PROJECT : MITTAL MAIN GATE - 1 CANOPY FOUNDATION
BAR BENDING SCHEDULE
DEVELOPMENT
BBS - FOUNDATION LENGTH
Reference Drawaing details
BBS Code
Location Mittal Main Gate-1 M25 54D S. No. 2
Level 1 M30 50D Drg. No. 2
Structure Details Canopy foundation M35 44D Particulars
Concrete Grade 35 M40 40D Revision
Dimension In MM standard Net
No. of Bars Per No. of Total Cutting
Location/G Dia Of Bar No Of No Of SHAPE lap Laps Nos of Bend Net Length in
S. No. Partiiculars Member Bars Per No. Shape Length in
RID NO. MM Member SET CODE Nos of length(IN length bend Deduction M=
(theortical) Member Of Bar a b c meter 16 22 25 32 RAMARKS
laps MM) (in mm)
Bottom With epoxy
1 200 22 2 6 10.00 10.00 120 200 560 1860 560 1100 2 88 2.89 347.04 - 347.04 - -
coated 22 mm rebar
Top With epoxy coated
2 201 16 2 6 10.00 10.00 120 200 560 1860 560 800 2 64 2.92 349.92 349.92 - - -
16 mm rebar
Connetion Bar (epoxy
3 202 16 6 6 4.00 4.00 144 201 100 200 100 800 2 64 0.34 48.38 48.38 - - -
coated 16mm)
Pedestal Bar ( Epoxy
4 203 25 1 6 12.00 12.00 72 111 400 1706 1250 1 50 2.06 148.03 - - 148.03 -
coated 25 mm)
Total Length (RM) 398.304 347.040 148.032 -
Unit Wt. 1.580 2.470 3.850 6.310
Total Weight in Kg 629.320 857.189 569.923 - 2056
Total Weight (In MT) = 2.06 2.056
Prepaired BY ( ) APPROVED BY ( )
Prepared by Page 1 of 1