0% found this document useful (0 votes)
99 views1 page

MPS Boiler Pipe Rack Specifications

The document shows a piping layout with three layers of pipes connected between a new boiler and a plant. Layer 1 includes 5" stainless steel and 2" carbon steel pipes. Layer 2 includes 1", 8", and 6" carbon steel pipes. Layer 3 returns to the boiler with 5" stainless steel, 2" carbon steel, 1" stainless steel, and 2" carbon steel pipes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views1 page

MPS Boiler Pipe Rack Specifications

The document shows a piping layout with three layers of pipes connected between a new boiler and a plant. Layer 1 includes 5" stainless steel and 2" carbon steel pipes. Layer 2 includes 1", 8", and 6" carbon steel pipes. Layer 3 returns to the boiler with 5" stainless steel, 2" carbon steel, 1" stainless steel, and 2" carbon steel pipes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

979 240 170 228

LAYER 1
FROM NEW BOILER PIPE 5" SS 304 SMLS Sch.10S (FEED WATER BOILER) PIPE 5" SS 304 SMLS Sch.10S (FEED WATER BOILER)
PIPE 2" CS WLD Sch.40 (COMPRESSOR) PIPE 2" CS WLD Sch.40 (COMPRESSOR)
PIPE 2" CS WLD Sch.40 (DISEL INCOMING) PIPE 2" CS WLD Sch.40 (DISEL INCOMING)
PIPA GAS (OUTOFSCOPE) PIPA 8" GAS (OUTOFSCOPE)

980 240 170 211

A LAYER 2
PIPE 1" SS 304 SMLS Sch.10S (CONDENSATE RETURN)
200 PIPE 1" CS WLD Sch.40 (PIPE BLOWDOWN)
TO PLANT

PIPE 8" CS SMLS Sch.40 (STEAM TO HEADER COAL BOILER)


PIPE 6" CS SMLS Sch.40 (STEAM TO TF1)
220 350 280 240 510

SECTION A LAYER 2 B
LAYER 3

220 350 280 240 511


PIPE 1" SS 304 SMLS Sch.10S (CONDENSATE RETURN)
PIPE 1" CS WLD Sch.40 (PIPE BLOWDOWN)
FROM NEW BOILER

PIPE 8" CS SMLS Sch.40 (STEAM TO HEADER COAL BOILER)


PIPE 6" CS SMLS Sch.40 (STEAM TO TF1)

SECTION PIPE RACK GSM

0 24/1/2024 GSM AAJ R0 FOR CONSTRUCTION


NO. DATE ISSUED BY ISSUED TO REV DESCRIPTION
FROM NEW BOILER
TO PLANT

PROJECT :

AAJ PROJECT
SECTION B LAYER 3

OWNER :

CONTRACTOR :

PT. GREGAH SUKSES MANDIRI ENGINEERING


PIPE 5" SS 304 SMLS Sch.10S (FEED WATER BOILER)
TO PLANT

THIS INFORMATION OR DATA CONTAINED HEREIN IS PROPRETARY TO PT.GSME


AND IS NOT TO BE COPIED. REPRODUCED, DUPLICATED, OR DISCLOSED TO OTHERS,

PIPE 2" CS WLD Sch.40 (COMPRESSOR)


IN WHICLE OR IN PART, WITHOUT PRICR WRITTEN CONSENT OF PT.GSME

PIPE 1" SS 304 SMLS Sch.10S (CONDENSATE RETURN) C:\Users\GSME\Downloads\LOGO KAN-.png C:\Users\GSME\Downloads\LOGO bsi.png
C:\Users\GSME\Downloads\LOGO bsi.png

350 280 130 110 130 170 PIPE 2" CS WLD Sch.40 (DISEL INCOMING)
PIPE 1" CS WLD Sch.40 (PIPE BLOWDOWN) SIGN DATE

DRAWN BY PT GREGAH SUKSES MANDIRI ENGINEERING


PIPE 8" CS SMLS Sch.40 (STEAM TO HEADER COAL BOILER)
DESIGN BY PT ASIANAGRO AGUNGJAYA
PIPE 6" CS SMLS Sch.40 (STEAM TO TF1)
CHECKED BY PT ASIANAGRO AGUNGJAYA

APPROVED BY PT ASIANAGRO AGUNGJAYA


350 280 130 110 130 170
APPROVED PT ASIANAGRO AGUNGJAYA

PLANNING :

SHOP DRAWING
DRAWING TITLE :

PIPE SECTION
PIPE RACK MPS BOILER
SECTION PIPERACK EXISTING
DRAWING NO. : SHEET

AAJ-PR-MPS-001 2 3