Tendernotice 3 NALCO
Tendernotice 3 NALCO
MC-5376
NATIONAL ALUMINIUM COMPANY LIMITED
NALCO BHAWAN, P-1 NAYAPALLI,
BHUBANESWAR – 751 013
Page 1 of 79
(MC-5376)
INDEX
Page 2 of 79
(MC-5376)
Page 3 of 79
(MC-5376)
68.1 Guarantee
68.2 Suggestions to fulfill the guarantees
68.3 Care of works
68.4 Defects prior to taking over
68.5 Defects after taking over
68.6 Guarantee/ Transfer of Guarantee
Certificate and Payments (Section-VI)
69. Schedule of Rates and Payments.
69.1 Contractor’s Remuneration.
69.2 Schedule of Rates to be inclusive.
69.3 Schedule of Rates to cover constructional plant, materials, labour etc.
69.4 Schedule of Rates to cover royalties, rents and claims
69.5 Schedule of Rates to cover taxes and duties.
69.6 Schedule of Rates to cover risks of delays.
69.7 Schedule of Rates can not be altered.
70. Procedure for measurement/ billing of work in progress.
70.1 Measurements.
70.2 Billing.
Page 4 of 79
(MC-5376)
Page 5 of 79
(MC-5376)
Page 6 of 79
(MC-5376)
SECTION – 1
In the contract (as hereinafter defined) the following words and expressions shall have the
meanings hereby assigned to them except where the context otherwise requires.
1.1.1 The ‘Owner’ shall mean the National Aluminium Company Limited (NALCO), a Company
th
incorporated under the Companies Act, 1956 having its registered office at IDCO Tower, 8
Floor, Janapath, Bhubaneswar –751007 or any other place as modified subsequently and shall
include its Chairman-cum-Managing Director or other Administrative Officers authorised to deal
with these presents are concerned on his behalf posted in the any of the Offices of NALCO and
shall also include Owner’s successors and assignees.
1.1.2 The ‘Tender’ shall mean the tender submitted by the tenderer for acceptance by the Owner.
1.1.4. The ‘Project Head’ shall mean General Manager/ Deputy General Manager of the Project of
National Aluminium Company Ltd., or his successor in office or his authorised representative.
1.1.5. The ‘Contractor’ shall mean the person or persons, firm or company whose tender has been
accepted by owner and includes the contractor’s legal representatives, his successors and
permitted assigns.
1.1.6. The ‘Sub-contractor’ shall mean any person or firm or company (other than the contractor to
whom any part of the work has been entrusted by the contractor, with the written consent of the
owner or his representative and the legal representatives, successors and permitted assignee
of such person, firm or company.
1.1.7. The ‘Engineer-in-Charge’ shall mean the person nominated by the Owner from time to time and
shall include those who are expressly authorised by the Owner to act for and on his behalf for
all function pertaining to operation of this contract. All functions pertaining to the operation of
contract means all acts necessary for execution of the contract coordinating between the
different agencies and final closing of the contract.
1.1.8. The ‘Works’ shall mean and include all works to be executed in accordance with the contract or
part thereof as the case may and shall include all extras, addition, altered or substituted works
as required for the purpose of the contract or as may be required to be executed by the owner/
engineer-in-charge.
Page 7 of 79
(MC-5376)
1.1.9. The ‘Contract’ shall mean the agreement between the Owner and the contractor for the
execution of the works including therein all documents such as the invitation to tender,
instructions to Tenders, General Conditions of Contract, Special Conditions of Contract, Job
Specifications, General Requirements, Time Schedule of Completion of Job, Drawings, Letter
of Intent awarding the work, Agreed variations, if any etc.
1.1.10. The ‘Contract Document’ shall mean collectively the tender documents, designs, drawings
specifications, agreed variations, if any and other documents constituting the tender and
acceptance thereof.
1.1.11. ‘Constitutional Plant’ shall mean all appliances or things of whatsoever nature required in or
about the execution, completion or maintenance of the works or temporary works (as
hereinafter defined) but does not include materials or other things intended to form of forming
part of the permanent work.
1.1.12. ‘Temporary Works’ shall mean all temporary works of every kind required in or about the
execution, completion or maintenance of the works.
1.1.13. ‘Specifications’ shall mean all directions, various technical specification, provisions, and
requirements, attached to the contract, which pertain to the method and manner of performing
the work or works to the quantities and qualities of the work or works and the materials to be
furnished under the contract for the work or works as may be amplified or modified by the
Owner or the Engineer-in-charge during the performance of Contract in order to provide the
unforeseen conditions or in the best interests of the work or works. It shall also include the
latest edition including all addenda/ corrigenda or relevant Indian Standard Specifications and
other relevant codes.
1.1.14. ‘Plans’ shall mean all maps, sketches, and layouts as are incorporated in the contract in order
to define broadly the scope and specifications of the work or works, and all reproductions
thereof.
1.1.15. ‘Drawings’ shall include maps, plans and tracings or prints thereof with any modifications
approved in writing by the Engineer-in-Charge and such other drawings as may, from time to
time, be furnished or approved in writing by the Engineer-in-charge.
1.1.16. ‘Foreign consultant’ shall mean a person, agency or firm including their successors and
assigns, who are nonresidents of India and are responsible for supply of process Technology
for expansion plant based on review of existing plant including material flow, energy balance,
additional facilities and improvement on the basis of the recent experience.
1.1.17. ‘Indian Consultant’ shall mean a person, agency or firm including their successors and assign
who are responsible for detailed engineering and construction management of the project.
1.1.18. ‘Project manager’ shall mean the authorised representative of the consultant posted at site. He
shall be responsible for supervision of the work by the contractors as well as coordinate with
different agencies within the organisation or otherwise.
1.1.19. ‘Site’ shall mean the lands and other places on, under in or through which the permanent works
are to be carried out and any other lands or places provided by the owner for the purpose of
the contract.
1.1.20. ‘Notice in writing or written Notice’ shall mean a notice in written, typed or printed characters
sent (unless delivered personally or other wise proved to have been received) by registered
post to the last known private or business address or registered office of the addressee and
shall be deemed to have been received in the ordinary course of post it would have been
delivered.
1.1.21. The ‘Completion Certificate’ shall mean the certificate to be issued by the owner or his
representative when the works have been completed to his satisfaction.
Page 8 of 79
(MC-5376)
1.1.22. The ‘Final Certificate’ in relation to the work shall mean the certificate regarding the satisfactory
compliance of the various provisions of the contract to be issued by the owner or his
representative after the period of liability is over.
1.1.23. ‘Approved’ shall mean approved in writing including subsequent written conformation of
previous verbal approval and ‘Approval’ means approved in writing including as aforesaid.
1.1.24. The ‘Period of Liability’ in relation to a work means the specified period from the date of issue
of completion certificate up to the date of issue of final certificate which the contractor stands
responsible for rectifying all defects that may appear in the works.
1.1.25. The ‘Appointing Authority’ for the purpose of arbitration shall be the Chairman and managing
Director or any other person so designated by him.
1.1.26. The ‘Alteration Variation Order’ means an order given in writing by the Engineer-in-Charge/
owner to effect additions to or deletions from or alteration in the works.
1.1.27. ‘Letter of Intent’ shall mean an intimation by a letter to tenderer that the tender has been
accepted in accordance with the provisions contained in the letter.
1.1.28. ‘Days’ means a day of 24 hours from mid night irrespective of the number of hours worked in
that day.
1.1.29. ‘Working Day’ mean any day which is not declared to be holiday or rest day by the Owner.
1.1.30. ‘Week’ means a period of any consecutive seven days.
1.1.31. ‘Metric System’: All technical documents regarding the construction of works are given in the
metric system and all work in the project should be carried out accordingly to the metric
system. All documents concerning the work shall also be maintained in the metric system.
1.1.32. ‘Value of Contract’ shall mean the sum accepted or the sum calculated in accordance with the
prices accepted in tender and / or the contract rates as payable to the contractor for the entire
execution and full completion of the work.
1.1.33. ‘Headings and Marginal Notes’ in these contract documents are given solely for facility of
reference and are not part of the contract documents and are not to be taken into account in
the interpretation of the provisions of the contract.
1.1.34. ‘Language for Drawings & Instruction’: All the drawings, titles, notes, instruction, dimensions
etc. shall be in English Language.
1.1.35. ‘Singular and Plural’: The singular shall include the plural and vice versa wherever the context
so requires.
Page 9 of 79
(MC-5376)
SECTION - II
2. FACILITIES TO CONTRACTOR
2.1 Location of Sites and Access by Road:
2.1.1 Locations of Sites:
The general information about Mines Alumina, Aluminium Smelter and Captive power Plants
furnished below is of indicative nature only and shall not be considered as binding in any way on
the Owner and shall not govern either the scope of work or the nature of the respective rights
and the obligations of the parties to such contract.
Alumina plant is on south-western side of the Panchpatmali hill near Damanjodi village in
Koraput District, Orissa State. The site is situated at 12 Km from the national highway No. 43
off Semiliguda village. The Alumina Plant Site has the form of saddle between groups of low
hills. The location of Red Mud Pond is in the natural basis of hills situated at a distance of 2 Km
from the western side of the plant. The Bauxite mine is located at 14 Km away from the
Alumina Plant Site.
Page 10 of 79
(MC-5376)
2.2.3. When the water is supplied by the Owner, the Owner’s main will be within 500 metres form the
site of work. The Contractor shall provide at his own cost, all necessary ferrules, pipes, fitting,
couplings and tanks and temporary works required and he shall maintain all such works in
satisfactory condition. The Contractor shall remove all such works and shall re-instate and
make good any work disturbed, to the satisfaction of the Engineer-in-Charge.
2.2.4. In the event of the Contractor’s drawing water from the Owner’s main/ source, he shall not
claim any compensation for interruption or failure of Owner’s water supply caused due to any
reasons beyond the control of the owner.
2.2.5. The water so supplied by the Owner shall be free of cost for the Constructional work only.
2.3. Power Supply:
2.3.1 Subject to availability, Owner will supply power at 400/440 V at only one point at the nearest
substation, from where the contractor will make his own arrangement for temporary distribution.
The point of supply will not be more than 500 Metres away from the Contractor’s premises. All
the works will be done as per IEA regulations and passed by the Engineer-in-Charge. The
temporary line will be removed forthwith after the completion of work or if there is any
hindrance caused to the other works due to the alignment of these lines, the contractor will re-
route or remove the temporary lines at his own cost. The Contractor at his cost will also
provide suitable electric metres, fuses, switches, etc. for purposes of payment to the Owner
which should be in the custody and control of the Owner. The cost of power supply shall be
payable to the owner every month. Rs. 1/- per kWh for power, which will be deducted from the
running bills. The owner shall not, however, guarantee the supply of electricity and no
compensation for any failure or short supply of electricity will be entertained and this does not
relieve the contractor of his responsibility for timely completion of this works as stipulated in the
contract.
2.3.2 It shall be the responsibility of the contractor to provide and maintain the complete installation
of the load side of the supply with due regard to safety requirement at site. All cabling,
equipment, installations etc. shall comply in all respects with the latest statutory requirements
and safety provisions i.e. as per and the Central/ State Electricity Acts and Rules etc. The
Contractor will ensure that his equipment and Electrical wiring etc. are installed modified,
maintained by a licensed Electrician/ Supervisor. A rest certificate is to be produced to the
Engineer-in-Charge for his approval, before power is made available.
2.3.3 At all times, IEA regulations shall be followed failing which the Owner has a right to disconnect
the power supply without any reference to the contractor. No claim shall be entertained for
such disconnection by the Engineer-in-Charge. Power supply will be reconnected only after
production of fresh certificate from authorised electrical supervisors.
2.3.4 The Owner is not liable for any loss or damage to the Contractor’s equipment as a result of
variation in voltage or frequency or interruption in power supply or other loss to the Contractor
arising there from.
2.3.5 The Contractor shall ensure that the Electrical equipment installed by him are such that
average power factor does not fall below 0.90 at his premises. In case power factor falls below
0.90 in any month, he will reimburse to the Owner at the penal rate determined by the Owner
for all units consumed during the month.
2.3.6 The Power supply required for Contractor’s colony near the plant site will be determined by the
Owner and shall as per state Electricity Board’s Rules and other Statutory provisions applicable
for such installations from time to time. In case of power supply to Contractor’s colony, the
power will be made available at a single point and the Contractor shall make his own
Page 11 of 79
(MC-5376)
arrangement at his own cost for distribution to the occupants of the colony as per Electricity
Rules & Acts. The site area and colony shall be sufficiently illuminated to avoid accidents.
2.3.7 The Contractor will have to provide and install his own light and power meters, which will be
governed as per Central/ State Government Electricity Rules. The meters shall be sealed by
the Owner.
2.3.8 In case of damage to any of the Owner’s equipment on account of fault, intentional or
unintentional on the part of the Contractor the Owner reserves the right to recover the cost of
such damage from the contractor’s bill. Cost of HRC Fuses replaced at the Owner’s terminals
due to any fault in the Contractor’s installation shall be to contractor’s account at the rates
decided by the Engineer-in-Charge.
