0% found this document useful (0 votes)
104 views15 pages

PM4 (Project Scheduling-Reading)

The document discusses key aspects of project scheduling, including: 1. Developing a project schedule involves defining activities based on a work breakdown structure, estimating activity durations, and sequencing activities to create a network diagram and Gantt chart. 2. A project schedule management plan provides guidelines for developing the project schedule and defines policies for tasks like activity sequencing and duration estimating. 3. Defining activities involves breaking down work packages into specific tasks and documenting attributes of each activity like resource requirements and dependencies between activities.

Uploaded by

saini1221rajnish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views15 pages

PM4 (Project Scheduling-Reading)

The document discusses key aspects of project scheduling, including: 1. Developing a project schedule involves defining activities based on a work breakdown structure, estimating activity durations, and sequencing activities to create a network diagram and Gantt chart. 2. A project schedule management plan provides guidelines for developing the project schedule and defines policies for tasks like activity sequencing and duration estimating. 3. Defining activities involves breaking down work packages into specific tasks and documenting attributes of each activity like resource requirements and dependencies between activities.

Uploaded by

saini1221rajnish
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Project Scheduling

From “Project Management” by Abdullah Oguz Ph.D.

Overview
The project schedule is one of the triple project constraints besides scope and cost (budget). A
project manager is responsible for planning, developing, managing, monitoring, and controlling the
project schedule to ensure that project objectives can be achieved, and project outcomes can be
delivered to the client and customers on time. Effective schedule management is integral to overall
project success. The objective is to create a schedule that effectively and efficiently uses allocated
resources to complete the project in the shortest amount of time possible. In order to develop a
schedule, we first need to create a plan that will guide us during the project. Afterward, we should
define the activities based on the WBS, sequence them in the right order, estimate the time it will
take to complete these activities and develop a schedule by creating a network diagram and Gantt
chart.
Project Schedule Management Plan
Project planning is at the heart of the project life cycle and tells everyone involved where we are
going and how we are going to get there. It involves creating a set of plans to help guide our team
through the implementation and closure phases of the project. The project schedule management
plan is one of the sub-plans of our overall project plan. It provides guidelines to project managers
on how to develop a project schedule by defining and sequencing project activities and milestones,
and by estimating activity durations. It is the process of establishing the policies, procedures, and
documentation for planning, developing, managing, executing, and controlling the project schedule.
A project schedule management plan can consist of the following:
• Unit of measurement - Work hours, days, weeks, months; daily working hours and shifts;
weekends and/or off-days; local, national, and federal holidays
• Creation of the activity list and attributes - Describe how activities and their attributes
will be defined, and who will be involved in this process.
• Level of accuracy - Acceptable range to ensure realistic activity duration estimate;
evaluation of the impact of risks on the overall project duration and each individual activity
duration based on the project risk management plan; methods describing how the schedule
contingencies will be assessed.
• Activity duration estimates - Estimation methods (e.g., analogous, parametric, three-
point, bottom-up)
• Methods, tools, and software utilized to develop, manage, and monitor project
schedule - Specify the organization’s procedures, policies, and resource calendars if they
should be utilized; methods and tools such as Gantt Chart, WBS, project baseline, master
and milestone schedule, Earned Value Management, and critical path method; software
such as Microsoft Project Professional, Excel, Visio, and Jira (for Kanban and Scrum), and
online collaboration tools such as Monday, Trello, and Basecamp.
• Rules and concepts to sequence activities and create an activity network diagram -
Critical path method (Forward pass, backward pass, slacks); critical chain method;
predecessor dependencies (e.g., finish-to-start, start-to-start)
• Rules for monitoring schedule performance - Earned Value Management (EVM); control
thresholds for deviations from the parameters in the schedule baseline; using software such
as Microsoft Project
• Reporting formats - Reporting formats and frequency should be in alignment with other
project plans.
• Approval of the schedule baseline - Who will be responsible for preparation and control?;
who will approve the schedule baseline?
Defining Activities
In line with the project schedule management plan, we should start scheduling the whole project
by defining activities based on the WBS (Work Breakdown Structure). The activity definition process
is a further breakdown of the work package elements of the WBS. It documents the specific
activities needed to fulfill the deliverables detailed in the WBS. These activities are not the
deliverables themselves but the individual units of work that must be completed to fulfill the
deliverables. Activity definition uses everything we already know about the project to divide the work
into activities that can be estimated. We might want to look at all the lessons learned from similar
projects our organization has done to get a good idea of what you need to do on the current one.
Detailed planning begins by identifying all the tasks to be completed. The project team begins by
reviewing the scope of the project which is found in the project scope statement (predictive/waterfall
projects) or the product backlog. A WBS allows the team to have a visual representation of the
forthcoming work. The WBS is a powerful planning tool. By breaking the project down into smaller,
more manageable components, the WBS assists project managers in identifying the specific tasks.
The team then determines how long it will take to complete the required tasks.
Expert judgment from project team members with prior experience and from stakeholders that can
be consulted can help us define activities while developing project scope statements and WBS. If
we are asked to manage a project in a new domain, we could use subject matter experts in that
particular field to help define tasks so we can understand what activities are going to be involved.
We may want to create an activity list and then have the expert review it and suggest changes.
Alternatively, we could involve the experts from the very beginning.
Sometimes we start a project without knowing a lot about the work that we will be doing later.
Rollingwave planning lets us plan and schedule only the portion that we know enough about to plan
well. When we don’t know enough about a project, we can use placeholders for the unknown
