0 ratings0% found this document useful (0 votes) 165 views5 pagesRepublic Act No. 11361
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
‘1310212026, 1457 Republic Act No. 11361
Today is Tuesday, February 13, 2024 t
The LAWPHIL Project
ARELLANO LAW FOVNDATION
PHILIPPINE LAWS AND JURISPRUDENCE DATABANK
Constitution Statutes Executive ssuances Judicial Issuances Other Issuances Jurisprudence International Legal Resources AUSL Exclusive
REPUBLIC OF THE PHILIPPINES
Congress of the Philippines
Metro Manila
‘Seventeenth Congress
Third Regular Session
Begun and held in Metro Manila, on Monday, the twenty-third day of July, two thousand eighteen,
[REPUBLIC ACT NO. 11361, August 08, 2019 ]
AN ACT ENSURING THE CONTINUOUS AND UNINTERRUPTED TRANSMISSION AND DISTRIBUTION OF
ELECTRICITY AND THE PROTECTION OF THE INTEGRITY AND RELIABILITY OF POWER LINES, AND
PROVIDING PENALTIES FOR VIOLATIONS THEREOF
Be it enacted by the Senate and House of Representatives of the Philippines in Congress assembled:
Section 1. Short Title. - This Act shall be referred to as the "Anti-Obstruction of Power Lines Act.”
Section 2. Declaration of Policy. - It is hereby declared the policy of the State to ensure uninterrupted conveyance
of electricity from generating plants to end users, and protect the integrity and reliability of the country’s
transmission, sub-transmission, and distribution systems by keeping the land beneath, the air spaces surrounding
and the are traversed by power lines clear of dangerous obstructions.
The State further recognizes that the continuous conveyance of electricity is a matter of national security and is
essential to sustaining the country’s economic development. Finally, the State acknowledge the crucial role of
property owners in ensuring that power lines remain free of any dangerous and hazardous activities and
improvements
Section 3. Coverage. - This Act shall cover all power lines and other related facilities for the conveyance of
electricity throughout the country.
Section 4, Definition of Terms, - For purposes of this Act, the following terms shall be defined as stated below:
(a) Board of Electrical Engineering refers to the Board created under Republic Act No. 7920, otherwise known
as the New Electrical Engineering Law under the general supervision and administrative control of the
Professional Regulation Commission.
(b) Civil Code of the Philippines refers to Republic Act No. 386, as amended;
(c) Conveyance of electricity refers to the delivery of electricity from the generating plants to the premises of
the end user, through power lines.
(4) Dangerous structure or building refers to those which are structurally unsafe; or which constitute a fire
hazard not provided with safe agress, or are otherwise dangerous to human health; or which in relation to
cxisting use constitute a hazard to safety, health, or public welfare, by reason of inadequate maintenance,
dilapidation, obsolescence, fire hazard, or abandonment; or which otherwise contribute to the pollution of the
site or the community to an intolerable degree. It also refers to any building or structure which has any or all
f the conditions or defects described in Section 1.01.08(b), Republic Act No. 6541, otherwise known as the
‘National Building Code of the Philippines": Provided, That such condition or defect exists to the extent that
lite, health, property, or safety of the public or its occupants are endangered;
(e) Distribution lines refers to the portion of the distribution system pertaining to the lines or wires;
(f) Distribution system refers to the system of wires and associated facilities belonging to a franchised
distribution utlity extending between the delivery points on the transmission or sub-transmission system or
generator connection and the point of connection to the premise of the end user;
ntps:tawphilneUistatutesirepactsrazotSira_11361_20°8.html‘1310212026, 1457 Republic Act No. 11361
(g) Distribution utility (DU) refers to any electric cooperative, private corporation, or government-owned utlity
Which has a franchise to operate a distribution system including those whose franchise covers economic
zones.