2.3.9 Only motors upto 3 HP will be allowed to be started direct on line. For motors above 3 HP
and up to 100 HP a suitable starting devices approved by the Engineer-in-Charge shall be
provided by the Contractor For Motor s above 100 HP slipping induction motors will suitable
starting devices as approved by the Engineer-in-Charge shall be provided by the Contractor.
2.3.10 The Contractor shall ensure at his cost that all electric lines and equipment and all
installations are approved by the State Electricity Inspector before power can be supplied by
the Owner.
2.3.11 The total requirement of power shall be indicated by the tenderer along with his tender.
2.4.1. The Owner will at his discretion and convenience and for the duration of the execution of the
work may provide the land for construction of Contractor’s field office, godown, workshops and
assembly yard required for the execution of the contract nearer to the site.
2.4. Land for Contractor’s Filed Office, Godown and Workshop :
The Contractor shall at his cost construct all these temporary buildings structures and provide
suitable water supply and sanitary arrangement as approved by the Engineer-in-Charge and
other inspectorates.
2.4.2. On completion of the works undertaken by the Contractor, he shall remove all temporary
works erected by him and have the site cleared as directed by Engineer-in-Charge. If the
Contractor fails to comply with these requirements, the Engineer-in-Charge has the right to
remove any structure, such surplus, rubbish materials and depose off the same as he deems
fit and get the site cleared and the contractor shall forthwith pay the amount of all expenses so
incurred and shall have no claim in respect of any such surplus materials disposed as
aforesaid. The Owner reserves the right to ask the Contractor at any time during the
pendancy of the contract, to vacate the land by giving 7 (seven) days notice on security
reasons or on national interest or otherwise. A token rent of Rs. 100/- (Rupees One hundred
only) per hectare or part thereof per annum or part thereof shall be charged for the land so
made available.
Land provided shall be solely on licence basis which is terminable by at any time without
notice or without assigning any reasons. In the event of any such termination or the
termination of the contract/completion thereof, the contractor shall forthwith vacate the
premises.
2.5. Land for Residential Accommodation:
Land for residential accommodation for staff and labour may be made available at the
discretion of the Engineer-in-Charge and rent for the same will be as decided by the Engineer-
in-Charge according to location and the area occupied by the Contractor.
Page 12 of 79
(MC-5376)
SECTION - III
GENERAL INSTRUCTIONS TO TENDERERS
3. SUBMISSION OF TENDER:
3.1. The documents issued to the tenderers shall be as follows:
(i) One complete set of tender documents as per index sheet and drawings marked ‘ORIGINAL’
(To be submitted along-with the quotation).
(ii) One complete set of tender documents as per index sheet marked ‘TENDERER’S COPY’ (To
be retained by the tenderer for reference).
3.1.1. The tender documents shall be in 2 parts viz. Technical Bid and Price Bid. Technical and
Price Bid should be put in separate sealed cover and marked with the tender reference and
name of the work. In addition, a note on the Price Bid “Quotation do not open” is to be
superscribed. Both the sealed covers are to be put in a single sealed cover. The name of the
work the tender reference and date of opening are to be superscribed on this sealed envelope
also.
The technical Bid shall be opened in the first instance. Clarifications, confirmations, if any,
shall be obtained with regard to technical specifications. After technical specifications are
firmed up, if a tenderer revises his price bid, he is required to submit justification in support of
the revision made. The price bid shall be opened thereafter.
3.2. If Addenda/ Corrigenda are issued to this tender document, they must be signed, submitted
along-with the tender documents. The tenderer should write clearly the revised quantities in
schedule of Rates of Tender Document and should price the work based on revised quantities
when amendments on quantities are issued in addenda.
3.3. Tenderers are advised to submit quotations based strictly on the terms and conditions and
specifications contained in the tender documents and not stipulate any deviations. Should it
however become unavoidable, deviations should be stipulated in the prescribed proforma
only, contained in the proposal form. Owner reserves the right to evaluate the quotations
containing deviations having financial implications, by adding the cost for such deviations are
determined by Owner.
3.4. Tenders should be submitted in double sealed envelope with the name of work superscribed
thereon and with the note “QUOTATION DO NOT OPEN” written prominently. The full name,
postal address and telegraphic address of the tenderer shall be written on the bottom left hand
corner of the sealed cover.
4.0. DOCUMENTS:
4.1.1 Bidders shall submit with his bids the particular/ documents as envisaged from Appendix (i) to
(x) along with tentative construction net work/ Bar chart for completion of work taking into
account various intermediate completion milestones/ component milestones and the overall
completion of work under the contract.
Page 13 of 79
(MC-5376)
If some discrepancies are found between the rates given in works and figures or the amount
shown in the tender, the following procedure shall be followed:-
a) When there is difference between the rates in figures and words, the rate which
corresponds to the amount worked out by the tenderer shall be taken as correct.
b) When the rate quoted by the tenderer in figures and words tally but the amount is
incorrect, the rate quoted by the tenderer shall be taken as correct.
c) When it is not possible to ascertain the correct rate by either of above methods the rate
quoted in words shall be taken as correct.
Page 14 of 79
(MC-5376)
6.2. The Bank Guarantee so furnished by the tenderer shall be only in the proforma prescribed by
the Owner and valid for six months from the date of opening of the tender. No interest shall be
paid by the Owner on the Earnest Money deposited by the tenderer.
7. VALIDITY: Tender submitted by tenderers shall remain valid for acceptance for a period of four
months from the date of opening of the tender. The tenderers shall not be entitled during the
said period of four months, without the consent in writing of the Owner, to revoke or cancel his
tender or to vary the tender given or any term thereof. In case of tenderer revoking or
canceling his tender or varying any terms in regard thereof without the consent a Owner in
writing, the earnest money paid by him along-with the tender shall be forfeited.
8. ADDENDA/ CORRIGENDA:
8.1. Addenda/ Corrigenda to the tender documents may be issued prior to the date of opening of the
tenders to clarify documents or to reflect modification in the design or contract terms.
8.2. The Addenda/ Corrigenda will be issued in duplicate to each person or organisation to whom a
set of tender documents has been issued. Each recipient should acknowledge the receipt of the
same and attach one copy of the addenda/ corrigenda along-with his offer. All addenda/
corrigenda issued shall become part of Tender Documents.
Page 15 of 79
(MC-5376)
more contractors or accepted in part (not entirely) if considered expedient. The quoted rates
would hold good for such eventualities. Tenders in which any of the particulars and prescribed
information are missing or incomplete in any respect and / or the prescribed conditions are not
fulfilled are liable to be rejected. The decision for the owner in respect of the above shall be
final and binding on the contractor.
9.2. Canvassing in connection with tenders is strictly prohibited. The submitted tenders of the
tenderers who resort to canvassing are liable to rejection. Tenders containing uncalled remarks
or any additional conditions are liable to be rejected.
10. THE SCHEDULE:
10.1. The work shall be executed strictly as per the Time Schedule given in Appendix –1. The period
of construction given in time Schedule includes the time required for mobilisation as well as
testing, rectification if any, re-testing and completion in all respects to entire satisfaction of the
Engineer-in-Charge.
10.2. A joint programme of execution of the work will be prepared by the Engineer-in-Charge and
contractor based on priority requirement of this project. This programme will take into account
the time of completion mentioned in 19.1 above and the time allowed for the priority works by
the Engineer-in-Charge.
10.3. Monthly/ weekly construction programme will be drawn up by the Engineer-in-Charge jointly
with the Contractor, based on availability of work fronts and the joint construction programme
as per 10.2 above. The contractor shall scrupulously adhere to these targets/ programs by
deploying adequate personnel construction tools and tackles and he shall also supply himself
materials of his scope of supply in good time to achieve the targets/ programmes. In all
matters concerning the extents of targets set out in the weekly and monthly programmes and
the degree of achievement, the decision of the Engineer-in-Charge will be final and binding on
the contractor.
10.4. CONSTRUCTION SCHEDULE AND PRESENTATION:
The construction schedule shall be in the form of network of PERT CHART/ CPM or other
suitable presentation for the programme of the work indicating therein the different components
item of works and time required for completion of each components item wise/ month wise
season wise so as to complete the work in all respects within the stipulated period. Before
award of the work the contractor is also required to make the presentation to satisfy owner of
their proposal for construction schedule in the form of BAR CHART and organizational
resources, equipments, machinaries, manpower to be deployed for timely completion of the
project.
Page 16 of 79
(MC-5376)
13. SIGNING OF THE CONTRACT: The successful tenderer shall be required to execute an
agreement with the Owner in the proforma attached with tender document within 10 days of the
receipt by him of the notification of acceptance of the tender. In the event of failure on the part
of the successful tenderer to sign the agreement within the above stipulated period, the earnest
money or his initial security deposit will be forfeited and the acceptance of the tender shall be
considered as cancelled. No bills shall be payable unless the agreement is executed.
14.2. The Engineer-in-Charge shall only co-ordinate with the other agencies engaged to work at site,
to ensure minimum disruption of work carried out by different agencies. It shall be the
responsibility of the contractor to plan and execute the works strictly in accordance with site
instructions and avoid hindrance to the works being executed by other agencies. The
instructions of the Engineer-in-Charge shall be binding on the contractor.
Page 17 of 79
(MC-5376)
SECTION - IV
GENERAL OBLIGATIONS
Page 18 of 79
(MC-5376)
accordance with the contract document whatever be the defects, omissions or errors that
may be found in the Contract Document. The contractor shall be deemed to have visited site
and surroundings areas, to have satisfied himself to the nature of all existing structures, and
also as to the nature and the conditions of available facilities like Railways, roadways,
bridges culverts, means of transport and communications like by land, water or air and
possible interruptions thereto the access to and egress from site and to have made enquiries,
examined satisfied himself of the sites for obtaining sand, stones, bricks and other materials,
the sites for disposal of surplus materials, the available accommodation like depots, buildings
as may be necessary for executing and completing the works, to have made local
independent enquiries as to the sub-soil water and variations thereof, storms, prevailing
winds and climatic conditions and all other similar matters affecting the works. He is deemed
to have acquainted himself his liability for payment of Government Taxes, Customs Duties
and other charges.
18.3. Any neglect or failure on the part of the tenderer in obtaining necessary and reliable
information or issues stated at 18.2 or any other matters affecting the contract shall not
relieve him from any risks or liabilities or the entire responsibility for completion of the works
at the scheduled rates and time in strict accordance with the contract documents.
18.4. Any change in layout due to site conditions or technological requirement shall be binding on
the contractor and no extra claim on this account shall be entertained.
18.5. No verbal agreement or inference from conversation with any officer or employee of the
Owner either before, during or after the execution of the contract agreement shall in any way
affect or modify and of the terms or obligations herein contained.
19. Security Deposit:
19.1. A sum of 10% of the accepted value of the tender or actual value of the work done whichever
is higher for contracts not exceeding Rs. 1 Crore, 71/2 % for the value of contracts over Rs. 1
up to Rs. 5 crores and 5%for the value of contracts over Rs. 5 crores shall have to be
deposited by the person/ persons (hereinafter called as contractor) as security deposit with
the owner until the expiry of defect liability period.
19.2. This may be deposited initially at 2 ½% of the value of the contract (referred as initial Security
deposit) within 20 days of receipt by him of the notification of acceptance of tender and the
balance will be recovered in installments through the deduction @ 10% of the gross value of
the each running account bill for the contract upto Rs. 1 crore, 71/2 % for contract between
Rs. 1 to Rs.5 crores and 5% for contract over Rs. 5 crores, till total security deposit is
collected. No further deduction from the bills will be made on this account subject to clause
19.6 below.
19.3. Alternatively the contractor may at his option to deposit the full amount percentage as
mentioned 19.1 above towards deposit within 10 days of issue of notification accepting his
tender. This amount will have to be suitably enhanced to the tune of above percentage of the
executed value.
19.4. The earnest money deposited with the tender shall be adjusted towards security deposit.
19.5. Contractor can furnish the initial or total security deposit amount (a) in Demand Draft or (b)
through a Bank Guarantee from any Scheduled bank in the prescribed proforma.
19.6. If contractor /sub-contractor or their employees damages, breaks, deface or destroy the
property belonging to the owner or other during the execution of the contract, the same shall
be made good by the contractor at his own expense and in default thereof; the Engineer-in-
Charge may cause the same to be made good by other agencies and recover expenses form
the contractor (for which the certificate of Engineer-in-Charge shall be final).
19.7. All compensation or other sums of money payable by the contractor to the Owner or
recoveries to be made under terms of this contract may be deducted from or paid by the sale
of a sufficient part of his security deposit or from any sums which may be due or may become
due to the contractor by the Owner on any account whatsoever. In the event of his security
being reduced by reasons of any such deduction or sale, the contractor shall within ten days
thereafter make good in cash, bank drafts, any sum or sums which may have fallen short or
Page 19 of 79
(MC-5376)
Security deposit amount or any part thereof. No interest shall be payable by the Owner for
sum deposited as security deposit.
