Police Department Power Load Calculation

This document summarizes the electrical panel and loads for a new police department location. It includes details on the medium voltage supply panel such as the voltage, location, and source. It then lists the various loads connected to the panel including HVAC, power panels, lighting, an AHU/heater, and a lift station. It provides information on the cable sizes and circuit breaker ratings for each load. Calculations at the bottom summarize the total connected load, demand load, spare capacity, and required line current.

Uploaded by

sales.honestco
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views1 page

Police Department Power Load Calculation

This document summarizes the electrical panel and loads for a new police department location. It includes details on the medium voltage supply panel such as the voltage, location, and source. It then lists the various loads connected to the panel including HVAC, power panels, lighting, an AHU/heater, and a lift station. It provides information on the cable sizes and circuit breaker ratings for each load. Calculations at the bottom summarize the total connected load, demand load, spare capacity, and required line current.

Uploaded by

sales.honestco
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Main MDB - Medium Voltage Supply

Panel : MDB Voltage : 400 / 230 60Hz, 4P,4Wire + Ground Location : BACKSIDE SWITCHGEAR ROOM TM1-ESU-01
Fed From : TM1-ESU-01 SITE NAME : NEW LOCATION FOR POLICE DEPARTMENT

CABLE LOAD VA CB CB CKT PHASE CKT CB CB LOAD VA CABLE


LOAD
SIZE POLE NO. NO. POLE Amp LOAD DESCRIPTION SIZE
DESCRIPTION ØR ØY ØB ØR ØY ØB
(mm²) (A) NO. (mm²)
16800 1 R 2 15803.33
2 SET [4X16+16 E] HVAC-PP 16800 80/100 3 3 Y 4 3 80/100 15803.33 POWER PANEL 1 2 SET [4X16+16 E]
16800 5 B 6 15803.33
13403.333 7 R 8 5816.667
2 SET [4X16+16 E] POWER PANEL 2 13403.33 80/100 3 9 Y 10 3 40/63 5816.667 LIGHTING PANEL 4X16+16 E
13403.33 11 B 12 5816.667
38431.373 13 R 14 6217.053
4CX240+120E AHU+HEATER 38431.37 250 3 15 Y 16 3 40/63 6217.053 LIFT STATION 4X16+16 E
38431.37 17 B 18 6217.053
19 Y 20
SPARE 80/100 3 21 B 22 3 80/100 SPARE
23 R 24
SUB-TOTAL 68,635 68,635 68,635 289,415 27,837 27,837 27,837

Use:
Phase R : 96472 VA CB : 600 AT / 1250 AF
Phase Y : 96472 VA
TOTAL CALCULATION

Phase B : 96472 VA
Connected Load 289415 VA
Demand Factor 0.9
Demand Load: 260.47 KVA
30% Spare load: 78.14 KVA
Total Demand Load: 338.62 KVA
LINE CURRENT: 488.76 A