according to the specifications;
When the layer is soft, i.e. moving excessively under load
Excessive drying out or rain falling on the working area during the process of
stabilisation may be sufficient cause for the Engineer to order any affected
areas to be reconstructed at the Contractor's own cost
Should the in-situ material be too moist it shall be ripped and dried-out prior to
any stabilisation activity.
86
Strength of Stabilised Material
No single value of the UCS measured on laboratory samples after 7 days
curing in airtight plastic bags and 4 hours soaking in water shall be less than
the minimum value specified in Table 3802/2.
The UCS strength of individual cores shall not be less than 90% of the
minimum value specified in Table 3802/2.
Water BS 1377:Part 3 Min 1 test per source, min 1 pH test per week
Mixtures: Every change in aggregate or design but at
least:
Moisture content CML 1.1 Min 3 tests per production day
Compaction test (BS CML 1.9 1 tests per week or at changes in material
Heavy) composition
UCS (7 days airtight CML 1.21 Min 4 per production day
cured and 4 hours
soaked)
Constructed layers:
UCS at 7 days age of CML 1.21 One core per 300m2; minimum 4 cores per
layer and 4 hours production day. Diameter of cores shall be
soaking of cores 150mm
Thickness of core Same cores as used for UCS
samples
Field density AASHTO T191 Refer Table 7110/1
87
Test Test method Testing frequency
Cement content AASHTO T211 3 tests per day
Surface levels Full cross sections every 25m
Surface regularity Two longitudinal and two transversal
measurements every 25m or as instructed by
the Engineer
Layer Thickness
The average layer thickness measured on core samples for each day’s
production shall not be less than the specified nominal thickness and no single
values shall be less than the specified nominal thickness minus 10mm.
In-situ Compaction
The minimum required compaction density for the stabilised subbase layers
shall be as specified in Sub-clause 3803 (i).
Amount of Stabiliser
The average amount of cement in the treated material measured within each
lot shall not be less than the Mix Design Cement Content. No single values
shall be less than 70% or more than 130% of Mix Design Cement Content.
The stabilisation work, excluding the cost of supplying the stabilising agent,
shall be paid as full cost rate under Item 38.02.
The payment for the stabiliser agent is paid for under Item 38.03.
88
Replace Sub-clause 38.05(c) of the Standard Specifications with the following:
The unit of measurement shall be the cubic metre of stabilised material, the
quantity of which shall be determined in accordance with the authorised
dimensions of the layers treated as instructed by the Engineer.
The bid rates for chemical stabilisation under Item 38.02(c) shall include full
compensation for all preparatory work such as reworking, aeration and
homogenising the material to be stabilised, procuring all materials (excluding
stabiliser agent), breaking down, placing, spreading and mixing-in the
stabiliser agent, curing including any curing membrane, any extra water
required, and all materials, supervision, labour, plant, equipment, tools and
incidentals, compacting, testing the material including the protection and
maintenance of the layer, all as specified.
3902 MATERIALS
Add at the end of Sub-clause 3902(d) of the Standard Specifications the
following:
The grading of the crushed aggregate base shall be within and approximately
parallel to the grading envelope given in Table 3902/1 for a 50mm (coarse
type). If the Contractor is unable to achieve the required grading directly and
continuously from multi stage crushing, it will be necessary for him to screen
89
the material into at least four fractions and reconstitute the material to conform
to the Specifications by mixing it together in a pug mill.
In all cases the material shall be conditioned by the addition of water in a pug
mill to bring it to the correct uniform moisture content for the compaction as
determined in the compaction trials. After the addition of water the material
shall be transported for laying and compaction without delay.
3903 CONSTRUCTION
Add the following paragraph at the end of Sub-clause 3903(c) of the Standard
Specifications:
Crushed stone base material, CRR shall be laid by an approved type of self-
propelled mechanical spreader and finisher capable of laying to the required
widths, thicknesses, profile, camber or cross-fall, without causing segregation,
dragging or other defects.
The paver shall be provided with skid beams and fitted with automatic
electronic screed controls which can even out local irregularities and ensure a
constant crossfall.
Add at the end of Sub-clause 3903(d) (ii) of the Standard Specifications the
following:
90
4000 BITUMINOUS LAYERS AND SEALS
4102 MATERIALS
Add at the end of Sub-clause 4102 (c) of the Standard Specifications
the following:
(d) General
The Contractor shall submit samples of the bituminous material that he
proposes to use, together with a statement as to its source, character
and all laboratory test results as specified in AASHTO M56, AASHTO
M140 and/or AASHTO M208 and written approval shall be obtained
before supplying such material to Site. The Contractor is advised to
initiate this process in due time before the intended start date for use of
the material. The actual choice of material to be used on the stabilised
subbase shall be based on trial section.
91
acceptance. All such test reports shall be subject to verification by
testing samples of materials received for use on the project.
Prime coat shall be applied with a spray rate of 0.8 litre/m2 - 1.2 litre/m2
with MC-70 medium curing cut-back bitumen equal to a bitumen residue
rate of 0.4 litre/m2 - 0.6 litre/m2. For tender purpose a spray rate of 1.0
litre/m2 has been assumed. The exact rate of application, which may be
varied to suit field conditions, will be determined following trials to be
carried out by the Contractor. Those trials shall be performed to the full
satisfaction of the Engineer and shall not be less than 50m in length
and the full width of one lane.
Replace the third paragraph after Table 4106/1 in Clause 4106 of the
Standard Specifications by the following:
The total width of primed surface shall be 150mm wider than the
specified width of the bituminous surface dressing.
92
4107 MAINTENANCE AND OPENING TO TRAFFIC
Add the following at the end of Clause 4107 of the Standard
Specifications:
The prime coat shall be left undisturbed until it has penetrated and
cured sufficiently so that the wheels of passing vehicles will not pick it
up.
Where no convenient detour is available for traffic, operation shall be
confined to one half the roadway widths at a time. The Contractor shall
provide proper traffic control in order that vehicles may proceed without
damage to the primed area. The primed surface shall be inspected and
repaired, if necessary, prior to the next layer being placed if the surface
has been opened to traffic.
4108 TOLERANCES
Change the deviation allowed from 0.10 l/m2 to 10% of target spray
rate.
Add the following at the end of the second paragraph after Pay Item
41.02 in Clause 4110 of the Standard Specifications:
93
This section covers all work in connection with the construction of hot
mixed bituminous concrete layers. These works include the procuring
and furnishing of aggregate, bituminous binder, mixing at a central hot
mixing plant, haulage, paving and compaction of the mixture, testing,
etc., all as specified for the construction of virgin hot mixed bituminous
materials.
4202A MATERIALS
Add after the first paragraph of Sub-clause 4202(a) of the Standard
Specifications the following:
94
(a) Replace Table 4202/1 with the following:
The bitumen used for all asphalt concrete works shall be performance
grade bitumen as specified in AASHTO M320 Table 1.
The certificate shall include all test data necessary to classify the
bitumen according to EN 12591. It shall further include the
manufacturer's recommendations for mixing and compaction
temperatures of bitumen with mineral aggregate in (i) the laboratory;
and (ii) in the asphalt plant and field paving.
95
Identification of a capable and independent bitumen testing laboratory
for comparative testing of binders;
Active filler (Cement) shall have at least 70% by mass passing the
0.075 mm sieve, all passing the 0.600 mm sieve.
96
Active filler for use in bituminous courses shall be introduced to the mix
prior to wetting with the binder. Payment would be made separately for
Active Filler (Cement). Measurement & Payment would be made as per
item no SS.42.05. of these Special Specifications.”
All gradations of coarse and fine aggregate shall comply with the
requirements detailed in Table 4202/2 when tested in accordance with
the specified standards.
The Laboratory Job-Mix Formula for the Wearing Course shall combine
mineral aggregates, bitumen and, if required, filler using the test methods and
standards for Superpave mix design as detailed in the AASHTO T 312.
98
The proposal shall further include information on storage, handling, mixing,
paving and compaction temperatures as detailed. The information in the table
shall either originate from certified test reports submitted by the Manufacturer
or be based on viscosity measurements as included in the “MS-2 manual,
latest edition”.
Full scale mixing, laying and compaction site trials shall be carried out by the
Contractor on all asphalt pavement materials proposed for the Works using the
construction plant and methods proposed by the Contractor for constructing
the Works. The trials shall be carried out with the agreement, and in the
presence of the Engineer, at a location approved by the Engineer. Following
laboratory and site trials by the Contractor, the Engineer will approve the
proportions of the working mix.
The Gmm value shall be tested and determined at all bitumen contents. The
loose mixture samples shall be short-term aged in accordance with AASHTO
R30 for two hours at the compaction temperature prior to compaction by the
Superpave Gyratory Compactor.
99
The Design requirement for Asphalt Concrete employing Superpave Mix
Design to be as per the “MS-2 manual, latest edition”.
The gyratory measured sample heights at Nini, Ndes and Nmax shall be
reported together with mould diameter and mass of asphalt in mould allowing
calculation of Gmb at each densification level. Gmb shall further be
determined as per AASHTO T166 and a correction factor between calculated
and laboratory determined Gmb at Nmax shall be established. This factor shall
be determined for each production date.
Replace the first line in the first paragraph of Sub-clause 4204(c) of the
Standard Specifications with:
100
The Engineer may instruct that hauling equipment shall have an engine
exhaust system blowing the gas vertical not to cause inconvenience to the
paving crew.
Tack Coat of 57% stable grade bitumen emulsion (K-1-60), spread rate of 0.4
litres per square metre. . The exact rate of application, which may be varied to
suit field conditions, will be determined by the Engineer following trials to be
carried out by the Contractor.
The manufacturer of the bitumen shall inform the maximum storage and
mixing temperatures of the approved bitumen.
The mix at delivery to the paver shall be not more than 10 oC below discharge
temperature at the mixing plant. The minimum temperature for the
commencement of breakdown rolling shall be determined on trial sections. Mix
loads of temperature less than the minimum temperature shall be disposed of.
101
4207A SPREADING THE MIXTURE
Add before Sub-clause 4207 (a) (i) of the Standard Specifications the
following:
The asphalt plant mixing capacity, the asphalt haulage fleet, the operating
speed of the asphalt paver, the number of rollers, etc. shall be so coordinated
to ensure continuous paving to avoid intermittent stopping of the paver.
Add at the end of Sub-clause 4207 (a) (i) of the Standard Specifications the
following:
The paver shall be equipped with 60°sloped side plates on the screed to
confine and to form a stable and neat permanent outer shoulder edge.
Spreading shall be so arranged that longitudinal joints do not coincide with
joints in the lower layers.
Add at the end of Sub-clause 4207 (a) (ii) of the Standard Specifications the
following:
The adjustment of the screed, tamping bars, feed screws, hopper feed, etc.
shall be frequently checked to ensure uniform pre-compaction and spreading
of the mixtures. If segregation occurs, the spreading operations shall
immediately be suspended until the cause is determined and corrected.
4208A JOINTS
Add the following after the 1st paragraph of Clause 4208 of the Standard
Specification
The Contractor shall mark out the material to be cut back using string line. At
least 100mm shall be cut back but additional material shall be removed should
material still be loose, incompletely compacted or having less height than
50mm.
The cutting shall be performed the same day as paving the adjacent lane and
the joint shall be protected against traffic. Trial sections shall determine
whether the cut shall be vertical full depth or be performed at an angle of 45°.
Cores shall be taken to determine the method resulting in the highest joint
compaction.
102
Add at the end of Clause 4208 of the Standard Specifications the following:
The paved pre-compacted "over height" after the screed shall be carefully
determined on trial sections (with e.g. 10mm and 20mm over-height) and
properly implemented for satisfactory joint construction. Joints shall have the
same texture and density as the remainder of the asphalt course.
4209A COMPACTION
Replace the fifth paragraph of Clause 4209 of the Standard Specification by
the following:
Add after the fifth paragraph of Clause 4209 of the Standard Specifications the
following:
The Contractor shall, when necessary, only employ approved slippage agents
for the rollers. Diesel will under no circumstances be accepted.
Cores shall be extracted from the completed trial section and in locations
determined in a stratified randomly sampled manner.
103
Add before the last paragraph of Clause 4210 of the Standard Specifications
the following:
The Contractor shall for each trial section prepare a plan for execution of the
trial. It shall at least include the following subjects:
Test programme for testing of the mix including binder content (min. 2
samples), gradation (min. 2 samples), Gmb @ Nini, Gmb @ Ndes, Gmb @
Nmax, Gmm, VMA, VFA, Va, dust ratio, IDT and TSR. At least 6 laboratory
prepared specimens shall be made for these tests;
Cutting of 2 samples from the paved trial section area. These samples shall be
tested for rutting under the test conditions specified in Clause 4202 except for
the compaction which shall be that obtained during the trial;
The smoothness of the finished surface shall be tested as specified in this
Clause; and Programme for instruction of every person involved in the trial
section.
The activity plan for the trials shall be forwarded to the Engineer for approval
not less than 7 working days before the planned trials.
104
The Contractor shall assess back-cuttings and separately document that
finished joints satisfy the compaction requirements by taking asphalt cores at a
distance of 50 mm from joints and tentative free edges.
4213A TESTING
In the first paragraph of Sub-clause 4213(b) of the Standard Specifications
delete the second sentence.
Add after the first paragraph of Sub-clause 4213 (b) of the Standard
Specifications the following:
Cores in the carriageway lanes shall be taken at the outer permanent edge, at
the centre of the paved lane and along the longitudinal joint. Cores at the outer
edges and at the joints shall be taken 50 mm from the edge after back-cutting
as approved. Cores in the shoulders shall be taken 300 mm from the outer
shoulder edge and 50 mm from the longitudinal joints to the carriageway
pavement. Cores taken for testing of compaction shall be taken as soon as
possible after the placing of the layer, but under no circumstances later than
seven days after paving. The Contractor is required to have back-up coring
machines available at all times.
Add at the end of Sub-clause 4213 (c) of the Standard Specifications the
following:
The Contractor shall at the start of the project prepare forms and summary
sheets for his reporting and present these to the Engineer for approval. The
digital format of the reporting shall be approved by the Engineer.
105
4214A MEASUREMENT AND PAYMENT
Amend the description of Pay Item 42.01 of the Special Specifications as
follows
ITEM DESCRIPTION UNIT
42.01 (a) Virgin Bituminous Base course:
(i) Asphalt concrete base course, SP37.5,175 mm thickness, using PG70-10 cu.m
penetration grade bitumen, using virgin bituminous surfacing materials.
(ii) Bitumen, PG70-10 penetration grade, for virgin asphalt concrete base course ton
42.01 (b) Recycled Bituminous Base course:( Provisional)
(i) Asphalt concrete base course, SP37.5,175 mm thickness, using PG70-10 cu.m
penetration grade bitumen and reclaimed bituminous surfacing materials with
recycling percentages: (50 % reclaimed and 50% virgin materials)
(ii ) Bitumen, PG70-10 penetration grade, for recycled asphalt concrete base ton
course
42.02 (a) Virgin Asphalt concrete surfacing Wearing Course:
(i) Asphalt concrete surfacing, SP12.5, using PG76-10 penetration grade bitumen, cu.m
50mm thickness
42.02 (b) Bitumen, PG76-10 penetration grade, for asphalt concrete wearing course: ton
42.03 Tack coat of 30% stable grade bitumen emulsion lts
42.04 Additives for Recycled Bituminous base course
(a) Rejuvenator Bitusol 40 or similar kg
(b) Hydrated lime to improve adhesion properties kg
The Active Filler: Cement shall be measured and paid as per actual of the
proportion as obtained from the approved design mix as approved by the
Engineer”.
“Add after the first paragraph of Pay Item 42.02 of the Standard Specifications
the following:
The binder for the asphalt concrete surfacing shall be paid for separately for
the certified asphalt concrete surfacing quantity. The bitumen shall be
calculated from the approved mix design (presenting the bitumen content as a
weight percentage of the total asphalt mix), the certified quantities of asphalt
106
mix and the asphalt densities determined at Ndes. A new mix design and recipe
shall be prepared if, in the opinion of the Engineer, this is warranted due to
significant variations in mix density or other material properties.
The Active Filler: Cement shall be measured and paid as per actual of the
proportion as obtained from the approved design mix as approved by the
Engineer”.
A traffic control plan that includes provisions for the placement and
maintenance of barriers required protecting the pavement from traffic,
for a minimum of 14 days after concrete placement.
Defined provisions for adequate lighting for all work done at night,
including finishing, curing, and sawing joints.
107
If forms are to be utilized define the material, dimensions, type,
connections, and staking of the forms.
Define the procedure for the protection of the fresh concrete pavement
from inclement weather.
Cement
Cement used for concrete shall be Portland cement, Type I or Type II
conforming to AASHTO M 85 or equivalent ISO standard class.
Portland cement, Type II, which has been pre-blended with a maximum
of 15 percent fly ash, by weight, and conforming to AASHTO M 240,
may be used. When blended Portland cement is used, no additional fly
ash shall be added.
Suitable means shall be provided for storing and protecting the cement
against dampness. Cement which for any reason has become partially
set or which contains lumps of caked cement will be rejected. The
temperature of the cement at the time of delivery to the mixer shall not
exceed 71oC.
(b) Water
Water used in mixing or curing shall be clean and free of oil, salt, acid,
alkali, sugar, vegetable, or other substances injurious to the finished
product.
Water will be tested in accordance with and shall meet the requirements
of AASHTO T 26. Water known to be of potable quality may be used
without test.
108
Where the source of water is relatively shallow, the intake shall be so
enclosed as to exclude silt, mud, grass, or other foreign materials.
The Contractor shall submit details of the nominated mix and the
Contractor shall nominate the proprietary source, type and name for
each admixture to be used. Documentary evidence of the quality and
chemicals compatibility shall be furnished by the Contractor to the
Engineer upon request at any stage of the work.
(e) Aggregate
Aggregates from a single source shall be used in anyone construction
work. Unless specifically authorized by the Engineer, the maximum
soluble sulphate salt content of aggregates, expressed as percentage
SO3 by mass, shall not exceed 0.1%.
109
Aggregates containing more than the maximum permissible amount of
sulphates or with visible encrustation of salts shall be washed and
drained before being used in concrete.The Engineer may direct washing
or rewashing of the aggregates until he is satisfied that harmful
quantities of salts are not present.
Fine Aggregate
Fine aggregate can be natural sand, manufactured sand, or a
combination of natural and manufactured sand, meeting the following
requirements:
Manufactured sand shall be made from stone meeting all the quality
requirements for coarse aggregates.
110
Table 4200B-1 Gradation of Fine Aggregate
Coarse Aggregate
Coarse aggregate for Portland Cement Concrete shall conform to the following
requirements:
Sodium sulphate soundness test AASHTO T104, the weighted loss shall not
exceed 15%.
The nominal size of coarse aggregate shall not exceed 37.5mm.When the
spacing between longitudinal reinforcement is less than 90mm, the nominal
size of coarse aggregate shall not exceed19 mm. In addition, when the slab
thickness is 150mm and over but less than175mm, the nominal size of coarse
aggregate shall not exceed 25mm, and when the slab thickness is100mm and
over but less than150mm, the nominal size of coarse aggregate shall not
exceed 19mm.
111
Gradation of Coarse Aggregate are as follows:
Preformed fillers for joints shall conform to AASHTO M33, AASHTO M153
Type II, and AASHTO M213 and shall be punched to admit the dowels. The
filler for each joint shall be furnished in a single piece for the full depth and
width required for the joint.When the use of more than one piece is authorized
for a joint, the abutting ends shall be fastened securely, and held accurately to
shape by stapling or other positive fastening.
The use of preformed, closed-cell, polyethylene foam backer joint filler shall
conform to ASTM D3204, Type I and shall be limited to vertical applications
only.
112
Joint Sealers
Hot-poured joint sealer shall conform to AASHTO M301. Cold-poured joint
sealant shall be silicone type conforming to US Federal Specification TT-S-
1543A, Class A.
All steel shall be clean and free from mill scale, loose rust oroil.
Reinforcement steel may be either deformed steel bars or cold-drawn steel wire
conforming to the following:
Bar Mats
Bar mats shall be cold-drawn steel wire or deformed steel bars from new billet
steel conforming to AASHTO M31M. The bars shall be size No.10. All bars
shall have the tensile requirement of Grade 300 or 400.
Fabrication of bar mats using deformed steel bars shall be in accordance with
ASTMA184/A184M. Barmats fabricated using rolled cold-drawn steel wire shall
be in accordance with ASTM A56.
113
Tie Bars & Dowels
Tie bars shall be deformed bars conforming to AASHTO M31M. All bars shall
have the tensile requirements of Grade 400.
Tie bars for use across joints shall have an epoxy coating conforming to
AASHTO M284/M284 M except that the thickness of the cured coating shall be
250+/- 50 microns.
Dowel bars shall be plain, round bars conforming to AASHTO M254 type A or
B. They shall be free from burring or other deformation restricting slippage in
concrete.
Dowel bars shall be coated with an approved material to break the bond
between the steel and concrete.
Place dowels and tie bars across joints where indicated, correctly aligned, and
securely held parallel to the surface of the finished pavement, such that after
placement they remain in their specified location. The spacing and vertical
location of dowels and tie bars shall be as detailed except where the planned
spacing cannot be maintained because of form length or interference with form
braces. In such cases, closer spacing with additional dowels or tie bars shall be
used.
All reinforcement, dowels and tie bars shall be clean and free of oil, grease,
loose rust and other foreign material when the concrete is placed. Paint free
portions of dowels, including ends, with two coats of bituminous emulsion. The
unpainted portions of dowels shall be installed in the initially placed concrete
slab.
Dowels and tie bars in fixed form paving shall be placed by the bonded-in-place
method. Installation by removing and replacing dowels and tie bars in
preformed holes, including their withdrawal to assist in form stripping,will not be
permitted.
114
(h) Curing materials
Curing materials for Portland cement concrete shall conform to the following:
Liquid membrane:-forming compounds shall conform to AASHTO M148, Type
1-D, clear or translucent with fugitive dye, or Type 2, white pigmented.
Burlap cloth:- made from jute or kenaf shall conform to AASHTO M156, Class
4.
The concrete shall contain the amount of cement as directed by the Engineer
115
Water cement ratio, including moisture on the aggregates, shall not be more
than 0.53. This shall be maintained by use of chemical admixtures and or
additional if necessary.
Air Content:- Where the Contractor wishes to use an air-entraining agent, the
total air content in the freshly mixed concrete shall be M±1%, where M is the
target value within the limits of 2% to 4%. Tests shall be conducted in
accordance with ASTM C231.
The percentage of entrained air voids in the mix shall be from 3 to 6 percent.
Where concrete is to be cast between fixed forms the nominal maximum size
of the mix shall be 40mm.
(2) The quantity of water added shall only be sufficient to produce a dense
concrete which can be fully compacted without undue difficulty, due allowance
being made for the moisture content of the aggregates.
116
The strength class of concrete shall be as designated in the following Table.
If during the progress of the work the requirements set out in Sub-clause 4202
B (j) are not being met by concrete manufactured from the materials or material
mix proportions being used, the Contractor shall immediately cease producing
such concrete and shall effect such changes to the mix proportions and/or
materials as may be necessary inorder to meet those requirements.
If during the progress of the work the Contractor wishes to use materials or mix
proportions other than those originally approved, or If the materials from the
sources originally approved change in regard to properties, he shall before
proceeding with further work submit adequate evidence to the Engineer that
the new materials or combination of materials will produce concrete which
complies with the requirements of Sub-clause 4202 B(j) and will not bring about
detrimental changes in the properties of the concrete.
117
Where concrete is placed by hand and vibrated or finished with hand
equipment, the requirements of Sub-clause 4202B (j) shall remain applicable
irrespective of thesize of the concrete panel or concrete patch placed. The mix
proportions, however, shall be adjusted to promote hand placing, vibrating and
finishing, and only if the Contractor has produced written proof to the Engineer
that the requirements of Sub-clause4 2 0 2 B (j) can not be complied with under
the circumstances, will the Engineer change the requirements in accordance
with Sub-clause 7102(j)(ii)4 at his own discretion.
Changes in Requirements
The Engineer shall have the power, at any time during the progress of the
work, to order changes in the requirements set out in Sub-clause 4202B(j). In
such cases, the Contractor shall be compensated in accordance with the terms
of the General Conditions for the additional cost of materials or additional
handling, placing and/or other costs, if any, entailed by such changes. If such
changes result in savings, the Engineer shall recover such savings from the
Contractor.
Stockpiles shall be built up in layers of not more than 3feet in thickness. Each
layer shall be completely in place before beginning the next, which shall not be
allowed to cone down over the next lower layer. Under no circumstances will
coningof stockpiles be permitted.
Aggregates from different sources shall not be stockpiled together unless
approved by the Engineer.
The fine aggregate and coarse aggregate shall be separately weighed into the
hopper in the respective amounts set by the Engineer in the job mix approval.
Cement shall be stored in a silo or in a dry weather proof shed with a raised
wooden floor, and each consignment shall be stacked separately. Cement shall
be used in the order in which it has been delivered at the site.
118
The varioustypes ofadmixtures shall be properlymarkedandstoredseparately.
Transporting
When mixing of the concrete is to be done at the job site, materials shall be
transported from the batching plant to the mixer in vehicles appropriate for this
job.
In the dry batch process, bulk cement shall be transported to the road side
paver in water tight compartments carrying the full amount of cement required
for the batch, or, if permitted, between the fine and coarse aggregate.
The time lapse from the moment when the cement and aggregate are
intermingled up to the time of placing and compacting the concrete shall not
truck agitators, and shall not exceed 45minutes in mild weather or 30minutes
when the concrete is transported in ordinary trucks.
Proportioning theComponents
All components shall be accurately proportioned in approved automatic
proportioning devices to within the following tolerances, and supplied
separately at the mixing drums.
119
of proportioning the admixture in quantities which will not deviate by more than
2% from the required quantities, and shall be done so as to spread the agent
uniformly throughout the entire concrete mix during the mixing process.
Water for the mix may be measured by volume or by weight. The accuracy of
the water measuring equipment shall be within a range of error of not over 1%,
and shall be so arranged that the measurement will not be affected by
variations of pressure in the water supply line and will be accurate under all
construction conditions encountered.
Methods and equipment for adding air-entraining agent or other admixtures into
the batch, shall be as recommended bythe manufacturer.
Mixing the Concrete
Batch mixing
The mixing period shall be at least 90seconds, but may be reduced to as little
as 50seconds or increased by the Engineer if necessary, to produce a
homogeneous mass.
The production capacity of the mixing plant shall be inaccordance with the
capacity of the paver used. Where the mixing plant is supplied with more than
one drum, the same unit shall be used for proportioning the components.
The drums shall always be kept clean, and all build-up shall be removed. The
total period between the times that the cement is placed in the drums until
mixing starts shall not exceed 15minutes.
An overload upto 10% above the mixers nominal capacity may be permitted
provided concrete test data for strength, segregation, and uniform consistency
is satisfactory and no spillage of concrete occurs.
Concrete shall not be mixed when either the coarse or fine aggregate contains
frozen particles. No more concrete shall be mixed than can be placed, finished
and covered during day light, unless the Engineer approves an artificial lighting
system.
120
Transit-mixing
The Contractor will be permitted to use appropriate truck mixers, which agitate
previously mixed concrete in transit.
Mixed concrete from the central mixing plant shall be transported in truck
mixers, truck agitators or non agitating trucks. The time elapsing from the time
water is added to the mix until the concrete is deposited in place shall not
exceed 30minutes when the concrete is hauled in non-agitating trucks, nor
60minutes when hauled in truck mixers or truck agitators.
The Contractor shall note the provisions regarding the construction tolerances
for underlying pavement layers and shall make provision in his prices for any
additional concrete, which may be necessary in respect of irregularities in the
layer underlying the concrete pavement.
The Sub-base shall include an area 900mm in width extending beyond the
edges of the base-course or pavement unless shown otherwise on the plans.
When curb and gutter is constructed contiguous with the pavement the sub-
base shall include an area two 610mm in width extending beyond the back of
the curb and gutter.
121
Conditioning of sub-base or base course
Compaction
The entire sub-base or base layer shall be thoroughly compacted. Any portion
of the sub-base that is not accessible to a roller shall be compacted with
handtampers to obtain the density requirements for the material.
Wetting the sub-base
The sub-base shall be kept continuously wet for a period of atleast one hour
before the concrete is placed. Immediately before the concrete is placed, the
excess water shall be broomed off the road ahead of the paver so as to ensure
that the sub-base will still be damp when the concrete is placed, but no
puddles of water or deleterious matter shall be left on the road.
Protection
Before placing any surfacing material on any section, ditches and drains along
that section shall be completed to drain the subgrade effectively. Until the sub-
base or base has been checked and approved, no material shall be deposited
thereon.
Before any pavement concrete is placed, the bituminous prime coat shall be
checked and any area shaving deficient or poor coverage, or where the
bituminous coating has been damaged, shall be repaired as directed by the
Engineer. The sprayed surface shall then be thoroughly cleaned. The
bituminous prime coat shall be dry before any reinforcing steel, tie bars, dowels
or concrete maybe placed.
122
4204B PREPARING THE UNDERLYING LAYERS
Compacting
The concrete shall be fully compacted by means of approved equipment
and shall be free from honeycombing and planes of weakness. The
average amount of air voids as measured in concrete cores shall not
exceed 3% without air-entrainment when measured byASTM C173.
shall be reduced by half an hour for every 5oC by which the concrete
permitted bytheEngineer.
