Schedules A - R
Schedules A - R
Government of India
&
Roads & Buildings Department, NH Wing
Govt. Of Andhra Pradesh
Vol – X
SCHEDULES
Jan. - 2023
Ministry of Road Transport & Highway Schedule-A
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to
4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Contents
Schedules
C Project Facilities
1. Project Facilities
2. Description of Project Facilities
3. Utilities
4. Rain water harvesting
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to
4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
SCHEDULE-A
1. The Site
(i) Site of the Four Lane Project Highway shall include land, buildings, structures and road
works as described in Annex-I of this Schedule-A.
(ii) The dates of handing over the Right of Way to the Contractor are specified in Annex-
II of this Schedule-A.
(iii) An inventory of the Site including the land, buildings, structures, road works, trees
and any other immovable property on, or attached to, the Site shall be prepared jointly
by the Authority Representative and the Contractor, and such inventory shall form part
of the memorandum referred to in Clause 8.2.(i) of this Agreement.
(iv) The alignment plans of the Project Highway are specified in Annex-III. Alignment
plans have been given for sections where the existing alignment is proposed to be
upgraded. The proposed profile of the Project Highways shall be followed by the
contractor with minimum FRL as indicated in the alignment plan. The Contractor,
however, improve/upgrade the Road Profile as indicated in Annex-III based on
site/design requirement.
(v) The status of the environment clearances obtained or awaited is given in Annex IV.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Annex – I
(Schedule-A)
1. The Site
The existing road from its junction with NH-167A near Kondamodu connecting Rajupalem,
Reddigudem, Sattenapalli, Medikonduru and terminating at its junction with NH-544D near
Perecherla in the state of Andhra Pradesh total 48.985 Km in the state of Andhra Pradesh. The
land carriageway and structures comprising the Site are described below.
2. Land
The Site of the Project Highway comprises the land (existing right of way) as described
below:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
3. Carriageway
The present carriageway of the Project Highway is intermediate to two lane. The type of the
existing pavement is flexible in nature as given below.
4. Major Bridges
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
6. Grade Separators
7. Minor Bridges
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
10. Culverts
Span Arrangement
Existing Type of Formation
Sl. No.
Chainage structure Width-((m)
No. W H
1 244+350 Slab 1 3 2 10
2 246+750 Slab 4 1 1.2 10
3 247+870 Slab 2 1.75 2 10
4 249+500 Slab 1 5 2 10
5 250+150 Slab 3 1.8 2 10
6 251+160 Slab 2 2.4 1.5 10
7 253+620 Slab 1 2 1 6.5
8 256+150 Slab 1 5 2.7 10
9 263+905 Slab 1 5.5 0.75 24.5
10 269+380 Slab 2 1.5 1.2 10
11 270+600 Slab 2 2.2 1 10
12 271+050 Slab 2 1.25 2.85 10
13 272+220 Slab 1 2 0.75 10
14 273+850 Slab 2 1 0.8 10
15 275+990 Slab 2 1.5 1 10
16 280+360 Slab 1 4.6 0.75 7
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Formation
Existing Type of Number of Dia. of Pipe
S. No width –
Chainage Structure Pipes (m) in (m)
L(m)
1 243+300 HPC 1 0.6 10
2 247+200 HPC 1 0.3 10
3 251+810 HPC 1 0.45 10
4 253+100 HPC 1 0.3 12
5 254+420 HPC 1 0.3 12
6 259+650 HPC 1 0.9 12
7 259+840 HPC 2 0.9 7.5
8 260+630 HPC 1 0.3 12
9 260+720 HPC 3 0.9 12
10 261+700 HPC 1 0.9 12
11 277+530 HPC 1 0.6 12
12 279+240 HPC 1 0.3 12
13 284+420 HPC 1 0.9 12
14 286+350 HPC 1 0.3 12
15 287+650 HPC 1 0.6 8
11. Bus Bays - The details of bus bays on the Site are as follows:
S. No. Chainage (km) Length (m) Left Hand Side Right Hand Side
Nil-
-Nil-
13. Road side drains - The details of the roadside drains are as follows:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
16. Bypasses
The details of the existing road sections proposed to be bypassed are as follows:
Chainage (km) Carriageway
S. No. Name of bypass Length
(town) (Km)
From To Width (m) Type
-Nil-
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Annex - II
(Schedule-A)
Dates for providing Right of Way of Construction Zone
The dates on which the Authority shall provide Right of Way to the Contractor on different
stretches of the Site are stated below:
Chainage Date of
Sr. Existing Proposed
Length Providing
No. From To ROW ROW
ROW
1 0+000 0+200 200 15 45
2 0+200 0+890 690 - 45
3 0+890 1+900 1010 - 45
4 1+900 2+920 1020 - 45
5 2+920 4+961 2041 20 45
6 4+961 5+550 589 20 45
7 5+550 7+220 1670 20 45 Proposed
8 7+220 11+800 4580 25 45 RoW
shall be
9 11+800 12+500 700 25 45 handed
over on
10 12+500 15+990 3490 25 45 appointed
11 15+990 17+020 1030 25 45 date
.
12 17+020 20+730 3710 25 45
13 20+730 21+875 1145 15 45
14 21+875 22+150 275 15 45
15 22+150 23+800 1650 15 45
16 23+800 26+500 2700 - 45
17 28+500 29+225 725 - 45
18 29+225 30+185 960 - 45
19 30+185 34+970 4785 - 45
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Chainage Date of
Sr. Existing Proposed
Length Providing
No. From To ROW ROW
ROW
20 34+970 36+450 1480 25 45
21 36+450 37+050 600 25 45
22 37+050 39+050 2000 20 45
23 39+050 39+509 459 25 45
24 39+509 41+294 1785 15 45
25 41+294 42+200 906 25 45
26 42+200 44+300 2100 15 45
27 44+300 44+575 275 15 45
28 44+575 49+046 4471 - 45
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Annex - III
(Schedule-A)
Alignment Plans
The existing alignment of the project Highway shall be modified in the following sections as per
the alignment plan indicated below:
(i) The alignment of the Project Highway is enclosed in alignment plan in digital form.
Finished road level indicated in the alignment plan shall be followed by the contractor as
minimum FRL. In any case, the finished road level of the project highway shall not be less
than those indicated in the alignment plan. The contractor shall, however, improve/upgrade
the road profile as indicated in Annex – III based on the site/design requirement.
(ii) Traffic Signage plan of the Project Highway showing numbers & location of traffic signs
is enclosed. The contractor shall, however, improve/upgrade upon the traffic signage plan
as indicated in Annex-III based on site/design requirement as per IRC: SP: 99 & IRC: 67
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Annex - IV
(Schedule-A)
Environment Clearances
Environment clearance is not required as per new notification of MoEF dated 22.08.2013.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
(Annexure-V)
Schedule-A)
(i) Electrical utilities
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-A
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
SCHEDULE – B
(See Clause 2.1)
Development of the Project Highway shall include construction of the Project Highway
as described in this Schedule-B and in Schedule-C.
Four Laning with paved shoulder shall include the Project Highway as described in
Annex-I of this Schedule-B and in Schedule-C.
The Project Highway shall be designed and constructed in conformity with the
Specifications and Standards specified in Annex-I of Schedule-D.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Annex – I
(Schedule – B)
Description of Four– Laning with paved shoulder
(i) The Project Highway shall follow the existing alignment unless otherwise specified by
the Authority and shown in the alignment plan and profile details specified in Annex-
III of Schedule A. Geometric deficiencies, in the existing horizontal and vertical profiles
shall be corrected as per the prescribed standards for (plan/rolling) terrain to the extent
land is available.
(a) Four-Laning with paved shoulders shall be undertaken. The paved carriageway shall
accordance with the typical cross sections attached in Annex-II of Schedule B.
(b) Except as otherwise provided in this Agreement, but subject to the provisions of
Annex-I of this schedule-B, the width of the paved carriageway shall conform to
clause 2.1 above.
(i) General
Geometric design and general features of the Project Highway shall be in accordance
with Section 2 of the Manual.
The design speed shall be the ruling design speed for plain terrain i.e.100 kmph as per
Manual.
In the following sections, where improvement of the existing road geometrics to the
prescribed standards is not possible, the existing road geometrics shall be improved to
the extent possible within the given right of way and proper road signs and safety
measures shall be provided:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Design Chainage
S. Built-up stretch Length Fully paved
TCS Remarks
No. (Township) (m) shoulders/footpath
From To
1.5m paved
Built-up
1 Anupalem 5+009 5+550 541 shoulders & 2 m TCS -5
Section
footpath cum drain
1.5m paved
Built-up
2 Rajupalem 11+800 12+500 700 shoulders & 2 m TCS -5
Section
footpath cum drain
1.5m paved
Built-up
3 Dhulipalla 22+000 22+500 500 shoulders & 2 m TCS -5
Section
footpath cum drain
1.5m paved
Built-up
4 Kantepudi 36+450 37+050 600 shoulders & 2 m TCS -5
Section
footpath cum drain
1.5m paved
shoulders & 2 m Built-up
5 Beeminenivaripalem 42+200 44+300 2100 TCS -5
footpath cum drain Section
(b) In open country section, paved shoulders and Earthen shoulders to be provided as
under -
(c) Earthen shoulders shall be covered with 150 mm thick compacted layer of granular
material conforming to clause 401 of MoRTH specifications and having soaked CBR
value not less than 30%.
(b) Lateral Clearance: The width of the opening at the underpasses shall be as follows:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
(a) Lateral and vertical clearances at overpasses shall be as per the provision of section
2.11 of the Manual.
(b) Lateral Clearance: The width of the opening at the overpasses shall be as follows:
-Nil-
Chainage
Sr. No. Length TCS
From To
1 0+890 1+400 510 TCS-6
2 1+400 1+420 20 TCS-9
3 1+420 1+850 430 TCS-6
4 4+961 5+009 48 TCS-20
5 5+009 5+550 541 TCS-5
6 11+800 12+500 700 TCS-5
7 15+990 16+410 420 TCS-6
8 16+410 16+430 20 TCS-9
9 16+430 16+844 414 TCS-6
10 16+844 16+889 45 TCS-11
11 16+889 17+020 131 TCS-6
12 22+000 22+500 500 TCS-5
13 27+240 27+600 360 TCS-6
14 27+600 27+640 40 TCS-9
15 27+640 28+000 360 TCS-6
16 29+225 29+647 422 TCS-6
17 29+647 29+677 30 TCS-9
18 29+677 30+185 508 TCS-6
19 36+450 37+050 600 TCS-5
20 42+200 44+300 2100 TCS-5
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Total Length of Service Road for both side is 8199 x 2 = 16398 m. The service road/slip road
length may vary as per site condition and shall be finalized as per provisions of Manual and in
consultation with the Authority Engineer. Increase in service road/slip road length on account
of such variation will not attract Change of Scope. The Entry/Exit ramps for entering into or
existing from the main carriageway to above slip road shall also be provided.
(a) Grade separated structures shall be provided as per paragraph 2.13 of the Manual.
The requisite particulars are given below:
VUPs
Interchange (Trumpet)
Span
S. Design Type of Width of
Proposal Arrangement/ Remarks
No. Chainage Structure Str.
Length
New Viaduct (1x15.0) + Over NH-
1 49+894 2 x 8.5
Construction (PSC) (1x 30.0) 544D
RE Wall
(i) Ramp-1 580 m Length 8.3m
Approach
RE Wall
(ii) Ramp-2 700 m Length 8.3m
Approach
RE Wall
(iii) Ramp-3 940 m Length 8.5m
Approach
RE Wall
(iv) Loop-1 1050 m Length 8.5m
Approach
The Length of service road/slip road/Ramp/Loop may vary as per site condition, FRL etc. and shall
be finalized as per provisions of Manual and in consultation with the Authority’s Engineer. Increase
in length of service road/slip road/Ramp/Loop on account of such variation will not attract Change
of Scope. The Entry/Exit ramps for entering into or existing from the main carriageway to above
slip road shall also be provided.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Proposed typical cross sections adopted for the project highway including Crust
Composition required to be developed in different segments of the project highway are
indicated in Annexure-II.
*The cross-section given in Annex-II table is indicative and stretches may increase
depending upon geometric design by contractor, and this shall not be treated as change
of scope.
* Any increase in FRL and length of approaches indicated in plan layout/detailed drawing
or any other place shall not constitute Change of Scope.
* Any variation in length of TCS as specified in the above table shall not constitute a
Change of Scope, save and except any increase in the length arising out of a change of
scope expressly undertaken in accordance with the provision of Article13.
All intersections and grade separators shall be as per the provision of Section 3 of the
Manual. Existing intersections which are deficient shall be improved to the prescribed
standards.
Properly designed intersections shall be provided at the locations and of the types and
features given in the tables below:
Major Intersections
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Existing Design
Type of Side
S. No. Chainage Chainage Type of Road
intersection (Left/Right/Both)
(km) (km)
NH (Pidigurala
1 - 0+400 T RHS
bypass)
2 241+110 1+410 X MDR-186 BHS
Kondamondu
3 242+380 2+672 Y Bypass End LHS
junction
4 250+405 10+695 T SH-23 RHS
5 256+155 16+445 T MDR-184 RHS
6 263+943 24+233 T - RHS
7 267+330 27+620 T SH-322 BHS
8 269+390 29+680 T MDR-191 BHS
9 273+571 33+861 T - LHS
10 276+357 36+647 T MDR-115 RHS
11 280+005 40+295 T MDR-111 LHS
12 283+195 43+485 T MDR-46 LHS
Perecherla Bypass
13 284+510 45+050 Y RHS
start junction
Minor Intersections
Type of Junction
S. No. Existing Chainage Design Chainage Side
(+, T, Y)
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Type of Junction
S. No. Existing Chainage Design Chainage Side
(+, T, Y)
Grade separated structures shall be provided as per paragraph 2.13 of the Manual. The
requisite particulars are given below:
VUPs
Interchange (Trumpet)
Span
S. Design Type of Width of
Proposal Arrangement/ Remarks
No. Chainage Structure Str.
