Geotechnical Report for KNUST Lab Redevelopment
Geotechnical Report for KNUST Lab Redevelopment
COLLEGE OF ENGINEERING
PROJECT TITLE:
Report by
Name: Francis Njibiche Nlansong
Index number: 8154219
[April, 2023]
i
EXECUTIVE SUMMARY
Development office of KNUST, Kumasi, Ghana, who intends to redevelop the master plan
laboratory building for college of engineering, has commissioned ABP Consult limited to
undertake the general planning and design of the project.
A geotechnical investigation was carried out on the project site to obtain geotechnical
information of the land for the design of the facilities. A field reconnaissance survey was
conducted on the project site. It was observed that the project site and its environs was used
for growing of crops such as lettuce, cabbage, okra and onion.
Standard Penetration Tests was carried out on the project site from 20th March to 24th March
2023, and from the results obtained, competent soil layer was encountered at a depth of 2m
and below. Five boreholes were drilled at the proposed site for the laboratory building. Water
table was encountered during the test, SPT was conducted to a depth of 12 and 15m. The
Meyerhof method of foundation design was implemented using a factor of safety of 3.
Maximum depth of placement of foundation footing should be 3m.
18 Dynamic Cone Penetration Tests alongside 2 trial pits were used for the analysis of the road
pavement and car park subgrade strength. Results indicated a two-layer structure with a weaker
top layer made of mainly loamy soil containing plant roots, underlain by a loose layer of soil
which contains sand and silt and soft clay. Results from trial pits indicates that the soil has a
high affinity for water, hence much efforts must be put in providing adequate sealing and
draining of road surface. Natural material to be borrowed for the base and sub-base will be
taken from Bonwire-Juaben road 15+120 RHS and aggregates will be taken from A. Kannin
Quarry site. Aggregates for concrete work (River sand) will be sourced from ANWOMASO,
Kumasi.
i
GLOSSARY
BH Borehole
BS British Standard
LL Liquid Limit
PL Plastic Limit
PI Plastic Index
TP Trial Pit
ii
TABLE OF CONTENTS
EXECUTIVE SUMMARY.................................................................................................... i
GLOSSARY ........................................................................................................................... ii
iii
3.5 SOURCES AND QUALITY OF CONSTRUCTION MATERIALS ................... 11
4.4.1Natural Gravel..................................................................................................... 19
6.1 CONCLUSION.......................................................................................................... 28
REFERENCES .................................................................................................................... 30
APPENDICES ..................................................................................................................... 31
iv
LIST OF FIGURES
Figure 1: Cabbage and water source used for the irrigation of the crops on project site ........ 5
Figure 2: Seismic Hazard Map of Southern Ghana(Ahulu et al., 2018). ................................ 6
Figure 3: Percussion drilling and sample collected ................................................................ 7
Figure 4: DCP points along the proposed road and car park .................................................. 8
Figure 5: SPT boreholes at the building site ........................................................................... 9
Figure 6: Carrying out the DCP test...................................................................................... 10
Figure 7: Trial pits along the proposed road and car park. ................................................... 10
Figure 8: USCS soil classification chart(“Principles of Geotechnical engineering,” n.d.). .. 14
Figure 9: graph of allowable load against foundation width for depth from (1-3) m. .......... 17
Figure 10: Summary data of DCP results along the proposed road ...................................... 18
Figure 11: Soaked CBR data for layer 2 pit 1 ....................................................................... 18
Figure 12: Two layers DCP1 point ....................................................................................... 19
Figure 13 graphs of natural gravel and river sand ................................................................ 36
Figure 14: Graph of chippings .............................................................................................. 37
Figure 15: Summary of compaction result on pit 1 layer 2 .................................................. 46
LIST OF TABLES
v
Table 14: Summary results of grading of aggregates ........................................................... 37
Table 15: Summary data of DCP values ............................................................................... 38
Table 16: DCP values at the proposed car park .................................................................... 39
vi
CHAPTER ONE
INTRODUCTION
The Kwame Nkrumah University of Science and Technology, Kumasi (KNUST), the premier
Institution in Ghana responsible for the training of engineers, medical personnel, scientists, and
technologists required to support the industrial and socio-economic development of Ghana is
undertaking a re-development of its facilities, which includes the expansion of the existing
facilities. The site for the expansion is to the south of the existing facilities for which a Master
Plan has been developed. The objective of the project is to develop the required infrastructure
to support the Master Plan and develop a new Civil Engineering laboratory to replace the
existing facility built some 50 years ago. The development would be done in two phases, as
indicated. Phase One is the several acres of land where the full infrastructure would be
developed, and Phase Two construction is anticipated to commence ten years later.
