STRUCTURAL ESTIM INPUT ON GRAY
FOOTING WALL FOOTING COLUMN BEAM
ESTIMATE
INPUT ON GRAY CELLS ONLY
SLAB WALL MATERIALS PRICE LIST
FOOTING EST
FOOTING DETAIL
Concrete Mix Class
Concrete AA Reinfo
FOOTING Quantity
Length Width Thickness Concrete Alon
Depth (m)
(m) (m) (m) Cover (mm) Bar Size
F-1 8.00 1.50 2.00 0.30 70 1.5 16mm Ø
F-2
F-3
F-4
F-5
F-6
F-7
F-8
F-9
F-10
MATERIALS
FOOTING ITEM QUANTITY UNIT
Cement 87 bags
Sand 3.60 cu.m
Gravel 7.20 cu.m
Tie Wire 11.50 kg
F-1 16mm Ø X 12m 23.00 pcs
F-1 12mm Ø X 9m 31.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
Excavation = 37.80 cu.m
Backfill = 30.24 cu.m
EXCAVATION COST =
BACKFILL COST =
ONE-BAGGER MIXER OUTPUT =
TOTAL DAYS (rounded up to 1 day) =
ONE-BAGGER MIXER RENTAL RATE =
ONE-BAGGER MIXER RENTAL COST =
TOTAL COST =
TING ESTIMATE
FOOTING DETAILS
Reinforcement (Rebar Length = Automatic)
Economical Along Length Top Along Width
Economical Top
Bottom Cutting
Bar Length Cutting Length Bar Bar Size Bar Bar
Bar (pcs) Length
(m) 12 1.66 (pcs)10 10 12mm Ø Length (m)
9 2.16 (pcs) 8
- -
- -
- -
- -
- -
- -
- -
- -
- -
ERIALS
PRICE TOTAL COST
₱ 220.00 ₱ 19,140.00
₱ 875.00 ₱ 3,150.00
₱ 1,875.00 ₱ 13,500.00
₱ 95.00 ₱ 1,092.50
#N/A #N/A
#N/A #N/A
MATERIAL COST = #N/A
35% #N/A
₱ 200.00 per cu.m
₱ 125.00 per cu.m
XCAVATION COST = ₱ 7,560.00
BACKFILL COST = ₱ 3,780.00
8.00 cu.m per day
1.00 day
₱1,200.00 per day
XER RENTAL COST = ₱ 1,200.00
TOTAL COST = #N/A
c)
Bottom
Bar
(pcs) 8
WALL FOOTING ESTIM
WALL FOOTING DETAILS
Concrete Mix Class
WALL Concrete B Reinforcement
Quantity
FOOTING Length Width Thickness Concrete
Depth (m)
(m) (m) (m) Cover (mm) Bar Size
WF-1 3.00 10.00 0.75 0.25 40 1 12mm Ø
WF-2
WF-3
WF-4
WF-5
WF-6
WF-7
WF-8
WF-9
WF-10
MATERIALS
FOOTING ITEM QUANTITY UNIT
Cement 45 bags
Sand 2.81 cu.m
Gravel 5.63 cu.m
Tie Wire 2.50 kg
WF-1 12mm Ø X 6m 22.00 pcs
WF-1 10mm Ø X 6m 10.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
Excavation = 23.63 cu.m
Backfill = 17.72 cu.m
EXCAVATION COST =
BACKFILL COST =
ONE-BAGGER MIXER OUTPUT =
TOTAL DAYS (rounded up to 1 day) =
ONE-BAGGER MIXER RENTAL RATE =
ONE-BAGGER MIXER RENTAL COST =
TOTAL COST =
NG ESTIMATE
NG DETAILS
Reinforcement (Rebar Length = Manual)
Economical Along Length Main
Steel Bars Temperature Bars
Bar Length Bars
Length (spacing) (mm)
(m) 6.00 6.00 (pcs) 4 400
-
-
-
-
-
-
-
-
-
ERIALS
PRICE TOTAL COST
₱ 220.00 ₱ 9,900.00
₱ 875.00 ₱ 2,460.94
₱ 1,875.00 ₱ 10,546.88
₱ 95.00 ₱ 237.50
₱ 235.88 ₱ 5,189.37
₱ 165.00 ₱ 1,650.00
AL MATERIAL COST = ₱ 29,984.68
35% ₱ 10,494.64
₱ 200.00 per cu.m
₱ 125.00 per cu.m
EXCAVATION COST = ₱ 4,725.00