Length
New Viaduct 1x15.0 + Over NH-
1 49+894 2 x 8.5
Construction (PSC) 1x 30.0 544D
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Span
S. Design Type of Width of
Proposal Arrangement/ Remarks
No. Chainage Structure Str.
Length
RE Wall
(i) Ramp-1 580 m Length 8.3m
Approach
RE Wall
(ii) Ramp-2 700 m Length 8.3m
Approach
RE Wall
(iii) Ramp-3 940 m Length 8.5m
Approach
RE Wall
(iv) Loop-1 1050 m Length 8.5m
Approach
Note:
5. Pavement Design
(i) Pavement design shall be carried out in accordance with Section 5 of the Manual.
Type of pavement for bus bay/truck lay byes shall be Flexible pavement.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Flexible pavement for new pavement or for widening and strengthening of the existing
pavement shall be designed for a minimum design period of 15 years. Stage
construction shall not be permitted.
Not with standing anything to the contrary contained in this Agreement or the Manual,
the Contractor shall design the pavement for design traffic of 70 MSA for the section
from km 0+000 to km 26+000 (LHS), 50 MSA for the section km 26+000 to km 0+000
(RHS) and 50 MSA for the remaining section from km 26+000 to km 49+917 (LHS),
50 MSA for the section km 49+917 to km 26+000 (RHS) or as per the actual traffic,
whichever is higher.
2. DBM with 30% Reclaimed asphalt pavement (RAP) has been considered for design.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Kondamudu – Sattenapalle -
S. No Rigid Pavement Elements
Sattenapalle Perecherla
A For Concrete Panel size of 3.5 m x 4.5 m
1 Pavement Quality Concrete (PQC) 280 280
2 Dry Lean Concrete (DLC) 150 150
3 Granular Subbase (GSB) 150 150
Minimum design traffic for service road shall be 10 million standard axles (MSA) as
per Manual.
The following stretches of the existing road shall be reconstructed; these shall be
designed as new pavement.
Design Chainage
Design Length (Km)
From To
0+000 0+200 0.200
2+920 23+800 20.880
34+970 44+575 9.605
Total Length (Km) 30.685
The following stretches of the existing road shall be realigned. These shall be
designed as new pavement.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
-Nil-
6. Roadside Drainage
Drainage system including surface and subsurface drains for the Project Highway shall
be provided as per Section 6 of the Manual.
Footpath cum RCC covered drain shall be provided at following locations as per cross
section schedule given in Annex-II of Schedule B.
Chainage
Sr. No. Length TCS
From To
1 0+890 1+400 510 TCS-6
2 1+400 1+420 20 TCS-9
3 1+420 1+850 430 TCS-6
4 4+961 5+009 48 TCS-20
5 5+009 5+550 541 TCS-5
6 11+800 12+500 700 TCS-5
7 15+990 16+410 420 TCS-6
8 16+410 16+430 20 TCS-9
9 16+430 16+844 414 TCS-6
10 16+844 16+889 45 TCS-11
11 16+889 17+020 131 TCS-6
12 22+000 22+500 500 TCS-5
13 27+240 27+600 360 TCS-6
14 27+600 27+640 40 TCS-9
15 27+640 28+000 360 TCS-6
16 29+225 29+647 422 TCS-6
17 29+647 29+677 30 TCS-9
18 29+677 30+185 508 TCS-6
19 36+450 37+050 600 TCS-5
20 42+200 44+300 2100 TCS-5
*In the built-up areas wherever the cross roads join the highway the drain slab shall
be kept flush with the pavement level designing the drain slab for traffic loads as per
the relevant IRC codes and Ministry’s specifications by lowering the drain slab top
level. The drains shall be designed with adequate bed slopes and shall be connected
to nearest outfall as decided by the Authority Engineer.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
*Any increase in the length with respect to that specified in this Clause of Schedule
B shall not constitute a Change of Scope, save and except any variations in the length
arising out of a Change of Scope expressly undertaken in accordance with the
provisions of Article 13
7. Design of Structures
(i) General
(a) All bridges, culverts and structures shall be designed and constructed in accordance
with section 7 of the manual and shall conform to the cross-sectional features and
other details specified therein.
(b) Width of the carriageway of new bridges and structures shall be as follows:
Major Bridges
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Minor Bridges
Design
Sr. No. Remark
Chainage (km)
1 4+985 Both Side Footpath
2 16+866 Both Side Footpath
3 48+745 Both Side Footpath
ROBs
Sl. No. Location at km Remark
1 49+644 Both Side Footpath
(e) All Structures (i.e. RoB, VUP, Major bridges, Minor Bridges, culverts etc.) shall be
designed to carry utility services. Provision of water pipeline and, Gas line shall not be
allowed
(f) Cross-section of the new culverts and bridges at deck level for the Project Highway
shall conform to the typical cross-sections given in section 7 of the manual.
(ii) Culverts
(a) Overall width of all culverts shall be equal to the roadway width of the approaches.
The existing culverts at the following locations shall be re-constructed as new culverts:
Span
Type of No. of
S. Existing Design length / Proposed Proposed
Structure Spans/ Proposal
No. Chainage Chainage Pipe Dia. Structure Span
Culverts Pipes
(m)
1 246+750 8+465 Slab 4 REC RCC Slab 1x4
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Span
Type of No. of
Existing Design length / Proposed Proposed
S.No. Structure Spans/ Proposal
Chainage Chainage Pipe Structure Span
Culverts Pipes
Dia.(m)
1 244+350 6+039 Slab 1 REC Box Culvert 1x2x2
2 251+810 13+590 Pipe 1 REC Box Culvert 1x2x2
3 275+990 38+750 Slab 2 REC Box Culvert 1x3x3
4 279+240 41+994 Pipe 1 REC Box Culvert 1x2x2
(c) Additional new culverts shall be constructed as per particulars given in table below:
Span
Type of No. of
S. Existing Design length / Proposed Proposed
Structure Spans/ Proposal
No Chainage Chainage Pipe Dia. Structure Span
Culverts Pipes
(m)
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
*Note- Additional 7 Nos of pipe culvert of size 1x1.2 dia. Shall be provided in ramp & loop,
location of pipe culvert shall be finalized as per site condition in consultation with AE.
Span
Type of No. of
S. Existing Design length / Proposed Proposed
Structure Spans/ Proposal
No Chainage Chainage Pipe Structure Span
Culverts Pipes
Dia. (m)
Box
1 - 1+900 - - - NeC 1x2x2
Culvert
Box
2 - 4+120 - - - NeC 1x2x2
Culvert
Box
3 - 5+650 - - - NeC 1x2x2
Culvert
Box
4 - 17+340 - - - NeC 1x2x2
Culvert
Box
5 - 18+890 - - - NeC 1x2x2
Culvert
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Box
6 - 19+990 - - - NeC 1x2x2
Culvert
Box
7 - 26+530 - - NeC 1x2x2
Culvert
Box
8 - 29+200 - - NeC 1x2x2
Culvert
Box
9 - 33+050 - - NeC 1x2x2
Culvert
Box
10 - 49+145 - - NeC 1x3x3
Culvert
*In addition to above Culverts, cross road culverts shall be provided at the location of
Major junctions/Minor Junctions.
* Any additional requirement of culverts found during the project implement action
stage, the same shall be deemed to be covered within the scope of work.
Existing Chainage
S. No. Design Chainage (km) Type of repair required
(km)
-NIL-
(e) Floor protection works shall be as specified in the relevant IRC Codes and
Specifications.
(iii) Bridges
(i) The existing bridges at the following locations shall be re-constructed as New
Structures:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Existing
S No. Existing Design Proposed Structure
Span Remarks
Chainage Chainage span Width
Arrangement
New bridges at the following locations on the Project Highway shall be constructed.
GADs for the new bridges are attached in the drawings folder.
S
Existing Design Proposed Structure
No. Remark
Chainage Chainage span Width
New Construction of 2 Lane
Bridge with Footpath on
RHS.
1 276+780 39+475 4x16 12.00 m
Existing Bridge on LHS is
to repaired and rehabilitated
MNB
1 240+550 2+033 2x15 2x10.6
(RCC Girder)
MNB
2 263+525 25+306 1x21 2x10.6
(RCC Girder)
MNB
3 264+770 27+050 1x21 2x10.6
(RCC Girder)
MNB RCC
Girder + PSC
4 268+250 31+495 1x33 2x10.6
Girder + RCC
Girder
MNB
5 283+000 45+613 1x20 2x10.6
(RCC Girder)
MNB
6 287+615 48+745 1x20 2x15.3
(RCC Girder)
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Major Bridges
Minor Bridges
-Nil-
-Nil-
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Proposal
Design
S. No. Type of Width of
Chainage Proposal Span Arrangement
Structure Str.
Instrumentation of ROB’s:
The Contractor shall do instrumentation in the Railways super-structure across Railway bridge
portion to ensure and carry out regular monitoring of the heath of bridge to meet its
serviceability and functionality requirement during the construction as well as Defect Liability
Period
(i) Phase -I: Installation of sensors and response monitoring during construction and pre-
stressing.
(ii) Phase-II: Study of performance parameters:
(a) Monitoring during peak summer
(b) Monitoring during peak winter
(c) Global Response Test
(iii) Phase-III: Long-term performance monitoring of bridge:
Monitoring stages for different structural parameter
(a) Temperature measurement through embedded sensors
(b) Strain measurement through embedded V.W/Optical Fiber strain Gauges
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
The grade separated structures shall be provided at the locations and of the type and
length specified in paragraphs 2 & 3 of this Annex-I.
The existing bridges and structures to be repaired/strengthened, and the nature and
extent of repairs /strengthening required is given below:
(a) Bridges
S. Design Span
Remarks
No. Chainage Arrangement
(b) ROB/RUB
Proposal
S. Design
No. Chainage Type of Span
Proposal Width of Str.
Structure Arrangement
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
8. Canal Shifting:
(i) Traffic control devices and road safety works shall be provided in accordance
with the provisions of Section 9 of the Manual.
Traffic signs and pavement markings shall include roadside signs, overhead signs; Kerb
mounted signs of retro reflective reflector and road markings of hot applied thermoplastic
material with glass reflective reflector along the Project Highway shall be as per IRC 67-
& IRC 35 with latest specification and guidelines. The location shall be finalized in
consultation with the Authority Engineer.
(i) Roadside furniture shall be provided in accordance with the provisions of Section
9 of the Manual.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Pedestrian facilities
Built up stretches
5 such as railings, guard As per Schedule D
and intersections
rails, footpath
Pedestrian crossings,
Intersections,
6 Road Studs Major/Minor Bridge, As per Schedule D
ROB and all
structures
Overhead traffic signs shall be provided at the project terminals and major
intersections.
Avenue plantation shall be as per the Manual of Specifications & IRC: SP:21.-2009.
Road Side safety barriers shall be provided at all locations of hazards locations such as
high embankment, road side obstacles, sharp curves, VUP and bridge approaches,
overpasses, ROB and any other locations as per Manual and as identified in
consultation with Authority Engineer during the execution of the project highway.
1. The length of Structures and bridges specified here in above shall be treated as an
approximate assessment. The actual lengths as required on the basis of detailed
investigations shall be determined by the Contractor in accordance with the
Specifications and Standards. Any variations in the lengths specified in this Schedule-
B shall not constitute a Change of Scope, save and except any variations in the length
arising out of a Change of Scope expressly under taken in accordance with the
provisions of Article13.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Annex. -II
(Schedule-B)
Typical Cross Sections for the project highway to be followed is given below: -
Chainage
Sr. No. Length Remark TCS
From To
1 0+000 0+200 200 TCS-1
Kondamodu
2 0+200 0+890 690 TCS-4
Bypass Start
3 0+890 1+400 510 VUP Approach TCS-6
4 1+400 1+420 20 VUP (1X20m) TCS-9
5 1+420 1+850 430 VUP Approach TCS-6
6 1+850 2+018 168 TCS-4
7 2+018 2+048 30 MNB (2X17) TCS-8 (C)
Kondamodu
8 2+048 2+920 872 TCS-4
Bypass End
9 2+920 3+160 240 TCS-1
10 3+160 4+040 880 Existing ROB
11 4+040 4+470 430 TCS-1
Curve
12 4+470 4+625 155 TCS-2
improvement
13 4+625 4+961 336 TCS-3
14 4+961 5+009 48 MNB (2x24) TCS-20
Habitation Both
15 5+009 5+550 541 TCS-5
Side
17 5+550 7+220 1670 TCS-2
18 7+220 7+230 10 MNB (1x10) TCS-8 (C)
19 7+230 11+400 4170 TCS-2
20 11+400 11+800 400 TCS-1
21 11+800 12+500 700 TCS-5
22 12+500 12+975 475 TCS-1
23 12+975 14+350 1374.5 TCS-2
24 14+350 14+365 15 MNB (1x15) TCS-8 (C)
25 14+365 15+990 1625.5 TCS-2
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Curve
56 39+050 39+350 300 TCS-2
improvement
57 39+350 39+443 93 TCS-3
58 39+443 39+507 64 MJB (4x16) TCS-7
59 39+507 41+294 1787 TCS-3
60 41+294 41+306 12 MNB (1x12) TCS-8 (C)
61 41+306 41+700 394 TCS-3
62 41+700 42+200 500 TCS-1
Habitation Both
63 42+200 44+300 2100 TCS-5
Side
64 44+300 44+575 275 TCS-1
Parecherla Bypass
65 44+575 45+603 1028 TCS-4
start
66 45+603 45+623 20 MNB (1x20) TCS-8 (C)
67 45+623 48+300 2677 TCS-4
68 48+300 48+735 435 TCS-10 (A)
69 48+735 48+755 20 MNB (1x20) TCS-10 (C)
70 48+755 49+606 851 TCS-10 (A)
71 49+606 49+682 76 ROB TCS-10 (B)
72 49+682 49+692 10 TCS-14
73 49+692 49+745 53 TCS-15
74 49+745 49+872 127 TCS-13
Trumpet/VUP
75 49+872 49+917 45 TCS-12
(1x15+1x30)
76 49+745 Ramp-1 580 TCS-16
77 49+745 Ramp-2 700 TCS-17
78 49+917 RAMP-3 940 TCS-18
79 49+917 LOOP-1 1050 TCS-19
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
Schedule B-1
The shifting of utilities and felling of trees shall be carried out by the contractor. Details of the
existing utilities have been provided in Annexure-V of Schedule-A.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
(Annexure-I to Schedule-B 1)
Utility Shifting:
Notes:
(i) The type/ spacing / size / specification of poles / towers / lines / cables to be used
in shifting work and shall be as per the guidelines of Utility Owning Department
and it is to be agreed solely between the Contractor and the Utility Owning
Department. No change of scope shall be admissible and no cost shall be paid for
using different type / spacing / size / specification in shifted work in comparison to
those in the existing work or for making any overhead crossings to underground as
per requirement of Utility Owning Department and/or construction of project
highway. The Contractor shall carry out joint inspection with Utility Owning
Department and get the estimates from the Utility Owning Department. The
assistance of the Authority is limited to giving forwarding letter on the proposal of
Contractor to Utility Owning Department whenever asked by the Contractor. The
decision/approval of Utility Owning Department shall be binding on the Contractor
(ii) The supervision charge at the rates / charges applicable of the Utility Owning
Department shall be paid directly by the Authority to the Utility Owning
Department as and when Contractor furnishes demand of Utility Owning
Department along with a copy of estimated cost given by the later.