portions until we know more. These are extra items that are put at high levels in the WBS to allow
us to plan for the unknown.
When we identify activities for the work packages, we can detail the activities in a project activity
list which is a list of everything that needs to be done to complete the project, including all the
activities that must be accomplished to deliver each work package with activity attributes. This list
can consist of, but is not limited to:
1. Activity identifier
2. WBS number
3. Activity title
4. Scope of Work
5. The person responsible (RACI chart can be used. A RACI matrix, describes the participation
by various roles in completing tasks or deliverables for a project)
6. Related activities
a. Higher level activities (WBS number)
b. Lower level activities (WBS number)
c. Predecessors (including dependencies, that are FS, FF, SF, SS)
d. Successors (including dependencies, that are FS, FF, SF, SS)
7. Resource requirements
8. Activity location
9. Level of effort required
10. Activity assumptions
11. Activity constraints
The example in Table 7.1 is based on the Project Charter for a grocery store (Grocery LLC’s
Mobile-Commerce Project). In Table 7.1, we focus on Activity 1.3 “Preparation of Project
Charter” in the WBS. Under Activity 1.3, we determined six activities that can serve as the lowest
level of activities, which are work packages.
Table 7.1: Activity List Template (Adapted from a template on www.projectmanagement.com)
We can explain each column available in Table 7.1 as below:
• Activity Identifier: Once the WBS is created for the project, the list of activities required to
complete each work package needs to be developed by the project team. Each activity then
needs to be assigned an Activity ID, which is placed in this column. The activity ID serves
as a reference identification number during planning, developing, and controlling the project
schedule.
• Activity List: The name/unique label for the activity (in brief) is placed in this column.
• Scope of Work: The description of work required to be done to complete the activity is
placed in this column (in as much detail as possible).
• Person Responsible: One person or more than one who will be responsible for delivering
the activity must be mentioned in this column. It is always good to have a primary and an
alternate team member assigned to this responsibility.
Estimating Activity Durations
After we define the lowest level of activities in an activity list, each activity is reviewed and
evaluated to determine the duration (how long it will take to accomplish from beginning to end)
and what resources (e.g., human resources, materials, facilities, and equipment) are needed.
An estimate is an educated guess based on knowledge, experience, and inference—the
process of deriving conclusions based on assumptions. The accuracy of the estimate is related
to the quality of the knowledge and how that knowledge is applied. The person with the most
knowledge may not be the most objective person to provide duration estimates. The person
responsible for the work may also want to build in extra time. Therefore, multiple inputs into the
duration estimate and a more detailed WBS help reduce bias—the making of decisions based
on a prejudged perspective.
It is of high importance here to highlight how a milestone is different from an activity. A milestone
is a significant point or event in a project. Milestones have zero duration because they represent
a significant point or event. A milestone list identifies all project milestones and indicates
whether the milestone is mandatory, such as those required by contract, or optional, such as
those based on historical information.
The unit of time used to develop the activity duration is a function of the level of detail needed
by the user of the schedule. The larger and more complex the project, the greater the need for
detail, which usually translates into shorter durations for activities. However, it is common to
use two types of units – one is days or weeks for activities, and hours to display the work hours.
In this textbook, we can elaborate on five types of estimation methods:
1. Expert judgment: The project team consults domain and implementation subject matter
experts who have technical knowledge and experience in the areas the project activities are
related to. If we are developing a new mobile application, we can consult software engineers,
developers and testers, and systems analysts who were involved in activities to develop other
mobile applications. They can provide us with information regarding scheduling estimates for
each activity we are planning to carry out.
2. Appropriation method (Analogous estimating): Actual durations from similar projects are
reviewed, and the same proportions are applied to the current project. However, internal and
external factors that affected the previous projects, and those that may affect the current project
should be taken into account. Identified risks with their probability and impact considered could
have a significant influence on duration estimates for the current project.
3. Parametric estimating: In this estimation technique, we can use equations and algorithms
to calculate the duration based on the resources we use and how many hours they need to
work, or how many of them we need to use. This method is quantitative. We can multiply the
quantity of work to be performed by the number of hours per unit of work. If we can estimate
the amount of the work, we can divide it by the work that can be done in an hour. For example,
let’s assume that, in our m-commerce project, we estimated that software developers need to
create 200 lines of code for a module. Based on the previous projects and the feedback we
received from the subject matter experts, we have estimated that a developer can finish 40 lines
in an hour. Therefore, a developer needs 5 hours to finish all 200 lines. We can also add a one-
hour break and two-hour review for this task. Therefore, the total work hours amount to 8 hours
which is translated to one day in our schedule. Another example can be regarding the
installation of cables in an infrastructure project. If workers can install 100 feet of cable per hour,
the duration required to install 1,000 feet would be 10 hours (1,000 feet divided by 100 feet per
hour). This technique can produce higher levels of accuracy depending on the sophistication
and underlying data built into the model. Parametric schedule estimates can be applied to a
total project or segments of a project, in conjunction with other estimating methods. Entering
data about the project into a formula, spreadsheet, or computer program produces a duration
estimate by extrapolating information from a database of actual durations from past projects.
4. Three-point estimates: Duration estimates are done based on three scenarios:
• A realistic estimate (most likely to occur – m)
• An optimistic estimate (best-case scenario – o)
• A pessimistic estimate (worst-case scenario – p)
In the three-point estimation method, two distributions are possible – triangular and beta. In
triangular distribution, all three duration estimates get the same weight. In a beta distribution,
the realistic estimate gets four-sixths of the weight whereas the other two estimates have one-
sixth of the weight.
Triangular distribution:

