TATA PROJECTS LIMITED, SERVICES SBG-IPMS.
PROJECT :
Document No:TPL / IPMS / MEP / PHE / 044 Rev:00
CHECKLIST FOR INSTALLATION OF WATER SUPPLY AND PRESSURE TESTING
Name of Contractor: RFI No: Date :
Drawing No: Location :
Checked
[Link]. Description Remarks
Not
Yes No
Applicable
1 Drawing with latest revision available at site
2 CPVC pipes of specified class and make
Check and ensure that routing of piping,location of valves and other accessories etc
3
are as per drawing
4 Check for the suspended pipes are levelled & clamped firmly as per standard
5 Check and ensure that all water supply system shall be flushed before testing
Check and ensure that all water supply system are tested to hydrostatic pressure test
6 of atleast one and a half (1.5)times the maximum pressure but not less than 7kg/[Link]
for a period of not less than 8 hours
7 Test start date and time
8 Test end date and time
9 No leakage observed during pressure testing
10 Retesting of water leakages is done wherever leakage observed.
11 Check for calibration certificate for all the testing equipments
A test register shall be maintained and all entries shall be signed and dated by
12
contractors and clients
Before commissioning the water supply system, the contractor shall arrange to disinfect
13
the entire system
Additional Remarks :
CONTRACTOR PMC CLIENT
Name
Designation
Signature
Date