PURANIK CITY RESERVA – IV
CONTENTS
ROAD MAP FOR COMPLETION
SEPT 23 MONTH PLAN vs ACTUAL
LAST SIX MONTHS ACTIVITIES COMPLETION STATUS
PROJECT HIGHLIGHTS
IMPACT ON CONSTRUCTION COST & TIMELINE
ROAD MAP FOR COMPLETION GIVEN IN JUNE 23
Jun 23 July 23 Aug 23 Sept 23 Oct 23
• Common area • Drainage • OC application • OC application • Possession
finishes application • SWD • Possession • Stack parking
completion • SWD application application • SWD NOC expected • Compound wall
(s/case and lift • •
• Stack parking • FAPA FAPA NOC expected Approach road
lobby)
• Compound wall completion • CFO NOC expected
• Solar
• Approach road • CFO • Drainage NOC
• RWH Stability
• Tree application application expected
• OWC
• FAPA completion
• CFO application
AUG’23 MONTH – BUILDING COMMITMENT
Month of AUG’23 Month of AUG’23
Project Activities Remarks
Planned Actual Status
Work completion certificate
FAPA 100% completion Application raised, Officer visited
received for OC
Work completion certificate Application raised, Officer visited
CFO FIRE 100% completion
received for OC
100% completion Work completion certificate Application raised, Officer visited
DRAINAGE
received for OC
STACK PARKING 100% completion 30% completed WIP
TREE 100% completion 100% completed WIP Application raised, Officer visited
LAST SIX MONTHS ACTIVITIES COMPLETION STATUS
Month of Jan’23 Month of June’23 Month of Sept’23
Project Activities
status Actual Status Actual Status
Podium 20 % completed Completed
Completed
STP Not started
Completed
Fire Pump room 5 % completed
Completed
Domestic & flushing tanks 30 % completed
Completed
Doors 60 % completed
Completed
Podium Fire fighting works Not started 95 % completed
Lift works
60 % completed Completed
LAST SIX MONTHS ACTIVITIES COMPLETION STATUS
Month of June’23 Month of Sept’23
Project Activities Month of Jan’23 status
Actual Status Actual Status
Completed
Substation Not started 90 % Completed
Completed
Drainage Not started 80 % Completed
Sliding windows Completed
60 % completed
Stair case finishing Not started WIP
WIP
Completed
Common lift lobby gypsum Not started 95 % Completed
Completed
Flooring 70% completed
Plumbing donwtakes 40% completed Completed
LAST SIX MONTHS ACTIVITIES COMPLETION STATUS
Month of June’23 Month of Sept’23
Project Activities Month of Jan’23 status
Actual Status Actual Status
80% Completed Completed
Fire chute 10 % completed
Not started 95 % Completed Completed
OWC
30 % completed Completed
RWH
Not started 80 % Completed Completed
Main cable line ducting
Not started 70 % Completed 90 % Completed
Temporary access road
MAJOR NOC’S APPLICATION STATUS
Project Activities July/Aug’23 NOC application status Sept’23 Official visit status
Drainage NOC NOC applied TMC officials visited
TMC officials visited
SWD NOC NOC applied
TMC officials visited
Tree NOC NOC Applied
CFO NOC NOC Applied Chief Fire officer visited
STP NOC NOC Applied TMC officials visited
OWC NOC NOC Applied TMC officials visited
PROJECT HIGHLIGHTS (FROM JAN’23 TO SEPT’23)
More than 320- 350 average labours working daily till date.
More than Rs. 110 cr work done in last 06 months of span.
Approx. 1.2 lacs sft of podium area constructed in 06 months.
Approx. Rs. 25 cr worth long lead items delivered like DG, Transformer, fire pumps etc.
CP & Sanitary materials procured for final possession and it will be installed at the time of final
handover.
Switches, final paint touch up and housekeeping will be done during handover.