123
When rain appear to be imminent, all paving operations shall cease and
the Contractor shall take the necessary steps to protect the unhardened
concrete. The Contractor shall be responsible for the repair of any
damage to the concrete, the texturing or the curing compound that may
occur.
Cold-weatherpaving
All reasonable precautions shall be taken to prevent the temperature of
the pavement concrete from failing below 5oC during the first 48 hours
after casting.
Concrete shall not be mixed when either the coarse or fine aggregate
contains frozen particles.
Hot-weather paving
When paving is done during hot weather and when the temperature of
the fresh concrete can be expected to exceed 25oC, the Contractor
shall implement appropriate precautionary measures to place the
concrete at the coolest temperature practicable.
124
low humidity, wind, rain and hail) shall be removed and replaced at the
Contractor’s expense.
Maintaining continuity during placing
The Contractor shall make adequate advance arrangements for
preventing delay in delivering and placing the concrete.
An interval of more than thirty minutes between the placing of any two
consecutive batches or loads of concrete shall constitute sufficient
reason for the Engineer to have the paving operations stopped, and the
Contractor shall then, at his own expense, make a construction joint in
the concrete already placed, at the location and of the type directed by
the Engineer.
Width of placing
Where the forms are tested with a 3m straight edge, the top edge shall
not deviate by more than 3mm at any place, neither the sides by more
than 6mm. The sides shall not deviate by more than 3mm from the
vertical. The height of the side-forms shall not be less than the nominal
thickness of the concrete slabless 15mm, and the resulting opening
between the side-forms and the layer on which it is supported shall be
caulked with a stiff mortar consisting of one part of rapid-hardening
cement and 3 parts of sand by volume and finished vertically on the
inside, and the mortar shall have hardened before any concrete may be
cast against it.
125
Therails,side-
formsandrunningsurfaceshallbekeptcleaninfrontofthewheelsofallpavinge
quipment.
Rails
The wheels of spreading and finishing machines and frame-mounted
covers shall not run directly on the top surface on the side-forms but on
rails rigidly attached to the forms, unless the forms are specially made to
double as rails.
Guide wires shall be so designed, manufactured and fixed that the paver
will be capable of producing a completed slab,which will comply with the
requirements of Clause 3918A.
Other control methods will also be considered, and should the Engineer
be satisfied that they will produce satisfactory results, their use will have
to be approved in writing.
126
Inspection of side-forms, guide wires and rails
Before any concrete may be cast, the Engineer shall approve all
assembledside-forms, guide wires and rails. For this purpose, the
Engineer shall be given sufficient notice and opportunity.
Approvalby the Engineer will not relieve the Contractor of any of his
obligations to construct the concrete slab in accordance with the
specified dimensions and tolerances.
Placingand Spreading
The concrete shall be spread uniformly by means of a purpose-made
mechanical hopper spreader running on rails and capable of spreading
the concrete uniformly to a specified level and to a uniform uncompacted
density over the entire surface of the slab. The machines shall be
capable of being rapidly adjusted for changes in slab thickness or
crossfall.
Compaction
The concrete shall be fully compacted by vibration or by a combination
of mechanical surface vibration, internal vibration and tamping. The
power supply to the vibrators shall cut out automatically as soon as the
compaction equipment stops moving.
Suitable internal vibrators shall be used against the side forms and at
joint assemblies to ensure compaction throughout the pavement layer.
Final Finishing
The surface of the concrete shall be finished smooth and true to grade
and level by means of an initial finishing machine equipped with a
transverse or oblique oscillating beam.
The final finish of the surface of the slab shall be carried out by a
machine that incorporates twin oblique oscillating finishing beams.The
beams in the case of both machines shall be readily adjustable for both
height and tilt. The leading beam shall be vibrated. The beam shall be
127
supported on a carriage with two wheels on either side, atleast 4metres
apart in the longitudinal direction. The oscillating beams shall be of
rectangular section, spanning the full width of the slab and each
weighing not less than 170kg/m.
Before the concrete starts setting, all pavement edges and the edges of
joints shall be rounded off to the prescribed radius.
After finishing, the Contractor shall test the concrete surface with a
straight edge of atleast 3metres in length. Irregularities indicated by the
straight edge shall be removed with a long-handled hand-operated
scraping straight edge of atleast 3metres length. A gang plank shall be
used when walking on the concrete.
128
4207B PLACING, COMPACTING AND FINISHING WITH SLIPFORM
EQUIPMENT
General
Slipform paving equipment shall be used for spreading, compacting,
floating and finishing the concrete in a continuous operation and in such
a manner that a minimum of finishing by hand will be required and a
dense and homogeneous concrete to the proper level and grade will be
produced.
The deposited concrete shall be struck off to the necessary average and
differential surcharge by means of a strike-off plate or screw auger
device extending across the entire width of the slab. The strike-off
equipment shall be capable of being rapidly adjusted for changes in
slab thickness or crossfall.
129
After the concrete has been finished by the finishing devices
incorporated in the slipform paving equipment, the surface of the
concrete shall be checked by means of a straight-edge of not less than
3.0metres in length. High spots indicated by the straight edge shall be
removed by hand floats.
After the final finishing and texturing of the concrete, but before curing,
the pavement edges shall be rounded to the prescribed radius.
Track support
The Contractor shall at his own cost ensure that adequate track support
is provided to suit the needs of the slip form paver, either by extending
the upper pavement layers or by providing alternative support layers.
Forms
Side forms complying with the requirements of Clause 3905A shall be
used.
130
The concrete shall be placed and spread uniformly to a surcharge of
about one-fifth more than the final pavement thickness and shall then be
compacted, struck off and finished to the level of the side forms.
The surface shall be regulated and finished to the level of the side forms
or adjacent slabs by using twin vibrating beams. The beams shall be of
metal with a contact surface atleast 50mm wide and a vibrating unit
having a minimum centrifugal force of 4kN with a frequency
recommended by the manufacturer or an equivalent compactive effort.
The vibrating beams shall be moved forward at a steady speed of 0.5m
to 1.0m per minute while vibrating over the compacted surface, to
produce a smooth finish.
131
reinforcement sheets. Alternatively, the reinforcement may be butt
welded.
132
Jointed reinforced concrete slabs
The reinforcement shall be so placed that after compaction of the
concrete, the cover below the finished surface of the slab is as indicated
on the Drawings, with a tolerance of +/-10mm for slabs less than 270
mm thick and +/- 2 mm for slabs 270 mm thick or more.
The vertical cover between any longitudinal joint groove forming strip
and any reinforcement shall be a minimum of 300 mm.
133
4210 B SURFACE TEXTURE
General
After the concrete has been placed, spread, compacted, finished and
completed and before the curing membrane is applied, the surface of
the concrete shall be provided with a surface texture.
The surface texture shall be applied and completed before the concrete
is so hard that the surface will be torn and coarse aggregate unduly
loosened during texturing.
Equipment
The required texturing shall be effected by means of a machine which
spans the full width of the concrete pavement and which is guided in
regard to both level and direction by the rails in the case of side form
construction or by the paver guide wires in the case of slipform
construction.
The dimensions of the burlap drag shall be such that atleast 1.0m of the
material is in contact with the surface of the concrete pavement
measured in the direction in which the drag is being moved. The burlap
with the bottom layer atleast 150mm longer than the top layer at the
dragging end; however, at the discretion of the Engineer, the number of
layers may be increased to four. The transverse threads of the trailing
150mm to 300mm of the burlap drag shall be removed.
134
Tine Grooving Device (GroovingComb)
The pavement shall be grooved by means of a metal tine grooving
device. The tines shall be made from flat spring steel approximately
0.6mm in thickness and 3mm in width, 125mm in length and spaced at
between 12mm and 25mm in an approved random pattern. The
Engineer may, however, require a different random pattern or equal
spacing of the tines during the course of the work, and provision shall be
made to supply different sets of combs as required. No additional
payment will be made for the first two changes in the spacing of the
tines.
The combs for applying the texturing shall be atleast 3.0m wide. It must
also be possible to adjust the combs to a lower position in order to
compensate for wear.
Burlap-Drag-and-Grooved Texture
This texture shall be obtained by first applying a burlap-drag finish to the
concrete surface and then by grooving it with a grooving comb.
The first pass of the burlap drag shall be made as soon as construction
operations permit and before the wet sheen has disappeared from the
surface. Burlap dragging shall be repeated until a gritty and uniform
texture having the required depth of texture has been obtained.
Every morning the burlap drag shall be wetted and kept moist
throughout the day. At the end of each day's pour the burlap mats shall
be cleaned or discarded and replaced with new burlap if cleaning is not
possible.
After the concrete has hardened, all loose particles generated by the
cutting of the grooves shall be broomed off the surface with stiff hand
brooms or mechanically operated rotary brooms.
When measured with a suitable depth gauge, the grooves shall be not
less than 2 mm and not more than 4 mm in depth.
The Engineer may permit the use of texturing equipment other than the
grooving comb, provided that it produces a texture similar to that
produced by the metal tines.
135
Hand texturing
Texturing the surface with hand-held brooms or combs shall be allowed
only where the pavement is so small or irregular, or the site is so
restricted as to make the use of the texturing machine impracticable, or
in cases of mechanical breakdown of the texturing machine, in which
case it may be used for the required texturing of concrete already
placed. The brush or comb to be used then shall be of the same type
and width used in the machine. In order to ensure straight grooves, the
comb shall be operated against a straight-edge placed at right angles to
the pavement centreline.
4211 B CURING
The exposed surfaces, including the sides of the slab, shall be treated
immediately after the required texturing of the surface has been effected
and after the side formwork has been removed by the application of a
white-pigmented curing compound as specified in sub-clause 7102.8
above in accordance with the directions of the manufacturer.
The curing compound shall be sprayed onto the surface at a rate of 0.35
liter/m2 or as approved by the Engineer by means of a mechanical
distributor capable of producing a fine fog-type of spray, which will not
damage the surface of the concrete. The curing compound shall be
applied in two layers with the distributor moving in opposite directions for
the two applications. Coverage shall be uniform over the entire surface
and the rate of application of the curing compound shall be carefully
controlled.
136
The curing membrane shall be maintained intact for at least seven days
after the concrete has been placed. Any damage to the curing
membrane, caused by the Contractor's activities, shall be repaired by
hand-spraying the affected areas.
Deviations of the filler board or bottom crack inducer from the intended
line of the joint shall not be greater than +/- 10mm;
The best fit straight line through the joint groove as constructed shall not
be more than 25mm from the intended line of the joint;
Deviations of the joint groove from the best fit straight line of the joint shall
not be greater than 10mm.
137
Contraction joints
Contraction joints shall consist of:
A sawn joint groove
Dowel bars
A sealing groove
Expansion joints
Expansion joints shall consist of:
Ajointfillerboard
Dowelbars
Asealinggroove
The joint filler board together with the sealing groove shall provide a
complete separation of adjacent slabs and any spaces around dowel
bars and between the layer underlying the slab and the filler board shall
be packed with a suitable compressible material after fixing the joint
assembly.
Warping joints
Warping joints shall consist of:
A sawn groove
Tie bars
A sealing groove
Construction joints
Construction joints made at the end of a working day in unreinforced
concrete slabs and jointed reinforced concrete slabs shall be contraction
joints. In the event of mechanical break down of the concreting
machinery, or at the on set of adverse weather, emergency joints may be
formed.
138
Emergency joints in jointed reinforced concrete slabs shall be not less
than 2.5m from the preceding or succeeding joint position. The stop end
formwork shall be sufficiently rigid to ensure that dowel bars, tie bars or
reinforcement will be held In position incompliance with the
Specification, and placed in such a position that it permits the
longitudinal reinforcement to project through the joint for a distance of
atleast750mm.
Deviations of the bottom crack inducer from the intended line of the
joint, parallel to the axis of the road shall be not greater than ±13 mm;
The joint groove shall be located vertically above the bottom crack
inducers within a horizontal tolerance of ±25 mm;
The best fit line along the constructed joint groove shall be not more
than 25mm from the intended line of the joint;
139
Deviations of the joint groove from the best-fit line of the joint shall not
be greater than 10 mm.
140
The grooves shall be between ¼ and ⅓ of the specified depth of the
slab and of any convenient width not less than 3mm.
The sealing groove may be sawn to the required width later. Expansion
joint sealing grooves shall be sealed as soon as practical after sawing.
Wet-formed longitudinal joint grooves
When slabs are constructed in more than one lane width in one
operation, a joint groove shall be formed by inserting a groove former
ahead of the finishing beams from dispenser. The concrete so displaced
shall be re-compacted by a vibrating compactor or similar device, atleast
300mm wide operating symmetrically along the line of the joint.
141
firmly fixed to the sub-base so as to remain in position during the whole
process of constructing the slab.
Tie bars in warping joints shall be positioned from the top surface of the
slab within 20-10mm of the mid depth of the slab.
Tie bars in other joints shall be positioned and remain within the middle
third of the slab depth, approximately parallel to the surface and
approximately perpendicular to the line of the joint, with the centre of
each bar on the intended line of the joints within a tolerance of 50mm,
and with a minimum cover of 30mm below any top crack inducer of joint
groove for slabs 200mm thick or more, or 20mm for slabs up to 200mm
thick.
142
At transverse construction joints in continuously reinforced concrete, tie
bars shall be fixed at twice the normal spacing mid-way between the
longitudinal reinforcement bars so that 750mm extends each side of the
joint at the same level as the longitudinal reinforcement and be tied to
the transverse reinforcement. Where paving from a construction joint is
not resumed within 5days, an extra longitudinal reinforcement bar 8m
long shall be lapped and tied to each tie bar. These extra bars may be
combined with the tie bars.Where the spacing between longitudinal
reinforcement and the extra 8m long bars is less than 90mm, the
nominal size of aggregate shall be 20mm for a sufficient number of
concrete batches to complete that section of pavement.
Dowels
Dowel bars shall be free from oil, dirt, loose rust and scale at the time of
concreting.
143
Bars shall be equally positioned about the intended line of the joint
within a tolerance of 25 mm.
Cradles supporting dowel bars shall not extend across the line of the
joint.
If rough arises develop when grooves are made, they shall be ground to
provide a chamfer approximately 5mm wide. If the groove is at an
angle up to 100 from the perpendicular to the surface, the over hanging
spalling occurs or the angle of the former is greater than 10 0 the joint
144
For applied sealants, the sides of the joint sealing groove shall be
scoured by dry abrasive blasting. This shall not be carried out before
the characteristic compressive strength of the concrete is expected to
reach 15 MPa. When compression seals are used, the sides of the
groove may be ground or wire brushed.
All groves shall be cleaned of any dirt or loose material by air blasting with
filtered, oil-free compressed air. The groove shall be clean and dry at the
time of priming and sealing.
For applied sealants, the joint grooves shall be primed with the relevant
primer for the hot or cold applied sealant in accordance with the
manufacturer’s recommendations. When necessary, the joint grooves
may be primed and sealed earlier than 14 days after construction, as
soon as the grooves have been grit-blasted and cleaned.
between 80C and 100C it may be carried out when the temperature is
rising.
145
recirculating pump. The sealant shall not be heated to a temperature
higher than the safe heating temperature nor for a period longer than
the safe heating period, both as specified by the manufacturer. The
dispenser shall be cleaned out at the end of each day and reheated
material shall not be used.
As soon as possible after mixing and within the work life of the sealant,
the material shall be dispensed into the joint, or applied using a caulking
gun, to the concrete below the concrete surface. The tack-free time
shall be achieved within 3hours for machine dispensed material, or
within 12hours for hand applied material.
The trial section shall be constructed with the same materials, concrete
mix, plant and equipment as those intended for use by the Contractor
for the pavement, and he shall also demonstrate the methods he
proposes to use for applying the required surface texture, the
construction of joints and the placing of tie-bars, dowels,etc.
An initial trial section of not less than 150m in length for mechanical
construction, and atleast 30m in length for manual construction, shall be
constructed in one continuous operation and be submitted for approval.
The Engineer shall also be entitled to call for a new trial section to be
constructed at any stage of the contract when changes by the
Contractor in the approved equipment, materials, mix or rate of paving
warrant the construction of another trial section.
The Contractor will be paid for the actual length of trial pavement
constructed as initial trial section and trial sections constructed in
consequence of changes in mixes, techniques, materials, etc, effected
by the Contractor, upto a maximum total length of 300m for mechanical
construction, and 60m for manual construction. In addition, he will be
paid for any trial lengths necessary as a result of similar changes
required by the Engineer, notwithstanding the fact that the trial section
built by th eContractor complied with the specified requirements.
147
Further trial sections and permission to start constructing the
pavement
The Contractor may, unless advised of any deficiencies in the trial
section, proceed with the construction of the pavement ten (10) days
after the completion of the trial section or such earlier time as the
Engineer may determine.
In the event of deficiencies in the trial section, the Engineer may order
the Contractor to construct a further trial section, which will again be
regarded as the initial trial section.The Contractor may then proceed
with the construction of the pavement ten (10) days after the
satisfactory completion of the second or subsequent trial section.
148
The assessment of test results and measurements, and the acceptance
of the work, shall bed one in accordance with a procedure developed by
the Engineer.
Compressive-strength control
The Engineer may, at his discretion, decide to use the Contractor's test
results in the acceptance plan, if he is satisfied that the Contractor has
complied with all the process control requirements.
For thi spurpose, sets of three sample each for both flexural and
compressive strength tests shall be manufactured from the same batch
of concrete and tested for flexural and compressive strength
respectively.
149
be repaired as specified in Clause 3921A, so that it shall comply with
the specified requirements after having been repaired.
P=(dw)5(fw)4x100(ds)5(fs)4
where:
P = percentage of normal compensation dw=actual average thickness of
slab
ds = specified average thickness of slab
Fw = actual28-day compressive strength of slab (average of 28-day
compressive-strength tests)
Fs = specified 28-day compressive strength of slab
150
Removing concrete
Where any section of the pavement, which does not comply with the
specified requirements, is to be removed and reconstructed, the entire
portion of the slab shall be removed and reconstructed as prescribed by
the Engineer in writing.
On all portions of the pavement where the surface texture has been
destroyed or reduced in depth by grinding, the surface texture shall be
restored by grooves being cut into the concrete surface. The grooves
shall be approximately of the same size and spacing as specified in
Sub-clause 3910A(b).
Repairing joints
Joints along which spalls occur that exceed 5mm indepth at any point
measured from the top surface of the pavement, or any other joints,
which in the opinion of the Engineer are unacceptable, shall be repaired
with an approved epoxy resin mortar. The method of repairing joints
requires the prior approval of the Engineer.
151
the opinion of the Engineer, the concrete can be placed with pavers, the
work shall be regarded as, and shall be measured and paid for as, new
work under the applicable items for new work.
Care shall be taken at existing joints to ensure that tie bars or dowels
are not damaged or bent so as to render them useless.
152
Where various adjacent panels are constructed, the concrete in every
alternate panel shall first be placed. The concrete in the rest of the
panels may be placed only after the concrete in the first panels has
sufficiently hardened so that no damage will be done to the first panels
during construction activities. All formwork shall remain in position for
atleast 24 hours.
Surface texture
Unless otherwise specified in the Project Specifications, the Contractor
shall produce a surface texture on the new concrete panels which shall
be the same as that on the existing panels.
Where tie bars or dowels are shown on the Drawings at joints between
existing and new concrete, but no such bars occur in the existing
concrete, holes shall be drilled in the existing concrete and fresh bars
placed and fixed as prescribed in the Project Specifications. In such
cases, the dowels shall be placed with their sliding ends in the new
concrete.
Where no bars are required between the existing and new concrete but
such bars do occur in the existing concrete, such bars shall be cut off
flush with the concrete edge.
153
All joints between the existing and new concrete shall be sawn after the
new concrete has hardened sufficiently to prevent splintering or other
damage from occurring.Sawing the joints may normally be done from
two (2) to five (5) days after the placing of the concrete. The width and
depth of the sawn grooves shall comply with the requirements set in the
Project Specifications and on the Drawings.
Repairing the joints and cracks in the existing concrete pavement shall
be done in accordance with the requirements set out in the Project
Specifications and on the Drawings, and as required by the Engineer.
Retexturing
Where in the opinion of the Engineer the skid resistance of the concrete
pavement surfaces is too low, or the texture is too irregular, and where
so specified in the Project Specifications, such surfaces shall be
provided with a fresh texture.
The depth of texture and groove spacing shall comply with the
requirements of the Project Specifications. The work shall be done with
approved sawing equipment.
154
The quantities to be measured and paid for will be the approved
quantity, in cubic meters, of Plain Cement Concrete Pavement or of
Reinforced Cement Concrete Pavement as appropriate and as shown
in the construction drawings.
The tendered rate shall include full compensation for procuring and
furnishing all the materials, storing the materials, providing all plant and
equipment, determining the mix proportions, mixing, transporting,
placing and finishing the concrete, texturing and curing, including
formwork, repairs done to defective work, protecting the pavement
against damage, construction joints, cleaning and sealing transverse
and longitudinal joints, tie-bars and dowel bars, abutting joints between
existing pavement, plastic sheeting 125microns thick, placing new
pavement and process control including the furnishing of test
specimens; extraction of core samples for testing of compressive
strength of laid concrete and repair of core holes.
The tendered rate shall also include full compensation for the provision
of any additional width required by the Contract or to the earthworks
and/or pavement layers to suit the particular requirements of the paving
equipment. It shall also include full compensation for the removal of the
additional widening, which extends beyond the limits of the specified
cross-section.
In the case of rehabilitation work, the tendered rate shall also include full
compensation for cleaning existing joints where new concrete has to join
up with existing work, for straightening existing dowels and tie bars, and
for cutting off existing bars as specified.
The tendered rate shall include full compensation for excavating the
material and disposing there-of to approved spoil dumps, including
transport.
155
Amend the description of Pay Item 4223 of the Special Specifications
as follows
ITEM DESCRIPTION UNIT
Cast in-situ plain concrete class 30 to rigid pavement laid on falls and
cambers, in alternate bays not exceeding 15 square meters including
side formworks mixing, spreading, finishing of concrete, sawing and
(i) cu.m
sealing joints, dowel bars, plastic sheeting 125 microns thick,
compaction and curing and all incidentals necessary to complete the
works
156
5000 ANCILLARY ROADWORKS
5100 MARKER AND KILOMETRE POSTS
5106 MEASUREMENT AND PAYMENT
Add at the end of Clause 5106 of the Standard Specifications the following
additional pay item:
ITEM UNIT
51.03 Bollards number (no.)
The bid rate shall include full compensation for supplying all materials and
labour, making and transporting the Bollards, setting out, excavating and
backfilling all the holes and disposing of surplus excavated material, including
all haulage, placing and painting the Bollards and all the equipment, the tools
and incidentals necessary for completing and maintaining the Works described
in this Section.
5200 GUARDRAILS
5202 MATERIALS
Replace first paragraph of Sub-clause 5202(a) of the Standard Specifications
by the following:
All guardrails including bolts, washers and other fixing materials as well as
steel posts shall be galvanised by hot-dip zinc coating, 550 g/m2, according to
AASHTO designation M232M/97 or equivalent.
157
5400 ROAD SIGNS
5403 MATERIALS
Add the following at the end of the fourth paragraph of Clause 5403 of the
Standard Specifications:
Words, figures and other symbols shall be applied to the reflective sheeting by
the “silk screen method” using a translucent paint for coloured parts but an
opaque paint for black parts. Paint types shall be in accordance with the
recommendations of the Manufacturer of the reflective sheeting.
5404 CONSTRUCTION
Replace second sentence of fourth paragraph of Clause 5404 of the Standard
Specifications by the following:
The signs shall be supported on a galvanised steel tube of not less than 75
mm outer diameter and securely bolted to it as shown on the Drawings. To
avoid theft of the signs, the ends of bolts shall be hammered or spot welded to
prevent the nuts being removed.
Where details for the construction of sign faces, the framework of the sign
faces and the attachment thereof to the supporting framework are not shown
on the Drawings, the Contractor shall design these himself and submit the
details to the Engineer for approval before manufacture.
Add at the end of the tenth paragraph of Clause 5404 of the Standard
Specifications the following:
158
Replace the third last paragraph of Clause 5404 of the Standard Specifications
by the following:
The signs shall be erected at a distance from the edge of shoulder as shown
on the Drawings or as directed by the Engineer.
Payment for Standard Road Signs shall differentiate between three types:
Warning Signs
Regulatory and Prohibitory Signs
Information signs and
Route Direction Guidance Signs
The price for each of these pay items shall be full compensation for all
provisions stated in this clause including sign support in accordance with the
Drawings.
Add at the end of second paragraph under pay item 54.03 of the Standard
Specifications the following:
The rate for Route Direction Guidance Signs shall include for the provision and
erection of sign support in accordance with the Drawings.
This Section also covers the construction of rumble strips, speed humps and
raised pedestrian crossings as indicated on the Drawings or as specified by
the Engineer.
5502 MATERIALS
Add at the beginning of Sub-clause 5502(a) of the Standard Specifications the
following:
159
Paint for kerb marking shall comply with the requirements as specified under
(i) below while all other road marking shall be thermo-plastic road marking
material as specified below under (iii) below.
Replace Sub-clause 5502(a)(iii) of the Standard Specification the following:
160
(c) Rumble Strips
Rumble Strips shall be constructed by three bituminous seals using
7mm aggregates with first seal applied in 250mm width, second in
200mm width and third seal in 150 mm width using bituminous binder
and aggregates complying with Section 4500. The 250mm wide rumble
strips shall be painted with yellow thermoplastic paint in thickness of 2
mm ±0.5 mm.
161
aggregates, pigments, binders and glass beads which have been factory
produced as a finished product, and meets the equirements of the
current edition of the Manual on Uniform Traffic Control Devices for
Streets and Highways. The thermoplastic material conforms to AASHTO
designation M249, with the exception of the relevant differences due to
the material being supplied in a preformed state.
3.1.2. The material must have factory applied coated surface beads in
addition to the intermixed beads at a rate of 1 lb. (± 10%) per 10
sq. ft, or equivalent 0.45kg per 0.93 sq.m. This factory applied
coated surface beads shall have a minimum of 80% true
spheres, minimum refractive index of 1.50, and meet the
following gradation.
Size Gradation
Retained, % Passing, %
US Mesh μm
12 1700 0 - 2% 98 - 100%
14 1400 0 - 3.5% 96.5 - 100%
16 1180 2 - 25% 75 - 98%
18 1000 28 - 63% 37 - 72%
20 850 63 - 72% 28 - 37%
30 600 67 - 77% 23 - 33%
50 300 89 - 95% 5 - 11%
80 200 97-100% 0 - 3%
3.2 Pigments
3.2.1. White: The material shall be manufactured with sufficient titanium
dioxide pigment to meet FHWA
Docket No. FHWA-99-6190 Table 5 and Table 6 as revised and
corrected.
162
3.2.2. Red, Blue, and Yellow: The material shall be manufactured with
sufficient pigment to meet FHWA Docket No. FHWA-99-6190 Table 5
and Table 6 as revised and corrected. The yellow pigments must be
organic and must be heavy-metal free.
3.5 Thickness:
The material must be supplied at a minimum thickness of 125 mils (3.15
mm).
3.6 Versatility:
As an option, turn arrows and combination arrows may come without
surface applied glass beads, thus facilitating the use of those arrows as
either left or right indicators, thereby reducing inventory requirements.
3.8 Retroreflectivity:
The material, when applied in accordance with manufacturer’s
guidelines, must demonstrate a uniform level of sufficient nighttime
retroreflection when tested in accordance to ASTM E 1710. The applied
material must have an initial minimum intensity of 500-med.mex.lx for
163
white and 300-med.mex.lx for yellow measured with a Delta pavement
marking retroreflectometer.
APPLICATION:
3.9 Asphalt
The materials shall be applied using the propane torch method
recommended by the manufacturer. The material must be able to be
applied without minimum requirements for ambient and road
temperatures and without any preheating of the pavement to a specific
temperature. The material must be able to be applied without the use of
a thermometer. The pavement shall be clean, dry and free of debris.
Supplier must enclose application instructions in English with each
box/package only pertaining to an application method that does not
require preheating of the pavement to a specific temperature before
application.
164
TECHNICAL SERVICES: The successful bidder shall provide technical
services as required. Regionally located manufacturer’s representative,
employed directly by the manufacturer, can provide no-cost on-site training for
proper application.
The machine shall be capable of spraying at a speed of not less than 5.0
km/hr.
Where instructed, Rumble edge line shall comprise a base line and ribs
formed in one continuous integral operation. The base line shall be screed
applied at 150 C to 180 C in 2.5 mm thickness +/- 0.5 mm and the ribs at 500
mm spacing shall have a thickness of 7 mm +/- 1 mm above the base line. A
microprocessor controlled mechanical shutter shall be used to form the solid
ribs, which shall a length of 50 mm +/- 0.5 mm and a width of at least 80% of
the base line width.
165
be applied at a rate of 250 grams per square metre by an applicator attached
to the machine.
Road marking paint shall not be applied to damp surfaces or when the relative
humidity exceeds 80%, or at temperatures lower than 10°C, or when, in
opinion of the Engineer, wind strength is such that it may adversely affect the
painting operations.
Road studs shall be of the type and size specified in Sub-clause 5502(b) and
shall be fixed in position at 5 m interval along the limit of chevron markings
ahead of raised median, at bridge approaches and other locations as directed
by the Engineer.
5513 PROTECTION
Add the following at the end of Clause 5513 of the Standard Specification:
The thermoplastic road-marking shall be kept track free for at least 10 minutes.
