Draft Design Report Road Material Analysis
Draft Design Report Road Material Analysis
EXECUTIVE SUMMARY
This report gives account of the final report of the geotechnical investigations that was carried
out to determine the characteristics of the soil for the foundation design of the proposed
administration block, road infrastructure, parking lots and selection of suitable material geologic
origin for the Centre for Innovation and Engineering Excellence at the Kwame Nkrumah
University of Science and Technology.
Desk study was carried out to obtain data that aided in the reconnaissance survey which was
carried out immediately after the desk study. The data obtained from the desk study were the
geology and the seismicity of the site. Geologically of the site location, KNUST is located within
the Birrimian metasediments made up mainly of phyllites and greywacke. The proposed site had
a Horizontal Ground Acceleration (HGA) of 0.15g.
The locals of the area thus the farmers were consulted during the reconnaissance survey for the
nature of the site this was followed by sub-surface exploration. Also from the reconnaissance
survey the topography of the land sloped gently.
Sub-surface investigations consisting of excavation of test pits, percussion drilling, SPT and
Dynamic Cone Penetration Test (DCPT). There were 5 test pits dug (3 along the centre line of
the proposed road network 1 each for the internal road network and parking lot). The DCPT were
carried along the centre line of proposed road network (5) internal road network (7) and the
parking lots (5) to determine the in-situ CBR. The percussion drilling was performed at the
administration block. The drilling was done in accordance with the BS 5930 to obtain the
disturbed samples for the laboratory test and also visual inspection of the soil strata. SPT were
performed in the borehole to extract information about strength of the soil.
Laboratory test on samples collected indicated that the subsoil material at the site is
predominantly were silt and sand with clay and traces of gravel. The PI-chart also showed that
the fine portions of the subsoil material at the administration area highly plastic silt (MH). The
proposed road corridor was made up of soil samples that were A-2-6(0)/A-2-7(0) generally
excellent to good. The internal road network and the parking lot were fair to poor thus A-7-6.
Page i
An allowable settlement of 25mm was used (Ghana Building Code). Groundwater is expected
not have effect on the foundation since groundwater was not encountered. An allowable bearing
capacity of 328.34kN/m2 was obtained for the footing size of 1m x 1m to be placed at a depth of
1.5m.
The in-situ CBR obtained is 19% since it is a medium road we use the 75th percentile and 18%
for the laboratory CBR along the proposed road network. The internal road network had CBR of
14%. For the parking lot a CBR value of 22%.
The borrow material from Kwaso most of the test qualifies that the material may be used as base
material whilst the borrow material from Piase may also be used as sub-base material since most
of the test satisfy the GHA specification. Stabilizer of cement or lime or quarry dust may be
added to the material in an appropriate proportion of mix so as to improve on the quality of the
materials.
Most of the test performed on the quarry material did not pass for the intended purpose so it will
advisable to source for a much better material.
No drainage problems are expected and that simple drains appropriately designed will be able to
manage the surface runoff.
Page ii
Contents
Page iii
LIST OF FIGURES
FIGURE 1: Picture showing Site configuration .......................................................................................... 3
FIGURE 2: Geological Map of Ghana ........................................................................................................ 5
FIGURE 3: Geological map and the legends ............................................................................................... 6
FIGURE 4: Seismic risk map of Ghana (Amonoo-neizer, 1990) ................................................................ 7
FIGURE 5: Flow Chart showing sequence of work .................................................................................... 8
FIGURE 6: Picture Showing farming activities at the site ........................................................................ 10
FIGURE 7: Aerial map indicating points considered for investigation ....................................................... 5
FIGURE 8: Percussion drilling ........................................................................................................................................... 12
FIGURE 9: SPT .......................................................................................................................................... 12
FIGURE 10: Trial Pitting ........................................................................................................................... 13
FIGURE 11: Carrying out the DCPT ......................................................................................................... 13
FIGURE 12: Graph of Qallowable (kPa) against Width of footing ........................................................... 23
FIGURE 13: DCPT ranked values CBR against CBR (%)........................................................................ 23
Page iv
LIST OF TABLES
TABLE 1: Assigned Horizontal Ground Acceleration ................................................................................ 7
