FMPRV41 Pressure Reducing Valve Manual
FMPRV41 Pressure Reducing Valve Manual
1. Preface .................................................................................1
8. Troubleshooting ..................................................................28
FMPRV41 1
2.3 Hazardous environment and media:
The product has to be protected from hazardous environment and check to ensure that no
hazardous liquids or gases pass through the product.
2.4 Depressurizing of systems and normalizing of temperature:
Ensure isolation and safety venting of any pressure to the atmospheric pressure. Even if the
pressure gauge indicates zero, do not make an assumption that the system has been
depressurized.
To avoid danger of burns allow temperature to normalize after isolation.
2.5 Tools and consumables:
Ensure you have appropriate tools and / or consumables available before starting the work.
Use of original Forbes Marshall replacement parts is recommended.
2.6 Protective clothing:
Consider for the requirement of any protective clothing for you/ or others in the vicinity for
protection against hazards of temperature (high or low), chemicals, radiation, dangers to
eyes and face, noise and falling objects.
2.7 Permits to work:
All work to be carried out under supervision of a competent person. Training should be
imparted to operating personnel on correct usage of product as per Installation and
Maintenance instruction. “Permit to work” to be complied with (wherever applicable), in
case of absence of this system a responsible person should have complete information and
knowledge on what work is going on and where required, arrange to have an assistant with
his primary goal and responsibility being safety. “Warning Notices” should be posted
wherever necessary.
2.8 Handling:
There is a risk of injury if heavy products are handled manually. Analyze the risk and use
appropriate handling method by taking into consideration the task, individual, the working
environment and the load.
2.9 Freezing:
Provision should be made to protect systems which are not self-draining, against frost
damage (in environment where they may be exposed to temperatures below freezing point)
to be made.
2.10 Returning products:
Customers and Stockist are reminded that, when returning products to Forbes Marshall they
must provide information on any hazards and the precautions to be taken due to
contamination residues or mechanical damage which may present a health, safety or
environmental risk.
This information must be provided in writing including Health and Safety data sheets
relating to any substances identified as hazardous or potentially hazardous.
200
150
Steam F
100 saturation
curve
50
G C E
0 5 10 15 17 20
Pressure bar g
The product must not be used in this region.
KV Values
The Kv values are full capacities and should be used for safety valve sizing purpose
only
SIZE DN15 DN20 DN25 DN40 DN50
KV 2.8 5.5 8.1 17 28
For conversion Cv (UK)=Kv x 0.963
Cv (US)=Kv x 1.156
FMPRV41 3
Figure 1: Forbes Marshall Pilot Oprated Presure Reducing valve - FMPRV41 steam.
FMPRV41 5
3.6 Product Dimension and Drawing:
Dimensions (approx.) in mm
FMPRV41 (Steam)
Size Screwed A Flanged A1 B D E
M
DN15 160 ..... 181 410 130
DN15 LC 160 ..... 181 410 130
DN20 160 ..... 181 410 130
DN25 180 ..... 203 430 144
DN40 ..... 212 251 450 149
DN50 ..... 232 251 480 174
FMPRV41 STEAM
FMPRV41 (Air)
Size Screwed A Flanged A1 B D E
DN15 160 ..... 181 360 130
DN15 LC 160 ..... 181 360 130
DN20 160 ..... 181 360 130
DN25 180 ..... 203 383 144
DN40 ..... 212 251 415 149
DN50 ..... 232 251 415 174
FMPRV41 AIR
FMPRV41 7
3.6.2. How to Use the Chart: (for air application)
Capacities are given in cubic decimeters of free air per second (dm3/s). The use of
the capacity chart can be best explained by an example.
Required, a valve to pass 100dm3/s of free air reducing from 12 bar g to 8 bar g.
Find the point at which the curved 12 bar g upstream pressure line crosses the
horizontal 8 bar g downstream pressure line. A perpendicular dropped
from this point shows that, a DN15 valve will pass approximately 120 dm3/s under these
conditions and is the correct valve size to choose.
KV Values
The Kv values are full capacities and should be used for safety valve
sizing purpose only.
SIZE DN15 DN20 DN25 DN40 DN50
KV 2.8 5.5 8.1 17 28
For conversion Cv (UK)=Kv x 0.963
Cv (US)=Kv x 1.156
Compressed Air Capacity Chart
Downstream pressure bar g
FMPRV41 9
5. Installation Guidelines:
Note: Before implementing any installations observe the 'Important Safety notes” in
section 2. Referring to the Installation and Maintenance Instructions, name-plate and
Technical Information Sheet, check that the product is suitable for the intended
installation.