The Development Office of KNUST, the Client, has commissioned a Planning and
Architectural Consulting Firm to undertake the general planning and the design of the
architectural aspects of the development scheme. Similarly, the Client has engaged the services
of Engineering Consultants to design the mechanical and electrical engineering aspects of the
proposed development scheme. The Client has completed and approved the planning proposals
and architectural designs of the laboratory. However, the design of the site layout has partly
been completed as the Planners are awaiting the engineers' advice, especially regarding the
road layout and other supplementary infrastructure. It is now required to propose conceptual
engineering designs and undertake the design of the Civil Engineering infrastructure structure
Works for the proposed Development Scheme.
To this end, the Client has commissioned M/s EDCIV 2023 Civil Group 27 to design the Civil
Engineering Infrastructure Works for the entire Project Site, emphasizing the development of
Phase One Works for the University in Kumasi
1
ENGINEERING DEPARTMENT, KNUST CE 497 CIVIL ENGINEERING DESIGN PROJECT
2023, 2023)..
2
• Carry out the appropriate investigation to support the safe and economic design of the
pavement of the road network and parking areas.
• Provide the necessary information about the sources and quality of construction materials of
geologic origin required
From the above, tests such as index property tests (Atterberg and Particle Size Distribution
test) will be conducted to classify and identify to check the engineering properties of the soil.
And based on that and other tests which would be clearly discussed later would be used to find
the bearing capacity of the soil on site. This needs to be done to ensure that the building does
not settle appreciably in the soil. Then also for the road pavement design, further tests will be
done to select the appropriate pavement materials and the required thickness needed to oversee
its construction.
3
CHAPTER TWO
DESK STUDY
2.1 BACKGROUND
The Engineering team (group 27) paid visits to the site on 24th February 2023 in order to be
informed of the prevailing conditions on the site. We traversed the entire site on foot, inspecting
the general conditions of the site. We studied the general ecosystem of the site. The project is
expected to have both environmental and social impacts which will be mitigated if being a
negative one. These visits were needed to inform us on how to accomplish the design task.
2.2 SITE LOCATION
The site for the expansion of phase I development of the master plan is to the south of the
existing facilities of the engineering laboratory of Kwame Nkrumah University of Science and
Technology, Kumasi. The site is a vegetative land used for the growing of crops such as lettuce,
cabbage, okra, and cassava by farmers around the KNUST enclave.
2.3 TERRAIN
The landscape is dotted with lush green vegetation, with rolling hill and valley. This part of the
laboratory is also home to streams that provide a source of water for the surrounding area. The
soil here is good in nutrients and offers great potential for agricultural production.
2.4 VEGETATION COVER
There are not many trees present and the few that are, are spread apart. The distribution of
vegetation on the land is uneven. There exists a farmland present near and around the site, the
farmland is grown with crops such as lettuce, cabbage, okra, and cassava.
4
Figure 1: Cabbage and water source used for the irrigation of the crops on project site
5
A reconnaissance study was made to the site on 24th February 2023 and the following
conditions were observed:
• Present on site is an ongoing farming of cabbage, lettuce, and okro by the farmers.
• Two test-pit are dug at the site for geotechnical investigation
• There is also a created foot path, which provides access for the farmers and for
conveying their farm products. This foot path leads down into the site and ends at the
center of rehabilitation at KNUST school of business; Therefore, access to the other
parts of the site (for example the to-be residential part) is very difficult since
everywhere is covered with natural vegetation.
2.7 SEISMICITY
The seismic hazard assessment map of Ghana as well as data of previous earthquakes in Ghana
were examined in order to determine the likelihood that an earthquake event will occur at the
project location. The country of Ghana is situated on the southern edge of the West African
Craton. The country normally has a lower risk of earthquakes due to its location far from major
earthquake zones.
The forces that produce seismic activity in the southeast of the nation include the Akwapim
Fault and the Coastal Boundary Fault. In general, the project location is close to Kumasi,
which has a reduced risk of significant seismic activity; as a result, the site may not be
vulnerable to earthquakes. Seismic Risk Map of Ghana(Ahulu et al., 2018).
6
CHAPTER THREE
To ascertain the soil's bearing capability at the project site, SPT tests were carried out from
March 20, 2023 through March 24, 2023. Boreholes were created using cable percussion
drilling so that the testing could be carried out underground. There were five boreholes created.
SPT tests were carried out and recorded at intervals of 1 m and 1.5 m during drillings to a depth
of 12 and 15 m. SPT-N readings and the visual features of soil samples were documented and
recorded for analysis. Using the Dando 2500 drilling equipment, five boreholes were created
at the location of the laboratory building, and samples were then taking to the laboratory for
testing and categorization. See the borehole log in the appendix.
7
Figure 4: DCP points along the proposed road and car park
8
Figure 5: SPT boreholes at the building site
In order to ascertain the in situ CBR of the subgrade soil, DCP tests were carried out on Friday,
May 6, 2022, at the location that would be used for the automobile parking lots and the network
of paved roads. To span the length of the proposed road pavements, 13 DCPTs were performed
on the site at predetermined intervals, 8 along the proposed road and 5 at the car park. For the
purpose of calculating the in situ CBR, the number of blows needed to drive the cone 100 mm
into the earth was noted(Ampadu, 2023).
