L WALL CALCULATION
SL NO PARTICULARS UNIT NUMBER LENGTH BREADTH DEPTH
1 EARTH WORK EXCAVATION
LONG WALL m^3 1 2.5 0.4 0.5
SHORT WALL m^3 1 1 0.4 0.5
TOTAL
2 FOUNDATION AND PLINTH
LONG WALL m^3 1 2.5 0.4 0.8
SHORT WALL m^3 1 1 0.4 0.8
TOTAL
3 BRICK WORK AND SUPER STRUCTURE
LONG WALL m^3 1 2.4 0.3 1.5
SHORT WALL m^3 1 1 0.3 1.5
TOTAL
H WALL CALCULATION
SL NO PARTICULARS UNIT NUMBER LENGTH BREADTH DEPTH
1 EARTH WORK EXCAVATION
LONG WALL m^3 2 5.6 1 0.9
SHORT WALL m^3 1 2.4 1 0.9
TOTAL
2 PCC BED
LONG WALL m^3 2 5.6 1 0.3
SHORT WALL m^3 1 2.4 1 0.3
TOTAL
3 MASONARY IN FOUNDATION(STONE)
FIRST FOOTING
LONG WALL m^3 2 5.3 0.7 0.2
SHORT WALL m^3 1 2.7 0.7 0.2
SECOND FOOTING
LONG WALL m^3 2 5.2 0.6 0.2
SHORT WALL m^3 1 2.8 0.6 0.2
THIRD FOOTING
LONG WALL m^3 2 5.1 0.5 0.2
SHORT WALL m^3 1 2.9 0.5 0.2
TOTAL
4 BRICK WORK IN SUPER STRUCTURE
LONG WALL m^3 2 5 0.4 4.5
SHORT WALL m^3 1 3 0.4 4.5
TOTAL
TOTAL EXPLAINATION
0.5 1X2.5X0.4X0.5X0.5
0.2 1X1X0.4X0.5X0.2
0.7
0.8 1X2.5X0.4X0.8X0.8
0.32 1X1X0.4X0.8X0.32
1.12
1.08 1X2.4X0.3X1.5X1.08
0.45 1X1X0.3X1.5X0.45
1.53
TOTAL EXPLAINATION
10.8 2X5.6X1X0.9X10.8
2.16 1X2.4X1X0.9X2.16
12.46
3.36 2X5.6X1X0.3X3.36
0.72 1X2.4X1X0.3X0.72
4.08
1.486 2X5.3X0.7X0.2X1.486
0.378 2X2.7X0.7X0.2X0.378
1.248 2X5.2X0.6X0.2X1.248
0.336 1X2.8X0.6X0.2X0.336
1.02 2X5.1X0.5X0.2X1.02
0.29 1X2.9X0.5X0.2X0.29
4.756
18 2X5X0.4X4.5X18
5.4 1X3X0.4X4.5X5.4
23.4