19.8. The security deposit will be refunded after the expiry of the period of liability as stipulated in
the contract.
20. Forfeiture of Security Deposit: Whenever any claim against the Contractor for the payment
of a sum of money arises out of or under the contract, the Owner shall be entitled to recover
such sum by appropriating in part or whole the security deposit of the contractor, and to sell
any Government securities, etc. forming whole or part of such security deposit. In the event
of security being insufficient or if no security has been taken from the contractor, then the
balance or the total sum recoverable as the case may be, shall be deducted from any sum
then due or which at any time thereafter may become due to the contractor. The contractor
shall pay to the Owner on demand any balance remaining due.
In the event of any breach by the contractor or any loss or damage occasioned to the owner
which in the opinion of the owner has arises, the decision where of shall be final and binding
on the contractor or in the event of the termination of the contract for any such breach, the
security deposit is liable to be forfeited. The decision of forfeiture by the Owner shall be final
and binding on the contractor.
21. Time of performance:
The work covered by this contract shall be commenced within twenty one days after the issue
of the letter of acceptance of tender and be completed in stages on or before the dates as
mentioned in the time schedule of completion of works. The contractor should bear in mind
that time is the essence of the contract, unless such time be extended pursuant to the
provision of clause No.22 Request for Revision of Construction time after tenders are
opened will not receive consideration. The above period of twenty one days is included
within the overall completion schedule, not over and above the completion time.
22. Extension of Time.
22.0. The application for extension of time is to be given to project head through the engineer –in-
charge and the project head may authorise extension of time after considering the due
merits.
Whenever extension of time is granted by the project head, the same shall be on the existing
terms and conditions of the contract and without any additional financial liability to the Owner.
The contractor in any case shall have no claim whatsoever for any type of compensation on
account of any delay attributable to any one.
23. Force Majeure:
23.1 Any delays in or failure of the performance of either parties thereto shall not constitute
default hereunder or give rise to any claims for damages, if any, to the extent such delays or
failure of performance caused by occurrences such as acts of God or the public enemy,
expropriation or confiscation of facilities by Government authority, compliance with any order
or request of any Governmental authorities, acts or war rebellion, sabotage, fire, floods,
explosions riots or illegal strikes, provided always that such occurrences result in impossibility
of performances of the contract.
23.2 Only events of Force Majeure which impedes the execution of the contract at the time of its
occurrence shall be taken into cognizance.
24. Compensation For Delay:
24.1. Time is essence of the contract. In case the contractor fails to complete the work within the
stipulated period, he shall be liable to pay to the Owner as compensation, an amount equal to
1% of the value of contract per week of the delay subject to a maximum of 10% of the value
of the contract. This is a genuine pre-estimate of the loss/ damage which will be suffered on
account of delay /breach on the part of the contractor and he agrees to pay the said amount
on demand without going in for any proof of the actual loss or damages caused by such
delay/ breach.
Page 20 of 79
(MC-5376)
24.2. To ensure good progress during execution of work, the contractor shall be bound in all case in
which the time allowed for any work exceeds by one month to complete one-fifth of the work
before one-fourth of the time allowed under the contractor has elapsed, three-eighth of the
work before the half of such time has elapsed and three-fourth of the work before three–fourth
of such time has elapsed. In the event of the contractor failing to comply with this condition, he
shall be liable to pay as compensation for delay an amount as stipulated above. The
compensation for delay so paid shall not relieve the contractor from his obligations to complete
the work or from any other obligations and liabilities under this contract.
25. Failure by the Contractor to Comply with the Provisions of the Contract:
25.1. If the contractor refuses or fails to execute the work or any separate part thereof with such
diligence as will ensure its completion within the time specified in the contract or extension
thereof or fails to perform any of his obligation under the Contract or in any manner commits a
breach of any of the provisions of the contract it shall be open to the Owner at its option by
written notice to the Contractor to: -
(a) Determine the Contract: In which event the Contract shall stand terminated and shall cease to
be in force and effect on and from the date appointed by the Owner on that behalf, whereupon
the contractor shall stop forth with any of the contractor’s work then in progress, except such
work as the Owner may, in writing, requires to be done to safeguard any property or work, or
installations from damage, and the owner, for its part, may take over the work remaining
unfinished by the Contractor and complete the same through fresh contractor or by other
means, at the risk and cost of the Contractor, and any of his sureties if any, shall be liable to
the owner for any excess cost occasioned by such work having to be so taken over and
completed by the Owner over and above the cost at the rates specified in the schedule of
quantities and rates.
(b) Without determining the Contract: To take over the work of the contractor or any part thereof
and complete the same through a fresh contractor or by other means at the risk and cost of the
Contractor. The contractor and any of his sureties are liable to the Owner for any excess cost
over and above the cost at the rates specified in the schedule of quantities/ rates, occasioned
by such works having been taken over and completed by the Owner. Besides, the contractor
shall also be liable for any compensation accruing under clause 24.
(c) In other cases, the decision of the Owner is binding on the contractor.
25.2. In such events of clause 25.1 (a) or (b) above
(a) The whole or part of the security deposit furnished by the Contractor is liable to be forfeited
without prejudice to the right of the Owner to recover from the contractor the excess cost
referred to in the sub-clause aforesaid, the Owner shall also have the right of taking possession
and utilizing in completing the works or any part thereof, such of materials, equipment and
plants available at work site belonging to the contractor as may be necessary and the
Contractor shall not be entitled for any compensation for use or damage to such materials,
equipment and plant.
(b) The amount that may have become due to the Contractor on account of work already executed
by him shall not be payable to him until after the expiry of six (6) calendar months reckoned
from the date of termination of contract or from the taking over of the work or part thereof by
the Owner as the case may be, during which period the responsibility for faulty materials or
workmanship in respect of such work shall under the contract, rest exclusively with the
contractor. This amount shall be subject to deduction of any amounts due from the Contractor
to the Owner under the terms of the contract authorised or required to be reserved or retained
by the Owner.
25.3. Before determining the contract as per clause 25.1 ( a) or (b) provided in the judgement of the
Owner, the default or defaults committed by the Contractor is/are curable and can be cured by
Page 21 of 79
(MC-5376)
the Contract if an opportunity given to him, then the Owner may issue notice in writing calling
the Contractor to cure the default within such time specified in the notice.
25.4. The Owner shall also have the right to proceed or take action as per 25.1 (a) or Clause 25.1(b)
above, in the event that the contractor becomes bankrupt, insolvent, compounds with his
creditors, assigns the contract in favour of his creditors or any other person or persons or being
a company or a corporation goes into liquidation, provided that in the said events it shall not be
necessary for the Owner to give any prior notice to the contractor.
25.5. Termination of the Contract as provided for in sub-Clause 25.1 (a) above shall not prejudice or
affect their rights of the Owner which may have accrued upto the date of such termination.
26. Contractor Remains Liable to Pay Compensation if Action Not Taken Under Clause 25.
In any case in which any of the powers conferred upon the owner by clause 25 hereof shall
have become exercisable and the same had not been exercised, the non-exercise thereof shall
not constitute a waiver of any of the conditions hereof and such powers shall not withstanding
be exercisable in the event of any further case of default by the contractor for which by any
clause or clauses hereof he is declared liable to pay compensation amount to the whole of his
security deposit and the liability of the contractor for past and future compensation shall remain
unaffected. In the event of the Owner putting in force the powers vested in him under the
proceeding clause no. 25 he may if he do so desires, take possession of all or any tools and
plants, materials and stores in or upon the works of the site thereof belonging to the contractor
or procured by him and intended to be used for the execution of the work or any part thereof
paying or allowing for the same in account at the contract rates or in case of these not being
applicable at current market rates to be certified by the Engineer-in-Charge whose certificate
thereof shall be final, otherwise the Engineer-in-Charge may give notice in writing to the
contractor or his clerk of the works, foremen or other authorised agent, requiring him to remove
such tools, plant, materials or stores form the premises (within a time to be specified in such
notice), and in the event of the contractor failing to comply with any such requisition, the
Engineer-in-Charge may remove them at the contractor’s expenses or sell them by auction or
private sale on account of the contract and at his risk in all respects without any further notice
as to the date, time or place of sale and the certificate of the Engineer-in-Charge as to the
expense of any such removal and the amount of the proceeds and expenses of any such sale
shall be final and conclusive against the contractor.
27. No Compensation For Alteration in or Restriction of Work:
At any time from the commencement of the work if the Owner decides for whatsoever reason,
not to carryout the whole work or part thereof as specified in the tender, then owner shall give
notice in writing of the fact to the contractor, who shall have no claim to any payment or
compensation on whatsoever account (profit or advantage which he might have derived by
executing the work in full) neither shall he have any claim for compensation by reason of any
alterations having been made from the original specifications, drawings, designs and
instructions which may involve any curtailment of the work as originally contemplated.
Page 22 of 79
(MC-5376)
dies or if the contractor is a partnership concern and one of the partners dies then, unless the
Owner is satisfied that the legal representative of the individual or the proprietary concern or
the surviving partners are capable of carrying out and completing contract, he (the Owner) is
entitled to cancel the contract for the uncompleted part without being in any way liable for any
compensation payment to the estate of the diseased contractor and/or to the surviving partners
of the contractor’s firm on account of the cancellation of contract. The decision of the Owner in
such assessment shall be final and binding on the parties. In the event of such cancellation,
the Owner shall not hold the estate of the diseased contractor and / or the surviving partners of
the contractor’s firm liable for any damages for non-completion of contract.
The Contractor shall provide and maintain an office at the site for the accommodation of his
agent and staff and such office shall be open at all reasonable hours to receive instructions,
notices or other communications. The contractor at all time shall maintain a site instruction
book and compliance of these shall be communicated to the Engineer –in-Charge from time to
time and the whole document to be preserved and handed over after completion of works.
33.1. The contractor on award of the work shall name and depute a qualified engineer having
sufficient experience in carrying out work of similar nature to whom the equipment, materials if
any, shall be issued and instruction for works given. The contractor shall also provide to the
satisfaction of the Engineer-in-charge sufficient and qualified staff to supervise the execution of
the works, competent sub-agents, foremen and leading hands including those specially
qualified by previous experience to supervise the types works comprised in the contract in such
manner as will ensure the best quality and expeditious working. At any time of in the opinion of
the Engineer-in-Charge any additional, qualified experienced staff is considered necessary,
they shall be employed by the contractor without additional charge. The contractor shall
ensure to the satisfaction of the Engineer-in-Charge that sub-contractors, if any, shall provide
competent and efficient supervision over the work entrusted to them.
33 .2. If any of the contractor’s sub-contractor’s, agents, sub-agents, assistants, foremen or any
employee in the opinion of Engineer-in-Charge be guilty of any misconduct or be incompetent
or insufficiently qualified or negligent in the performance of their duties or that in the opinion of
the Owner Engineer-in-Charge, undesirable for administrative or any other reasons, for such or
person (s) to be employed on the works, then at the directions of Engineer-in-Charge the
Contractor shall at once remove such person (s) from employment with the works without the
written permission of the Engineer –in-Charge. Vacancy so created shall be immediately filled
at the expenses of the contractor by a qualified and competent substitute. Should the
contractor be requested to repatriate any person removed from the works he shall do so and
shall bear all costs in connection therewith.
Page 23 of 79
(MC-5376)
33.3. The contractor shall be responsible for the proper behaviour of all the staff, foremen, workmen
and others, shall exercise proper degree of control over them and in particular without prejudice
to the said generality the contractor shall be bound to prohibit/ prevent any employees from
trespassing or acting in any way detrimental or prejudicial to the interest of the community or the
properties or the occupiers of land or properties in the neighborhood. In the event of such
trespassing, the contractor shall be responsible for all consequent claims or actions for
damages or injury or any other grounds whatsoever. The decision of the Engineer-in-Charge
upon any matter arising under this clause shall be final.
33.4. If and when required by the Owner, all contractor’s personnel entering upon the owner’s
premises shall be properly identified by badges of a type acceptable to the owner which must be
worn at all times on Owner’s premises.
33.5. It is made clear that no relationship of employer and employee is created between the owner
and the contractor labourer and no claim for employment of any such labourer shall be tenable
or entertained.
At the commencement of each month, the contractor shall furnish to the Engineer-in-charge, a
list of sub-contractors, persons or firms engaged by the contractor and worked at the site during
the previous month with particulars like general nature of the sub-contract or works done by
them.
Page 24 of 79
(MC-5376)
If the contractor shall not commence the work in the manner described in the contract
documents or if he at any time in the opinion of the Engineer-in-Charge.
