1. The document provides calculations for estimating the volume of various construction works. It includes calculations for site preparation works, earthworks, foundation works, and concrete works. 2. The calculations determine the volume of works such as clearing, installing bowplanks, soil excavation, backfilling, installing sand beds, laying stone foundations, and casting concrete foundations and flooring. 3. The volumes are calculated based on parameters like length, width, height/thickness, and number of units for each item and their formulas. The totals are provided in column d.

Uploaded by

ndacantik34
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
277 views26 pages

Ajeng Ayu Tabel AHSP Dan Rab PDF

1. The document provides calculations for estimating the volume of various construction works. It includes calculations for site preparation works, earthworks, foundation works, and concrete works. 2. The calculations determine the volume of works such as clearing, installing bowplanks, soil excavation, backfilling, installing sand beds, laying stone foundations, and casting concrete foundations and flooring. 3. The volumes are calculated based on parameters like length, width, height/thickness, and number of units for each item and their formulas. The totals are provided in column d.

Uploaded by

ndacantik34
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

TABEL 1.

PERHITUNGAN VOLUME PEKERJAAN


No Jenis Pekerjaan Perhitungan Volume Jumlah
a b c d
I PEKERJAAN PERSIAPAN
1.1 Pembersihan Lokasi Panjang = 17625 mm 278.65 m2
= 17.63 m
Lebar = 15810 mm
= 15.81 m
Volume = pxl
15.8

= 17.6 x 15.8
= 278.65 m2

17.6

1.2 Pemasangan Bowplank Panjang = 17.63 + (2 x 1) 74.87 m'


= 19.63 m
Lebar = 15.81 + (2 x 1)
= 17.81 m
[Link] = 2 (p + l)
15.8

= 2 (19.6 + 17.8)
= 74.87 m'

17.6

1.3 Pembuatan Bedeng Panjang = 3000 mm 15.00 m2


= 3.00 m
Lebar = 5000 mm
= 5.00 m
Volume = pxl
5.0

= 3x5
= 15.00 m2
3.0

II PEKERJAAN TANAH DAN PONDASI


2.1 Galian tanah
A [Link] = 25.00 bj 37.50 m3
Galian tanah pondasi footplat
[Link] = 1.00 m
-0.30 [Link] = 1.00 m
Tinggi Galian = 1.50 m
Volume = jml (p x l x t)
= 37.50 m3

-1.30
-2.00

1.00
B
Galian tanah pondasi Batu Kali (A)
[Link] = 87.97 m 114.36 m3
-0.3 [Link] = 1.00 m
Tinggi Galian = 1.30 m
Volume = (p x l x t)
= 114.36 m3
-1.30

1
C
Galian tanah pondasi Batu Kali (B)
[Link] = 51.06 m 66.38 m3
-0.3 [Link] = 1.00 m
Tinggi Galian = 1.30 m
Volume = (p x l x t)
= 66.38 m3
-1.30

1
2.2 Urugan Tanah
A Galian footplat = 37.50 m3 37.08 m3
Urugan tanah kembali footplat
Total [Link] = 4.80 m
Total [Link] pendek = 1.80 m
Volume = {37.5-(5.57+2.09)}x 1.2
= 37.08 m3

B
Urugan tanah kembali Batu kali
Vol. Total galian = 180.74 m 109.41 m3
Vol. Total pondasi = 89.56 m
Volume = (180.74-89.16)x1.2
= 109.41 m3

C Urugan tanah peninggi elevasi


Lantai rumah Luas lt. 1 = 181.07 m 65.18 m3
Tinggi/Tebal = 0.30 m
Volume = (181.07 x 0.3)x 1.2
= 65.18 m3

D
Urugan tanah peninggi elevasi
Luas lt. teras = 10.54 m 2.53 m3
lantai teras, KM, dan gudang
Tinggi/Tebal = 0.20 m
Volume = (10.54x0.2) x 1.2
= 2.53 m3

2.3 Urugan Pasir


A jmlh footplat = 25.00 bj 2.50 m3
Urugan pasir bawah footplat
Panjang = 1.00 m
Lebar = 1.00 m
Tinggi/Tebal = 0.10 m
Volume = 25 x (1x1x0.1)
= 2.50 m3