(iii) The dismantled material/ scrap of existing utility to be shifted / dismantled shall
belong to the Contractor who would be free to dispose- off the dismantled material
as deemed fit by them unless the Contractor is required to deposit the dismantled
material to Utility Owning Department as per the norm and practice and in that
case the amount of credit for dismantled material may be availed by the Contractor
as per estimate agreed between them.
(iv) The utilities shall be handed over after shifting work is completed to Utility Owning
Department to their entire satisfaction. The maintenance liability shall rest with
Utility Owning Department after handing over process is completed as far as utility
shifting works are concerned.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
(Annexure-II to Schedule-B 1)
Scope of Work for Shifting of obstruction existing utilities indicated in Schedule A and Utility
Shifting Relocation Plan is give, below.
a) Erection of 12,570 Mtrs 33KV line over proposed 12.5 Mtrs spun poles with 150Sq.mm
AAA Conductor duly dismantling of existing 12,570Mtrs 33KV line with 100 Sq.mm
AAAC condutor along with poles.
b) Erection of 9300 Mtr 11Kv line over proposed M+6 towers and 4.1 KM over proposed
9.1Mtr PSCC poles with 100Sq.mm AAA Conductor duly dismantling of existing 13.4
km 11KV line with 55 Sq.mm AAAC condutor along with poles.
c) Erection of 142 Nos M+6 towers (14No's -33KV & 128No's -11KV) proposed near
road crossings.
d) Erection of 800Mtr LT3-Ph 5W line with 55Sq.mm AAA Conductor duly dismantling
of existing 800Mtr LT3-Ph 5W line with 34Sq.mm AAA Conductor
e) Erection of 2.550 lt line with LT3cX25+25 cable duly dismantling of existing 1700Mtr
LT cable line.
f) Newly proposed DTRs 19No's: Erection of 19 no's new DTRS (63KVA-1No, 25KVA-
16 No's,15KVA-2No's) along with necessary switch gear arrangements.
g) Shifting of existing DTRs 21No's:100KVA-3No's,63KVA-6No's,15/25KVA DTRs-
12No's along with necessary switch gear arrangements.
a) Erection of 1690Mtrs 33KV line over proposed 11Mtr Spun poles with 150Sq.mm
AAA Conductor duly dismantling of 1.69 KM existing 33KV line with 100 Sq.mm
AAAConductor along with poles
b) Erection of 12950Mtrs 11KV line over proposed 9.1Mtr PSCC poles with 100Sq.mm
AAA Conductor duly dismantling of 12.95 KM existing 11KV line with 55 Sq.mm
AAAConductor along with poles
d) Shifting of 4No's HT serices with 11KV potential & 1No. 33KV service.
e) Shifting of 7No's 25KVA DTRs & 8No's 63/100KVA DTRs with neccesary swicth gear
arrangements.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
(Annexure-II to Schedule-B 1)
3. Km 27+400 to Km 37+800 (Electrical Department Division- Sattenapalli town of
Sattenapalli sub-Division in Narasaraopet Division)
b) Erection of 210mtr 11KV line under 11KV Muppala feeder 70mtr under 11KV B
feeder respectively duly dismantling of 330mtr & 70mtr respectively.
a) Shifting of 6.55KM 11KV line and 0.25KM 6.3KV lines with 100Sqmm Conductor
over proposed 12.5mts Spun Poles.
c) Shifting of 4Nos 1Ph DTRs, 1No.3Ph 63KVA DTR, 4Nos 100KVA DTRs and 4Nos
3Ph 25KVA DTRs duly proposing 2Nos 3Ph 25KVA new DTRs to avoid LT Road
crossings with necessary arrangements.
a) Shifting of 1080Mts,11KV double line over proposed 12.5 mts Spun poles with 100
Sq.mm AAAC and 1200mts,11KV line over 12.5mts Spun poles with 100 Sq.mm
AAAC.
c) Shifting of 320Mts, LT S-Ph,3W line with LTAB Cable of 2Cx16+25 Sq.mm over
proposed Poles
e) Shifting of 2.2KM 33KV line over proposed 12.5mts Spun Poles with 150 Sq.mm
AAAC.
Note for Electrical Utility Shifting: Above mentioned Scope of work for Shifting of obstructing
existing Electrical utilities is indicative and an approximate assessment. Any increase in Scope of work
such as increase in no. of poles/GI Tower/ increase in no. of DTR/ increase in length of Electrical line
etc. from specified scope of work hereabove for Shifting of Existing utilities indicated in Annex-
V of Schedule A shall not constitute any Change of Scope.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-B
(Annexure-II to Schedule-B 1)
B. Scope of Works to be carried out for RWS Utility Shifting Work:
Construction/Shifting/Laying of pipe line for water supply along with all incidental work such as
to provision of Sluice Valve/Air Release Valve, construction of Valve chamber etc. as per the
guidelines of Utility Owning Department and as per their Specification in following section to
done by Contractor:
(42+400 to 48+700)
9 3.4 km (160mm HDPE)
Edga in Medikonduru to Ganesh Temple JG palem
Note for RWS Utility Shifting: The above-mentioned pipe size and length is indicative and may vary in size/
length/specification etc. The type/ spacing/ size/ specification of pipes and other incidental items necessary for
Shifting of Utility shall be as per the guidelines of Utility Owning Department. No change of scope shall be
admissible and no cost shall be paid for using different type / spacing / size / specification for any change in type/
spacing/ size/ specification of pipes mentioned above. The Contractor shall carry out joint inspection with Utility
Owning Department. It may also be noted that all incidental and other work necessary for Shifting of above
mentioned RWS Utility such shall be carried out by Contractor and No change of scope shall be admissible.
The Scope of work for Shifting of all obstructing existing utilities specified in Annexure-II to
Schedule-B 1 is indicative and an approximate assessment. Any increase in Scope of work
from specified hereabove for Shifting of Existing utilities indicated in Annex-V of Schedule A
shall not constitute any Change of Scope.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Ministry of Road Transport & Highway Schedule-C
SCHEDULE - C
(See Clause 2.1)
PROJECT FACILITIES
1. Project Facilities
The Contractor shall construct the Project Facilities in accordance with the provisions of
this Agreement. Such Project Facilities shall include:
a. Toll plaza(s)
b. Roadside furniture
c. Street lighting
d. Pedestrian facilities
e. Landscaping and Tree plantation
f. Rest Areas
g. Truck lay-byes
h. Bus-bays and bus shelters
i. Highway Patrol Unit(s)
j. Crane Services
a) Toll Plaza
Toll plaza shall be provided in accordance with the Manual of Specifications and
Standards as referred in Schedule-D & NHAI/Policy Guidelines /Management of Plaza /
2021 Policy Circular No. 17.5.82 dated 24th May 2021.
Toilet has to be provided at both sides of each toll plaza as per NHAI circular
NHAI/GM/CMII/SBM/Misc/2016/96855 dated 20.03.2017.
Road side furniture shall be provided in accordance with section 9 of the Manual of
Specifications and Standards. The Concrete/Metal Beam Crash Barriers shall be
provided in accordance with the Manual of Specifications and Standards as referred In
Schedule –D.
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its junction with
NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
.
Page C-1
Ministry of Road Transport & Highway Schedule-C
The provision of road side furniture shall be finalized as per Manual of Specifications
and in consultation with the Independent Consultant/Engineer.
Traffic signs and pavement markings shall include roadside signs, overhead signs as per
relevant IRC standards including curb mounted signs and road markings along the
project highway. The design and marking for the project highway shall be as per the
design standard indicated in Schedule –D and the location for various treatments shall be
finalized in consultation with the Independent Engineer. Adequate number of Cat’s eyes
and delineators demarcating the edge lines, lane markings and junctions shall be
provided to ensure safety of pedestrians & traffic.
d) Highway Lighting
Highway lighting shall be provided in accordance with the Manual of Specifications and
Standards as refereed in Schedule-D
e) Pedestrian Facilities
At grade pedestrian crossings shall be provided for all the intersections of cross roads
with service roads and entry exit ramps. At grade pedestrian crossing shall be controlled.
Controlled form of crossing shall be achieved through provision of Zebra Crossings,
whether at signalized intersection or pedestrian actuated signal.
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its junction with
NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
.
Page C-2
Ministry of Road Transport & Highway Schedule-C
Landscaping of the highway shall be provided as per provisions of 4 lane manual (IRC
SP 84 2019)
g) Rest Areas
Design Chainage
S.N. Remarks Side of the road
(km)
-Nil-
Truck Lay bye shall be provided at following locations in accordance with the Manual of
Specifications and Standards as referred in Schedule-D.
Design Chainage
S.N. Remarks Side of the road
(km)
1 6+600 Near Anupalem Both side
Bus Shelters with Extra widening of paved shoulder shall be provided at locations in
accordance with the Manual of Specifications and Standards as referred in Schedule-D
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its junction with
NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
.
Page C-3
Ministry of Road Transport & Highway Schedule-C
Traffic Aid Posts shall be provided at the Toll Plazas in accordance with the Clause
12.10 of the Manual of Specifications and standards as refereed in Schedule-D &
MORTH Circular No. RW/G-23012/01/2019-W&A (Pt. III) dated 09.02.2021.
k) Cranes Services
Vehicle rescue posts shall be provided at the Toll Plaza in accordance with clause
12.12 of the Manual of specifications and standards as referred in Schedule-D &
MORTH Circular No. RW/G-23012/01/2019-W&A (Pt. III) dated 09.02.2021.
3. Utilities
Provision of accommodating utilities has been made over as well as underground within
utility corridor on either side of the Project Highway. Utility ducts in the form of 600
mm diameter NP-4 pipe across the project highway along with inspection box/chamber
at a spacing of 500m shall be provided for crossing of underground utilities in built up
areas and at 200 m interval in urban areas.
4. Rainwater Harvesting
As per Ministry of Environment and Forests Notification, New Delhi dated 14.01.1997
(as amended on 13.01.1998, 05.01.1999 & 6.11.2000) the construction of rain water,
harvesting structure is mandatory in and around water crisis area, notified by the Central
Ground Water Board.
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its junction with
NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
.
Page C-4
Ministry of Road Transport & Highway Schedule-D
SCHEDULE – D
1. Construction
The Contractor shall comply with the Specifications and Standards set forth in
Annex-I of this Schedule -D for construction of the Project Highway.
2. Design Standards
Manual of Specifications and Standards for Four Laning of Highways (IRC: SP:
84-2019), referred to herein as the Manual.
3. Utility Shifting
As regards, the work of utility shifting, the relevant specification, relevant rules,
regulations and acts of Utility Owning Department/agencies shall be applicable.
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its
junction with NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
Ministry of Road Transport & Highway Schedule-D
Annex - I
(Schedule-D)
Clause
S. referred Provision as per Manual
Item Modified Provision
No. in (IRC: SP:84-2019)
Manual
As per manual, minimum
Right of Way (ROW) of 60 m
45 m ROW to be available as
1 Clause 2.3 ROW should be available for
mentioned in schedule-A
development of a 4-lane
highway.
As per Fig.2.2- 4-Lane 1.5 m paved shoulder & 1.0 m
Clause 2.6 Shoulder divided carriageway without earthen shoulder to be
2
& 2.7 Width Service Roads and with adopted as per shown in TCS-
Raised Median 1,2,3 & 4.
Width of 5.5 m width of service road
Service As per Fig.2.6- 4-Lane
road & 2.0 m drain cum
Clause 2.6 Road, Divided Highway with
3 footpath with railing to be
& 2.7 Shoulder Service Roads and with
adopted instead of separator
Width & Raised Median
Drain as per shown in TCS-5
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its
junction with NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
Ministry of Road Transport & Highway Schedule-D
Clause
S. referred Provision as per Manual
Item Modified Provision
No. in (IRC: SP:84-2019)
Manual
Fig. 7.1A & 7.1B Cross- As per highway TCS & ROB
Clause Width of Section of Pipe Culvert &
9 GAD approved by concern
7.3 culverts Box Culvert at Road Level 4-
Lane Divided Highway railway authority
Clause Design
6.2.2. of Speen As per Table 6.1 desirable 65 kmph design speed to be
10
IRC -92- ofLoop design speed is 40 Kmph adopted as mentioned in P&P
2017 Ramps
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its
junction with NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
Ministry of Road Transport & Highway Schedule-D
Clause
S. referred Provision as per Manual
Item Modified Provision
No. in (IRC: SP:84-2019)
Manual
Length &
width of Fig. 12.3 Typical Layout of Layout of Bus Bay as per
11 Fig.12.3
Bus Bay Bus Bay mentioned in P&P.
layout
The provision of IRC-SP:21 are to be followed except that the first row of Avenue
plantation should be 14m away from the centre line of the extreme traffic lane to
allow recovery area for road safety concerns. Following guidelines are to be adhered
to:
a. Provision of chain link fencing barbed-wire fencing, Iron fencing \, individual iron
trees guard fencing with wire mesh/cement/brick guard etc. as per the site
requirement.