(i) fail to carry on the works in conformity with the contract documents or
(ii) fail to carry on the works in accordance with the contract schedule or
(iii) substantially suspend work or the works for a period of fourteen days without authority
from the Engineer-in-Charge or
(iv) fail to carry on and execute the works to the satisfaction of Engineer-in-Charge or
(v) fail to supply sufficient or suitable constructional plant, temporary works, labour materials
or other things or
(vi) Commit, suffer or permit any other breach of any of the provisions of the contract on his
part to be performed or observed or persist in any of the above mentioned breaches of
the contract for fourteen days, after notice in writing shall have been given to the
contractor by the Engineer-in-Charge requiring such breach to be remedied or
(vii) If the contractor abandons the works or
(viii) If the contractor during the continuance of the contract shall become bankrupt, make any
arrangement or composition with his creditors, or permit any execution to be levied or go
into liquidation whether compulsory or voluntary not being merely a voluntary liquidation
for the purpose of amalgamation or reconstruction then in any such case, the owner shall
have the power to enter upon the works and take possession thereof and of the
materials, temporary works, constructional plant, and stock thereon, and to revoke the
contractor’s licence to use the same, and to complete the works by his agents, other
contractors, or workmen, or to relate the same upon any terms and to such other person,
firm or corporation as the Owner in his absolute discretion may think proper to employ
and for the purpose aforesaid to use or authorize the use of any materials, temporary
works, constructional plant, and stock as aforesaid, without making payment or allowance
to the contractor for the said materials other than such as may be certified in writing by
the Engineer-in-Charge to be reasonable, and without making any payment or allowance
to the contractor for the use of temporary said works, constructional plant and stock or
being liable for any loss or damage thereto and if the Owner shall by reason or his taking
possession of the work or of the works being completed by other contractor (due account
being taken of any such extra work or works which may be omitted) than the amount of
such excess as certified by the Engineer–in-Charge shall be deducted form any money
which may be due for work done by the contractor under the contract and not paid for any
deficiency shall forthwith be made good and paid to the Owner by the contractor and the
Owner shall have power to sell in such manner and for such price as he may think fit all
or any of the constructional plan, materials etc. constructed by or belonging to and to
recoup and retain the said deficiency or any part thereof out of the proceeds or the sale.
36. Contractor’s Responsibility with other Agencies:
36.1 Without repugnance to any other condition, it shall be the responsibility of the contractor
executing the work of civil construction to work in close cooperation and to coordinate in
the works with the mechanical, electrical, air-conditioning and intercommunication
contractors and other agencies or their authorised representatives, in providing the
necessary grooves, recesses, cuts and opening etc. in wall, slabs beams and column etc.
and making good the same to the desired finish as per specification, for the placement of
Page 25 of 79
(MC-5376)
36.2 The contractor shall conform in all respect with the provisions any statutory regulation,
ordinance or bye-laws of any local or duly constituted authorities or public bodies which
may be applicable from time to time to the works or any temporary works. The contractor
shall keep the Owner indemnified against all penalties and liabilities of every kind, arising
out of non-adherence to such statues, ordinances, laws, rules, regulations, etc.
(i) The Owner reserves the right to distribute the work between more than one contractor.
The contractor shall cooperate and afford the other contractors all reasonable opportunity
for access to the works for the carriage and storage of materials and execution of their
works.
(ii) Wherever the work being done by any department of the Owner or by the contractor
employed by the Owner as per the contingent upon work covered by this contract, the
respective rights and various interests involved shall be determined by the Engineer-in-
Charge to secure the completion of the various portions of the work in general harmony.
Page 26 of 79
(MC-5376)
employed the performance of this contract, is covered by a patent under which the
contractor is not licensed then the contractor before supplying or using the equipment,
machinery, materials, composition, method or processes shall obtain such licenses and
pay such royalties and license fees as may be necessary for performance of this contract.
In the event the contractor fails to pay any royalty or obtain any such license, any suit for
infringement of such patents which is brought against the contractor or the Owner as a
result of such failure will be defended by the contractor at his Own expense and the
contractor will pay damages and costs awarded in such suit. The contractor shall
promptly notify the Owner if the contractor has acquired knowledge of any plant under
which a suit for infringement could be reasonably brought because of the use by the
owner of any equipment, machinery, materials, process, methods, to be supplied
hereunder. The contractor agrees to and does hereby grant to Owner, together with the
right to extent the same to any of the subsidiaries of the Owner as irrevocable, royalty-
free licence to use in country, any invention made by the contractor or his employee in or
as a result of the performance of the work under the contract.
40.2. All charges on account of royalty, tollage, rent octroi terminal or sales tax and/ or other
duties or any other levy on materials obtained for the work or temporary work or part
thereof (excluding materials provided by the Owner) shall be borne by the contractor.
40.3. The contractor shall not set or otherwise dispose of or remove except for the purpose of
this contract, the sand stone, clay, ballast, earth, rock or other substances, or materials
obtained from any excavation made for the purpose of the works or any building or
produce upon the sited at the time of delivery of the possession thereof, but all such
substances, materials buildings and produce shall be the property of the Owner provided
that contractor may with the permission of the Engineer-in-Charge, use the same for the
purpose of the works by payment of cost of the same at such a rate as may be
determined by the Engineer-in-Charge.
The Owner shall indemnify and save harmless the contractor from any loss on account of
claims against contractor for the contributory infringement of patent rights arising out and
based upon the claim that the use by the Owner of the process included in the design
prepared by the Owner and used in the operation of the plant infringes on patent right.
With respect of any sub-contract entered into by the contractor pursuant to the provisions
on the respect to any sub-contract entered into by the contractor pursuant to the
provisions of the relevant clause thereof, the contractor shall obtain from the sub
contractor an undertaking to provide the Owner with the same patent protection that
contractor is required to provide under the provisions of this clause.
41. Liens:
41.1. If at any time there should be evidence or any lien, claim for which the Owner might have
become liable, which is chargeable to the contractor, then the Owner may pay and
discharge the same and deduct the amount so paid from any amount which may be or
may become due and payable to the contractor, if any lien or claim remain unsettled after
all payments are made, the contractor shall refund or pay to the Owner the cost such lien
or claim including all payment and reasonable expenses. Owner reserves the right to the
same.
41.2. Nothing Extra for Adverse Sub-Soil Conditions:
The nature of sub-soil of the work site varies widely horizontally and vertically. The KI
and KII values also vary widely from place to place. In addition the water bearing seems
are also conspicuous with the water table at a depth of 0.75 to 3.0 metres from ground
level. A number of cohesive and non-cohesive strata are available particularly
everywhere. The contractor shall have to make cuts and resort to pumping with due care
to avoid collapsing of sides and occurrence of ‘Piping’. The Contractor shall also be
Page 27 of 79
(MC-5376)
41.3. Slips and falls in excavation shall be cleared by the contractor at his own cost.
Excessive heaving shall have to cut and refill with lean concrete by the contractor at his
own cost. The contractor shall have to adopt under-water work in case of occurrence of
piping/ quick condition without any additional cost to the Owner.
The contractor will be paid for the earthwork as per the drawing. The slopes etc. as
required for the safety of the work has to be provided as per the decision of the Engineer-
in-Charge at his own cost. All types of dewatering including seepage, rain water entering.
The earthwork in excavation or from any other source is to be done by the contractor at his
own cost till the completion of foundation upto ground level including back filling.
Change of location of site do not invalidate the contract and tenderer have no claim for any
compensation for such changes.
Page 28 of 79
(MC-5376)
SECTION – V
PERFORMANCE OF WORK
All the work shall be executed in strict conformity with the provisions of the contract
documents explanatory detailed drawings, specifications and instructions by the Engineer-
in-Charge whether mentioned in the contract or not. The contractor shall be responsible
for ensuring that works are executed in the most substantial, proper and workman like
manner using the quality materials and labour, through out the job Completion in strict
accordance with the specifications and to the entire satisfaction of the Engineer-in-Charge.
The coordination and inspection of the day-to-day work under the contract shall be the
responsibility of the Engineer-in-Charge or his authorised representative. A work order
book will be maintained by the contractor for each sector in which the aforesaid written
instructions will be entered. These will be signed by the contractor or his authorised
representative by way of acknowledgement within 12 hours.
For carrying out works on Sundays and holidays, the contractor will to keep Engineer-in-
Charge or his representative at least two days in advance and obtain permission in writing.
The contractor shall observe all labour laws and other statutory rules and regulations in
force. In case of any violation of such laws, rules and regulations, consequence if any,
including the cost thereto shall be exclusively borne by the contractor and the Owner shall
have no liability whatsoever on his account.
Page 29 of 79
(MC-5376)
Agreement No ……………………………………
Signed
(Contractor) (Engineer-in-Charge)
48.3 A period of 3 weeks from the date of receipt shall be required for approval of drawings by
the Engineer-in-Charge.
48.4 As built drawing showing all Corrections, adjustments etc. shall be furnished by the
Contractor in five copies and one transparent to record purposes to the owner.
49 Setting Out Works:
49.1 The Engineer-in-Charge shall furnish to the contractor with only the four corners of the
work site that is plant boundary limits, and a level bench mark only. The contractor shall
set out the works, provide an efficient staff for the purpose and shall be solely responsible
for the accuracy of such setting out.
49.2 The contractor shall provide, fix and be responsible for the maintenance of all stacks,
templates, level marks, profiles and other similar things and shall take all necessary
precautions to prevent their removal or disturbance. He shall be responsible for their
consequences arising of such removals, disturbances corrections thereon and for their
efficient and timely reinstatement. The contractor shall also be responsible for the
maintenance of all existing survey marks, boundary marks, distance marks and centre
line marks, either existing or supplied and fixed by the contractor. The work shall be set
out to the satisfaction of the Engineer-in-Charge. The approval thereon or jointing with the
contractor by the Engineer-in-Charge in setting out the work, shall not relive the contractor
of any of his responsibilities.
Page 30 of 79
(MC-5376)
49.3 Before beginning the work the contractor shall at his own cost, provide all necessary
reference and level posts-pegs, bamboos, flags, ranging rods, strings, and other materials
for proper layout of the work in accordance with the scheme for bearing marks acceptable
to the Engineer-in-Charge. The centre, longitudinal, face and cross lines shall be marked
by means of small masonry pillars. Each pillar shall have distinct mark at the centre to
enable the theodolite to be set over it. No work shall be started until all these points are
checked and approved by Engineer-in-Charge in writing, but such approval shall not
relieve the contractor of any of his responsibilities. The contractor shall also provide all
labour, materials and other facilities as necessary, for the proper checking or layout and
inspection of the points during construction.
49.4 Pillars bearing geodetic marks located at the sites of units of works under construction
should be protected and faced by the contractor.
49.5 On completion of work, the contractor must submit the geodetic documents according to
which the work was carried out.
50. Responsibility for Level and Alignment:
50.1 The contractor shall be entirely and exclusively responsible for the horizontal and vertical
alignment, the level and correctness of every part of the work shall rectify effectually any
errors or imperfections therein. Such rectification shall be carried out by the contractor at
his own cost, when instructions are issued to that effect by the Engineer-in-Charge.
50.2 Lighting, Watch & Ward:
The contractor shall in connection with works provide and maintain at his own cost all
lightings, guards, fencing and watch and ward and the security of the entire work in
progress including all the machineries, materials shall be the responsibility of the
contractor till taken over by the owner by way of the written taking over certificate.
51. Materials to be Supplied by Contractor :
51.1 The contractor shall procure and provide the whole of the materials required for the
construction including M.S. Rods, Cement and other building materials, tools, tackles,
construction plant and equipment for the completion and maintenance of the work except
the materials which will be issued by the Owner and shall make his own arrangement for
procuring such materials and for the transport thereof. The owner may give necessary
recommendation to the respective authorities, if so desired by the contractor, but assumes
no further responsibility of any nature. The owner will insist on the procurement of
materials which has the approval of Indian Standards Institution having ISI stamp and/or
which are supplied by reputed suppliers borne on DGS & D list.
51.2 The contractor shall properly store all materials either issued to him or brought by him to
the worksite to prevent damages due to rain, wind, direct exposure to sun etc. as also from
theft, pilferage, etc. for proper and speedy execution of his works. The contractor shall
maintain sufficient stocks of all materials required by him.
51.3 No material shall be despatched from the contractor’s stores before obtaining the approval
in writing of the Engineer-in-Charge.
51.4 All plants, tools and other materials brought by the contractor to the site must be declared
at the time of bringing the same to the site.
52. Stores Supplied by the Owner:
52.1 If the specification of the work provides for the use of any material other than Steel &
Cement of special description to be supplied from the Owner’s stores or it is required that
the contractor shall use certain stores to be provided by the Engineer-in-Charge, such
materials and stores, and price to be charged therefore as hereinafter mentioned being so
far as practicable for the convenience of the contractor, but no so as in way to control the
Page 31 of 79
(MC-5376)
meaning or effect of the contract, the contract shall be bound to purchase and shall be
supplied much materials and stores as are from time to time required to be used by him for
the purpose of the contract only. The sums due from the contractor for the value of
materials supplied by the Owner will be recovered from the Running Account Bill on the
basis of actual consumption of materials (after taking into account any wastage allowance
as may be provided for in the contract). The contractor should raise requisite copies of
indents in a proforma as prescribed by the Engineer-in-Charge and no claim whatsoever
will be entertained by the Engineer-in-Charge on this account. After completion of the
works, the contractor is required to account as per relevant clauses in this document, for
the full quantity of materials supplied to him.