(h) Easement fee refers to the just compensation for the legal easement imposed upon the property of the
owner, as determined by the courts in accordance with relevant laws, rules and regulations;
(i) End users refers to any person or entity requiring the supply and delivery of electricity for its own use,
() Hazardous activities refer to burning of waste and other materials, excavation, quarrying, construction, and
other activities of the same nature and character, which are performed partially or wholly inside the power line
corridor which threaten or endanger the continuous and uninterrupted conveyance of electricity
(k) Hazardous improvements refer to structure buildings, and improvements of whatever kind, whether
temporary or permanent in character and regardless of the purpose for which they are intended, which are
located partially or wholly inside the power line corridor which threaten or endanger the continuous and
Uninterrupted conveyance of electricity;
() Joint Congressional Energy Commission (JCEC) refers to the congressional oversight body created under
Section 62 of Republic Act No. 9136, otherwise known as the Electric Power Industry Reform Act of 2001, as
‘amended by Republic Act No. 11285, otherwise known as the Energy Efficiency and Conservation Act,
(m) Other distribution entities refer to entities that own, operate or control one or more distribution systems in
the main grid and off-grid other than DUs such as, but not limited to, Qualified Third Parties and those under
management contracts for the conveyances of electricity;
(n) Owner or operator of power lines refers to generation companies, the transmission owner and its
concessionaire, DUs, other distribution entities, which have ownership or responsibility for the operation and
maintenance of power lines;
(0) Philippine Electrical Code refers to the set of rules which provide for the safety in electrical installation,
construction, operation and maintenance, and the utilization of electricity mandated under the New Electrical
Engineering Law;
(p) Power lines refer to transmission lines, sub-transmission lines, distribution lines, and generation dedicated
point to point lines, and other connection assets including the poles and towers used to support the lines, and
other related facilities constructed or erected used for the purpose of conveyance of electricity;
(q) Power line obstruction refers to any hazardous activity or hazardous improvement and other similar
circumstances that threaten or endanger the continuous and uninterrupted conveyance of electricity;
(1) Sub-transmission lines refer to he portion of the sub-transmission system pertaining to the lines or wires;
(5) Sub-ransmission system refers to the portion of the distribution system that is delineated by the
Connection point to the transmission system and the primary side of all substation transformers;
() Tall growing plants refer to plants, vines, and other plant species, which grow or have the potential to grow
‘more than three (3) meters in height from the ground;
(u) transmission lines refer to the portion of the transmission system referring to the lines or wires; and
(¥) Transmission system refers to the high voltage backbone system of interconnected transmission lines,
Substations and related facilities, located in each of Luzon, Visayas, and Mindanao, or as may be otherwise
determined by the Energy Regulatory Commission in accordance with Section 45 of Republic Act No. 9136,
otherwise known as the Electric Power Industry Reform Act of 2001
Section 5. Power Line Corridor. - The land beneath, the air spaces surrounding, and the areas traversed by power
lines including its horizontal, vertical, and similar clearance requirements shall constitute the power line corridor,
which shall at all times be kept clear and free from any power line obstructions, dangerous structures, hazardous
activities and improvements, and other similar circumstances in accordance with the provisions of this Act.
The horizontal, vertical and other similar clearance requirements that constitute the power line corridor shall be
determined by the Board of Electrical Engineering and approved by the Department of Energy (DOE), and shall be
in accordance with the current Philippine Electrical Code.
In case where the power line corridor is wholly or partially located within a private property not owned by the owner
cr operator of the power lines, it shall constitute a legal easement upon the private property in accordance with the
relevant provisions under Book Il, Title VII, Chapter 2 of the Civil Code, except if the owner or operator of the power
/ntps:tawphineistatutesirepactsraz0otSira_11361_2018.Mtmi‘1310212026, 1457 Republic Act No. 11361
lines shall acquite, lease or enter into other gratuitous or onerous arrangement with the property owner. In the case
of legal easement, the owner of the private property shall be compensated the proper easement fee pursuant to the
provisions of the Civil Code and other relevant laws, rules and regulations,
Section 6. Prohibited Acts. - It is hereby declared unlawful for any person, whether natural or juridical, public or
private, to:
(2) Plant or cause to be planted tall growing plants, including plants of whatever kind, variety, or height within
the power line corridor:
(b) Construct or erect any hazardous improvements within the power line corridor;
(©) Conduct or perform any hazardous activities within the power line corridor,
(4) Prevent or refuse duly authorized agents of the owner or operator of power lines, entry to the property in
the performance of acts enumerated under Section 7: Provided, That such entry is in accordance with the
provisions of Section 8; and
(e) Perform other analogous acts or activities, which will impair the conveyance of electricity and cause
damage to power lines.