TABLE 2: Summary of Laboratory Result for Administration Block ...................................................... 16
TABLE 3: Summary of Laboratory Result for the road network ............................................................... 18
TABLE 4: Factors for allowable bearing capacity .................................................................................... 18
TABLE 5: Allowable bearing capacity (kPa) and Corresponding Width (m) ............................................ 18
TABLE 6: Summary of the Compaction and CBR results ........................................................................ 20
TABLE 7: Summary of CBR Ranking for Pavement Design of Parking Areas and Road Network ........ 21
TABLE 8: Dimension of Pavement and Volume of Material Required .................................................... 23
TABLE 9: Dimension of Pavement and Volume of Material Required .................................................... 23
TABLE 10: Summary of Laboratory Results on Borrow Material ............................................................ 24
TABLE 11: Summary of Laboratory Test of Quarry Material .................................................................. 25
TABLE 12: Summary Sieve Analysis of Quarry Material ......................................................................... 26
TABLE 13: Chemical tests on Aggregate and the charges ........................................................................ 26
Page v
ABBREVIATION NAME
AASHTO American Association of State Highway
and Transport Officials
Page vi
1.0 INTRODUCTION
1.1 Background
The College of Engineering of the Kwame Nkrumah University of Science and Technology, the
largest public university established in Ghana for the training of engineers, medical personnel,
scientists and technologists, is to establish a Centre for Innovation and Engineering Excellence to
promote the Development of innovation and research.
The Centre will be a science and technology park that will link academia to industry. Various
innovative and research products would be displayed for industry to view. It would also develop
a links between the researchers and businesses that would be interested in the product.
The College of Engineering has therefore commissioned an Architectural Firm to undertake the
general planning and the design of the architectural aspects of the Centre. Preliminary planning
and designs of the various facilities for the hospital have been completed and approved by the
Client. It is now required to undertake the engineering design aspects of the proposed Centre.
The Client has therefore commissioned us, 8M/S EDCIV 2016/17 Civil Group 169 design team to
undertake a review of the preliminary layout proposed by the previous consultant and also carry
out a detailed engineering design of the Infrastructure facilities for the proposed project.
For the design of the infrastructure, road pavement and parking facility a geotechnical
investigation would be carried out at the site to confirm and make appropriate recommendations
in the design report to help for the safe and economic design of the infrastructural facilities.
vi. Assess Traffic impacts, especially at the main entrance from the network of roads around the
development.
vii. Assess the cost of Environmental Management Plan.
The proposed site is located at KNUST, between the college if engineering and the new college of arts
building. The distance is approximately 1km-2km from college of engineering when using the only access
route.
2.2 Topography
The site had been cleared of the moist semi-deciduous forest and overgrown by grass and isolated trees.
The soils per our observations were dark and loamy which is good for farming. Existing structures
includes New College of Art and Social Sciences Block. The site sloped gently.
The area has a good drainage. There is the Bibini stream runs through the southern part of the site and the
local farmers use as irrigation.
The project area lies within the wet semi-equatorial climatic zone which is characterized by high rainfall
and high humidity occurring between the months of July and October. There are two rainfall maxima, but
the mean annual rainfall is between 125cm and 200cm. The first rainy season is from May to June with
the heaviest rainfall in June, and the second rainy season is from September to October. The vegetation in
the wet semi-equatorial climatic zone is classified as moist deciduous forest. (Dickson & Benneh 1980)
Geological formation which is underlying Kumasi metropolis, within which the project site falls consists
of rocks, which belong to the early Proterozoic Birimian System.
The rocks are metasediments and felsic granitoids. Metasediments cover about 45% of the metropolis and
consist mainly of phyllites, metagreywackes and schists. Structurally, the rocks are folded and they
generally strike and dip to northeast and southeast respectively with the amount of dip varying from 35 o
to 89o. The granitoids are variably textured with muscovite and biotite-rich micas. They occur as large
batholiths, which are cut by pegmatite, quartz veins and minor intrusives (amphibolites and dolerites),
(Murray, 1961).
2.5 Seismicity
A study of the seismic risk map of Ghana, shown in Figure 4 was done to determine the risk to
the infrastructures due to seismic activities. This study showed that the area has Horizontal
Ground Acceleration (HGA) of 0.15g. Thus, no serious seismic activity is anticipated at the site.