BACKFILL COST = ₱ 2,214.84
8.00cu.m per day
1.00day
₱ 1,200.00 per day
IXER RENTAL COST = ₱ 1,200.00
TOTAL COST = ₱ 48,619.16
COLUMN ESTI
COLUMN DETAILS
Concrete Mix Class
Concrete AA Footing
Reinfor
COLUMN Quantity
Concrete Cover Depth if MAIN R
B1 (m) B2 (m) Height (m)
(mm) Ground Bar Size
C-1 4.00 0.40 0.40 4.00 40 Column 1.5 16mm Ø
C-2
C-3
C-4
C-5
C-6
C-7
C-8
C-9
C-10
MATERIALS
COLUMN ITEM QUANTITY UNIT
Cement 31 bags
Sand 1.28 cu.m
Gravel 2.56 cu.m
Tie Wire 7.00 kg
2x3x8 Good Lumber 46.00 pcs
2x2x8 Good Lumber 46.00 pcs
3/4" Phenolic Board 9.00 pcs
Common Nail 2" 6.00 kg
Common Nail 3" 6.00 kg
C-1 16mm Ø X 6m 24.00 pcs
C-1 10mm Ø X 12m 15.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
ONE-BAGGER MIXER OUTPUT =
TOTAL DAYS (rounded up to 1 day) =
ONE-BAGGER MIXER RENTAL RATE =
ONE-BAGGER MIXER RENTAL COST =
TOTAL COST =
C
o
n
c
r
N ESTIMATE e
t
e
V
OLUMN DETAILS o
T
Reinforcement (Rebar Length = Automatic) l
i
u
MAIN e
MAIN REINFORCEMENT
Economical Top LATERAL TIES
Economical m
Steel Bars Bottom Cutting TIES
Bar Length Bar Bar Size Bar e
Length Bar (pcs) Length SPACING W
(m) 6 5.96 (pcs) 3 3 10mm Ø Length (m)
12 1.54 ###
200
(mm) i
- - ### r
- - ### e
- - ###
- - ###
- - ###
- - ###
- - ###
- - ###
- - ###
###
###
IALS Tie Wire
PRICE TOTAL COST Sand
₱ 220.00 ₱ 6,820.00 Gravel
₱ 875.00 ₱ 1,120.00
₱ 1,875.00 ₱ 4,800.00
₱ 95.00 ₱ 665.00
₱ 275.00 ₱ 12,650.00
₱ 210.00 ₱ 9,660.00
₱ 1,200.00 ₱ 10,800.00
₱ 90.00 ₱ 540.00
₱ 90.00 ₱ 540.00
₱ 419.47 ₱ 10,067.32
₱ 328.84 ₱ 4,932.57
MATERIAL COST = ₱ 62,594.89
35% ₱ 21,908.21
8.00 cu.m per day
1.00 day
₱1,200.00 per day
XER RENTAL COST = ₱ 1,200.00
TOTAL COST = ₱ 85,703.11
APPROXIMATE BEA
BEAM DETAILS
Concrete Mix Class
Concrete AA Reinforce
MAIN RE
BEAM Quantity
Concrete Cover Development
B (m) H(m) Length (m)
(mm) Length (m) Bar Size
FTB-1
FTB-2
B-1 1.00 0.30 0.90 8.40 40 0.2 16mm Ø
B-2
B-3
B-4
B-5
RB-1
RB-2
RB-3
MATERIALS
COLUMN ITEM QUANTITY UNIT
Cement 28 bags
Sand 1.13 cu.m
Gravel 2.27 cu.m
Tie Wire 3.50 kg
2x3x8 Good Lumber 54.00 pcs
2x2x8 Good Lumber 54.00 pcs
3/4" Phenolic Board 7.00 pcs
Common Nail 2" 5.00 kg
Common Nail 3" 5.00 kg
B-1 16mm Ø X 6m 5.00 pcs
B-1 10mm Ø X 12m 10.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
SHORING JACK
Area = 2.52 sq.m
Required Qty. = 5.00 pcs
SHORING JACK RENTAL (28 DAYS) =
ONE-BAGGER MIXER OUTPUT =
TOTAL DAYS (rounded up to 1 day) =
ONE-BAGGER MIXER RENTAL RATE =
ONE-BAGGER MIXER RENTAL COST =
TOTAL COST =
ATE BEAM ESTIMATE
BEAM DETAILS
Reinforcement ( Main Rebar Length = Manual)
MAIN REINFORCEMENT STIRRUPS
MAIN
Economical Economical