IMPACT ON CONSTRUCTION COST & TIME DUE TO MATERIAL RATE ESCALATION
All Infra related works hampered due to heavy rainfall.
Overall Rs. 4 cr balance recovery from customers affected progress.
Overall cost impact is approx. Rs.350 per sft
Steel prices have increased by 110%
Concrete prices increased by 25%
Plumbing material increased by 62%
Electrical copper material increased by 45%
Covid’19 affects labour movement more than 1.5 years.
MAJOR HIGHLIGHTS
HT ELECTRICAL LINE PERMISSION RECEIVED
TMC WATER LINE CONNECTED
PODIUM COMPLETED
CFO FIRE VISIT DONE
ALL MAJOR NOC’S APPLIED
ALL COMMON LOBBIES COMPLETED
FIRE CHUTE COMPLETED
T5 -106 sample Flat ready for visit
BUILDING FRONT SIDE PHOTOS
BUILDING ELEVATION
BUILDING ELEVATION
FLAT COMPLETED PHOTOS
FLAT COMPLETED PHOTOS
Flat completed
Flat completed
Flat completed
Flat completed
LIFT LOBBY AREA
T4/T5 common area Lobby Gypsum ,Tiling, and light fixing completed
LIFT LOBBY
LIFT LOBBY
ACCESS ROAD PHOTOS
ACCESS ROAD PHOTOS
ACCESS ROAD PHOTOS
APPROACH ROAD
T4/T5 PODIUM –ENTRY 1 PHOTOS
APPROACH ROAD
T4/T5 PODIUM –ENTRY 1 PHOTOS
APPROACH ROAD
T4/T5 PODIUM
APPROACH ROAD
T4/T5 PODIUM ENTRY
APPROACH ROAD
CFO VISIT PHOTOS
CFO VISIT PHOTOS
CFO VISIT PHOTOS
SUBSTATION AND DG
CONNECTION COMPLETED
METER ROOM TO SUB STATION CONNECTION
CONNECTION COMPLETED
METER ROOM IN PROGRESS
FLAT WIRING IN PROGRESS
PODIUM FAPA WORKS
PODIUM FAPA WORKS
FIRE CHUTE COMPLETION
FIRE WORK- T4 T5 COMPLETED
Fire Pump room work completed
FIRE NOC WORK
FIRE WORK- T4 T5
Fire Pump room work completed
FIRE ACCESSORIES WORK
Building Fire accessories fixing completed
FIRE FIGHTING AND FAPA WORK
FIRE FIGHTING AND FAPA WORK
PODIUM PARKING
PODIUM PHOTOS
Podium Fire fighting work in progress
PODIUM WORK
TREMIX works at P1 level work In Progress
PAVER FIXING WORK IN PROGRESS
Pavers at completion stage
PAVER FIXING WORK IN PROGRESS
Pavers at completion stage
TMC WATER CONNECTION COMPLETED
STP WORK WITH SIGNAGE COMPLETED
OWC completed
TREE work completed
MIYAWAKI 650 trees planted Geo-tagging done. Lawn grass planted.
Labours working at site
WORK AFFECTED DUE TO RAIN -COMPOUND WALL
Compound wall work in progress
WORK AFFECTED DUE TO RAIN –ACCESS ROAD
Road work in progress
WORK AFFECTED DUE TO RAIN – DRAINAGE WORKS
CURRENT LABOUR STRENGTH
PCR Infra
PCR Building
Civil work 45 numbers
Civil work 24 numbers
Infra SWD drainage work 25 numbers
Waterproofing 16 numbers
InfraElectrical work 40 numbers
Tiling Work 20 numbers
Electrical Work 23 numbers
FirefightingWork 19 numbers
FAPA work 14 numbers
Current labour strength 510 numbers
Paintingwork 19 Numbers
Sept month strength 525 numbers
Miscellaneouswork 134 Number
Departmental Labour 124 numbers Oct month strength 325 numbers
Some Ready Flats