However, seismic response may be considered in the design process.
Zone 0 1 2 3
Horizonta
l ground
0 0.15 0.25 0.35
accelerati
on (g)
3.0 METHODOLOGY
For the design of any project it is very necessary for the team of consultants to adopt methods in
order to achieve the objectives of the project. The methodologies must be appropriate, safe and
economic. These methodologies are desk study, reconnaissance study, and field work
(excavation, in-situ test and sampling). The site investigation will be done in accordance to the
Code of Practice for Site Investigations, BS 5930 and 1377: 1990. The flowchart below gives the
sequence for the investigation approach:
Site Investigation
Laboratory Test
Report
We carry out a desk study which is the first stage to identify the geotechnical and/or geo-
environmental characteristics of the ground in sufficient detail to enable economic design to help
minimize the risk of unforeseen ground conditions which can cause increased costs and/or
schedule delays.
A desk study was undertaken to obtain information on the site. The study consisted of an
overview of the topography, geology, climate and vegetation, accessibility, seismicity, historical
records, especially in relation to floods, landslides and subsidence and also engineering records
and reports on any major works in the vicinity of the site. All this aided us to the selection of
boring method to use and other field test we will be conducted on the site
On 17th September, 2016, between the hours of 15:00-17:00 GMT, the team carried out a
reconnaissance survey for us to confirm the desk study information that will aid us in planning
field work.
The proposed site is located at Kwame Nkrumah University of Science and Technology between
the College of Engineering and the College of Arts building along the Ayeduase fence wall.
From the college of engineering to the proposed site a 5minutes walk-time. There was no
construction activity going on at the proposed site. The ground was floored with sandy-loam soil
material, overgrown grass and isolated trees. There were farming activities at the location. I had
an interaction with the farmers on the site to gain knowledge about the nature of the land.
Shallow dug out wells were observed which indicated that the water table was just shallow deep
from the land surface. There was no history of floods from the locals. The land slopped gently.
The College of Arts building which is closed to the proposed site was checked for cracks and any
undesirable defects.
I accessed the proposed road infrastructure. The proposed road from the Petroleum Building at
the college of engineering to the proposed passed through the Bibini stream and a densly marshy
area. There is a need to weed or clear the area for me to carry out the necessarily geotechnical
investigation.
After the desk study and reconnaissance survey the team had a meeting and the discussed the
various design that was going to be carried out at the proposed site and how the geotechnical
investigation is going to be relevant to their design. Consultation with the structural engineer we
identified the critical columns of the administration block and in case needs be water storage
tank. With that information I concluded that the critical columns and the just a column of the
water tank are the points on the layout that I will consider and conduct my geotechnical
investigation. Also consultation from the highway engineer we identified points on the proposed
route and parking area where I will carry out relevant geotechnical investigation.
Geotechnical engineers from each group went to the site to identify the exact locations that our
investigations will be carried out. A tape measure and the site layout were used for this exercise.
There was an existing landmark at the proposed site that was used as a reference point in the
determination of the exact area using trigonometry.
The following are the field test that was carried out in accordance with the BS 5930-1990;
Administration Block
I. Percussion drilling
II. Standard Penetration Test
Figure 10: Trial Pitting Figure 11: Carrying out the DCPT
The liquid limit is the boundary water content between the plastic and liquid states. The plastic
limit is the moisture content that defines where the soil changes from a semi-solid state to a
plastic state.Plasticity Index is the range of water content over which a soil behaves in a plastic
state. It is the difference between the liquid limit and the plastic state.
This is a test which be done to improve the density of the soil by adding water and reducing the
air volume in the soil.
V. Specific Gravity(Glass Jar)
The specific gravity of a soil is used in the phase relationship of air, water and solids in a given
volume of the soil. Specific gravity is the ratio of the mass of unit volume of soil at a stated
temperature to the mass of the same volume of gas-free distilled water at a stated temperature.
This is a test conducted for evaluating the suitability of subgrade and other materials used in sub-
base and base of a flexible pavement.
1.0-2.0 25.07 2.17 53.0 31.0 22 37.0 31.0 29.0 3.0 Highly plastic Clay.
2.0-3.0 18.79 2.18 52.0 31.0 21 25.0 34.0 32.0 9.0 Highly plastic Silt.