Steel Bars At At Cutting TIES
Bar Length Bar Size Bar
Length Support Midspan Length SPACING
(m) Length (m)
(mm)
- -
- -
6.00 6.00 4 4 10mm Ø 12 2.34 200
- -
- -
- -
- -
- -
- -
- -
IALS
PRICE TOTAL COST
₱ 220.00 ₱ 6,160.00
₱ 875.00 ₱ 992.25
₱ 1,875.00 ₱ 4,252.50
₱ 95.00 ₱ 332.50
₱ 275.00 ₱ 14,850.00
₱ 210.00 ₱ 11,340.00
₱ 1,200.00 ₱ 8,400.00
₱ 90.00 ₱ 450.00
₱ 90.00 ₱ 450.00
₱ 419.47 ₱ 2,097.36
₱ 328.84 ₱ 3,288.38
MATERIAL COST = ₱ 52,612.99
35% ₱ 18,414.55
JACK
₱ 300.00 per pc. Rental
rate
RENTAL (28 DAYS) = ₱ 1,500.00
8.00cu.m per day
1.00 day
₱1,200.00 per day
XER RENTAL COST = ₱ 1,200.00
TOTAL COST = ₱ 73,727.54
C
o
n
c
r
e
t
e
V
o
Bottom l
Bar u
(pcs) m
e
-
-
-
-
-
-
-
-
-
-
###
###
Tie Wire
###
###
###
###
###
SLAB EST
SLAB DET
Concrete Mix Class
Concrete AA R
SLAB Quantity
Length Width Thickness Concrete Cover Ground or
(m) (m) (m) (mm) Suspended Bar Size
S-1 2.00 3.33 2.49 0.125 20 Suspended 10mm Ø
S-2 2.00 3.33 2.49 0.125 20 Suspended 10mm Ø
S-3
S-4
S-5
S-6
S-7
S-8
S-9
S-10
MATERIALS
FOOTING ITEM QUANTITY UNIT
Cement 50 bags
Sand 2.07 cu.m
Gravel 4.15 cu.m
Tie Wire 6.00 kg
3/4" Phenolic Board 12.00 pcs
2x2x12 Good Lumbe 51.00 pcs
Common Nail 3" 4.00 kg
Common Nail 2" 2.00 kg
S-1 10mm Ø X 10.5m 22.00 pcs
S-1 10mm Ø X 10.5m 13.00 pcs
S-2 10mm Ø X 10.5m 22.00 pcs
S-2 10mm Ø X 10.5m 13.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
SHORING JACK
Area = 33.17 sq.m
Required Qty. = 56.00 pcs
SHORING JACK RENTAL (28 DAYS) =
ONE-BAGGER MIXER OUTPUT =
TOTAL DAYS (rounded up to 1 day) =
ONE-BAGGER MIXER RENTAL RATE =
ONE-BAGGER MIXER RENTAL COST =
TOTAL COST =
AB ESTIMATE
SLAB DETAILS
Reinforcement (Rebar Length = Automatic)
Bottom
Economical Along Length Top Bar Economical Along Width
Bar Cutting
Bar Length Cutting Length (spacing) Bar Size Bar
(spacing) Length
(m) 10.5 3.42 (mm)200 200 10mm Ø Length 10.5
(m) 2.58
(mm)
10.5 3.42 200 200 10mm Ø 10.5 2.58
- -
- -
- -
- -
- -
- -
- -
- -
RIALS
PRICE TOTAL COST
₱ 220.00 ₱ 11,000.00
₱ 875.00 ₱ 1,813.81
₱ 1,875.00 ₱ 7,773.47
₱ 95.00 ₱ 570.00
₱ 1,200.00 ₱ 14,400.00
₱ 320.00 ₱ 16,320.00
₱ 90.00 ₱ 360.00
₱ 90.00 ₱ 180.00
#N/A #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
MATERIAL COST = #N/A
35% #N/A
G JACK
₱ 300.00 per pc. Rental
rate
RENTAL (28 DAYS) = ₱ 16,800.00
8.00cu.m per day
1.00 day
₱1,200.00 per day
XER RENTAL COST = ₱ 1,200.00
TOTAL COST = #N/A
omatic)
Bottom
long Width Top Bar
Bar
(spacing)
(spacing)
(mm)200 200
(mm)
200 200
###
20mm Ø
25mm Ø
28mm Ø
32mm Ø
###
###
Tie Wire
Sand
Gravel
WALL ESTIMATE
WALL DETAILS
Mortar Mix Class
Concrete B
Deductible Reinforcemen
WALL Quantity Areas (ex.