ITEM UNIT
55.10 RUMBLE STRIPS, SPEED HUMPS AND
RAISED PEDESTRIAN CROSSINGS
(a) rumble strips metre (m)
(b) Speed humps (extra over Subitems of 37.02, metre (m)
37.04, 38.02, 38.03, 39.01 and 45.01 for forming
speed hump)
(c) Raised pedestrian crossing by full cost payment metre (m)
166
of subbase, crushed aggregate base course and
reinforced concrete slab
The unit of measurement for rumble strips, speed humps and raised
pedestrian crossings shall be the metre of the different types constructed to
the thickness and cross sectional shape shown on the Drawings and the
quantity paid for shall be the actual number of the various types constructed in
accordance with the instructions of the Engineer.
The bid rates shall include full compensation for furnishing all materials,
preparing the surface including providing, heating, mixing, transporting, laying
and compacting the materials in accordance with Section 4200 and this
Section 5500 of the Specifications and to the satisfaction of the Engineer.
However, for Item 55.10(b) payment shall be as an extra-over rate with all
materials paid for separately under Subitems of 37.02, 37.04, 38.02 and 38.03
as relevant as well as under Subitems 39.01(a) and 45.01(a). Any road
marking will be paid for separately.
167
the drawings, but which are necessary for the completion and
satisfactory functioning of the works to meet the requirements of the
specification.
5603 MATERIALS
All materials and workmanship shall comply with the relevant and
applicable standards, in particular those imposed by Tanzanian laws,
regulations and/or by-laws.
Technical details
Component / 168
Materials
Number of cells : 36
Cell type : Polycrystalline
Cell size : 156.75 mm x 156.75 mm
Front : Low – iron tempered glass
Back : Film, White
Frame : Anodized Aluminium
J-box : IP67
Connector : MC4 Comp.
Dimensions / Weight
Length : 1020 mm
Width : 990 mm
Height : 40 mm
Weight : 12.2 kg
Thermal Characteristics
NOTC : 460 C
Isc : 0.041%/K
Uoc : -0.30%/K
Pmpp : -0.41%/K
169
170
LED Lighting Armature - 1
171
LED Lighting Armature - 2
Battery
The battery shall be Gel deep cycle with nominal voltage of 25.6 and minimum
typical capacity of 150Ah and a Depth of Discharge (DoD) of at least 80%. The
battery must have a Warranty of at least Five (5) Years with a complete
replacement guarantee for defective unit within the first 5 years.
Control system
The switching of the lighting circuits shall be through an automatic control
arrangement comprising of a contactor, photocell, timer and selector switch.
The photocell operation shall be backed up, such that the lights remain on in
case of photocell failure.
172
of the lights. The unit shall be based on Sangamo Suntracker series, so that it
can automatically track sunset and sunrise over a period of the year.
The timer shall be plug in type and shall have sealing arrangement to prevent
tampering of settings. It shall be possible to manually override the timer.
A selector switch shall select the following mode of operation: (1) Auto on
timer, (2) Auto on photocell, (3) Auto on timer/photocell, (4) OFF and (5)
Manual.
All luminaires offered shall have a minimum guarantee period of Five (5)
Years. The scope of this guarantee includes the LED drivers, luminaire
housing, LED module(s), brackets and protector.
The Contractor shall ensure that a warranty for luminaire is secured from the
manufacturer in such a way that if luminaires are found to have failed within
this period as a result of poor manufacturing processes and//oor poor
materials, it shall be replaced free of charge by the manufacturer.
173
The columns shall be made from hollow sections to BS EN 10201-2 or
equivalent norms approved by the Engineer. The hollow section shall be of
steel to BS EN 10025 grade Fe 430C / S275J0 or equivalent and shall have a
minimum ultimate tensile strength of 430 N/mm2 and minimum yield stress of
255 N/mm2. The steel plate thickness shall be minimum 4 mm.
The columns shall be designed in accordance with BS5649 in steel and hot dip
galvanised internally and externally after manufacture in accordance with BS
EN ISO 1461, Table 2 or equivalent.
The design shall include safety factors in accordance with Technical Report
no. 7 of the Institution of Public Lighting Engineers, UK. They shall be
designed to withstand the wind velocities stated in the general Standard
Specifications for Roads. At 105 km/h (29.2 m/s) 3 second duration gust wind
speed the deflection of the top of the mast or column shall not exceed 1/40 of
the height.
The column shall be provided with an internal base chamber with a fully
weatherproof door/cover secured by tamperproof lock of stainless steel.
Special keys such as Allen keys to open the door shall be provided on
completion in the ratio of one key to 20 columns, minimum two keys. All doors
for the same mast- or column type shall be interchangeable.
All doors shall be fitted with a door-retaining device to ensure that the door
cannot be dropped or lost. Any steel wire or chain used to achieve captivity
shall be galvanised or stainless steel.
174
complete with two washers and a nut and locknut of the same material as the
terminal. The terminal shall be positioned so as to be readily accessible
through the door opening.
The base compartment shall be provided with terminals for looping-in and -out
a 4x16 mm2 or 4x10 mm2 or 4x6 mm2 armoured copper cable, as indicated in
the drawings, with earth conductor and a single pole mcb for each luminaire
mounted on the column.
Cables hanging inside the column, connecting the mcb's with the luminaires,
shall be 3 x 2.5 mm2 flexible cable to BS 7919 or BS 6500 with conductors of
class 5 stranded, plain annealed copper to BS EN 60228, heavy duty class as
type HO7RN-F, min. 300/500 V grade, with EP rubber insulation and circular
jacket of polychloroprene rubber or equal to be approved by the Engineer.
The top of the column shall be designed suitably to fix the bracket arm collar to
the top of the column. A minimum of 8 nos. threaded holes on the four sides in
two rows to suit M10x16 mm knurled cup-pointed hexagon socket set screws
shall be provided for mounting the bracket arm on top of column The required
number of hexagonal socket set screws to suit these holes shall be supplied
with each column.
Brackets shall be of side entry mounting type single or double arms. The
design shall be as indicated on the drawings. Outreach from the lighting
column to the spigots shall be in accordance with lighting design calculations
or as specified on the drawings.
The spigot outside diameter shall match the luminaire, but shall not be less
than 42 mm.
Base flange
A minimum of four holes adjustable (slots) shall be provided on a min. 20 mm
thick flange plate of suitable size for the foundation bolts to fix the column on
to the foundation. The base flange plate shall be manufactured from steel
plate, which is free from lamination. The main shaft of the pole shall penetrate
175
the full thickness of the base plate and shall be fully welded above and below
in accordance with BS EN 1011. Gusset plates shall be provided to give
additional strength to the poles. Gussets shall be located between the fixing
holes.
Foundations
All foundations for road lighting poles and -masts shall be made of pre-cast
reinforced concrete. The supplier of street lighting masts shall provide a
detailed calculation / design for the Engineer's approval for all reinforced
concrete foundations for each combination of type of column, type of luminaire
mounted on the column, and type of soil.
Identification labels
Each column shall be fitted with an identification label with 50 mm high
lettering on a white background. The labels shall be stainless steel or equal
weather resistant, durable material compatible with the galvanised surface.
The labels shall be fixed with galvanised or stainless steel bolts and nuts at a
height 50 mm above the base compartment door, but facing oncoming traffic.
5605 CONSTRUCTION
General requirements
Prior to planning of construction works the Contractor shall prepare a detailed
description of methodology for all erection and installation works and submit it
to the Engineer for his comments and approval. No works shall be carried out
before a written approval from the Engineer has been issued to the Contractor.
The Contractor to ensure that all trade work shall be carried out by tradesmen
fully competent and qualified in the respective trade, and the entire installation
shall be neat, orderly and well arranged and carried out in a methodical
competent manner.
All cable runs and all equipment, boxes, labels, etc. shall be mounted strictly in
lines, horizontally and vertically. Components out of sight, for example inside
switchboards, are also covered by this requirement.
176
All materials shall be stored, handled and installed in strict compliance with the
manufacturer's recommendations. Particular attention shall be given to avoid
damages to surface treatments of metallic objects and to provide adequate
cover to prevent cables and cable ducts with an outer polymer surface from
being exposed to prolonged ultraviolet radiation, i.e. more than 50 hours in
total.
Lighting poles
The poles shall be erected and aligned before the luminaires are mounted on
the poles.
Columns with flange plates shall be painted with bituminous paint at the
underside of the flange and at the inside of the pole to a height of 500 mm.
Flange plate columns shall be carefully lowered onto the foundation base
prepared for it and shall be set vertical using nuts and washers under and
above the base plate. The nuts shall be made tight to secure the column to the
foundation and the nuts and exposed bolts shall be coated with "Denso paste"
and protected with "Denso tape" or equal. The space between the flange plate
and foundation base shall be grouted and trowelled to a smooth finish.
The foundations and planted root columns shall be placed with a horizontal
tolerance of ± 20 mm in all directions and a vertical tolerance of ± 20 mm.
After final fixing and adjustment no column shall deviate more than 0.1˚ from
true vertical (≈ 18 mm per 10 m).
The base compartment door shall be positioned as per the schedule below.
The door-locking device shall be lubricated.
177
Column position Door position
On green area between Facing away from the incoming traffic
Median
walkwayofand
BRT lanes
MTL Facing away from the incoming traffic
Installation of luminaires
The luminaire shall be securely fixed to the spigot in accordance with the
manufacturer's recommendation.
The lamp shall not be inserted into the luminaire until the luminaire is securely
fixed to the erected column and until any adjustable mirror- and lamp holder
positions have been set and secured in accordance with the drawings and
lighting calculations.
Testing shall be used to determine whether the tested property of the street
lighting system fulfils the Contract requirements as specified directly or by
reference to other documents such as standards, etc., and/or with guarantees
issued by the Contractor.
The term "testing" shall, depending of the context also comprise examination,
inspection and measurement.
The Contractor shall have on the Site all the relevant standards required for
the work he is to undertake under the Contract. A second complete set of such
standards shall be available for the sole use of the Engineer.
Testing includes, but is not necessarily limited to the following typical tests
listed in normal chronological order:
Type tests
Factory acceptance tests (FAT)
178
Inspection and testing on delivery
Inspection and testing of the Works during the progress of the work
Tests on completion, site acceptance tests (SAT) / commissioning tests / trial
operation tests / performance tests
Specific requirements for control, testing and commissioning of different types
of components and installations are given in the individual sub-sections below.
The acceptable age of such calibration certificates will depend on the type of
instrument and type of test and measurement, and shall be agreed between
the Contractor and Engineer prior to the test. Without such agreement, the
calibration certificate shall be not more that 6 months old.
Type Tests
Type testing is applicable to mass-produced components of a manufacturer's
standard range of products, such as cables and luminaires.
179
A population of the specific component type, model and range will have been
tested for compliance with specified standards at a testing laboratory, which
shall have certified compliance with the relevant standards.
The Engineer reserves the right to request copies of such test certificates and
to approve the issuing testing laboratory.
The Engineer and the Employer shall be invited to witness the FAT. The
Contractor shall call for FAT a minimum of two (2) months in advance and at
the same time submit the test plans to the Engineer.
The FAT shall be performed on a complete system under simulated load, with
selected instrumentation.
As a minimum the following shall be demonstrated and tested during the FAT:
Prior to the FAT, the Contractor / manufacturer shall perform an in-house test
and prepare all documentation to be used during the FAT.
The FAT shall be considered complete when all specified tests have been
completed with exception of mutually agreed items from the punch list.
180
Inspection and testing on delivery to site
The Contractor shall inspect all plant and material on their arrival to site and
shall satisfy himself that the items delivered are in strict accordance with the
Contract requirements and / or the material approvals issued by the Engineer,
and that items tested in the factory are identical to the items actually received
on site.
The Contractor shall record any shortage, defect or default noticed by the
inspection.
The Contractor shall retain Bills of Lading, shipping labels and similar
identification of the received Plant and materials and submit copies to the
Engineer.
All work shall be inspected and, where relevant, tested before it is covered up
or put out of sight.
In general, functional testing - hot test - of operational systems shall be
conducted after pre-functional testing (cold test, static test) and start-up has
been satisfactorily completed.
The Engineer shall witness the SAT. The Contractor shall call for the SAT a
minimum of three (3) weeks in advance and at the same time submit the test
plans to the Engineer.
181
As a minimum, the following shall be inspected, demonstrated and tested for
compliance with the Contract requirements during the SAT:
- Completeness and adequacy of as-built documentation
- Mechanical completeness and integrity
- Cabling, wiring, terminations, labelling
- System functionality
- Safety systems labelling and functionality
- Performance
- Operator interfaces / man-machine interfaces
- Any non-compliance to requirements or incomplete work detected
during the SAT shall be remedied immediately.
The SAT shall be considered completed when all specified tests have been
completed and all non-conformances or incomplete work detected have been
remedied and successfully re-tested.
182
Visual test of correct orientation, numbering and labelling of masts and
columns.
5606 DOCUMENTATION
General requirements
The Contractor's Bid shall include specific data sheets and manufacturer
details for all types of transformers, feeder pillars, masts, columns, lamps and
luminaires that the Contractor will provide.
Technical data sheets, brochures and type test certificates for all types of
transformers, feeder pillars, masts, columns, electrical components, luminaires
and lamps shall be submitted to the Engineer for approval. The Engineer may
request samples of luminaires for approval.
Workshop drawings
The Contractor shall prepare and submit workshop drawings in accordance
with the Special Specifications.
As-built documentation
The Contractor shall prepare and submit As-built documentation in accordance
with the SpecialSpecifications.
183
3 nos. 12 m high lighting poles with double arm incl. internal electrical
installations and foundation bolts
1 no. 10 m high lighting pole with single arm and side arm at 5m from the
finished road level incl. internal electrical installations and foundation bolts
The spares shall be of same manufacture and range as the components
actually provided and installed.
The spare parts shall prior to Taking-Over be delivered to the Employer's store
in Iringa in original packaging and clearly labelled.
The spare parts shall not be used by the Contractor for the maintenance and /
or remedial works carried out by the Contractor during the Defects Liability
period.
The layout of the street lighting system has been prepared for tender purpose.
During Tendering, the Contractor shall in his price; cost of designing a
complete street lighting system based the Specifications and the
manufacturer’s directions and practices. Notwithstanding this the Contractor
shall prepare detailed plans and lighting calculations for approval by the
Engineer. The works described in this section comprise the manufacture,
packing, shipment, insurance, customs duties, delivery to site, storage,
installation, testing, commissioning, and documentation for a complete street
lighting system covering the road corridors under BRT Project of about
30.45Km.
The works comprise all materials and workmanship required for providing the
street lighting system as specified.
The works shall include all ancillary equipment and appurtenances which may
not be particularly called for in this specification or shown on the drawings, but
184
which are necessary for the completion and satisfactory functioning of the
works to meet the requirements of the specification.
5610 MATERIALS
General
All materials and workmanship shall comply with the relevant and applicable
standards, in particular those imposed by Tanzanian laws, regulations and/or
by-laws.
The standards and regulations to be applied shall always be the latest issue,
which is in force 30 days prior to Contract signing.
All components and items of iron or steel shall be effectively protected against
corrosion by hot-dip galvanising with a minimum average thickness of 115 μm
185
for steel thickness > 5mm and 60 μm for steel thickness ≤ 5mm (sheet steel)
according to EN/ISO 1459-1461.
Paint systems providing equal protection may be acceptable, but are subject to
the Engineer’s approval.
All materials, components and systems shall be new, factory made and
specifically designed and constructed for the actual application.
The entire street lighting system shall function and work properly without
undue deterioration from the power supply of 400/230 V AC ±10%, 50 Hz, 3-
phase, 4-wire system provided by the Contractor.
Transformers
The transformer shall be designed for safe, reliable and maintenance friendly
operation under the environmental conditions at the site.
The transformer substations shall be for outdoor location on H-pole
configuration.
The transformer rated power under the specific site conditions in accordance
with IEC 60076 shall be in ratings as specified in the drawings.
186
All power transformers shall be constructed in accordance with lEC 60076 and
be of the naturally air-cooled oil filled type (ONAN). They shall be suitable for
outdoor installation and provided with a first filling of mineral oil to comply with
BS 60l48 Grade B30 or similar. The transformers shall be hermetically sealed.
Winding insulation shall be to Class ‘A’. The temperature rise shall be limited
to the maximum operating temperature for Class ‘A’ materials as defined in
[EC 60076 de-rated for the climatic 187luminium187 on site.
The high voltage windings shall be provided with off-load tapping from +5% to
-5% in 22’/% stages with constant flux voltage variation as defined in [EC
60076.
A metal label warning that power must be switched off before the tap changer
is operated shall be fitted.
Tanks shall be provided with external cooling tubes, fins, or ducts, to provide
natural cooling at maximum rated capacity under the site temperature and
climatic conditions.
The tank shall be fitted with lifiing lugs suitable for handling the mass of the
transformer complete with oil.
The tank covers shall be constructed to enable them to be bolted to the top of
the tank without distortion. All tank and terminal box joints shall prevent entry
of moisture or leakage of oil. All joint faces shall fit properly and no additional
thickness ofjointing shall be used to make good irregularities. All gaskets shall
be of synthetic rubber and cork composition or similar material, and not subject
to deterioration.
187
The design and construction of the transformer core, winding and tank shall
ensure that the noise level at full load is kept to the minimum, commensurate
with economic design. The tank shall be reinforced or braced where necessary
to reduce the noise level.
All windings, winding terminals and connections shall be fully immersed in oil
under all operating conditions. All materials shall be suitable for this duty and
not subject to deterioration.
LV feeder pillars
Each LV feeder pillar shall be equipped with the following:
One incoming circuit breaker feeding the busbar from the transformer
One busbar
3x1 phase mcb’s per each outgoing circuit
3 no’s current transformers for incoming circuit xxx.5A Class 0.3-3VA
One energy kWh meter (LV measurement of transformer output) phase
measuring
3 no’s ammeters for measuring phase currents in the incoming circuit
Spare space prepared for additional mcb’s
Outgoing circuits protected by Incb’s and controlled by a common
photoelectric device and contactors
Feeder pillar lighting with switch
Socket outlet
Single—phase mcb for feeder pillar lighting and socket outlet
188
The design, material, construction and performance of all low voltage
distribution feeder pillars for power distribution shall comply with the latest
international standards.
Finish shall be durable and easy to clean and shall be epoxy powder coated
70-80 pm after pre- treatment RAL 7032 or manufacturer’s standard colour.
Plinth mounted feeder pillars shall be provided with a base frame. The base
frame shall be manufactured from 3 mm thick electro galvanised sheet steel,
minimum 100 mm high and RAL 7021 epoxy powder coated
Access to the inside and the protective devices shall be by means ofa hinged
door fixed shut by means of a moulded lever type latch which shall be able to
be locked with the means of a proprietary locking system.
Hinged doors shall not exceed 800 mm in width. The doors shall be lined with
adequate number ofhinges and stiffeners to avoid sagging and wobbling.
With the door in the open position, it shall not be possible to touch or gain
access to live parts without the use ofa tool. The hinged tloor shall be easily
removable when the open position to aid installation and maintenance.
All fixing accessories shall have anti-corrosion tinish. All le‘rrous materials
shall either be stainless steels with min. 2.5% Mo-content, such as AISI 316
types (BS EN 10088-2 type 1.4432 to 1.4436), or otherwise corrosion inhibited
to the Engineer’s approval and painted or hot-dip galvanised to BS EN ISO
1461. Non-ferfous metallic components shall be electroplated to protect
against corrosion
189
All low voltage exposed terminals of feeder pillars that may be exposed to
touch woth the door open or cover removed) shall be shrouded to IP 2X to BS
EN 60529.
The neutral busbar shall be the same cross sectional area as phase busbars.
The earthing system shall be TN-S to BS 7671, i.e. the protective (earth)
conductor and the neutral conductor shall be electrically separate throughout
the installation and only be connected at one place, in the main feeder pillar
receiving the transformer feeder. Breakers rated up to 400A shall be plug in
type MCCB.
The main structure of the feeder pillar shall be bonded directly to the earth bar.
Installed devices, module steel cases and framework shall be bonded to earth.
All hinged covers shall be bonded to module cases via a separate flexible
copper conductor min. 2.5mm2.
All feeder pillars shall be equipped from the factory with removable lifting eyes
and all structural support necessary for installation by the Contractor.
Control System
The switching of the lighting circuits shall be through an automatic control
arrangement comprising of a contactor, photocell, timer and selector switch.
The photoelectric cell shall operate on a supply voltage of 230V AC. The
operating range shall be adjustable between 5 to 300 lx as a minimum. It shall
be suitable for operation at the specified ambient temperatures. ‘
The photocell operation shall be backed up, such that the lights remain on in
case of photocell failure.
190
An additional 24-hour timer shall be provided as a backup to the photocell. The
synchronous timer shall be of the solar dial type designed for automatic control
of the lights. The unit shall be based on Sangamo Suntracker series, so that it
can automatically track sunset and sunrise over a period of the year.
The timer shall be plug in type and shall have sealing arrangement to prevent
tampering of settings. It shall be possible to manually override the timer.
A selector switch shall select the following mode of operation: (1) Auto on
timer, (2) Auto on photo cell, (3) Auto on timer/photocell, (4) OFF and (5)
Manual.
Busbars
Main busbars shall be provided to suit the transformer rating including the
requirement of 120 % capacity, across the top or side of the feeder pillar and
secured with insulated fixings, Current rating and short-circuit withstand
current capacity shall be assessed by the Contractor.
The busbars shall be high conductivity half hard drawn, tinned copper 99.98%
purity as per BS EN 13601, [01% conductivity as per lACS (international
annealed copper standard)
The busbar shall be free from any type of cracks and insulated with heat
shrinkable colour coded sleeves throughout the length and vertical dropper.
191
The busbars shall be of sufficient cross-sectional area to continuously conduct
rated current with a maximum average temperature of 20°C above an ambient
temperature of 50°C.
All interconnections between busbar and outgoing feeders shall be with rigid
insulated lengths of busbar orjumpers.
The feeder pillars shall have continuous tinned copper earth bar at full width of
the feeder pillar at bottom and at vertical cable alley. The earth bar shall have
colour-coded identification at reasonable intervals to indicate earth system
using durable non-removable labels.
Internal wiring
Internal wiring shall conform to BS 72l l.
Feeder pillars shall be furnished completely wired including all cleats and
terminal blocks.
Cables and wires shall be installed neatly and secured together in channels, or
by the use of purpose non—PVC cable clips or ties. The securing ot‘cables by
self-adhesive tape will not b%e accepted.
No cable or wire sizes smaller than 2.5 mm2 shall be used to internal power
wiring. Control wiring shall be with minimum 1.5 mm 2 except for wiring
associated with switchgear control, protection and CT circuits, which shall not
be less than 2.5mm2.
Intemal wiring shall be flexible; single core fine stranded copper with low
smoke and fume insulation.
192
The wiring on instrument panels shall have llexihle connections to the terminal
blocks. – No wires shall be teed or jointed between terminal points.
Terminal blocks and individual terminals shall be numbered in the factory with
the number as stated in the control circuit wiring diagram of the manufacturer.
Cable/wire identification tags shall be factory fitted to each end of all internal
cable cores and wires by the manufacturer and be referenced to coincide with
the internal wiring diagrams. All wiring is to be readily identifiable with
identification ferrules on each end of the cable.
Insulated ring/pin crimping type end terminals shall be used for internal wiring.
Terminal boards
All terminal boards shall be mounted in accessible positions and, when in
enclosed cubicles, shall preferably be inclined towards the door. Spacing of
adjacent terminal boards shall be not less than 100 mm and the bottom of
each board shall be not less than 200 mm above the incoming cable gland
plate. Separate terminations shall be provided on each terminal strip for the
cores of incoming and outgoing cables including all spare cores.
screw or stud type used with crimped ring type termination. Screws and studs
shall be of not less than size M6, but stainless steel and bronze down to size
MS may be used provided that the current carrying capacity is adequate. All
studs shall be provided with nuts, washers and lock washers,
193
Terminal assemblies shall preferably be of the unit form suitable for mounting
collectively on a standard assembly rail, secured from the front and giving the
number of ways necessary to accommodate all wires, including those
ofincoming cables along with 10% spare.
Labelling
All feeder pillars containing functional units shall be clearly labelled with circuit
unit rclerence and current rating in English.
Every functional unit shall be labelled separately from all others. External
labels shall have letters not less than 10 mm in height and internal labels not
less than 6 mm. The letters shall be black in colour on a white background.
The labels shall be of Traffolyte or equal permanent indelible type and fixed
with stainless steel non-pointed selftap screw to the individual doors.
The rod earth electrode shall be connected to the earth electrode cable by
proprietary bolted clamp of high strength copper alloy, designed for the
dimensions of the rod electrode and the earth electrode cable.
194
Earth electrode cables shall be stranded single—core copper cable to BS EN
60228, with yellow- green insulation. Earth electrode cables shall be sized in
accordance with TANESCO’s rules, but shall not be less than 50 mmz. Other
protective earthing and bonding conductors shall be sized in accordance with
TANESCO’s rules.
Each earth electrode shall be provided with an inspection pit suitable for the
type of ground surface pavement at the place of installation. The earth
electrode inspection pits may be factory made of a manufacturer’s standard
range, to be approved by the Engineer, or the Contractor may produce it.
The inspection pits including the lid shall withstand for its useful lifetime the
traffic load at the installation place without any settling or damage.
The lid shall carry unique identification of the earthing system, such as for
example: “LV Earth” or equal. The identification shall be permanent, cast or
embossed into the top face of the lid.
Cable ducts
Cable ducts shall be of a rigid type, made from high impact PVC. The wall
thickness shall correspond with minimum class PN6 (pressure: 0.6 Mpa / 6
kp/cmz).
The inner diameter of the ducts shall be minimum 75 mm, but it will be the
option of the Contractor at his expense to use ducts of larger size if desired
and, where used, it shall be for the entire length of the crossing. Reducing
couplings shall not be used.
The Contractor shall provide all ducts with pull wire as minimum dia. 3 mm
nylon rope or equal to be approved by the Engineer.
195
All cables to be laid underground, directly buried or in ducts, shall be steel wire
armoured. The cables be type XLPE.SWA.PVC complying with BS 6724 or
equal which provides similar nut ll protection.
Identification labels
Each column shall be fitted with an identification label with 50 mm high
lettering on 21 white background. The labels shall be stainless steel or equal
weather resistant durable material compatible with the galvanised surtace. The
labels shall be fixed with galvanized or stainless steel bolts and nuts at a
height 50 mm above the base compartment door, but facing oncoming traffic.
All luminaires shall be purpose built design incorporating the specified type
and size of lamp.
All road lighting luminaires shall have precise documented light distribution
with precise mirror optics specially designed for road lighting purpose
The lamps shall not contain any lead, cadmium or hexavalent chromium, and
shall be chosen from ranges with a minimum of other environmentally harmful
chemicals such as mercury.
196
Technical Specification for Anti-theft High-powered LED Street Light Luminaire
of Phillips or Thorn makes or approved equivalent
197
S/N Description Minimum Requirement
conductive 198luminium with fins to
dissipate the heat to ambient air
Driver board
Details shall be given for getting spare
Pole entry/ Retro fitting
Suitable for fixing in existing lighting pole
(30 mm to 55mm dia with bracket and
locking bolt & nut.
Applicable Standard
IEC/EN LM 79 for fixture and with stand to
wind adverse weather conditions with test
certificate
Electrical connector
Connecting wires with minimum one meter
length
Warranty
The Cotractor to ensure that: -
All luminaires offered shall have a minimum
guarantee period of Five (5) Years. The
scope of this guarantee includes the LED
drivers, luminaire housing, LED module(s),
brackets and protector.
The Contractor shall submit the required test certificates as specified in S/N
10, 11, 12, 24 along with facilitation for factory inspection of materials and pilot
project where the same have been installed.
All luminaires shall be fitted with integral control gear and have a heat barrier
between the lamp enclosure and gear compartment. The control gear shall be
fitted to a tool-less, quick release gear tray, equipped with a plug and socket
connector for ease of maintenance or replacement purposes.
198
Electrical equipment shall be installed so that levels of radio interference given
in BS EN 55014-1 are not exceeded.
5611 CONSTRUCTION
(a) General requirements
Prior to planning of construction works the Contractor shall prepare a detailed
description of methodology for all erection and installation works and submit it
to the Engineer for his comments and approval. No works shall be carried out
before a written approval from the Engineer has been issued to the Contractor.
The Contractor to ensure that all trade work shall be carried out by tradesmen
fully competent and qualified in the respective trade, and the entire installation
shall be neat, orderly and well arranged and carried out in a methodical
competent manner.
All cable runs and all equipment, boxes, labels, etc. shall be mounted strictly in
lines, horizontally and vertically. This also covers components out of sight, for
example inside switchboards requirement.
All materials shall be stored, handled and installed in strict compliance with the
manufacturer's recommendations. Particular attention shall be given to avoid
damages to surface treatments of metallic objects and to provide adequate
cover to prevent cables and cable ducts with an outer polymer surface from
being exposed to prolonged ultraviolet radiation, i.e. more than 50 hours in
total.
199
Transformers
Surge arresters shall be connected to the earthing system by means of
insulated cable with a cross section not less than equnvalent to 25 mm“ Cu. he
mounting plate of the arrester shall be earthed
by means ofa separate cable. l-V le‘eder pillars l‘he le‘eder pillars shall be
installed as indicated in the drawings or as agreed by the Engineer.
The Contractor shall ensure that concrete bases and foundations provided for
feeder pillars have been constructed in accordance with the approved
Construction Drawings and feeder pillar tnanula‘cturer's drawings.