4.0-5.0 20.35 2.15 56.0 34.0 22 12.0 47.0 39.0 2.0 Highly Plastic Silt..
7.0-8.0 22.89 2.15 59.0 33.0 26 4.0 38.0 57.0 1.0 Silty Sand.
9.0- 26.36 2.25 59.0 40 19 8.0 41.0 48.0 3.0 Silty Sand..
10.0
Table 3: Summary of Laboratory Result for the Subgrade material along the road network and the parking lot
excellent to
TRIALPIT 1 1 0.6 - 1.00 18.74 20.42 75.58 4 18 NP 18 A-2-6(0)
good
excellent to
TRIALPIT2 1 0.29- 1.00 27.18 14.7 73.27 12.03 17 NP 17 A-2-6(0)
good
excellent to
TRIAL PIT 3 1 0.20 - 1.00 24.5 35 63 2 48.66 24.5 24.16 A-2-7(3)
good
TRIAL PIT 4 1 0.18 - 1 31.73 48.28 51.01 0.71 51 21.57 29 A-7-6(10) fair to poor
TRIALPIT 5 1 0.10-1.00 18.24 37 49.68 13.32 58 29.1 28.47 A-7-6(6) fair to poor
( )
Factor F1 F2 F3 F4
Value 0.04 0.06 0.30 1.20
From the computation, using the equation the allowable bearing capacity was obtained as
328.34kN/m2
Table 5: Allowable bearing capacity (kPa) and Corresponding Width (m)
BEARING CAPACITY
Qallowable (kPa) Width (m)
328.34 1.00
328.34 1.20
322.76 1.40
289.38 1.60
248.28 1.80
217.12 2.00
192.73 2.20
173.15 2.40
164.75 2.50
The values obtained here were supported with what was obtained in the laboratory test to come
out with the CBR value to be used by the highway engineer for the structural design of the
pavement and parking areas. See results in Appendix B.
( )
The percentage of swell was also determined measuring the change in height to the original
height of soil and multiplying by 100%. The swell gives indication of how the soil displaces
when it has been flooded.
Table 7: Summary of CBR Ranking for Pavement Design of Parking Areas and
Road Network
2 2 45 118.42
4 1 43 113.16
5 1 42 110.53
6 1 41 107.89
7 2 40 105.26
8 1 38 100.00
9 2 37 97.37
10 1 35 92.11
11 1 34 89.47
14 3 33 86.84
17 2 30 78.95
19 2 28 73.68
20 1 26 68.42
21 1 25 65.79
24 3 24 63.16
29 1 21 55.26
31 1 20 52.63
39 1 19 50.00
40 1 18 4.7.37
41 1 178 44.74
45 2 16 42.11
52 1 14 36.84
54 3 13 34.21
64 1 10 26.32
82 1 9 23.68
111 1 8 21.05
∑f = 38
350
300
200
150 Qallowable
100
50
0
0 0.5 1 1.5 2 2.5 3
Width (m)
120.00%
100.00%
Ranked CBR
80.00%
60.00%
40.00%
20.00%
0.00%
0 20 40 60 80 100 120
% of CBR values ≥ ranked value (percentile)
The strength of any soil is affected by certain parameter such as the moisture content, particle
size distribution, consistency limits (liquid limit, plastic limit and plastic index) and density.
Pavement design of any road, we determine the strength of the soil by using the California
Bearing Ratio (CBR) test. In order to provide the necessary information about the sources and
quality of borrow pit materials of geologic origin for the sub-base and base construction.
This lead to a search in the environs of the project area by considering proximity that is
reasonable to reduce haul during construction of the road networks. We considered two borrow
pits and they are the Kwaso and Piase Borrow pits which we visited and samples taken to
determine their suitability. Unfortunately due time constraints we could not perform the test so
data obtained from M/S EDCIV 2015/16 were used to check the suitability of the borrow pit
material which were compared with the Ghana Highway Authority (GHA) specification. From
the data the Kwaso borrow material qualified used as a base material and that of the Piase
material also qualified as a subbase material. Below are tables which gives the summary the
dimension of pavement and its required volume material required and table 11 gives us the test
conducted on the borrow materials.