Length Height Plaster Thickness
Thickness Doors &
(m) (m) Sides (1 or 2) Bar Size
Windows)
W-1 3.00 3.00 2.40 _150mm 2 0.85 12mm Ø
(sq.m)
W-2
W-3
W-4
W-5
W-6
W-7
W-8
W-9
W-10
MATERIALS
FOOTING ITEM QUANTITY UNIT
Cement Err:508 bags
Sand 2.90 cu.m
Tie Wire 1.00 kg
100mm CHB - pcs
150mm CHB 270.00 pcs
200mm CHB - pcs
W-1 12mm Ø X 9m 7.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
TOTAL COST =
TIMATE
TAILS
Reinforcement (Rebar Length = Manual)
Vertical
Economical Along Length
Bars Horizontal Bars
Bar Length Steel Bars Length
Spacing Spacing (mm)
(m)9.00 9.00 800 800
(mm)
ERIALS
PRICE TOTAL COST
Err:508 Err:508
₱ 875.00 ₱ 2,540.16
₱ 95.00 ₱ 95.00
₱ 14.00 ₱ -
₱ 18.00 ₱ 4,860.00
₱ 25.00 ₱ -
#N/A #N/A
MATERIAL COST = Err:508
35% Err:508
TOTAL COST = Err:508
Name Price
Cement ₱ 220.00
Sand ₱ 875.00
Gravel ₱ 1,875.00
Tie Wire ₱ 95.00
10mm Ø X 6m ₱ 165.00
10mm Ø X 7.5m ₱ 205.67
10mm Ø X 9m ₱ 247.50
10mm Ø X 10.5m ₱ 288.17
10mm Ø X 12m ₱ 328.84
12mm Ø X 6m ₱ 235.88
12mm Ø X 7.5m ₱ 295.14
12mm Ø X 9m ₱ 354.40
12mm Ø X 10.5m ₱ 413.66
12mm Ø X 12m ₱ 471.76
16mm Ø X 6m ₱ 419.47
16mm Ø X 7.5m ₱ 524.05
16mm Ø X 9m ₱ 628.63
16mm Ø X 10.5m ₱ 733.20
16mm Ø X 12m ₱ 837.78
20mm Ø X 6m ₱ 655.35
20mm Ø X 7.5m ₱ 818.03
20mm Ø X 9m ₱ 981.87
20mm Ø X 10.5m ₱ 1,145.70
20mm Ø X 12m ₱ 1,309.54
25mm Ø X 6m ₱ 1,020.21
25mm Ø X 7.5m ₱ 1,275.85
25mm Ø X 9m ₱ 1,530.32
25mm Ø X 10.5m ₱ 1,785.95
25mm Ø X 12m ₱ 2,040.42
28mm Ø X 6m ₱ 1,280.49
28mm Ø X 7.5m ₱ 1,600.04
28mm Ø X 9m ₱ 1,919.58
28mm Ø X 10.5m ₱ 2,240.28
28mm Ø X 12m ₱ 2,559.82
32mm Ø X 6m ₱ 1,672.08
32mm Ø X 7.5m ₱ 2,090.39
32mm Ø X 9m ₱ 2,508.70
32mm Ø X 10.5m ₱ 2,925.85
32mm Ø X 12m ₱ 3,344.15
One-Bagger Mixer ₱ 1,200.00
100mm CHB ₱ 14.00
150mm CHB ₱ 18.00
200mm CHB ₱ 25.00
2x3x8 Good Lumber ₱ 275.00
2x2x8 Good Lumber ₱ 210.00
2x2x12 Good Lumber ₱ 320.00
3/4" Phenolic Board ₱ 1,200.00
Common Nail 2" ₱ 90.00
Common Nail 3" ₱ 90.00