9
Figure 6: Carrying out the DCP test
Two trial pits were excavated on Saturday, March 18, 2022, at specific DCP locations to
evaluate the soil layers and their qualities in a laboratory setting.
The pit's visual features were noted, and disturbed samples were brought to the lab for analysis.
Samples taken from the boreholes, trial pits, borrow pits, quarry sites and river sand were tested
in the lab to determine its composition and classification. The Test conducted were;
• Compaction Test
Figure 7: Trial pits along the proposed road and car park.
• Flakiness index
• Elongation index
• Absorption Test
10
These tests are conducted with reference to(REPUBLIC OF GHANA Ministry of
Transportation STANDARD SPECIFICATION FOR ROAD AND BRIDGE WORKS,
2007).
A.Kanin Quarry site was selected as the source of chippings for both concrete mixes and for
road pavement construction. Results obtained from tests conducted by GHA on samples taken
from the site were obtained and used for the analysis. Natural Gravel and river sand located at
Bonwire and Anwomaso respectively was selected and results obtained from tests conducted
by GHA was used for analysis.
11
12
CHAPTER FOUR
DISCUSSION OF RESULTS
4. 1 SOIL PROFILE DESCRIPTION
TRIAL PIT 1
DATE: 18-Mar-2023 18-Mar-2023 LOCATION: KNUST
Latitude: 6.670406° N Longitude: 1.566268°E
TRIAL PIT 2
DATE: 18-Mar-2023
LOCATION: KNUST
Latitude: 6.6707622° N Longitude: 1.5649704°E
13
Figure 8: USCS soil classification chart(“Principles of Geotechnical engineering,” n.d.).
As sand made up the majority of the soil at the predicted depth, it made it rather trustworthy to
estimate the soil carrying capacity using the N values acquired from the SPT test. The
foundation of the proposed structure was developed in collaboration with my structural
engineer. Based on the predicted bearing capacity, each footing will be isolated and the width
of the footing fixed.
14
In order to determine the bearing capacity of the soil, the Meyerhof approach was adopted.
This requires the computation of soil bearing capacities using the parameters.
𝑆𝑒
𝑞𝑎𝑙𝑙 = 19.16𝑁𝑑𝑒𝑠 𝑥𝐹𝑑 ( ) 𝑓𝑜𝑟 𝐵 ≤ 1.22
25.4
3.28𝐵 + 1 2 𝑆𝑒
𝑞𝑎𝑙𝑙 = 11.98𝑁𝑑𝑒𝑠 𝑥( ) 𝐹𝑑 ( ) 𝑓𝑜𝑟 𝐵 > 1.22
3.28𝑏 25.4
𝐷
𝐹𝑑 = 1 + 0.33 ≤ 1.33
𝐵
In the determination of the design N, SPT N values obtained from the SPT tests needs to be
corrected. Skempton’s formula was used. The formula can be written as;
2
𝑁𝑐𝑜𝑟 = ( )𝑁
1 + 0.01044𝛿
Where, N=SPT value at a given depth Ncor= corrected N value and 𝜎𝑣 ′ = effective overburden
pressure
This approach allows the determination of soil bearing capacity, using an allowable settlement
of 25mm and a factor of safety of 3(Fundamentals of Geotechnical Engineering, n.d.;
“Principles of Geotechnical engineering,” n.d.). Design of the foundation was based on
borehole 1, 3 and 5 since they have similarities in the properties of soil encountered at the trial
pits. An isolated footing
15
Table 4: Finding the allowable load for a depth of 1.5m
d=1.5
B(m) D/B fd Q (kN/m2) Area (m2) Q all (KN)
1.25 1.200 1.006 256.99 1.5625 401.54
1.3 1.154 1.006 253.09 1.69 427.73
1.4 1.071 1.006 246.21 1.96 482.57
1.5 1.000 1.330 317.87 2.25 715.22
1.6 0.938 1.309 306.37 2.56 784.31
1.7 0.882 1.291 296.45 2.89 856.75
1.8 0.833 1.275 287.81 3.24 932.51
1.9 0.789 1.261 280.22 3.61 1011.61
2 0.750 1.248 273.51 4 1094.03
2.1 0.714 1.236 267.52 4.41 1179.76
2.2 0.682 1.225 262.15 4.84 1268.82
2.3 0.652 1.215 257.31 5.29 1361.19
2.4 0.625 1.206 252.93 5.76 1456.88
2.5 0.600 1.198 248.94 6.25 1555.88
16
3 3 1 16 16 9.81 39.19 4
5.12 12 2.12 18 38.16 20.7972 56.5528 15
6 8 0.88 18 15.84 8.6328 63.76 10
7.5 9 1.5 18 27 14.715 76.045 10
9 10 1.5 18 27 14.715 88.33 10
10.5 29 1.5 22 33 14.715 106.615 27
12 50 1.5 22 33 14.715 124.9 43
13.5 50 1.5 22 33 14.715 143.185 40
15 50 1.5 22 33 14.715 161.47 37
1.5m
1000
2m
800
2.5m
600
3m
400
200
0
0 0.5 1 1.5 2 2.5 3
Width(m)
Figure 9: graph of allowable load against foundation width for depth from (1-3) m.