Piase 35 6 - 100 92.3 91.1 73.5 45.8 23.4 11.4 8.2 2.10 11 34.1 23 20 68.5 2.57 0.43
borrowed
pit
Kwaso 23.48 7.98 - 100 100 85.3 63.8 41.0 23.9 12.6 8.03 2.21 12 107 97 73 100.5 2.55
borrowed
pit
Specification for
14mm Nominal
size(MRT, 2006)
SEIVE SIZE(mm) Percentage passing
37.5 100 100
20 100 100
14 91 95-100
10 48 0-20
5 15 -
2.36 0 -
It should be noted that if the aggregate are to be used for concreting (columns, beams, slabs) for
the construction of the Administration Block, the following test are to performed on the
aggregate together with the sand so as to prevent the chemicals from reacting with cement
1.30 Chlorides
1.50 pH
From the analyses, the following conclusions have been arrived at:
I. The soil type at the site is residual soil derived from the weathering of the underlying
phyllites. The predominant soil at the site is silt and sand with significant amount of clay and
some gravel mostly found on the surface.
II. Groundwater was encountered along the proposed road corridor at the TP2 at depth 0.6m from
the ground surface the time of the investigation.
III. The allowable bearing capacities as determine by the SPT, since shear strength parameters
could not be extracted by using the triaxial test at depths 1.5m was 328.34kPa.
IV. An allowable settlement of 25mm was used ato compute the allowable bearing capacity.
V. The subgrade material classified as A-2 and A-7 along the road corridor and internal road
networks respectively by the AASHTO classification system. Along the proposed road
corridor quality were good and that of the internal road network poor. So for the materials on
the internal road network soil improvement is required.
VI. The borrow material from Kwaso most of the test qualifies the material to be used as base
material since it satisfy the specification of G60 whilst the borrow material from Piase may
also be used as sub-base material since most of the test satisfy the GHA specification of G40.
Stabilizer of cement or lime or quarry dust may be added to the material in an appropriate
proportion of mix so as to improve on the quality of the materials.
VII. Crushed rock aggregate test results obtained were found to be acceptable per the MRT
specification for use of crushed rock aggregate as base course.
III. Drainage problems are not expected and that simple drains appropriately designed will be able
to manage the surface runoff.
IV. Since the subgrade material for the internal road network is of poor quality, it is advised that
initial conditioning of the subgrade (such as compaction) should be done prior to the
placement of other layers to improve it strength.
V. Routine test on the aggregate from the quarry site should be conducted to ensure it conformity
with the MRT specification.
VI. The relative compaction that should be achieved is 95% from the lab.
nr 11 70..00 770.00
B712 Atterberg limits
7.1 Introduction
Environmental impact assessment involves the process of assessing the project and identifying,
predicting, evaluating and mitigating the positive or negative effects it has on the environment,
society and the economy. This report, therefore, gives account on the possible positive and
negative impacts of the project during the geotechnical site investigation and also to provide a
remedy of the impacts.
7.2 Scope
The Environmental Protection Agency that the Environmental Impact Assessment (EIA) under
the Environmental Protection Agency Act, 1994 Act 490, be provided before any construction is
undertaken. The following are the processes that will be gone through.
5. Ensure that the mitigation measures are implemented by developing a monitoring Programme.
Under this, data collected from the site is recorded. The data should include the species that will
be endangered and they comprise plants and animals. The effects of site investigation on them
will be studied. From the baseline studies the investigations that will be carried will affect the
vegetation of the proposed site since the site is to be cleared before carrying out any field test.
During drilling of the borehole it will cause noise pollution. Trial pits that will be dug will affect
the farmers because their farmlands are situated exactly along the proposed road network.
1. The project will serve as a source of employment to people in the nearby community.
1. Destruction of the habitats of living organisms. Also some organisms living in the soil may
lose their lives.
2. Air pollution which results from dust particles emitted during the digging of trial pits.
Inhalation of dust can go a long way to cause respiratory diseases.
3. Water may be retained in dug pits and this serves as a breeding site for harmful organisms
like mosquitoes (vector of malaria) and snakes which pose danger to humans.
4. Land pollution: Deforestation due to the removal of trees and shrubs during field
explorations. Removal of surface vegetation leads to erosion.
