Standard Operating Procedure for
Loop Wiring Connection Modification PLTGU Blok 2 PCU 1
PT. Indonesia Power Semarang PGU
End User: PT. INDONESIA POWER SEMARANG PGU Doc. No.
PO/Contra - Proj. no. ENP20016
ct/SKP No: Project UPGRADE DCS PLTGU BLOK 2 (GTG 2.1)
Prepared: DBN
Appr. WW Customer PT. INDONESIA POWER SEMARANG PGU
Title STANDARD OPERATING PROCEDURE Resp. dept IAEN/2869 Status INFORMATION
Lan: Rev: Page
ABB SAKTI INDUSTRI
EN 00 1
No of Page
4
PT. ABB Sakti Industri Doc Type. Standard Operating Procedure
Industrial Automation
Energy Industry
Distributed Control System
Doc No.
Revision 00
Page 2 of 4 Language ENG
Customer PT. Indonesia Power Semarang PGU Reviewed/Checked MJ
Prepared DBN Approval WW
Standard Operating Procedure
1. Purpose
- LOOP WIRING CONNECTION MODIFICATION PLTGU BLOK 2 PCU 1
2. Scope
- NTCF02 - NTCL01
- NTCF03 - NKLS01
- NFTP01 - IEB800
- NKTT01
Documents: Standard Operating Procedure
PT. ABB Sakti Industri Doc Type. Standard Operating Procedure
Industrial Automation
Energy Industry
Distributed Control System
Doc No.
Revision 00
Page 3 of 4 Language ENG
Customer PT. Indonesia Power Semarang PGU Reviewed/Checked MJ
Prepared DBN Approval WW
3. Execution Plan
1. Mounting
- Insert the tabs of the circuit board into the proper slots of the termination panel
standoff and slide the circuit board into position.
2. Communication Cable (NTCL01 – NTCL01)
The communication cable connects the NTCL01 termination unit to Cnet.
- Using coaxial cable, connect the cable to the termination unit at the appropriate
BNC connector (loop 1 or 2).
3. Power Wiring
There is one terminal (E1) that connects to +24 VDC and one terminal (E2) that
connects to system common.
- Attach a wire from a source of +24 VDC within the cabinet to the E1 terminal on
the NTCL01 termination unit.
- Attach a wire from system to the E2 terminal of the NTCL01 termination unit.
4. Termination Unit Cable
After mounting the termination unit to the field termination panel, connect a
NKLS01 termination cable.
- Install the hooded end of the NKLS01 cable to the module mounting unit (MMU)
backplane slot assigned to the NIS21 module.
- Insert the socket connector end of the cable into P1 of the NTCL01 termination
unit.
5. Communication Cable (NTCF02 – NTCL01 – NTCF03)
The communication cable connects the NTCL01 termination unit to Cnet.
- Using coaxial cable, connect the cable to the termination unit at the appropriate
BNC connector (loop 1 or 2).
Documents: Standard Operating Procedure
PT. ABB Sakti Industri Doc Type. Standard Operating Procedure
Industrial Automation
Energy Industry
Distributed Control System
Doc No.
Revision 00
Page 4 of 4 Language ENG
Customer PT. Indonesia Power Semarang PGU Reviewed/Checked MJ
Prepared DBN Approval WW
6. Mounting (Termination Unit Circuit Board – Field Termination Panel)
- Secure the termination unit circuit board to the field termination panel with two No.
10 screws.
7. Installation Complete
The NTCL01 termination unit is ready for operation if:
- The circuit board is mounted on the field termination panel.
- All required cables are connected to the termination unit.
- Power is connected and is applied to the termination unit.
Documents: Standard Operating Procedure