(v) Species-Matrix
(Annexure A to F of IRC-SP:21)
a. Details of plant species prescribed according to agro climatic zones in IRC SP-
21-2009.
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its
junction with NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
Ministry of Road Transport & Highway Schedule-D
(xi) Activities schedules for Avenue and median plantation (As per IRC SP-21 Table-5
at Page no 52 & 53
4. Any other activities of operations which are not covered in the annexure will be
carried out as per specification in IRC SP-21.
Upgradation to 4-Lane Configuration of newly declared NH 167AG from its junction with NH-167A near
Kondamodu connecting Rajupalem, Reddigudem, Sattenapalli, Medikonduru and terminating at its
junction with NH-544D near Perecherla in the state of Andhra Pradesh total 48.985 Km
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH‐ 167AG to 4 Lane
with paved shoulder Configuration on EPC Mode in the state of Andhra Pradesh under AnnuaI Plan 2022‐23
Schedule ‐ E
(See Clauses 2.1 and 14.2)
MAINTENANCE REQUIREMENTS
1.Maintenance Requirements
i. The Contractor shall, at all times maintain the Project Highway in accordance with
the provisions of this Agreement, Applicable Laws and Applicable Permits.
ii. The Contractor shall repair or rectify any Defect or deficiency set forth in Paragraph
2 of this Schedule-E with in the time limit specified therein and any failure in this
behalf shall constitute non-fulfilment of the Maintenance obligations by the
Contractor. Upon occurrence of any breach hereunder, the Authority shall be
entitled to effect reduction in monthly lump sum payment as set forth in Clause 14.6
of this Agreement, without prejudice to the rights of the Authority under this
Agreement, including Termination thereof.
iii. All Materials, works and construction operations shall conform to the MORTH
Specifications for Road and Bridge Works, and the relevant IRC publications. Where
the specifications for a work are not given, Good Industry Practice shall be adopted.
[Specify all the relevant documents]
In respect of any Defect or deficiency not specified in Annex - I of this Schedule-E, the
Authority’s Engineer may, in conformity with Good Industry Practice, specify the
permissible limit of deviation or deterioration with reference to the Specifications and
Standards, and any deviation or deterioration beyond the permissible limit shall be
repaired or rectified by the Contractor within the time limit specified by the
Authority’s Engineer.
5.Emergency repairs/restoration
The Contractor shall, through its engineer, undertake a daily visual inspection of the
Project Highway and maintain a record thereof in a register to be kept in such form and
manner as the Authority’s Engineer may specify. Such record shall be kept in safe custody
of the Contractor and shall be open to inspection by the Authority and the Authority’s
Engineer at any time during office hours.
The Contractor shall carry out a detailed pre-monsoon inspection of all bridges, culverts
and drainage system before [1st June] every year in accordance with the guidelines
contained in IRC: SP35. Report of this inspection together with details of proposed
maintenance works as required on the basis of this inspection shall be sent to the
Authority’s Engineer before the [10th June] every year. The Contractor shall complete the
required repairs before the onset of the monsoon and send to the Authority’s Engineer a
compliance report. Post monsoon inspection shall be done by the [30th September] and
the inspection report together with details of any damages observed and proposed action
to remedy the same shall be sent to the Authority’s Engineer.
All damages occurring to the Project Highway on account of a Force Majeure Event or
wilful default, or neglect of the Authority shall be undertaken by the Authority at its own
cost. The Authority may instruct the Contractor to undertake the repairs at the rates
agreed between the Parties.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Annex – I
(Schedule‐E)
Repair/Rectification of Defects and deficiencies
The Contractor shall repair and rectify the Defects and deficiencies specified in this Annex-I of Schedule-E within the time limit set forth in
the table below.
Standards and
Time limit for
Frequency of Tools / References for Maintenance
Level of Service (LOS) Rectification /
Performance Inspection Equipment Inspection and Specifications
Asset Type Repair
Parameter Data Analysis
Desirable Acceptable
< 0.1 % of area
Flexible and subject to MORT&H
Potholes Nil Daily 24-48 hours
Pavement limit of 10 mm Length IRC 82: 2015 and Specification 3004.2
(Pavement of in depth Measurement Unit Distress
MCW, Service < 5 % subject like Scale, Tape, Identification
Road, to limit of 0.5 odometer etc. Manual for Long MORT&H
Cracking Nil Daily 7-15 days
approaches of sqm for any 50 Term Pavement Specification 3004.3
Grade m length Performance
structure, Program, FHWA MORT&H
approaches of Rutting Nil < 5 mm Daily Straight Edge 2003 15 -30 days
Specification 3004.2
connecting (http://www.tfhr
roads, slip Corrugations and Length c.com/pavement/
Nil < 0.1 % of area Daily 2-7 days IRC:82-2015
roads, lay byes Shoving Measurement Unit lttp/reports/0303
etc. as like Scale, Tape, 1/)
applicable) MORT&H
Bleeding Nil < 1 % of area Daily odometer etc. 3-7 days
Specification 3004.4
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Standards and
Time limit for
Frequency of Tools / References for Maintenance
Level of Service (LOS) Rectification /
Performance Inspection Equipment Inspection and Specifications
Asset Type Repair
Parameter Data Analysis
Desirable Acceptable
Standards and
Time limit for
Frequency of Tools / References for Maintenance
Level of Service (LOS) Rectification /
Performance Inspection Equipment Inspection and Specifications
Asset Type Repair
Parameter Data Analysis
Desirable Acceptable
Classification of
Automatic
Pavement
Condition Survey
Equipment
Deflection/ Falling Weight
Annually IRC 115: 2014 180 days IRC:115-2014
Remaining Life Reflectometer
ASTM E950 (98)
Rigid Roughness Class I
2200 mm/km Bi-Annually :2004 and ASTM 180 days IRC: SP:83-2008
Pavement BI 2400 mm/km Profilometer
E1656 -94: 2000
(Pavement of Skid Resistance no. at
MCW, Service different speed of vehicles
Road, Grade Minimum Traffic SCRIM
structure, SN Speed (Sideway-force
approaches of (Km/) Coefficient
connecting Skid Bi-Annually Routine IRC: SP:83-2008 180 days IRC: SP:83-2008
36 50
roads, slip Investigation
33 65
roads, lay byes Machine or
32 80
etc. as equivalent)
applicable) 31 95
31 110
Edge drop at MORT&H
Nil 40mm Daily 7-15 days
shoulders Specification 408.4
<2% variation
in prescribed Length
Slope of MORT&H
Embankment/ Nil slope of Daily Measurement Unit 7-15 days
camber/cross fall IRC Specification 408.4
Slope camber /cross like Scale, Tape,
fall odometer etc.
<15 % variation
Embankment MORT&H
Nil in prescribe Daily 7-15 days
Slopes Specification 408.4
side slope
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Standards and
Time limit for
Frequency of Tools / References for Maintenance
Level of Service (LOS) Rectification /
Performance Inspection Equipment Inspection and Specifications
Asset Type Repair
Parameter Data Analysis
Desirable Acceptable
Embankment MORT&H
Nil Nil Daily NA 7-15 days
Protection Specification
Daily Specially
Rain Cuts/ MORT&H
Nil Nil During Rainy NA 7-15 days
Gullies in slope Specification
Season
In addition to the above performance criterion, the contractor shall strictly maintain the rigid pavements as per requirements in the
following table
Table ‐2: Maintenance Criteria for Rigid Pavements:
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
CRACKING
0 Nil, not discernible
No Action Not applicable
1 w < 0.2 mm. hair cracks
w = 0.2 - 0.5 mm, discernible from
2 Seal, and stitch if L >
slow-moving car
w = width of crack Seal without delay lm.
w = 0.5 - 1.5 mm, discernible from
Single Discrete Cracks Not L = length of crack 3 Within 7days
1 fast-moving car
intersecting with any joint d = depth of crack
D = depth of slab 4 w = 1.5 - 3.0 mm Staple or Dowel Bar
Retrofit, FDR for
Seal, and stitch if L > l m.
affected portion.
5 w > 3 mm. Within 7 days
Within 15days
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
1 w < 0.2 mm, hair cracks Route and seal with Staple or Dowel Bar
w = 0.2 - 0.5 mm, discernible from epoxy. Retrofit.
2
slow vehicle Within 7 days Within 15days
L = length of crack Route, seal and stitch, if L
Diagonal Crack intersecting d = depth of crack w = 0.5 - 3.0 mm, discernible from
3 > 1 m.
with one or more joints D = depth of slab fast vehicle
Within 7 days
Dowel Bar Retrofit. Full Depth Repair
4 w = 3.0 - 6.0 mm
Within 15 days Dismantle and
reconstruct affected.
w > 6 mm, usually associated with Not Applicable, as it may Portion with norms
5 spalling, and/or slab rocking under be full and specifications -
traffic depth See Para 5.5 & 9.2
Within 15days
0 Nil, not discernible No Action
Staple or dowel bar
Seal with epoxy, if L > 1
w < 0.5 mm, discernible from slow retrofit.
1 m.
moving vehicle Within 15days
Within 7 days
Route seal and stitch, if L
w = 0.5 - 3.0 mm, discernible from
2 > l m. -
fast vehicle
Within 15 days
w = width of crack
Single Longitudinal Crack Staple, if L > 1 m.
L = length of crack 3 w = 3.0 - 6.0 mm Partial Depth Repair
3 intersecting with one or more Within 15 days
d = depth of crack with stapling.
joints w = 6.0 - 12.0 mm, usually associated
D = depth of slab 4 Within 15 days
with spalling
Full Depth Repair
Not Applicable, as it may Dismantle and
w > 12 mm, usually associated with be full reconstruct affected
5 spalling, and/or slab rocking under depth portion as per norms
traffic and specifications -
See Para 5.6.4
Within 15 days
4 Multiple Cracks intersecting w = width of crack 0 Nil, not discernible No Action -
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
only) parts.
3 w > 1.5 mm and L < 3 m/m2 Within 15days
w > 3 mm, L < 3 m/m2 and Full depth repair - Cut
4 out and replace
deformation
damaged area taking
w > 3 mm, L > 3 m/m2 and care not to damage
5 reinforcement.
deformation
Within 30days
Surface Defects
Short Term Long Term
0 Nil, not discernible
No action.
1 r<2% Local repair of areas
r = area damaged damaged and liable to be
surface/total 2 r = 2 - 10 % damaged.
Ravelling or Honeycomb type
7 surface of slab (%) Within 15 days
surface Not Applicable
h = maximum 3 r = 10-25% Bonded Inlay, 2 or 3 slabs
depth of damage 4 r = 25 - 50 % if Affecting.Within 30 days
Reconstruct slabs, 4 or
5 r > 50% and h > 25 mm more slabs if affecting.
Within 30 days
Short Term Long Term
0 Nil, not discernible
No action.
1 r<2% Local repair of areas
r = damaged
damaged
surface/total
2 r = 2 - 10 % and liable to be damaged.
8 Scaling surface of slab (%)
Within 7days Not Applicable
h = maximum
3 r = 10 - 20% Bonded Inlay within 15
depth of damage
4 r = 20 - 30 % days
Reconstruct slab within 30
5 r > 30 % and h > 25 mm
days
0
No action.
t = texture depth, 1 t > 1 mm
9 Polished Surface/Glazing Not Applicable
sand patch test 2 t = 1 - 0.6 mm Monitor rate of
3 t = 0.6 - 0.3 mm deterioration
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
4 t = 0.3 - 0.1 mm
Diamond Grinding if
affecting
50% or more slabs in a
5 t < 0.1 mm continuous stretch of
minimum
5 km.
Within 30 days
0 d < 50 mm; h < 25 mm; n < 1 per 5 m2 No action.
d = 50 - 100 mm; h < 50 mm; n < 1 per
1 Partial depth repair 65
5 m2
mm deep.
d = 50 - 100 mm; h > 50 mm; n < 1 per
2 Within 15 days
5 m2
d = 100 - 300 mm; h < 100 mm n < 1 Partial depth repair
3
per 5 m2 110mm
n = number/m2 i.e.10 mm more than the
Popout (Small Hole), Pothole d = diameter d = 100 - 300 mm; h > 100 mm; n < 1 depth
10 4 Not Applicable
Refer Para 8.4 h = maximum per 5 m2 of the hole.
depth Within 30 days
Full depth repair.
Within 30 days
d > 300 mm; h > 100 mm: n > 1 per 5
5
m2
Joint Defects
Short Term Long Term
0 Difficult to discern.
No action.
loss or damage
Discernible, L< 25% but of little
11 Joint Seal Defects L = Length as %
immediate consequence with regard to Not Applicable
total joint length 1 Clean joint, inspect later.
ingress of water or trapping
incompressible material.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
appropriate.
Strengthen subgrade and Within 30days
5 f> 18 mm sub-base by grouting and
raising sunken slab
h = vertical 1 h < 6 mm
14 Blowup or Buckling displacement from 2 h = 6 - 12 mm Install Signs to Warn
normal profile Traffic
3 h = 12 - 25 mm
within 7 days
Full Depth Repair.
4 h > 25 mm
Within 30 days
Replace broken slabs.