Beta distribution:

Let’s estimate the duration of the “1.3 Preparation of Project Charter” sub-activities. Our team
gathered together in a meeting to review and discuss alternative durations. We also consulted
subject matter experts who work in relevant departments in our organization and also external
stakeholders who have an interest and/or power. Our organization and the team had
implemented software and website development projects as well as several mobile application
development projects. Therefore, we have reports including information regarding the realized
durations and lessons learned. So, we can start with analogous estimating first. As we have
already worked on similar projects, that would facilitate the estimation process both for schedule
and budget. We can place the historical information on the Most Likely column. Based on the
expert judgment, lessons learned, and discussions during our team meeting, we determined
pessimistic and optimistic durations in Table 7.2.
Table 7.2: Estimating Activity Duration by Applying Three-Point Estimate Method

The computation of the duration for Activity 1.3.2 is shown below:

We can roll the duration estimates down or up to the nearest integral number.
5. WBS method (Bottom-up estimating): In this method, we start from the lowest level
activities in the WBS – work packages. After we estimate the duration for all six activities (Table
7.2), we can find the duration of the parent activity, 1.3 “Preparation of Project Charter”. The
addition of duration for all six activities wouldn’t be an operation of adding all numbers
(4+5+6+2+8+5), which is equal to 30 days. We must consider the dependencies between the
activities, which are detailed in sections ahead of this chapter. Hence, we can find 22 days for
1.3. The same bottom-up estimating is applied to the activities (1.1., 1.2, 1.3, 1.4, 1.5), and the
duration for “1. Scope” is found as 35 days. “1.6 Completion of the Scope Phase” is a milestone
and has a duration of zero. The overall duration for “1. Scope” is computed as 35 days as seen
in Table 7.3.
Creating an Activity Network Diagram
After we define the activities and estimate their duration, we are ready to create an activity
network diagram which is a graphical representation of the logical relationship (i.e.,
dependencies) among the project activities. Duration estimation can also accompany the
creation of an activity network. The process can be iterative, and the project team can move
back and forth to refine the activities, durations, and their relationships with other activities.
Table 7.3. Schedule for Scope activities with durations rolled up in the higher levels