B
Urugan pasir bawah anstamping
Lebar = 1.00 m 13.90 m3
Batu Kali A dan B
Tinggi/Tebal = 0.10 m
Panjang Pondasi = 139.03 m
Volume = (1 x 0.1 x 139.03)
= 13.90 m3

C Urugan pasir bawah lantai


Luas Lt.1 = 191.61 m 19.16 m3
Tinggi/Tebal = 0.10 m
Volume = (191.61 x 0.1)
= 19.16 m3
2.4 Pasangan Batu Kali
A Lebar = 1.00 m 20.85 m3
Anstamping Pondasi A dan B
Tinggi/Tebal = 0.15 m
Panjang = 139.03 m
Volume = (1 x 0.15 x 139.03)
= 20.85 m3

B LGB = 0.80 m 35.55 m3


Pasangan Pondasi Bt. Kali A
LGA = 0.30 m
Tinggi/Tebal = 0.75 m
Panjang = 87.97 m
Volume kolom pendek = 1.80 m3
Volume
= {1/2 x (0.8+0.3) x 0.75} x 87.97 - 1.8
= 35.55 m3

C LGB = 0.80 m 19.26 m3


Pasangan Pondasi Bt. Kali B
LGA = 0.30 m
Tinggi/Tebal = 0.75 m
Panjang = 51.06 m
Volume kolom pendek = 1.80
Volume
= {1/2 x (0.8+0.3) x 0.75} x 51.06 - 2.09
= 19.26 m3

III PEKERJAAN BETON


3.1 Pek. beton non-struktur
A Lantai kerja Footplat Jmlah Footplat = 25.00 bh 0.80 m3
Panjang = 0.80 m'
Lebar = 0.80 m'
Tinggi/Tebal = 0.05 m'
Volume = 25 (0.8 x 0.8 x 0.05)
= 0.80 m3

B Rabatan Tidak ada


3.2 Pek. Beton bertulang
A Pondasi Footplat Jmlah footplat = 25.00 bh 1.50 m3
LGB = 0.80 m
LGA = 0.30 m
Tinggi/Tebal = 0.25 m
- Volume footplat = 25 (0.8 x 0.3 x 0.25)
= 1.50 m3

- Volume Bekisting
Jmlah footplat = 25.00 bh 24.00 m2
Panjang = 0.80 m
Tinggi/ Tebal = 0.30 m
Volume = 4 (0.8 x 0.3) x 25
= 24.00 m2

B Kolom Pendek
Jmlah Footplat = 25.00 bh 1.80 m3
Panjang kolom = 0.15 m'
Lebar kolom = 0.30 m'
Tinggi/Tebal = 1.60 m'
Volume = 25 (1.6 x 0.3 x 0.15)
= 1.80 m3

- Volume Bekisting = 4 (1.6 x 0.3)x29 24.00 m2


= 24.00 m2

C
Balok Sloof Batu Kali A dan B
Lebar = 0.15 m 5.91 m2
Tinggi/Tebal = 0.30 m
Panjang sloof = 131.44 m
Volume = 131.44 (0.3 x 0.15)
= 5.91 m2

- Volume Bekisting
Panjang sloof = 131.44 m 78.86 m2
Tinggi/Tebal = 0.30 m
Volume = 2 (131.44 x 0.3)
= 78.86 m2

D Kolom Induk Lt. 1


Jmlh Kolom = 25.00 bh 4.50 m3
Panjang = 0.30 m'
Lebar = 0.15 m'
Tinggi = 4.00 m'
Volume = 25 (0.15 x 0.3 x 4)
= 4.50 m3

- Volume Bekisting
Jlmh Kolom induk = 25.00 bh 30.00 m2
Tinggi = 4.00 m'
Lebar = 0.15 m'
Volume = 2 x (4 x 0.3) x 28
= 30.00 m2

E Kolom praktis Lt. 1


Jmlh Kolom = 14.00 bh 1.26 m3
Panjang = 0.15 m'
Lebar = 0.15 m'
Tinggi = 4.00 m'
Volume = 14 (0.15 x 0.15 x 4)
= 1.26 m3

- Volume Bekisting
Jlmh Kolom induk = 14.00 bh 16.80 m2
Tinggi = 4.00 m'
Lebar = 0.15 m'
Volume = 2 x (4 x 0.15) x 14
= 16.80 m2