5 shattered slabs, ie 4 or more pieces
Within 30 days
0 Not discernible, h < 5 mm
No action.
1 h = 5 - 15 mm
h = negative 2 h = 15-30 mm, Nos <20% joints Install Signs to Warn
vertical Traffic
3 h = 30 - 50 mm
15 Depression displacement from within 7 days Not Applicable
normal profile L Strengthen subgrade.
=length 4 h > 50 mm or > 20% joints Reinstate pavement at
normal level if L < 20 m.
5 h > 100 mm Within 30 days
Short Term Long Term
0 Not discernible. h < 5 mm
h = positive vertical No action.
displacement from 1 h = 5 - 15 mm Follow up.
16 Heave
normal profile. 2 h = 15 - 30 mm, Nos <20% joints Install Signs to Warn scrabble
L = length Traffic
3 h = 30 - 50 mm
within 7 days
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
Drainage
0 not discernible No Action
quantity of fines
Repair cracks and joints Inspect and repair
and water expelled 1 to 2 slight/ occasional Nos < 10%
19 Pumping Without delay. sub-drainage at
through open joints
Lift or jack slab within 30 distressed sections
and cracks Nos 3 to 4 appreciable/ Frequent 10 - 25%
days. and upstream.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Repair Action
S. Measured Degree of
Type of Distress Assessment Rating
No. Parameter Severity For the case d < D/2 For the case d > D/2
Repair distressed
pavement sections.
Nos/100 m stretch 5 abundant, crack development > 25% Strengthen subgrade and
subbase. Replace slab.
Within 30 days
0-2 No discernible problem No action.
Ponding on slabs Blockages observed in drains, but Clean drains etc within 7 Action required to
3 to 4
20 Ponding due to blockage of water flowing days, Follow up stop water damaging
drains Ponding, accumulation of water foundation within 30
5 -do-
observed days.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Table ‐3: Maintenance Criteria for Safety Related Items and Other Furniture Items:
Initial (7 Minimum
days) Threshold level
(TL) & warranty
period required up
to 2 years
Up to 200 80
65
65 - 250 120
100
Above 350 150
100
Initial and Minimum Performance for
Night Visibility under wet condition
(Retro reflectivity):
Initial 7 days Retro reflectivity: 100
mcd/m2/lux
Minimum Threshold Level: 50
mcd/m2/lux
Initial and Minimum performance for As per Within 24 hours IRC:35-2015
Skid Resistance: Annexure-G of
Initial (7days): 55BPN IRC:35-2015
Min. Threshold: 44BPN
*Note: shall be considered under
Skid Resistance Bi-Annually
urban/city traffic condition
encompassing the locations like
pedestrian crossings, bus bay, bus stop,
cycle track intersection delineation,
transverse bar markings etc
Visual with Improvement of IRC:67-2012
Shape and Position as per IRC:67-2012.
video/image shape, in case if 48 hours in case of
Shape and Signboard should be clearly visible for
Road Signs Daily backup shape is damaged. Mandatory Signs,
Position the design speed of the section.
Cautionary and
Relocation as per Informatory Signs
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Bridges Visual
MORT&H
including ROBs Riding quality No pothole in wearing coat on bridge inspection as Repairs to BC or
Daily 15 days Specification
Flyover etc. as or user comfort deck per IRC SP:35- wearing coat
2811
applicable 1990
Repairs to BC on
either side of
Visual expansion joints,
MORT&H
inspection as profile correction
Bumps No bump at expansion joint Daily 15 days Specification
per IRC SP:35- course on approach
3004.2 & 2811.
1990 slab in case of
settlement to
approach embankment
Visual
Bridge -Super User safety inspection and Repairs and IRC: 5-1998,
Structure (condition of No damaged or missing stretch of crash detailed replacement of safety IRC:SP 73-2015
Daily 3days
crash barrier barrier or pedestrian hand railing condition survey barriers as the case and IRC SP: 40-
and guard rail) as per IRC SP: may be 1993.
35-1990.
Detailed All the corroded
Rusted condition survey reinforcement shall IRC SP: 40-1993
Not more than 0.25 sq.m
reinforcement as per IRC SP: need to be thoroughly and MORTH
Bi-Annually 15 days
35-1990 using cleaned from rusting Specification
Spalling of Mobile Bridge and applied with anti- 1600.
Not more than 0.50 sq.m Inspection Unit corrosive coating
concrete
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Detailed
Rainwater condition survey Grouting of deck slab
MORTH
seepage as per IRC SP: at leakage areas,
Leakage - nil Quarterly 1 months specifications
through deck 35-1990 using waterproofing, repairs
2600 & 2700.
slab Mobile Bridge to drainage spouts
Inspection Unit
Detailed
No damage to elastomeric sealant condition survey
MORTH
compound in strip seal expansion joint, as per IRC
Leakage in Replace of seal in specifications
no leakage of rain water through Bi-Annually SP:35-1990 15 days
Expansion joints expansion joint 2600 and IRC SP:
expansion joint in case of buried and using Mobile
40-1993.
asphalt plug and copper strip joint. Bridge
Inspection Unit
Detailed
condition survey
MORTH
Debris and dust as per IRC
Cleaning of expansion specifications
in strip seal No dust or debris in expansion joint gap. Monthly SP:35-1990 3 days
joint gaps thoroughly 2600 and IRC SP:
expansion joint using Mobile
40-1993.
Bridge
Inspection Unit
Cleaning of drainage
spouts thoroughly.
Replacement of
Detailed missing/broken down
No down take pipe missing/broken below condition survey take pipes with a
MORTH
soffit of the deck slab. No silt, debris, as per IRC SP: minimum pipe
Drainage spouts Monthly 3 days specification
clogging of drainage spout collection 35-1990 using extension of 500mm
2700.
chamber. Mobile Bridge below soffit of slab.
Inspection Unit Providing sealant
around the drainage
spout if any leakages
observed.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
In case of failure of
even one bearing on
Detailed
Delamination of bearing reinforcement any pier/abutment, all
condition survey MORTH
not more than 5%, cracking or tearing of the bearings on that
as per IRC SP: specification
Bearings rubber not more than 2 locations per Bi-Annually pier/abutment shall 3 months
35-1990 using 2810 and IRC SP:
side, no rupture of reinforcement or be replaced, in order
Mobile Bridge 40-199.
rubber to get uniform load
Inspection Unit
transfer on to
bearings.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
Condition
survey and
visual
inspection as
per IRC SP:35-
1990 using IRC SP: 40-1993,
Mobile Bridge Suitable protection IRC 83-2014,
Bridge Scouring around Scouring shall not be lower than
Bi-Annually Inspection Unit. works around 1 month MORTH
Foundations foundations maximum scour level for the bridge
In case of pier/abutment specification
doubt, use 2500
Underwater
camera for
inspection of
deep wells in
major Rivers.
Note: Any Structure during the entire contract period which is found that does not complies with all requirements of this Table will be prepared, rehabilitated or
even reconstructed under the scope of the contractor.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh under AnnuaI Plan 2022-23
In addition to above, for hill roads the following provisions for maintenance is also to done.
Hill Roads
Note: For all tables 1 to 5 above, latest BIS & IRC standards (even those not indicated herewith) along with MoRTH specifications shall be
binding for all maintenance activities.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4
Lane with paved shoulder Configuration on EPC Mode in the state of Andhra Pradesh under AnnuaI
Plan 2022-23
Flexible Pavement
(iii) Deterioration in health of trees and bushes Timely watering and treatment
15 (fifteen) days
Damage in approach roads, pedestrian facilities,
truck lay- byes, bus-bays, bus-shelters, cattle
(i)
crossings, [Traffic Aid Posts, Medical Aid Posts] and
service roads
4 (four) hours
(ii) Damaged vehicles or debris on the road
4 (four) hours
(iii) Malfunctioning of the mobile crane
Bridges
(a) Superstructure
(b) Foundations
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG to 4
Lane with paved shoulder Configuration on EPC Mode in the state of Andhra Pradesh under AnnuaI
Plan 2022-23
(e) Joints
(g)Hill Roads
APPLICABLE PERMITS
1. Applicable Permits
(i) The Contractor shall obtain, as required under the Applicable Laws, the
following Applicable Permits:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule – G
(See Clauses 7.1 and 19.2)
Annex‐I
(See Clause 7.1)
Form of Bank Guarantee
WHEREAS:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
conclusive, final and binding on the Bank. The Bank further agrees that the
Authority shall be the sole judge as to whether the Contractor is in default in
due and faithful performance of its obligations during and under the Agreement
and its decision that the Contractor is in default shall be final and binding on the
Bank, notwithstanding any differences between the Authority and the
Contractor, or any dispute between them pending before any court, tribunal,
arbitrators or any other authority or body, or by the discharge of the Contractor
for any reason whatsoever.
3. In order to give effect to this Guarantee, the Authority shall be entitled to act as
if the Bank were the principal debtor and any change in the constitution of the
Contractor and/or the Bank, whether by their absorption with any other body or
corporation or otherwise, shall not in any way or manner affect the liability or
obligation of the Bank under this Guarantee.
4. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its
demand under this Guarantee.
5. The Authority shall have the liberty, without affecting in any manner the liability
of the Bank under this Guarantee, to vary at any time, the terms and conditions
of the Agreement or to extend the time or period for the compliance with,
fulfillment and/ or performance of all or any of the obligations of the Contractor
contained in the Agreement or to postpone for any time, and from time to time,
any of the rights and powers exercisable by the Authority against the Contractor,
and either to enforce or for bear from enforcing any of the terms and conditions
contained in the Agreement and/or the securities available to the Authority, and
the Bank shall not be released from its liability and obligation under these
presents by any exercise by the Authority of the liberty with reference to the
matters aforesaid or by reason of time being given to the Contractor or any other
forbearance, indulgence, act or omission on the part of the Authority or of any
other matter or thing whatsoever which under any law relating to sureties and
guarantors would but for this provision have the effect of releasing the Bank
from its liability and obligation under this Guarantee and the Bank hereby waives
all of its rights under any such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or
security now or which may hereafter be held by the Authority in respect of or
relating to the Agreement or for the fulfillment, compliance and/or performance
of all or any of the obligations of the Contractor under the Agreement.
7. Not with standing anything contained hereinbefore, the liability of the Bank
under this Guarantee is restricted to the Guarantee Amount and this Guarantee
will remain in force for the period specified in paragraph 8 below and unless a
demand or claim in writing is made by the Authority on the Bank under this
Guarantee all rights of the Authority under this Guarantee shall be forfeited and
the Bank shall be relieved from its liabilities here under.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
8. The Guarantee shall cease to be in force and effect on**** $.Unlessademand or
claim under this Guarantee is made in writing before expiry of the Guarantee,
the Bank shall be discharged from its liabilities here under.
9. The Bank undertakes not to revoke this Guarantee during its currency, except
with the previous express con sent of the Authority in writing, and declares and
warrants that it has the power to issue this Guarantee and the undersigned has
full powers to do so on behalf of the Bank.
10. Any notice by way of request, demand or otherwise here under may be sent by
post addressed to the Bank at its above referred branch, which shall be deemed
to have been duly authorised to receive such notice and to effect payment
thereof forthwith, and if sent by post it shall be deemed to have been given at
the time when it ought to have been delivered in due course of post and in
proving such notice, when given by post, it shall be sufficient to prove that the
envelope containing the notice was posted and a certificate signed by an officer
of the Authority that the envelope was so posted shall be conclusive.
11. This Guarantee shall come into force with immediate effect and shall remain in
force and effect for up to the date specified in paragraph 8 above or until it is
released earlier by the Authority pursuant to the provisions of the Agreement.
Signed and sealed this ………. day of ……….., 20……… at
……….. SIGNED, SEALED AND DELIVERED
For and on behalf of the Bank by:
(Signature)
(Name)
(Designation)
(Code Number)
(Address)
NOTES:
(i) The bank guarantee should contain the name, designation and code number of the
officer(s) signing the guarantee.
(ii) The address, telephone number and other details of the head office of the Bank as
well as of issuing branch should be mentioned on the covering letter of issuing
branch.
$Insertdate being 2 (two) years from the date of issuance of this Guarantee (in accordance
with Clause 7.2 of the Agreement).
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Annex – II
(Schedule ‐ G)
(See Clause 19.2)
Annex‐II
WHEREAS:
(A) [name and address of contractor] (hereinafter called the “Contractor") has
executed an agreement (hereinafter called the “Agreement”) with the [name and
address of the authority], (hereinafter called the “Authority”) for the construction
of the Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km
49+917) of NH‐ 167AG to 4 Lane with paved shoulder Configuration on EPC Mode
in the state of Andhra Pradesh through through Engineering procurement &
Construction (EPC) basis. subject to and in accordance with the provisions of the
Agreement
(B) In accordance with Clause19.2 of the Agreement, the Authority shall make to the
Contractor an interest bearing @Bank Rate + 3% advance payment(here in after
called “Advance Payment”)equalto10%(ten percent) of the Contract Price; and
that the Advance Payment shall be made in two installments subject to the
Contractor furnishing an irrevocable and unconditional guarantee by a scheduled
bank for an amount equivalent to 110% (one hundred and ten percent) of such
installment to remain effective till the complete and full repayment of the
installment of the Advance Payment as security for compliance with its obligations
in accordance with the
Agreement.Theamountof{first/second}installmentoftheAdvancePayment is Rs. ------
cr. (Rupees ------ crore) and the amount of this Guarantee is Rs.------- cr. (Rupees --
---- crore) (the “Guarantee Amount”)$.
(C) We,___________________through our branch at____________________ (the
“Bank”) have agreed to furnish this bank guarantee (hereinafter called the
“Guarantee”) for the Guarantee Amount.