Activities are carried out in order. Therefore, they have predecessors and successors. They have
logical relationships or dependencies which show the sequence in which the activities are to be
performed. There are four relationships between activities, which can be indicated as “Finish-to-
Start” (FS), “Finish-to-Finish” (FF), “Start-to-Start” (SS), and “Start-to-Finish” (SF). The most
common relationship is Finish-to-Start at which we start a successor activity once we finish the
predecessor activity. Microsoft Project also uses FS as the default relationship. In the MS Project
tutorial below, this topic has been also discussed. A start-to-Finish relationship is very rarely used.
Showing the activities in rectangles or circles, and their relationships (dependencies) as arrows is
called a precedence diagramming method (PDM). This kind of diagram is also called an activity-
on-node (AON) diagram (Figure 7.1). Another way to show how tasks relate is with the activity-on-
arrow (AOA) diagram (Figure 7.1). AOA diagram is traditionally drawn using circles as the nodes,
representing the beginning and ending points, and the arrows representing activities. AON is more
commonly used and is supported by all project management programs. In this textbook, as is also
used by PMBOK Guide Sixth Edition, we are using AON diagrams for creating activity network
diagrams. Although we used circles in Figure 7.1 for AON, the most common implementation is to
use rectangles. Microsoft Project uses rectangles as well.
Logical Relationships / Dependencies - As explained above, four logical relationships can be
used in the precedence diagraming method while creating activity network diagrams. Besides
these relationships, we will also discuss lags and leads.
• Finish-to-Start (FS) Relationship In this relationship, a predecessor activity should be finished
in order to start the successor activity. This is the most common relationship between activities.
As seen in Figure 7.2, Activity A must be finished to start Project B.
Examples:
• We need to assemble all hardware and network components of a laptop
(predecessor) to install the operating system on this laptop (successor).
• We must finish cooking all our meals (predecessor) to start serving them in the
dinner (successor).
• We should finish packing all the luggage to start driving to the airport for the holiday.

• Lag A lag is the amount of time a successor activity can be delayed with respect to a
predecessor activity. Consider that we should paint one room in our house. We need to apply
plaster to walls first (predecessor). When the walls dry, we can paint them (successor). It is an
FS relationship. However, we need to wait for two days for the walls to dry. This causes a two-
day delay between two activities which is called a lag (Figure 7.3).

• Lead A lead is the opposite of a lag. A lead is the amount of time a successor activity can be
advanced with respect to a predecessor activity. In Figure 7.4, Activity B (successor) can start
three days before Activity A (predecessor) finishes. For example, in the project, we should elicit
the requirements of stakeholders first. Then, we can start designing the product based on the
requirements. If we have ten stakeholder groups, and five of them are key stakeholders, we
can start the design before we finish all the elicitation.

• Finish-to-Finish (FF) Relationship In this relationship, we cannot finish a successor activity


(Activity B) if we don’t finish a predecessor activity (Activity A). Therefore, Activity A must be
finished to ensure that we can finish Activity B as well (Figure 7.5). These tasks can be carried
out in parallel. It is common to have a lag between the predecessor and successor.

Examples:
• We are writing a new textbook, and it has 15 chapters. When we finish writing
Chapter 15, we can complete the book.
• The contractor is finishing the installation of gas lines and plumbing in our new house
(predecessor – Activity A). Another contractor who will install the kitchen appliances
can finish the installation of these appliances (successor – Activity B) when gas lines
and plumbing are done. The second contractor will finish the installation of
appliances five days after the predecessor activity is completed. So, there is a lag
of five days (Figure 7.5).
• Start-to-Start (SS) Relationship In this relationship, a successor activity (B) cannot start until
we start the predecessor activity (A). Like a finish-to-finish relationship, it is possible to see a
lag between these two activities. In Figure 7.6, the relationship on the right illustrates a 5-day
lag. Activity B can start five days after Activity B starts.