52.2 The value of the stores/materials as may be supplied to the contractor by the Owner will
be debited to the contractor’s account at the rates shown in the schedule of materials and
if they are not entered in the schedule, they will be debited at cost price, which for the
purpose of the contract shall include the cost of carriage and all other expenses
whatsoever such as normal storage supervision charges which shall have been incurred in
obtaining the same at the Owner’s stores. All materials so supplied to the contractor shall
remain the obsolute property of the Owner and shall not be removed on any account from
the site of the work and shall be at all times open for inspection to the Engineer-in-
Charge. Any such materials remaining unused at the time of the completion or termination
of the contract shall be returned to the Owner’s stores or at a place as directed by the
Engineer-in-Charge in perfectly good condition at contractor’s cost.
52.3.2 Such materials of steel and cement shall be issued only for permanent works and not for
making other temporary works etc. Contractor shall bear all cost including lifting and
loading carting from issue points to work site/contractor stores, custody and handling etc.
and return of surplus serviceable/unserviceable materials to owner’s store or other places
to be designed by owner and no separate payment for such expenditure shall be made.
52.3.3 Items of steel as per specification of the work as mentioned above shall be supplied in the
available length only. No claim on account of supply of non-standard length shall be
entertained. Steel materials shall be issued on actual weight basis.
52.3.4 Cement as mentioned above will be supplied to the contractor a receive from the
manufacturer/stockiest. The theoretical weight of each bag of cement supplied will be
considered as 50 Kg.
Page 32 of 79
(MC-5376)
Unaccountable Accountable
(i) Cement 3% Nil
(ii) Reinforcement Steel ½% 2.5%
(iii) Steel structural (Plates & Sections) ½% 4.5%
(iv) M.S. Plates for fabrication of Pipes ½% As per cutting diagrams approved by
Engineer-in-Charge before cutting and
fabrication.
The charging of penal rate shall be without the prejudice to the other remedies or action
available to the owner against the contractor including any criminal action.
Every month the Contractor shall submit a statement for all the materials supplied to him
by the owner in the proforma prescribed by the Engineer-in-Charge.
52.3.8 On completion of the work, the Contractor shall submit material appropriation statement
for the materials supplied to him by the Owner.
52.3.9 All materials supplied to the contractor shall remain the absolute property of the all times
and title therein shall not pass to the contractor at any time. The possession of the
materials in the hands of the contractor is only for the purpose of incorporating the same in
the Owner’s work. The material supplied shall not be removed by the contractor on any
account from the site of work and shall be at all times open for inspection by the Engineer-
in-Charge or owners representative. The contractor shall not use the materials supplied to
him for any purpose or work other than the work, which the said materials are supplied.
(i) Materials specified as to be issued by the Owner will be supplied to the contractor by the
Owner from his stores. It shall be the responsibility of the contractor to take delivery of
the materials and arrange for its loading, transport and unloading at the site work at his
own cost. The material shall be issued during the working hours of his Stores and as per
the rules of the Owner framed from time to time.
(ii) The contractor shall bear all incidental charges for the storage and safe custody of
materials at site after these have been issued to him.
(iii) The contractor shall construct suitable godown at the site of work for storing the materials
safe against damage by rain, dampness, fire, theft, etc. He shall also employ necessary
watch and ward establishment for the purpose.
(iv) Materials specified as to be issued by the Owner shall be issued in standard sizes as
obtained from the manufacturers.
(v) It shall be duty of the contractor to inspect the materials supplied to his at the time of
taking delivery and satisfy himself that they are in good condition. After the materials
have been delivered by the Owner, it shall be the responsibility of the contractor to keep
them in good condition and if the materials are damaged or lost, at any time, they shall be
Page 33 of 79
(MC-5376)
repaired and or replaced by him at his own cost according to the directions of the
Engineer-in-Charge.
(vi) The Owner shall not be liable for delay in supply or non-supply of any materials, which
the Owner has undertaken to supply where such failure or delay is due to natural
calamities, act of enemies, transport and procurement difficulties and any circumstances
beyond the control of the Owner. In no case, the contractor shall be entitled to claim any
compensation or loss suffered by him on his account.
(vii) It shall be the responsibility of the contractor to arrange in time all materials required for
the works other than those to be supplied by the Owner. If however in the opinion of the
Engineer-in-Charge the execution of the work. Is likely to be delayed due to the
contractor’s inability’s to make arrangements for supply of materials which normally he
has to arrange for, the Engineer-in-Charge shall have the right at his own discretion to
issue such materials if available with the Owner or procure the materials from the market
or elsewhere. The contractor will be bound to take such materials at the rates decided by
the Engineer-in-Charge. This however, does not in anyway absolve the contractor from
responsibility of making arrangement for the supply of such materials in part or in full,
should such a situation occur nor shall this constitute a reason for the delay in the
execution of the work.
(viii) Non of the materials supplied to the contractor will be utilised by the contractor for
manufacturing item which can be obtained as supplied from standard manufacturer in
finished form unless approved by Engineer-in-Charge in writing.
(ix) The contractor shall, if desired by the Engineer-in-Charge, be required to execute an
indemnity bond in the prescribed form for safe custody, usage and accounting of all
materials issued by the Owner.
(x) The contractor shall furnish to Engineer-in-Charge sufficiently in advance a statement
showing his requirements of the quantities of the materials to be supplied by the Owner
and the time when the same will be required by him for the works, so as to enable the
Engineer-in-Charge to make necessary arrangement for procurement and supply of
material.
(xi) Account of the materials to be issued by the Owner shall be maintained by the contractor
indicating the daily receipt, consumption and balance in hand in a manner prescribed by
the Engineer-in-Charge. All connected papers requisitions, issues returns etc. shall be
always available for inspection in the contractor’s office at site.
(xii) The contractor should see that only the required quantities of materials are got issued.
The contractor shall not be entitled to cartage and incidental charges for returning the
surplus materials, if any, to the stores, place of issue or to the place as directed by the
Engineer-in-Charge.
(xiii) Materials/equipment supplied by Owner shall not be utilised for any other purpose (s)
than issued for.
(xiv) The owner may issue the material in phases at his discretion keeping in view the
programmes of the work.
(xv) In case of free issue of materials, the contractor shall submit an indemnity bond in the
prescribed format for 80% (eighty) value of the materials and a bank guarantee for 20%
(twenty) of the value of the materials. The indemnity bond and bank guarantee shall be
valid till the material account is totally settled.
Page 34 of 79
(MC-5376)
return, if required by the project head all surplus or unserviceable materials that may be
left with him after the completion of the contract or at its termination for any reason
whatsoever on his being paid or credited such price as the Project head shall determine
having due regard so the condition of the materials. The price allowed to the contractor
however, shall not exceed the amount charged to him excluding the storage charges, if
any. The decision of the project head shall be final and conclusive in such matter. In the
event of breach of the aforesaid conditions, the contractor shall, in the terms of the
licences, or permits and/ or for criminal breach of trust, be liable to compensate the
Owner at double rate or any higher, in the event of those materials at the time having
higher rate or not being available in the market, then any other rate to be determined by
the project head and his decision shall be final and conclusive.
If the contractor in the course of execution of the work is called upon to dismantle any
part for reasons other than those stipulated in clauses 57 and 65 hereunder, the materials
obtained in the work of dismantling etc. will be considered as the Owner’s property and
will be disposed off to the best advantage of the Owner.
All gold silver and other materials of any descriptions, precious stones, coins, treasures,
relics, antiques and other similar things which shall be found, in, under or upon the site,
shall be property of the Owner and the contractor shall duly preserve the same to the
satisfaction of the Engineer-in-Charge and shall from time to time delivery the same to
such person or persons indicated by the Owner.
Page 35 of 79
(MC-5376)
Should any discrepancy arise between the various instructions furnished to the contractor
or his agents or staff or if any doubt arises on the meaning or implementation of any such
instructions or should there be any difference of opinion on the issues, the contractor
shall refer the matter immediately in writing to the Engineer-in-Charge whose decisions
thereon shall be final and conclusive. No claim on losses alleged to have been caused
by such discrepancies between instructions, doubts or misunderstanding shall in any
event be admissible.
(a) The Project Head shall have power to make any alterations, in omission from
additions to or substitutions, for the schedule of rates, the original specifications,
drawings and instructions that may appear to him to be necessary or advisable
during the progress of the work, and the contractor shall be bound to carry out
such altered/ extra/ new items of work in accordance with any instructions which
may be given to him in writing signed by the Project Head and such alterations,
omissions, additions or substitutions shall not invalidate the contract and any
altered, additional or substituted work which the contractor may be directed to do
in the manner above specified as part of the work shall be carried out by the
contractor on the same conditions in all respects on which he agreed to do the
main work. The time of completion of work may be extended for the part of the
particular job at the discretion of the Project Head for any such alterations,
additions, or substitutions of the work, as he may consider as just and reasonable.
The rates for such additional, altered or substituted work under the clause shall be
worked out in accordance with the following provisions:-
(b) If the rates for the additional, altered or substituted work are specified in the
contract for the work, the contractor is bound to carry out the additional, altered or
substituted work at the same rates as are specified in the contract.
(c) If the rates for the additional, altered or substituted work are not specifically
provided in the contract for the work, the rates will be derived from rates for similar
class of work as are specified in the contract for the work. The opinion of the
Project head as to whether or not the rates can be reasonably so derived from the
items in this contract will be final and binding on the contractor.
(d) If the rates for the additional, altered or substituted work can not be determined in
the manner specified in sub-clause (a) & (b) above, then the contractor shall
within 7 days of the date of receipt of order to carry out the work, inform the
Project Head of the rate which it is his intention to charge for such class of work,
supported by analysis of the rate or rates claimed, and the project Head shall
determine the rate or rates on the basis of the prevailing market rates of materials
plus labour cost including equipment hire charge at schedule of hourly/ daily rates
plus 15% to cover contractor’s supervisions overhead and profit and pay to the
contractor accordingly. The opinion of the Project Head to current market rates of
the materials and the quantum of labour and equipment involved per unit of
measurement will be final and binding on the contractor. The schedule of hourly/
daily rates shall be as enclosed.
Page 36 of 79
(MC-5376)
62 Abnormal Rates:
The contractor is expected to quote the rate for each item after careful analysis of cost
involved for the satisfactory performance and completion of item work considering all
specifications and conditions of contract. This will avoid loss of profit or gain in case of
curtailment or change in specification for any other item. In case the rate quoted by the
tenderer for any item are usually high or unusually low it will be sufficient cause of the
rejection of the tender unless the Owner is convinced about the reasonableness of the
analysis for such rate furnished by the tenderer (on demand) after scrutiny.
64. Samples:
The contractor shall furnish to the Engineer-in-Charge for approval when request or if
required by the specifications, adequate samples of all materials and finished to be used
in the work. Such samples shall be submitted before the work is commenced and in
sample time to permit tests and examinations thereof. All materials furnished and
finishes applied in actual work shall be fully equal to the approved samples.
If it shall appear to the Engineer-in-Charge that any work has been executed with
unsound, imperfect or unskilled workmanship, or with materials of any inferior description,
or that any materials or articles provided by the contractor for the execution of work are
unsound or of quality inferior to that contracted for, or otherwise not in accordance with
the contract, the contractor shall on demand in writing from the Engineer-in-Charge or his
authorised representative specifying the work, materials or articles complained of,
notwithstanding that the same may have been inadvertently passed, certified and paid
for, forthwith rectify or remove and reconstruct that work so specified and provide other
proper and suitable materials or articles at his own charge and cost, and in the event of
Page 37 of 79
(MC-5376)
Page 38 of 79
(MC-5376)
In case contractor shall fail to do so, the Owner may take, at the cost of contractor, such
steps as may in all circumstances be reasonable to make good such defects. The
expenditure so incurred by the owner be recovered from the amount due to the
contractor. The decision of the Engineer-in-Charge with regard to the amount to be
recovered from the contractor will be final and binding on the contractor. As soon as the
works have been completed in accordance with the contract (except minor respects that
do not affect their use for the purpose for which they are intended and except for
maintenance thereof provided in clause 68.1 of General Conditions of Contract) and have
passed the tests on completion, the Engineer-in-Charge shall issue a certificate
(hereinafter called completion certificate) in which he shall certify the date on which the
works have been so completed and have passed the said tests and the Owner shall be
deemed to have taken over the works on the date so certified. If the works have been
divided into various groups in the contract, the Owner shall be entitled to take over any
group or groups before the other or others.
If by reason of any default on the part of the contractor a completion certificate has not
been issued in respect of every portion of the works within one month after date fixed by
the contract for the completion of the works, the Owner shall be a liberty to use the work
or any portion thereof in respect of which a completion certificate has not been issued,
provided that the works or the portion thereof so used as aforesaid shall be afforded
reasonable opportunity for completion of these works for the issue of completion
certificate.
Page 39 of 79
(MC-5376)
SECTION – VI
CERTIFICATE AND PAYMENT
Generality of this present provision shall not be deemed to cut down or limited in any way
because in certain cases it may and in other cases it may not expressly stated that the
contractor shall do or perform a work or supply articles or perform with services at his
own cost or without addition of payment or without extra charge or works to the same
effect or that it may be stated or not stated that the same are included in and covered by
the schedule of rates.
use on the works of any such articles, processes or charges if levied on materials,
equipment or machinery to be brought to site for use on work, shall be borne by the
contractor.