F Balok Induk Lt. 1


Jmlh kolom induk = 25.00 bh 3.88 m3
Panjang Balok = 147.43 m'
Lebar Balok = 0.15 m'
Tinggi Balok = 0.30 m'
Lebar kolom induk = 0.15 m'
Tebal Plat = 0.12 m'
Volume
- Volume Kolom tertabrak
= 25 (0.15 x (0.3 - 0.12) x 0.15)
= 0.10 m3
- Volume balok induk
= 147.43 x 0.15 (0.3 - 0.12)
= 3.98 m3
- Volume Total = (3.98 - 0.10)
= 3.88 m3

- Volume Bekisting
Jlmh bekisting = 2.00 bh 132.68 m2
Panjang Balok = 147.43
Tinggi = 0.30 m'
Lebar = 0.15 m'
Volume = 3 (147.43 x 0.3)
= 132.68 m2

G Balok anak Lt. 1


Jmlh kolom induk = 25.00 bh 0.23 m3
Panjang Balok = 54.08 m'
Lebar Balok = 0.15 m'
Tinggi Balok = 0.15 m'
Lebar kolom praktis = 0.15 m'
Tebal Plat = 0.12 m'
Volume
- Volume Kolom tertabrak
= 25 (0.15 x (0.15 - 0.12) x 0.15)
= 0.02 m3
- Volume balok induk
= 54.08 x 0.15 (0.15 - 0.12)
= 0.24 m3
- Volume Total = (0.24 - 0.01)
= 0.23 m3

- Volume Bekisting
Jlmh bekisting = 2.00 bh 24.34 m2
Panjang Balok = 54.08
Tinggi = 0.15 m'
Lebar = 0.15 m'
Volume = 3 (54.08 x 0.15)
= 24.34 m2
H Plat Tangga
Tebal plat tangga = 0.18 m' 2.25 m3
Panjang Sisi samping = 2.40 m'
Sudut tangga bawah A = 34 derajat
Pnjng plat tangga bawah = 2.4/cos 34
= 2.89 m'
Panjang sisi samping B = 4.895 m'
Pnjng plat tangga tengah = 4.895/cos 34
= 5.90 m'
Panjang sisi samping C = 1.95 m'
Panjang plat tangga atas = 1.95/cos 34
= 2.35 m'
Lebar tangga = 0.95 m'
Lebar bordes = 1.00 m'
Volume
- Plat tangga bawah = (2.89 x 0.95 x 0.18)
= 0.50 m3
- Plat tangga tengah = (5.90 x 0.95 x 0.18)
= 1.01 m3
- Plat tangga atas = (2.35 x 0.95 x 0.18)
= 0.40 m3
- Plat Bordes = 2x (0.18 x(0.95 x 1))
= 0.34 m3
Volume total = 2.25 m3

Volume Bekisting
Volume plat 15.34 m2
Bawah = 3.73 m2
Tengah = 7.62 m2
Atas = 3.03 m2
Jumlah = 14.39 m2
Volume bordes = 0.95 m'
Volume = (31.91+0.95)
= 15.34 m2

I Anak tangga Jmlah anak tangga = 21 bh


Panjang = 0.95 m 0.57 m3
Lebar = 0.30 m
Tinggi = 0.19 m
Volume = 21x(1/2x0.95x0.3x0.19)
= 0.57 m3
Volume bekisting
Jumlah = 21 bh 3.79 m2
Tinggi = 0.19 m
Panjang = 0.95 m
Volume bekisting = (21 x 0.19 x 0.95)
= 3.79 m2

J Plat Lantai 2 Volume Plat lantai


Panjang = 15.81 m' 1.47 m3
Lebar = 13.095 m'
Tebal = 0.12 m'
Volume Lubang tangga = 23.38 m3
Volume = (15.81x13.095x0.12)-23.38
= 1.47 m3

Volume bekisting = 2{(15.81x0.12)+(13.095x0.12)


= 5.37 m2 5.37 m2

K Kolom Induk Lantai 2 Panjang = 0.15 m' 4.52 m3


Lebar = 0.30 m'
Tinggi = 4.18 m'
Jumlah = 24 bh
Volume = 24x(0.15x0.3x4.182)
= 4.52 m3