Feeder pillars shall be installed level and securely attached to the concrete
foundations with appropriate fixings and/or expansion anchors.
To provide the earth connection between the cable armour and the main earth
bar, each cable gland plate shall be connected to the earth bar using a copper
link of an appropriate cross section. Reliance on the gland plate fixing screws
to provide an earth path is not acceptable.
200
Unless otherwise indicated on the drawings the trench width measured at the
bottom shall be minimum 200 mm. Trenches for more than one cable or duct
shall be 200 mm with addition of at least 50 mm plus the cable / duct diameter
for every extra cable / duct.
The use of trench digging machinery will be permitted except where its
operation will be likely to cause damage to buildings or existing structures and
installations above or below the ground. At such looations hand-methods shall
be carried out to avoid such damage.
Any part of the trench excavated below grade shall be backfilled to grade with
thoroughly compacted material before placing the cables / ducts.
All excavated material shall be piled in a manner that will not endanger the
work or obstruct traffic.
The cables / ducts shall be laid on 100 mm. thick bedding consisting ofsand or
material free from sharp-edged stones and with no particles exceeding 15mm.
The bedding shall be thoroughly compacted to give a uniform bed.
The same material shall then be placed over the cables /ducts for not less than
l00 mm and be thoroughly compacted.
PVC or concrete tiles and marker tape shall be placed as shown on the
drawings.
Where mechanical plant is to be used for placing and /or compacting the main
backlill, the first 200 mm of cover to the cables / ducts shall be compacted by
hand. The remaining backfill shall be placed and compacted to l00% MDD/BS
compaction.
All excavations shall be backfilled to the level ofthe original ground surfaces
Cable ducts
Where cables cross under paved areas and where shown on the drawings
they shall be installed in ducts.
Ducts shall be buried with bottom level at least 0.7 m below finished ground
surface level unless otherwise indicated on the drawings. Ducts of plastic
201
material laid under roads and other areas where heavy vehicles traffic may be
expected shall be surrounded with concrete class 20.
Where one or more ducts are laid under paved areas one spare duct of the
same dimension shall be provided along with the duct(s) to be used for future
cables.
The exact number, size and position of ducts, and of pull boxes if used, shall
be proposed by the Contractor and agreed by the Engineer.
All ducts shall be capped until the cable will be installed. Ducts for future use
shall remain capped. A pull wire shall be installed in all ducts. At least 1.0 m of
pull wire shall be tied to a wooden block or doubled back into the duct at each
termination.
Location of the ducts, the Contractor shall carry out excavation for temporarily
buried duct ends, removal of temporary plugs or caps and cleaning of the
ducts.
After pulling cables into the ducts they shall be permanently sealed with plastic
compound.
Cables
The cable arrangements shall be well planned by the Contractor and
performed in such a way that replacement can easily be made.
Cables, which are installed along parallel runs, shall be arranged in such a
way that unnecessary crossing of cables shall be avoided.
Bending radii of the cables during handling and after installation shall not be
less than: for multicore cables: 10 times the cable diameter, for single core
cables: 15 times the cable diameter.
202
Cables shall be installed free of sharp edges on metal or concrete structures
as foundations, pull pits etc.
lf possible, cables shall be laid in one length, and through joints will not be
permitted without the approval of the Engineer. T-joints will not be permitted.
Directly buried cables shall be tested for insulation and continuity before
backfilling.
The same colour of the conductor insulation shall be used for the same phase
throughout the entire installation.
The poles shall be erected and aligned before the luminaires are mounted on
the poles.
Columns with flange plates shall be painted with bituminous paint at the
underside ofthe flange and at the inside ofthe pole to a height of 500 mm.
Flange plate columns shall be carefully lowered onto the foundation base
prepared for it and shall be set vertical using nuts and washers under and
above the base plate. The nuts shall be made tight to secure the column to the
foundation and the nuts and exposed bolts shall be coated with "Denso paste"
and protected with "Denso tape" or equal. The space between the flange plate
and foundation base shall be grouted and trowelled to a smooth finish.
The foundations and planted root columns shall be placed with a horizontal
tolerance of ±20 mm in all directions and a vertical tolerance of ±20 mm.
203
After final fixing and adjustment no column shall deviate more than 0.1° from
true vertical (≈ 18 mm per 10 m).
The base compartment door shall be positioned as per the schedule below.
The door locking device shall be lubricated.
Installation of luminaires
The luminaire shall be securely fixed to the spigot in accordance with the
manufacturer‘s recommendation.
The lamp shall not be inserted into the luminaire until the luminaire is securely
fixed to the erected column and until any adjustable mirror- and lamp holder
positions have been set and secured in accordance with the drawings and
lighting calculations.
Each mast and pole shall be bonded to the earthing cable. Where the supply is
looped into the column, the earthing cable shall not be cut.
Cables between fuse holders and luminaires shall hang freely inside the
column and shall enter the fuse holders / mcb' from below, thus forming a loop
allowing water running along the cables to drip off instead of entering the
terminals.
204
5612 TESTING AND COMMISSIONING
General requirements
Testing shall be an essential, integrated part of the Contractor's quality
assurance system.
Testing shall be used to determine whether the tested property of the street
lighting system fulfils the Contract requirements as specified directly or by
reference to other documents such as standards, etc, and/or with guarantees
issued by the Contractor.
The term "testing" shall, depending of the context also comprise examination,
inspection and measurement.
Testing includes, but is not necessarily limited to the following typical tests
listed in normal chronological order:
Type tests
Factory acceptance tests (FAT)
Inspection and testing on delivery
Inspection and testing ofthe Works during the progress at the work
Tests on completion, site acceptance tests (SAT), commissioning tests, trial
operation tests/ performance tests
205
The Contractor shall produce calibration certificates on the Engineer's request.
The acceptable age of such calibration certificates will depend on the type of
instrument and type of test and measurement, and shall be agreed between
the Contractor and Engineer prior to the test. Without such agreement, the
calibration certificate shall be not more that 6 months old.
Type tests
Type testing is applicable to mass-produced components of a manufacturer's
standard range of products, such as cables and luminaires. '
A population of the specific component type, model and range will have been
tested for compliance with specified standards at a testing laboratory, which
shall have certified compliance with the relevant standards.
The Engineer reserves the right to request copies of such test certificates and
to approve the issuing testing laboratory.
FAT shall be performed in the premises where the tested system or Plant is
assembled, before shipment to site.
The Engineer and the Employer shall be invited to witness the FAT. The
Contractor shall call for FAT a minimum of two (2) months in advance and at
the same time submit the test plans to the Engineer.
206
The FAT shall be performed on a complete system under simulated load, with
selected instrumentation.
As a minimum the following shall be demonstrated and tested during the SAT:
Preliminary system documentation
System start-up, full load/overload performance
Operator interfaces / man-machine interfaces
All safety functions
All other specified functions
Prior to the FAT, the Contractor's manufacturer shall perform an in-house test
and prepare all documentation to be used during the FAT.
The FAT shall be considered complete when all specified tests have been
completed with exception ofmutually agreed items from the punch list.
The Contractor shall record any shortage, defect or default noticed by the
inspection.
The Contractor shall retain Bills of Lading, shipping labels and similar
identification of the received Plant and materials and submit copies to the
Engineer.
207
Insepection and testin durin progress of work
The Contractor shall inspect and test parts of the Works during erection and
installation in accordance with his quality plan.
All work shall be inspected and, where relevant, tested before it is covered up
or put out ofsight.
The Engineer shall witness the SAT. The Contractor shall call for the SAT a
minimum of three (3) weeks in advance and at the same time submit the test
plans to the Engineer.
208
The SAT shall be considered completed when all specified tests have been
completed and all non—conformances or incomplete work detected have been
remedied and successfully re-tested.
Power transformers, 11/0.4 kV, shall undergo type test, FAT and SAT and
inspection upon reception on site and erection.
Earthing systems for the transformers shall be individually inspected and their
resistance to earth shall be measured and recorded.
Feeder pillars
Feeder pillars shall undergo FAT and SAT and inspection upon reception on
site and erection.
SAT shall include all tests alter installation and before and after energising
required by local regulations and by BS EN 60439. The SAT shall also include
verification oflabelling and colour coding.
Earthing systems for the feeder pillars shall be individually inspected and their
resistance to earth shall be measured and recorded.
Cables
Cables shall undergo type tests and SAT and inspection upon reception on
site and erection.
Directly buried cables shall undergo insulation (megger-) tests and continuity
tests belo‘re backfilling.
Cable ducts
Cable ducts shall be visually checked for type, size and capping of ends
bucklilling.
209
Clearance shall be checked by pulling through each duct a mandrel with
diameter 90% of the internal diameter ofthe duct and 500 mm long, before and
after backfilling. Ducts, which do not allow the smooth drawing without binding,
shall be repaired or replaced as agreed with the Engineer.
Cable trenches shall be visually checked for size and cable quality and
smoothness of cable bed before laying of cables or ducts.
Lighting poles and luminaires
Lighting poles and luminaires shall undergo visual and functional tests.
The visual inspection shall as a minimum include: -
Visual test of alignment of all columns and angle of brackets and vertical
mounting. if the visual test reveals discernible deviations of one or more
columns/brackets from the majority, the deviating column/brackets shall be
measured.
Random sample visual test of lamp types. After confirmation of one lamp type
in an area of similar luminaires, a visual inspection of the entity at night with
the system energised will reveal any wrong lamp types or -sizes and any
missing or burnt-out lamps.
Visual test of light distribution / luminance. The entire illuminated area shall be
inspected and anomalies of luminance shall be recorded. If the lighting
calculations do not indicate such anomalies, the optical adjustment of the
luminaires and mirrors involved shall be checked.
Visual test of masts and columns for completeness of bolts, nuts and washers,
tightening of nuts, and soundness of surface treatment.
In addition to the visual and functional tests, the voltage drops from the feeder
pillar to the farthest end. at full load afier minimum one hour operation of all
210
luminaires and loads on the circuit shall he measured for all circuits together
with the full load current ofthe circuit.
5613 DOCUMENTATION
General requirements
The Contractor's Bid shall include specific data sheets and manufacturer
details for all types of transformers, feeder pillars, masts, columns, lamps and
luminaires that the Contractor will provide.
Technical data sheets, brochures and type test certificates for all types of
transformers, feeder pillars, masts, columns, electrical components, luminaires
and lamps shall be submitted to the Engineeer for approval. The Engineer may
request samples of luminaires for approval.
The Contractor shall submit to the Engineer copies of all agreements made
with TANESCO regarding power supply to the street lighting systems.
Workshop drawings
The Contractor shall prepare and submit workshop drawings in accordance
with the Special
Specifications, comprising as a minimum:
Circuit diagrams for 11 kV connections and transformer assembly drawings
incl. connection ,details
Voltage drop and short-circuit calculations for all final lighting circuits
211
Comprehensive lighting calculations based on the luminaires and lamps
actually provided by the Contractor.
As-built documentation
10 nos. 12 m high lighting poles with double arm including internal electrical
installations and foundation bolts
10 no. 10 m high lighting pole with single arm incl. internal electrical
installations and foundation bolts ‘~
212
The spare parts shall not be used by the Contractor fpor the maintenance
and/or remedial works carried out by the Contractor during the Detects Liability
period
The items shall be measured as lump sum and shall include foundations,
foundation bolts, arms or brackets where specified or shown, terminals, mcb's
and internal cables, labelling and all accessories supplied, installed, connected
and tested in accordance with the Specifications and TANESCO's guidelines
and regulations.
The bid rate shall include full compensation for supplying to the Employer’s
store all spare parts, special tools, documentation and incidentals necessary
for completing the delivery of spare parts as described in this Section.
214
5618 Q3x200 mm LED AUTO SIGNAL LIGHTS
Q5 mm in diameter and 30° degree angled.
7 LEDs connected in series and making one PCB.
Green LEDs are in blues green tone.
In case of out of break of one LED in a group, the electical circuit is not cut off
and the other groups go on working.
Green LEDs work in between 3 – 3.6 volt and the illumination is in 15.000 –
25.000 mcd.
Yellow LEDs work in between 1.8 – 2.4 volt and the illumination is in 12.000 –
15.000 mcd and in amber colour tone.
Red LEDs work in between 1.8 – 2.4 volt and the illumination is in 12.000 –
15.000 mcd
LEDs work with maximum 0.02 ampere.
There are 186 LEDs in (3x200) Ø200mm module.
There are 186 LEDs in (3x300) Ø300mm module
Ø200mm module consumes 6 watt energy.
Ø300mm module consumes 7.5 watt energy.
Ø200-300 modules work with 220-240 VAC (+-%15 )
Modules work with transformer which has 24 volt outlet
Resistant to abnormal air temperature ( - 40°C, + 70°C)
Body is made up of polycarbonate.
Body is in orange, black optional
Glass is made up of transparent polycarbonate.
Insulatıon sealing is used in it.
215
Ø300mm module consumes 7.5 watt energy.
Ø300 modules work with 220-240 VAC (+-%15 )
Modules work with transformer which has 24 volt outlet
Resistant to abnormal air temperature ( - 40°C, + 70°C)
Body is made up of polycarbonate.
Body is in orange, black optional
Glass is made up of transparent polycarbonate.
Insulatıon sealing is used in it.
216
Yellow LEDs work in between 1.8 – 2.4 volt and the illumination is in 12.000 –
15.000 mcd and in amber colour tone.
Red LEDs work in between 1.8 – 2.4 volt and the illumination is in 12.000 –
15.000 mcd
LEDs work with maximum 0.02 ampere.
There are 88 LEDs in Ø1x200mm module.
There are 88 LEDs in Ø1x300mm module
Ø200mm module consumes 6 watt energy.
Ø300mm module consumes 7.5 watt energy.
Ø200-300 modules work with 220-240 VAC (+-%15 )
Modules work with transformer which has 24 volt outlet
Resistant to abnormal air temperature ( - 40°C, + 70°C)
Body is made up of polycarbonate.
Body is in orange, black optional
Glass is made up of transparent polycarbonate.
Insulatıon sealing is used in it.
217
Glass is made up of transparent polycarbonate.
Insulatıon sealing is used in it.
218
Ø200mm module consumes 6 watt energy.
Ø300mm module consumes 7.5 watt energy.
Ø200-300 modules work with 220-240 VAC (+-%15 )
Modules work with transformer which has 24 volt outlet
Resistant to abnormal air temperature ( - 40°C, + 70°C)
Body is made up of polycarbonate.
Body is in orange, black optional
Glass is made up of transparent polycarbonate.
Insulatıon sealing is used in it.
5625 Q200 - Q300 mm. ANIMATED PEDESTRIAN & COUNT DOWN LIGHT’S
LEDs used in 5mm in diameter and 30 ° angle.
The light intensity of the LEDs is 8000-10000mcd.
The LEDs used will be 100.000 hours guaranteed up to + 70 ° C.
Operate in the voltage range 170-250 VAC (50Hz (+ -5Hz)) and will not be
affected by network fluctuations.
Consume a maximum of 20 watts of power.
It will have necessary software and hardware features against interference
from network and external factors.
The materials used will be completely industrial.
Working temperature - 40 ° C + 70 ° C.
Adjusting the night light intensity will use LDR to ensure a clear view and not to
disturb the environment.
Animated pedestrian units will have 1 power signal led.
Animated pedestrian units will be completely under microprocessor control.
Animated pedestrian units will operate independently of the Intersection
control unit. (Any time without knowledge, he will show the passing and
stopping of the springs during his energy.)
By memorizing the green period of the pedestrian, the driver will accelerate the
pedestrian animation in the last few seconds and report that the pedestrian is
about to run out
Pedestrian animation will work throughout the green period.
The body should be made of polycarbonate; the body may be in black-gray-
orange colors.
By calculating the pedestrian green period, it accelerates the animation in the
last seconds and warns the floods.
Insulation seals are to be used on the bodies.
219
5626 MEASUREMENTS AND PAYMENT
Measurement and payment of all street lighting works shall be in accordance
with items listed in the bills of quantities, the preamble to the bills of quantities
and the specifications.
Amend the description of Pay Item 56.15 of the Special Specifications as
follows
ITEM DESCRIPTION UNIT
SS Traffic Lights:
56.06
56.09 Supply and installation of main powered Traffic LED Auto Signal lights, including
(a) 16 Group Intersection Controller, TCO3, 2 Group Intersection Controller, TCO3,
Detector Module, GPSR Module, PS Module, cabling,100mm diameter PVC
sleeve for traffic lights cabling complete with standard and overhead signal
transmitting anchorage pillars, fittings and accessories as per approved
manufacturer's specifications;
(i) Q3x100mm Auto traffic signal light (Type VI) No.
(ii) Q3x200- Q3 X300 mm Arrow Auto traffic signal light (Type VI-IZ) No.
(iii) Q2x200mm Pedestrian traffic signal light (Type PI) No
(iv) Audible Warning Device for Disabilities No
(v) Q2x200mm Animated and Countdown Pedestrian Signal light (R/G) No
(vi) Q2x300mm Animated and Countdown Pedestrian Signal light (R/G) No
56.09 Software, installation, testing and commissioning
(b)
(i) 16-32 Group turn key of the traffic signal lights system (take on the system) L.S
(ii) Traffic lighting system software, materials inspection at factory by 5 persons from L.S
the parties prior to ordering, training, testing of system and commissioning.
56.09 Allow for provision of TANESCO power supply connection for traffic lights for 46 L.S
(c) junctions
56.09 Supply and install Traffic lights poles ,85 mm diameter galvanized steel pipes
(d) including 2-meter arm, earthing of the pole, excavations, backfill and reinforced
concrete post base, bearing plates and anchor bolts.
(i) 3 meters high traffic poles No.
(ii) 8 meters long traffic poles with single arm out reach. No.
220
5700 LANDSCAPING AND GRASSING
5702 MATERIALS
Add after the first paragraph of Sub-Clause 5702(c) and after second
paragraph of Sub-Clause 5702(e) of the Standard Specifications the following:
A grass sod shall be placed on the top of the side slopes in one metre width
from the shoulder breakpoint in order to protect the pavement material against
erosion by water runoff. The remaining disturbed area of the embankment is to
be scarified and hydroseeded as specified in Sub-Clause 5705. The Engineer
may prescribe an anti erosion compound to be added in the hydroseeding
mixture for these areas.
221
Eragrostis (Teff) 5%
Eragrostis curvula (Weeping love grass) 20 %
Paspalum notatum (Bahia grass) 10 %
Chloris gayana (Rhodes grass) 25 %
Digataria eriantha (Finger grass) 20 %
Dactylus glomerata (Cocks foot) 10 %
Locally harvested grass seed 10 %
5708 GENERAL
Add after the first paragraph of Sub-Clause 5708(c) of the Standard
Specifications the following:
All side slope areas which consist of a sandy material shall be hydroseeded
with the addition of an anti erosion compound. The application rate will be as
specified by the manufacturer. PAM (Polyacrylmide) or suitable alternative
may be used.
Payment for the supply of the anti erosion compound will be made under
SUBITEM 57.08 (i) and (ii).
222
to 1:4 side slopes. On gentle sloping areas the distances between the rows
can increase up to 30 metres apart.
Vetiver Hedge Rows can be considered for protection to cut and fill slopes,
bridge approach embankments, gully erosion protecting, storm water and
culvert outlets. Vetiver grass is available in Tanzania.
Where so directed by the Engineer side slopes of drains etc shall be protected
by the laying of a Geo fabric such as “Soil Saver or Biomac”. The matting is to
be placed in accordance with the manufacturer’s specification.
Item Unit
57.13 Soil analysis of topsoil taken from the Site No.
The quantity to be measured for payment shall be the number of soil analysis
undertaken on topsoil samples taken from the Site in accordance with the
Specifications and accepted.
The quantity measured as prescribed above shall be paid for at the Contract
unit price for the pay item, which price and payment shall be full compensation
for taking topsoil sample, laboratory testing and preparation of soil analysis
report with recommendation on type and quantity of fertiliser / soil-
improvement material, including all labour, equipment, tools, transport and all
costs necessary to complete the soil analysis.
5800 FINISHING THE ROAD AND ROAD RESERVE AND TREATING OLD
ROADS
5804 MEASUREMENT AND PAYMENT
Omit both pay items under Clause 5804 of the Standard Specifications and
replace by the following:
223
No separate payment will be made in respect of work undertaken in
compliance with the provisions of this Section. The relevant cost shall be
included by the Contractor in his rates in the Bill of Quantities.
6000 STRUCTURES
Add the following at the beginning of Series 6000:
GENERAL
The extension of existing bridges/box/pipe culverts culverts shall in general be
made as shown on the Drawings and in accordance with the latest edition of
BS 5400 for “Steel, concrete and composite bridges”.
The Section covers foundation works required for extension of existing box
culverts as well as extension and provision of new wing walls including base
slabs and toewalls as specified. It also include associated works such as
channel excavation, while excavation for clearing/desilting under bridges and
in culvert barrels is not included, but covered by Section 2100.
EXCAVATION
Excavation must be done for the approaching wing walls. The works must be
made in two stages, in order to let the river pass while doing the foundation
works. While doing the excavation and the foundation works, the river flow
must be lead to pass only through one of the cells. To minimise the temporary
drainage and pumping works the activities needs to be carried out during the
dry season. The Contractor must plan his work in such a way that this is being
taken care of.
6102 MATERIALS
Add at the end of Clause 6102 of the Standard Specifications the following:
224
(j) Concrete
The concrete for the manufacture of the reinforced concrete piles shall be
Class 30 in accordance with Section 6400 of the Standard Specification and
BS 5610.
6113.01 General
This specification concerns permanent works and is to be read in
conjunction with the conditions of contract, drawings, the General
Specification, theparticular Specification for Precast, Pre tensioned
Spun Pile, Specification for Concrete and Reinforcing Steel for Piling
Work, Specification for Pile Testing and Specification for Excavation.
225
out with full diligence and expedience as are expected for works of
this nature.
All piles shall have protective sleeve for a minimum depth of 3m below
the cut-off level of the pile. This sleeve shall be plastic or metal bedded
in mastic to form a fully water-proofed seal to the concrete.
Pile Foundation:-
Supply and install pile foundation to carry the working loads as
specified in the contract drawings.
Strip pile to cut-off level and check pile eccentricity at cut-off level.
Construct pile caps and ground beams (if applicable) to the underside
of slabs in contact to the ground.
Failure load test of preliminary test piles and working load test of works
piles as specified.
Integrity tests and High Strain Dynamic Load Test on preliminary test
piles and works piles.
The Contractor shall keep records for the installation of each pile and
shall submit two signed copies of these records to the Engineer not
later than noon of the next working day after the pile was installed.
226
shall allow in his tender for variation in the total number of piles to
be installed up to 10% of the provisional number specified at tender
stage.
6113.02.02 Other
Provide temporary drains, sumps and all other measures necessary to
keep the Site dry. Any other
Incidental works, whether of a temporary or permanent nature, for the
satisfactory completion of the contract.
The Contractor shall ensure that his system and method of pile
installation is suitable and safe for use at the proposed site of
work, taking into account the nature and proximity of adjacent
properties and their facilities. The Contractor shall indemnify the
Employer against any expense, liability, loss, claim or proceedings
which the Employer may incur or sustain by reason of damage to any
property real or personal other than works, injury or accident to
workmen or public caused by collapse, subsidence, vibration,
weakening or removal of support or lowering of ground water, arising
out of or in the course of or by reason of the execution of the works.
227
Neither the completeness nor the accuracy of the information provided
is guaranteed. No responsibility is assumed by the Employer or the
Engineer for any opinion or conclusion given in the soil report.
The Contractor shall study the given soil report in detail and shall be
obliged to place his own interpretation on the information provided, and
to make due allowance for the effects of site conditions on his
construction operations. No claims shall be entertained or accepted on
grounds that the information provided is incomplete or incorrect.
228
interpretation of the soil investigation report. The Contractor's report
shall be in the form of a written notice of Adverse Physical Conditions
and Artificial Obstructions which shall be given to the Engineer at the
earliest possible time after encountering such conditions and
obstructions. The report shall be accompanied by all information
available to the Contractor which will materially assist the Engineer
in verifying the conditions reported, and in determining the cause and
reasonableness of any claim relating thereto in accordance with the
conditions of contract.
229
monitoring measures when carrying out his piling operations so as not
to disturb or damage existing adjacent properties and building
foundations. The Contractor shall include in the submission of the
tender his proposal for monitoring adjacent properties for any
detrimental effects arising out of his execution of the piling works, so
that appropriate and timely preventive action can be taken to minimise
damage. The Contractor's monitoring program, when deemed
adequate by the Engineer, shall be included in the contract.
The Contractor shall include in the contract the cost for carrying
out a condition survey of adjacent properties to establish the condition
of the existing buildings and facilities prior to commencement of piling
work. Condition surveys shall be conducted by a registered building
surveyor. The results of the survey shall be lodged with the Architect
for record.
The Contractor shall be responsible for and shall bear the cost of
any claims for damage to adjacent buildings and facilities arising
from his execution of the piling works.
230
the relevant clauses of the contract specification and the latest
British Standard Code of Practice for Foundations BS8004:1986.
In matters not specifically covered by this specification the Contractor
shall comply with BS 8004. Where discrepancies arise between this
specification and BS8004, the provisions of this specification shall take
precedence. The Contractor shall allow in the unit rate for piles the
cost of material quality tests on concrete and reinforcement, which
shall be conducted by him in the manner and at such frequency as
required under the General Concrete Specification.
The method of placing and workability of the concrete shall be such that
a continuous monolithic concrete shaft of the full cross-section is
formed.
The Contractor shall take all precautions in the design of the mix and
placing of concrete to avoid arching of the concrete in temporary
casing. No soil liquid or other foreign matter, which would adversely
affect the performance of the piles, shall be permitted to contaminate
the concrete.
Slump measured at the time of discharge into the pile bore shall be in
accordance with the standard shown in Table 6113/1. The concrete
shall be of the workability approved when in its final position and shall
remain sufficiently workable for all pile construction procedures to be
safely completed.
Table 6113/1
231
concrete between bars.
II 100 - 200 Where reinforcement is not spaced widely; where
cut-off level of concrete is within temporary casing;
where pile bore is water-free and diameter is less
than 600mm.
III 150 or more Where concrete is to be placed by tremie under
water or drilling mud or by pumping.
Unless designated as basement piles all piles shall be placed with their
tops at least 1 meter above pile cut-off level in their respective pile
caps. All bore holes, except for basement piles or unless otherwise
specified, shall be filled with concrete to the top of the hole so that the
Engineer can be assured that the concrete has displaced all the
bentonite. Internal vibrators shall not be used to compact concrete.
Details of the pile caps layout are given in the contract drawings. The
Contractor shall be responsible for determining the lengths of piles
supported by detailed calculations in accordance with the following:
The results of the failure load tests, which shall form the basis for
assessing the depth of penetration required to achieve the pile working
capacity with a minimum factor of safety of 2.0 for compression piles.
232
The bearing in underlying rock formation will only be allowed when
proven by the Contractor to the satisfaction of the Engineer. Proof
shall comprise drilling, sampling and testing of material obtained from
the pile toe and 5 metres or 5 times the pile diameter, whichever the
greater, below the pile toe.
233
Specifications for the proposed system, including type of piling
equipment, maximum length of piles that can be satisfactorily installed
and average output in linear metres of installed pile per piling frame per
normal working day of 8 working hours per day.
234
6113.10 Piles Group
Spacing of piles shall be not less than 2.5 times the diameter of the pile.
The Contractor shall consider the effect of size of the group when
determining the number of piles for the given column loads. He shall
submit his calculation showing the group capacity of the pile group for
the approval of the Engineer. If the group capacity is found to be less
than the required capacity, the Contractor shall provide at his own cost
additional piles as approved by the Engineer to compensate the
deficiency.
235
within the time period stipulated in the approve construction
programme. The Contractor is deemed to have made provision for
the availability of standby plant at all times to allow for the contingency
of equipment failure. Equipment found to have a consistent record of
breakdowns shall be removed from the Site.
236
Other information relevant to the construction activities.
ii. In what respects, in the opinion of the Engineer, the said methods
fail to meet the requirements of the contract or will be detrimental
to the permanent works.
In the latter event, the Contractor shall take such steps or make such
changes in the said methods as may be necessary to meet the
Engineer's requirements and to obtain his consent. While the Engineer
will attempt to respond to such amendments or corrections speedily,
the Contractor shall in no case assume that it can be undertaken in
less than ten (10) working days.
The Contractor shall not change the methods, which have received the
Engineer’s consent without the further consent in writing of the
Engineer, which shall not be unreasonably withheld. Works shall
237
commence at such times when and not before the Engineer has given
his consent to the method of construction.
The Contractor shall not be entitled for extra time and/or cost for his
compliance with the Engineer's instructions on the adequacy and
safety of his method statements.
238
working day ahead for weekday overtime and 2 working days ahead
for weekends shall be considered adequate notice.
239
the Contractor's responsibility, due care shall be taken by the
Contractor in his planning and execution of the Works.
Where piles are not arranged along a single line, the maximum
permissible deviation of the centre of each finished pile in a group of 3
or more piles shall be 75 mm in any direction from the true position of
the same pile, provided also that the centre of the finished pile group
shall not deviate laterally from the true centre of the same group by
more than 40 mm.
The verticality of each pile shall not deviate at any point below the
ground by more than 1 in 75 from the true vertical position.
240
6113.20 Adjacent Piles
Piles shall be installed in such a manner as to ensure that no damage
is sustained by previously installed piles in adjacent positions.
