1
AT006000000053461
BEFORE MAHARASHTRA REAL ESTATE APPELLATE TRIBUNAL
MUMBAI
APPEAL NO. AT006000000053461 0F 2021
IN
coMPLAINT NO.CC006000000192332
Mr. Vijay Choksi l
301, Ghumman Villa (Palazzo) l
Plot No.53, Road No.12, Vile Parle (W), l
I\4umbai- 400 049 l ,..Appellant
-vs-
1) SSSC Escatics Pvt. Ltd. l
2) Wadhwa Group Holding Pvt. Ltd. l
Ram Krupa Bldg., Devji BhimjiLane l
l4athuradas Road, Kandivali (West), ]
lYumbai- 400 067. l ,..Respondents
Adv Ms. lennifer Michael for Appellant.
Adv Mr. Bhupesh Dhumatkar for Respondent No.l.
None for Respondent No.2.
CORAM : SHRIRAM R. JAGTAP, MEMBER (J) &
S.S. SANDHU, MEMBER (A)
DATE : 18th October,2O22.
(THROUGH VIDEO CONFERENCING)
JU DG MENT
[PER: SHRIRAM R. ]AGTAP, MEMBER (J.)]
The complainant (allottee) being dissatisfied with order
w dated 24th September 2021 passed by learned Memberl, MahaRERA
1/21
2
AT005000000053461
(for short "Authority"), whereby the learned Authority instead of
granting reliefs sought in the complaint, directed the respondents to
execute agreement for sale, has preferred instant appeal on the
grounds enumerated in the appeal.
21 For the sake of convenience, we would refer the parties in
their original status as complainant and respondents as referred in the
impugned order.
3l It is revealed from the pleadings that the respondents have
jointly undertaken redevelopment of building known as "The Nest" on
the land bearing CTS N0.196(Part), situated at Ganesh Chowk, Bhavans
Camp, D.N. Nagar, Andheri (West), Mumbai under S"R.A. Scheme
Regulation 33(10) of the Development Control Rules, 1991. On 19th
July 2013, the complainant booked a 3 BHK flat bearing No.8-502 in
the project of the respondents for total consideration of
Rs.2.62,35,000^ and paid Rs.1,20,00,000/- to the respondents by
cheque. Pursuant to the said booking, the respondent no.1 issued
allotment letter dated 24th July 2013 to the complainant. Subsequently,
the complainant made payment of entire consideration amount i.e.
Rs.2,62,35,0561- to respondent no.1 from time to time.
4l Since 2015, the complainant has been enquiring about the
date of possession, but respondent no.1 has been giving evasive reply
2/21
3
AT006000000053461
to complainant. It being on going project, the respondents have
registered the project with MahaRERA and declared the date of
possession as 31.3.2019. However, the respondents failed to hand over
possession of the subject flat to complalnant by 31.3.2019. The
respondents without obtaining consent of the complainant have
unilaterally revised the date of possession to 31.3.2020
sl The respondent no.1 represented to the complainant that
the area of the subject flat is 2385 [Link]. A letter of allotment also
shows saleable area of the subject flat as 2385 [Link].(221 sq. mt.).
However, on the website of MahaRERq the area of subject is shown as
976.82 [Link]. (90.25 [Link].) which depicts that there is short fall ln the
area of subject flat. The respondent no.1 duped the complainant. The
complainant suffered economic loss because of misrepresentation of
respondents. The respondents have violated the provisions of Sections
12 and 18 of RERA and thereby constrained the appellant to file
complaint.
6l The complainant has sought following reliefs -
(i) To direct the respondents to refund Rs.2,62,35,056/- to the
,'{ complainant with interest.
(ii) To direct the respondents to pay compensation of
Rs.3,00,000/- to the complainant for mental stress and agony
3/2t
4
AT006000000053461
(iii) To award costs of R.3,00,000/-.