69.5 Schedule of Rates to cover taxes and duties:
No exemption or reduction of custom duties, excise duties, sales tax, quay or any port
duties, transport charges, stamp duties or Central or State Government or Local Body (or
from any other body) or Municipal Taxes or duties, taxes or charges whatsoever will be
granted or obtained and all expenses of which shall be deemed to be included in and
covered by the schedule of rates. The contractor shall be obtain and pay for all permits
or other privileges necessary to complete the work.
69.6 Schedule of Rates to cover Risk of Delay:
The schedule of rates shall be deemed to include and cover the risk of all responsibilities
of delay and interference with the contractor’s conduct of work which occur from any
cause including orders of the owner in the exercise of his powers and on account of
extension of time granted due to various and for all other possible or probable causes of
delay.
69.7 Schedule of Rates cannot be altered:
For work under unit rate basis no alteration will be allowed in the schedule of rates by
reasons of works or any part of them being modified, altered, extended, diminished or
omitted. The schedule of rates is of fully inclusive rates which have been fixed by the
contractor and agreed to by the Owner and cannot be altered.
69.7.1 The schedule of rates to cover for working in operating plant. Contractor’s rates shall be
deemed to include taking into account that he has to work in operating plant and shall
take sufficient care in moving the plants, equipments and materials from one place to
another, so that they do not cause any damage to any person or to the property of the
owner or to thirty party including over head and underground cable/pipe lines. In the
event of such damages including eventual loss of production and operation of the plant or
services in any plant or establishment as estimated by the owner or ascertained or by the
third party shall be borne by the contractor. Since the work is to be executed for the
expansion of the plant, the rate of the contractor shall also deem to include all
interference/obstruction/interruption for which no compensation shall be paid to be
contractor.
70. Procedure For Measurement/ Billing of Work in Progress:
70.1 All measurements shall be in metric system. All the works in progress will be jointly
measured by the representative of the Engineer-in-Charge and the contractor’s
authorised agent progressively. Such measurements will be got recorded in the
measurement book by the Engineer-in-Charge or his authorised representative and
signed in token of acceptance by the contractor or his authorised representative.
For the purpose of taking joint measurement the contractor’s representative shall be
bound to be present whenever required by the Engineer-in-Charge. If, however, he
absents for any reason whatsoever the measurements will be taken by the Engineer-in-
Charge or his representative and this will be deemed to be correct and binding on the
contractor.
70.2 Billing:
The contractor will submit a bill in approved proforma in accordance with the contract
terms and the agreed billing schedules in quintuplicate to the Engineer-in-Charge giving
abstract and detailed measurement for the various items executed during a month, before
the expiry of the first week of the succeeding month. The Engineer-in-Charge shall take
Page 41 of 79
(MC-5376)
or cause to be taken the requisite measurements for the purpose of having the same
verified and the claim as far as admissible, adjusted, if possible, before the expiry of 10
days form presentation of the bill.
70.2.1 The bill shall be submitted by the contractor in computerised formats approved by the
owner. The bills along-with floppies containing measurement of work, particulars of
materials, recoveries etc. have to be submitted to the owner.
70.2.2 For lump-sum contracts, the payment will be according to agreed billing schedule. No
adjustment shall be allowed in lump-sum prices for any variations in the quantities,
specifications etc. shall take or a cause to be taken the requisite measurement for the
purposes of having the same verified and the claim as far as admissible, adjusted, if
possible, before the expiry of 10 days from presentation of the bill.
70.3 Secured Advance on Materials:
In case of tenders for completed items of works, contractor may be allowed “Secured
Advance” on the security of materials brought to site for execution of the contracted items
of work to the extent of 75% of the value of materials which go into the completed works
as assessed by the Engineer-in-Charge provided that the materials are of an
imperishable nature and that formal agreement is drawn up with the contractor under
which the Owner secures a lien on the materials and is safe guarded against losses due
to the contractor postponing the execution of the work or to the improper storage &/or
misuse of the materials and against the expenses entitled for their proper watch and safe
custody. Recoveries of advances so made would not be postponed until the whole of the
work entrusted to the contractor is completed. They should be adjusted from his running
account bills for work done as the materials are used, the necessary deductions being
made whenever the items of work in which they are used and billed for.
Page 42 of 79
(MC-5376)
of the accruing of any claim by the contractor, nor shall it, conclude, determine or affect in
any way the powers of the Owner under these conditions or any of them as to the final
settlement and adjustments of the accounts or otherwise, or in any other way vary or
affect the contract. The final bill shall be submitted by the contractor within one month
from the sate of physical completion of the work, otherwise, the Engineer-in-Charge’s
certificate of the measurement and of total amount payable for the work accordingly shall
be final and binding on all parties.
Payment due to the contractor shall be made by the Owner, by Crossed Account Payee
Cheque forwarding the same to registered office or the notified office of the contractor. In
no case will owner be responsible if the Cheque is mislaid or misappropriated by un-
authorised person/ persons. In all cases, the contractor shall present his bill duly pre-
receipted on proper revenue stamp.
Page 43 of 79
(MC-5376)
The Owner or his representative shall normally issue to the contractor the completion
certificate within one month after receiving an application therefore from the contractors
after verifying from the completion documents and satisfying himself that the work has
been completed in accordance with and as set out in the construction and erection
drawings, and the contract documents.
The contractor, after obtaining the completion certificate, is eligible to present the final bill
for the work executed by him under the terms of contract.
If the contractor shall fail to comply with the requirements of this clause on or before the
date fixed for the completion of the work, the Engineer-in-Charge may at the expenses of
contractor remove such scaffolding, surplus materials and rubbish and dispose off the
same as he thinks fit and clean off such dirt as aforesaid, and the contractor shall
forthwith pay the amount for all expenses so incurred and shall have no claim in respect
of any such scaffolding or surplus materials as aforesaid except for any sum actually
realized by the sale thereof.
Page 44 of 79
(MC-5376)
Page 45 of 79
(MC-5376)
SECTION – VII
Sales Tax or any other tax on materials required for the works as also Tax on works contract
shall be payable by the Contractor and the Owner will not entertain any claim whatsoever in this
regard.
79.2. Notwithstanding anything contained elsewhere in the contract, the owner shall deduct at source
from the payments due to the contractor, the taxes as required under Section -13–AA of the
Orissa Sales Tax Act or as amended from time to time or under any other statue. The amounts
so deducted shall be deposited by the Owner with the Sales Tax authorities as per Law. It is for
the contractor to deal with the Sales Tax authorities directly in respect of any claim or refund
relating to the above deductions and the owner shall not be liable or responsible for any claims
or payments or reimbursement in this regard.
80. INSURANCE:
Contractor shall at his own expense carry and maintain insurance with reputed insurance
companies to the satisfaction of the Owner as follows:
The contractor agrees to fill in with the Employees State Insurance Corporation, the Declaration
Forms and all forms which may be required in respect of the contractor’s or sub-contractor’s
employees, whose aggregate remuneration is Rs. 560.00 per month or less and who are
employed in the work provided for or those covered by ESI from time to time under the
Agreement. The contractor shall deduct and secure the agreement of the sub-contractor to
deduct the employee’s contribution as per the first schedule of the Employee’s State Insurance
Act from wages and affix the employee’s contribution cards at wages payments intervals. The
contractor shall remit and secure the agreement of the sub-contractor to remit to the State Bank
of India, Employees State Insurance Corporation Account, the employee’s contribution as
required by the Act. The contractor agrees to maintain all cards and records as required under
the Act in respect of employees and payments and the contractor shall secure the agreement of
the sub-contractor to maintain such records. Any expenses incurred for the contributions,
making contributions or maintaining records shall be to the contractor’s or sub-contractor’s
account.
Page 46 of 79
(MC-5376)
The Owner shall retain such sum as may be necessary from the total contract value until the
contractor shall furnish satisfactory proof that all contribution as required by the Employees State
Insurance Act, 1984, have been paid. This will be pending on the contractor when the
Employees State Insurance Act is extended to the place of work.
Page 47 of 79
(MC-5376)
SECTION – VIII
LABOUR LAWS AND ARBITRATION
83 LABOURER LAWS:
Contractor shall comply with any and all laws, ordinances, regulations and decision of courts
(which shall be deemed to be a part of this Agreement) concerning the health, sanitary
arrangements, wages, welfare, safety and employment of any and all of his workers upon the
Project or any portion thereof and shall exclusively bear the consequences of failure to comply
therewith Contractor shall Indemnify and hold Engineer and Owner harmless from any claims,
fines or penalties which may be made against Engineer or Owner as result of Contractor’s
failure to fulfill these obligations.
Without limiting the generality of the foregoing, Contractor shall fully comply with.
The contractor shall obtain clearance from the Labour Department regarding the compliance of
the labour laws on 6 monthly basis and submit to the owner for record.
(i) No labour below the age of 18 (eighteen) years shall be employed on the work.
(ii) The contractor shall not pay less than what is provided under law to labourers engaged
by him on the work.
(iii) The contractor shall at his expense comply with all labour laws and keep the Owner
indemnified in respect thereof .
(iv) The contractor shall pay equal wages for men and women in accordance with applicable
labour laws.
(v) If the contractor is covered under the contractor labour (Regulation and Abolition) Act, he
shall obtain a licence from licensing authority (i.e. office of the labour commissioner) by
payment of necessary prescribed fee and the deposit, if any, before starting the work
under the contract.
(vi) The Contractor shall employ labour in sufficient numbers either directly or through sub-
contractors to maintain the required rate of progress and of quality to ensure
workmanship of the degree specified in the Contract and to satisfaction of the Engineer-
in-Charge. The contractor shall not employ in connection with the works any person who
has not completed his 18 (eighteen) years of age.
(vii) The Contractor shall furnish to the Engineer-in-Charge the distribution return of the
number and description, by trades of the work people employed on the works. The
th th
Contractor shall also submit on the 4 and 19 of every month to the Engineer-in-Charge
a true statement showing in respect of the second half of the preceding month and the
first half of the current month (1) the accidents that occurred during the said fortnight
showing the circumstance-under which they happened and the extent of damage and
injury caused by them and (2) the number of female workers who have been allowed
Maternity benefit as provided in the Maternity Benefit Act 1961 or Rules made thereunder
and the amount paid to them.
(viii) The contractor shall comply with the provisions of the payment of Wages Act 1936,
Minimum Wages Act 1938, Employees Liability Act 1928. Workmen’s Compensation Act,
1923, Industrial Dispute Act 1947, the Maternity Benefit Act 1961, Employees Provident
Fund Act, 1952 and Contract Labour regulation and abolition Act 1937, Employment of
Children Act 1938 or any modifications thereof or any other law relating thereto and rules
made thereunder from time to time.
(ix) The Engineer-in-Charge shall on a report having been made by an Inspecting Officer as
defined in Contract Labour (Regulation and Abolition) Act 1970 have the power to deduct
from the moneys due to the Contractor any sum required or estimated to be required for
making good the loss suffered by a worker or Workers by reason of non-fulfillment of the
Page 48 of 79
(MC-5376)
85.3 In every case in which by virtue of the provisions of section 12, sub-section (i) of workmen’s
compensation Act, 1923 or other applicable provision of Workman Compensation act or any
other act, the Owner is obliged to pay compensation to workman employed by the contractor in
execution of the works, the Owner will recover from the contractor the amount of the
compensation so paid, and without prejudice to the rights of Owner under section 12, sub-section
(2) of the said act. Owner shall be at liberty to recover such amount or any part thereof by
deducting it from the security deposit or from any sum due to the contractor whether under this
Page 49 of 79
(MC-5376)
contract or otherwise. The Owner shall not be bound to contest any claim made under section
12 sub-section (I) of the said Act except on the written request of the contractor and upon his
giving to the Owner full security for all costs for which the Owner might become liable in
consequence of contesting such claims.
For the purpose of appointing the sole Arbitrator referred to above, the Appointing Authority will
send within thirty days of receipt of the notice, to the contractor a panel of three names of
persons.
The contractor shall on receipt of the names as referred selected any one of the person names
to be appointed as a sole Arbitrator and communicate his name to the Appointing Authority within
thirty days of receipt of the names. The appointing Authority shall there upon without any delay
appoint the said person as the sole Arbitrator. If the contractor fails to communicate such
selection as provided above within the period specified, the Appointing Authority shall make the
selection and appoint the selected person as the sole Arbitrator.
If the Arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacate his
office due to any reason whatsoever sole Arbitrators shall be appointed as aforesaid. The work
under the contract shall, however continue during the arbitration proceedings.
The Arbitrator shall be deemed to have entered on the reference on the date he issues notices to
both the parties fixing the date of the first hearing.
The Arbitrator may, from time to time, with the consent of the parties, enlarge the time for making
and publishing the award.
The Arbitrator shall give a separate award in respect of each dispute or difference and shall give
a reasoned and speaking award/ awards.
