Outperformed Planning Engineer with 5 years of Planning engineering and Project management hands-on experience in construction
industry, including successful exposures to a wide diversified project, with full assurance of delivering leadership excellence in
Engineering and Projects handled roles & responsibilities.
Technical Skills - Summary:
• Decided on the most appropriate engineering techniques and sequences of activities for each project stage.
• Drawing plans; using specialized design software packages.
• Ensured plans meet the client’s specifications.
• Developed estimations for timescales and costs.
• Supervised the project at all stages and providing solutions to problems.
• Collaborated with site managers, surveyors, engineers, site worker and other professionals.
• Organized the transportation of materials.
• Ensured procedures are carried out safely.
Other Skills - Summary:
• Excellent socialized key person, create links between team members, invent bonds and enrich team work environment.
• Able to travel anywhere for extended times and ensure all projects requirements are achieved as planned if not better.
• Train and develop subordinates and colleagues, and effectively delegating tasks to ensure optimum overall performance of the
team and inevitable customers’ satisfaction.
Professional Qualifications and Certifications
B.Sc. computer sciences engineering - 2015 / Graduation Grade: Very Good
Certified MCITP - Microsoft Information Technology Professional.
Professional Experience (Recent to old)
Project manager & Senior Planning engineer Jun 2021 – Present
Gv Group (Development & Construction Company)
Projects & Responsibilities
1. Damietta Governorate public building, Egypt
Responsible for demolition, site mobilization, and organization among government agencies, completing licenses and starting construction of the new
building
2. Entrance to the Suez Canal, Egypt
Responsible for demolition work, site mobilization, organization between government and security agencies, securing the borders of the canal and port,
completing licenses, and starting construction of the new building.
3. Time square, Port said, Egypt
Planning Bas line Program, Cash flow and Updated Until Finishing.
4. Medical waste incinerator, Ismailia, Egypt.
Project manager, mobilization and construction of facilities.
5. Forsan mall, Egypt
Site manager & planning engineer for Developing and raising the efficiency of the building and converting it into a commercial and medical building
2. Senior Planning engineer Nov 2018 – Jan
2020
Ramco trading & contracting, Al-Andalus Schools Project, Qatar
Ramco Group is one of the few privately held, domestic firms with solid financial footing and long-term stable management and ranked as one of the
largest private companies in Qatar with assured diverse mix of clients, markets and services.
Responsibilities
• Oversighted site work activities all civil work (excavation work, concrete & Block works, steel structure and all finishing work).
• Coordinated With MEP work & LPG system
• Supervised selection and delivery of furniture for Class rooms, teacher Rooms and laboratories.
• Administrated progression of work.
• Ensured adequate coordination between multi sub-contractors.
Key Achievements
• Successful delivery of USD 41.3M project for 4 Schools (Primary, Elementary, secondary & Girls) including and not limited to
the following:
Swimming pool.
Administration Building.
Kinder Garten.
Staff Housing.
Separate Kitchen.
Under Ground Services tanks (Fire, Irrigation, and Domestic & Buffer).
External work (Drainage, water supply, fire system, H.V cable, hard land scape and soft land scape).
3. Senior Planning engineer
Feb 2018 – Nov 2018
Ramco trading & contracting, Accommodation complex Project, Qatar
Ramco Group is one of the few privately held, domestic firms with solid financial footing and long-term stable management and ranked as one of the
largest private companies in Qatar with assured diverse mix of clients, markets and services.
Responsibilities
• Ensured adequate coordination between multi sub-contractors.
• Ensured proper reporting to the construction manager on the site requirement.
• Liaised with the Construction Managers to ensure that all labor and plant is available when required and used effectively at all
times.
• Ensured timely management for preparation and monitoring of all construction, installation and commissioning Schedules.
• Analyzed deviation, change of contract scope or delay, if required reschedule to meet target dates in co-ordination with Project
Managers.
• Prepared look ahead schedule, equipment & manpower histogram turnover forecast, as applicable for each contract. Attend all
the progress and coordination meetings with the consultant ant subcontractors.