7) The respondent no.1 appeared in the complaint and
remonstrated the complaint by filing affidavit-in-reply. The crux of the
contentions of the respondent no.1 which emerged from the impugned
order and from material on record, is that the respondent no.1 did not
make representation as alleged by the complainant. The complainant
has failed to make out any case that he has suffered loss due to mis-
representation of the respondent no.1 which is pre-requisite condition
to invoke Section 12 of RERA. The respondent no.1 had never promised
any date of possession to complainant. The project is facing numerous
difficulties such as -
(a) The slum-dwellers did not vacate thetr hutments.
(b) The delay in obtaining permissions from the concerned
Authorities, policy paralysis of the authorities of the Government, delay
at the level of tvlunicipal Corporation of Gr. Mumbai etc. which were
beyond the control of the respondent no.1.
(c) Non clearance of access road.
(d) A pandemic of Covid 19 and stringent restrictions that
affected business of promoter severally and constructions of the
V building was stopped due to non-availabiltty of essential construction
material, transport means etc. which led to suspension of work and
4/21
5
aToo6000000053461
services of man power. Therefore, the respondent no.1 had no option
but to get extension of period for timely completion of project on
lvlahaRERA website as 30.9.2021. The respondent no.1 endeveoured
to complete the project within time line.
8I The respondent no.1 has not denied that in 2013/ the
complainant booked subject flat for total consideration of
Rs.2,62,35,000/- excludlng other charges. The respondent No.1 has
denied that the complainant has paid Rs.90,00,000/- plus
Rs.10,00,000/- in cash. In fact, the complainant has only paid
Rs.1,62,35,000/-. The respondent no.1 claimed that the complainant
booked the subject flat for investment purpose. The complainant was
apprised by respondent no.1 that the respondent no.1 was always
willing to give timely possession of the flat to the complainant, but
because of aforementioned force majeure factors, the respondent no.1
could not complete the poect. The respondent no.1 has further
contended that the area mentioned in allotment letter dated 24.7.2073
is saleable area. It is not carpet area. Saleable area consists of carpet
area, balcony, area covered by walls and flowerbed etc. Upon request
of complainant that he intends to avail loan, in the month of December
2019 the respondent no.1 promoter provided cost sheet to him
s/21
6
aT006000000053461
el The respondent no.1 has further contended that on several
occasions/ the respondent no.1 requested lvlr. Aakash Choksi, the son
of complainant to pay necessary stamp duty and registration charges
for execution of agreement for sale, however, the complainant has
failed to come forward for executing agreement for sale.
101 The respondent no.1 has further contended that
respondent no.1 has completed the constructlon of B-Wing of the
subject project and applied for occupation ceftificate. The respondent
no.1 endevoured to complete the construction of the said wing building
within timeline as mentioned on the website of tt4ahaRERA.
111 Upon hearing the parties, the learned Member-1,
l4ahaRERA came to the conclusion that since no agreement for sale
has been executed by the parties, therefore, Authority found claim of
the complainant for refund of amount under Section 18 of RERA is not
maintainable. However, Authority has found that only relief the
complainant can ask is under Section 13 of RERA. Consequenfly, the
Authority directed both the parties to execute and register the
agreement for sale within a period of 30 days from the date of order
Y
failing which the entire amount paid by complainant be refunded to him
within a period of next six months.
6/21
4T006000000053461
LZ) We have heard arguments of learned counsel for respective
pa ries.
13] Adv. Ms. Jennifer tyichael for Appellant assailed the
impugned order on the following grounds-
(i) The impugned order is perverse as it is passed in ignorance
and contrary to the relevant facts and evident from the record
submitted before the learned Authority. The learned Authority has
declined to grant relief of refund of amount only on the ground that no
agreement for sale has been executed by the parties and the allotment
letter dated 24.7.20t3 does not disclose the date of possession.