Volume bekisting = {2x(4.182x0.3)}x24 60.22 m2


= 60.22 m2

L Kolom Praktis Lantai 2 Panjang = 0.15 m' 0.85 m3


Lebar = 0.15 m'
Tinggi = 4.18 m'
Jumlah = 9 bh
Volume = 9x(0.15x0.15x4.182)
= 0.85 m3
Volume bekisting = {2x(4.182x0.15)}x9
= 11.29 m2 11.29 m2

M Balok Ring Volume Balok ring


Panjang = 143.40 m' 3.12 m3
Lebar = 0.15 m'
Tinggi = 0.15 m'
Jumlah = 33 bh
Lebar Kolom = 0.15 m'
- Volume kolom tertabrak = 33 x (0.15 x 0.15 x 0.15)
= 0.11 m3
- Volume balok ring = (143.40 x 0.15 x 0.15)
= 3.23 m3
- Volume total = 3.23-0.11
= 3.12 m3

Volume Bekisting
Jumlah = 2.00 bh 64.53 m2
Panjang = 143.40 m
Lebar = 0.15 m
Volume Bekisting = 3 x (143.40 x 0.15)
= 64.53 m2

IV PEKERJAAN PASANGAN DINDING


4.1 Trasram rumah (1:2) Panjang dinding = 32.41 m 4.36 m2
Panjang lubang kusen = 22.72 m
Lebar = 0.15 m
Tinggi = 3.00 m
Volume = (32.41-22.72) x 3 x 0.15
= 4.36 m2

4.2 Pasangan Dinding


A Panjang = 116.41 m 426.54 m2
Pasangan Dinding Lt.1 (1:6)
Tinggi = 4.00 m
Luas trasram = 4.36 m2
Luas lubang pintu jendela
= 34.72 m2
dan ventilasi
Luas = (116.41 x 4)-(4.36 + 34.72)
= 426.54 m2

B Panjang = 133.71 m 500.31 m2


Pasangan Dinding Lt.2 (1:6)
Tinggi = 4.00 m
Luas trasram = 4.36 m2
Luas lubang pintu jendela
= 30.17 m2
dan ventilasi
Luas = (133.71 x 4 )-(4.36 + 30.17)
= 500.31 m2

C Panjang = 12.80 m 1.44 m2


Dinding kamar mandi Lt.1 (1:4)
Tinggi = 1.00 m
Luas lubang pintu = 11.36 m2
Luas = (12.80 x 1) - 11.36
= 1.44 m2

D Panjang = 19.61 m 8.25 m2


Dinding kamar mandi Lt.2 (1:4)
Tinggi = 1.00 m
Luas lubang pintu = 11.36 m2
Luas = (19.61 x 1) - 11.36
= 8.25 m2

4.3 Pek. Plesteran dan Acian


A Luas dinding Lt.1 = 426.54 m2 1342.27 m2
Plesteran dinding rumah (1:6)
Luas dinding KM Lt. 1 = 1.44 m2
Luas dinding Lt.2 = 500.31 m2
Luas dinding KM Lt.2 = 8.25 m2
Luas Plesteran
=(2 [(426.54 - 1.44)+(500.31 - 8.25)]
= 1342.27 m2

B Luas dinding luar KM Lt.1 9.69 m2


Plesteran dinding luar KM (1:4)
= 1.44 m2
Luas dinding luar KM Lt.2
= 8.25 m2
Luas plesteran = 1.44 + 8.25
= 9.69 m2

C Panjang KM Lt.1 = 12.80 m 106.92 m2


Plesteran dinding dalam KM (1:4)
Tinggi KM Lt.1 = 4.00 m
Panjang KM Lt.2 = 19.61 m
Tinggi KM Lt.2 = 4.00 m
Luas lubang pintu Lt.1 = 11.36 m2
Luas lubang pintu Lt.2 = 11.36 m2
Luas
=[(12.8 x 4)-11.36]+[(19.61 x 4)-11.36]
= 106.92 m2

D Acian Luas plesteran dinding rumah 1458.88 m2


= 1342.27 m2
Luas plesteran dinding (luar) kamar mandi
= 9.69 m2
Luas plesteran dinding (dalam) kamar mandi
= 106.92 m2
Luas acian = 1149.79 + 9.69 + 106.92
= 1458.88 m2

E Benangan Dalam Benangan dalam Lt.1 = 192.00 m' 404.00 m'


Benangan dalam Lt.2 = 212.00 m'
Panjang = 192 + 212
= 404.00 m'