Two trial pits were dug for examination of the soil profile of the subgrade. Each one of them
was used in classifying and estimating the strength of each of the two roads. Three layers of
soil was encountered in trial pit 1 at DCP point 9 with other.
17
DCP NO OF AV.
ALONG THE ROAD DCP POINTS
POITS LAYERS CBR PERCENTILE%
100.00%
1 2 4 8.3 90.00%
80.00%
2 3 5 41.6 70.00%
PERCENTILE%
60.00% ALONG THE
3 2 6 83.3 ROAD
50.00%
4 2 7 100 40.00%
30.00% 10th
5 2 6 83.3 20.00% percentile at
4.1
10.00%
6 2 4 8.3
0.00%
2 0.00 5.00 10.00
7 5 41.6
CBR VALUES
8 2 5 41.6
9 3 5 41.6
10 2 5 41.6
11 2 4 8.3
12 2 4 8.3
13 2 3 0
Figure 10: Summary data of DCP results along the proposed road
15
SOAKED CBR
5.00 14
55 BLOWS
4.50 13
25 BLOWS
4.00 12
10 BLOWS
3.50 11
CBR (%)
3.00
10
LOAD(kN)
2.50
9
2.00
8
1.50
7
1.00
6
0.50
5
0.00 80 82 84 86 88 90 92 94 96 98 100
0.00 2.00 4.00 6.00 8.00 10.00 MDD (%)
PENETRATION(mm)
18
1
-100 0 2 4 6 8 10 12 14 16
0
100
y = 80.124x - 3.7267
200
Layer 1
300 Layer 2
400
500
y = 50x + 200
600
700
800
900
1000
Two layers of soil were encountered in trial pit 2, where DCP point 5 for car park was
conducted. The results are shown below.
The site investigation revealed that the top soil contained lots of organic matter and is an
unsuitable material for the job. It was observed that the soil in trial pit 1 is predominantly
clayey-SAND and sandy Clay material after stripping of the top soil, whiles the soil in trial pit
2 is silty-SAND with no gravel, water was encountered at a depth of 0.69m with the top soil
caving, this suggest that the soil is unable to support itself weight. The average CBR values
from the proposed road and the car park from the DCP computations are respectively 4 and 3.
This shows that the sub-grade strength is weak hence fill materials has to be imported.
19
indicated that it met the required standards for Material class G60 and G80. Summary of the
results is shown in the table below.
53 mm 100
80 - 100 100 - 80
37.5 mm 99.3
19 mm 83.8 60 - 85 100 - 75
% Passing 10 mm 69.0 45 - 70 90 - 45
4.75 mm 49.5 30 - 55 75 - 30
2.00 mm 38.7 20 - 45 50 - 20
425 µm 26.5 8 - 26 33 - 8
75 µm 8.4 5 - 15 22 - 5
LL % 24.0 ≤25 ≤30
ATTERBERG
PI % 11.0 ≤10 ≤12
100% 73.0
96Hrs 98% 69.0 ≥80 ≥60
CBR TEST
Soaked 95% 65.0
93% 61.0
20
4.4.2 Aggregates for Pavement Sealing Works
The A. Kanin Quarry, which is close to Bonwire, was chosen. Due to time restrictions, GHA
provided the findings of lab tests performed on samples from the quarry site for evaluation.
The findings demonstrate that the materials adhere to the given requirements. The results
collected are summarized in the table below.
Table 7: Summary test results for 10mm chippings
21
Table 8:Summary test results for 14mm chippings
STATED
TEST RESULTS
SPECIFICATION
BULK DENSITY (Kg/M³ 1.38g/cm^3
Flakiness Index Test Fi
24.20 MAX 35%
Test
Elongation Index 11.40 MAX 30%
Particle Size Distribution (Grading) Refer attachment Refer attachment
Chippings for concrete mix will be sourced from A. Kanin Quarry. Summary of laboratory
results is tabulated below.
22
SIZE: 20mm chippings
TEST RESULTS STATED SPECIFICATION
BULK DENSITY (Kg/M³ 1.36 g/cm^3
Flakiness Index Test Fi
13.29 MAX 35%
Test
Elongation Index 28.12 MAX 30%
Particle Size Distribution (Grading)
refer attachment refer attachment
23
Table 10: Summary test results for river sand
REFERENCE STATED
TEST RESULTS TEST METHOD
SPECIFICATION SPECIFICATION
ORGANIC IMPURITIES
GLASS ≤ GLASS
STANDARD GSSRB STANDARD AASHTO T21
COLOUR NO. 2 COLOUR NO. 3
FINENESS MODULUS
3.36 BS 882 BS 812 - PART 112
24
CHAPTER FIVE
IMPACT
Bore Hole Drilling Noise and Air pollution from Site is location is remote, and
drilling machinery hence noise pollution may have
little or no impact on residents
Holes
Proper serviced machinery was
used to reduce emissions.