(ii) The learned Authority has failed to consider the law laid
down by the Hon'ble Apex Court in Fortune Infrastructure &
Another Versus Trevor D'Lima & Others reported in (2019) 5 SCC
442 that where no delivery date is stipulated, a reasonable time has to
be taken into consideration and reasonable time period would be 3
years for completion of the project. The said three years period would
come to an end on 24.7.2076. Besides, the learned Authority has
miserably failed to consider that the respondents themselves have
w declared the date of completion of
31.3.2019.
poect on MahaRERA portal as
(iii) The learned Authority has failed to consider that the
7121
8
AT006000000053461
respondents did not complete the project and failed to hand over
subject flat to the appellant by 31.3.2019
(iv) The learned Authority has failed to consider that the
respondents unilaterally revised the date of completion of project from
31.3.2019 to 31.3.2020 and again to 30.9,2021 and now to 30.3.2022
(v) This Tribunal in the matter of Ratul Lahiri Vs. Tata
Housing Development Co. Ltd. observed that the original date of
possession as declared by the promoter on the l.4ahaRERA portal was
the date of possession promised to the allottee and any unilateral
extension of the possession date was not binding on the allottee. This
Tribunal has also held that even though no agreement for sale is
executed, the date of possession can be ascertained from the other
documents including the original date of possession committed by the
promoter on the I'4ahaRERA portal. Therefore, the learned Authority
ought to have held that the original committed date of possession was
31.3.2019, therefore the fact that non execution of registered
agreement for sale and allotment letter did not disclose any date of
possession was entirely irrelevant.
(vi) The learned Authority ought to have applied its mind to
ascertain committed/promised date of possession from the factors such
as information uploaded by respondents on MahaRERA portal. The
8/21
9
aTo06000000053461
learned Authority ought to have considered that the allotment letter
discloses saleable area of the subject flat as 2385 [Link]. (221 [Link].)
However, information uploaded by the promoter on l4ahaRERA website
shows area ofthe subject flat as976.82 [Link]. (90.25 [Link].) only. Thus,
there is considerable shortfall in the area of the subject flat.
(vii) The learned Authority has failed to consider that RERA is
welfare legislation to provide protection and remedy to the appellant
against promoter to deal with various evils. The allottee has
indefeasible right under Section 18(1) of RERA to get the refund of
amount, if promoter fails to deliver possession as agreed for the
reasons not attributable to allottee. In the present case, the promoter
having failed to hand over possession by agreed date ls rinder
obligation to refund the amount under Section 18(1) with interest
(viii) The learned Authority has failed to consider the ratio and
dictum laid down by the Hon'ble High Court in Neelkamal Realtors
Suburban Pvt. Ltd, Vs. Union of India ((2017 2 SCC Online 9302)
that purpose of Section 18(1) (a) is to ameliorate buyers in Real Estate
Sector and balance the rights of the all stake holders. The promoter is
supposed to be conscious of getting poect registered under RERA.
Having sufflcient experience in the open market, the promoter is
expected to have fair assessment oF the time required for completing
9/21
10
AT006000000053461
the poect. If the promoter defaults to hand over possession of flat to
the allottee in the agreed timeline or extended period, then allottee
shall reasonably expect compensation from the promoter' Therefore, it
was expected of learned Authority to grant relief of refund of amount
with interest to appellant.
(ix) The learned Authority has miserably failed to consider that
the appellant has paid entire consideration of Rs'2,62,35,000/- to the
respondents from time to time and despite this, the respondents have
failed to execute agreement for sale and thereby respondents have
violated the provisions of Section 4(1A) (ii) of MOFA and Section 13(2)
of RERA. The impugned order is not only contrary to the facts of the
case, but is also contrary to the provisions of RERA The learned
Authority instead of granting relief of refund of amount with interest,
has erroneously directed parties to execute agreement for sale. Such
an order cannot be countenanced and sustainable in law.
With these submissions, the learned Advocate for appellant
prayed that appeal be allowed and grant reliefs sought in complaint
and appeal.
w L4J Disagreeing
supporting the impugned order
with contentions of allottee and
to have been correctly
while
passed, the
learned Adv. I4r. Bhupesh Dhumatkaar for respondent No'1 has
10/21
11
aro05000000053461
submitted that the project has faced numerous difficulties such as -
(1) Non vacation of structures by slum-dwellers due to
which the promoter could not commence the construction
work.