F Benangan Luar Benangan luar Lt.1 = 44.00 m' 72.00 m'


Benangan luar Lt.2 = 28.00 m'
Panjang = 44 + 28
= 72.00 m'

G Sopi-sopi Alas = 10.654 m 13.14 m2


Tinggi = 2.467 m
Luas = 1/2 x a x t
= 13.14 m2

V PEKERJAAN ATAP DAN PENUTUP ATAP


5.1 Pekerjaan Kuda-kuda
Panjang bentang = 10.654 m' 16.24 m2
Rangka Kuda-kuda Baja Ringan
Lebar bentang = 15.810 m'
Tinggi Rangka = 3.049 m'
Kemiringan = 30 Derajat
Total kuda-kuda = luas rangka x jumlah
= 259.87
Luas rangka kuda-kuda = 1/2 x a x t
= 16.24 m2

5.2 Kerangka penutup atap = Luas atap 1/kemiringan 389.00 m2


= 194.50 m2
total luas kerangka penutup atap
= luas atap x jumlah atap
= 389.00 m2

5.3 Penutup atap genting beton = Luas atap 1/kemiringan 389.00 m2


= 194.50
total luas penutup atap = luas atap x jumlah atap
= 389.00 m2

VI PEKERJAAN LISPLANK DAN PLAFOND


6.1 Lisplank Panjang = 31.62 m2 0.28 m2
Uk. Papan Lisplank = 3/30 cm
Volume = 31.62 (0.3 x 0.03)
= 0.28 m2

6.2 Pekerjaan Plafond


A Rangka Plafond Lt. 1 Teras depan = 5.445 x 2.29 203.74 m2
= 12.47 m2
Carport = 8.47 x 3.688
= 31.24 m2
Ruang Tamu = 6.295 x 3.63
= 22.85 m2
Ruang makan = 5.465 x 6.65
= 36.34 m2
Ruang Tidur 1 = 3.63 x 4.355
= 15.81 m2
Ruang Tidur 2 = 3.025 x 4.275
= 12.93 m2
Ruang Tidur 3 = 3.025 x 3.33
= 10.07 m2
Ruang Tidur 4 = 1.775 x 2.95
= 5.24 m2
KM/WC 1 = 1.775 x 1.75
= 3.11 m2
KM/WC 2 = 1.56 x 1.625
= 2.54 m2
Gudang = 1.74 x 1.625
= 2.83 m2
Dapur = 3.69 x 5.049
= 18.63 m2
Teras Belakang = 10.345 x 2.87
= 29.69 m2
Luas Total = 203.74 m2

B Rangka Plafond Lt. 2 Ruang Tidur 1 = 6.061 x 4.65 172.56 m2


= 28.184 m2
Ruang Tidur 2 = 3.691 x 5.945
= 21.94 m2
Ruang Tidur 3 = 3.999 x 2.93
= 11.72 m2
Ruang Tidur 4 = 2.969 x 3.3
= 9.80 m2
KM/WC 1 = 2.0 x 3.38
= 6.76 m2
KM/WC 2 = 2.075 x 2.35
= 4.88 m2
Ruang Keluarga = 5.975 x 10.595
= 63.31 m2
Void = 4.37 x 5.945
= 25.98 m2
Luas Total = 172.56 m2

C Plafond Lt. 1 Teras depan = 5.445 x 2.29 203.74 m2


= 12.47 m2
Carport = 8.47 x 3.688
= 31.24 m2
Ruang Tamu = 6.295 x 3.63
= 22.85 m2
Ruang makan = 5.465 x 6.65
= 36.34 m2
Ruang Tidur 1 = 3.63 x 4.355
= 15.81 m2
Ruang Tidur 2 = 3.025 x 4.275
= 12.93 m2
Ruang Tidur 3 = 3.025 x 3.33
= 10.07 m2
Ruang Tidur 4 = 1.775 x 2.95
= 5.24 m2
KM/WC 1 = 1.775 x 1.75
= 3.11 m2
KM/WC 2 = 1.56 x 1.625
= 2.54 m2
Gudang = 1.74 x 1.625
= 2.83 m2
Dapur = 3.69 x 5.049
= 18.63 m2
Teras Belakang = 10.345 x 2.87
= 29.69 m2
Luas Total = 203.74 m2