The venue of arbitration shall be at Bhubaneswar. However, if the situation so warrants, it may,
as and when required, be held at the place where the site of work is situated.
Page 50 of 79
(MC-5376)
The fees, if any, of the Arbitrator shall, if required to be paid before the award is made and
published be paid half and half by each of the parties. The costs of the reference and of the
award including the fees, if any of the Arbitrator shall be in the discretion of the Arbitrator who
may direct to and by whom and in what manner, such costs or any part thereof shall be paid may
fix or settle the amount of costs to be so paid.
The award of the arbitrator shall be final and binding on both the parties.
Subject to aforesaid, the provisions of the Arbitration Act 1940 or any statutory modification or re-
enactment thereof and the rules made thereunder, and for the time being in force shall apply to
the arbitration proceeding under this clause.
For Public Sector Enterprises guidelines as per the circular of BPE No. 15/9/86-BPE (FIN) dated
30.03.89 as amended time to time will be followed.
For all disputes arising of this contract, the jurisdiction shall be lie under the jurisdiction of
direct courts in the respective areas in the State of ORISSA (India) only.
Page 51 of 79
(MC-5376)
SECTION – IX
SAFETY CODE
89. GENERAL:
Contractor shall adhere to safe construction practice and guard against hazardous and unsafe
working conditions and shall comply with Owner’s safety rules as set forth herein. Prior to start
of construction, contractor will be furnished copies of Owner’s ‘Safety Code’ for information and
guidance, if it has been prepared.
(ii) Contractors shall make outside arrangements for ambulance service and for treatment of
industrial injuries. Name of those providing these services shall be furnished to Owner
prior to start of constructions and their telephone numbers shall be prominently posted in
Contractor’s field office.
(iii) All critical industrial injuries shall be reported promptly to owner, and a copy of
Contractor’s report covering each personal injury requiring the attention of a physical
shall be furnished to the Owner.
Page 52 of 79
(MC-5376)
94. Scaffolding:
(i) Suitable scaffoldings should be provided for workmen for all works that cannot safety be
done from the ground or from solid construction except such short period works as can be
done safely from ladders. When a ladder is used a Mazdoor shall be engaged for holding the
ladder and if the ladder is used for carrying materials as well, suitable footholds and
handholds shall be provided on the ladder and the ladder shall be given an inclination not
steeper than 1 in 4 (1 horizontal and 4 vertical).
(ii) Scaffolding or staging more than 4 metres above the ground or floor swing on suspended
from an overhead support or erected with stationary support shall have a guard rail properly
attached, bolted, braced and otherwise retarded at least one metre high above the floor or
platform of such scaffolding or staging and extending along with entire length of the outside
and ends thereof with only such openings as may be necessary for the delivery of materials.
Such scaffolding or staging shall be so fastened as to prevent it from swaying from the
building or structure.
(iii) Working platform, gangways and stairways should be so constructed that they should not sag
unduly or unequally and if the height of the platform of gangway or the stairway is more than
4 metres above ground level or floor level, they should closely boarded, should have
adequate width and should be suitable fastened as described in (ii) above.
(iv) Every opening in the floor of a building or in a working platform be provided with suitable
means to prevent the fall of persons or materials by providing suitable fencing or railing
whose minimum height shall be 1 metre.
(v) Safe means of access shall be provided to all working platforms and other working places.
Every ladder shall be security fixed. No portable single ladder shall be over 9 metres in
length. The width between the side rails in run ladder shall in no case be less than 30 cm.
For ladder upto and including 3 metres in length; for longer ladders this width should be
increase at least 15 mm for each additional metre of length. Uniform step spacing shall not
exceed 30 cms. Adequate precautions shall be taken to prevent danger from electrical
equipment. No materials on any of the sites of work shall be so stacked or placed as to
cause danger or inconvenience to any person or public. The contractor shall also provide all
necessary fencing and lights to protect the workers and staff from accidents, and shall be
bound to bear the expenses of defence of every suit, action or other proceedings of law that
may be brought by any person for injury sustained owing to neglect of the above precautions
and to pay any damages and cost which may be awarded in any such suit or action or
proceedings to any such person or which may with the consent of the contractor be paid to
compromise any claim by any such person.
Ladder shall be extended from bottom of the trench to at least 1 metre above the surface of the
ground. The sides of the trenches which are 1.5 metres in depth shall be stepped back to give
suitable slope, or securely held by timber bracing, so as to avoid the danger of sides to collapse.
The excavated materials shall not be placed within 1.5 metres of the edge of the trench or half of
the trench width whichever is more. Cutting shall be done from top to bottom. Under no
circumstances undermining or under-cutting shall be done.
Page 53 of 79
(MC-5376)
protected.
(b) No electric cable or apparatus which is liable to be a source of danger shall remain
electrically charged.
(c) All practical steps shall be taken to prevent danger to persons employed from risk of
fire or explosion or flooding. No floor, roof or other part of the building shall be so
overloaded with debris or materials as to render it unsafe.
(ii) All necessary personal safety equipment as considered adequate by the Engineer-in-
Charge, should be kept available for the use of the persons employed at the site and
maintained condition suitable for immediate use and the contractor should take adequate
steps to ensure proper use of equipment by persons concerned as outlined below:
(a) Workers employed on mixing asphalt materials, cement and lime mortars shall be
provided with protective footwear and protective gloves.
(b) Those engaged in white washing and mixing or stacking of cements bags or any
materials which are injurious to the eyes shall be provided with protective goggles.
(c) Those engaged in welding and cutting works, shall be provided with protective face and
eye –shields, hand gloves etc.
(d) Stonebreakers shall be provided with protective goggle and protective clothing and
seated at sufficiently safe intervals.
(e) When workers are employed in sewers and manholes which are in use, the contractor
shall ensure that the manhole cover are opened and are ventilated at least for an hour
before the workers are allowed to get into the manholes, and the manholes so opened
shall be cordoned off with suitable railing and provided with warning signals or board to
prevent accident to the public.
(f) The contractor shall not employ men below the age of 18 years and women on the work
of painting with products containing lead in any form. Wherever men above the age of
18 years are employed on the work of lead painting, the following precautions should be
taken:
(1) No paint containing lead or lead products shall be used except in the form paste
or readymade paint.
(2) Suitable facemasks should be supplied for use by the workers when paint is
applied in the form of spray or a surface having lead paint dry rubbed and
scrapped.
(3) Overalls shall be supplied by the Contractor to the workmen and adequate
facilities shall be provided to enable the working painters to wash them on
cessation of work.
(iii) When the work is done near any place where there is a risk of drowning all necessary safety
equipment shall be provided and kept ready for use and all necessary steps taken for prompt
rescue of any person in danger and adequate provision should be made for prompt first aid
treatment of all injuries likely to be sustained during the course of the work.
(iv) Use of hoisting machines and tackles including their attachments anchorage and supports
shall conform to the following standard or conditions:
(a) These shall be of good mechanical construction, sound materials and adequate
strength and free from patent defect and shall be kept in good working order.
(b) Every rope used in hoisting or lowering materials or as means of suspension shall be of
durable quality and adequate strength and free from patent defects.
(c) Every crane driver or hoisting appliance operator shall be properly qualified and no
person under the age of 21 years should be in charge of any hoisting machine including
any scaffolding which or give signals to the operator.
(d) In case of every hoisting machine and of every chain ring hook, shackle swivel and
pulley block used in hoisting or lowering or as means of suspension, the safe working
load shall be ascertained by adequate means. Every hoisting machine and all gear
referred to above shall be marked with the safe working load and the conditions under
which it is applicable shall be clearly indicated. No part of any machine or any gear
Page 54 of 79
(MC-5376)
referred to above in this paragraph shall be loaded beyond the safe working load except
for the purpose of testing.
(e) In case of department machines, the safe working load shall be notified by the
Engineer-in-Charge. As regards contractor’s machines, the contractor shall notify the
safe working load of the machine to the Engineer-in-Charge, whenever he brings any
machinery to site of work and get it verified by the Engineer-in-Charge.
(v) Motors, gears, transmission lines, electric wiring and other dangerous parts of hoisting
appliances should be provided with efficient safe-guards. Hoisting appliances should be
provided with such means as to reduce to the minimum the accidental descent of the load,
adequate precaution should be taken to reduce to the minimum the risk of any part or
parts of a suspended load becoming accidentally displaced. When workers are employed
on electrical installations, which are already energized, insulating mats, wearing apparel
such as gloves sleeves and boots as may be necessary should be provided. The workers
shall not wear any rings, watches and carry keys or other materials, which are good
conductors or electricity.
(vi) All scaffolding, ladders and other safety devices mentioned or described herein shall be
maintained in safe conditions and no scaffoldings, ladder or equipment shall be altered or
removed while it is in use. Adequate washing facilities should be provided at or near
places of works.
(vii) These safety provisions should be brought to the notice of all concerned by displaying on
a notice board at a prominent place at the work spot. The person responsible for
compliance of the safety code shall be named therein by the contractor.
(viii) The ensure effective enforcement of the rules and regulations relating to safety
precautions, the arrangements made by the contractor shall be open to inspection by the
welfare officer Engineer-in-Charge or safety Engineer of the Administration or their
representatives.
(ix) Notwithstanding the above clauses there is nothing in these to exempt the contractor from
the operations of any other Act or rules in force in the Republic of India. The works
throughout, including any temporary works, shall be carried out in such a manner as n9ot
to interfere in any way whatsoever with the traffic on any roads or footpaths at the site or in
vicinity thereto or any existing works whether the property of the Administrations or of a
third party.
97. Care in handling Inflammable gas:
The Contractor has to ensure all precautionary measures and exercise utmost care in handling
the inflammable gas cylinder/ inflammable liquids/ paints etc. as required under the law and/ or
as advised by the fire authorities of the Owner.
98. Temporary Combustible Structures:
Temporary combustible structures will not be built near or around work site.
99. Precautions Against Fire:
The Contractor will have to provide Fire Extinguisher/ Fire Buckets and drums at work site as
recommended by Engineer-in-Charge. They will have to ensure all precautionary measures and
exercise utmost care in handling the inflammable gas cylinders/ inflammable liquid/ paints etc. as
advised by Engineer-in-Charge. Temporary combustible structures will not be build near or
around the work-site.
100. Explosives:
Explosives shall not be stored or used on the works or on the site by the contractor without the
permission of the Engineer-in-Charge in writing and then only in the manner and to the extent to
which such permission is given. When explosives are required for the works they shall be stored
in a special magazine to be provided at the cost of the contractor in accordance with the Explosive
Rules. The contractor shall obtain the necessary licence for the storage and the use of explosives
and all operations in which or for which explosives are employed shall be at sole risk and
Page 55 of 79
(MC-5376)
responsibility of the contractor and the contractor shall indemnify the owner against any loss or
damage resulting directly or indirectly therefrom.
101. Mines Act:
101.1 Safety Code: The contractor shall at his own expense arrange for the safety provisions as
required by the Engineer-in-Charge in respect of all labour directly employed for performance of
the works and shall provide all facilities in connection therewith. In case the Contractor fails to
make arrangements and provides necessary facilities as aforesaid. The Engineer-in-Charge shall
be entitled to do so and recover the costs thereof from the Contractor.
101.2 Failure to comply with Safety code or the provisions relating to report on accidents and to grant of
maternity benefits to female worker shall make the Contractor liable to pay Company liquidated
damages an amount not exceeding Rs. 50/- for each default or materially incorrect statement.
The decision of the Engineer-in-Charge in such matters based on reports from the Inspecting
Officer or from representatives of Engineer-in-Charge shall be final and binding and deductions
for recovery of such liquidated damages may be made from any amount payable to the Contractor
from all the provisions of the Mines Act 1952 or any statutory modification’s or re-enactment
thereof the time being in force and any Rules and Regulations made thereunder in respect of all
the persons employed by him under this contractor and shall indemnify the Owner from and
against any claim under the Mines Act or the rules and regulations framed thereunder by or on
behalf of and persons employed by him or otherwise.
Page 56 of 79
(MC-5376)
B. G. No._____________ Date:_____________
Page 57 of 79
(MC-5376)
8. We………………Bank, lastly undertake not to revoke this guarantee during its currency except
with the previous consent of the Company in writing. We further undertake to keep this Guarantee
renewed from time to time on the request of Tenderer (s).
Date……………..
………………………….Bank
Corporate Seal of the Bank By its constitutional Attorney
Signature of duly
Authorised person
On behalf of the Bank
With seal & signature code
Page 58 of 79
(MC-5376)
2. We ……………………………..Bank having its branch office at ……..do hereby agree and undertake to
pay the amount due and payable under this guarantee without any demur, merely on a demand from the
Company stating that in the opinion of the company which is final and binding, the amount claimed is due
by way of loss or damage caused to or would be caused to or suffered by the Company by reason of any
breach by the said Contractor(s)/seller(s) of any of the terms and conditions contained in the said
contract(s) orders(s) or by reasons of the said Contractor(s)/ Seller(s) failure to perform the said
Contract(s)/ Order(s) including defect liability obligations or that the amount covered under this guarantee
is forfeited. Any such demand made on the Bank by the owner shall be conclusive as regards the
amount due and payable by the Bank under this guarantee. However, our liability under this guarantee
shall be restricted to an amount not exceeding Rs………………. (Rupees………………..only).