5.1 Fitting:
The valve should always be fitted in a horizontal pipeline with the main diaphragm chamber
below the line (figure 7). To meet the high capacities or widely varying loads or where stand-
by facility is required, two or more valves may be used in parallel (figure 6). For pressure turn
down in excess of 10 to 1 consideration should be given to using the two valves in series. To
avoid turbulence between the two pressure reducing valves, the distance must be
equivalent to atleast 50 pipe diameters. To ensure adequate drainage of the space between
the two pressure reducing valves a trap set should be fitted as shown in figure 8.
FMPRV41 11
Sr. No. DESCRIPTION
1 Interconnecting Pipework for Pressure Reducing Station
2 Stop Valve (Inlet)
3 Stop Valve (Bypass)
4 Strainer
5 Forbes Marshall Pilot Operated Pressure Reducing Valve, FMPRV41
6 Stop Valve (Outlet)
7 Safety Valve
8 Stop Valve ( Pressure Balancing Line)
9 Moisture Separator
10 Drain Trap Assembly
11 Dial Pressure Gauge (Inlet)
12 Dial Pressure Gauge (Outlet)
13 Stop Valve (Dial Pressure Gauge)
5.2 Pipeline sizing:
The piping on both sides of the valve must be sized so that velocities do not exceed 30 m/s.
normally, a correctly sized FMPRV41 will be smaller than the connecting pipe work.
5.3 Pipeline stresses:
Line stresses caused by expansion or inadequate support should not be imposed on the
valve body.
5.4 Isolating Valves:
These should preferably be of the full bore type.
5.5 Removal of condensate:
Ensure that the pipework is supplied with dry steam. The ideal arrangement is to fit a
separator in the steam supply. If the steam is known to be dry then a drain pocket may be
adequate. If there is a rise in the low pressure line after the valve then a further drain point
should be provided to keep the valve drained after shutdown.
5.6 Preventing Dirt:
The valve should be protected from dirt / foreign particles using pipeline strainer. The
strainer should be fitted on its side to prevent the accumulation of water.
5.7 Pressure Control Pipe:
For applications that require closer control, improved stability or maximum capacity
condition the internal balance pipe should be replaced by an external pressure sensing pipe
(supplied by others) as follows:
FMPRV41 13
5.11 Position in relation to other control valves
Line or system stop valves, either remotely actuated or manually, should be installed on the
upstream side of the Forbes Marshall Pilot Operated Pressure Reducing Valve FMPRV41.
Where there is downstream control equipment, particularly temperature control valve,
ensure the control equipment is atleast 50 pipe diameters away from the FMPRV41 to
prevent pressure pulses being transmitted back causing unstable operation and premature
wear or if this is impractical an intermediate vessel can provide a similar benefit.
Where a safety valve is required to protect the process system downstream of a FMPRV41
and where a temperature control valve is also being used downstream of the FMPRV41, it is
recommended that the safety valve is fitted downstream of the temperature control valve
rather than in between the FMPRV41 and the temperature control valve. If any slight
leakage occurs this will avoid any pressure build-up causing nuisance operation of the
safety valve but provide complete protection for the downstream system.
Where valves are installed downstream of the FMPRV41 the intermediate downstream
pipework must be properly trapped to ensure no condensate can build up on the
downstream side of the FMPRV41.
1. Ensure that all connections are properly made and that all stop valves (2, 3 and 6) are
closed.
2. Close all stop valve (2, 3 and 6) at reducing valve station, including valves on bypass line
if fitted.
3. Check that adjustment screw of the Forbes Marshall Pilot Operated Pressure Reducing
Valve, FMPRV41 (5) is turned fully anti-close wise until spring is slack.
4. Check that the pressure gauge isolating valve (13) are open.
5. For correct operation of the FMPRV41 (5) it is important that the pilot and main valves
are not subjected to dirt or other hard particles .Therefore, prior to bringing the
FMPRV41 (5) into operation ensure that the upstream pipework has been cleared of all
the loose dirt and hard particles and that the main strainer screen (4) is examined and
cleaned if necessary.
6. Slowly open the upstream stop valve (2) until it is fully open.
7 Using a suitable sized spanner slowly turn adjustment screw of FMPRV41 (5) in a
clockwise direction until desired downstream pressure reading is obtained.
8. Holding the adjustment screw of FMPRV41 (5) in position with the spanner tighten
down the lock-nut to secure the setting of the adjustment spring.