241
directed, cut-off level shall be 75 mm above the underside of pile cap
and all cut-off piles shall be disposed as waste material.
When cutting off and trimming piles to the specified cut-off level, the
Contractor shall take care to avoid shattering or otherwise damaging
the rest of the pile. Any cracked or defective concrete shall be cut away
and the pile to be repaired in an approved manner to provide full and
sound section at the cut-off level
Piles shall not be bored so close to other piles, which have recently
been cast, and which contain workable or unset concrete that a flow of
concrete could be induced from or damage caused to any of the piles.
Where boring takes place through unstable water bearing strata, the
process of excavation and the depth of temporary casing employed
shall be such that soil from outside the area of the pile is not drawn into
the pile section and cavities are not created outside the temporary
casing as it is advanced.
242
Temporary casings shall be extracted while the concrete within them
remains sufficiently workable to ensure that the concrete is not lifted.
During extraction the motion of the casing shall be maintained in an
axial direction relative to the pile.
For piles cast in dry bores using temporary casing and without the use
of a permanent lining, pile heads shall be cast to a level above the
specified cut-off so that, after trimming, a sound concrete connection
with the pile can be made. No pile shall be cast with its head below
standing water level unless approved measures are taken to prevent
inflow of water causing segregation of the concrete as temporary casing
is extracted; and where applicable, the standing water level for each
pile shall be agreed with the Engineer, and this level is to be treated as
the cut-off for the purpose of calculating tolerance.
For piles cast in dry bores within the permanent lining tubes or
permanent casings, or where their cut-off levels are in stable ground
below the base of any casing used, pile heads shall be cast to a level
above the specified cut-off so that, after trimming, a sound concrete
connection with the pile can be made.
243
For piles cast under water or drilling fluid, the pile heads shall be cast to
a level above the specified cut-off so that, after trimming to remove all
debris and contaminated concrete, a sound concrete connection with
the pile can be made.
6113.23 Cleaning Up
The Contractor shall propose to the Engineer the frequency of his
periodic removal of debris from the Site in the course of the work.
The Contractor shall adhere strictly to the agreed program of debris
removal and the Engineer reserve the right to instruct the Contractor to
increase his frequency of debris removal at no extra cost to the
contract.
244
d) Depth of penetration of each pile or reduced level of toe of each pile
and cut-off level of each pile.
The format of the record shall be approved by the Engineer and shall contain
but not be limited to the following information where applicable:
- Pile Location Mark (All Pile)
- Pile Type (Compression or Tension) (All Pile)
- Pile Size (All Pile)
- Date and Time of Installation (All Pile)
- Date of Concreting (Bored Pile)
- Concrete Mix (Bored Pile)
- Method of Concreting (Bored Pile)
- Standing Ground water Level (Bored Pile)
- Pile Reference (Driven Pile)
- Driving Record (penetration & blow count) (Driven Pile)
- Set Value (Driven Pile)
- Combination of Pile Lengths (Driven Pile)
- Weather Condition (All Pile)
- Ground Level Before Commencement of Pile Installation (All Pile)
- Working Level of Ground for Pile Installation (All Pile)
- Depth from Working Level to Pile Toe (All Pile)
- Level of Pile Toe (All Pile)
- Pile Cut-off Level (All Pile)
- Depth from Cut-off Level to Pile Toe (Pay Length) (All Pile)
- Length of Temporary Casing (Bored Pile)
245
- Length of Permanent Casing (Bored Pile)
- Details of Soil Strata Penetrated (Bored Pile)
- Soil Samples taken and In-situ Tests carried out (Bored Pile)
- Length and Details of Reinforcement (Bored Pile)
- Estimated Volume of Concrete required to form the pile shaft (Bored Pile)
- Actual Volume of Concrete used in forming the pile shaft (Bored Pile)
- Type and Model of Plant, Equipment
All records shall bear the names of person who records and person who
checks.
6113.28 Wastages
It is held that the Contractor is responsible for and shall bear the cost of
all wastages in material, labour and plant arising from his execution of
the works.
6404 MATERIALS
Add at the end of Clause 6404 “(b) Strength concrete” of the Standard
Specifications the following:
The following concrete grades for use in the structures are applicable
unless otherwise shown on the Drawings or specified by the Engineer:
246
6900 REHABILITATION OF EXISTING CONCRETE AND MASONRY
STRUCTURES
6901 SCOPE
This Section covers the repair of existing concrete and masonry
structures by patching, pointing and coping.
The type of repair work required for rehabilitation of the structures might
change by the time of construction. Therefore the Engineer will on the
Site verify if the repair works shown on the Drawing are appropriate for
the given structure at the time of construction and shall instruct on type
and extent of repair work to be carried out.
6902 WORKMANSHIP
The Contractor should engage experienced personnel to accomplish
restoration of Concrete and masonry structures. The experience shall
be relevant to anticipated conditions and to the special techniques
required. The Contractor shall demonstrate to the satisfaction of the
Engineer evidence of the above required experience and dependability
of equipment and techniques to be used and shall submit
documentation of past projects on which this type of work has been
performed. If as an experienced contractor he wants to use his own
technique for the repair works he must get the prior approval of the
Engineer on site.
6903 MATERIALS
(a) General
All materials shall conform to the relevant requirements of Section 2500
and Section 6400.
247
Injection materials
Materials for injection shall be from a well-reputed company, and it shall
be proven that, the materials have been used for similar works in a
number of other cases with good result.
The materials shall be duly dated and may only be used if the time limit
for the materials has not expired. The materials shall be stored properly
and shall be kept dry at all time.
248
provided. The time period recommended by the manufacturer before
opening to traffic shall be observed.
Temporary access for traffic shall be provided and kept good by the
Contractor for the structural restoration work.
6904 INJECTION
Personnel with experience in similar jobs shall carry out the works,
which are of a specialised character.
249
Identification of cracks for injection. The cracks, which are suitable for
repair with injection, are rather deep cracks (more than 50 mm deep),
but not necessarily very wide cracks.
The actual concrete zone shall be cleaned and the drilling works shall
be carried out and cleaned again with high pressure jet air. Dependent
on the final choice of material for injection, the actual zone shall be pre-
watered.
The injection material shall be injected into the drilled holes, which shall
be sealed off after finalisation.
After sealing of the repaired zone, this shall be nicely finished, and after
hardening eventually grinded.
There shall be prepared an injection journal for the works, in which the
considerations from the injection works shall be recorded.
6905 PATCHING
This work consists of the repair and resealing of cracks and spallings in
existing concrete structures.
250
ceased, the cracks/spallings shall be flushed with water and brushed
again. After flushing and rebrushing, the cracks/spallings shall be blown
out with compressed air.
(iv) Sawing
Sawing shall be limited to only exposing clean, new concrete faces on
the cracks/spallings with a minimum allowable cut of 1.5 mm on each
face of the cracks/spallings. All dust, sawing residue, or other
contamination shall be removed from the cracks/spallings faces. If wet
sawing with diamond or abrasive blades is used, the sawing residue
shall be removed by blowing out the cracks/spallings and surrounding
area with compressed air. If dry sawing with diamond or abrasive
blades is used, the resulting saw laitence or slurry shall be completely
removed from the cracks/spallings and surrounding area by flushing
clean with a high-pressure jet of clean water. After flushing, the
cracks/spallings shall be blown out with compressed air.
251
For Accelerated Cement Concrete patching the epoxy prime coat shall
be applied in a thin coating and scrubbed into the surface with a stiff
bristled brush. Placement of the concrete shall be deployed until the
epoxy becomes tacky. The patch mixture shall be placed and
consolidated to eliminate voids at the interface of the patch and existing
concrete.
6906 POINTING
(a) Scope
This work shall consist of repairing existing masonry mortar joints by
pointing after thoroughly cleaning the joints and removing of all loose
mortar and foreign material.
(b) Materials
Cement and sand for the mortar shall be in accordance with Sub-clause
6400. The mortar shall be composed of 1 part cement to 3 parts of sand
by volume with sufficient water to produce a mortar with thick, cream
consistency.
(c) Construction
Where pointing of existing masonry structures are specified for a
particular area of the structure all loose or partly disintegrated mortar in
the joints of such area shall be scraped or lightly chiselled out to a
minimum depth of 20 mm below the face of the stones.
The joints shall be made moist just before starting of the pointing. The
mortar shall be flush pointed unless the existing pointing is with raked
252
joints in which case also the new pointing shall be raked out squarely to
the same depth as the existing pointing.
Immediately after the pointing all face stone shall be thoroughly cleaned
of mortar stains and shall be kept clean until the work is completed.
Before final acceptance and if ordered by the Engineer, the surface of
the masonry shall be cleaned using wire brushes and acid if necessary.
The pointing shall be protected from direct sunshine and kept moist for
a minimum of 24 hours after completion.
6907 COPING
(a) Scope
This work shall consist of repairing existing or providing new coping on
top of existing masonry walls and gabions.
(b) Materials
Mass concrete Class 20/14 in accordance with Clause 6402 shall be
used for the coping, except for minor repairs for which the materials
shall be composed of 1 part cement to 3 parts of sand by volume with
sufficient water to produce a mortar with thick, cream consistency.
(c) Construction
Where coping of existing masonry structures are specified for a
particular area of the structure all loose or partly disintegrated mortar or
concrete of such area shall be removed.
After thoroughly cleaning the surface of the masonry it shall, just prior to
placing of coping material, be made moist. Necessary side forms for
Class F3 Surface Finish in accordance with Sub-clause 6209(c) shall be
fixed before placing of the coping concrete.
The coping shall be protected from direct sunshine and kept moist for a
minimum of 48 hours after completion.
253
6908 EXTENSION OF EXISTING CONCRETE STRUCTURES
Scope
This Section covers the extension of existing concrete structures such
as pipe culverts, box culverts and underpasses.
The type of repair work required for extension of the structures might
change by the time of construction. Therefore the Engineer will on the
Site verify if the extension works shown on the Drawing are appropriate
for the given structure at the time of construction and shall instruct on
type and extent of work to be carried out.
254
Preparing Existing Structure for Extension
All un-necessary parts of the structure (wing walls, parapets, etc.) will
be removed with a care not to disturb the remaining parts/connections
of the structure.
ITEM UNIT
69.01(a) Crack repair by mortar injection metre (m)
The tendered rates shall include full compensation for all costs and direct,
incidental and ancillary expenses for furnishing all materials and works,
including drilling of injection holes, cleaning by high pressure jet air, mortar
injection, sealing, refacing and finishing, as specified in the Contract
Documents.
255
ITEM UNIT
69.01(b) Concrete patching square metre (m2)
The tendered rates shall include full compensation for all costs and direct,
incidental and ancillary expenses for furnishing all materials and works,
including preparation of test repair specimens, refacing, cutting crack
reservoir, cleaning patching and finishing, as specified in the Contract
Documents.
ITEM UNIT
69.01(c) Pointing of existing masonry and gabions square metre (m2)
The unit of measurement shall be the metre of stone masonry joints repaired
by mortar pointing according to the Contract Documents.
The tendered rate shall include full compensation for all costs and direct,
incidental and ancillary expenses for furnishing all materials and works,
including chiselling, cleaning joints, pointing, cleaning of stone surfaces and
protection of the works as specified in the Contract Documents.
ITEM UNIT
69.01(d) Coping of existing masonry and gabions cubic metre (m3)
The unit of measurement shall be the cubic metre of concrete for coping of
existing stone masonry and gabions according to the Contract Documents.
The tendered rate shall include full compensation for all costs and direct,
incidental and ancillary expenses for furnishing all materials and works,
removal of old damaged coping, cleaning, fixing of side forms, placing of
coping concrete, finishing and protection of the works as specified in the
Contract Documents.
256
7000 TOLERANCES, TESTING AND QUALITY CONTROL
7100 TESTING OF MATERIALS AND WORKMANSHIP
7109 TAKING AND SUBMITTING SAMPLES
Add at the end of Clause 7109(a) of the Standard Specifications the following:
Test results shall be submitted daily and without delay to the Engineer in both
in hard copy and digital format with layout to be agreed with the Engineer.
Routine inspection and spot checks will be carried out by the Engineer to
check the completed work for compliance with the dimensional tolerances,
quality of material, density of compaction and any further requirements stated
in this Section 7100.
257
Layer and Test to be Sampling frequency, minimum
nominal carried
class of out
material
Softening Point 1 sample per 40 tonnesor twice per
week as decided by the Engineer
Note 1: % of Gmm at Nini, % of Gmm at Nmax, VFA at Ndes, VMA at Ndes, Air
Voids at Ndes
The Contractor shall have on the Site all the relevant standards required for
the work he is to undertake under the Contract. A second complete set of such
standards shall be available for the sole use of the Engineer.
258
Layer and nominal class of material Frequency, minimum Absolute
minimum
Asphalt Field core density (AASHTO 1 test every 400 m2 6 per
concrete T166, Method A), compaction production day
surfacing percent, air voids content and
core thickness
Thickness 1 test every 400 m2 6 per
measured from cores drilled production day
for field density
Tensile Strength Ratio Every third production day (3
(AASHTO T283) dry and 3 conditioned cores
taken from the mat)
259
The Engineer may approve that AASHTO T 238 Method B (nuclear density
gauge) is used as basis for approval of the compaction work for earthwork and
CRR layers after calibration of this method with BS 1377:Part 9:1990. If
nuclear density gauges are approved the Contractor shall carry out the tests
and calibrate the nuclear density gauges for each type of material used and in
accordance with Sub-clause 7114(c). If the Contractor chooses to apply this
method a calibrated nuclear density gauge shall be available for the
Engineer's laboratory. The calibration shall be repeated at regular intervals or
when requested by the Engineer.
abs( Xo − Xn)
To =
Sn
Where Xn and Sn are the arithmetic mean and the sample standard deviation
respectively, and Xo is the value of the test differing most from the mean.
Compare the value of to with the value of T for the applicable value of n from
Table 7204/1.
If To is greater than T, then Xo is an outlier.
Every outlier shall be disregarded and replaced by another random test value.
The sample mean and the sample standard deviation shall then be
recalculated. If an outlier cannot be replaced, the sample mean and the
standard deviation shall be calculated using the remaining test results. The
260
final number of test results used in the assessment, after the elimination of
outliers, shall never be less than three.
7205 PROCEDURES
Replace the entire Sub-clause 7205 (f) including Table 7205/1 of the Standard
Specifications by the following:
261
After outliers have been examined and replaced as directed by the Engineer,
compliance with the specified density requirements shall be determined by the
statistical method specified below unless a fixed minimum average value
and/or absolute minimum value has been specified for the compaction
elsewhere in these Specifications.
The lot will be considered to comply with the requirements for field density if
the following conditions are fulfilled:
Accept the lot if the sample mean satisfies the expression, otherwise
reject the lot.
Where
0.5
(X - X n )2
Sn =
n-1
where
262
K is a statistical constant defined by:
t
K=
n
where
t is the Student's t.
263
SIGNAL TRANSMITTER PILLAR
The signal to the bottom of the pillar of the standard 300 mm diameter and
10 mm thick st 37 sheet must be flange. In addition 6x7 x120 mm, 4 flag
sheet must be secured by welding on the sheet. For wiring, sheets should
have 10cm hole in the middle of the flange.
Special leak-proof top cap should be installed to pillars for water and dust
protection.
264
(width x height x height) where refuge protection is available, and should
be additional 50 cm higher and as much as close to edges where refuge
protection is not available.
Pillar lengths should be at least 200 cm for 5 fingered and at least 250 for
4 fingered and L shaped console pillar length should be as long as where
the middle of the road is.
265
6 x M16 bolts with 40 cm diameter should be welded to sheets for lower
anchorage. Bolt lengths must be 53 cm.
With the top of the pillar konsülü the angle between the lower konsülü will
be more than 90 degrees.
Special leak-proof top cap should be installed to pillars for water and dust
protection.
266
SECTION VI (2C): BUILDING WORK SPECIFICATIONS FOR BUS
STATIONS
267
1.0 General description of materials and workmanship
The following apply to all sections hereafter
1.2.3 Standards
Where commodities or workmanship are specified by reference of British
Standard (BS) or codes of practice (CP) or International (ISO) or Tanzania
Standard or other Standards, such standards are deemed to be the latest
published at the time of tendering. The Contractor will be deemed to have read
and understood the standards specified, and no claim of want of knowledge
will be allowed. The substitution of commodities or standards of workmanship
complying with other standards may be well allowed at the discretion of the
Engineer, but application for permission for such substitution must be made in
writing in sufficient time to allow adequate investigation. Obtain Certificate of
Compliance with standards and supply to the Engineer on request.
268
1.2.4 Local conditions
All materials, commodities, components and equipment must be suitable for
use in tropical climates.
1.2.5 Samples
Where samples of commodities or specimens of finished work are specified
submit samples or specimens to the Engineer and obtain his approval before
confirming orders or carrying out the work. Finished work must conform in all
respects with the samples or specimens approved. Remove samples and
specimens when no longer required. The cost of supplying samples and
specimens deemed to be included in finished work.
The items of pulling down and alterations are to include for both labour and
materials and for any shoring, needling and strutting and temporary works in
connection therewith. The contractor must allow in his pricing for making good
all works disturbed in all trades and for carting away all debris arising.
The Contractor must give all necessary notices and must exercise due care in
the demolitions. He must not collapse large sections of walls, floors, etc, and
must provide all necessary shoring and supports during the demolitions.
During demolition works the Contractor shall keep the debris constantly
watered to minimise the dust arising and this shall be included in the prices.
All materials arising from the demolitions, unless specifically stated otherwise,
are to become the property of the Contractor and any credit allowed for the
value of such materials shall be shown in the space provided.
269
All materials, including rubbish shall be removed from the Site as soon as
possible.
‘Remove’ shall mean taking down, hacking up, breaking down, removing, etc,
and clearing away from Site and all other expenses thereby entailed.
‘Make good’ shall be deemed to mean, all making good, fitting, facing,
plastering, paving, repairing and painting to match and jointing to remaining
existing work.
‘Re-fix” shall apply to existing materials arising from the Works and shall mean
take from store and fix in new position, including making good, repairing and
adjusting as necessary.
270
3.0 EXCAVATION AND EARTHWORK
3.1 Nature of excavation
The contractor must ascertain for him the nature of the material to be
excavated and price work accordingly as no allowance will be made beyond
the contract sum of any alleged ignorance in this respect.
271
Generally formwork has not been measured for plain concrete foundations or
column bases and therefore, excavations for these has been measured net.
Formwork has been measured to reinforced concrete foundations and column
bases and all faces of columns and walls and working space excavation has
been measured and included accordingly. Adjustments to excavations widths
as measured will, therefore, be made only in the case of the Structural
Engineer ordering the addition of formwork to plain concrete foundations etc,
or the omissions of formwork to reinforced concrete foundations or column
bases. Ordinary use of planking and strutting along foundations to prevent
earth falls and to save concrete will not be considered as formwork.
3.6 Rock
Rock shall be defined as “Compact rock of such hardness and compaction that
it cannot be removed with a pick but requires the use of sledges or
compressor driven tools or blasting to remove it,” and the Engineer’s opinion
shall be final. Excavation in any material such as compacted murrum, soft tuff,
stiff clay or similar materials which in the opinion of the Engineercan be
reasonably be removed by pick, traxcavator or similar means will be deemed
to be included in the prices for normal excavation.
3.7 Blasting
No blasting will be permitted.
3.8 Inspection
When the excavations have been made to the sizes and depths required from
the drawings, the Structural Engineer shall be called to the site immediately for
an inspection, and upon approval the Contractor shall proceed with the work to
prevent rainwater or other surface water draining into the foundations. The
excavations are to be left open until any variation in depth has been measured
and agreed.
272
3.9 Excavation below required depths
Should any excavation be made below the levels or lines shown on the
drawings or otherwise required by the Structural Engineer, the contractor must
fill up the resultant over-excavation to the proper levels or lines with concrete
nominal mix (1:4:8) at his own expense (see "concrete work").
3.10 Filling
The fill shall be clean, selected coarse sand or gravel. It should be taken from
borrow pits if the soil on the site is found to contain too much fines and to have
too low plasticity limit to be used as fill.
At each area (control area) of 500m2 compacted fill, three-field density tests
(e.g. by the sand replacement method) should be taken randomly.
The Control area shall be accepted if all three-test results are above 97% of
the maximum density as determined at a homogenous mixing of all three
samples by the Standard Proctor Method. Otherwise, repeat the test, each
time with three new samples until the above requirement is met or re-compact
and test again.
273
3.12 Levelling
No item is measured for levelling and consolidating ground and rates for
excavation must include for levelling and preparing the ground for concrete or
other works including ramming or rolling.
That the chemicals applied comply with the requirements specified herein for
chemical concentration and rates of application.
That the treatment will remain effective against termite infestation for a period
of five years.
The free re-treatment by the firm of any areas showing signs of infestation
before the expiry of the five-year period.
Some of the chemicals listed above are toxic to animal and plant life and must
therefore, be applied only with caution by an experienced person. Where
individual water supply systems are proposed precautions must be taken to
274
prevent in filtering and endangering the water supply. Treatment shall not be
made when soils of fill are excessively wet or immediately after heavy rain.
The rate of application is to be 5 litres per square metre and the areas
measured include those under floor and round wall and column foundations.
The contractor shall notify the structural engineer in sufficient time before the
filling of foundation trenches and laying of concrete floor bed in order that the
Engineer may nominate a specialist firm to execute the soil sterilisation.
Any additional costs caused by the contractor not rendering sufficient prior
notice to the Engineer will be borne entirely by the Contractor.
275
the Structural Engineer due to such failure. An item has been included in these
Bills in each relevant section.
3.17 Hardcore
Hardcore shall be hard crushed stone to pass a 100mm ring in all directions.
No sand, quarry dust or fine material will be permitted. All hardcore beds shall
be topped with a layer of fine stone or aggregates minimum size 12mm to fill
the voids on the surface to receive concrete beds. Rates for hardcore shall
include for levelling or finishing or laying to falls and consolidating by rolling as
described for "Filling" above.
In rates for item “allow for keeping the whole of excavations free from water”
the Contractor shall allow and make provision for keeping the whole Works
thoroughly drained and clear of water below the lowest level of any part of
them so long as may be required if considered necessary by the Engineer,
continuously day and night by petrol or hand pumps or other mechanical
appliances, pipes, chutes, dams, manholes, sumps, diversions or any other
means necessary for the that purpose. Water pumped from trenches shall not
be allowed to run down the road channels but shall be conveyed to the nearest
surface water sewer, ditch or river through troughs, chutes or pipes.
276
3.19 Rates for Disposal
Rates for disposal of excavated material are to include for selection of spoil as
it arises and for all double handling and re-excavation from spoil heaps not
specifically ordered by the Engineer.
277
4.0 CONCRETE WORK
4.1 Materials and workmanship generally
The recommendations of the recent British Standard Codes of Practice BS
5610 for the Structural use of reinforced concrete in buildings shall be deemed
to be incorporated in these preamble clauses unless otherwise specifically
stated.
4.3 Cement
The cement, unless otherwise specified on the drawings shall be Ordinary
Portland Cement of approved manufacture, delivered in the manufacturer's
bags and shall comply in all respects with the requirements of the latest British
Standard 12. The consignments of cement shall be delivered in sealed bags
and shall be stored on the site so as to be used in the order in which they are
delivered. The structural engineer shall have the right to take samples for
testing in accordance with BS. 12 and the contractor are to obtain current
certificates of test from the manufacturer prior to bulk deliveries. Under no
circumstances is High Alumina Cement to be used.
Rapid hardening cement may be used in lieu of ordinary Portland cement only
with the prior approval of the Engineer or Engineer, provided that all conditions
applying to its use are strictly observed. Any additional expenses in
connection with the use of such cement shall be borne by the Contractor.
278
called upon by the Structural Engineer for testing in accordance with BS. 856.
Normal aggregates will have particle densities of greater than 2000 Kg / m 3 but
not exceeding 3,000 Kg/ m3.Only approved materials shall be used.
Graded samples of all types of aggregate shall, after approval, be kept on site
behind glass for visual checking of subsequent deliveries for grading, shape
and where applicable, colour. Aggregate shall be stored on site on paved
areas with divisions between each type of aggregate, and shall be used in the
order in which they are received on site. No aggregate shall be stored directly
on the ground.
The four nominal aggregate sizes shall be 40mm (1½"); 20mm (3/4"); 10mm
(3/8"); 6mm (¼"); and the grading when analysed as described in BS. 562
shall be within the limits given in BS. 856. Structural Engineer will specify sizes
of aggregates to be used in specific areas. For most work 20 mm maximum
size aggregates will be used. The nominal maximum size of coarse
aggregates should be not greater than ¼ of the minimum thickness of concrete
section or element.
4.7 Water
Water used for mixing of concrete, washing out of shuttering and similar
purpose shall be clean, fresh and free from organic impurities in amounts likely
to impair the quality of the concrete and should comply with requirements of
BS 5328 and BS 3148:1980 “Methods of test for water for making concrete”.
279
4.8 Admixtures
Structural Engineer will approve all concrete admixtures after submission of
specifications or proprietary brands and relevant trial mix verification at site by
Contractor. Admixtures to comply with BS 5075: Concrete Admixtures.
The steel shall be stored so that it is kept clean and reasonably free from rust.
The number, size, form and position of all reinforcement shall unless otherwise
directed or permitted by the Engineer, be strictly in accordance with the
drawings. Bars shall be of the required lengths, and lapping, except where
indicated on the drawings, is not permitted unless approved by the Engineer.
280
Overall dimensions shall not be exceeded and shall not be less than 6mm
below the required dimensions. The sizes of links and the like shall be within
tolerance of 3mm under or over the specified dimensions. Any tolerance in the
top length of the bar as cut shall be taken up in the end hooks or other
approved portions of the bar. The internal radius of the bends at corners of
links and the like shall equal half the diameter of the bar embraced by the link.
Laps in bars of random lengths shall be staggered in such a way that no more
than 1/3 of bars having same number are to be lapped in the same section.
The steel reinforcement shall be assembled and fixed in the form of a rigid
cage. To prevent displacement before or during concreting the bars shall be
secured to each other with approved wire. Concrete distance blocks shall,
unless otherwise directed, be used between the reinforcement and the bottom
and sides of the forms to ensure correct concrete cover to the bars, as
specified on the drawings. The specified cover shall be provided and
maintained within the specified tolerance.
Great care must be taken to ensure the correct positioning of beam and
column starter bars and to secure projecting bars against displacement both
during and after concreting.
At the time of fixing and when concrete is being placed, all reinforcement shall
be free from oil, paint, grease excessive dust and scale or any other coating,
which would destroy its bond with the concrete.
281
4.12 Construction and Movement joints
The positioning, type and frequency of construction joints are to conform to
requirement of BS 5610 and be approved by Engineer. Methods of forming
movement joints to follow drawings and the requirements of BS 5610.
NOMINAL
G MAX.SIZE MAX WATER MINIMUM CRUSHING
1:1:2
3 20mm 0.45 24
7 DAYS 35
8 DAYS OF
MIX
R OF COARSE CEMENT STRENGTH
1:1:2
3
5 20mm 0.50 20 30
A
1:1½:3
2 AGGREGATE
20mm RATIO
0.55 BY WORKS
17 TEST
25.5
0
1:2:4
D
2
5 20mm WEIGHT
0.60 CUBES (N/mm2)
14 20
1:3:6
1
E
0 25mm 0.60 8 15
1:4:8
1
5 40mm 0.60 - 10
0
282
Contractor will be responsible for submitting his proposals for the concrete mix
proportions together with aggregate grading curves to the Engineer for
approval and for the payment of the fees of an approved Testing Authority in
carrying out the crushing tests. The strength of the preliminary cubes must be
a minimum of 33% above those in the above table, which is the minimum
works strength.
The approval of any mix by the Engineer will not relieve the contractor of the
responsibility for ensuring that all concrete used in the works obtain the
minimum works strength shown above.
Only sufficient water shall be added to the cement and aggregate during
mixing to produce a concrete having sufficient workability to enable it to be
well consolidated, to be worked into the corners of the shuttering and around
the reinforcement, to give the specified surface finish and to have the specified
strength. When a suitable amount of water has been determined the resulting
consistency shall be maintained throughout the corresponding parts of the
work and the slump test or compaction factor test shall be carried out from
time to time to ensure the maintenance of this consistency. In no case should
the slump be more than 65mm as determined by the standard slump test nor
should the compaction factor be more than 0.87 as determined by the
standard compaction factor test as described in BS. 1856.
283
The cube shall be made, cured and tested in accordance with the
requirements of BS. 1856 when directed by the Engineer and in his presence
or that of the Approved Testing Authority. A sample of concrete shall be taken
at random on eight separate occasions during each of the first 5 days of using
that mix.
Thereafter at least one sample shall be taken on each day any concrete of that
particular mix is used. From each sample four cubes shall be made two for
testing at 7 days and two for testing at 28 days. The works cube results shall
be examined both individually and in consecutive (but not overlapping) sets of
four, for which the average and the range of each set are calculated.
The mix proportions shall be modified to increase the strength if, in the first
and consecutive (but not overlapping) sets, any of the following conditions are
not satisfied:-
a. Not more than 2 individual results of the 40-cube test should fall below
the specified work cube strength.
b. No value of the range in any set should exceed 4 times the designed
standard deviation.
c. Not more than one set should have an average, which is less than the
specified strength plus 1.1/3 times the designed standard deviations.
d. No value of the average for any set should be less than the specified
strength plus the designed standard deviation.