25
5.2 BILL OF QUANTITIES
TRIAL PITS
SITE TESTS
SAMPLES
LABORATORY TEST
B712 Atterberg Limits nr 6 150 900
Classification
B714 Particle Size nr 8 150 1200
Distribution
Analysis
B741 Compaction nr 3 250 750
Test
26
B768 Soil Strength by nr 3 400 1200
CBR
PROFESSIONAL SERVICES
B831 Preparation and Lump 200 200
submission of Sum
reports
27
CHAPTER SIX
• Foundation footing should be placed at a depth between (1-3m) from ground surface.
• For other loading otherwise stated, minimum footing sizing should be determined
from graph provided.
• Sub-grade strength was found to be weak, hence need fill material
• At the car par, water was encountered, hence geotextiles should be used before
building the pavement
• Source of natural gravel for road works is the Bonwire borrow pit
• Aggregates for road works and concrete mixes shall be obtained from A.Kanin
Quarry Products.
• River bed Sand for concrete mix shall be sourced from sand pits at Anwomaso
6.2 RECOMMENDATION
• Due to the limited site exploration conducted on the site, required investigations
should be conducted on site on the event of discovery of features not covered in this
report.
• Recommended depth for foundation footing is 2m
• Borrowed materials should be periodically tested to ensure they meet the standard
specifications.
• It must be ensured that pavement surface is properly sealed and drained.
6.3 LIMITATIONS
This report's conclusions are solely based on data supplied by ABP Consult and a little
amount of site exploration and research at the project site per current geotechnical standards.
Investigations must be carried out if aspects not included in this report are found during the
project's construction phase.
28
6.4 DISCLAIMER
This geotechnical site study report was created exclusively for KNUST's development office
for the redevelopment of the college of engineering laboratory's master plan. Any test on the
soil only provides a snapshot of the soil that was being created at the time of the
examination. There is no promise or assurance that soils tested on multiple dates will match
due to differences in nutrients, pH, the composition of soils, the volume of soil generated,
and other variables. In light of the fact that anybody who utilizes this report somewhere other
than the suggested place does so at their own risk and will be held responsible for the results.
29
REFERENCES
Acheampong Aning, A., Addai, E., Sarpong Asare, V.-D., 2016. Application of Shallow
Seismic Refraction and 2D Electrical Resistivity Imaging to Site Investigations.
International Journal of Scientific and Research Publications 6, 357.
Ahulu, S.T., Danuor, S.K., Asiedu, D.K., 2018. Probabilistic seismic hazard assessment of
southern part of Ghana. J Seismol 22, 539–557. https://doi.org/10.1007/s10950-017-
9721-x
Andrews ND, Aning AA, Danuor SK, Noye RM, 2013. Geophysical investigations at the
proposed site of the KNUST teaching Hospital building using the 2D and 3D resistivity
imaging techniques, International Research Journal of Geology and Mining (IRJGM.
30
APPENDICES
Table 13: Pit 1 layer 2 data and results from lab test
31
PIT 1 LAYER 2
30
Plastic limit 1 2
Container No gm A25 C18
Mass of Container gm 3.75 3.73
Mass of Container & Wet
Sample gm 13.44 11.4
32
Mass of Container & Dry
Sample gm 11.94 10.32
Mass of Water gm 1.5 1.08
Mass of Dry Sample gm 8.19 6.59
Water content % 18.32 16.39
Average Water content % 17.4
PIT 1 LAYER 3
30
y = 0.7649x + 1.8106
Penetration depth (mm)
25
20
15
10
0
0 5 10 15 20 25 30 35
Moisture content%
Liquid limit
Container No gm A27 B24 K3 K6 B26
Mass of Container gm 3.58 3.64 3.7 3.73 3.66
LL 22.31
Penetration mm 9.2 12.5 15.6 20 26.8
Mass of Container & Wet
PL 0.00
Sample gm 20.31 34.31 25.16 27.02 38.22
Mass of Container & Dry
PI 0.00