NOW, THEREFORE, the Bank hereby, unconditionally and irrevocably, guarantees and
affirms as follows:
1. The Bank hereby unconditionally and irrevocably guarantees the due and faithful
repayment on time of the a foresaid instalment of the Advance Payment under
and in accordance with the Agreement, and agrees and undertakes to pay to the
Authority, upon its mere first written demand, and without any demur,
reservation, recourse, contest or protest, and without any reference to the
Contractor, such sum or sums up to an aggregate sum of the Guarantee Amount
$ The Guarantee Amount should be equivalent to 110% of the value of the applicable
instalment.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
as the Authority shall claim, without the Authority being required to prove or to
show grounds or reasons for its demand and/or for the sum specified therein.
A letter from the Authority, under the hand of an officer not below the rank of
[General Manager in the National Highways Authority of India], that the
Contractor has committed default in the due and faithful performance of all or
any of its obligations for the repayment of the instalment of the Advance
Payment under and in accordance with the Agreement shall be conclusive, final
and binding on the Bank. The Bank further agrees that the Authority shall be the
sole judge as to whether the Contractor is in default in due and faithful
performance of its obligations during and under the Agreement and its decision
that the Contract or is in default shall be final and binding on the Bank,
notwithstanding any differences between the Authority and the Contractor, or
any dispute between them pending before any court, tribunal, arbitrators or any
other authority or body, or by the discharge of the Contractor for any reason
whatsoever.
2. In order to give effect to this Guarantee, the Authority shall be entitled to act as
if the Bank were the principal debtor and any change in the constitution of the
Contractor and/or the Bank, whether by their absorption with any other body or
corporation or otherwise, shall not in any way or manner affect the liability or
obligation of the Bank under this Guarantee.
3. It shall not be necessary, and the Bank hereby waives any necessity, for the
Authority to proceed against the Contractor before presenting to the Bank its
demand under this Guarantee.
4. The Authority shall have the liberty, without affecting in any manner the liability
of the Bank under this Guarantee, to vary at any time, the terms and conditions
of the Advance Payment or to extend the time or period of its repayment or to
postpone for any time, and from time to time, any of the rights and powers
exercisable by the Authority against the Contractor, and either to enforce or
forbear from enforcing any of the terms and conditions contained in
5. the Agreement and/or the securities available to the Authority, and the Bank
shall not be released from its liability and obligation under these presents by any
exercise by the Authority of the liberty with reference to the matters aforesaid
or by reason of time being given to the Contractor or any other for bearance,
indulgence, actor omission on the part of the Authority or of any other matter or
thing whatsoever which under any law relating to sureties and guarantors would
but for this provision have the effect of releasing the Bank from its liability and
obligation under this Guarantee and the Bank hereby waives all of its rights
under any such law.
6. This Guarantee is in addition to and not in substitution of any other guarantee or
security now or which may hereafter be held by the Authority in respect of or
relating to the Advance Payment.
7. Notwithstanding anything contained hereinbefore, the liability of the Bank under
this Guarantee is restricted to the Guarantee Amount and this Guarantee will
remain in force for the period specified in paragraph 8 below and unless a
demand or claim in writing is made by the Authority on the Bank under this
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Guarantee all rights of the Authority under this Guarantee shall be forfeited and
the Bank shall be relieved from its liabilities here under.
$Insert
a date being 90(ninety) days after the end of one year from the date of payment of the
Advance payment to the Contractor (in accordance with Clause 19.2 of the Agreement).
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Project Management Consultancy Services For UP Gradation To 4 Lane Configuration of Newly Declared NH
167AG From Its Junction With NH-167A Near Kondamodu Connecting Rajupalem, Reddigudem, Sattenapalli,
Medikonduru And Terminating At Its Junction With NH-544D Near Perecherla In The State of Andhra Pradesh
Total 49.917Km.
Schedule - H
Weightage in
Percentage
Item percentage to the Stage for payment
weightage
(1) Contract price (3)
(4)
(2)
Schedule - H
Weightage in
Percentage
Item percentage to the Stage for payment
weightage
(1) Contract price (3)
(4)
(2)
Minor
Bridges/Underp B.1-New underpasses/overpasses/EUP/Eco Duct
14.524%
asses/Overpasse
(1) Foundation + Sub Structure: On completion of the foundation
s/EUP/Eco Duct
work including foundations for wing and return walls, abutment, 6.53%
piers upto the abutment/pier cap
Schedule - H
Weightage in
Percentage
Item percentage to the Stage for payment
weightage
(1) Contract price (3)
(4)
(2)
Schedule - H
Weightage in
Percentage
Item percentage to the Stage for payment
weightage
(1) Contract price (3)
(4)
(2)
viaducts if any. (5) Miscellaneous Items like hand rails, crash barriers, road
0.23%
marking etc.)
(6) Wing wall / Return Wall -
(7) Approaches including Retaining wall/Reinforced Earth Wall,
-
stone pitching and protection works.
Schedule - H
Weightage in
Percentage
Item percentage to the Stage for payment
weightage
(1) Contract price (3)
(4)
(2)
B.1- Widening and repair of (i) Foundation: Cost of each ROB/RUB shall be determined on pro rata basis with
(a) ROB respect to the total linear length (m) of the ROBs/RUBs. Payment against foundation
(b) RUB shall be made on prorata basis on completion of a stage i.e. not less than 25% of the
scope of foundation of the ROB/RUB subject to completion of atleast two foundations
of the ROB/RUB.
(1) Foundation -
In case where load testing is required for foundation, the trigger of first payment shall
include load testing also where specified.
(ii) Sub-Structure:. Payment against Substructure shall be made on pro-rata basis on
completion of a stage i.e. not less than 25% of the scope of substructure of the
(2) Sub-structure -
ROB/RUB subject to completion of atleast two sub-structures of abutments/piers upto
abutment/pier cap level of the ROB/RUB.
(4) Wearing Coat (a) in case of ROB - Wearing Coat including (iv) Wearing Coat: Payment shall be made on completion of (a) in case of ROB-
expansion joints complete in all respacts as specified and (b) in wearing coat including expansion joints complete in all respects as specified and (b) in
case of RUB - rigid pavement under RUB including drainage - case of RUB- rigid pavement under RUB including drainage facility complete in all
facility complete in all respacts as specified. respects as specified as specified.
1.3.3
Stage for payment Percentage
Payment Procedure
weightage
(5) Miscellaneous Items like hand rails, crash barriers, road
(v) Miscellaneous: Payments shall be made on completion of all miscellaneous works
marking etc.) 0.23%
like hand rails, crash barriers, road markings etc. complete in all respects as specified.
(6) Wing wall / Return Wall (vi) Wing walls/return walls: Payments shall be made on completion of all wing
-
walls/return walls complete in all respects as specified.
(7) Approaches including Retaining wall/Reinforced Earth Wall, (vii) Approaches: Payments shall be made on completion of both approaches
-
stone pitching and protection works. including stone pitching, protection works, etc. complete in all respects as specified.
B.2- New ROB/RUB (i) Foundation: Cost of each ROB/RUB shall be determined on pro rata basis with
(a) ROB respect to the total linear length (m) of the ROBs/RUBs. Payment against foundation
(b) RUB shall be made on prorata basis on completion of a stage i.e. not less than 25% of the
(1) Foundation scope of foundation of the ROB/RUB subject to completion of atleast two foundations
of the ROB/RUB. In
4.63%
case where load testing is required for foundation, the trigger of first payment shall
include load testing also where specified.
(2) Sub-structure (ii) Sub-Structure:. Payment against Substructure shall be made on pro-rata basis on
completion of a stage i.e. not less than 25% of the scope of substructure of the
2.98%
ROB/RUB subject to completion of atleast two sub-structures of abutments/piers upto
abutment/pier cap level of the ROB/RUB.
(3) Super-structure (including bearings)
(iii) Super-structure: Payment shall be made on pro- rata basis on completion of a
stage i.e. completion of super- structure including bearings of at least one span in all
respects as specified excluding any payment made in pursuance to here in under:
If precast girders/ segments are used, on casting of all such girders and segments for at
least one span and on submission of Indemnity Bond by the Contractor, 40% of the
10.74%
actual cost of such precast girders/segments determined based on SoR prevalent on the
Base date within 30 days of submission of the bill therefor. In case the Contract Price
is lower/ higher than the Estimated Project Cost as per RFP, then the SOR rates shall
be reduced/ increased in the same proportion accordingly. Balance payment shall be
after erection of / launching of these elements as per stage payment stipulations
1.3.3
Stage for payment Percentage
Payment Procedure
weightage
(4) Wearing Coat (a) in case of ROB - Wearing Coat including (iv) Wearing Coat: Payment shall be made on completion of (a) in case of ROB-
expansion joints complete in all respacts as specified and (b) in wearing coat including expansion joints complete in all respects as specified and (b) in
case of RUB - rigid pavement under RUB including drainage 0.66% case of RUB- rigid pavement under RUB including drainage facility complete in all
facility complete in all respacts as specified. respects as specified as specified.
(5) Miscellaneous Items like hand rails, crash barriers, road (v) Miscellaneous: Payments shall be made on completion of all miscellaneous works
marking etc.) 0.02% like hand rails, crash barriers, road markings etc. complete in all respects as specified.
(6) Wing wall / Return Wall (vi) Wing walls/return walls: Payments shall be made on completion of all wing
-
walls/return walls complete in all respects as specified.
(7) Approaches including Retaining wall/Reinforced Earth Wall, (vii) Approaches: Payment shall be made on pro-rata basis on completion of a stage
stone pitching and protection works. i.e. completion of approaches in all respect as specified excluding any payment made
in pursuance to here in under:
If Reinforced Earth Wall is used with Facia Panels/Blocks, on casting of all the Facia
Panels/Blocks of all approaches and on submission of Indemnity Bond by the
23.00% Contractor, 40% of the actual cost of such precast girders/segments determined based
on SoR prevalent on the Base date within 30 days of submission of the bill therefor. In
case the Contract Price is lower/ higher than the Estimated Project Cost as per RFP,
then the SOR rates shall be reduced/ increased in the same proportion accordingly.
Balance payment shall be after erection of / launching of these elements as per stage
payment stipulations
C.1- Widening and repair of Elevated Section / Flyovers / (i) Foundation: Cost of each structure shall be determined on pro rata basis with
Grade Separators respect to the total linear length (m) of the structure. Payment against foundation shall
(1) Foundation be made on pro rata basis on completion of a stage i.e not less than 25% of the scope
of foundation of the structure subject to completion of atleast two foundation of the
- structure.
In case where load testing is required for foundation, the trigger of first payment shall
include load testing also where specified.
1.3.3
Stage for payment Percentage
Payment Procedure
weightage
(2) Sub-structure (ii) Sub-structure: Payment against Sub-structure shall be made on pro-rata basis on
completion of a stage i.e not less than 25% of the scope of sub-structure of structure
-
subject to completion of atleast two sub-structure of abutments/piers upto
abutment/piers cap level of the structure.
(3) Super-structure (including bearing) (iii)Super-structure: Payment shall be made on pro- rata basis on completion of a
stage i.e. completion of super- structure including bearings of at least one span in all
respects as specified excluding any payment made in pursuance to here in under:
If precast girders/ segments are used, on casting of all such girders and segments for at
least one span and on submission of Indemnity Bond by the Contractor, 40% of the
- actual cost of such precast girders/segments determined based on SoR prevalent on the
Base date within 30 days of submission of the bill therefor. In case the Contract Price
is lower/ higher than the Estimated Project Cost as per RFP, then the SOR rates shall
be reduced/ increased in the same proportion accordingly. Balance payment shall be
after erection of / launching of these elements as per stage payment stipulations
(4) Wearing Coat including expansion Joints. (iv) Wearing coat: Payment shall be made on completion of wearing coat including
-
expansion joints complete in all respects as specified.
(5) Miscellaneous Items like hand rails, crash barriers, road (v) Miscellaneouse: Payments shall be made on completion of all miscellaneouse
marking etc.) - works like hand rails, crash barriers, road marking etc. Complete in all respects as
specified.
(6) Wing wall / Return Wall (vi) Wing wall/return walls: Payments shall be made on completion of all wing
-
wall/return walls complete in all respects as specified.
1.3.3
Stage for payment Percentage
Payment Procedure
weightage
(7) Approaches including Retaining wall/Reinforced Earth Wall, (vii) Approaches: Payment shall be made on pro-rata basis on completion of a stage
stone pitching and protection works. i.e. completion of approaches in all respect as specified excluding any payment made
in pursuance to here in under:
If Reinforced Earth Wall is used with Facia Panels/Blocks, on casting of all the Facia
Panels/Blocks of all approaches and on submission of Indemnity Bond by the
- Contractor, 40% of the actual cost of such precast girders/segments determined based
on SoR prevalent on the Base date within 30 days of submission of the bill therefor. In
case the Contract Price is lower/ higher than the Estimated Project Cost as per RFP,
then the SOR rates shall be reduced/ increased in the same proportion accordingly.
Balance payment shall be after erection of / launching of these elements as per stage
payment stipulations
C.2- New Elevated Section / Flyovers / Grade Separators (i) Foundation: Cost of each structure shall be determined on pro rata basis with
(1) Foundation : On complation of the foundation work respect to the total linear length (m) of the structure. Payment against foundation shall
including foundations for wing and return walls, abutments, piers be made on pro rata basis on completion of a stage i.e not less than 25% of the scope
of foundation of the structure subject to completion of atleast two foundation of the
1.55% structure.
In case where load testing is required for foundation, the trigger of first payment shall
include load testing also where specified.
(2) Sub Structure : On completion of the abutments, piers upto (ii) Sub-structure: Payment against Sub-structure shall be made on pro-rata basis on
the abutment/pier cap including wing/return/retaining wall upto completion of a stage i.e not less than 25% of the scope of sub-structure of structure
1.64%
top subject to completion of atleast two sub-structure of abutments/piers upto
abutment/piers cap level of the structure.