D Plafond Lt. 2 Ruang Tidur 1 = 6.061 x 4.65 172.56 m2


= 28.184 m2
Ruang Tidur 2 = 3.691 x 5.945
= 21.94 m2
Ruang Tidur 3 = 3.999 x 2.93
= 11.72 m2
Ruang Tidur 4 = 2.969 x 3.3
= 9.80 m2
KM/WC 1 = 2.0 x 3.38
= 6.76 m2
KM/WC 2 = 2.075 x 2.35
= 4.88 m2
Ruang Keluarga = 5.975 x 10.595
= 63.31 m2
Void = 4.37 x 5.945
= 25.98 m2
Luas Total = 172.56 m2

VII PEKERJAAN KUSEN PINTU DAN JENDELA (ALUMUNIUM)


7.1 Kusen Pintu dan Jendela (PG 1) 1 Lebar = 0.15 m 10.28 m3
Unit Tinggi = 2.40 m
Panjang = 2.78 m
Volume = Jmlh x P x L x T
= 1.00 m3

7.2 Kusen Pintu dan Jendela (PJ 1) 1 Lebar = 0.15 m


Unit Tinggi = 2.40 m
Panjang = 2.18 m
Volume = Jmlh x P x L x T
= 0.78 m3

7.3 Kusen Pintu (P1) 1 Unit Lebar = 0.15 m


Tinggi = 2.40 m
Panjang = 1.68 m
Volume = Jmlh x P x L x T
= 0.60 m3

7.4 Kusen Pintu (P2) 12 Unit Lebar = 0.15 m


Tinggi = 2.40 m
Panjang = 0.88 m
Volume = Jmlh x P x L x T
= 3.80 m3

7.5 Kusen Pintu (P 3) 4 Unit Lebar = 0.15 m


Tinggi = 2.14 m
Panjang = 0.78 m
Volume = Jmlh x P x L x T
= 1.00 m3
7.6 Kusen Pintu (P4) 2 Unit Lebar = 0.15 m
Tinggi = 2.40 m
Panjang = 0.88 m
Volume = Jmlh x P x L x T
= 0.63 m3

7.7 Kusen Jendela (J1A) 1 Unit Lebar = 0.15 m


Tinggi = 2.40 m
Panjang = 1.48 m
Volume = Jmlh x P x L x T
= 0.53 m3

7.8 Kusen Jendela (J2) 8 Unit Lebar = 0.15 m


Tinggi = 1.78 m
Panjang = 0.78 m
Volume = Jmlh x P x L x T
= 1.67 m3

7.9 Kusen Jendela (J3) 2 Unit Lebar = 0.15 m


Tinggi = 0.53 m
Panjang = 1.42 m
Volume = Jmlh x P x L x T
= 0.23 m3

7.10 Kusen Jendela (J4) 1 Unit Lebar = 0.15 m


Tinggi = 0.30 m
Panjang = 0.70 m
Volume = Jmlh x P x L x T
= 0.03 m3
Total Volume Kusen Pintu dan Jendela
= 10.28 m3

VIII PEKERJAAN KERAMIK


8.1 Pekerjaan Tegel Lantai
A Lantai 1 Granit tile (60 x 60) Teras depan = 5.445 x 2.29 166.86 m2
= 12.47 m2
Ruang Tamu = 6.295 x 3.63
= 22.85 m2
Ruang makan = 5.465 x 6.65
= 36.34 m2
Ruang Tidur 1 = 3.63 x 4.355
= 15.81 m2
Ruang Tidur 2 = 3.025 x 4.275
= 12.93 m2
Ruang Tidur 3 = 3.025 x 3.33
= 10.07 m2
Ruang Tidur 4 = 1.775 x 2.95
= 5.24 m2
Gudang = 1.74 x 1.625
= 2.83 m2
Dapur = 3.69 x 5.049
= 18.63 m2
Teras Belakang = 10.345 x 2.87
= 29.69 m2
Total Luas Lantai Granit = 166.86 m2