Sample gm 17.57 28.97 21.43 22.75 31.6
Mass of Water gm 2.74 5.34 3.73 4.27 6.62
33
Mass of Dry Sample gm 13.99 25.33 17.73 19.02 27.94
Water content % 19.59 21.08 21.04 22.45 23.69
PIT 2 LAYER 1
30
y = 0.7649x + 1.8106
Penetration depth (mm)
25
20
15
10
0
0 5 10 15 20 25 30 35
Moisture content%
34
PIT 2 LAYER 2
30
y = 0.7649x + 1.8106
Penetration depth (mm)
25
20
15
10
0
0 5 10 15 20 25 30 35
Moisture content%
35
Appendix B Materials for project construction
RIVER SAND
120
100
PERCENTAAGE PASSING %
80
SIEVE SIZE (mm)
60
LOWER
BOUNDARY
40
UPPER BOUNDARY
20
0
0.1 1 10
SIEVE SIZE (mm)
36
Figure 14: Graph of chippings
SIEVE SIZE (mm) 0.075 0.425 2.36 4.75 9.50 19.0 37.0
natural gravel
37
% PASSING BS SIEVE 8 14 37 59 85 97 99
LOWER BOUNDARY 5 8 20 30 45 75 80
UPPER BOUNDARY 22 33 50 75 90 100 100
SIEVE SIZE (mm) River
Sand 0.15 0.3 0.6 1.18 2.36 5 10
98.156
% PASSING BS SIEVE 8 21 40 64 86 95 682
LOWER BOUNDARY 0 5 15 30 60 89 100
UPPER BOUNDARY 15 70 100 100 100 100 100
Penetration DCP 1 CUMM1 BLOWS DCP2 CUMM2 DCP3 CUMM3 DCP4 CUMM4 DCP5 CUMM5 DCP6 CUMM6 DCP7 CUMM7 DCP8 CUMM8 DCP9 CUMM9 DCP10 CUMM10 DCP11 CUMM11 DCP12 CUMM12 DCP13 CUMM13
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
100 1 1 2 2 2 2 2 2 2 2 1 1 2 2 3 3 1 1 2 2 1 1 1 1 1 1
200 2 3 3 5 2 4 4 6 3 5 2 3 3 5 4 7 2 3 2 4 2 3 2 3 1 2
300 1 4 2 7 1 5 2 8 2 7 1 4 2 7 2 9 2 5 3 7 2 5 1 4 1 3
400 1 5 1 8 1 6 3 11 2 9 2 6 1 8 2 11 3 8 2 9 3 8 1 5 2 5
500 1 6 1 9 2 8 2 13 1 10 1 7 1 9 1 12 2 10 3 12 1 9 1 6 2 7
600 2 8 1 10 3 11 2 15 1 11 1 8 1 10 1 13 1 11 2 14 1 10 2 8 2 9
700 2 10 2 12 2 13 3 18 1 12 1 9 2 12 1 14 1 12 1 15 1 11 2 10 1 10
800 2 12 2 14 3 16 4 22 2 14 2 11 1 13 2 16 3 15 1 16 2 13 1 11 2 12
900 2 14 2 16 3 19 2 24 1 15 2 13 1 14 1 17 2 17 2 18 2 15 1 12 1 13
DCP POINTS 1 2 3 4 5 6 7 8 9 10 11 12 13
CBR
LAYERS 1 3 4 4 6 6 4 6 7 5 6 5 3 2
2 5 5 7 8 6 3 3 3 5 3 3 4 4
3 7 4
DCP
POINTS AV.CBR%
1 4.00
2 5.00
3 6.00
4 7.00
38
5 6.00
6 4.00
7 5.00
8 5.00
9 5.00
10 5.00
11 4.00
12 4.00
13 3.00
PERCENTILE%
DCP POINT LAYERS VALUES E% 60
DCP AT
40 CAR
1 2 4 75
PARK
20
2 2 3 0
0
3 2 3 0 0 1 2 3 4 5
AVERAGE CBR VALUES
4 2 3 0
5 2 4 75
39
CAR PARK DCP1 CAR PARK DCP2
Penetration(mm)
200 200
300 300
400 400
500
500
600
600
700
700 800
800 900
900
200 200
300
300
400
400
500
500 600
600 700
700 800
800 900
900
200
300
400
500
600
700
800
900
40
1 2
-200
-100 0 5 10 15
0
0
100 y = 80.124x - 3.7267 y = 57.627x - 8.4746
200
Layer 1 200
300 Layer 2
400
400 y = 47.619x + 92.857
500
y = 50x + 200
600
600 layer
700 y = 36.735x + 208.16
1
800
800
900
1000
1000
3 4
-200
0 5 10 15 20 -200
0 5 10 15 20 25 30
0
y = 64.898x - 20.408 0
200 layer
200
1
400
400
y = 36.885x + 205.74 600 y = 38.532x - 2.7523
600 800
y = 31.795x + 122.05
1000
800
1000
41
0 5 5 10 15 20 6
0
y = 43.233x + 1.1278 Axis Title
200 0 5 10 15
y = 65.789x
0 + 15.789
400 laye…
200 y = 70.588x + 14.706
Axis Title
600 y = 80.124x - 298.14 400
600
800
800
1000 1000
7 -200 8
0 5 10 15 20
0 5 10 15
0
0
y = 41.379x + 5.1724 y = 35x - 10
100
200
200
300
400 400
y = 80.124x - 458.39
500 y = 81.507x - 250
600 600
700
800 800
900
1000 1000
10
9
0 5 10 15 20
0 5 10 15 20 0
0 y = 41.447x + 15.132
100
100 y = 47.097x + 38.065
200
200
300 300
400 400
500 y = 52.941x + 11.765 500 y = 70x - 350
600 600
700 700
800 800
900 900
1000 1000
42
11 12
0 5 10 15 20 -200
0 5 10 15
y0 = 48.544x + 34.951 0
y = 80.124x - 3.7267
200 200
400 400
y = 64.655x + 92.241
y = 70.588x - 126.47
600 600
800
800
1000
1000
0 2 4 6 8 10 12 14
0 13
100 y = 100x
200
300
400
y = 58.961x + 103.05
500
600
700
800
900
1000
43
44
45
15
SOAKED CBR
5.00 14
55 BLOWS
4.50 13
25 BLOWS
4.00 12
10 BLOWS
3.50 11
CBR (%)
3.00
10
LOAD(kN)
2.50
9
2.00
8
1.50
7
1.00
6
0.50
5
0.00 80 82 84 86 88 90 92 94 96 98 100
0.00 2.00 4.00 6.00 8.00 10.00 MDD (%)
PENETRATION(mm)
Pit 1, Layer 2.