1.3.3
Stage for payment Percentage
Payment Procedure
weightage
(3) Super-structure (including bearings) (iii)Super-structure: Payment shall be made on pro- rata basis on completion of a
stage i.e. completion of super- structure including bearings of at least one span in all
respects as specified excluding any payment made in pursuance to here in under:
If precast girders/ segments are used, on casting of all such girders and segments for at
least one span and on submission of Indemnity Bond by the Contractor, 40% of the
1.87% actual cost of such precast girders/segments determined based on SoR prevalent on the
Base date within 30 days of submission of the bill therefor. In case the Contract Price
is lower/ higher than the Estimated Project Cost as per RFP, then the SOR rates shall
be reduced/ increased in the same proportion accordingly. Balance payment shall be
after erection of / launching of these elements as per stage payment stipulations
(4) Wearing Coat including expansion Joints. (iv) Wearing coat: Payment shall be made on completion of wearing coat including
0.34%
expansion joints complete in all respects as specified.
(5) Miscellaneous Items like hand rails, crash barriers, road (v) Miscellaneous: Payments shall be made on completion of all miscellaneouse
marking etc.) 0.11% works like hand rails, crash barriers, road marking etc. Complete in all respects as
specified.
(6) Wing wall / Return Wall (vi) Wing wall/return walls: Payments shall be made on completion of all wing
-
wall/return walls complete in all respects as specified.
(7) Approaches including Retaining wall/Reinforced Earth Wall, (vii) Approaches: Payment shall be made on pro-rata basis on completion of a stage
stone pitching and protection works. i.e. completion of approaches in all respect as specified excluding any payment made
in pursuance to here in under:
If Reinforced Earth Wall is used with Facia Panels/Blocks, on casting of all the Facia
Panels/Blocks of all approaches and on submission of Indemnity Bond by the
39.26% Contractor, 40% of the actual cost of such precast girders/segments determined based
on SoR prevalent on the Base date within 30 days of submission of the bill therefor. In
case the Contract Price is lower/ higher than the Estimated Project Cost as per RFP,
then the SOR rates shall be reduced/ increased in the same proportion accordingly.
Balance payment shall be after erection of / launching of these elements as per stage
payment stipulations
1.3.4
Stage for payment Percentage
Payment Procedure
weightage
Unit of measurement is each completed toll plaza. Payment of each toll
(i) Toll Plaza 14.47% plaza shall be made on pro rata basis with respect to the total of all toll
plazas.
(ii) Road side drains
- 1.5 m wide RCC Covered Drain 9.99% Unit of measurement is linear length in km. Payment shall be made on
- 2.5m wide RCC Covered Drain 13.59% pro rata basis on completion of a stage in a length of not less than 10
(iii) All Road signs, Road markings, Km Stone, safety Devices, W Metal % (ten per cent) of the total length.
13.34%
Beam Crash Barrier, Boundary Pillars Kerb Stone…….
(iv) Project facilities
a) Bus Bays & Bus Shelters 2.93%
b) Truck Lay-Byes 2.64%
c) Other (to be specified)
‐Junction Improvement
Major Junctions 14.87%
Minor Junctions 8.02%
Median Openings 1.45%
‐Footpaths and Separators 3.35%
Payment shall be made on pro rata basis for completed facilities.
‐Electrification
Street lights 4.60%
High Mast Lights 1.14%
‐Toilet Blocks & Highway Nest Mini 0.44%
‐Cable Duct Across the Road 0.76%
-Tubular Steel Railing 5.35%
‐Rain Water Harvesting 0.86%
1.3.4
Stage for payment Percentage
Payment Procedure
weightage
Monthly Payment shall be made for 60 months during Defect and
Liability Period. Cost per activity shall be determined on pro-rata basis
‐Incident Management Service 2.20%
as per its weightage. With reference to total cost of Incident
Management
1.3.4
Stage for payment Percentage
Payment Procedure
weightage
Unit of measurement is as per completed activities. Cost per activity
shall be determined on pro-rate basis as per its weightage with
reference to total cost of EHT line. Payment shall be made for
completed activity. (The average weightage of major
(i) EHT line - activities (only for payment purpose) in shifting work is (i) Erection of
Poles-20%, (ii) Conductor stringing including laying of cable- 30%, (iii)
OTR erection (if involved)-15% and (iv) Charging of line including
dismantling and site clearance-35% (with OTR)
and 50%without OTR)
DRAWINGS
1. Drawings
In compliance of the obligations set forth in Clause 10.2 of this Agreement, the
Contractor shall furnish to the Authority’s Engineer, free of cost, all Drawings
listed in Annex-I of this Schedule-I.
2. Additional Drawings
If the Authority’s Engineer determines that for discharging its duties and
functions under this Agreement, it requires any drawings other than those listed
in Annex-I, it may by notice require the Contractor to prepare and furnish such
drawings forthwith. Upon receiving a requisition to this effect, the Contractor
shall promptly prepare and furnish such drawings to the Authority’s Engineer, as
if such drawings formed part of Annex-I of this Schedule-I.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Annex – I
(Schedule - I)
[Note: The Authority shall describe in this Annex-I, all the Drawings that the
Contractor is required to furnish under Clause 10.2.]
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule ‐ J
(See Clause 10.3 (ii))
PROJECT COMPLETION SCHEDULE
1. Project Completion Schedule
During Construction period, the Contractor shall comply with the
requirements set forth in this Schedule-J for each of the Project Milestones
and the Scheduled Completion Date. Within 15 (fifteen) days of the date of
each Project Milestone, the Contractor shall notify the Authority of such
compliance along with necessary particulars thereof.
2. Project Milestone‐I
i. Project Milestone-I shall occur on the date falling on the 256th [35% of
the Scheduled Construction Period] day from the Appointed Date (the
“Project Milestone- I”).
ii. Prior to the occurrence of Project Milestone-I, the Contractor shall have
commenced construction of the Project Highway and submitted to the
Authority duly and validly prepared Stage Payment Statements for an
amount not less than 10% (ten per cent) of the Contract Price.
3. Project Milestone‐II
i. Project Milestone-II shall occur on the date falling on the 438th [60% of
the Scheduled Construction Period] day from the Appointed Date (the
“Project Milestone- II”).
ii. Prior to the occurrence of Project Milestone-II, the Contractor shall have
continued with construction of the Project Highway and submitted to the
Authority duly and validly prepared Stage Payment Statements for an
amount not less than 35% (thirty five percent) of the Contract Price and
should have started construction of all bridges.
4. Project Milestone‐III
i. Project Milestone-III shall occur on the date falling on the 621st day the [85%
of the Scheduled Construction Period] from the Appointed Date (the “Project
Milestone- III”).
ii. Prior to the occurrence of Project Milestone-III, the Contractor shall have
continued with construction of the Project Highway and submitted to the
Authority duly and validly prepared Stage Payment Statements for an amount
not less than 70% (seventy percent) of the Contract Price and should have
started construction of all project facilities.
5. Scheduled Completion Date
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
i. The Scheduled Completion Date shall occur on the Scheduled Construction
Period day (730th day) from the Appointed Date.
ii. On or before the Scheduled Completion Date, the Contractor shall have
completed construction in accordance with this Agreement.
6. Extension of time
Upon extension of any or all of the aforesaid Project Milestones or the
Scheduled Completion Date, as the case maybe, under and in accordance
with the provisions of this Agreement, the Project Completion Schedule shall
be deemed to have been amended accordingly.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule ‐ K
TESTS ON COMPLETION
The Contractor shall, no later than 30 (thirty) days prior to the likely
completion of construction, notify the Authority’s Engineer and the Authority
of its intent to subject the Project Highway to Tests, and no later than
10(ten) days prior to the actual date of Tests, furnish to the Authority’s
Engineer and the Authority detailed inventory and particulars of all works and
equipment forming part of Works.
The Contract or shall notify the Authority’s Engineer of its readiness to subject
the Project Highway to Tests at any time after 10 (ten) days from the date of
such notice, and upon receipt of such notice, the Authority’s Engineer shall, in
consultation with the Contractor, determine the date and time for each Test and
notify the same to the Authority who may designate its representative to witness
the Tests. The Authority’s Engineer shall there upon conduct the Tests itself or
cause any of the Tests to be conducted in accordance with Article 12 and this
Schedule-K.
2. Tests
i. Visual and physical test: The Authority’s Engineer shall conduct a visual and
physical check of construction to determine that all works and equipment
forming part thereof conform to the provisions of this Agreement. The physical
tests shall include [***].
ii. Riding quality test: Riding quality of each lane of the carriageway shall be
checked with the help of a Network Survey Vehicle (NSV) fitted with latest
equipment’s and the maximum permissible roughness for purposes of this Test
shall be [2,000 (two thousand)] mm for each kilometer.
iii. Tests for bridges: All major and minor bridges shall be subjected to the rebound
hammer and ultrasonic pulse velocity tests, to be conducted in accordance with
the procedure described in Special Report No. 17: 1996 of the IRC Highway
Research Board on Nondestructive Testing Techniques, at two spots in every
span, to be chosen at random by the Authority’s Engineer. Bridges with a span of
15 (fifteen) meters or more shall also be subjected to load testing.
iv. Other tests: The Authority’s Engineer may require the Contractor to carry out or
cause to be carried additional tests, in accordance with Good Industry Practice,
for determining the compliance of the Project Highway with Specifications and
Standards, except tests as specified in clause 5, but shall include measuring the
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
reflectivity of road markings and road signs; and measuring the illumination level
(lux) of lighting using requisite testing equipment.
vi. Safety Audit: The Authority’s Engineer shall carry out, or cause to be carried
out, a safety audit to determine conformity of the Project Highway with the
safety requirements and Good Industry Practice.
All Tests set forth in this Schedule-K shall be conducted by the Authority’s
Engineer or such other agency or person as it may specify in consultation with
the Authority.
4. Completion Certificate
Upon successful completion of Tests, the Authority’s Engineer shall issue the
Completion Certificate in accordance with the provisions of Article 12.
5. The Authority Engineer will carry out tests with following equipment at his own cost
in the presence of contractor’s representative.
The first testing with the help of NSV shall be conducted at the time of issue of
Completion Certificate.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule ‐ L
(See Clause 12.2)
COMPLETION CERTIFICATE
(Signature)
(Name)
(Designation) (Address)
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule ‐ M
(See Clauses 14.6, 15.2 and 19.7)
PAYMENT REDUCTION FOR NON‐COMPLIANCE
1. Payment reduction for non‐compliance with the Maintenance Requirements
Monthly lump sum payments for maintenance shall be reduced in the case of
non-compliance with the Maintenance Requirements set forth in Schedule-E.
(ii) The Authority’s Engineer shall calculate the amount of payment reduction on
the basis of weightage in percentage assigned to non-conforming items as
given in Paragraph2.
S. Item/Defect/Deficiency Percentage
No.
(a) Carriageway/Pavement
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
S. Item/Defect/Deficiency Percentage
No.
(iii) Painting, repairs/replacement kerbs, railings, 5%
parapets, guideposts/crash barriers
For any Defect in a part of one kilometre, the non-conforming length shall
be taken as one kilometre.
Schedule ‐ N
(See Clause 18.1 (i))
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
SELECTION OF AUTHORITY’S ENGINEER
The provisions of the Model Request for Proposal for Selection of Technical
Consultants, issued by the Ministry of Finance in May 2009, or any substitute
thereof shall apply for selection of an experienced firm to discharge the
functions and duties of an Authority’s Engineer.
2. Terms of Reference
The Terms of Reference for the Authority’s Engineer (the “TOR”) shall
substantially conform with Annex 1 to this Schedule N.
Not with standing anything to the contrary contained in this Schedule, the
Authority may in its discretion appoint a government-owned entity as the
Authority’s Engineer; provided that such entity shall be a body corporate having
as one of its primary functions the provision of consulting, advisory and
supervisory services for engineering projects; provided further that a
government-own identity which is owned or controlled by the Authority shall not
be eligible for appointment as Authority’s Engineer.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Annex – I
(Schedule - N)
Annex‐I Terms of Reference for Authority’s Engineer
1. Scope
These Terms of Reference (the “TOR”) for the Authority’s Engineer are being
specified pursuant to the EPC Agreement dated........... (The “Agreement),
which has been entered into between the [name and address of the
Authority] (the “Authority”) and.......... (the “Contractor”)# for Widening of
Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917)
of NH‐ 167AG to 4 Lane with paved shoulder Configuration on EPC
Mode in the state of Andhra Pradesh through EPC basis, and a copy of
which is annexed hereto and marked as Annex-A to form part of this TOR.
# - In case the bid of Authority’s Engineer is invited simultaneously with the bid of EPC
project, then the status of bidding of EPC project only to be indicated
The TOR shall apply to construction and maintenance of the Project Highway.
i. The words and expressions beginning with or in capital letters and not
defined herein but defined in the Agreement shall have, unless
repugnant to the context, the meaning respectively assigned to them
in the Agreement.
ii. References to Articles, Clauses and Schedules in this TOR shall, except
where the context otherwise requires, be deemed to be references to
the Articles, Clauses and Schedules of the Agreement, and references
to Paragraphs shall be deemed to be references to Paragraphs of this
TOR.
3. General
The Authority’s Engineer shall discharge its duties in a fair, impartial and
efficient manner, consistent with the highest standards of professional
integrity and Good Industry Practice.
The Authority’s Engineer shall perform the duties and exercise the authority
in accordance with the provisions of this Agreement, but subject to obtaining
prior written approval of the Authority before determining:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
a. any Time Extension;
e. Any other matter which is not specified in (a), (b), (c) or (d) above and which
creates a financial liability on either Party.
The Authority’s Engineer shall submit regular periodic reports, at least once
every month, to the Authority in respect of its duties and functions under this
Agreement. Such reports shall be submitted by the Authority’s Engineer
within 10 (ten) days of the beginning of every month.
The Authority’s Engineer shall inform the Contractor of any delegation of its
duties and responsibilities to its suitably qualified and experienced
personnel; provided, however, that it shall not delegate the authority to
refer any matter for the Authority’s prior approval in accordance with the
provisions of Clause 18.2.
