100% found this document useful (1 vote)
2K views3 pages

Testing and Commissioning Forms Hybrid or Off Grid FINAL

The document provides testing and commissioning guidelines for a solar energy system. It includes checking that the inverters and components are properly installed, connected, and secured. System parameters like voltage, current, and power levels are monitored during testing. If all installation and performance checks are passed, the client signs a certificate of acceptance for the new solar energy system.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views3 pages

Testing and Commissioning Forms Hybrid or Off Grid FINAL

The document provides testing and commissioning guidelines for a solar energy system. It includes checking that the inverters and components are properly installed, connected, and secured. System parameters like voltage, current, and power levels are monitored during testing. If all installation and performance checks are passed, the client signs a certificate of acceptance for the new solar energy system.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
  • Testing and Commissioning: Outlines the step-by-step procedure for conducting testing and commissioning of solar panel systems, including safety checks and operational validations.
  • Technical Parameters: Provides a template for recording technical parameters related to the grid connection, inverter output monitoring, and grid monitoring.
  • Sign-Off: Includes spaces for comments and signatures to sign off on the completion and acceptance of the testing procedures.

TESTING AND COMMISSIONING

Client Name: Date: Dec 6, 2023


Name of Establishment:
Address:
Solar Panel KW Capacity: # of Panels:
Inverter KW Capacity: # of Inverters:
Battery Capacity: # of Batteries:

Ensure that all items mentioned below are being followed:

1. Check if the Inverter is firmly installed and if all bolts are reliably tightened. For an inverter
installed on a metal supporter, make sure each bolt is tightened and the support has enough
load bearing capacity.

2. Make sure that the location of the Inverter has enough ventilation in order to maintain the
working temperature and to avoid overheating.

3. Check if all cables in the system are firmly connected without any missed or wrong
connection, and especially check if all positive and negative poles are correct.

4. Check if the PV Cable and Wire sizes are correct and check if the MC4 connectors and
terminal lugs are crimped properly

5. Make sure the DC input voltage of the inverter is within the expected input voltage of the
inverter indicated in the specification.

6. Applicable warning signs and labels are posted appropriately especially on the protection
devices.

7. Ensure that the whole system is properly grounded.

8. If the Solar Panels are installed in the roof, make sure that there is no leak after the solar is
installed.

9. The job site is clean and orderly and tools are removed from the site after installation.

10. Make sure the Automatic Transfer Switch works when Grid is out and the critical loads
operate during power outage.

GDC-TCH-TAC-HYB-10-REV.1
TECHNICAL PARAMETERS

Grid Connection: Inverter Rated Output:


Grid Voltage : Inverter Rated Voltage:

Inverter Output Monitoring


PV Input PV PV Input Battery Battery Inverter Inverter
Frequenc
Time Power Voltage Current Voltage Current Voltage Current
y (Hz)
(kW) (Volts) (Ampere) (Volts) (Ampere) (Volts) (Ampere)

Grid Monitoring Critical Loads:


Time Power (kW) Ampere Voltage 1.
2.
3.
4.
5.
6.

For Online Monitoring (if applicable):


Website:
Username:
Password:

Inverter Settings:

GDC-TCH-TAC-HYB-10-REV.1
Comments:

If all conditions mentioned above are being followed and passed the working parameters, please request
the client to sign the certificate of acceptance.

Performed by: Reviewed/Approved by:

MICHAEL GLENN ECOBEN ENGR. JOSHUA BONGCAC

GDC-TCH-TAC-HYB-10-REV.1

You might also like