2.05
2
MDD=1.986
Maximum dry density(kg/cc)
OMC=10.985
1.95
1.9
1.85
1.8
1.75
1.7
0 2 4 6 8 10 12 14 16
Water content%
46
60
50
40
30
20
10
0
0 10 20 30 40 50 60 70 80 90 100
Liquid Limit (LL or wL)
The best recommendation for a foundation footing for a three-story laboratory building
in a waterlogged area is a pile foundation. Pile foundations are deep foundations that
use long, slender foundation elements (sometimes called piles) to transfer the load
from the building to a more stable stratum. This type of foundation is best suited for
waterlogged areas, as it is designed to penetrate deep into the ground, bypassing the
waterlogged layers and reaching the stable strata below. Pile foundations also provide
good lateral stability, which is especially important for taller structures like a laboratory
buildings.
47
Appendix D - Borehole logs and foundation design details
Borehole No. BH 1
PROJECT NAME: REDEVELOPMENT MAS TER PLAN FOR COE LAB N 6.670608
LOCATION: KNUS T - KUMAS I GPS Coordinates E 1.565231
DRILLING METHOD: Cable Percus s ion Z
EQUIPMENT TYPE/NO. Dando 2500 Logged by: FRANCIS Checked by: Date: 20TH MARCH,2023
Depth (m)
Elevation
Symbol
Ground
Casing
Water Soil Description
Depth
Sample
Ty pe
Sample
No.
Test N-v alue
Comments
0.00 - 0.00
2.91
Moist, loose, greyish, clayey
3.00 - 3.0 3.00
silty SAND 3.00-3.45 3 2
3
5.12-5.57 SS 7 12
DS 8
7.50-7.95 SS 12 9 5
10.50-10.95 SS 15 29 8
13.50-13.95 SS 18 74
DS 19
15.00 - 15.0 15.00
15.00-15.45 SS 20 Refusal
NOTES:
SS Split spoon sample Static groundw ater level
DS Disturbed sample Dynamic groundw ater level
US Undisturbed sample
48
Borehole No. BH3
PROJECT NAME: REDEVELOPMENT MASTER PLAN FOR COE LAB N 6.67065
LOCATION: KNUST - KUMASI GPS Coordinates E 1.564811
DRILLING METHOD: Cable Percussion Z
EQUIPMENT TYPE/NO. Dando 2500 Logged by: FRANCIS Checked by: Date: 20TH MARCH,2023
SOIL SAMPLE SPT
Depth (m)
Depth (m)
Elevation
Symbol
Ground
Casing
Water
Soil Description Sample Sample Comments
Depth Test N-value
Type No.
0.00 - 0.00
4.50-4.95 SS 8 11
7.50-7.95 SS 13 10 5
6
8.00 - 8.0 8.00
49
Borehole No. BH5
PROJECT NAME: REDEVELOPMENT MASTER PLAN FOR COE LAB N 6.670482
LOCATION: KNUST - KUMASI GPS Coordinates E 1.565025
DRILLING METHOD: Cable Percussion Z
EQUIPMENT TYPE/NO. Dando 2500 Logged by: FRANCIS Checked by: Date: 20TH MARCH,2023
Depth (m)
Elevation
Symbol
Ground
Casing
Water
Soil Description Sample Sample Comments
Depth Test N-value
Type No.