The Authority’s Engineer shall aid and advise the Authority on any proposal
for Change of Scope under Article 13.
In the event of any disagreement between the Parties regarding the meaning,
scope and nature of Good Industry Practice, as set forth in any provision of
the Agreement, the Authority’s Engineer shall specify such meaning, scope
and nature by issuing a reasoned written statement relying on good industry
practice and authentic literature.
4. Construction Period
During the Construction Period, the Authority’s Engineer shall review and
approve the Drawings furnished by the Contractor along with supporting data,
including the geo-technical and hydrological investigations, characteristics of
materials from borrow areas and quarry sites, topographical surveys, and the
recommendations of the Safety Consultant in accordance with the provisions
of Clause 10.1 (vi). The Authority’s Engineer shall complete such review and
approval and send its observations to the Authority and the Contractor within
15 (fifteen) days of receipt of such Drawings; provided, however that in case
of a Major Bridge or Structure, the aforesaid period of 15 (fifteen) days may
be extended up to 30 (thirty) days. In particular, such comments shall specify
the conformity or otherwise of such Drawings with the Scope of the Project
and Specifications and Standards.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
The Authority’s Engineer shall review and approve any revised Drawings sent
to it by the Contractor and furnish its comments within 10 (ten) days of
receiving such Drawings.
The Authority’s Engineer shall review and approve the Quality Assurance Plan
submitted by the Contractor and shall convey its comments to the Contractor
within a period of 21 (twenty one) days stating the modifications, if any,
required thereto.
The Authority’s Engineer shall complete the review and approve of the
methodology proposed to be adopted by the Contract o for executing the
Works, and convey its comments to the Contractor within a period of 10 (ten)
days from the date of receipt of the proposed methodology from the
Contractor.
The Authority’s Engineer shall review the monthly progress report furnished
by the Contractor and send its comments thereon to the Authority and the
Contractor within 7 (seven) days of receipt of such report.
The Authority’s Engineer shall inspect the Construction Works and the Project
Highway and shall submit a monthly Inspection Report bringing out the results
of inspections and the remedial action taken by the Contractor in respect of
Defects or deficiencies .In particular, the Authority’s Engineer shall include
in its Inspection Report, the compliance of the recommendations made by
the Safety Consultant.
For determining that the Works conform to Specifications and Standards, the
Authority’s Engineer shall require the Contractor to carry out, or cause to be
carried out, tests at such time and frequency and in such manner as specified
in the Agreement and in accordance with Good Industry Practice for quality
assurance. For purposes of this Paragraph 4 (ix), the tests specified in the IRC
Special Publication-11 (Handbook of Quality Control for Construction of Roads
and Runways) and the Specifications for Road and Bridge Works issued by
MORTH (the “Quality Control Manuals”) or any modification/substitution
thereof shall be deemed to be tests conforming to Good Industry Practice for
quality assurance.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
The Authority’s Engineer shall test check at least 50 (fifty) percent of the
quantity or number of tests prescribed for each category or type of test for
quality control by the Contractor.
The timing of tests referred to in Paragraph 4 (ix), and the criteria for
acceptance/ rejection of their results shall be determined by the Authority’s
Engineer in accordance with the Quality Control Manuals. The tests shall be
undertaken on a random sample basis and shall be in addition to, and
independent of, the tests that maybe carried out by the Contractor for its
own quality assurance in accordance with Good Industry Practice.
In the event that results of any tests conducted under Clause 11.10 establish
any Defects or deficiencies in the Works, the Authority’s Engineer shall
require the Contractor to carry out remedial measures.
The Authority’s Engineer may instruct the Contractor to execute any work
which is urgently required for the safety of the Project Highway, whether
because of an accident, unforeseeable even to otherwise; provided that in
case of any work required on account of a Force Majeure Event, the
provisions of Clause 21.6 shall apply.
In the event that the Contractor fails to achieve any of the Project
Milestones, the Authority’s Engineer shall undertake a review of the progress
of construction and identify potential delays, if any. If the Authority’s
Engineer shall determine that completion of the Project Highway is not
feasible within the time specified in the Agreement, it shall require the
Contractor to indicate within 15 (fifteen) days the steps proposed to be taken
to expedite progress, and the period within which the Project Completion
Date shall be achieved. Upon receipt of a report from the Contractor, the
Authority’s Engineer shall review the same and send its comments to the
Authority and the Contractor forthwith.
The Authority’s Engineer shall obtain from the Contractor a copy of all the
Contractor’s quality control records and documents before the Completion
Certificate is issued pursuant to Clause12.2.
In the event that the Contractor carries out any remedial measures to secure
the safety of suspended works and Users, and requires the Authority’s
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Engineer to inspect such works, the Authority’s Engineer shall inspect the
suspended works within 3 (three) days of receiving such notice, and make a
report to the Authority forthwith, recommending whether or not such
suspension may be revoked by the Authority.
The Authority’s Engineer shall carry out, or cause to be carried out, all the
Tests specified in Schedule-K and issue a Completion Certificate, as the case
maybe. For carrying out its functions under thisParagraph4 (xviii) and all
matters incidental thereto, the Authority’s Engineer shall act under and in
accordance with the provisions of Article 12 and Schedule-K.
5. Maintenance Period
The Authority’s Engineer shall aid and advise the Contractor in the
preparation of its monthly Maintenance Programme and for this purpose carry
out a joint monthly inspection with the Contractor.
The Authority’s Engineer shall specify the tests, if any, that the Contractor
shall carry out, or cause to be carried out, for the purpose of determining
that the Project Highway is in conformity with the Maintenance
Requirements. It shall monitor and review the results of such tests and the
remedial measures, if any, taken by the Contractor in this behalf.
The Authority’s Engineer shall examine the request of the Contractor for
closure of any lane(s) of the Project Highway for undertaking
maintenance/repair thereof, and shall grant permission with such
modifications, as it may deem necessary, within 5 (five) days of receiving a
request from the Contractor. Upon expiry of the permitted period of closure,
the Authority’s Engineer shall monitor the reopening of such lane(s), and in
case of delay, determine the Damages payable by the Contractor to the
Authority under Clause14.5.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
The Authority’s Engineer shall determine the costs, and/or their
reasonableness, that are required to be determined by it under the
Agreement.
The Authority’s Engineer shall determine the period of Time Extension that is
required to be determined by it under the Agreement.
7. Payments
The Authority’s Engineer shall withhold payments for the affected works for
which the Contractor fails to revise and resubmit the Drawings to the
Authority’s Engineer in accordance with the provisions of Clause 10.2 (iv) (d).
The Authority’s Engineer shall certify final payment within 30 (thirty) days of
the receipt of the final payment statement of Maintenance in accordance
with the provisions of Clause 19.16.
The Authority’s Engineer shall perform all other duties and functions as specified in the
Agreement.
9. Miscellaneous
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
A copy of all communications, comments, instructions, Drawings or
Documents sent by the Authority’s Engineer to the Contractor pursuant to
this TOR, and a copy of all the test results with comments of the Authority’s
Engineer thereon, shall be furnished by the Authority’s Engineer to the
Authority forthwith.
The Authority’s Engineer shall retain at least one copy each of all Drawings
and Documents received by it, including ‘as-built’ Drawings, and keep them
in its safe custody.
The Authority’s Engineer shall inform the Authority and the Contractor of any
event of Contractor’s Default within one week of its occurrence
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule ‐ O
(See Clauses 19.4 (i), 19.6 (i), and 19.8 (i))
FORMS OF PAYMENT STATEMENTS
1. Stage Payment Statement for Works
a) the estimated amount for the Works executed in accordance with Clause
19.3 (i) subsequent to the last claim;
f) Deductions:
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
c) Net payment for maintenance due, (a) minus(b);
Note: The Contractor shall submit its claims in a form acceptable to the Authority.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule ‐ P
(See Clause 20.1)
INSURANCE
The Contractor shall effect and maintain at its own cost, from the Appointed
Date till the date of issue of the Completion Certificate, the following
insurancesforanylossordamageoccurringonaccountofNonPoliticalEvent of Force
Majeure, malicious act, accidental damage, explosion, fire and terrorism:
a) insurance of Works, Plant and Materials and an additional sum of [15 (fifteen)]
per cent of such replacement cost to cover any additional costs of and incidental
to the rectification of loss or damage including professional fees and the cost of
demolishing and removing any part of the Works and of removing debris of
whatsoever nature; and
b) Insurance for the Contractor's equipment and Documents brought onto the Site
by the Contractor, for a sum sufficient to provide for their replacement at the
Site.
The insurance under sub para (a) and (b) of paragraph 1(i) above shall cover the
Authority and the Contractor against all loss or damage from any cause arising
under paragraph 1.1 other than risks which are not insurable at commercial
terms.
The Contractor shall effect and maintain insurance cover of not less than 15% of
the Contract Price for the Works from the date of issue of the Completion
Certificate until the end of the Defects Liability Period for any loss or damage
for which the Contractor is liable and which arises from a cause occurring prior
to the issue of the Completion Certificate. The Contractor shall also maintain
other insurances for maximum sums as may be required under the Applicable
Laws and in accordance with Good Industry Practice.
The Contractor shall insure against its liability for any loss, damage, death or
bodily injury, or damage to any property (except things insured under Paragraphs
1 and 2 of this Schedule or to any person (except persons insured under Clause
20.9), which may arise out of the Contractor's performance of this Agreement.
This insurance shall be for a limit per occurrence of not less than the amount
stated below with no limit on the number of occurrences.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
The insurance shall be extended to cover liability for all loss and damage to the
Authority's property arising out of the Contractor’s performance of this
Agreement excluding:
The insurance under paragraphs 1 to 3 above shall be in the joint names of the
Contractor and the Authority.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule‐Q
Riding quality test: Riding quality of each lane of the carriageway shall be
checked with the help of a calibrated bump integrator and the maximum
permissible roughness for purposes of this Test shall be [2,200 (two
thousand and two hundred only)] mm for each kilometre.
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
Schedule‐R
(Signature)
Widening of Kondamodu to Perecherla Section (Design Ch. Km 0+00 to Km 49+917) of NH- 167AG
to 4 Lane with paved shoulder Configuration on EPC Mode
The project includes provisions for Light Vehicular Underpasses (LVUP), aimed to facilitate smooth cross traffic flow. However, the document specifies that there are no designated locations (-Nil-) for such light vehicular crossings at the moment . This indicates a future scope for including these crossings based on evolving traffic assessments.
Completion and payment for bridge substructures follow a stage-based approach where payments are made on completion of different stages of the work. Payment is made on a pro-rata basis upon completing at least 25% of the foundation and substructure work for each bridge, including up to the abutment/pier cap level of at least two foundations. Where load testing is required, the first payment is triggered by the completion that includes this testing . Furthermore, stage payment statements must reflect the estimated amounts for works executed, adjusted for scope changes and price variations, leading to a net claim after necessary deductions . Completion is certified through a series of tests managed by the Authority’s Engineer, who ensures that construction complies with standards and provisions of the agreement before issuing a Completion Certificate .
Hazardous locations in the project scope are addressed by providing safety barriers at identified risk spots. These include areas with high embankments, roadside obstacles, sharp curves, vehicular underpasses (VUP), bridge approaches, overpasses, and railway overbridges (ROB). The provision of these safety barriers is guided by the Manual and finalized in consultation with the Authority Engineer during project execution . Additionally, all intersections and grade separators are to be designed and constructed as per specified standards to ensure safety and functionality . Furthermore, regular safety audits are conducted to ensure conformity with established safety requirements .
Payment for wearing coats in the project is made upon completion of the wearing coat, including expansion joints, in all respects as specified. This payment is processed after submission by the contractor within 30 days of the bill submission and proportionate SoR rates adjustments if the contract price varies from the estimated project cost as per RFP .
The Authority's Engineer plays a critical role in reviewing and approving various submissions from the Contractor, such as Drawings and Quality Assurance Plans, ensuring they conform to project specifications and standards within specified timelines . They oversee quality control by requiring tests and inspections of construction works to be conducted, specifying the frequency and methods according to industry standards . Additionally, the Engineer handles approval processes for construction methodologies, manages traffic flows during construction, and inspects the site to identify defects and recommend remedial actions . They also conduct audits to ensure compliance with environmental and safety requirements .
The manual specifies providing grade-separated structures according to paragraph 2.13 of the Manual. Span arrangements for these structures include: - Vehicular Underpass (VUP) at design chainage 1+410 and 16+420 with a span arrangement of 1x20.0 and 2x10.6 meters on the Kondamodu Bypass and the existing alignment, respectively. - Another VUP at design chainage 27+620 with a span arrangement of 2x20.0 and 2x10.6 meters on the Sattenpalli Bypass. - A Major Bridge Cum VUP at chainage 29+662 with a span of 1x30.0 and 2x10.6 meters. - A Viaduct (PSC) at an interchange at chainage 49+894 spans 1x15.0 + 1x30.0 with a width of 2x8.5 meters . They must follow specifications such as the Ministry’s Type Design of Intersections detailed in IRC: SP: 84-2019 .
The Authority's Engineer is required to recommend the suspension of the whole or part of the works if the continuation of the work threatens the safety of users and pedestrians . To revoke such suspensions, once the Contractor has carried out remedial measures, the Authority's Engineer must inspect the remedial measures and report to the Authority recommending whether the suspension may be revoked . This inspection must take place within three days of the Contractor's request for inspection following the completion of remedial measures, and a report should be made to the Authority forthwith .
The structural elements defined for rigid pavement in the Kondamodu to Perecherla road widening project include the construction of rigid pavement specifically at the toll plaza locations . The rest of the project utilizes flexible pavement for areas such as bus bays/truck lay-byes, road widening, realignment, strengthening, and service roads . Rigid pavements are also designed to adhere to specified standards and requirements for design traffic and minimum thickness, although these details pertain predominantly to flexible pavements over other sections .