Ma
Sr No Checkpoint
1 2 3 4
1 Check Standard bin used for Mechanical housing
2 Check all bins should be free from dust
3 Check polythene used as per packing standard
4 Check rubber packing done as per packing standard
5 Check inner box used as per packing standard
6 Check outer box used as per packing standard
7 Check trolley available for mirror plate storage.
8 Trolley should not be damage
9 All bins should be ok ,Not in damage condition.
10 Check no material lying on shop floor
11 Rejected material kept in red bin .
12 All material kept at defined location.
13 Check Handgloves used for mirror plate handling
Operator- Daily
Supervisior- Weekly
QA Inspector- Foutnightly
Material Handling Checksheet-Assembly
Date
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
20 21 22 23 24 25 26 27 28 29 30 31
Mate
Sr No Checkpoint
1 2 3 4
1 Check required trolley,Bins available on line
2 Check partition bin used for mirror plate storage
3 Check trolley available for mirror plate storage.
4 Trolley should not be damage
5 All bins should be ok ,Not in damage condition.
6 Check no material lying on shop floor
7 All material kept at defined location.
8 Rejected material kept in red bin .
9 Check Handgloves used for mirror plate handling
10
11
12
13
Operator- Daily
Supervisior- Weekly
QA Inspector- Foutnightly
Material Handling Checksheet-Mirror Plate
Date
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
20 21 22 23 24 25 26 27 28 29 30 31