Ceiling Installation Method Statement

This method statement is for the ceiling installation works of the Citadines Bacolod Project in Brgy. Bata, Bacolod City. The scope of works includes the installation of gypsum ceiling, cove lights, curtain cove, shadow gap, and bulkheads according to the approved shop drawings, specifications, and construction methodology. Southern Pine Construction Co., Inc. will carry out the works adhering to inspection requirements, conformance criteria, safety plans, and using the outlined materials, personnel, equipment, and subcontractors/suppliers.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views6 pages

Ceiling Installation Method Statement

This method statement is for the ceiling installation works of the Citadines Bacolod Project in Brgy. Bata, Bacolod City. The scope of works includes the installation of gypsum ceiling, cove lights, curtain cove, shadow gap, and bulkheads according to the approved shop drawings, specifications, and construction methodology. Southern Pine Construction Co., Inc. will carry out the works adhering to inspection requirements, conformance criteria, safety plans, and using the outlined materials, personnel, equipment, and subcontractors/suppliers.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

METHOD STATEMENT

PROJECT SUMMARY

PROJECT NAME CITADINES BACOLOD PROJECT REFERENCE

PROJECT
CEILING INSTALLATION WORKS
SUMMARY
START DATE TBD
SITE ADDRESS BRGY. BATA, BACOLOD CITY
END DATE 180 DAY/S
CONTROL
DATE ISSUED
NO.

CONTRACTOR'S COMPANY DETAIL


SOUTHERN PINE CONSTRUCTION CO.,
COMPANY NAME CONTACT NO.
INC.
PROJECT IN CHARGE
SOPINCO BLDG., HERNAEZ STREET, JOB TITLE
ADDRESS
BACOLOD CITY CONTACT
NO.

List of Contents
Section Title

1.0 SCOPE OF WORKS

2.0 CONSTRUCTION PROCEDURES

3.0 INSPECTION REQUIREMENTS

4.0 CONFORMANCE CRITERIA

5.0 MATERIALS

6.0 PERSONNEL ROLES AND RESPONSIBILITIES

7.0 ENVIRONMENTAL REQUIREMENTS

8.0 HEALTH AND SAFETY

9.0 PLANT AND EQUIPMENT


10.0 SUB-CONTRACTORS / SUPPLIERS

11.0 STORAGE AND HANDLING

12.0 REFERENCE

1. SCOPE OF WORKS

Intended Application/Usage: Citadines Bacolod Project.

This method statement is prepared for the Installation of ceiling as part of the the fit-out works
of the Citadines Bacolod Project as described in the relevant drawings and specifications i n c l u
des but not limited to:

Sequence of work and workmanship will be reviewed and resolved during the co-ordination of the
MEPF requirements and other trade works, if any.

2. CONSTRUCTION METHODOLOGY

Installation of Gypsum Ceiling, Cove light. Curtain Cove, Shadow Gap, Bulk Head

a) Site Survey.The receipts of shop drawings approved the consultant the site will be surveyed and any
discrepancies found will be notified to the main contractor for clarification.
b) Setting Out. Setting out and marking will be done as per approved shop drawing, ceiling height of various
areas shall be marked based on the benchmark provided by main contractor, level will be transferred on all
the corners and chalk lines will be marked.
c) Fixing of Wall Angles.The wall angles will be fixed along the marked ceiling depending on the substrate and
approved spacing.
d) Fixing of Hangers.Fixing of hangers will be done as per approved shop drawing layout details and using
hanger anchorage devices of the soffit.The position of the hangers will be marked on the soffit of the slab
which has to be reviewed by main contractor site engineer upon receipt of MEPF clearance hangers.
e) Framework.The framework will be done as per approved shop drawing and with approved materials.
f) Framework Inspection and MEPF Clearance.Upon completion of the framework, respective areas shall be
for approval by owner consultant representative.
g) Ceiling Enclosure. The ceiling enclosure will be done as per approved materials.

3. INSPECTION REQUIREMENTS

Inspection will be carried out according to the approved shop drawings and specifications.

4. CONFORMANCE CRITERIA

Installation works to be carried out according to the approved shop drawings, material/samples
and comply with Specification.

5. MATERIALS

The materials to be used are as follows.

 Gypsum Board 9mm thick


 Metal Furring
 Carrying Channel
 Wall Angle
 Gypsum Screw

6. PERSONNEL ROLES AND RESPONCIBILITIES

Project in Charge
-Monitor project progress and over all site coordination and arrangement.
-Liaise with Sub-contractors.

CAD/Assistant Architect
-Prepare Shop Drawings.
-Prepare As-built Plan.

Field Architect/Engineer
-Full time supervision on scope of admin workers and sub-contractors.
-Request missing information.
-Identifying conflicts in design.

QAQC Engineer
-Prepare Method Statement.
-Prepare Material/Sample Submissions.
-Prepare documents such as:
 Inspection Request.
 Hand-over and Punch listing Report.

Safety
- Prepare Safety Plan.
- Prepare Daily Safety Man-hour.
-Prepare Weekly Toolbox Meeting.
- Monitor Labour Site Safety.

7. ENVIRONMENTAL REQUIREMENTS

Installation works to be carried out complying with Regulations and Specifications.


8. HEALTH AND SAFETY

Installation works to be carried out according to approved safety plan and safety regulations.

9. PLANT AND EQUIPMENT

Plant
 Chalk Line
 Level
 Hand tools (drill, screw gun, gun fastener, metal cutting scissors, measuring tape, )

10. SUBCONTRACTORS/SUPPLIERS

Triumph Hardware

11.0 STORAGE AND HANDLING

Storage and handling according to approved Crimson Logistics Plan.

12.0 REFERENCE

Installation works to be carried out complying with Relevant Standards and Specification