King Faisal Air Academy Project
Job Safety Analysis (JSA) -Asphalt Paving/cutting
Date:_____________________________
Steps of Work Identified Hazard Control Measures
1. Authorized PTW holder shall ensure obtaining
1. Work permits to be obtained. 1. Unauthorized commencement of works may and maintaining valid work permit.
result in exposing workers and or potential to 2. Inform all workers regarding permit condition
2. Pre-task briefing toolbox talks
harm or danger before work starts. Supervisor shall conduct TBT
before work starts.
3. Wear appropriate PPE
1. Walk down job, sign permit, flag off work 1. Fall of objects / Tools 1. Body positioning, be aware of other activities,
area. 2. Accidental Fall of Person wear proper PPE, and communication.
2. Clean surface/pavement using high powered 3. Hit by structure. 2. Pay attention to spotter, check equipment
blowers. 4. Potential for muscle or back strain before use, body positioning, avoid pinch
3. Applying Sealcoating/Fill Cracked pavement. 5. Workers burned by hot asphalt, resulting points, be aware of other activities,
4. Using shovels and hand tools in minor burns. communication with spotter.
5. Loading asphalt and debris into truck for 6. Workers could experience hearing loss 3. Workers to wear Hi-Vis vests.
outhaul. while working around or with power tools. 4. Operator will pay attention to spotter. The
6. Using of cutting tools 7. Workers burned by hot asphalt. spotter will maintain good vision of
8. Worker hit by equipment while its moving. surroundings while equipment is moving.
9. Could back equipment into other moving 5. Maintain proper body positioning, breaks as
equipment in area, causing property necessary, proper use of tools. Get assistance
damage. for large chunks.
10. Incompetent workers 6. Use ear plugs and double hearing protection if
required.
7. Stop work in bad weather conditions.
8. Ensure competency of workers
1. House keeping 1. Poor maintaining of working area causing of 1. Housekeeping regimes to help keep site clear
slips, trips, falls and or other injuries 2. Ensure sufficient space around work areas
Prepared by: Review by:
PHASE 6 HSE Dept. KFAA-1422-FOR-HS-0028-R0
King Faisal Air Academy Project
Job Safety Analysis (JSA) -Asphalt Paving/cutting
Date:_____________________________
Steps of Work Identified Hazard Control Measures
PHASE 6 HSE Dept. KFAA-1422-FOR-HS-0028-R0