B Lantai 2 Granit Tile (60 x 60) Ruang Tidur 1 = 6.061 x 4.65 242.02 m2
= 28.184 m2
Ruang Tidur 2 = 3.691 x 5.945
= 21.94 m2
Ruang Tidur 3 = 3.999 x 2.93
= 11.72 m2
Ruang Tidur 4 = 2.969 x 3.3
= 9.80 m2
Ruang Keluarga = 16.975 x 10.037
= 170.38 m2
Total Luas Lantai Granit = 242.02 m2
C Lantai 1 Keramik (40 x 40) KM/WC 1 = 1.775 x 1.75 5.64 m2
= 3.11 m2
KM/WC 2 = 1.56 x 1.625
= 2.54 m2
Total Luas Lantai Keramik = 5.64 m2

D Lantai 2 Keramik (40 x 40) KM/WC 1 = 2.0 x 3.38 51.16 m2


= 6.76 m2
KM/WC 2 = 2.075 x 2.35
= 4.88 m2
Teras Belakang = 2.50 x 15.81
= 39.53 m2
Total Luas Lantai Keramik = 51.16 m2

E Carport = 8.47 x 3.688 31.24 m2


Lantai 1 Keramik Kasar (40 x 40)
= 31.24 m2
Total Luas Lantai Keramik = 31.24 m2

8.2 Keramik Dinding


A Tinggi = 3.00 m2 28.90 m2
Keramik Dinding KM Lt.1 (25 x 40)
Luas lubang kusen = 5.68 m2
KM/WC 1 = 2 x (1.775 + 1.75)
= 7.05 m2
Volume = (7.05 x 3) - 5.68
= 15.47 m2
KM/WC 2 = 2 x (1.56 + 1.625)
= 6.37 m2
Volume = (6.37 x 3) - 5.68
= 13.43 m2
Volume Total = 15.47 + 13.43
= 28.90 m2

B Tinggi = 3.00 m2 47.47 m2


Keramik Dinding KM Lt.2 (25 x 40)
Luas lubang kusen = 5.68 m2
KM/WC 1 = 2 x (2.0 + 3.38)
= 10.76 m2
Volume = (10.76 x 3) - 5.68
= 26.60 m2
KM/WC 2 = 2 x (2.075 + 2.35)
= 8.85 m2
Volume = (8.85 x 3) - 5.68
= 20.87 m2
Volume Total = 26.6+20.87
= 47.47 m2

VIIII PEKERJAAN INSTALASI LISTRIK


9.1 Instalasi Listrik Lantai 1
Panjang kabel = 84.10 m
Panel MCB = 1 bh
Meteran Listrik = 1 bh
Saklar Tunggal = 5 bh
Saklar Ganda = 8 bh
Stop Kontak Tunggal = 22 bh
Stop Kontak Ganda = 1 bh
Lampu Gantung = 1 bh
Lampu SL = 36 bh

9.2 Instalasi Listrik Lantai 2


Panjang kabel = 93.13 m
Tv Kabel = 2 bh
Saklar Tunggal = 8 bh
Saklar Ganda = 5 bh
Stop Kontak Tunggal = 20 bh
Stop Kontak Ganda = 6 bh
Lampu Led strip plafond = 7.21 m
Lampu Led strip dipan = 7.00 m
Lampu SL = 33 bh

X PEKERJAAN INSTALASI AIR


10.1 Instalasi air Lantai 1
Pipa air bersih = 59.22 m
Pipa air bekas = 39.01 m
Pipa Pembuangan air AC = 20.53 m
Pipa air kotor = 12.49 m
Kloset duduk = 2 bh
Kran air = 2 bh
Shower = 1 bh
Floor Drain = 2 bh
Kitchen set = 1 unit
Wastafel = 1 bh
AC = 3 bh

10.2 Instalasi air Lantai 2


Pipa air bersih = 31.12 m
Pipa air bekas = 22.98 m
Pipa Pembuangan air AC = 29.19 m
Pipa air kotor = 20.00 m
Kloset duduk = 2 bh
Shower = 2 bh
Floor Drain = 2 bh
Wastafel = 2 bh
Pompa = 1 bh
Toren/Tandon Air = 1 bh
AC = 6 bh

XI PEKERJAAN FINISHING
11.1 Pekerjaan Pengecatan dinding
Luas dinding Lt.1 = 129.21 m2 461.56 m2
Luas dinding Lt.2 = 153.32 m2
Luas Sopi-sopi = 13.14 m2
Luas kusen = 64.89 m2
Luas Total
= (2 sisi x ((129.21 + 153.32 + 13.14) - 64.89))
= 461.56 m2