After 10 consecutive sets of results have been obtained the overall average
and the standard deviation of the 40 results shall be calculated and any
appropriate modifications made. Subsequently, if any of the foregoing
conditions are not satisfied, the overall average and the standard deviation of
the previous consecutive 40 results, including the non-complying sets, should
be calculated and the appropriate steps taken if the overall average strength
twice the standard deviation is less than the specified work cube strength.
284
4.17 Quality control requirements
4.17.1 Supervision
A competent person shall be employed whose duty shall be to supervise all
stages in the preparation and placing of the concrete. He shall supervise all
tests on the materials and cubes and the maintenance and calibration of
mixing and measuring plant. This person shall also be responsible for keeping
an accurate record of the dates on which concrete is poured and where.
Where the Engineer is not satisfied with the performance of concrete
supervisor he shall recommend to the Engineer for removal from site.
4.18 Workmanship
4.18.1 Placing of reinforcement
Reinforcement shall be accurately placed and maintained in the position
described on the drawings or elsewhere to the entire satisfaction of the
Engineer. Bars intended to be in contact at passing points shall be securely
wired together with 16 gauge annealed soft iron tying wire.
Binders and the like shall tightly embrace the bars and any slackness or
misplacement of bars shall be rectified before the Engineer is called for
inspection. Spacers of approved design shall be used for ensuring the correct
positioning of the bars and diagonal wiring shall be provided to ensure rigidity
of all assembled units of reinforcement. The vertical distance required
between successive layers of bars in beams or similar members shall be
maintained by the provision of mild steel spacer bars inserted at such intervals
that the main bars do not perceptibly sag between spacers. The rates for
reinforcement must include for all requisite wiring, spacers and precast
concrete blocks to maintain the required spacing and cover. All bars are to be
bent in accordance with BS 4466: 1969.
285
Cover of concrete to the reinforcement shall be, unless shown otherwise:-
Columns - 40mm minimum to main bars
Base - 50mm minimum to main bars
Beams - 25mm minimum to main bars
Slab - 15mm minimum to main bars
Wall - 25mm minimum to main bars
Raft slab - 100mm minimum to main bars
All formwork and moulds shall be rigidly constructed to accurate shape and
dimensions as described on the drawings and to requirement of BS 5975.
Timber shall be well seasoned, free from loose knots and be of a kind and
thickness that will avoid deflection and warping, remaining true to line and
level. Faces in contact with the concrete shall be free from adhering grout,
projecting nails, splits or other defects and shall be coated with an approved
mould oil so as to prevent grout adhering to them, care being taken to prevent
such coatings from any contact with the reinforcement.
286
Joints in the moulds of formwork shall be carefully made so as to prevent
leakage of cement grout and particular care shall be exercised to this respect
for moulds in which it is intended to place vibrated concrete. Openings in the
formwork for inspection of the inside and for the escape of water used for
washing out accumulated debris shall be formed in such a manner that they
can effectively be closed before placing the concrete.
If formwork of columns; walls and other deep sections is erected to the full
heights, one side shall be left open and shall be built up in sections as placing
of the concrete proceeds. Before concreting, bolts and fixings shall be in
position. Cores and other devices used for the forming of openings, holes,
pockets, chases, recesses and other cavities shall be fixed to the formwork
and no subsequent holes shall be cut in any concrete without the Engineer's
approval
287
The Engineer shall approve mixing of each batch. Mixing of each batch shall
continue until the concrete is uniform in colour and, in any case, for not less
than two minutes after all the materials and the water is used in the drum. The
entire contents of the drum shall be discharged before the materials for the
succeeding batch are fed into the drum. Upon completion of the day's mixing,
the drum shall be thoroughly cleaned free of adhering concrete.
(1) The class of concrete required is specified in the following table, on the
drawings and/or in the Bills of Quantities for the particular position of the works
to be constructed.
(2) The quantity of water added shall only be sufficient to produce a dense
concrete which can be fully compacted without undue difficulty, due allowance
being made for the moisture content of the aggregates.
7 days 28 days
Kgs mm - N/mm2 N/mm2
For blinding concrete in normal
C15 220 20 - 10 15
structures and manholes
288
4.18.5 Distribution of Concrete
The concrete shall be distributed from the mixer to the position required by
approved means, which do not cause separations or otherwise impair the
quality of the concrete. All equipment shall be cleaned before commencing
mixing and distribution and be kept free from set concrete. All concrete must
be in position and consolidated before the initial set is commenced and the
contractor shall ascertain the initial setting time for the brand of cement being
used and ensure that his means of distribution are such that it is impossible for
concrete to have set prior to placing.
289
4.18.7 Vibration
Mechanical vibrators or hand tamping must be used in placing all reinforced
concrete work unless the Engineer has approved specially designed mixes
and preliminary work cube test results have been obtained without their use.
Rates for all reinforced concrete work include for this. Where mechanical
vibration is required the contractor shall allow for using two vibrators at any
one time.
290
width, if any required for working space. The Engineer shall decide the depths
where these are not given on the drawings. Any obstructions or unusual solids
encountered during the excavation shall be reported to the Engineer and dealt
with as then instructed.
The formwork shall be removed in all cases by gradual easing without jarring
and the process shall be such that the sharp edges of the concrete are not
chipped and spilled away. If the imposition of a load is anticipated, props shall
be provided in an approved manner after removal of the formwork and before
the imposition of the loads.
The concrete shall be of the grade specified on the drawings but with
maximumaggregate size 12mm and shall be thoroughly vibrated in the moulds
and shall not be removed until seven days after placing the concrete.
Prices for precast concrete shall include for all moulds, reinforcement as
specified, hoisting and fixing in the position required bedding and pointing as
described and temporary props and other necessary supports.
292
4.21 General
No holes or chases are to be cut in any part of the reinforced concrete
construction without first consulting the Engineer. No part of the reinforcement
shall be used for conduiting electrical current. Notice must be taken of any
appearing on the drawing and not mentioned in these preambles.
Joints topping are to be 'Plastic' or similar approved hot poured rubber bitumen
compound.
Rates for the expansion or separation joint shall include all necessary labour
and the materials described above, temporary supports and cutting where
required to line with concrete surfaces finished to falls. Formwork has been
measured as a separate item to one side only of expansion joints.
Rates for mortises shall include for all necessary templates and raking out and
the complete removal of the polystyrene when the concrete has set. No
deduction from concrete quantities has been made for any mortise, pocket or
any other void in the concrete of 0.05 cubic metres or less and the Contractor
may take this into account when pricing. Grouting up has been measured
separately.
293
4.24 Pricing concrete work
The Contractor must allow for all costs incurred during the progress of the
Contract for complying with the provisions concerning the preparation and use
of graded mixes.
Prices for plain or reinforced concrete shall include for mixing, hoisting,
depositing, compacting, curing and protecting at various levels required
throughout the building, and shall also include for forming or hacking a
satisfactory key for all faces receiving asphalt and plaster work. Prices for
slabs shall include for forming construction joints at bay edges, including all
necessary temporary formwork and supplying records of such joints to the
Engineer.
Prices for steel bar reinforcement shall include for cutting to lengths and all
labour in bending and cranking, forming hooked ends, handling, hoisting and
fixing in position and for providing all necessary tying wire, spacer blocks and
supports. Prices for fabric reinforcement shall include for all straight cutting
and waste, handling, hoisting and fixing in position, providing all necessary
tying wire, and supports and all extra material in laps.
The prices for formwork shall include for extra materials at joints, extra labour
and waste for narrow widths, small quantities, overlaps, passings, etc, and for
fixing at the various levels including battens, struts, and supports and for
bolting, wedging, easing striking and removal. Prices for linear items such as
boxing shall include for angles and ends,
Prices of all precast concrete shall include all moulds, finishing as described,
handling, reinforcement, hoisting and fixing at the required levels and for
casting or cutting to the exact lengths required and any waste resulting from
such cutting.
Prices for expansion joints shall include for cutting to size and all temporary
supports and prices of expansion joint sealers shall include for all temporary
battens or fillets required to form the necessary grooves.
Prices fro hollow concrete block suspended construction must be “all inclusive”
to include for concrete hollow tiles, in-situ concrete ribs, concrete topping,
294
concrete filling to open ends of hollow concrete tiles and solid concrete
bearings and beams.
The Contractor is to allow in his prices for carrying out tests as specified in this
section.
The prices for wrought (wrot) formwork shall include for fair face finish either
by rubbing down or by smooth lining all faces as described in these
preambles.
5.0 WATERPROOFING
5.1 General
5.1.1 Description
Furnish all labor, materials, services and equipment required for the
membrane waterproofing of the entire structure below grade and roofing
system as well as indicated and as hereinafter specified shall include all
related material and accessories as required to achieve a completely
watertight installation in strict accordance with the manufacturer's
recommendations.
Submittals
Submit shop drawings for approval prior to proceeding with work.
Shop drawings shall include: Outline of waterproofing area and size, location
and type of all penetrations, perimeter and penetration details, and special
details.
Store materials, except membrane, in dry area and protect from water and
direct sunlight.
295
Job Conditions (Cautions and Warnings)
Do not use bitumen base cement.
Do not install waterproofing membrane directly onto low melting point asphalt
(ASTMD312, Type 1 & 2).
Qualification
The water proofing systems including protection and all associated
accessories and works shall be executed by a specialist firm(s) having at least
7 years experience in installation of materials described herewith in the
Tanzania. The specialist(s) shall provide evidence of successful completion of
similar works for the approval of the Engineer before commencing any work.
The manufacturer's qualified representative shall visit the job site immediately
prior to commencement of works and as and when required and directed by
the Engineer to satisfy the Engineer and to instruct the specialist(s) in the
correct methods of execution of the Works.
296
Application Areas
Below and Around Foundations
Two coats of Bituminous Waterproofing coating.
Materials - The rubber bitumen emulsion shall be a water bound emulsion with
a minimum 60% total solids content by volume, comprising bitumen with fine
particles of rubber. Not less than 10% nor more than 20% of the total solids
shall be rubber. The consistency shall be such that it can be applied to the
surface by brush at normal temperature.
Backfilling shall not be commenced until the second coat of emulsion is quite
dry.
297
on suitable substrates under new structural concrete slabs and are generally
post-applied externally on new walls.
5.3.1 Slurry,
1) component, rigid and cement based active crystalline waterproofing slurry
for internal and external applications on concrete.
298
Range of hydrophilic profiles and gun applied sealants, designed for the
sealing and waterproofing of construction joints and penetrations (e.g. pipe
entries).
299
6.0 WALLING
6.1 Water
Water shall be as previously specified in 'concrete work.'
6.2 Cement
Cement shall be as previously specified in 'concrete work'.
6.5 Lime
Hydrate limes for cement/lime mortars shall comply with B.S.890 semi-
hydraulic class 'B' calcium limes
The concrete is to be placed into the moulds in thin layers and shall be
properly tamped or vibrated to secure complete consolidation without voids or
flaws produce smooth surfaces and sharp straight corners.
Blocks shall be cast on loose pellets and after removal from the moulds shall
be carefully stored under for at least 24 hours before the pellets are removed.
The blocks shall thereafter be stored under cover for a further seven days
protected from the sun and drying of the blocks may commence on the ninth
day after manufacture and no blocks may be used within 14 days of their
production.
300
The compressive strength of the type 'A' concrete blocks shall be not less
than:-
Average of 13 blocks 50 kg. per square centimetre (700 lbs. per square inch)
Lowest individual blocks 40kg. per square centimetre (580 IBS per square
inch)
6.9 Stone
Stone for walling shall be hard, dense, and stone from an approved quarry
with accurately dressed faces on all sides.
301
6.13 Chasing
Chasing of load-bearing walls for electrical conduits, pipes, etc, is kept to a
minimum size of cut and positions and runs of chases are to be approved by
the Engineer before any cutting is commenced. Horizontal runs will not be
permitted.
6.14 Mortar
The mortar used for walling shall be composed of one part of cement to two
parts of hydrated lime to nine parts of sand (1:2:9) measured in gauge boxes
and thoroughly mixed dry and preferably with an approved mixing platform
with water added afterwards until all parts are completely incorporated and
brought to a proper consistency and used within the hour. No partially or
wholly set mortar will be allowed to be re-used or re-mixed.
6.15 Workmanship
All blocks and stone to be wetted before laying out the top of walling where left
off, shall be well wetted before recommencing building, walls to be kept wet
three days after building.
All walling to be built true, plumb and level with all perpends vertical and in line
and work shall not rise more than 900mm above the adjoining work and all
such risings are to be properly raked back.
302
All perpends, reveals, quoins and other angles and joints of the walls, etc,
shall be built strictly true and square.
All exposed faces of walls for plastering ate to be left rough and the joints
raked out while the mortar is green to form adequate key.
All other faces shall be cleaned down on completion with wire brush or as
necessary and mortar droppings, smear marks, etc, removed and rates must
include for this.
303
7.0 FIBERCEMENT REINFORCED PANEL
General
Section Includes
** NOTE TO SPECIFIER ** Delete items below not required for project.
Fibre reinforced cement panel siding system
Accessories required for complete installation.
Related Sections
** NOTE TO SPECIFIER ** Delete any sections below not relevant to this
project; add others as required.
Section 05 4000 – Cold Formed Metal Framing
Section 06 10 00 - Rough Carpentry.
Section 06 11 00 - Wood Framing.
Section 06 16 36 - Wood Panel Product Sheathing.
Section 07 21 26 - Blown Insulation.
Section 07 90 00 - Joint Protection.
Section 08 31 13 - Access Doors and Frames.
Section 09 20 00 - Plaster and Gypsum Board.
References
** NOTE TO SPECIFIER ** Delete references from the list below that are not
actually required by the text of the edited section.
ASCE 7 -Minimum Design Loads for Buildings and Other Structures
ASTM C 1186 - Standard Specification for Flat Non-Asbestos Fiber-Cement
Sheets.
ASTM E 84 - Standard Test Method for Surface Burning Characteristics of
Materials.
ASTM E 330 - Standard Test Method for Structural Performance of Exterior
Windows, Doors, Skylights and Curtain Walls by Uniform Static Air Pressure.
System Description
Performance Requirements:
Design and size components to withstand live loads caused by pressure of
wind acting normal to plane of wall as calculated in accordance with
ANSI/ASCE 7, and as measured in accordance with ANSI/ASTM E 330.
304
Deflection:
Provide system capable of withstanding wind loading within the following
limitations:
Submittals
Submit under provisions of Section 01 30 00 - Administrative Requirements.
Product Data
Manufacturer's data sheets on each product to be used, including:
Shop Drawings
Provide shop drawings and erection plans for review including the following:
305
Calculations
Provide wind load calculations, engineering calculations and substantiating
data to validate wind resistance of roof system.
Product certificates including Research//Evaluation report or Code Authority
approval of the system use for intended application.
** NOTE TO SPECIFIER ** Include the following paragraph(s) for product
specified requiring color selection. Delete selection samples if colors have
already been selected.
Selection Samples:
For each finish product specified, two complete sets of color chips
representing manufacturer's full range of available colors and patterns.
Verification samples
For each finish product specified, two samples, minimum size 3 inches by 6
inches (76 mm by 150 mm) square, representing actual product, color, and
patterns.
Manufacturer's Certificates:
Certify materials and accessory component products meet or exceed specified
requirements.
Manufacturer's warranties:
Executed by manufacturer and installer.
Quality Assurance
Installer Qualifications:
Provide installer with not less than three years of experience with products
similar to those specified.
Mock-Up:
** NOTE TO SPECIFIER ** Include a mock-up if the project size and/or quality
warrant taking such a precaution. The following is one example of how a
mock-up on a large project might be specified. When deciding on the extent of
the mock-up, consider all the major different types of work on the project.
Provide a mock-up of complete panel system including furring, insulation,
weather barrier and panels for approval by Engineer.
Finish areas designated by Engineer.
306
Mock-up shall be a minimum of 4 panels showing one vertical and one
horizontal joint and complete installation system and fastener layout.
Do not proceed with remaining work until workmanship and color are approved
by Engineer.
Refinish mock-up area as required to produce acceptable work.
Pre-Installation Conference:
Prior to any panel application, the Contractor shall convene a pre-installation
conference.
Coordinate conference scheduling with the Engineer. Conference shall be
attended by the Contractor, Engineer, personnel directly responsible for the
installation of panels, flashing and sheet metal work and other trades
interfacing with the panel work.
Provide a copy of meeting notes and action items to all attending parties. Note
action items requiring resolution prior to start of roof work.
Store materials off the ground, flat and under cover in a dry place until
erection.
Project Conditions
Maintain environmental conditions (temperature, humidity, and ventilation)
within limits recommended by manufacturer for optimum results. Do not install
products under environmental conditions outside manufacturer's absolute
limits.
307
Warranty
Installed material shall have a manufacturer's 5 year warranty.
Warranty includes the repair or replacement of siding that does not comply
with requirements or that fails within specified warranty period. Failures
include, but are not limited to, cracking, deforming or otherwise deteriorating
beyond normal weathering.
Products
Materials
Prefinished Cement Board Siding Panels: siding sheets, fiber reinforced,
cement based product conforming to ASTM C 1186 and manufactured of
cement sand, cellulose fibers and fillers.
** NOTE TO SPECIFIER ** SIL-BONIT™ siding panels are intended for use
for new construction, building facade refurbishment or insulation projects with
light facades. SIL-BONIT™ cement panels meet the highest requirements of
quality, function, weather resistance and aesthetics.
Panel Size:
5/16 inch 4 feet by 8 feet. (8 mm by 1220 mm by 2440 mm).
5/16 inch 4 feet by 10 feet. (8 mm by 1220 mm by 3050 mm).
Colors:
Natural colors:
Ash - Natural.
Desert - Natural.
Almond - Natural.
Stone - Natural.
Olive - Natural.
Coral - Natural.
Gold - Natural.
Iceberg – Natural
Bark - Natural
Chestnut - Natural
Mechanical fasteners:
External tamper proof screws, stainless steel, torx head fasteners.
Screws shall be length as required by the panel manufacturer for the furring
material used.
Wood screws: Size: #10 by 1-1/2 inch (38 mm).
308
Steel Screws: Size: #10 by 10 inch (25.4 mm).
** NOTE TO SPECIFIER ** Painted screws are optional delete if not required.
Use painted screws to match panel finish
Continuous cushions of black EPDM rubber, 1-1/4 inch (32 mm) and 3-1/2
inch (95 mm) as required.
** NOTE TO SPECIFIER ** Select the color(s) required from the following
Natural Colors or Treated Colors paragraphs as required and delete the ones
not required. If more than one color is required indicated the location of each
on the Drawings.
** NOTE TO SPECIFIER ** Select the fastener type required from the
following paragraphs and delete those not required.
Accessories
Trim: PVC, composite and stainless steel trim shapes suitable for trim
conditions.
Sheet Metal Flashing: Minimum 26 gauge hot-dipped galvanized steel sheet,
or stainless steel.
Execution
Examination
Do not begin installation until substrates have been properly prepared.
Ensure that framing is completed and that electrical rough-in, windows, doors,
and flashing are in place before proceeding with work of this section.
309
Prepare surfaces using the methods recommended by the manufacturer for
achieving the best result for the substrate under the project conditions.
Ensure that all dust, dirt, fingerprints and all other foreign marks on the
material are removed prior to installation of the panels.
Installation - General
Install in accordance with manufacturer's instructions and the approved shop
drawings.
Panel Cutting:
Cut panels using a high-speed circular saw with a segmented diamond blade.
Cut panels from the front side and protect the face from being damaged during
cutting.
For incidental cuts, cut panels from the front side using a jigsaw with carbide
tip blade.
Provide adequate ventilation during cutting. Use of a dust extractor is
recommended.
Reseal fabricated edges per manufacturer's instructions.
Drilling:
Drilling of holes must be done from the front of the panel using a carbide tip
drill bit.
Holes are recommended to be done using a universal drill.
Larger holes, or cut-outs on the panel, can be made by a jig saw with a
carbide blade or a hole saw with a diamond blade.
Prepare structural backing with studs, backer board, weather barrier and
furring as required to meet the performance requirements specified. Install
fiber reinforced panels over a properly prepared support system in accordance
with the manufacturer's installation instructions and approved shop drawings.
Install weather barrier over prepared substrate.
310
Panels shall be attached to furring using the attachment pattern and fasteners
indicated in the manufacturer's installation instructions and approved shop
drawings.
Fasten fiber cement board to furring as per vendor's details with approved
stainless steel fasteners.
Protection
Protect installed products until completion of project.
Inspect walls for any damage. Replace panels that are damaged. Do not
attempt to repair.
Ensure all dirt, dust, fingerprints and all foreign marks are immediately
removed from the face of the material to avoid from permanent damage.
311
8.0 ROOFING
8.1 Vermiculite lightweight screed
Vermiculite lightweight screed shall be mixed in the proportions of 6 parts by
volume of vermiculite Grade 5 to 1 part of Ordinary Portland Cement with
approximately 2 parts of clean potable water to give a density of 700 kg per
m3.
8.3.2 Materials
Bitumen felt roofing (or Build up roofing) shall be Bitumat Polyframe
waterproofing to ISO 9002 or Sarnafil Waterproofing Systems or any other
equal and approved system.
Prepare screed surfaces, clean properly and apply one coat of bituminous
concrete primer. Then lay 4mm thick black sand finished polyframe under-
layer, touch bonded to screed base and finished with one layer 4mm thick
coloured (slate granules) polyframe touch bonded to under-layer.
Abutment felt finishing shall be properly wedge in groove and pointed with
mastic felt.
312
8.3.4 Fixing of Sarnafil Waterproofing Systems
Sarnafil Waterproofing Systems shall composed of first layer Sarnafil
A300g/m2 levelling layer; second layer Sarnafil S327-12EL and Sarnafil G410-
12EL as main field sheet and for detail work respectively; all laid by a
Specialist as specified in accordance with the manufacturer’s printed
specifications.
8.3.5 Guarantee
The Contractors will be required submit detailed specification and fixing
method including guarantee of his proposed product to be used for the works
for Engineer’s approval.
8.4.2 Fixing
The sheets shall be fixed to steel angle or timber purlins with aluminium alloy
bolts and nuts. The bolts shall be at least 50mm longer in the shank than the
purlin to which they are fixed. All bolts shall have approved washers.
Fixing of the sheet must conform strictly to the printed instructions or otherwise
to the requirements of CP 143 part 1 BS 2855.
8.5.2 Fixing
The sheets shall be fixed to steel Z-purlins or timber purlins with roofing nails,
bolts and nuts or any other accessory to be approved by the Engineer.
Fixing of the sheet must conform strictly to the printed instructions.
313
9.0 JOINERY
9.1 General
The provisions contained in the carpentry section shall apply also in the joinery
section where applicable.
9.3 Workmanship
All timber shall be wrot by machine dressing on exposed faces, with all
machine marks sanded out, unless otherwise specified.
The dimensions and thickness given in these Bills of Quantities are finished
(unless otherwise stated). In the event of nominal sizes being stated, an
allowance of 3mm should be allowed for each wrought face.
The joinery shall be worked strictly in accordance with the details drawings
and is to be framed up and put together as soon as possible, and is to be
stored for as long as possible before being wedged up . All joints and angles
are to be glued and where necessary cross-tongued with hardwood tongues,
and surfaces finished clean and smooth with machine marks sand papered out
before fixing.
Should any of the joinery work shrink, wind or fly unduly before the end of the
maintenance period of the contract, the work is to be taken down, and new
work fixed in its place, together with any other works, which may thereby be
affected at the Contractor's sole expense.
In pricing the items, the contractor will allow for nails and screws and fixing, all
labours, cuttings, notching, havling, mortising, tenoning and welding except
where otherwise provided. Rates are also to include for one coat approved
priming paint on all concealed surfaces.
314
Allow in the rates for easing and adjusting all doors, and leave in perfect
working order.
9.5 Plywood
Plywood shall be manufactured from tropical hardwoods of the first grade with
BS 145, and unless otherwise stated shall be 'interior' quality. Where stated to
be of ' exterior' quality, the plywood shall be W.B.P. bonded weatherproof
grade. Where veneered plywood is specified, samples must be submitted to
the Engineer for his prior approval.
9.6 Blockboard
Blockboard shall be of Tanzania manufacture and comply with BS. 3444 and
shall be of moisture resistant quality.
9.7. Chipboard
Chipboard shall comply with BS 2604 resin-bonded wood chipboard.
9.8 Plugging
All work described as plugged shall be fixed with brass screws to plugs formed
by drilling concrete, wall, etc. with a screw of suitable "philplug", "Rawplastic",
or other approved plugging compound in accordance with the manufacturer's
instructions.
315
9.9 Protection
Any fixed joinery which, in the opinion of the Engineer is liable to become
damaged in any way shall be cased and protected by the Contractor until the
completion of the works and the contractor must allow for this in his rates as
no separate item for protection has been measured.
9.10 Ironmongery
All ironmongery will be fixed with matching screws to be supplied by the
contractor and the contractor must allow for adjusting locks and striking plates
and handling over all keys on completion of the contract with identifying tags
attached.
The contractor must also allow for oiling locks and hinges and leaving them in
perfect working order
316
10.0 STRUCTURAL STEEL WORKS
10.1 Generally
All steel to be grade 43 conforming to BS 5950-2-2000.
Structural use of steel work in buildings BS 5950-1-2000 Part 1, Code of
practise for design of rolled and welded sections form part of these
specifications.
10.3 Submittals
The Contractor must submit the following for approval.
Shop drawings
Certificates of structural steel
Welding materials
Shop coat primer paint
Welders qualifying tests
Final paint sample and specification
10.4 Bolts
Bolts are to be galvanised bolts grade 10.8 unless approved otherwise. Bolts
must conform to BS 4190.
10.5 Welding
Welding shall be done in accordance with BS 5950 clause 6.7.
10.6 Painting
10.6.1 Shop painting
All steel shall be shop painted with epoxy primer or any other approved primer.
Surfaces within 50mm of joints to be welded in the field should not be painted.
Surfaces that will be encased in concrete must not be painted.
Finish painting of steel surfaces with epoxy polyester based paint in two coats
to satisfaction of the Engineer.
317
11.0 METALWORK
11.1 Mild steel
Mild steel shall comply with BS 15 Grade 1, and the sizes of all small section
shall be in accordance with BS 4 and 4A.
11.3 Aluminium
Aluminium shall be of the alloys described in and shall comply with BS 1470.
Aluminium sheet for flashings shall be soft tamper, super purity S1 or S1A)
and not less than 18 SWG (1.2mm) in thickness.
11.5 Bolts
Mild steel bolts, nuts and washers shall comply with B.S.916 for black bolts
with hexagonal heads and nuts, High Tensile Steel Bolts and nuts shall be in
accordance with B.S.3139.
318
Sheet size: 720x2000 mm, 1200x2000 mm, 900x2000 mm
Thickness: will be decided after material calculations by manufacturer..
Operation: The door is arranged for an electric motor unit with manual hand
hoisting and lowering facility. The motor unit is complete with an in-built safety
drive system. Operating voltage 400V 3 phase IP54 protection 60% duty cycle
maintenance free and TUV tested, complying with all current European safety
standards. Opening speed approx. 220mm per second.
Colour: Hot dip galvanised steel* Optional polyester powder coating, RAL9010
PURE WHITE, RAL9006 WHITE ALUMINIUM, RAL3000 SUNSET RED,
BS10E55 AZTEC YELLOW, RAL6002 LEAF GREEN, RAL5010 GENTIAN
BLUE, BS08B29 VAN DYKE BROWN or RAL9005 BLACK. Other colours and
finishes available by request.
Barrel: Manufactured from seamless mild steel tube to BS4760 Grade 50C.
Size to suit door width and height. Maximum barrel deflection 1:400. Fitted
with precision-machined BDMS axles to BS970 EN33.
Main Support Brackets: The main support brackets for the barrel and motor
unit are manufactured from mild steel plates of varying thickness and
incorporate the necessary fixing positions for securing back to the opening
structure.
319
is designed to allow reduced working faces and tapered inner faces to provide
automatic interlocking/retaining feature for performance
Bottom Seal: The bottom panel of the shutter curtain is terminated with a
specially designed aluminium extruded section complete with interlocking
(EPDM) rubber weather seal.
End Locks: The curtain, when assembled is held in position with purposely-
designed injection moulded end fittings, manufactured from hardwearing
nylon-6, which sits on the outside of the panels minimising scuffing and
damage.
Vision Panels: each vision panel is 200mm wide number of vision panels per
row will vary according to door width, max number of rows of vision panels is
ten.
Certification:
CE Mark (Declaration of conformity)
Type Approval (Chiltern Dynamics - UKAS approved test laboratory)
Mechanical Aspects EN12604, Safety in use of power operated doors
Side guide protection EN 12604: 2000 4.5.1 and EN 12453: 2000 5.1.1.3
Protection Against crushing, shearing or drawing in
Electrical Safety Depending on the use
Water Tightness EN 12489 Resistance to Wind Load EN 12444
Thermal resistance EN 12428
Air permeability EN 12427
Closing Forces (Auto close only) EN 12453 - 5.1.1.5
Anti fall back device EN 12453 - 5.1.1.5
Durability of Mechanical Performance EN 12635: 2002 4.1.1.1
320
11.12 Structural hollow sections
All hollow sections are to be connected by electric welding. For butt welds the
fusion surfaces of each member must be aligned and prepared.
11.15 Marking
All components delivered to the site are to be marked in paint with the Mark
number in accordance with any shop and erection drawings.
11.16 Storage
All components are to be stored at site in proper racks provided for the
purpose, which provide full support to each member, and to avoid any
deflection and distortion. Steelwork is to be stored at least 250mm clear of the
ground and temporary protection is to be provided for protection against water
and damage from any other source.
