0% found this document useful (0 votes)
64 views3 pages

Construction Cost Breakdown for Project

This document provides a cost estimate for building a shed located in Pascua Beachfront in Ilocos Norte, Philippines. It includes costs for excavation, slab flooring, footings, columns, masonry walls, floor finishing, and painting. The total estimated cost is PHP 58,769.18 which includes materials, labor, markups, and taxes for excavation, concrete work, masonry, finishing, and painting.

Uploaded by

Jun Narvaez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
64 views3 pages

Construction Cost Breakdown for Project

This document provides a cost estimate for building a shed located in Pascua Beachfront in Ilocos Norte, Philippines. It includes costs for excavation, slab flooring, footings, columns, masonry walls, floor finishing, and painting. The total estimated cost is PHP 58,769.18 which includes materials, labor, markups, and taxes for excavation, concrete work, masonry, finishing, and painting.

Uploaded by

Jun Narvaez
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Name of Project PASCUA BEACHFRONT SHED

LOCATION CALIOET PASQUQUIN ILOCOS NORTE


Name of Contractor RDN DESIGNS & ENGINEERING

Structure Excavation Volume = 1.728

Quantity Unit Description Unit Cost Amount

1.73 Cu.m Excavation 800 ₱ 1,382.40


Materials ₱ 1,382.40
Labor ₱ 552.96
Direct Cost ₱ 1,935.36
Mark up ₱ 580.61
VAT ₱ 301.92
Total Cost ₱ 2,817.88

SLAB FLOORING volume = 2.4

Quantity Unit Description Unit Cost Amount

2.40 Cu.m Embankment PHP 1,100.00 ₱ 2,640.00


Materials ₱ 2,640.00
Labor ₱ 1,056.00
Direct Cost ₱ 3,696.00
Mark up ₱ 1,108.80
Vat ₱ 576.58
Total Cost ₱ 5,381.38
Footings 4
Length 0.6
width 0.6
depth 0.5
Volume 0.72

Reinforced Concrete Volume = 0.72

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

5 Bags Cement 240.00 ₱ 1,209.60


1 Cu.m Sand 1,100.00 ₱ 887.04
0 Cu.m Gravel 1,600.00 ₱ 645.12
Pcs 16mm dia. X 6m 380.00 ₱ -
1 Pcs 12mm dia. X 6m 210.00 ₱ 302.40
6 Pcs 10mm dia. X 6m 160.00 ₱ 921.60
10 Kg #16 Tie wires 75.00 ₱ 750.00
Materials ₱ 4,715.76
Labor ₱ 1,886.30
Direct Cost ₱ 6,602.06
Mark up ₱ 1,980.62
VAT ₱ 1,029.92
Total Cost ₱ 9,612.61
Columns 4
Length 0.3
width 0.3
Height 3
Volume 1.08

Reinforced Concrete Volume = 1.08

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

8 Bags Cement 240.00 ₱ 1,814.40


1 Cu.m Sand 1,100.00 ₱ 1,386.00
1 Cu.m Gravel 1,600.00 ₱ 1,008.00
- Pcs 16mm dia. X 6m 380.00 ₱ -
8 Pcs 12mm dia. X 6m 210.00 ₱ 1,680.00
12 Pcs 10mm dia. X 6m 160.00 ₱ 1,920.00
4 Kg #16 Tie wires 75.00 ₱ 300.00
Materials ₱ 8,108.40
Labor ₱ 3,243.36
Direct Cost ₱ 11,351.76
Mark up ₱ 3,405.53
VAT ₱ 1,770.87
Total Cost ₱ 16,528.16
Masonry
Length 20
Width 0.9
Area 18

Masonry Area = 18

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

Pcs 6" CHB 20.00 ₱ -


225 Pcs 4" CHB 15.00 ₱ 3,375.00
12 Pcs 10mm dia. X 6m 160.00 ₱ 1,920.00
9 Bags Portland Cement 265.00 ₱ 2,385.00
0.90 Cu.m Sand 1,100.00 ₱ 990.00
0 Cu.m Gravel 1,600.00 ₱ 720.00
25 Kgs #16 Tie wires 75.00 ₱ 1,875.00
Materials ₱ 11,265.00
Labor ₱ 4,506.00
Direct Cost ₱ 15,771.00
Mark up ₱ 4,731.30
VAT ₱ 2,460.28
Total Cost ₱ 22,962.58
Length 6
Width 4
Area 24
Floor Finishing Area = 24

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

10 Bags Portland Cement PHP 240.00 2304.00


2 Cu.m Sand PHP 1,100.00 1689.60
Materials ₱ 3,993.60
Labor ₱ 1,597.44
Direct Cost ₱ 5,591.04
Mark up ₱ 1,677.31
VAT ₱ 872.20
Total Cost ₱ 8,140.55

Painting Works area 24

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

7 Lites MARINE PAINT PRIMER 720.00 5184.52


5 liters MARINE PAINTTOPCOAT 560.00 2688.00
4 Liters Masonry putty 165.00 660.00
12 Liters Skimcoat 115.00 1380.00
1 PC PAINT ROLLER 520.00 520.00
1 PC PAINT BRUSH 4" 65.00 65.00
Materials ₱ 10,497.52
Labor ₱ 4,199.01
Direct Cost ₱ 14,696.53
Mark up ₱ 4,408.96
VAT ₱ 2,292.66
Total Cost ₱ 21,398.14
Length 6
width 4
area 24

Roofing Area 28.8

QUANTITY UNIT DESCRIPTION UNIT COST AMOUNT

518 PCS PALM THATCH MATERIALS PHP 18.00 9,331.20


0 Pcs GA # 26 PL. G.I. END FLASHING PHP 1,105.00 0.00
0 LM SPANDREL OVERHANG + FRAMING PHP 715.00 0.00
0 Pcs GA # 26 PL. G.I. Gutter PHP 1,105.00 0.00
1 lot roofing accessories and fasteners PHP 3,500.00 3,500.00
0 GALLONS Roof paint RE-TOUCH PHP 950.00 0.00
Materials ₱ 12,831.20
Labor ₱ 6,415.60
Direct Cost ₱ 19,246.80
Mark up ₱ 5,774.04
VAT ₱ 3,002.50
Total Cost ₱ 28,023.34

TOTALCOST EXCL. STEELFRAME & ROOF PHP 87,561.30

GRAND TOTALCOST TO COMPLETE PHP 114,864.64