WEEKLY SAF
Contractor Name LAJV
Project Title Limak & Al-Ayuni Joint Venture – Neom Trojena Time Travel Tunnel, Depot
Department /Division HEALTH, SAFETY & ENVIRONMENT
PQP
Incidents Record FAT LTI MTC HPE
# of Incidents Recorded this Week 0 0 0 0
# of Incidents Recorded this Month 0 0 0 0
# of Incidents Recorded Year to Date (YTD) 0 0 0 0
# of Incidents Recorded Project to Date (PTD) 0 0 0 0
FAT - On-Job Fatality, LTI - Lost Time Injury/Illness Case, MTC - Medical Treatment Injury/Illness Case, HPE - H
Occupational Illness / Disease, , FAI - First Aid Injury Case, NM - Near Miss, UA - Unsafe Act, UC - U
Manpower / Manhours
Total Average Manpower this Week 348
Total Manhours this Week 24,360
Manhours this Month 131,400
Manhours Year to Date (YTD) 139,260
Manhours Project to Date (PTD) 139,260
Safe Manhours (without LTI) 139260
Contractor Site HS&E Staff Total HSE Manager
Number of Approved / Qualified HS&E Personnel On Site this
12 2
Week
Contractor Medical Staff Total Nurse Paramedic
Number of Approved / Qualified Medical Personnel On Site 11 2 4
this Week
Contractor Support Staff Total Traffic Coordinator Traffic Foreman
Number of Approved / Qualified traffic Personnel On Site this 0 0 0
Week
Safety Manager Mushtaq Ansari
Signature & Date #VALUE!
Note: This form (Weekly Safety Statistics Report [WSSR]) shall be completed/updated and signed by Con
WEEKLY SAFETY STATISTICS REPORT
Week No
Trojena Time Travel Tunnel, Depot & Vault Excavation Week Period
Contract/WO/SO
RWC OI/D FAI NM UA UC EI
0 0 0 0 2 10 0
0 0 0 0 2 10 0
0 0 0 0 2 10 0
0 0 0 0 2 10 0
tment Injury/Illness Case, HPE - High Potential Event, RWC - Restricted Work Case, OI/D -
Near Miss, UA - Unsafe Act, UC - Unsafe Condition, EI - Environmental Incident
This Week Average Head Count/ This Week Manhours / Worked
Manpower Hours
Manpower added 0
this week
Offsite 0 0
Site Directs 348 24,360
Site Indirects 0 0
Total 348 24,360
HSE Supervisor HSE Officer Environmental Manager
2 6 2
No of Ambulance
First Aid Room First Aiders Ambulance Driver
1 4
1 2
Mushtaq Ansari Contractor's Administrator M
#VALUE! Signature & Date #
completed/updated and signed by Contractor on weekly basis. It shall be submitted to NEOM/PMC safety representative every Friday before 5pm fo
13
Sat-Fri
03rd To 09th Feb 24
4800000946
Contractor Weekly Observations
New Observations Closed Open
Observations Observations
This Week
12 10 2
Human Development - This Week
No of Trainings No of Attendees No of Training
Conducted Hours
OSH Induction 8 83 332
Visitor induction 11 46 23
Trade/Technical 2 37 37
Management 0 0 0
Activity Briefing Forms 12 134 67
(ABF)
Tool Box Talks (TBT) 2 57 14
Contractor Engagement - This Week
# of OSH Inspection 11
# of OSH Meeting 1
# of OSH Audit 0
# Environmental 0
Monitoring
Mustafa
#VALUE!
sentative every Friday before 5pm for review and further handling.