TESTING AND COMMISSIONING
Client Name: Date: Dec 6, 2023
Name of Establishment:
Address:
Solar Panel KW Capacity: # of Panels:
Inverter KW Capacity: # of Inverters:
Battery Capacity: # of Batteries:
Ensure that all items mentioned below are being followed:
1. Check if the Inverter is firmly installed and if all bolts are reliably tightened. For an inverter
installed on a metal supporter, make sure each bolt is tightened and the support has enough
load bearing capacity.
√
2. Make sure that the location of the Inverter has enough ventilation in order to maintain the
working temperature and to avoid overheating.
√
3. Check if all cables in the system are firmly connected without any missed or wrong
connection, and especially check if all positive and negative poles are correct.
√
4. Check if the PV Cable and Wire sizes are correct and check if the MC4 connectors and
terminal lugs are crimped properly
√
5. Make sure the DC input voltage of the inverter is within the expected input voltage of the
inverter indicated in the specification.
√
6. Applicable warning signs and labels are posted appropriately especially on the protection
devices.
√
7. Ensure that the whole system is properly grounded.
√
8. If the Solar Panels are installed in the roof, make sure that there is no leak after the solar is
installed.
√
9. The job site is clean and orderly and tools are removed from the site after installation.
√
10. Make sure the Automatic Transfer Switch works when Grid is out and the critical loads
operate during power outage.
√
GDC-TCH-TAC-HYB-10-REV.1
TECHNICAL PARAMETERS
Grid Connection: Inverter Rated Output:
Grid Voltage : Inverter Rated Voltage:
Inverter Output Monitoring
PV Input PV PV Input Battery Battery Inverter Inverter
Frequenc
Time Power Voltage Current Voltage Current Voltage Current
y (Hz)
(kW) (Volts) (Ampere) (Volts) (Ampere) (Volts) (Ampere)
Grid Monitoring Critical Loads:
Time Power (kW) Ampere Voltage 1.
2.
3.
4.
5.
6.
For Online Monitoring (if applicable):
Website:
Username:
Password:
Inverter Settings:
GDC-TCH-TAC-HYB-10-REV.1
Comments:
If all conditions mentioned above are being followed and passed the working parameters, please request
the client to sign the certificate of acceptance.
Performed by: Reviewed/Approved by:
MICHAEL GLENN ECOBEN ENGR. JOSHUA BONGCAC
GDC-TCH-TAC-HYB-10-REV.1