• Gathered information and design drawings in a timely manner, to suit the construction Schedule for the work Development of
Contract Program with required delivery date of overseas materials in conjunction with Head Office Commercial Mahmoud
Ihab Samir Department and Contracts Manager.
• Monitored the progress of work against the planned schedule/base line schedule.
Key Achievements
• Successful delivery of USD 280K project deliverables including and not limited to the following:
Two club houses
Two swimming pool
Underground service tanks
Infrastructure works (foul water, potable water, firefighting, irrigation)
Landscape works (interlocks, curb stone, green areas)
Four substations building
4. Planning engineer (Part time)
Sep 2015 – Feb 2018
Ramco trading & contracting, MILAHA LOGISTIC CITY Project, Qatar
Ramco Group is one of the few privately held, domestic firms with solid financial footing and long-term stable management and ranked as one of the
largest private companies in Qatar with assured diverse mix of clients, markets and services.
Responsibilities
• Ensured timely management for preparation and monitoring of all construction, installation and commissioning Schedules.
• Analyzed deviation, change of contract scope or delay, if required reschedule to meet target dates in co-ordination with
Project Managers.
• Prepared look ahead schedule, equipment & manpower histogram turnover forecast, as applicable for each contract.
• Participated at all the progress and coordination meetings with the consultant and subcontractors.
• Gathered information and design drawings in a timely manner, to suit the construction Schedule for the work Development of
Contract Program with required delivery date of overseas materials in conjunction with Head Office Commercial Mahmoud
Ihab Samir Department and Contracts Manager.
• Monitored the progress of work against the planned schedule/base line schedule.
Key Achievements
• Successful delivery of USD 110 Million project deliverables including and not limited to the following:
Warehouse with 36000 m2 steel structure elements, cold stored with (-23 D) 8000 m2, Insulated sandwich panel,
special flooring, heater matt.
Refrigeration system with water cooling tower.
Potable water tank, irrigation water tank, grey water tank, firefighting tank,
Service water tank, holding tank, underground fuel tank.
6 substation, Qtel room, 6 gate houses.
Infrastructure works (foul water, surface water, perforated, slot drain, irrigation, potable water, firefighting) pipe
line work.
Roads (flexible pavement and concrete), Krebs, footway and paved area, traffic sings, road marking, CCTV and
street light.
5. Site & Planning engineer
Dec 2015 – Jan 2018
Mountain Hooks for Construction, Qatar
A well reputed Construction Company in Qatar.
Responsibilities
• Managed the preparation and monitoring of all construction, installation and commissioning Schedules
• Obtaining information and design drawings in a timely manner, to suit the construction Schedule for the work
• Produced all necessary reports such as weekly, Monthly Project Report, Cash flow statements, Look ahead program etc.
• Liaised with the Construction Managers to ensure that all labor and plant is available when required and used effectively at all
times.
• Developed Contracts Programs with required delivery date of overseas materials in conjunction with Head Office Commercial
Department and Contracts Manager.
• Monitored and reported the progress of work against the planned schedule/base line schedule.
• Analyzed deviation, change of contract scope or delay, if required reschedule to meet target dates in co-ordination with
Project Managers.
• Prepared look ahead schedule, equipment & manpower histogram turnover forecast, as applicable for each contract.
6. Site Engineer
June 2012 – Dec 2015
Modern Company for trading and construction, Egypt.
The UAE national steel production company (Scope - Air separation, water treatment and fuel gas reduction plants)
Responsibilities
• Maintained a full control and supervising for the work on site.
• Oversighted material procurement and shop drawing submittals.
• Conducted regular inspections with the consultant in site.
• Ensured ultimate coordination with consultants and assured efficient timely progress in light of the agreed project schedule.
Key Achievements
Successful delivery of project deliverables including and not limited to the following:
First Heights Compound at 6 of October city, construction and completion of 80 Vila and 10 Residential buildings
consist of 7 floors
Car parking.
Warrak residential Tower, construction and completion of 20 Floor
Residential tower
Professional Computer Skills:
• MS Office.
• AutoCAD.
• Introduction to C++.
• Visual Basic.
• Oracle Data base system.
• SQL Data base system.
• MCITP - Microsoft Information Technology Professional.
• Primavera 3.
• Primavera 6.
Other Interests: