0% found this document useful (0 votes)
70 views4 pages

SOP Loop Wiring Connection Modification

Loop wiring
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views4 pages

SOP Loop Wiring Connection Modification

Loop wiring
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Standard Operating Procedure for

Loop Wiring Connection Modification PLTGU Blok 2 PCU 1


PT. Indonesia Power Semarang PGU

End User: PT. INDONESIA POWER SEMARANG PGU Doc. No.

PO/Contra - Proj. no. ENP20016


ct/SKP No: Project UPGRADE DCS PLTGU BLOK 2 (GTG 2.1)
Prepared: DBN
Appr. WW Customer PT. INDONESIA POWER SEMARANG PGU
Title STANDARD OPERATING PROCEDURE Resp. dept IAEN/2869 Status INFORMATION

Lan: Rev: Page

 ABB SAKTI INDUSTRI


EN 00 1

No of Page
4
PT. ABB Sakti Industri Doc Type. Standard Operating Procedure
Industrial Automation

 Energy Industry


Distributed Control System
Doc No.

Revision 00

Page 2 of 4 Language ENG

Customer PT. Indonesia Power Semarang PGU Reviewed/Checked MJ

Prepared DBN Approval WW

Standard Operating Procedure

1. Purpose

- LOOP WIRING CONNECTION MODIFICATION PLTGU BLOK 2 PCU 1

2. Scope

- NTCF02 - NTCL01
- NTCF03 - NKLS01
- NFTP01 - IEB800
- NKTT01

Documents: Standard Operating Procedure


PT. ABB Sakti Industri Doc Type. Standard Operating Procedure
Industrial Automation

 Energy Industry


Distributed Control System
Doc No.

Revision 00

Page 3 of 4 Language ENG

Customer PT. Indonesia Power Semarang PGU Reviewed/Checked MJ

Prepared DBN Approval WW

3. Execution Plan

1. Mounting
- Insert the tabs of the circuit board into the proper slots of the termination panel
standoff and slide the circuit board into position.

2. Communication Cable (NTCL01 – NTCL01)


The communication cable connects the NTCL01 termination unit to Cnet.
- Using coaxial cable, connect the cable to the termination unit at the appropriate
BNC connector (loop 1 or 2).

3. Power Wiring
There is one terminal (E1) that connects to +24 VDC and one terminal (E2) that
connects to system common.
- Attach a wire from a source of +24 VDC within the cabinet to the E1 terminal on
the NTCL01 termination unit.
- Attach a wire from system to the E2 terminal of the NTCL01 termination unit.

4. Termination Unit Cable


After mounting the termination unit to the field termination panel, connect a
NKLS01 termination cable.
- Install the hooded end of the NKLS01 cable to the module mounting unit (MMU)
backplane slot assigned to the NIS21 module.
- Insert the socket connector end of the cable into P1 of the NTCL01 termination
unit.

5. Communication Cable (NTCF02 – NTCL01 – NTCF03)


The communication cable connects the NTCL01 termination unit to Cnet.
- Using coaxial cable, connect the cable to the termination unit at the appropriate
BNC connector (loop 1 or 2).

Documents: Standard Operating Procedure


PT. ABB Sakti Industri Doc Type. Standard Operating Procedure
Industrial Automation

 Energy Industry


Distributed Control System
Doc No.

Revision 00

Page 4 of 4 Language ENG

Customer PT. Indonesia Power Semarang PGU Reviewed/Checked MJ

Prepared DBN Approval WW

6. Mounting (Termination Unit Circuit Board – Field Termination Panel)


- Secure the termination unit circuit board to the field termination panel with two No.
10 screws.

7. Installation Complete
The NTCL01 termination unit is ready for operation if:
- The circuit board is mounted on the field termination panel.
- All required cables are connected to the termination unit.
- Power is connected and is applied to the termination unit.