(2) Delay in obtaining necessary permissions from S.R.A
and concerned Authorities,
(3) Non clearance of access road.
(4) Pandemic Covid 19 and stringent restrlctions imposed
by the Government that affected business of promoter
severely and construction of the buildings was stopped due
to non-availability of essential construction material,
transport means etc which led suspension of work and
services of man power which constrained promoter to get
extension of time for completing the project from time to
time.
151 The learned Advocate has further sorely submitted that
despite force majeure factors as above and odd circumstances, the
respondent no.1 endevoured to complete the project within timeline.
The promoter was always willing to give timely possession of the
w subject flat to the complainant, but because of aforesaid force majeure
factors, the promoter was helpless in delivering possession of the
11/2t
12
4T006000000053461
subject flat to the complainant
161 It is futher argued that admittedly no agreement for sale
has been executed and registered by the parties. Therefore, the
complaint seeking relief under Section 18(1) of RERA, 2016 is not
maintainable. There is no mention of specified date of possession in
allotment letter. The respondent no.1 had never promised or committed
any date of possession to the complainant and therefore relief sought
by the appellant to refund the amount with interest is liable to be
rejected. It is fufther argued that Mr. Aakash Choksi (son of appellant)
was apprised by the respondent No.1 that the project is being
developed under S.R.A. Scheme and delay in completing the project is
due to reasons beyond the control of developer and the developer is
endeavouring to complete the project. The learned Adv. N4r. Bhupesh
Dhumatkar further submitted that the judgments relied upon by the
appellant are not applicable in the present case as the facts of those
cases are not same or similar to the facts of the present case.
L7) The learned Adv. I\4r. Dhumatkar sorely submitted that it is
not in dispute that the letter of allotment does not specify the date of
possession of the subject flat. In Mohit Melwani Vs, AA Estates
w ( Appeal No.AT006000000010873 of 2019) this Tribunal has hetd that
letter of allotment is silent on agreed or fixed date of handing over
12/21
13
AT006000000053461
possession and therefore, letter of allotment would not assist the
appellant to substantiate his case regarding commltted date of
possession and therefore there is no violation of Section 18 of RERA,
2016.
181 The learned Adv. l,lr. Dhumatkar has submitted that
saleable area and super built-up area are same as per the definition of
RERA, 2016. The respondent no.1 has not misrepresented any
information to the appellant in regard to the area of the subject flat
and therefore, there is no violation of Section 12 of RERA on the part
of respondents. The Section 2(k) of RERA defines carpet area. RERA
also defines balcony or varanda area. Thus, it is crystal clear that
saleable area consists of carpet area plus balconies plus varanda plus
area occupied by walls and plus flower bed. On the contrary the carpet
area does not include any extra area as above. The appellant has
miserably failed to make out a case for invoklng Section 12 of RERA.
The appellant has not produced any material to show that he has
suffered any loss due to alleged misrepresentation by respondent no.1.
191 The learned Adv. Mr. Dhumatkar has further submitted that
respondents have denied that the appellant has paid Rs.90,00,000/-
and Rs.10,00,000/- ln cash to the respondent no.1. The appellant has
paid only Rs.1,62,35,000/- to respondent no.1. The respondent no.1
L3/2"t
14
ATO06000000053461
took all possible efforts to execute and register agreement for sale in
compliance of order dated 24.9.2027 passed by the learned Authority,
but it is the appellant who was unwilling to pay balance consideration
and to pay necessary charges for execution and registration of
agreement for sale.
In the light of the above submissions, the learned Advocate
for respondent no.1 urged to uphold the impugned order and dismiss
instant appeal with cosG.
2Ol The respondent no.2 has fijed written submissions
contending therein that in 2013 the complainant had approached
respondent no.1 for booking of the subject flat. The respondent no.1
issued letter of allotment on 24.7.20!3 to the complainant. The
complainant has made payments to the respondent no.1. There is no
privity of contract between complainant and the respondent no.2. The
respondent no.2 is neither party to the transaction between the
complalnant and respondent no.1, nor signatory of the allotment letter.