Section 7. Prevention and Removal of Power Line Obstruction on Public Property or on Property Owned by Owner
or Operator of Power Lines. - In cases where the power line corridor is wholly or partially located within public
property or on property owned by the owner or operator of the power lines, the owner or operator of power lines
shall have the right to enter the said property to prevent and remove any power line obstruction, and in particular,
perform the following acts:
(@) To conduct maintenance and inspection activities within the power line corridor
(b) To conduct repair or restoration activities within the power line corridor;
(C) To conduct trimming, pruning, cutting, or clearing activities for tall growing plants within the power line
corridor without securing prior clearance or permit from, but with due notice to, the Department of
Environment and Natural Resources (DENR), Philippine Coconut Authority (PCA) in the case of coconut
trees, the concerned local government units (LGUs), and other relevant government agencies.
(@) To remove, dismantle, or demolish hazardous improvements in accordance with the National Building
Code of the Philippines: Provided, That such acts may be carried out without prior clearances or permit from,
but with due notice to, the Department of Public Works and Highways (DPWH), Housing and Land Use
Regulatory Board (HLURB), and the concemed LGUs;
(e) To stop, prevent, or prohibit the conduct of hazardous activities; and
(f Perform other analogous acts or activities, which will cause the prevention and removal of any power line
obstruction.
Section 8. Prevention and Removal of Power Line Obstruction on Private Property. - The owner or operator of
power lines shall have the primary duty and responsibilty to remove power line obstructions. In cases where the
power line corridor is wholly or partially located within a private property, the property owner shall coordinate and
assist the owner or operator of the power lines by facilitating the necessary access in order to perform the acts
‘enumerated in Section 7
The property owner shall have the primary duty and responsibility to prevent power line obstructions and to inform
the owner or operator of the power line of their existence. In the performance of these acts, the property owner shall
be entitled to necessary assistance such as, but not limited to, education, and information, and technical and
‘manpower support from the owner or operator of power lines.
In the event that the property owner fails to perform any duty and responsibility under the preceding paragraphs, the
owner or operator of the power lines shall have the right to access the power line corridor in order to undertake the
acts enumerated under Section 7: Provided, That the entry to private properly may only be effected after due notice
to, and proper coordination with the property owner: Provided, however, That the foregoing shall no longer be
required to avert an imminent danger posed by a power line obstruction in accordance with Article 432 of the Civil
Code.
Section 9. Assistance from Local Goverment Units, Philippine National Police, and Armed Forces of the
Philippines. - In the performance of this acts under Sections 7 and 8, the owner or operator of the power lines may
seek the assistance of LGU officials, the Philippine National Police (PNP), or the Armed Forces of the Philippines
/ntps:tawphineistatutesirepactsraz0otSira_11361_2018.Mtmi‘1310212026, 1457 Republic Act No. 11361
(AFP): Provided, That the LGU officials, the PNP, or the AFP shall render such assistance, as may be deemed
necessary,
Section 10, Information, Education, and Communication. - The owner or operator of the power lines shall have the
duty and responsibility to inform, educate, and communicate to individuals and communities in the areas ir serves
the danger of existing power line obstructions, the urgency of removing them, the manner of preventing them, and
other important related information.
Section 11. Resettlement. - Persons residing in hazardous improvements shall be relocated in accordance with
Republic Act No. 7279, otherwise known as the "Urban Development and Housing Act of 1992," as amended.