9. Slowly open the downstream stop valve (6) until it is fully open.
Note: After installation or maintenance ensure that the system is fully functional. Carry
out tests on any alarms or protective devices. It is recommended that after
commissioning the pilot filter is changed and the spare one (supplied with the valve) is
fitted.
FMPRV41 15
7. Maintenance Guidelines:
Before undertaking any maintenance on the product it must be isolated from both
supply line and return line and any pressure should be allowed to safely normalize to
atmosphere. The body gasket (all FMPRV41derivatives) and actuating chamber gasket
contains a thin stainless steel support ring which may cause physical injury if not
handled and disposed of correctly.
7.1 Routine and Preventive Maintenance:
Please refer to the maintenance schedule mentioned in the table below to undertake
routine maintenance of the FMPRV41.
FMPRV41 17
7.3 Procedure to renew the pilot filter element: (Refer to Figure 10)
1. Isolate the reducing valve and depressurize the system completely.
2. Unscrew the filter cap (1) and carefully withdraw the filter element (2).
3. Replace the element and tighten the filter cap.
Note: The gasket is re-usable.
Filter
element
2
Filter cap
1
Figure 10: Filter element
7.4 Procedure to renew or change the pressure adjustment spring: (Refer to Figure 11)
Isolate the reducing valve and completely depressurize the system in order to change the
pressure adjustment spring.
1. Release the adjustment lock-nut (2) by turning in the anticlockwise direction.
2. Turn the adjustment screw (1) anticlockwise. Ensure there is no compression on the
pressure adjustment spring (4).
3. Undo the 4 off spring housing securing nuts and bolts (3) and remove the spring
housing.
4. Remove and replace the pressure adjustment spring (4) and the top spring plate (5).
Reassemble in reverse order.
Adjustment
Screw (1)
1 Adjustment
Locknut (2)
Adjustment
Spring (4)
Straight edge
Spring (3) Spring [Link] nuts and
bolts (2)
Pilot Valve
Assembly (7)
FMPRV41 19
6. Refit the two pilot diaphragms (6) and ensure that all contact faces are clean.
Diaphragms showing signs of wear or damage should be replaced.
7. Replace the bottom spring plate (5).
8. Assemble the spring housing and tighten the nuts to the recommended torques.
7.6 Procedure to renew the pilot valve assembly for FMPRV41 air: ( Refer to fig.13 & 14)
Isolate the reducing valve and zero the pressure.
1. Unscrew the unions of balancing pipe and controlling pipe (1) and release the pipe work.
2. Unscrew spring housing securing nuts and bolts (2), thereby releasing the spring
housing, spring (3), top spring plate (4), bottom spring plate (5) and pilot diaphragm (6).
Spring (3)
Spring [Link] nuts
and bolts (2)
Pilot Valve
Assembly (9)
Main Valve
Return Spring (8)
FMPRV41 21
Spring Hsg. securing nuts
and bolts (2)
Pilot Valve Hsg. (3)
Unions (1)
Gasket Faces (5)
7.8 Procedure to renew the pilot valve diaphragms: (FMPRV41 Steam/Air) (Refer to
Figure 16)
Isolate the reducing valve and zero the pressure.
1. Unscrew the unions of balancing pipe and controlling pipe (1) and release the pipe work
2. Unscrew spring housing securing nuts and bolts (2), thereby releasing the spring
housing, spring (3), top spring plate (4), bottom spring plate (5) and pilot diaphragm (6)
3. Ensure the bottom spring plate (5) and pilot valve assembly is clean.
4. Replace the pilot valve diaphragms (6).
5. Assemble the spring housing and tighten the nuts to the recommended torque as
shown in Table 1. Bring the valve back into commission, following as many steps as
necessary in section 6.
Top spring plate (4)
Spring (3)
Spring [Link] nuts and
bolts (2)
Unions of
control pipe (1)
Unions of balancing
pipe (1)
M12 nuts
and bolts (2)
Push Rod
assembly (6) 17 (a)
Lower Diaphragm
Chamber (3)
17 (c)
17 (a)
FMPRV41 23
7.10 Procedure to service or renew the main valve and seat (FMPRV41 Steam/Air):
(Refer to Figure 18, 19 and 20)
Isolate the reducing valve and zero the pressure.
For this section refer to figure 18
1. Unscrew the unions of balancing pipe and controlling pipe (1) and release the pipe
work
2. Unscrew spring housing securing nuts and bolts (2), thereby releasing the pilot valve
housing (3), complete with spring housing assembly (4).