Therefore, the claim of the complainant as alleged in the complaint is
against respondent no.1 with whom the complainant had entered into
letter of allotment and paid consideraUon amount.
w With these submissions, the respondent no.2 has prayed
to dismiss the appeal in limine.
14/)1
15
AT0050000000s3461
211 A perusal of pleadings in complaint and defence raised by
the promoter before the learned Authority and this Tribunal and
considering the grievances of the parties in the instant appeal,
following points arise for our consideration and we have recorded our
findings against each of them for reasons to follow -
POINTS FINDINGS
(1) Whether the respondents have failed
to deiiver possession of the subject flat
to the complainant without there being
situation beyond their control ? In the afflrmative
(2) Whether impugned order is sustainable
in law ? In the negative
(3) Whether order under challenge calls
for interference in this appeal ? In the affirmative
(4) What order ? As per final order
REASONS
221 On careful examination of pleadings of the parties, we find
that the respondents jointly took redevelopment of the building known
w as "The Nest". On 79.7.2073, the complainant booked
bearing No.8-502 in the project of respondents for consideration of
3 BHK flat
Rs.2,62,35,000/-. Pursuant to this the respondent no.1 issued
ts/zl
16
aT006000000053451
allotment letter dated 247.2013 to the complainant. Admittedly, no
agreement for sale has been executed and registered by the parties till
date even though the complainant paid more than 20olo amount of total
consideration in the course of time. The letter of allotment is silent on
the specified date of possession. It is not in dispute that as a part of
process of registration of the project under RERA which came into force
on 1.5.2017, the respondents have declared original date of possession
as 31.3.2019. It is also not in dispute that the respondents have not
delivered possession of the subject flat to the complainant till date.
23'J After ensembling of broad factual account of events as
above, it appears that considering the averments made in the
complaint and reliefs sought therein, the Authority had a doddle task
in hand to consider only issue of delay in possession and decide
entitlement of the complainant/allottee in the light of provisions
primarily under Section 18 of RERA. However, it is seen that the
Authority has denied reliefs sought in the complaint only on the ground
that agreement for sale has not been executed behveen the parties
and letter of allotment does not disclose the date of possession and
w therefore, the provisions of Section 18 of RERA do not apply to entitle
the benefits envisaged thereunder. It is significant to note that both
Sections i.e. Section 4 of MOFA and Section 13 of RERA cast obligation
16121.
17
AT006000000053451
on promoter to execute agreement for sale before receiving 20o/o and
100/o amount respectively of the total consideration amount. It is not in
dispute that at the time of booking of the subject flat, the complainant
had paid Rs.1,20,00,000/- to the respondent no.1 by cheque. There is
no material on record to show that the respondents have forwarded
draft agreement for sale with terms and conditions stipulated therein
to complainant for execution prior to filing of complaint. The
respondents have themselves failed to comply with their obligations
and now cannot take advantage of their own wrong to deny the
provisions under Section 18 of RERA in the absence of agreement
24) Section 4(1A) (ii) of I\4OFA provides that before accepting
advance payment or deposit more than 200/o of the sale price, lhe
promoter is liable to enter into written agreement for sale and mentlon
in it the date by which possession of the flat is to be handed over to
the allottee. Section 13(2) of RERA also casts similar obligation/liability
on the promoter. Therefore, we are of the view that promoter cannot
take advantage of lts own wrong. In fact, the respondents have
contravened the provisions of Section 4 of MOFA and Section 13 of
RERA.