1. Dug holes should be filled immediately after tests have been carried out.
3. Operators of mechanical equipment should wear safety clothing like safety boots, coats and
ear plugs.
4. Temporary drains should be created to direct unwanted water in order to prevent the retention
of water.
7.7 Conclusion
All the possible positive and negative impacts of the project, in relation to site investigation have
been analysed and it can be guaranteed that mitigation measures will be strictly adhered to
ensure safe execution of the project.
REFERENCES
Amonoo-Neizer, K. (1990), Building and Road Research Institute. Code of practice: Seismic
Design of Concrete Structures
British Standards Institution (1990) BS1377: Methods of Test for Soil for Civil Engineering
Analysis and Modeling Vol. 1.
Dickson, K. B. and Benneh, G. A. (2004), A New Geography of Ghana. Revised Edition. Longman
Group UK Limited. 170pp
Kesse, G.O. (1985),The Mineral and Rock Resources of Ghana.A. A.Balkema, Rotterdam, The
Netherlands, 610pp
Terzaghi, Karl (1843), Theoretical Soil Mechanics. New York: John Wiley and Sons Inc.
Tomlinson, M.J. (1990): Foundation Design and Construction, 6th Edition: Longman ELBS.
Murray R. J., 1961: The Geology and Economic Resource of the Kumasi Area Gold Coast
Geological Survey bulletin No.26
Bowles, J.E (1977), Foundation Analysis and Design 5th Edition.
APPENDICES
200
Penetration(mm)
400 Layer 1
Layer 2
600
y = 28.809x + 119.85
800
1000
1200
DCPT 1
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 200 64.286 3.705279
2 800 28.809 8.655232
200
Penetration(mm)
400
Layer 1
600
800
1000
1200
DCPT 2
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 1000 100 2.322737
200
y = 29.293x + 44.949
PENETRATION(mm)
400 Layer 1
Layer 2
600
800
1200
DCPT 3
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 400 29.293 8.504144
2 600 6.0725 44.87253
Cumulative No of Blows
0 20 40 60 80 100
0
y = 127.27x + 54.545
200
Layer 1
y = 17.742x + 275.81
Penetration/mm
400 Layer 2
Layer 3
600
y = 5.3009x + 425.07 Layer 4
800
1200
DCPT 4
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 300 127.270 1.800133
2 200 17.7420 14.44789
3 200 5.3009 51.80390
4 300 11.160 23.58408
Cumulative No of Blows
0 10 20 30 40 50
0
y = 46.154x + 23.077
200
Layer 1
Penetration (mm)
400
y = 18.443x + 127.05
8 Layer 2
600 Layer 3
800
1000 y = 25x - 25
1200
DCPT 5
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 200 32.143 5.259334
2 400 18.443 13.86807
3 400 25.000 10.05489
Cumulative No of Blows
0 20 40 60 80 100 120
0
y = 100x
200
Layer 1
Penetration (mm)
400
Layer 2
600 Layer 3
800
1200
DCPT 6
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 100 100.0000 2.322737
2 600 6.9681 38.79968
3 300 12.7040 20.56529
Cumulative No of Blows
0 50 100 150 200 250 300
0
y = 4.2514x + 10.721
200
Layer 1
Penetration (mm)
400
Layer 2
y = 6.6769x - 124.22
600 Layer 3
1000
1200
DCPT 7
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 200 4.2514 65.40963
2 500 6.6769 40.5905
3 300 2.5757 111.0922
Cumulative No of Blows
0 50 100 150 200
0
200
Penetration (mm)
400
Layer 1
600 y = 6.0903x + 5.5787
800
1000
1200
DCPT 8
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 1000 6.0903 44.73392
Cumulative No of Blows
0 20 40 60 80 100 120
0
200
Penetration (mm)
400
Layer 1
600 y = 10.283x + 5.4816
800
1000
1200
DCPT 9