Examples:
• When developers start coding in a software project, testers may not need to wait
until they finish all the coding. They can start testing after the coding starts. However,
they may need to wait for several hours or days to start testing since some of the
coding should be done so that the testers have an adequate number of lines to test.
This delay is named “lag” as explained above and also in the “Finish-to-Finish”
relationship.
• We are drafting a user manual for our product (predecessor). This manual must be
also reviewed to make it ready for publishing (successor). In order to start this
review, we should start drafting the manual.
• Start-to-Finish (SF) Relationship This is the rarest relationship between project activities.
Activity B (successor) cannot finish until Activity A (predecessor) activity has started (Figure
7.7). Consider that we developed a new order processing software. In the meantime, we still
need to use the current software not to cause any interruptions in our operations. Activity A is
“Shutting down the current software” while Activity B is “Making the new software operational”.
We can finish Activity B when we start Activity A.
Activity Network Diagram - An Activity Network Diagram is a diagram of project activities that
shows the sequential relationships of activities using arrows and nodes. An activity network
diagram is a tool that is used extensively in project management and is necessary for the
identification of a project's critical path. Consider the following chart (table 7.4) as a reference
to create an activity network diagram:

Table 7.4 Activities

An activity node includes the labels as seen in Figure 7.8.


• Early Start (ES): The earliest time we can start an activity.
• Duration: How long it takes to finish all the tasks in an activity. It can be hours, days,
weeks, or months.
• Early Finish (EF): The earliest time we can finish an activity.
• Late Start (LS): The latest time we can start an activity. Some activities may have
some flexibilities (slacks or floats) that allow us to have some delay to start without
affecting the overall project duration and other activities.
• Late Finish (LF): The latest time we can finish an activity. Based on the slacks
(floats), we can finish an activity later than its scheduled completion time.
• Slack (Float): It is the difference between LS and ES, or between LF and EF. Both
subtractions generate the same result
In order to connect nodes, we can drag a line connector to connect two activities (Figure 7.9).

We should place each activity node on the diagram by adhering to their precedence relationships
with other activities. After we connect all the nodes, we can type the duration for each activity as
can be seen in Figure 7.10. All other parts in the nodes are zero for now. Besides, as all the
dependencies are finish-to-start, the arrows (connectors) start from the right side of a predecessor
activity and finish on the left side of a successor activity. For instance, when we finish Activity A, we
can start both Activity C and Activity D. When we finish both, we can start Activity F.

Forward Pass: Now, we can start with a forward pass to determine the early start and early finish
dates, and on the last activity, the overall time to finish the whole project. It is an additive move
through the network from start to finish.
1. For two starting activities (A and B), ES is marked zero, which means that it is the very first
day of the project (Figure 7.11)

2. We add ES to the duration for each activity to find EF. For A, EF is (0+1) = 1 week, and for
B, it is (0+2) = 2 weeks. It means that we can finish A at the end of the first week, and finish
B at the end of the second week (Figure 7.11).
3. Then, we carry the EF time to the nodes immediately succeeding the recently completed
nodes (predecessors). C and D inherit 1 (EF) from A, and it becomes ES for both successor
activities. For E, we pass 2 (EF for B) to E as the ES time. Then, we add new ES times to
the duration of activities to find the EF for new successors (Figure 7.12).

4. At a merge point, as is the case when C and D merge at F, we pass the highest EF time of
predecessors (C and D) to the successor activity (F) (Figure 7.13). EF time of D becomes
ES time for F.
5. When the forward pass is done, we can generate all ES and EF times for all the activities.
The EF of the last activity (M) gives us the overall duration of the project which is 15 weeks
(Figure 7.14).