Spring Housing
Assembly (4)
Spring Housing
securing nuts and bolts
(2)
Pilot Valve
Housing (3)
Gasket (2)
M12 nuts
and bolts (1)
Push Rod
assembly (5)
Lower Diaphragm
Chamber (4)
FMPRV41 25
4. Refit the pushrod assembly.
5. Refit the main valve head, make sure valve locates on seat.
6. Check the valve lift shown in Table 3 using a depth gauge and adjust if necessary
byscrewing the pushrod in or out of the diaphragm plate.
Table 3 : VALVE LIFT FMPRV41 STEAM/AIR
Lower diaphragm
chamber (4)
Gasket (1)
Main Valve
spring (2)
Unions (4)
Main Valve
Head (3) Unions (4)
Internal Strainer
Screen (5)
FMPRV41 27
8. Troubleshooting:
Before undertaking the following fault finding procedure, ensure the valve has been isolated and
that upstream & downstream pressures are zero. Possible fault checks are given in a logical order
below. A pressure reducing valve typically has the following failure modes:
1) Downstream pressure zero or too low:
If downstream pressure of Forbes Marshall Pilot Operated Pressure Reducing Valve is zero,
please check following before dismantling the Forbes Marshall Pilot Operated Pressure
Reducing Valve.
1. Downstream pressure gauge: - Please ensure that it should be in working condition.
2. Upstream pressure: - It Should be as per the pressure reducing valve upstream design
pressure.
3. Isolation valve not fully Open - Ensure Upstream & Downstream Isolation valves are in
full open condition
4. Upstream Strainer Clogged – Ensure upstream Strainer is in clean condition: Clean it if it
is found as clogged.
Downstream
If main diaphragms are permanently deformed or
pressure zero Main Diaphragms
punctured - replace the same.
or too low
FMPRV41 29
3) Hunting:
Hunting or Pressure Fluctuations may coincide with variations in steam load. In such case,
check following before dismantling the Forbes Marshall Pilot Operated Pressure Reducing
Valve.
1. WET Steam- Ensure steam is not wet and Moisture separator is installed before the
pressure reducing valve & the steam trap below it, is operational.
2. Up Stream Pressure – It is recommended to have stable upstream pressure however the
Forbes Marshall Pilot Operated Pressure Reducing Valve will give constant downstream
pressure with + or - 20% variation in designed Upstream pressure.
3. Partial Blockage in Upstream - If the pressure drops during full-load conditions, it is
possible that there is a partial blockage in the upstream line or that the upstream pipe
work is undersized. Steam Line should be sized properly to carry the required steam
flow rate at given pressure considering steam velocity of 25 M/S. Please refer steam line
sizing chart for correct steam line size.
4. Isolation valves - Ensure Upstream & Downstream Isolation valves are in full open
condition. By pass valve should be in full closed condition and it should not be leaking.
5. Upstream Strainer Clogged – Ensure upstream Strainer is in clean condition: Clean it if it
is found as clogged.
6. Bypass valve – Check whether the bypass valve is leaking. Replace if found so.
Sticking of push rod Check that the Main valve pushrod is not sticking. Open & clean
in the Main Valve it. Also check whether the push rod outer surface is not
Chamber deformed. Replace the push rod if it is found deformed.
Diaphragms Over
Stretched / If Pilot diaphragms or main diaphragms overstretched or
permanently deformed -replace the same.
deformed
Check Split pin port Check the port is clean and the split pin is free to move
STEAM
U
R L
A,B
A
Q
Pilot valveassembly
M B S
AIR
Pilot valveassembly
O
T STEAM
C
H
D
I
E J P
F
Push rodassembly
K
G
STEAM AIR
FMPRV41 31
No. Description Version Symbol Spare Code
How to Order:
1 no. Forbes Marshall Pilot Operated Forbes Marshall Pilot Operated Pressure Reducing
Valve, DN 40 FMPRV41 having a 0.2-17 bar g spring and flanged BS10 table “F/H”
connections.
FMPRV41 33
Disclaimer:
This information is strictly proprietary and legally privileged. All contents herein shall be the property of Forbes
Marshall Pvt Ltd and having protection under the intellectual property rights. No part of this information or data may
be distributed or disclosed in any form to any third party. Any dissemination, use, review, distribution, printing or
copying is strictly prohibited, if you are not the intended recipient or user of this information.
Doc# FMSS/0415/UM-FMPRV41/V2.R0