0.00 - 0.00
4.50-4.95 SS 8 3
Moist, very soft, brownish grey,
5.00 - 5.0 silty CLAY 5.00
DS 9 2
3
4
7.50-7.95 SS 13 10
Moist, medium, yellowish grey,
8.00 - 8.0 clayey SILT 8.00
DS 14
50
BH1 BH2 BH3 BH4 BH5
SPT SPT SPT SPT SPT
Depth n- Depth n- Depth n- Depth n- Depth n- Average
(m) values (m) values (m) values (m) values (m) values n-value Refusal
1 9 1 12 1 8 1 16 1 2 9 50
2 2 2 3 2 4 2 7 2 4 4 50
3 3 3 4 3 8 3 9 3 14 8 50
5.12 12 4.5 5 4.5 11 4.5 4 4.5 3 7 50
6 8 6 11 6 6 6 12 6 9 9 50
7.5 9 7.5 7 7.5 10 7.5 11 7.5 10 9 50
9 10 10.02 13 9 8 9 12 9 9 10 50
10.86 29 11.07 14 10.5 17 10 16 10 11 17 50
12 59 12 17 38 50
13.5 74 13.5 28 51 50
15 50 15 37 44 50
51
SPT N-value
0 20 40 60 80
0
1
2
3
4
5
6
7
Depth (m)
8
9 BH1
10 BH2
11
BH3
12
Average n-value
13
Refusal
14
BH4
15
BH5
16
B3
52
2 4 1 18 18 0 36 6
3 8 1 19 19 0 55 10
4.5 11 1.5 19 28.5 14.715 68.785 13
6 6 1.5 19 28.5 14.715 82.57 6
7.5 10 1.5 19 28.5 14.715 96.355 10
9 8 2.52 19 47.88 24.7212 119.5138 7
10.5 18 1.05 20 21 10.3005 130.2133 15
B4.
B5
for d=2
B D/B Fd q all(net) (kN/m2) Area (m2) Qall (net) (KN)
1.25 1.600 1.007 257.23 1.5625 401.92
1.3 1.538 1.007 253.33 1.69 428.13
1.4 1.429 1.007 246.45 1.96 483.04
1.5 1.333 1.006 240.55 2.25 541.24
1.6 1.250 1.006 235.45 2.56 602.75
53
1.7 1.176 1.006 230.99 2.89 667.55
1.8 1.111 1.006 227.06 3.24 735.66
1.9 1.053 1.006 223.57 3.61 807.07
2 1.000 1.330 291.59 4 1166.38
2.1 0.952 1.314 284.53 4.41 1254.78
2.2 0.909 1.300 278.20 4.84 1346.50
2.3 0.870 1.287 272.50 5.29 1441.55
2.4 0.833 1.275 267.35 5.76 1539.91
2.5 0.800 1.264 262.66 6.25 1641.60
d=2.5
B D/B Fd q all(net) (kN/m2) Area (m2) Qall(net) (KN)
1.25 2.000 1.008 257.40 1.5625 402.19
1.3 1.923 1.008 253.50 1.69 428.42
1.4 1.786 1.007 246.62 1.96 483.37
1.5 1.667 1.007 240.72 2.25 541.63
1.6 1.563 1.007 235.62 2.56 603.19
1.7 1.471 1.007 231.16 2.89 668.05
1.8 1.389 1.007 227.23 3.24 736.22
1.9 1.316 1.006 223.74 3.61 807.69
2 1.250 1.006 220.62 4 882.46
54
2.1 1.190 1.006 217.81 4.41 960.54
2.2 1.136 1.006 215.27 4.84 1041.91
2.3 1.087 1.006 212.97 5.29 1126.59
2.4 1.042 1.006 210.86 5.76 1214.57
2.5 1.000 1.330 276.37 6.25 1727.31
D=3
B D/B Fd q all(net) (kN/m2) Area (m2) Qall(net) (KN)
1.25 2.400 1.008 257.52 1.5625 402.38
1.3 2.308 1.008 253.63 1.69 428.63
1.4 2.143 1.008 246.74 1.96 483.62
1.5 2.000 1.008 240.85 2.25 541.91
1.6 1.875 1.008 235.75 2.56 603.52
1.7 1.765 1.007 231.29 2.89 668.43
1.8 1.667 1.007 227.36 3.24 736.64
1.9 1.579 1.007 223.87 3.61 808.17
2 1.500 1.007 220.75 4 882.99
2.1 1.429 1.007 217.94 4.41 961.12
2.2 1.364 1.007 215.40 4.84 1042.56
2.3 1.304 1.006 213.10 5.29 1127.29
2.4 1.250 1.006 211.00 5.76 1215.33
2.5 1.200 1.006 209.07 6.25 1306.67
55
1.9 1011.61 807.072 807.69 808.1657752
2 1094.03 1166.376 882.46 882.9917632
2.1 1179.76 1254.778 960.54 961.1218119
2.2 1268.82 1346.504 1041.91 1042.555438
2.3 1361.19 1441.550 1126.59 1127.292218
2.4 1456.88 1539.915 1214.57 1215.331782
2.5 1555.88 1641.596 1727.31 1306.673807
My suggestion for a new road design with a field CBR of 4% and a laboratory CBR of 12% is
to combine soil stabilizing methods with pavement reinforcing methods. While pavement
reinforcement techniques like the use of geotextiles, geogrids, and paving fabric can be used
to strengthen the road surface and increase the laboratory CBR, stabilizing techniques like lime
stabilization, cement stabilization, and bituminous stabilization can be used to improve the
field CBR of the soil. To guarantee that the road surface stays dry and does not get flooded, a
sufficient drainage system should also be provided.
56