Section 12. Gathering, Collecting, Removing,and Transporting of Timber, Forest Products, and Coconut Lumber. -
Gathering, collecting, removing, and transporting of timber, forest products, and coconut lumber as a result of acts
performed under Sections 7 and 8 shall not be considered illegal acts: Provided, That due notice is given to the
DEN, and the PCA in the case of coconut lumber, and other relevant government agencies.
Section 13. Right of Eminent Domain. - Subject to the limitations and procedures prescribed by the law, the power
to exercise the right to eminent domain granted to any person with a franchise to operate, manage, or maintain the
electric power lines shall be governed by the pertinent provisions of the Rules of Court,
Section 14. Permits. - Building officials of LGUs shall require the building owner who will be undertaking
construction or maintenance activities surrounding, adjacent, or proximate to the power line corridor to give due
notice to, and coordinate with the concerned owner or operator of the power lines prior to the issuance of a building
permit
Section 15. Penatties. - Without prejudice to civil and administrative liability, the following penalties shall be imposed
upon any person, both natural and juridical, found guilty of committing any of the prohibited acts specified in Section
6 of this Act
(a) First Offense - the penalty of arresto mayor or a fine of Fifty thousand pesos (P50,000.00), or both, at the
discretion of the court;
(b) Second Offense - the penalty of prison correccional or a fine of One hundred thousand pesos
(100,000,00), or bath, at the discretion of the court; and
(c) Third Offense - the penalty of prison mayor or a fine of Two hundred thousand pesos (P200,000.00), or
both, at the discretion of the court.
If the offenses are committed by or in conspiracy with an officer or employee of the owner or operator of the power
line, such officer or employees shall suffer a penalty one (1) degree higher than the penalty provided herein.
The local building official who issued a building permit n violation of Section 14 of this Act shall be meted a penalty
cone (1) degree higher than the penalty provided herein and shall forthwith suffer the penalty of dismissal,
Section 16, Congressional Oversight. - The Joint Congressional Energy Commission shall exercise oversight
powers over implementation of this Act.
Section 17. Implementing Rules and Regulations. - The DOE shall, in consultation with the National Electrification
Administration, National Power Corporation, Board of Electrical Engineering. National Transmission Corporation,
DPWH, National Housing Authority, HLURB, Housing and Urban Development Coordinating Council, DENR, PCA,
National Commission on the Indigenous Peoples, PNP, AFP, electric power industry stakeholders, and private
stakeholders, issue the implementing rules and regulations of this Act within one hundred twenty (120) days upon
the effectivity of this Act.
Section 18. Separability Clause. - Any portion or provision of this Act, which may be declared unconstitutional or
invalid shall not have the effect of nullifying other portions or provisions hereof.
Section 19. Repealing Clause. - The relevant provisions of Presidential Decree No. 705, as amended, otherwise
known as the Revised Forestry Code of the Philippines, Republic Act No. 8048, as amended, otherwise known as
the "Coconut Preservation Act of 1995," and the "Urban Development and Housing Act of 1992" are hereby
amended. All other laws, ordinances, rules, regulations, and other issuance or parts thereof, which are inconsistent
with this Act, are hereby amended, modified, or repealed accordingly.
Section 20. Effectivity. - This Act shall take effect fifteen (15) days after its publication in at least two (2) newspapers
of general circulation,
Approved,
/ntps:tawphineistatutesirepactsraz0otSira_11361_2018.Mtmi‘1310212026, 1457 Republic Act No. 11361
(SGD.) GLORIA MACAPAGAL-ARROYO (SGD.) VICENTE C. SOTTO II
‘Speaker of the House of Reprasentatives President of the Senate
This Act which is a consolidation of Senate Bill No, 2098 and House Bill No. 6276 was passed by the Senate of the
Philippines and the House of Representatives on May 28, 2019 and May 29, 2019, respectively.
(SGD.) DANTE ROBERTO P. MALING
Acting Secretary General House of Representatives
(SGD.) MYRA MARIE D. VILLARICA
Secretary of the Senate
Approved: AUG 08 2019
(SGD.) RODRIGO ROA DUTERTE
President of the Philippines