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 1000 10.283 25.71517
Cumulative No of Blows
0 20 40 60 80 100 120 140
0
y = 4.3478x
200 Layer 1
y = 9.325x - 119.63
Penetration (mm)
400 Layer 2
Layer 3
600
Layer 4
800
y = 12.969x - 699.83
1000
1200
DCPT 10
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 100 4.3478 63.87767
2 400 9.325 28.51551
3 200 5.0737 54.25899
4 300 12.969 20.12138
Cumulative No of Blows
0 50 100 150 200 250
0
y = 2.6708x - 5.0529
200
Penetration (mm)
400 Layer 1
Layer 2
600
y = 5.0798x - 173.26
800
1000
1200
DCPT 12
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 200 2.6708 106.9154
2 800 5.0798q 54.19012
Cumulative No of Blows
0 50 100 150 200 250 300
0
400 Layer 1
Layer 2
600
800
1200
DCPT 13
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 500 3.1013 91.29316
2 500 5.1396 53.52389
Cumulative No of Blows
0 10 20 30 40 50 60
0
y = 39.474x + 7.8947
200
Penetration (mm)
400 Layer 1
Layer 2
600 y = 15.139x + 171.07
800
1000
1200
DCPT 14
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 200 39.474 6.204391
2 500 15.139 17.08588
Cumulative No of Blows
0 10 20 30 40 50 60 70
0
y = 64.286x + 14.286
200
Penetration (mm)
400 Layer 1
800
1000
1200
DCPT 15
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 200 64.286 3.705279
2 800 13.143 19.83992
Cumulative No of Blows
0 10 20 30 40 50 60 70
0
200
y = 33.333x
Layer 1
Penetration (mm)
400
Layer 2
600 Layer 3
y = 18.132x + 276.92
800
1200
DCPT 16
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 600 33.333 7.41859661
2 200 18.132 14.11961595
3 200 6.8289 39.6361309
Cumulative no of Blows
0 5 10 15 20 25 30 35
0
y = 150x + 50
200
Layer 1
Penetration (mm)
400
Layer 2
600 Layer 3
y = 32.053x + 188.63
800
1200
DCPT 17
D-
SOIL LAYER THICKNESS(mm) VALUE CBR
1 200 150.000 1.513113615
2 600 32.053 7.732088238
3 200 15.116 17.11335717
Appendix-C-Laboratory Graphs
BH1-0.1-1m
Grading Curve BH1 (0.1 - 1m) CLAY-46%
SILT-22%
100.00
SAND-30%
90.00
GRAVEL-2%
Percentage Passing (%)
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.00 0.01 0.10 1.00 10.00 100.00
Particle Size (mm)
BH1-1-2m
Grading Curve BH1 (1 - 2m) CLAY-37%
100.00
SILT-31%
SAND-29%
90.00
GRAVEL-3%
Percentage Passing (%)
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.00 0.01 0.10 1.00 10.00 100.00
Particle Size (mm)
BH1-2-3m
Grading Curve BH1 (2 - 3m) CLAY-25%
SILT-34%
100.00
SAND-32%
90.00
GRAVEL-9%
BH1-4m-5m
Grading Curve BH1 (4 - 5m) CLAY-12%
SILT-47%
100.00
SAND-39%
90.00 GRAVEL-2%
Percentage Passing (%)
80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.00 0.01 0.10 1.00 10.00 100.00
Particle Size (mm)
BH1-7-8m
Grading Curve BH1 (7 - 8m) FINES-4%
SILT-38%
100.00
SAND-57%
GRAVEL-1%
Percentage Passing (%)
80.00
60.00
40.00
20.00
0.00
0.00 0.01 0.10 1.00 10.00 100.00
Particle Size (mm)
BH1-9-10m
Grading Curve BH1 (9 - 10m) CLAY-8%
SILT-41%
100.00
SAND-48%
90.00 GRAVEL-5%
80.00
Percentage Passing (%)
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.00 0.01 0.10 1.00 10.00 100.00
Particle Size (mm)
TP1-0.6-1.0m
Grading Curve (TP1) FINES-21%
100.00 SAND-75%
GRAVEL-4%
90.00
80.00
Percentage Passing(%)
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.010 0.100 1.000 10.000
Sieve Size(mm)
TP1-0.2-0.6m
Grading Curve (TP2) FINES-15%
100.00 SAND-73%
GRAVEL-12%
90.00
80.00
Percentage Passing(%)