11.2 Pekerjaan Pengecatan Lisplank


Panjang = 31.62 m 18.97 m2
Lebar = 0.30 m
Volume = 2 sisi x (p x l)
= 18.97 m2

XII PEKERJAAN LAIN-LAIN


12.1 Pekerjaan Septictank
A Galian tanah Septictank Panjang galian I = 1.00 m 3.50 m3
Lebar galian I = 1.00 m
Dalam galian I = 2.00 m
Volume (I) = 1x1x2
= 2.00 m3
Panjang galian I = 1.00 m
Lebar galian I = 1.00 m
Dalam galian I = 1.50 m
Volume (I) = 1 x 1 x 1.5
= 1.50 m3

Total Volume = 2 + 1.5


= 3.50 m3

B Urugan pasir bawah septictank


Luas sisi septictank = 8.00 m2 0.80 m3
Ketebalan = 0.10 m2
Volume = 8x1
= 0.80 m3

C Balok septictank (15/15)


Jumlah = 2 unit 0.09 m3
Panjang = 2.00 m
Lebar = 0.15 m
Tebal = 0.15 m
Volume = 2 x (2 x x 0.15 x 0.15)
= 0.09 m3

D Plat penutup septictank


Jumlah unit = 2 unit 0.40 m3
Panjang = 2.00 m
Lebar = 1.00 m
Tebal = 0.10 m
Volume = 2 x (2 x 1 x 0.1)
= 0.40 m3

E Trasram septictank (1:2)


Luas sisi septictank = 12.00 m2 3.60 m3
Kedalaman trasram = 0.30 m
Volume = 12 x 0.3
= 3.60 m3
12.2 Pekerjaan Sumur Resapan
A Galian tanah sumur resapan
Diameter = 1.20 m 2.03 m3
Jari-jari = 0.60 m
Kedalaman = 1.80 m
Volume = 3.14 x 0.6 x 0.6 x 1.8
= 2.03 m3

B Plat penutup sumur resapan


Diameter = 1.00 m 0.08 m3
Jari-jari = 0.50 m
Tebal = 0.10 m
Volume = 3.14 x 0.5 x 0.5 x 0.1
= 0.08 m3

12.3 Pekerjaan bak kontrol


A Galian tanah bak kontrol
Jumlah bak kontrol = 2 unit 0.23 m3
Panjang = 0.50 m
Lebar = 0.50 m
Kedalaman = 0.45 m
Volume = 2 x (0.5 x 0.5 x 0.45)
= 0.23 m3

B Plat penutup bak kontrol


Jumlah = 2 unit 0.01 m3
Panjang = 0.30 m
Lebar = 0.30 m
Tebal = 0.05 m
Volume = 2 x (0.3 x 0.3 x 0.05)
= 0.01 m3

12.4 Pekerjaan pipa saluran


A Galian tanah pipa saluran limbah
padat 4" Panjang = 12.49 m 1.22 m3
Kemiringan = 0.03
Kedalaman = 12.49 x 2.5%
= 0.31 m
Volume = 0.3 x 0.3 x 12.49
= 1.22 m3

B Galian tanah pipa saluran limbah


cair 3" Panjang = 22.98 m 1.21 m3
Kemiringan = 0.01
Kedalaman = 22.98 x 1%
= 0.23 m
Volume = 0.2 x 0.2 x 22.98
= 1.21 m3

C Urugan tanah kembali pipa


limbah padat 4" Volume galian = 1.22 m3 1.06 m3
Diameter pipa = 0.114 m
Panjang galian = 12.49 m'
Volume
= [1.22 - (1/4 x 3.14 x 0.114 x 0.114 x 12.49)]
= 1.06 m3

D Urugan tanah kembali pipa


limbah cair 3" Volume galian = 1.21 m3 1.04 m3
Diameter pipa = 0.089 m
Panjang galian = 22.98 m'
Volume
= [1.21 - (1/4 x 3.14 x 0.089 x 0.089 x 22.98)]
= 1.04 m3

12.5 Railing tangga dan void


Panjang tangga = 7.42 m 16.21 m
Panjang void = 8.79 m
Total = 7.42+8.79
16.21 m

12.6 Tandon air atau toren


Jumlah = 1 Unit 1 Unit

12.7 Set Wifi


Jumlah = 1 bh 1 bh

12.8 Parabola
Jumlah = 1 bh 1 bh