11.17 Erection
Rates for all metalwork are to include for the complete erection including any
temporary supports required and any necessary templates and wedges.
321
12.0 PLUMBING AND ENGINEERING INSTALLATION
12.1 Execution of Works
The works shall be carried out strictly in accordance with: -
The plumbing work shall be carried out by a specialist and if the contractor is
not a firm approved by the Engineer for the type and/or value of plumbing
installations contained in this contract, he must sublet this work to a specialist
Sub-Contractor who is so approved
The Contractor shall obtain all the necessary permits from the Local
Authorities for making connection to the existing municipal services including
permits for final disposal of effluents from the Building.
322
The Contractor shall undertake all modifications demand by the Authorities in
order to comply with current regulations, and produce all certificates, if any,
from the Authorities without extra charge.
The works include, unless otherwise specified, supply, installation, testing and
commissioning and delivering up clean and in working order the installations
shown on the drawings and specified in the specifications including all details
such as;
Cold water pipes, Foul water soil pipes, ventilating pipes, valves, storage
Tanks, sanitary appliances including all necessary taps and discharge fittings,
Fire fighting installations and equipment, thermal insulation etc. and all labour,
materials, tools instruments and scaffolding necessary to execute the work in a
first class manner, even such labour or materials which are not specially
mentioned in the project but are necessary for a satisfactory completion of
work.
The Contractor shall be responsible for ensuring that runs for floor or wall
chases, holes to cut or left will be marked out at the appropriate stage of the
structural work.
The Contractor shall be responsible for verifying all dimensions relative to his
work by actual measurement taken on site.
323
After the completion of the work the contractor shall, on set of drawings,
indicate all alterations and/or modifications carried out during the constructions
period.
Competent workmen under unskilled supervision shall carry out the work. The
Engineer shall have the Authority to have any of the work undertaken down or
changed, which is executed in unsatisfactory manner.
324
All tubing specified as chased into walls shall have the wall face neatly cut and
chased, the tubing wedged and fixed and plastered over.
All tubing specified as fixed to ceilings, roofs or roof structures shall be fixed
with approved mild steel hangers cut and pinned to ceilings, roofs or roof
structures.
Tubes shall be fixed to true lines parallel to adjacent lines of the building
unless otherwise specified.
Pipes runs shall be secured by pipe clips connected to pipe hangers, wall
brackets, or trapeze type supports. ”U” bolts shall not be used as substitute
for pipe clips without the prior approval of the Engineer.
Each support shall take its due proportion of the weight of the tube or pipe and
shall allow free movement for expansion and contraction.
All formed bends shall be made so as to retain the full diameter of the pipe.
Tubing shall be cut by hacksaw or other method, which does not reduce the
diameter of the tube or form a bead or feather, which might restrict the flow.
Where tubing is laid in trenches care should be taken to ensure that fittings are
not strained.
325
The Support spacing for vertical runs shall not exceed one and a half time the
distances given for horizontal runs.
All water systems shall be provided with sufficient drain points and automatic
air vents to enable them to function correctly.
Valves and other user equipment shall be installed with adequate access for
operation and maintenance.
Full allowance shall be made for expansion and contraction of pipe work,
precautions being taken to ensure that any forces produced by pipe
movements are not transmitted to valves, equipment or plant.
Sleeves shall be provided where pipes pass through walls and solid floors to
allow movements of the pipes without damage to the structure. The overall
length of the sleeve shall be such that it projects at least 2 mm beyond the
finished thickness of the wall or partition.
Elsewhere they shall be of P.V.C. The sleeves shall have 5-15 mm clearance
all round the pipe, or for insulated pipe work, all round the insulation. The
sleeves shall then be packed with slag wool or similar.
The Contractor shall provide all necessary rodding and inspection facilities
within the draining system in positions with easy access.
Access for rodding and testing shall be provided at the foot of each stack.
326
Pipes for Cold Water Services
Fitting for the same shall be galvanized malleable iron to B.S. 1356:1952
Table 6A or 7A with threads to B.S. 21:1951. All changes of direction shall be
obtained by use of proper fittings. Formed bends will not be accepted.
Joints shall be made with fine hemp and approved jointing compound or tape.
Compound containing red lead must not be used.
Long screw connectors and flat –faced unions shall not be used; unless
otherwise specified.
Where laid underground; galvanised mild steel tubing shall be protected with
two coats ‘Flinkote’ or two coats of approved bitumen. Minimum earth cover to
underground tubing shall be 600mm.
Malleable iron pipe rings, with either pack plate, plugs or gilder clips, or
Wrought fittings and tubular fittings shall be to B.S. 1740 and B.S. 1387:1967
respectively.
327
Oxy-acetylene welding carried out in accordance with the welding and testing
procedure detailed in B.S. 2633.
Manual arc-welding carried out in accordance with the welding and testing
procedure detailed in B.S. 2633
328
12.5.1 PVC, HDPE and PE Pipes
PVC pipes and fittings for cold water supply shall comply with BS. 3505.
Joints for small diameter PVC pipes for cold water supply shall be done by
using special jointing solvent provided by the pipe maker. Joints shall be of
use spigot and socket tyre, having the socket formed integral with the pipe or,
alternatively, separate sleeves shall be used.
Joints for sizes of 76 mm bore and upwards shall be of the spigot and socket
type made with jointing solvent or flanged joints.
Joints of small diameter PVC pipes for water supply to metal tubing shall be by
means of union adaptors.
Polyethylene (PE) pipes and fittings for cold water supply shall be to BS 6730
(only for above ground use).
High-density polyethylene (HDPE) pipe and fittings for cold water supply shall
be to B.S. 6572 with joints in brass o-ring connectors (only for below ground
use).
Bib Taps shall comply with B.S. 1010 and shall be of brass with crutch handles
or loose key where so described shall be chromium plated or shall have nozzle
screwed for hose union and locking arm.
329
Brass ball valves comply with BS 1212.1953 Floats not exceeding 150mm
diameter made of plastic type, which comply, with BS 1968 class C.
Copper alloy gate valves shall comply with BS.1952:1964
Copper alloy float valves shall comply with BS.1953:964
Sluice valves shall comply with BS.1218:1946
Bib taps comply with BS 1010:1959 and made of brass with clutch handles or
loose key where so described chromium plated or nozzle screwed for hose
union and locking arm.
Stop valves comply with BS 1010:1959 and made of brass with crutch handles
or loose key where so described. Those in exposed positions shall have
polished brass bodies.
Gate and check valves comply with BS 5154 and made of copper alloy.
Manually operated mixing valves for ablutionary and domestic purposes shall
comply with BS.1415:1955
Draining taps shall comply with BS 2879:1957.
Water hammer shall be controlled by providing pipes three times larger than
the branch line pipe and 500 mm long.These air chambers have been
provided with a shut-off sluice valve and a drain and vent cork to renew the air
periodically.
All valves and cocks shall have the same flow areas, as the corresponding
pipes and shall be accessible for operation and maintenance and suitably
labelled by an approved method. Stop valves have been and are being fixed in
positions shown on the drawings to form branch services for group control, or
where else specified.
All valves, cocks and taps shall have the correct pressure rating according to
the recommendations of the relevant British Standards or the local authority.
At commencement of the contract, the Contractor shall, if necessary, ask the
Engineer for guidance on this point.
330
Thermal insulating material for hot and cold water supply installation shall
conform to BS 5422:1977, unless otherwise specified. Maximum permissible
length of insulated hot water pipes shall be observed. Where lengths exceed
the maximum permissible length, the whole hot water pipe shall be insulated.
Where anti-siphoned traps are specified, these shall be similar or equal to the
range of traps manufactured by Greenwood and Hughes Ltd of England.
For all sanitary appliances, the necessary number of supports, brackets, plugs,
screws, and washers, jointing materials etc. shall be provided.
Where supports, brackets etc. are screwed to wall or structure raw plugs or
similar shall be used.
No trap for any appliance whatsoever shall be with less seal than 70 mm
Upon complexion of work, all appliances shall be cleaned for plaster, paint etc.
and carefully examined for defects.
331
12.10 Floor Gully
Floor gullies shall be PVC with a 150 x 150 mm stainless steel grating as
manufactured by Key Terrain or similar to be approved with built in water trap
with 50mm water seal with bottom outlet. The gullies shall also have side inlet
(s) of diameter of waste pipe from sanitary fixture connecting into drain.
Before handing over, the Contractor shall confirm that the installation has been
examined tested and that it will operate and can be maintained efficiently.
The whole of the water and discharge installations shall be tested to the
satisfaction of the Engineer and the Local Authority. The Contractor shall
provide all necessary testing apparatus and facilitates for testing the
installations and any defective work shall be replaced immediately and shall be
the subject of re-testing until found satisfactory.
All water pipe works shall be hydrostatically tested to 1.5 times working
pressure or 10 bar whichever is greater and this test maintained for 8 hours
.The test pressure shall not drop over the 8 hours period.
All water piping shall be flushed and cleaned thoroughly after hydrostatic
testing. All tanks and piping for drinking water after being hydrostatically tested
shall be sterilized with a solution of chloride or lime to the agreement and
satisfaction of the Engineer.
332
13.0 FLOOR, WALL AND CEILING FINISHINGS
13.1 Sand
Sand for backings, floor and wall finishes is to comply with B.S.1199, Table 1.
13.2 Aggregate
Coarse aggregate is to be as described for ‘concrete work’.
13.3 Cement
Cement is to be as described for ‘Concrete Work’.
13.4 Lime
Lime is to be non-hydraulic hydrated lime to B.S.890 Class ‘A’ obtained from
an approved source and run into putty at least 24 hours before use.
13.5 Workmanship
All concrete beds or slabs shall be thoroughly brushed if necessary and well
wetted and flushed over with a cement and sand (1:1) grout immediately
before screeds or pavings are laid
Screeds and cement pavings shall be laid in accordance with the relevant BS
Code of practice. Working joints between bays of the floor finish should be
placed in accordance with the Engineer’s instructions and will be plain butt
joints placed over joints in the concrete bed under. Pavings shall be damp
cured with sand or sawdust and kept damp for at least 7 days after laying.
333
to include for this. They are also to include for all necessary curing and
protecting until the building is handed over to the Employer.
334
The contractor shall cut out and make good all cracks, blisters and other
defects and leave the whole of the plastering and rendering perfect at
completion. When making good defects the plaster shall be cut out to a
rectangular shape with edges undercut to form dovetailed key, and all finished
flush with the face of surrounding plaster.
335
13.8.2 Styles
Tactile Warning Tile (Attention Tile) Rubber Tiles (TW1): 4.0 mm dome height
with 3.2 mm base thickness; 7.2 mm overall thickness.
Tile Size: (20 cm x 20 cm or 40 cm *40 cm)
13.8.4 Installation
See rubber tile flooring installation instructions for complete details.
Adhesives:
Tarkett 965 Adhesive Coverage: Porous Substrate: 125-150 sq. ft. per gallon
Non-porous Substrate: 150-175 sq. ft. per gallon
Tarkett 996 Two-Part Epoxy Adhesive Coverage: Porous & Non-porous
Substrate: 150-175 sq. ft. per gallon
Tarkett 975 Two-Part Polyurethane Adhesive Coverage: Porous & Non-porous
Substrate: 150-175 sq. ft. per gallon
Warranty:
Limited 5 year warranty. For complete details, contact Tarkett or an authorized
Tarkett distributor.
336
14.0 GLAZING
14.1 General
Glass generally shall comply with the requirements of B.S.952 and shall be
free from bubbles, specks waves, flows or any other defects.
The thickness and type of the glass shall be as specified by the Engineer.
Glass for louvre blades shall be clear sheet flat drawn or roughcast obscured
rolled glass to the thickness shown on the drawings with all exposed edges
ground and polished.
14.2 Putty
The putty shall be hard setting tropical putty to B.S.544
14.3 Workmanship
All glass is to be accurately cut to fit easily into rebates with a tolerance of
2mm all round. It is to be well puttied at the back and to the sprigged with non-
ferrous pins. The putty is to be mostly trimmed and cleaned off and care must
be taken that it does not show beyond the slight lines of the saches. All
rebates must be treated with one coat of lacquer (as described under 'Painting'
hereafter) prior to glazing.
337
15.0 PAINTING
15.1 Colour range
All painting shall be carried out in colours selected by the Engineer.
15.2 Materials
Paints generally shall be ready mixed and supplied by one of the
manufacturers listed below and delivered to the site in sealed containers
clearly labelled with the a manufacturer's name, type of paint and colour. Oil
based priming paint shall comply with B.S.2521-2524 inclusive.
Jotum Paints
Coral Paints
Galaxy Paints
Leyland Paints (T) Ltd
Robbialac Paints (T) Ltd
Sadolins Paints (T) Ltd
Goldstar Paints Tanzania Ltd
15.3 Preparation
All surfaces to receive treatment are to be clean and dry before paint
application and surface irregularities are to be removed by filling or the use of
suitable abrasives.
Apply one primer coat thinned with water and two subsequent coats of
Leyland's Leymure Co-polymer' or other approved plastic emulsion paint in
accordance with the manufacturer's instructions. Where specified internal
plastered wall surfaces are to be painted gloss. In addition to the preparation
338
described above, apply one coat of Leyland’s P 20 or other approved alkali,
resistant primer and flat down with 320 grade 'wet or dry' abrasive paper.
Apply two coats Leyland's Leylac Polymeric gloss finish or other equal and
approved gloss paint lightly rubbed down coats in accordance with the
manufacturer's instructions.
After priming all nail holes and other imperfections shall be filled with stopping
and the whole surface rubbed down to a smooth even finish. The stopping
must be 'Scadofil' or other approved make.
15.6 Metalwork
All rust and loose scale on steel and ironwork must be removed by wire
brushing and rubbing with emery paper. Where patches of ingrained rust
cannot be removed they are to be thoroughly rubbed down and treated with
one coat of 'Galvafroid' or other zinc paint in accordance with manufacturer's
instructions. One coat of zinc chromate primer will then be applied followed by
two undercoats and one finishing coat of gloss paint as described for
woodwork above. The contractor is to note that where mild steel burglar bars
are housed into wood frames the full length of the bar is to be treated before
fixing.
339
16.0 DRAINAGE
16.1 Generally
The preambles for the previous trade sections are applicable to this section
together with the following preambles. The drainage is to be carried out in
accordance with the directions of the Engineer and the requirements of the
Byelaws. No length of drain is to be covered until it has been tested and
passed.
Pipes shall be jointed with asbestos yarn and caulked with molten lead or
jointed with special jointing compound all to approval.
For foul water drainage sulphate resisting concrete pipes shall always be
used. The manufacturer of sulphate resisting pipes shall be in general
conformity with BS. 556. The concrete mix not weaker than grade '30'. Pipes
up to and including 45cm diameter shall be un-reinforced and shall incorporate
spigot and socket type joints. Pipes above 45cm diameter shall be reinforced
with not less than steel fabric required by British Standard BS 5610 or the
equivalent in mild steel and shall have spigot and socket joints or if the
Engineer so approved shall have open type joints. The main reinforcement to
be in circumferential direction. Pipes reinforcement shall be placed midway
between the inner and outer surfaces of the concrete. In socketed pipes the
340
reinforcement shall be extended continuously from the pipe barrel into the
socket, the longitudinal bars cranked as necessary.
No wall thickness of the pipe barrels is specified but the reinforcement (if any)
and the wall thickness must be so balanced that the pipes are in conformity
with B.S.556 and the test specified therein.
16.6 Manholes
Manholes shall be constructed on drain lines in the positions indicated or
wherever ordered by the Engineer.
Benching shall be carried out in concrete grade "20" and rendered with 15mm
1:3 cement mortar. Rendering to be carried out in sulphate resisting cement
for foul water drainage .The ends of all entering the manholes are to be
carefully cut to shape to suit the internal dimensions of the manholes and are
to be as short as possible and are to be surrounded with 150mm concrete up
to the first pipe joint.
The manhole shall be constructed in accordance with the drawings for typical
and special manholes.
Manholes cast iron steps for manholes shall comply with BS. 1247. All steps
be hot dip galvanised after manufacture.
341
16.7 Concrete beds etc
Concrete beds shall be grade "15" laid to correct falls, 300mm wider than the
external diameter of the pipe. Rates are to include for laying in two parts, the
first part being laid on the trench bottom 75mm thick and allowed to set before
pipe laying is commenced. Individual pipes shall be firmly supported on
precast concrete blocks placed immediately behind the socket and in such a
manner that each pipe is accurately position in both line and level and the
underside of the barrel is at least 75mm above the top of the concrete.
After the joints have been made and the pipelines satisfactorily tested, the first
layer of the concrete bed shall be thoroughly washed down and cleaned and
the remainder of the bedding concrete (and the launching or surrounding
concrete where required) shall be placed and consolidated under and around
the pipe in such manner as not to cause any damage or disturbance to the
pipe or joints.
The contractor is to ensure that his, method of placing this second layer of
concrete is such that the full length of each pipe is fully supported. The overall
depth of beds is to be in accordance with the table given on the drawings.
Where pipes are specified to be haunched, the bed shall be brought up with
the second layer of concrete to a minimum overall depth of 150mm to the
underside of the barrel of the pipes plus half the diameter of the pipe and then
sloped up to the top of the barrel of the drain pipes. Where pipes are specified
to be surrounded, the bed shall be brought up with the second layer of
concrete to a minimum overall depth of 150mm to the underside of the barrel
of the pipe and then completely surrounded with concrete with 150mm
minimum cover all round. Rates for this item are to include for any formwork
required.
342
Back filling shall be executed with selected material in 150mm layers (300mm
layers if a mechanical rammer is used) each layer being well rammed and
watered to obtain the maximum compaction. Care should be taken to ensure
that no stone or other work is placed within 300mm of such work.
Rates for manhole excavation shall include for levelling the bottoms. All
surface material including topsoil, which differs in any nature whatsoever from
the substrata, shall in every case be carefully set aside and stored separately
from other excavated materials. No claim for extras will be allowed for setting
aside topsoil for later use.
Each pipe shall be laid accurately to line and gradient so that the finished
pipeline shall be in a straight line both in horizontal and vertical planes. The
contractor shall fix properly painted and securely positioned sight rail, the
levels and positioning of which shall be checked by the Engineer's
representatives before the rails are used and as often thereafter as may be
necessary. There shall be at no time less than three sight rails in position on
each length of pipeline under construction to any one gradient and the sight
rails shall be situated vertically above the line of pipes or immediately adjacent
thereto.
343
Do not disturb the joint for five minutes whilst cement is hardening
The cement used shall be supplied by the factory, which is supplying the pipe.
Cement mortar joints for concrete pipes with spigot and socket joints shall be
made as follows:
Before commencing the jointing operation the socket of the previously placed
pipe and the spigot of the new pipe shall be cleaned and thoroughly soaked
with water.The spigot shall be wrapped one complete lap with tarred hemp
spun yarn and the new pipe shall be carefully drawn towards the previously
laid pipe so that the spigot enters the full depth into the socket of the
previously laid pipe. The new pipe shall then be adjusted and fixed in its
correct position in line, level and gradient and the yarn shall be caulked tightly
home into the socket. On completion of this operation the yarn shall not fill
more than one quarter of the total depth of the socket.
The remainder of the socket shall be completely filled with cement mortar
consisting of one part of cement (sulphate resisting cement for foul water
drainage) to three parts of sand. The mortar filling shall terminate flush with
the socket and shall be neatly trowelled to a smooth finish completely around
the pipe.
To assist the curing of the mortar the contractor shall cover the joints
immediately after they are made with a layer of hessian which shall be kept
continuously wet during daylight hours and he shall further adopt such other
measures as the Engineer may direct all at the Contractor's expense.
344
16.10 Position of floor gullies etc.
The contractor shall before positioning floor gullies duck-foot bends for
ventilating stacks, etc should consult the Engineer in order to ensure the
correct position of these. Failure to do so, shall in no way relieve the contractor
from positioning floor gullies, duck-foot bends for ventilating stacks etc in
positions, the Engineer later may direct.
16.11 Testing
After the drains are laid and jointed and before the trenches are filled in, they
are to be tested in the presence of the Engineer's representatives. The drains
shall be tested in lengths between manholes or such shorter lengths as the
representative or the Engineer may approve.
Water shall be passed into the length under test until such time as all the air
has been expelled and the line is full of water and subjected to a head of
1500mm at the upstream end. The test shall be considered to be satisfactory
if there is no visible leakage, see page or weeping from any of the pipes of
joints and if the head of water in a 76mm diameter upstand tube fitted at the
upstream does not fall at a rate faster than 12mm per minute per 30 metres
length. The contractor shall make such time allowance as may be necessary
for the pipe to absorb water being subjected to test.
Manholes are to be tested for water- tightness in the same way as for drains
by filling with water but not exceeding 1500mm head.
The contractor is to supply all testing apparatus and materials necessary for
these tests and provide all labour and assistance required. Any failure
whatsoever in the drainage system to withstand the specified tests and any
defects appearing are to be made good and the drains re-tested to the
satisfaction of the Engineer.
345
17.0 ELECTRICAL INSTALLATION
17.1 GENERAL SPECIFICATION
17.1.1 Scope of work
The work includes, unless otherwise specified, supply, installation, testing and
commissioning and delivering up clean and in working order of the entire
electrical installation as shown on the drawings in compliance with the
specification, drawings and generally accepted utility standards required of
buildings. The work to be undertaken shall include, but not be limited to the
following:
346
17.1.1.2 Record drawings
During the execution of the Works on Site, the Contractor shall in a
manner approved by the Engineer record on working Drawings all
deviations or modification on the electrical work as actually installed
from work indicated on the drawings. All construction drawings on-site
shall be updated by the contractor on a regular basis to reflect current
as-built conditions and as commissioned drawings are submitted to the
Engineer for final approval.
Coordinated drawings
A co-ordinated set of construction drawings will be issued based on
tender drawings showing all the services and equipment described in
the specification. The contractor shall be responsible for developing
the final coordinated drawings for construction purposes. The
drawings shall show the precise routing of all the services, all fixing and
bracketing details for all plant, equipment and distribution systems and
the builders work.
347
The Engineer must grant structural approval for all plant and builders
work requirements but this approval shall not relieve the Contractor of
his responsibility for complying with the specification.
Setting out and Builders Work
The contractor shall execute all builders’ work in connection with the
Electrical installation.
In the event of any portion of the work or materials failing to pass the
test specified herein, or set forth in the manufacturer’s lists for that
particular item, The Engineer may, at his discretion, reject that portion
of the work or material entirely.
Working drawings
All controls and safety devices must be tested to ensure that they
function according to their design.
348
During commissioning, the contractor shall instruct the Employer’s
representative on how to operate and maintain the installations.
Materials
Where materials of particular manufacture are called for in the
specification, the Engineer shall have the Authority to reject any
materials that are not of the make specified. Where the word “or other
approved equivalent “ are used, it is understood that this means make
of equal quality but written approval of the Engineer for the use of any
such alternative shall be obtained prior to their use in the installation. In
the absence of any such request the Engineer is entitled to suppose
that the material as specified will be used.
17.1.1.10 Workmanship
The whole work shall be carried out in a straightforward manner by
competent workmen, under skilled supervision as stipulated in
conditions of contract. The Engineer shall have authority to have portion
of the work taken down, removed or undone, which is executed in a
poor workmanship like manner or with improper materials. Where
required, the contractor shall submit to the Engineer samples of
materials that he proposes to install for tests and approval for
installation.
In the event of the portion of the work or materials failing to pass the
specified test, or approval of the Engineer, the Contractor will be
required at his own expense to put right such defects.
349
In addition, all facilities will be constructed and put into service
according to Tanzanian laws, regulations, codes and guidelines.
The codes and regulations shall include, but shall not be limited to, the
following:
350
and normal practices as stipulated by the Contractors Registration
Board.
The Contractor shall be solely responsible for the safety and protection
of persons and property on or near the place of Work.
Environmental Protection
17.1.2.1 General
The impact on the environment and on the surrounding community
during construction, commissioning and operation shall be minimized.
No more than one (1) month after the completion of the contract, the
contractor shall update all drawings to as-built and as-commissioned
status. These as-built drawings to be submitted to the Employer shall
include:
351
and as commissioned drawings are submitted to the Employer for
approval.
Spare Parts list - This list shall show the recommended items and
quantities for each of the system as a whole.
352
The International system of Units (SI) with imperial in brackets shall be
used on all drawings and design documents, except that imperial units
may be used if followed by SI equivalent in brackets.
17.1.4.4 Materials
All materials and equipment shall be new and unused commercially
available materials, and shall be suitable to perform satisfactorily under
the operating conditions described in this specification.
Before submitting any finished site work for inspection by the Engineer,
the Contractor shall completely inspect such work and shall carry out all
tests that the specifications require. The Contractor shall keep
inspection and test records covering all phases of the work and shall
submit these records to the Engineer
353
17.1.5 Tagging and identification
All equipment shall be identified by a permanently attached tag or
nameplate. The tag shall identify the service, identification number and
use. Wording on tags and nameplates shall be in English
17.1.6 Painting
Where painting is required a priming coat of paint shall be applied to the
surfaces, followed by an undercoat and finishing coat. The paint
system used shall have a minimum total dry thickness of 0.15 mm with
no porosity. The finishing coat shall be resistant to weathering.
The Contractor shall submit, for the Engineer’s approval, the painting
method and color standards he intends to adopt. In particular, he shall
specify paint material and the nominal value of the thickness of each
coat.
All spare parts shall be interchangeable with, and of, the equipment
furnished.
The Engineer may at his discretion order all, any or none of the
recommended spares.
Spare parts shall be packaged for indefinite storage in the climate at the
Site. Each part shall be marked with its description and purpose and
stock number on the outside of the packaging.
354
The contractor shall safeguard the use by the public and the Employer
of all adjacent highways, roadways, and footpaths, and shall conform to
all laws and regulations concerning the use thereof, especially limitation
of traffic and movement of heavy equipment. Access to the site for
delivery of construction materials and/or equipment shall be made only
at the locations approved by the Employer’s site representative. The
contractor shall be responsible for all damages to roads, crossovers,
service and the like arising from his execution of the work.
The contractor shall not house any labour on the site, with the exception
of the watchmen. He shall allow for all cost of moving the labour to and
from the site daily and at such times and by routes approved by the
Police and Local Authorities.
The contractor shall provide all temporary roads, tracks, hard standings,
crossing and the like to ensure satisfactory and efficient access to the
work. All such temporary roads and structures shall be to the approval
of the Employer’s site representative and may have to be removed on
completion of the work.
355
meetings and to review any or all-technical correspondence between
the Contractor and major equipment manufacturers.
Inspection
The Contractor shall be wholly responsible for the inspection of all
materials and equipment within the Contractor's scope at the sub-
vendor and sub-contractor's works, including establishing inspection
and test points. All such points shall be indicated in the Sub-vendor's
production schedule.
The Contractor shall provide the Engineer with certified copies of all
testing reports
Expediting
The Contractor shall be wholly responsible for the expediting of
information, documentation, equipment, materials and/or services from
its Sub-contractors and major equipment manufacturers in a timely
manner to meet the agreed-upon project schedule.
The contractor shall take all necessary precautions to ensure that all
materials that may be subject to deterioration in humid tropical
conditions are packed in such a manner as to prevent such
deterioration.
356
All parts shall be carefully boxed or otherwise suitably prepared for
shipment to a tropical climate. All openings shall be tightly closed
before shipment. Equipment that will be vulnerable to damage due to
seawater or moisture during transportation or storage at the Site shall
be protected by a suitable vapour barrier and, if considered necessary
by the Contractor or on Engineers request, by an internal atmosphere of
inert gas or approved desiccant.
All parts exceeding 100 kg gross weight shall be prepared for shipment
so that slings for handling by crane may be readily attached while the
parts are on railway cars or on broad ship. The Contractor shall paint or
mark the weight of all pieces in excess of 5 tones. The Contractor shall
take necessary measures to avoid ingress of moisture during
transportation, storage and installation.
Three (3) copies of all bills of lading and packing lists shall be forwarded
to the Engineer on shipment of materials and twenty (20) days notice
shall be given to the Engineer of the arrival of any materials at the Port
of Entry.
Permit
The Contractor shall prepare applications and submit on Employer's
behalf, for all necessary permits for the safe and legal construction,
installation and operation of the equipment from the required approving
bodies.
357
The inspection, testing and commissioning of all works under the
project shall be carried out in accordance with the acceptable
TANESCO procedures.
The Contractor shall not submit equipment for testing or inspection until
he has completed his own inspection and remedied any faults.
Upon practical completion of the works and before handing over the
building and installations to the employer, an acceptance test on proper
operation of the electrical installations will be carried out.
358
These will involve but not restricted to:
359
The Contractor shall supply all materials, labour, installations, fixing,
connecting, testing, labeling, commissioning and delivering the
installations complete and working in every detail as described
elsewhere in the specifications and on the drawings to the satisfaction
of the Engineer.
The codes and regulations shall include, but shall not be limited to, the
following:
Current Government Electrical Regulations
360
Relevant ANSI regulations
In addition to the minimum requirements described in the codes and
standards referenced herein, the contractor shall comply with all other
requirements contained in this specification. Alternative codes and
standards at least equivalent to those referenced may be substituted,
but the Engineers written approval will be required for this substitution.
In the event of any conflict, the Contractor shall seek resolution with the
Engineer.
Any and all applicable costs that the client is liable for to TANESCO in
conjunction with this service in any way shall be included. The client will
reimburse the Contractor of the TANESCO costs for service line and
commissioning at actual.