Backward Pass - Before starting the backward pass process, we should explain the critical path
which is the path through the network that results in the latest completion date of the project. If any
activity on the critical path is delayed, the completion of the project will be delayed by an equal
amount. It is the path with the greatest total duration. Therefore, we can add the amount of time
estimated for the duration of each activity to the previous activity to determine which path through
the network has the longest total duration. As we will explain below, slack will be zero for all the
activities on the critical path.
After we complete the forward pass process for all the activities, we can start backward pass by
moving from the last activity to the starting activities. It is a subtractive move through the network
from finish to the start. In our exercise, the last activity is M with a one-week duration, an ES of 14
weeks, and an EF of 15 weeks which also indicates the overall duration of the project.
1. Late Finish (LF) for the last activity M is passed from EF (15 weeks). Then, we subtract LF
from the activity duration to find the Late Start (LS). It is (15-1) = 14 weeks (Figure 7.15).
2. Now, it is possible to compute slacks for each activity. It is the difference between LS and
ES, or between LF and EF. Both calculations will generate the same result. For Activity M,
it is (14-14) or (15-15), which is zero. Therefore, there are no slacks for this activity. We
don’t have any flexibility for this activity. We cannot have any delays to start the activity or
to finish it. The activities where slack is zero are critical.
3. Then, we carry back the LS time to the nodes immediately preceding the successor node.
K and L inherit 14 (LS) from M, and it becomes LF for both predecessor activities. Then, we
subtract LF times from the duration of activities to find the LS for these predecessors (Figure
7.16). The slack for L is (10-10) or (14-14), which is zero. Therefore, L is also a critical
activity. The slack for K is (11-8) or (14-11), which is 3. It means that we can wait for an
additional three weeks to start K because we need to wait until week 14.

4. At a burst point, as is the case when G is followed by two successors, H and I, we pass the
lowest LS time of successors (H and I) to the predecessor activity G as its LF time.
Therefore, 6 becomes the LF for Activity G (Figure 7.17).
5. When the backward pass is done for all the activities, we can generate all LS and LF times
as well as slack times for all of them (Figure 7.18). Thus, we can determine the critical path
where the total slack is zero.

The critical path of this project is B – E – G – I – L – M. It is also the longest path. We need
to start and finish all these six activities on their scheduled time not to cause any delay in
the overall project. Noncritical paths are:
1. A – C – F – J – K – M: 1+2+2+1+3+1=10 weeks
2. A – D – F – J – K – M: 1+4+2+1+3+1=12 weeks
3. B – E – G – H – K – M: 2+1+3+1+3+1=11 weeks
We should always keep in mind that the WBS is not a schedule, but it is the basis for it. The network
diagram is a schedule but is used primarily to identify key scheduling information that ultimately
goes into user-friendly schedule formats, such as milestone and Gantt charts. The network diagram
provides important information to the project team. It provides information about how the tasks are
related, where the risk points are in the schedule, how long it will take as currently planned to finish
the project, and when each task needs to begin and end.
Schedules must be communicated to project stakeholders. Generally speaking, stakeholders want
to know when the work will be completed. Once the completion date is determined, it is important
to confirm whether this date can meet the expectations of the stakeholders, in particular the project
sponsor, and internal or external clients. Once timeline commitments have been made,
stakeholders must be kept up to date on any delays that will cause deviation from the agreed-upon
schedule.
Creating a Gantt Chart
A Gantt chart is a type of bar chart, developed by Henry Gantt, that illustrates a project schedule.
Gantt charts are easy to read and are commonly used to display scheduled activities. These charts
display the start and finish dates of project activities. Gantt charts also show the dependency
relationships (i.e., precedence network) between activities.
Gantt charts show all the key stages of a project and their duration as a bar chart, with the time
scale across the top. The key stages are placed on the bar chart in sequence, starting in the top
left corner and ending in the bottom right corner (Figure 7.12). A Gantt chart can be drawn quickly
and easily and is often the first tool a project manager uses to provide a rough estimate of the time
that it will take to complete the key tasks. The detailed Gantt chart is usually constructed after all
WBS activities are identified, an activity list is created, activity durations are estimated, and
predecessors are determined.
Let’s continue with our example in table 7.3. The Gantt Chart for the Scope activities was created
by using MS Project (Figure 7.19)

In the Gantt chart in Figure 7.19, red bars show the critical tasks whereas blue bars illustrate the
non- critical tasks. Dependencies between all the activities are Finish-to-Start, which is the most
common dependency and the default relationship in MS Project.

You might also like