3. We undertake to pay to the Company any money so demanded not withstanding any dispute or
disputes raised by the contractor (s)/ Seller(s) in any suit or proceeding pending before any office, court
or tribunal relating thereto our liability under present guarantee being absolute and unequivocal. The
payment so made by us under this bond shall be valid discharge of our liability for payment thereunder.
Our liability to pay is not dependent or conditional on the owner proceeding against the Contractor(s)/
Seller(s).
4. The guarantee herein contained shall not be determined or affected or suspended by the liquidation or
winding up, dissolution or change of constitution or insolvency of the said Contractor(s)/ Seller(s) but shall
in all respect and for all purposes be binding and operative until payment of all money due or liabilities
under the said contract(s)/ Order(s) are fulfilled.
5. We ……………..Bank further agree that the guarantee herein contained shall remain in full force and
effect during the period that would be taken for the performance of the said Contract(s)/ Order(s) and that
it shall continue to be enforceable till all the dues of the company under or by virtue of the said
Contract(s)/Order(s) have been fully paid and its claims satisfied or discharged or till a duly authorised
officer of the company certifies that the terms and conditions of the said Contract(s)/Order(s) have been
fully and properly carried out by the said contractor(s) and accordingly discharges the guarantee.
6. We ……………Bank further agree with the Company that the company shall have the fullest liberty
without our consent and without affecting in any manner our obligations hereunder to vary any of the
terms and conditions of the said Contract(s)/ Order(s) or to extend the time of performance by the said
Contractor(s) Seller(s) form time to time or to postpone for any time or from time to time any of the
powers exercisable by the Company against the said Contractor(s)/ Seller(s) and to forbear or enforce
any of the terms and conditions relating to the said Contract(s)/ Order(s) and we shall not be relieved
from our liability by reason of any such variations, or extension being granted to the said Contractor (s)/
Seller(s) or for any forbearance, act or omissions on the part of the Company or any indulgence by the
Company to the said Contractor(s)/ Seller(s) or by any such matter or thing whatsoever which under the
law relating to sureties would, but for this provision, have affect of so relieving us.
Page 59 of 79
(MC-5376)
7. Notwithstanding anything contained herein before, our liability shall not exceed
Rs………………….(Rupees…………………………only) and shall remain in force till……………..Unless a
demand or claim under this Guarantee is made on us within three months from the date of expiry we shall
be discharged form all the liabilities under this guarantee.
8. We…………………Bank, lastly undertake not to revoke this guarantee during its currency except with
the previous consent of the Company in writing. We further undertake to keep this Guarantee renewed
from time to time at the request of Contractor(s)/ Sellers(s).
Date………. ………………………….Bank
Signature of duly
Authorised person
On behalf of the Bank
With seal & signature code
Page 60 of 79
(MC-5376)
WHEREAS National Aluminium Company Limited (A Government of India Enterprise) having its
Corporate Office at NALCO BHAWAN, P-1 Nayapalli, Bhubaneswar (hereinafter called “Company’/
‘Owner” which expression shall unless repugnant to the subject or context includes its legal
representatives, successors and assigns) has entered into a contract with M/s.
………………………………. / has placed a purchase order on M/s………………………….(hereinafter
referred to as “Contractor(s)/ Seller(s)” which expression shall unless repugnant to the subject or context
includes their legal representatives, successors and assigns) for …………………………….on the terms
and conditions as set out inter alia, in the Company’s contract No./ P.O. No. ………….. date
…………and various documents forming part thereof hereinafter referred to as the “said contract” which
expression include all amendments, modifications and/ or variations thereto and where as the
Contractor(s)/ Seller(s) has agreed for due execution of the entire contract and guarantees its
performance including any parts executed through any other agencies/ subcontractors.
AND WHEREAS one of the conditions of the “said contract” is that “contractor(s)/seller(s) shall furnish to
the owner a Bank Guarantee from a bank for …….%(……….percent) of the total value of the “said
contract” against due and faithful performance of the “said contract” including defect liability obligations”
and the performance guarantee obligations of the contractor(s)/seller(s) for execution/ supplies made
under the “said contract.”
Page 61 of 79
(MC-5376)
6. We ……………Bank further agree with the Company that the company shall have the fullest liberty
without our consent and without affecting in any manner our obligations hereunder to vary any of the
terms and conditions of the said Contract(s)/ Order(s) or to extend the time of performance by the said
Contractor(s) Seller(s) form time to time or to postpone for any time or from time to time any of the
powers exercisable by the Company against the said Contractor(s)/ Seller(s) and to forbear or enforce
any of the terms and conditions relating to the said Contract(s)/ Order(s) and we shall not be relieved
from our liability by reason of any such variation, or extension being granted to the said Contractor (s)/
Seller(s) or for any forbearance, act or omission on the part of the Company or any indulgence by the
Company to the said Contractor(s)/ Seller(s) or by any such matter or thing whatsoever which under the
law relating to sureties would, but for this provision, have affect of so relieving us.
7. Notwithstanding anything contained herein before, out liability shall not exceed
Rs………………….(Rupees…………………………only) and shall remain in force till……………..Unless a
demand or claim under this Guarantee is made on us within three months from the date of expiry we shall
be discharged form all the liabilities under this guarantee.
8. We…………………Bank, lastly undertake not to revoke this guarantee during its currency except with
the previous consent of the Company in writing. We further undertake to keep this Guarantee renewed
from time to time at the request of Contractor(s)/ Sellers(s).
Date………. …….…………………….Bank
Corporate Seal of the Bank By its constitutional Attorney
Signature of duly Authorised
person on behalf of the Bank
with seal & signature code
Page 62 of 79
(MC-5376)
Page 63 of 79
(MC-5376)
8. We…………………Bank, lastly undertake not to revoke this guarantee during its currency except
with the previous consent of the Company in writing. We further undertake to keep this
Guarantee renewed from time to time on the request of the Tenderer(s).
Date………. ………………………….Bank
Page 64 of 79
(MC-5376)
Page 65 of 79
(MC-5376)
APPENDIX –I A
_____________________________________________________________________________
Sl. Name of work Estimated When When Date of Remarks
No. done cost started completed Completion
As per contract
_____________________________________________________________________________
______________________________________________________________________________
Note : 1. In the remarks column, please state whether the works stated above are carried
out by you in the name of the Firm in which the present Bid is submitted or any
other names. If later, state the relationship of the firm and also a copy of the
Partnership Deed.
2. Please enclose the true copy of the certificate issued by the authorities, if any.
Signature of Bidder
Page 66 of 79
(MC-5376)
APPENDIX –I B
Name of Work:
Name of Tenderer:
SIGNATURE OF TENDERER
Page 67 of 79
(MC-5376)
APPENDIX –II
NAME OF WORK:
NAME OF TENDERER:
Tenderer shall submit herein details of equipment, tools, tackles, etc required to perform the
work and shall note in each case whether the same is (a) already owned by tenderer and
available for use on this contract (b) anticipated to be hired by Contractor or (c) anticipated to be
purchased by Contractor, in case of (a) anticipated (b) and (c) Location of hirer or supplier shall
be stated.
Sl. Description, Make Year of Category (a) or Location Remarks
No. Mode & Capacity Manufacture (b) or (c) below
(1) (2) (3) (4) (5) (6)
2. Contractor agrees to augment the above chart with additional number/ categories of
equipment, if required to complete the work within the agreed time schedule of completion
and directed by the Engineer-in-charge.
3. In case of hiring of equipment form other agencies, copies of the arrangements made with
the hirer/ supplier shall have to be furnished.
SIGNATURE OF TENDERER
Page 68 of 79
(MC-5376)
APPENDIX – III
_____________________________________________________________________________
Sl. No. Details of Manpower No. Remarks
_____________________________________________________________________________
_____________________________________________________________________________
Note : Please furnish the above details in two categories – To be deployed by (I)
Contractor and (ii) Sub- contractors.
Page 69 of 79
(MC-5376)
APPENDIX - IV
_____________________________________________________________________________
Note: Names and short resume of their experiences may also be given for key personnel.
The tentative chart of your site organisation as above furnished by you shall be subject
to variation to suit the construction programme/ requirement and as directed by Owner/
Engineer.
Page 70 of 79
(MC-5376)
APPENDIX – V
LIST OF PROPOSED SUB CONTRACTORS
______________________________________________________________________________
Sl. Name of Description of Amount (Rs.)
No. sub-contractor work or trade
______________________________________________________________________________
______________________________________________________________________________
( Signature of Bidder )
Page 71 of 79
(MC-5376)
APPENDIX – VI
PPROGRESS BILLINGS
Tentative construction schedule indicating the expected dates of start of activity is to be given
by the contractor. This schedule shall be updated within specified milestones from time to time
depending upon the availability of fronts equipment and priorities fixed by Engineer. Contractor
shall submit within 15 days of the date of letter of intent programme/ schedule for supply of
items covering all phases of work including design, procurement, manufacture, assembly,
fabrication, testing, transportation, erection, testing at site and commissioning matching the
overall completion schedule.
(Signature of Bidder)
Page 72 of 79
(MC-5376)
APPENDIX – VII
NAME OF WORK:
NAME OF TENDERER:
INFORMATION ABOUT TENDERERS (FORM – H)
Copies of audited Profit & Loss Account and the Balance sheet shall be enclosed in
case of Individuals, partnerships as well as limited companies for the last 3 years.
( Signature of Tenderer)
Name & Address of the Tenderer
Page 73 of 79
(MC-5376)
APPENDIX – VIII
NAME OF WORK:
NAME OF TENDERER:
The tenderer is required to enclose the following documents as part of his tenderer.
Signature of Tenderer
** In absence of Income Tax Clearance Certificate tenderer may not be awarded the work
tendered for as per Central Govt. Directives.
Page 74 of 79
(MC-5376)
APPENDIX – IX
NAME OF WORK:
NAME OF TENDERER:
As pointed out in the NIT/ LIT, tenderer may stipulate here exceptions and deviations to the
tender conditions, if considered un-avoidable.
______________________________________________________________________________
Sl. Page No. of Sl. No. of Subject Deviation
No. tenderer document tender document
______________________________________________________________________________
_____________________________________________________________________________
SIGNATURE OF TENDERER
Page 75 of 79
(MC-5376)
AMENDMENT TO GCC
02 2.4 Land for Contractor’s Clause No. 2.4 of General Condition of Contract modified to the
Field office, Godown following extend:
and Workshop
“The owner shall provide land to the Contractor for their offices,
go-down and workshop “
03 2.5 Land for Residential Clause No. 2.5 of General Condition of Contract modified to the
Accommodation following extend:
“The land for residential accommodation for staff and labour may
be made available to Contractor outside plant boundary limit.”
04 22 Extension of time The word “any one” appearing in the end of the second para of
Clause No. 22.0 shall be read as “OWNER”.
Page 76 of 79
(MC-5376)
06 53 (xv) Conditions for issue The contents of the sub-clause No.53.(xv) shall stand deleted
of materials and replaced with the following:
“For the free issue materials, the following norms shall be
adopted:
i. For issue of materials within plant boundary wall limit, the
Contractor shall submit only indemnity bond for the entire value
of the materials issued to them free of cost as Clause 53 (ix) of
GCC.
ii. For the materials which are issued to out side plant boundary
like township etc., the Contractor shall furnish Bank Guarantee
equivalent to 20 % of value of materials and indemnity bond for
the 80 % value of the materials.
iii. For materials taken out side Damanjodi/ Angul to the vendor’s
Shop, 100 % Bank Guarantee against value of the materials will
be submitted by the vendor before taking of the materials. The
Indemnity Bond and the Bank Guarantee shall remain valid till
the material account is totally settled.
11 New - Add a new clause designated as Sub clause 80.6 after existing
Sub Cl no. 80.5,
clause
“80.6 – The contractor shall comply with all relevant and
applicable statutory provisions in respect of the workers engaged
by him at his cost and above stipulation are only indicative are
not exhaustive.”
Page 77 of 79
(MC-5376)
12 83 (viii) Labour Laws Clause 83 (viii) of GCC shall be modified to the following extent:
Add the words “all relevant statutes at their own costs including”
between the words “provisions of” and “the payment of Wages
Act 1936” appearing in the first line of this sub-clause.
13 New Jurisdiction / Add a new clause designated as Sub clause 88 (c) after existing
Clause Governing Law Cl no. 88 (b)
All the works that will be carried out inside the factory premises
shall attract the provisions of factory act for the contract
labourers engaged therein.
Page 78 of 79
(MC-5376)
14 79 Taxes & Duties The rates quoted by the tenderer will cover all the taxes, duties,
and levies as applicable on the date of bid/ revised bid (if any).
- In case of any imposition of new taxes by Govt notification at a
later date, same shall be reimbursed to the contractor against
submission of authentic document towards payment of such
taxes by them.
Page 79 of 79