0% found this document useful (0 votes)
31 views1 page

Construction & Engineering Project Status 2023

1. The document discusses the status of various construction projects for STANCOS HEALTH & OTC including civil works, electrical work, HVAC systems, plumbing, flooring, ceilings and more. 2. It provides details on the priority, description, contractor, costs including total, payments made and remaining, and current status of each project. 3. Several projects are nearing completion or completed while others are still in progress, pending payments, or waiting on material delivery.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views1 page

Construction & Engineering Project Status 2023

1. The document discusses the status of various construction projects for STANCOS HEALTH & OTC including civil works, electrical work, HVAC systems, plumbing, flooring, ceilings and more. 2. It provides details on the priority, description, contractor, costs including total, payments made and remaining, and current status of each project. 3. Several projects are nearing completion or completed while others are still in progress, pending payments, or waiting on material delivery.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

As discussed with Hammad Latif Sb / Saqib Ilyas / Siddiq Sb.

Yellow
STANCOS HEALTH & OTC UPDATED ON 01-12-2023
highlighted are required urgently
Detail of Project

Priority Project Description COST REMAINING CURRENT STATUS


set by Contractor/Vendor Name
TOTAL COST PAYMENT PAYMENT
Hammad Sb Activity PO # WORK
PKR PKR PKR
Done, Doors are under
1 CIVIL WORKS Azmat Construction NQ/SPL-2224 3,143,360.00 3,143,360.00 -
fabrication
Siddiq Sb will visit site on 6-
1 2 CIVIL WORKS ADDITIONAL Azmat Construction T-22020012 3,553,632.00 2,465,526.00 1,088,106.00
12-23 and will share detail
3 ELECTRICAL WORK SUFI Engineering NQ/SPL-2201 5,016,550.00 4,480,719.00 535,831.00 80% Work Done
4 ELECTRICAL WORK ADDITIONAL SUFI Engineering NQ/SPL-2215 1,938,693.00 1,633,087.00 305,606.00 80% Work Done
2 5 HVAC UNITS & DUCTING WORK SS Engineering NQ/SPL-2222 7,349,725.00 4,898,722.00 2,451,003.00 Bills under verifications
2 6 HVAC UNITS & DUCTING WORK ADDITIONAL NQ/SPL-2344 1,795,198.00 - 1,795,198.00 Bills under verifications
1 7 EPOXY FLOORING Zor Chemical NQ/SPL-2339 3,225,000.00 - 3,225,000.00 75% Advance Pending
Material 100 % Received &
8 PLUMBING WORK INHOUSE NQ/SPL-2202 2,264,968.00 2,264,968.00 -
Installation 100%
Material 100 % Received &
9 PLUMBING WORK INHOUSE NQ/SPL-2203 1,936,268.00 1,936,268.00 -
Installation 100%
Material 100 % Received &
10 PLUMBING ADDITIONAL INHOUSE 400,000.00 400,000.00 -
Installation 100%
Material 100 % Received &
11 PLUMBING ADDITIONAL 2 Ghalib International SURGE/SPL-2330 120,000.00 120,000.00 -
Installation 100%
12 PLUMBING ADDITIONAL 2.1 Bavian Enterprises NQ/SPL-2338 354,360.00 354,360.00 - Work Completed 100%
32 Ton Chiller approved by
1 13 Air Cooled Chiller 32 Ton (NQ-SPL 2345) Umer Engineering NQ-SPL 2348 4,720,000.00 4,720,000.00 CE Sb SPL and case is with
HO Purchasing
Akram & Co. Material 100 % Received &
14 PLUMBING INSULATION & CLADDING NQ/SPL-2342 515,900.00 257,950.00 257,950.00
( final payment awiated ) Installation 100%
Additional : Insulation of Chilled water lines
Akram & Co. Material 100 % Received &
15 insdie the facility of Health & OTC. NQ/SPL-2346 175,000.00 175,000.00 -
Installation 100%
( Bottle Neck for ceiling)
16 FALSE CEILING Azmat Construction NQ/SPL-2306 1,312,500.00 634,000.00 678,500.00 80% Work Done
advance Paid, Work Started
Mian Construction Works
3 17 FURNITURE NQ/SPL-2345 5,484,000.00 3,436,800.00 2,047,200.00 & Delivery is expected 1st
Sheikhupura week of Feb

PAINT WORK PO Shared with Finance for


1.00 18 Azmat Construction NQ-SPL-2350 1,372,800.00 - 1,372,800.00
50% payment
(NQ-SPL-2350 - Azmat Contractor Paint Job)
Advance Paid, Delivery is
Sampling & Dispensing Booth, Laminaar &
19 Reflex Engineering NQ/SPL-2314-R 954,000.00 954,000.00 - ready , will be picked once
Pass box epoxy is planned
80% Work completed
20 Networking, CCTV & Public Address System SUFI Engineering SURGE/SPL-2335 2,452,967.00 2,195,404.00 257,563.00 remaining will start
after paint work
Pre-Works completed and
21 Machines & Equipments Arrangements and Installation
INHOUSE- Atif Siddiqui/HO all remain works can start
after machine Installation
22 MISc ITEMS NO PO 500,000.00 - 500,000.00
TOTAL 48,584,921.00 29,350,164.00 19,234,757.00