The Contractor is strongly advised to inspect the site. Any claim due to
lack of knowledge that should otherwise have been obtained by so
doing shall not be entertained.
361
17.2.3.2 MCB Distribution Boards
Distribution boards shall be manufactured in accordance with IEC 364,
439-1, BS 5486, IP 31. The Distribution Boards shall be fitted with
components as shown in drawings.
The distribution boards shall be surface mounted, fitted with DIN rail
and integral RCD incomers and current limiting circuit breakers. The
MCB’s for lighting shall be type B in accordance with IEC 898 and BS
EN 60898.
The Contractor shall ensure that cables are run and connected to the
appropriate equipments on the suitable location of the feeder
connection at the motor control centres.
362
The motor control centres to be supplied shall comply with the short
circuit levels as indicated in the drawings.
The Contractor shall ensure that all mounting arrangements, trim and
accessories for all fixtures are complete and to suit ceilings and walls in
which they are installed.
363
types of ceilings used, with particular regard to supporting frames,
spacing, ceiling panels etc. prior to ordering the fixtures.
The Contractor shall provide and install all lamps as shown on the
drawings and as specified herein.
All fluorescent fittings shall be power factor compensated to a minimum
of 0.9 and their control gears shall be rated 230V AC.
Exit signage shall provide clear and unambiguous light for the escape
route to final exits. The signage shall conform to BS 5499 part 1.
364
Mounting of detectors and alarm sounders as detailed below: -
Call points mounted at a height of 1400mm above finished floor lever to
centre.
Alarm sounders 1800mm above finished floor lever to centre.
Smoke and heat detectors shall be mounted on ceiling.
All fire alarm system call and sounder points shall be connected using
1.5mm2 Fire tuf cable with red PVC over – sheath. Surface mounted
accessories shall be supplied with the necessary bases.
A surface mounted alarm panel shall be installed with alarm circuit and
sounder circuits as indicated on the drawings. All sounders shall ring on
the operation of one or more of the manual call points.
365
Cables shall be installed flat, parallel and without kinks or twists. Care
must be taken to ensure that the bending radius at a turning is not less
than that recommended.
The protective sheath, screen and insulation of all the installed cables
shall be intact at all points along each cable. Any cable found to be
damaged during or after installation should be replaced in its entirety.
Trench Electrodes: in rocky areas or seabeds, the metal tapes are laid
in 0.5 m deep trenches of length as per the required resistance
(minimum of 9m length is required). Shorter lengths in parallel, dully
interconnected, or single length depending on space available are used.
Ground Grid Mesh Electrodes; Combination of plates and rods of
identical metals are put deep in ground for Grid mesh earthing.
The deep driven earthing and ground grid mesh electrodes systems are
the preferred methods. The design assumes that the ground grid mesh
electrodes shall be applicable for this installation.
The Contractor shall measure the soil characteristics and pit resistance
and accordingly recommend to the Engineer the type of earthing and
the earth electrodes to be used.
366
Non live conductors and parts designed to become live during
operation, all metal work forming part of or associated with electric
installation shall be earthed or protected as required by BS 7430:1991
Each apparatus shall be earthed through the shortest direct route with
minimum joints. Earthing by series of conductors looped from an earth
terminal on one equipment to another shall be prohibited.
367
conductors shall be jointed and sweated or attached in other permanent
and approved manner to the principal protective conductor as required.
In all cases where plastic conduits are used a protective conductor shall
be drawn into it in addition to circuit wiring. The protective conductor
shall run from the distribution board to the farthest point in each circuit
directly and without any break or looping point.
368
level. The earth wire of 95 sq. mm shall be connected to the said rods
by copper clamps supplied with electrodes.
The earth dispersion resistance shall be not more than 1.0*ohm at the
socket to the combined earth grid by earth plates and shall be not more
than 10*ohm at the socket to earth grid for lightning discharge earth
terminal.
Where more than one earth termination is required the earth leads from
these will be brought to a convenient point and bolted individually to a
common bar, which will form part of the main earth lead. Where multiple
earth terminations are used, the spacing between these will normally be
twice the maximum depth of the terminations.
369
17.2.8.8 Earth Resistance
The desired earth resistance is less than 1 ohms for equipment earth
and less than 5 ohms for lightning earth.
370
17.2.8.14 Test Points
There shall be a test point in every down lead of a lightning protection
system, and in every earth lead to multiple earth terminations where
they cannot otherwise be disconnected for testing individually.
Test points shall be provided 150cm from ground level in all down
tapes. They shall be a screw down type test clamp of an approved
pattern and the ends of the tape at this point shall be tinned. Both ends
of tape shall pass through both sides of the test clamp. Special
requirement will be stated in the particular specification.
The Contractor has to deliver and install the Diesel Generating Sets,
including all additional equipment and accessories that are necessary to
371
get a very reliable emergency power system which meets the present
state of the art.
Load imposition: Dynamic behaviour must comply with DIN 6280, part 3
50% load 8 seconds after start command.
30% load after each subsequent 3-4 second period, so that start-up and
load imposition sequences are completed at maximum 15 seconds after
start initiation
372
The fuel system shall provide 6 hours Genset operation under full load.
30 kVA, Stand-By Diesel Generator System, including housing, all parts
and accessories for Type B - Bus Stations
The Contractor has to deliver and install the Diesel Generating Sets,
including all additional equipment and accessories that are necessary to
get a very reliable emergency power system which meets the present
state of the artfulfilled and carried out:
Basic Requirements
Genset designed for operation according to DIN 6280 for emergency
power supply
Speed: 1500 rpm
Cos : 0.8
Voltage: 400V, 3-phase
Frequency: 50 Hz
Generator: 3-phase synchronous alternator, 1500 rpm
Design standard: DIN 6280 for
Intake air temperature: up to 45 °C
Site altitude: 830 m
373
Verification of all control and monitoring functions 3 starts with
preheated engine
Load imposition: Dynamic behaviour must comply with DIN 6280, part 3
50% load 8 seconds after start command 30% load after each
subsequent 3-4 second period, so that start-up and load imposition
sequences are completed at maximum 15 seconds after start initiation
Load test sequence:
1h 100% load
¼h 75% load
¼h 25% load
¼h 110% load
Load testing to be performed with cos = 0.8
Fuel System
The fuel system shall provide 6 hours Genset operation under full load.
The overload capacity shall be 10% of the rated output for one hour
every 12 hours of operation.
374
the engine/generator unit, and take all necessary steps to avoid
excessive stresses being set up.
17.2.9.1.3.3 Foundations
The engine and generator shall be mounted on a common base frame
to simplify alignment and to allow anti vibration mounting supplied by
Contractor to be introduced between base frame and foundation.
17.2.9.1.3.4 Pumps
The pumps for cooling-water, lubrication oil and fuel injection shall be
gear driven.
17.2.9.1.3.5 Governor
The Governor shall be of electronic sensing type, meeting the
requirements of BS 649 or equivalent approved standards as specified
for class A2, viz:
On suddenly taking off load while running at rated speed, the max.
change in speed shall not exceed 15% and permanently 4.5%. The
recovery time shall be 15 seconds.
Onchange of load by any step of 25% of the rated load while running at
rated speed, the maximum change in speed shall temporarily not
exceed 4% and permanently 1.5%. The maximum recovery time shall
be 5 seconds.
The steady load speed band shall not exceed 1% of the rated speed.
375
17.2.9.1.3.6 Charge Air System
The engine shall draw the charge air inlet. The Contractor shall take
care to ensure that the distance between the air intakes and the air
discharge is adequate to prevent air short-circuiting.
The cooling water pump shall be of the centrifugal type and the cooling
water circuit shall be fitted with a thermostatically operated bypass in
order to enable the engine to read the operating temperature in a
minimum time.
Provision shall be made for the checking of the return cooling-water for
rust and corrosion, acidity and impurities.
376
tank shall be sufficient for approximately twelve hours operation on full
load. The tank shall be provided with a float switch and fuel level gauge.
The fuel shall pass through a fine mesh filter before entering the fuel
injection pump on the engine. The tank shall be provided with all
necessary cocks including drain cock to enable maintenance crew to
isolate the tank from the rest of the fuel system for repairs.
A drip tray shall be installed below the service tank to each minor leak.
To drain the drip tray a cock shall be provided in a suitable position.
The battery charger shall be of current limiting type with automatic and
manual control. The capacity shall be sufficient to recharge a
completely discharged battery in a maximum of 24 hours.
Charger Specifications
Power supply - 230V single phase
Output voltage adjustment - +15% of nominal
Stability of output - +1.5% for maximum input and F Variations and 1%
to 95% of rated output current.
Dry type transformers and solid state (thyristor) rectifiers.
Toggle switch for independent battery measurement of voltage
Instruments - MCBs for protection on AC and DC side
One VDC – meter
377
One ADC – meter
One lamp indicating the charger is charging.
The change over switch shall be air integral part of the main LV
Switchboard as shown on drawings.
378
Generator earth fault
Bearing temperature supervision with alarm and stop should the control
circuit power fail, the standby unit must shut down
High oil temperature
Low coolant level
Prolonged overload.
17.2.9.1.4.5 Instruments
As minimum requirements, the following shall be provided either engine
mounted or in control panel:-
379
Cooling water temperature, oC
V-meter with selector switch, V
A-meter, one in each phase A
W-meter, W
Generator stator winding temperature oC
Engine running hours counter
17.2.9.1.4.7 Controls
The following shall be installed in the control panel
380
17.2.9.1.5 Operation
17.2.9.1.5.1 Starting Sequence
Should the control register a mains failure for a period between 0.5
second and 2 minutes (to be set) the ACOS shall initiate the automatic
starting sequence of the standby unit. When the generator stabilizes, a
tripping signal shall be given for the busbar breakers in the low-voltage
boards from the supply. Therefore the associated generator breaker
and other breakers necessary to connect the low voltage boards shall
close and connect the standby generator to the busbar.
The standby plant shall be allowed to idle for some time before the
engine is brought to a stand still in order to effect after cooling of the
unit.
Time delay (adjustable from 2 to 15 min), this time delay shall prevent
premature initiation of the shutdown sequence before the mains has
been fully restored.
The work shall include for the supply and installation of all jointing
materials, cable supports, steel racking and making all the necessary
381
cable joints. The cable shall be installed and tested in strict accordance
with the appropriate clauses of the IEE Regulations, the Factories Acts
and B.S. 6346 P.V.C. Insulated cables.
Cables shall at all times be handled with care and every effort made to
avoid damage. Unloading, rolling to position and mounting of cable
drums shall be carried out efficiently and carefully in the recognized
manner and cable shall be pulled from the top of drum and twisting shall
at all times be avoided.
Where cables are run vertically heavy gauge sheet metal guards shall
be supplied and fixed to the wall. The casing shall be fixed from floor
382
level to the underneath side of the appropriate end diving box or to a
height of 1.5 meter above floor level.
Where cables run through service ducts or cable trenches they shall be
fixed by means of purpose made cable hangers.
The sizes of cleats shall be selected such that all cleats can be
tightened down without exerting undue pressure or strain on the cable.
Where cables are spaced some distance from a supporting surface, the
cable racks shall be separately bolted to additional lengths of channel
section which in turn shall be fixed to brackets bolted and fixed into the
structure. Cables shall be colour coded throughout their length.
383
all cable terminations. Characters shall not be less than 3mm high and
shall be clearly visible.
The Contractor will carry out trenching and back filling, and he will be
responsible for marking out the cable route and for the supervision of
the back filling insofar as the prevention of damage to cables in this
process is concerned.
The Contractor shall supply and install concrete marker post at each
cable entry into a building, each change of direction, each change road
or pathway crossing and throughout the length of the cable at intervals
not exceeding 50 metres.
The position of all cable marker posts shall be agreed with the Engineer
before installation.
The Contractor's attention is drawn to the fact that all cable size, circuit
breakers and fuse ratings given in the specification and/or Contract
Drawings are based on the use of cables with copper conductors unless
specifically specified to the contrary.
384
The Contractor shall be deemed to have allowed in his prices for
supplying sufficient cable lengths of each type and size to complete the
system and for making allowance for any additional length for cutting
and waste.
17.2.10.2.2 LV Cables
These shall be of steel wire armoured capable to withstand highest
equipment voltage of 1200V at 50Hz, and they shall be single core.
17.2.10.2.3 Wiring
Wiring shall be carried out in an approved type of PVC insulated single
core copper conductor cable. The colours of the cores shall comply with
the colour code requirements of the IEE Regulations. Under no
circumstances shall it be permitted to draw cable into an incomplete
section of the conduit installation. The wiring shall be carried out in the
looping-in principle. All joints shall be made at the terminals of main
switches, and socketed outlets, etc, and fixed apparatus only. No joints
shall be made in boxes unless approved.
385
The cable shall be run in the conduit so as not to exceed the capacities
as set out in the IEE Regulations (16th Edition) with current
amendments.
Not more than six final sub-circuit cables shall run in conduits feeding
outlet boxes without the approval of the Engineer. Not more than eight
cables running straight back to the distribution board shall be enclosed
in any one conduit.
386
and unnecessary, short lengths of conduit not exceeding 0.9 m in length
between boxes need not be secured further than by connection to the
adjacent boxes. Sunken conduit run in chases in walls shall be fixed by
means of mild steel pipe hooks or non-metallic saddles spaced not
more than 0.9 m. Where conduit is concealed behind plaster it shall be
sunk to a depth of either 15 mm below finished plaster level, or installed
flush with the structural wall level before application of plaster,
whichever is the lesser depth.
Immediately prior to installing the wiring all conduit and fittings shall be
dried and cleaned out by drawing through a cloth swab. Rawlplugs shall
be used for fixing to aluminium section, rawlnuts, spring toggles,
gravitytoggles or rawlbolts shall be used for fixing to other materials as
approved by the Engineer. Corners shall be turned by easy bends or
sets made in accordance with the manufacturer's instructions without
altering the section or splitting the conduit.
387
conduit enters the flameproof area. All Conduits installed within this
areas shall be solid drawn galvanized, as shall be conduit fittings and
accessories and Buxton Certified as suitable for Group II hazards.
Equipment shall comply with B.S.229, B.S. 889, and Code of Practice
C.P. 1003.
Metal Trunking shall be fabricated from galvanized steel of not less than
18 swg. All section of trunking shall be rigidly fixed together and
attached to the framework or fabric of the building at intervals of not
less than 1.2 m. Joints in trunking shall not overhang fixing points by
more than 0.5m.
All trunking fittings (i.e. bends, tees, etc.) shall leave the main trough
completely clear of obstruction and continuously open except through
walls and floors, at which points suitable fire resisting barriers shall be
provided as may be necessary. The inner edge of bends and tees shall
be chamfered where cables large than 35 mm2 are employed.
Where trunking passes through ceilings and walls the cover shall be
solidly fixed to 150 mm either side of ceilings and floors and 50 mm
either side of walls.
388
Where trunking is used to connect switchgear or fuse boards, such
connections shall be made by trucking fittings manufactured for this
purpose and not by multiple conduit couplings.
Conduit shall be swabbed out prior to drawing in cables, and they shall
be laid so as to drain off all condensed moisture without injury to end
connections.
Conduits and trunking shall be run at least 150 mm clear of hot water
and steam pipes, and at least 75 mm clear of cold water and other
services unless otherwise approved by the Engineer.
389
Conduits installed and buried in walls shall allow a minimum of 15 mm
cover. Sunk circular conduit boxes shall be provided with break joint
rings of white moulded material or metal.
All conduit boxes, except loop-in pattern in concrete floors shall be fixed
direct to the structure apart from the support provided by the conduits.
Box lids where required shall be heavy gauge metal, secured by means
of zinc plated or cadmium plated steel crews.
All adaptable boxes and lids of the same size shall be interchangeable.
Draw-in boxes in the floors are generally to be avoided but where they
are essential they must be grouped in positions approved by the
Engineers and covered by suitable floor traps, with non-ferrous trays
and covers.
Where buried in the ground outside the building the whole of the buried
conduit is to be painted with two coats of approved bitumastic
composition before covering up. Paint damaged and joints under screed
are to be similarly treated.
Where run on the surface, unpainted fittings and joints shall be painted
with two coats of oil bound enamel applied to rust and grease free
metalwork.
390
Large sizes of conduit shall be pre-heated before inserting rubber cord
to prevent kinking. Conduit badly formed or bent, or damaged in any
way, shall not be used.
Where ceiling roses occur and the ceiling box is recessed below the
finished level of the ceiling, suitable extension rings to accommodate
the ceiling rose must be provided.
All spare ways in junction boxes etc. left for possible future extension
shall be fitted with stopping plugs.
391
Non metallic trunking shall be manufactured from high impact resistant
PVC-U material in compliance with the requirements of BS 4678 Part 4
(1956). All screening lengths shall be butt jointed and corners mitred.
Joints shall be electrically connected by means of screening bonding
straps to maintain continuity when earthed.
All testing and inspection shall be carried out in the presence of and to
the entire satisfaction of the Engineer at such times as may be required.
The Contractor shall give the Engineer at least seven clear days notice
of the commencement of any tests in order that he may, at his
discretion, make arrangements to attend and witness the tests. The
Contractor shall ensure that he completes his own inspections and
tests, and rectifies any installation faults, prior to submitting the
equipment for witness tests.
392
It shall be the responsibility of the Contractor to provide, at his own cost,
all the test equipment necessary for the complete testing of the
installation in accordance with this Specification. All test equipment
used shall be calibrated "in date" and records of equipment serial
numbers together with calibration details shall be available for
examination by the Engineer on demand.
Five copies of the records of inspection and complete results of all tests
shall be delivered to the Engineer, together with copies of the
manufacturer's test certificates.
17.2.12.1.2 Earthing
Measurement of resistance/impedance of earth bonding and earthing
conductors. Continuity shall be checked with one lead of an ohmmeter
at the main earth termination and the other probing all conductive metal
to verify that the protective conductors are electrically sound and
correctly connected.
393
Fault Loop impedance shall be carried out using both substantial
current testers and also with intrinsically safe tester. The results of both
tests shall be recorded so that subsequent tests may be carried out
using only Intrinsically Safe testers, allowing the condition of the Earth
System to be assessed by comparing the results of the I.S. test with
results obtained initially in conjunction with the high current test.
17.2.12.1.3 Insulation
The insulation resistance between cores and earth on all LV and MV
cables shall be checked and recorded. Cables shall be tested for
correct insulation resistance as follows: -
Before and after jointing or making off, low voltage cables shall be
tested with a 500-Volt insulation tester.
Before and after joint or making-off, high voltage cables shall be tested
with a 2500 volt high voltage tester.
Phasing out and continuity tests on M.V. and L.V. cables shall be
carried out with battery operated lamp or bell set and not with an
insulator tester.
All M.V. cables, and when required L.V. cables, shall be pressure tested
in accordance with BS 6480 Part 1 after laying and jointing (i.e. before
commissioning)
17.2.12.1.4 Continuity
All cores of all cables shall be tested for point-to-point continuity to
ensure that conductors are not damaged or connected incorrectly.
Where cables are installed in underground trenches, point to point
checks shall be carried out before the trench is backfilled to avoid
having to re-excavate the cable route if any faults are discovered.
394
General
Equipment is installed and wired in accordance with final approved
drawings.
All labels and warning notices are correctly located and secured.
Glands have been correctly made off and any barrier glands properly
filled and sealed. In particular, on steel wire armoured cables, no amour
is visible outside the seal on the outer sheath on the cable when the
shroud is pulled back.
After carrying out initial inspections and Tests but before the installation
is put into service, the Contractor shall submit to the Engineer a
Completion Certificate in accordance with BS 7671.
395
17.3 ELECTRICAL EQUIPMENT SPECIFICATIONS FOR TYPE A – BUS
STATIONS
17.3.1 EARTHING SYSTEM
17.3.1.1 30x3.5 mm Galvanized Steel Strip
Supply and installation of 30x3.5 mm Galvanized Steel Strip as shown
in related drawings. They have to be factory assembled.
397
17.3.2.6 Single Pole One Gang lighting switch
Supply and installation of Single Pole One Gang lighting switch
including all parts. They have to be factory assembled.
All wall mounted lighting switches shall unless otherwise specified be
mounted 1.5 m above finished floor level.
Switches and socket outlets installed in rooms with embedded wiring
shall be designed for flush mounting in moulded plastic wall boxes and
rated for 10 A.
398
The cables shall be designed, manufactured and tested according to
the latest version of IEC 61034-1/2, IEC 60754-1/2, IEC 60332-1-2 and
IEC 60332-3-24.
Cables shall be produced acc. to VDE 0276-604.
Permissible operaton temperature shall be 90 oC.
399
Construction
Stand mounted unit fitted with heavy cast iron base.
Wall mounted unit comes with a heavy duty wall bracket and tube.
Impellers are of aluminium and fully balanced.
Wire finger guards are grey painted mesh.
All steel components have a corrosion resistant finish.
Motors
Type - squirrel cage induction motor
Electricity supply - 220-240V, single-phase, 50Hz
Bearings - sealed-for-life, ball
3-speed motor with switchImpellers shall be manufactured from
aluminium and shall operate in 3 speeds which are controlled by a
switch that includes an off position. Wire finger guards shall be of grey
painted mesh.
400
weight and dimensions in excess of the specified quantity. The design
of such trays shall include a factor of safety to guard against permanent
distortion when supporting erection staff during cable installation. The
trays shall be of suitable aluminium alloys or hot-dip galvanized steel
standard material.
All trays, supports, ladders, etc., shall be of hot-dip galvanized steel
elements.
401
extension at side. The frame and cladding shall be fabricated from
sheet steel at least as follows:
Frame: 2.5 mm
Cladding: 2.0 mm
Top cover: 1.5 mm
Division sheet: 1.0 mm
All bolts, screws, washers, etc., shall be corrosion protected.
The cubicles shall be complete with all locks, cable end boxes, colour
coded busbars, internal wiring, terminal boards and accessories.
402
Electrical cubicles shall be constructed of braced rolled steel sections,
with recessed panels, and substantial mounting frames for mounting of
power and control cables. The frame shall consist of sturdy steel
sections that are bolted together by means of corner pieces. The
cladding shall be bolted to the frame from the outside to simplify
extension at side. The frame and cladding shall be fabricated from
sheet steel at least as follows:
Frame : 2.5 mm
Cladding: 2.0 mm
Top cover: 1.5 mm
Division sheet: 1.0 mm
All bolts, screws, washers, etc., shall be corrosion protected.
The cubicles shall be complete with all locks, cable end boxes, colour
coded busbars, internal wiring, terminal boards and accessories.
403
EN 60439 Specification for low-voltage switchgear and control-
gear assemblies.
EN 60439 Low-voltage switchgear and control-gear
IEC 439 assemblies.
EN 607421 Isolation transformers and safety isolating
transformers.
EN 60947 Specification for low-voltage switchgear and control-
gear.
IEC 60044 Instrument transformer.
IEC 60051 Direct acting indicating analogue electrical
measuring instruments and their accessories.
IEC 60186 Voltage transformers.
IEC 60255 Electrical relays.
IEC 60521 Class 0.5, 1 and 2 alternating-current watt-hour
meters.
IEC 60529 Degrees of protection provided by enclosures (IP
Code).
IEC 61000 Electromagnetic compatibility (EMC).
404
Busbars shall be suitably mounted in enclosed compartments running
the full length of the distribution boards. Access to the busbars shall be
possible only by removing bolted covers.
405
comply with the requirements of the latest relevant approved standard
specifications.
Busbars shall be suitably mounted in enclosed compartments running
the full length of the distribution boards. Access to the busbars shall be
possible only by removing bolted covers.
406
Technical data
Input 400/230 V +/- 10 % , 50 Hz +/- 5 %
Intermediate 220 V or 372 V +/- 15 %
Output
circuit 230 V +/- 1 % static, +/- dynamic, 50 Hz +/- 0.1 %, Quartz
Overhead 50%
synchronised for 60 sec.
Short
behaviour circuit short
25 circuit proof,
% short circuit
for current <
10 2*I-nom for 20
min.
Wave form
behaviour sine
sec. wave
10 % for 20 min.
Power factor 0.0 ind. – 0.0 cap
Distortion
range < 3 % with lin. load
System
factor > 90 %
Battery
effectivity for 3hr back-up time
Norms
capacity IEC, VDE, DIN, EN
407
17.4.1.6 Bonding Cable, 1x16mm² Yellow-Green Insulated Cable
Supply and installation of 1x16mm² Yellow-Green Insulated Cable as
shown in related drawings. They have to be factory assembled. They
shall be used for all metalic parts bonding.
All fixed devices are to be connected to the power supply via cable-
connection-boxes or junction-boxes.
Operating voltage: 100 - 277 VAC (50 / 60 Hz)
Light source: SMD-LEDs
System performance: 162.2 - 264 W
Lighting current: 17'089 - 32'327 lm
System efficiency: up to 136.5 lm / W
Light colour: 5'000 K
CRI: Ra > 80
Beam angles: 30° / 60° / 90° / 120°
LED-Operating life: [L70 / B10] > 80'000 h
Protection category: IP65
Protection class: I
Dimming: optional 1~10V or DALI
Operating range of temperature
160 W: –30° C to +60° C
Max. surface temperature: +90° C (suitable for use in industrial
Housing: Die-cast aluminium
Housing colour: black
408
Protection class: IP67
409
0.6/1 kV LV indoor cables shall be low smoke, flame reterdant and
halogen free type.
410
The cables shall be designed, manufactured and tested according to
the latest version of IEC 61034-1/2, IEC 60754-1/2, IEC 60332-1-2 and
IEC 60332-3-24.
Cables shall be produced acc. to VDE 0276-604.
Permissible operaton temperature shall be 90 oC.
Construction
Stand mounted unit fitted with heavy cast iron base.Wall mounted unit
comes with a heavy-duty wall bracket and tube.Impellers are of
aluminium and fully balanced.Wire finger guards are grey painted
mesh.All steel components have a corrosion resistant finish.
411
Motors
Type - squirrel cage induction motorElectricity supply - 220-240V,
single-phase, 50HzBearings - sealed-for-life, ball3-speed motor with
switch
Impellers shall be manufactured from aluminium and shall operate in 3
speeds which are controlled by a switch that includes an off position.
Wire finger guards shall be of grey painted mesh.
17.4.3.2 Galvanized steel cable trays, cable ladders and their accessories.
Supply and installation of Galvanized steel cable trays, cable ladders
and their accessories.
412
All trays, supports, ladders, etc., shall be of hot-dip galvanized steel
elements.
413
All bolts, screws, washers, etc., shall be corrosion protected.
The cubicles shall be complete with all locks, cable end boxes, colour
coded busbars, internal wiring, terminal boards and accessories.
Busbars shall be made of high conductivity electrolytic copper
conductors suitably protected against corrosion and rigidly supported on
approved type of insulators and shall, unless otherwise specified,
comply with the requirements of the latest relevant approved standard
specifications.
414
cladding shall be bolted to the frame from the outside to simplify
extension at side. The frame and cladding shall be fabricated from
sheet steel at least as follows:
Frame : 2.5 mm
Cladding : 2.0 mm
Top cover : 1.5 mm
Division sheet : 1.0 mm
415
IEC 60255 Electrical relays.
IEC 60521 Class 0.5, 1 and 2 alternating-current watt-hour meters.
IEC 60529 Degrees of protection provided by enclosures (IP Code).
IEC 61000 Electromagnetic compatibility (EMC).
Frame : 2.5 mm
Cladding : 2.0 mm
Top cover : 1.5 mm
Division sheet : 1.0 mm
416
The LV switchgears and the relevant equipment shall be designed,
manufactured and tested according to the latest version of:
Frame : 2.5 mm
Cladding : 2.0 mm
Top cover : 1.5 mm
Division sheet : 1.0 mm
417
Busbars shall be made of high conductivity electrolytic copper
conductors suitably protected against corrosion and rigidly supported on
approved type of insulators and shall, unless otherwise specified,
comply with the requirements of the latest relevant approved standard
specifications.
418
Technical data
419
B Gigabit Ethernet Switch - 24 x 10/100/1000 PoE Ports - 4 x SFP
C 12-Core ODF
D 12-Core MM Fiber Cable ( Provisional)
E MM SFP Card complete with Modules
F MM Fiber Patch Cords
G 24 Port Ethernet Patch Panel
H Cat 7 UTP Ethernet Cable
I Cat 7 UTP Ethernet Patch Cords
J Cat 7 Dual Port Ethernet Faceplate complete with backboxes
K Cat 7 RJ45 complete with rubber cap
L 120mm PVC Pipe for ducting
M 30x30 ducting manholes complete with anti-rust metal cover
N 18U Standing/Wall mounted Data Cabinet complete with PDUs and Ventilation
fan
1.11.4 AS BUILT DRAWINGS
O Allow for provision of three(3) sets of as an installed drawings for the whole of
AFCS installations including operation and maintenance manuals.
420
1.13 OPTICAL FIBER NETWORK-OFN
Mobile Inspection Devices with Smart Card Reader (NFC Based), Camera and
biometric scanner
B Outdoor Fiber Optical Single Mode Core 12 G652D
C In-Line Type Fiber Optic Spicing Closure complete with spice trays of
appropriate sizing and sleeves as required
D Fiber Patch Cord with LC/E2000/SMA Connectors
1.14 AS BUILT DRAWINGS
E Allow for provision of three(3) sets of as an installed drawings for the whole of
OFN installations including operation and maintenance manuals.
Prices and payments will be full compensation for all work specified in this
Section, including supplying, Installations, Testing, Commissioning and associated
buiders work.
421