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.01 0.1 1 10 100
Sieve Size(mm)
TP3-0.2-1m
Grading Curve (TP3) FINES-35%
100.00 SAND-63%
GRAVEL-2%
90.00
80.00
Percentage Passing(%)
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.01 0.1 1 10 100
Sieve Size(mm)
TP4-0.18-1m
Grading Curve (TP4) FINES-48%
100.00 SAND-51%
GRAVEL-1%
90.00
80.00
Percentage Passing(%)
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.01 0.1 1 10 100
Sieve Size(mm)
TP5-0.1-1m
Grading Curve (TP5) FINES-37%
100.00 SAND-50%
GRAVEL-13%
90.00
Percentage Passing(%) 80.00
70.00
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.01 0.1 1 10 100
Sieve Size(mm)
COMPACTION CURVE
1.700
TP5
1.680
1.660
Dry Density, g/cm3
1.640
1.620
1.600
Series1
1.580
1.560
1.540
1.520
0.00 5.00 10.00 15.00 20.00 25.00
Moisture Content, (%)
COMPACTION CURVE
2.150
TP1
2.100
2.050
Dry Density, g/cm3
2.000
1.950 Series1
1.900
1.850
1.800
0.00 2.00 4.00 6.00 8.00 10.00
Moisture Content, (%)
COMPACTION CURVE
2.000
TP3
1.950
Dry Density, g/cm3
1.900
1.850 Series1
1.800
1.750
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00
Moisture Content, (%)
COMPACTION CURVE
2.000
TP4
1.950
1.900
Dry Density, g/cm3
1.850
1.800 Series1
1.750
1.700
1.650
0.00 5.00 10.00 15.00 20.00
Moisture Content, (%)
COMPACTION CURVE
2.08
TP2
2.06
2.04
Dry Density(g/cm3)
2.02
1.98
1.96
1.94
0 2 4 6 8 10 12 14
Moisture Content(%)
8m)
CI BH1(9m-
30 10m)
20 C - Clay
M - Silt
L - Low
Plasticity
C I -
Intermedia
10 te
MI SILT Plasticity
M H - High
Plasticity
V - Very
0
High
0 10 20 30 40 50 60 70 80 90 100
Plasticity
Liquid limit, % E-
Extremely
High
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
PenetratIon (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
80.00
70.00
Moisture Content, %
60.00
50.00
40.00
30.00
20.00
10.00
0.00
1.00 10.00 100.00
Penetration (mm)
7.00
TP1CBR CURVE
6.00
5.00
4.00
LOAD (kN)
3.00 CBR
2.00
1.00
0.00
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000
PENETRATION (mm)
30
TP2 CBR CURVE
25
20
LOAD (kN)
15
CBR
10
0
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000
PENETRATION (mm)
10
TP3 CBR CURVE
9
6
LOAD (kN)
4 CBR
0
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000
PENETRATION (mm)
4.00
TP4 CBR CURVE
3.50
3.00
2.50
LOAD (kN)
2.00
CBR
1.50
1.00
0.50
0.00
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000
PENETRATION (mm)
6
TP5 CBR CURVE
4
LOAD (kN)
3
CBR
0
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000
PENETRATION (mm)
90
80
PERCENTAGE PASSING(%)
70
60
50
40
30
20
10
0
0.001 0.01 0.1 1 10 100
SIEVE SIZE(mm)
1.500
1.000
0.500
0.000
0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00
OMC(%)
2.000
MDD(g/cm3)
1.500
1.000
0.500
0.000
0.00 5.00 10.00 15.00 20.00
OMC(%)
7.00 MDD 97
6.00
5.00
LOAD (KN)
55 BLOWS
4.00
25 BLOWS
3.00
10 BLOWS
2.00
1.00
0.00
0 2 4
PENETRATION(mm) 6 8
20
15
10 blows/ layer
25 blows/ layer
10 56 blows/ layer
0
0 1 2 PENETRATION(MM)
3 4 5 6
20.00
15.00
10.00
5.00
0.00
92 93 94 95 96 97 98
Relative dry density
120
100
80
CBR
60
40
20
0
85 87 89 91 93 95 97
Relative compaction
DISCLAIMER
This report contains the geotechnical investigation that was carried out for the project Center for
Innovation and Engineering Excellence. It solely represents the interpretation of the sub-soil
condition derived from the field work and should not be used for any other project.
lkl