251 It is not in dispute that there is no mention of date of
delivery of possession of subject flat in the allotment letter. In the
17 /21
18
ATO06000000053461
absence of agreement executed by the parties, the date of possession
can be deciphered from any other document such as brochure,
pamphlet, email communications, letters etc. In Fortune
Infrastructure & Another Versus Trevor D'Lima & Others
(supra), the Hon'ble Apex Court has held that when no date of
possession is mentioned in the agreement, promoter is expected to
hand over possession within reasonable time and the time of three
years held to be reasonable time. The complainant has booked flat on
79,7,2013. The respondent no.1 issued allotment letter on 24.7.2013
to the complainant. Therefore, considering ratio and dictum laid down
by the Hon'ble Supreme Court the promoter was supposed to hand
over possession of the subject flat to the complainant by 24.7.20t6. It
is not in dispute that as a part of process of registration of the project
under RERA which came into effect on 7.5.20U, the respondents have
declared original date oF possession as 31.3.2019. It is also not in
dispute that the respondents have revised the date of completion of
project from 31.3.2019 to 31.3.2020 and again to 30.9.2021.
261 Admittedly, till date the promoter has not handed over
possession of subject flat to the complainant. The promoter has
mentioned various reasons in reply which caused delay in completing
the project. We are not able to accept the same for the reasons that
18/21
19
ATO06000000053461
the respondents from the day one were aware that completion of slum
projects are dependent on several factors as also illustrated by
respondent no.1 in its reply. It is known to respondents that the slum
projects accord first priority to the rehabilitation of the slum-dwellers
subject to which the permissions to undertake construction of the said
building for third party purchasers like allottee herein are granted by
Slum Rehabilitation Authority (S.R.A.) The Hon'ble Bombay High Court
in Neelkamal Realtors Suburban Pvt. Ltd. Vs. Union of India
(supra) held that being expert in the open market, the promoters
ought to have assessed the likely timelines for completing the project
and provided the possession date accordingly. This being no concern
of allottee, he cannot be held responsible or liable for any delay and to
suffer adverse consequences in case of delay. The respondent no.1 also
indicated Covid 19 as one of the reasons for delay which appears to be
farfetched considering that the respondents themselves declared on
MahaRERA portal the date of completion of project as 31.3.2019 which
was long over when the pandemic of Covid 19 broke out in 2020. We
therefore give no weightage to the delay, if any, caused due to above
factors. It is held by the Hon'bte Supreme Couft in Newtech
Promoters and Developers Pvt. Ltd Vs. State of UP that allottees
are entitled to reliefs under Section 18 of RERA, if the delay is not
19/21
20
4T005000000053451
attributable to them.
271 For the forgoing observations, we have no hesitation in
arriving at the conclusion that the respondents had originally
committed to delivery of possession of the subject flat by 31.3.2019 as
declared on MahaRERA portal and later unilaterally revised the same
as 31.3.2020 and again to 30.9.2021. Therefore, there is clear delay in
delivering possession of the subject flat. This delay alone entiued
allottee to refund of his amount with interest under Sections g and 18
of MOFA and RERA respectively. Section 18 of RERA gives absolute right
to the allottee when promoter fails to hand over possession of the
apartment on the date agreed by him to either to continue in the
project and claim interest on payment till getting possession or
withdraw from the project to get refund of the amount paid with
interest. This right cannot be denied to the allottee merely because no
agreement for sale has been executed.
281 In the above premise, it is our considered view that the
complainant is entitled to refund of amount paid with interest as per
provisions of Section 18 of RERA on account of delay in possession.
291 In the result, the impugned order cannot be sustained in
w law and therefore, it calls for jnterference. We answer the points
accordingly and pass the following order
20/2r
21
aroo6000000053461
ORDER
(i) Appeal No,AT006000000053461 is partly allowed.
(ii) Order dated 24th September 2021 passed by learned
lvlember-1, MahaRERA in Complaint
No.CC006000000 192332 is set aside.
(iii) The respondents are directed to refund entire amount
paid by the complainant with interest @ SBIt Highest
Marginal Cost of Lending rate plus 2olo (simple interest)
to allottee i.e. appellant w.e.f. dates of payments till
actual realization of the entire amount.
(iv) The respondents are further directed to pay costs of
Rs. 20,000/- to the appellant/allottee.
(v) Copy of this judgment be sent to the Authority and the
parties as per provisions of Section 44(4) of RERA, 2016.
-1^ /'^/ $fry
(s."s: ^^J
SAN (SHRI Aarq n. IAGTAP)
21/21