0% found this document useful (0 votes)
47 views14 pages

120kwsolar Sumbawa-System Configuration

Uploaded by

ddh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
47 views14 pages

120kwsolar Sumbawa-System Configuration

Uploaded by

ddh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

SELF-SUFFICIENT POWER SOLUTION

Hybrid Solar System


120kw Solar Panel 430kwh LFP Battery

--- Feasible & Flexible, Stable & Sustainable On-grid/Off-


grid/Hybrid Energy Solution
Application Scenarios

• 1. Regions without grid power or unstable grid supply, like


remote countryside, islands, isolated places.
• 2. Schools, hospitals and other public utilities needs stable &
constant energy supply.
• 3. Factories wish to restructure energy consumption.
• 4. Regions with step electricity rate or peak-valley rate policy,
to store the energy at low rate hours and using at high rate
hours.
• 5. Individuals or entities who wish to be independent at
energy supply to be less depending on grid power.
System Diagram

Grid
Load

PV array PV
Combiner box

HPS hybrid inverter

LFP battery

Monitoring system
System Diagram Block

Grid Power

Hybrid
PV panel array PV combiner box Solar Load
Inverter

Battery
pack
Operation Mode

• On-grid Mode

• I. Zero Export
• When Zero Export actived, the redundant PV power is limited to flow to
the grid.

• II. Load First (Zero Export is optional)


• PV generation will be first used to supply the load, the excess part will be
used to charge the battery;

• III. Battery First (Zero Export is optional)


• PV generation is used to charge battery first ,the excess PV power will be
used to supply the load.
Operation Mode

• IV. Economy Mode (Zero Export is optional)


• 1.During off-peak period, the working mode is same as battery-first mode.
• 2.During shoulder period:
a) Battery doesn’t discharge, grid won’t charge battery.
• 3.During peak duration:
a) Grid won’t charge battery.

• V. Peak Shaving (Zero Export is optional)


Operation Mode

• Off-grid Mode

• 1. When PV power is greater than load consumption, PV is used to supply


load and charge battery.
• 2. When PV power is less than load consumption, battery will discharge
until reaching the under voltage threshold, then,
• a) In default setting the inverting part (bidirectional DCAC) will stop
working, all the PV power will be used to charge battery.
• b) If generator is connected, HPS/PCS will start generator using its relay
output, generator will supply load and charge battery.
Operation Mode

• Optional Function

• I. Generator connection(dry contact control)


• In off grid mode: When battery voltage is approaching under voltage threshold,
HPS/PCS will start generator to supply load and charging battery. HPS/PCS will stop
supplying power, only using generator power to charge battery.
• If generator is started,
• 1.When PV power is greater than charging power, PV power will be limited to max
battery charging power.
• 2.When PV power is less than max charging power, generator can be used to
charge battery according to customer’s requirement.
• 3.When battery is full, HPS will stop the generator and go back to off-grid mode.
• 4.When there is no grid, generator can connect to HPS’s grid terminal. If grid and
generator need to connect to HPS/PCS simultaneously, an ATS will be needed for
the connection.
Solar Panel

Mono solar panel 620W

• MBB and half-cut technology to improve


module reliability and reduces loss
• Higher power output effectively reduces
BOS and LCOE
• 25-year performance warranty
• 12-year product warranty
• 550W/600W/660W also optional
Mounting Structure

• Mounting Structure

• For roof top or ground mounting


• Tailored to the project
• Adaptable for all kinds of installation
requirement
• Aluminum or hot-dip galvanizing steel
materials ensure excellent resistance to
corrosion
• Easy assemble for high efficiency
installation
• Excellent mechanical property
PV Combiner Box

• PV Combiner Box

• Lightening protection
• Optional string monitoring function
• IP 65 environment compatibility
• Flexible design,2/20 input optional
• RS 485 communication interface
• Input fuse for over current protection
Scontroller inbuilt for monitoring
Hybrid Solar Inverter

• Hybrid Solar Inverter

• Modular design Isolation Transformer


• Seamless on/off-grid transfer,easy
maintenance
• Scalable design, quadruple capacity by
paralleling 4 units
• Hot back-up
• One inverter fails in parallel system, the
other(s) takes over seamlessly.
Lithium-Ion Battery

• Battery Rack, Cabinet or Container

• Safe and reliable


• Self-designed 3 level BMS
• Easy installation and maintenance
• Standard rack and module, front
maintenance
• High power density
• LFP battery,≥130Wh/kg
• Flexible customization
• For different application and
installation
Monitoring

• System Monitoring Unit


• Local webserver for easy configuration
• Supports export control with meters
• Up to 32 inverters connection
• Multi-function and high performance

• Data logger for overall system monitoring, collect


operation data from different units via Modbus
• RS485 and communicate with server via
internet.