p3m3 Maturity Model Self Assessment
p3m3 Maturity Model Self Assessment
0 Self Assessment
Contents Page
Introduction 4
User Guidance 6
P3M3 Self-Assessment Guidance 10
P3M3 Model Answers 28
Next Steps 32
Introduction
4 Self-Assessment
P3M3™ (Portfolio, Programme and Project Management Maturity Model) is an
overarching model containing three individual models:
Each model uses a five level process capability framework which may be used to gauge
the overall organizational maturity. The descriptions and characteristics of the five
Maturity Levels apply equally to each of the three sub-models.
P3M3 focuses on seven Process Perspectives, which exist in all three models and can
be assessed against five levels of capability. The flexibility of P3M3 allows organizations
to review all seven Process Perspectives across all three models – portfolio, programme
and project management – but they can also review just one (or several) of the Process
Perspectives, whether across all three models or across only one or two of them. This can
be useful to gain a better understanding of an organization’s overall effectiveness in, for
example, risk management or resource management.
An organization may choose to view how mature it is against any or all of the sub-models,
or may wish to gauge their process capability, e.g. at organizational governance across
portfolio, programme or project management.
This self-assessment tool should be read in conjunction with the P3M3 version 2 standard
itself and the OGC Glossary of terms. These can be found at:
Self assessment at www.p3m3-officialsite.com
It should of course be recognised that the actual P3M3 model and in particular the
Attributes - indicators of process and behavioural maturity, should be referenced in
drawing-up an improvement plan. The P3M3 model and knowledge of where the
organization needs or wants to be positioned in future, should underpin any subsequent
improvement initiatives and the P3M3 model and not simply the self-assessment
questionnaire should be the basis of continuous improvement initiatives.
User Guidance
6
The self-assessment consists of nine questions and although the self-assessment is
based on a few questions, it remains a powerful tool addressing both process capability
and providing insight into an organization’s Maturity Levels in respect of portfolio,
programme and project management.
In completing the self-assessment, a decision needs to be taken on whether the scope will
be limited to a particular combination of portfolio, and/or programme and/or project
management. For example, an organization may wish to assess just project management,
or programme and project management. A second decision on scope is to determine the
boundary of the organization that is to be reviewed i.e. is it the whole organization or a
particular division or department alone?
The first question relates to the overall organizational maturity levels. The aim in
answering this question is to ascertain which of the five Maturity Level descriptions best
describes the portfolio, programme and/or project management processes within the
organization. In answering this question, users are encouraged not only to familiarize
themselves with the definitions of portfolio, programme and/or project management within
Chapters 3, 4, and 5 of the P3M3 respectively, but to familiarize themselves with the
characteristics which constitute best practice.
The questionnaire then contains seven questions, one for each of the Perspectives
contained within P3M3 covering:
J Management Control
J Benefits Management
J Financial Management
J Stakeholder Management
J Risk Management
J Organizational Governance
J Resource Management
A description is presented for each perspective covering five levels of process capability
for portfolio and/or programme and/or project management. The user needs to simply
decide which of the five descriptions most adequately reflects the organization’s current
capability.
In reading the descriptions, the user may conclude that the organization could be
positioned within perhaps two of the Levels. In such circumstances, the user should
review the specific Attributes associated with the Perspective Level descriptions within
P3M3. There are usually c.10 attributes associated with each Perspective Level and the
user should review each of the specific Attributes in turn for the two Levels and consider
7
whether the specific attribute is true or false in respect to current practice within the
organization. By simply counting the number of affirmative specific Attributes within two
Levels, a decision can be taken based on the greater number of affirmative Attributes. In
the unlikely case that the count is the same between two levels, then the organization
should select the lower Perspective Level.
The final question, provides a cross-check on the structural components i.e. between the
individual perspectives and the overall process capability maturity level for portfolio,
programme and/ or project management.
Step-by-Step Guide
The following steps provide a simple guide to accomplishing a P3M3 self-assessment.
The first step, after familiarizing oneself with the general scope of P3M3, is to decide on
the intent of the self-assessment, the range of areas to be covered and the parts of the
overall organization to be included. For example, it may be the intent to limit the
assessment to programme and/or project management, or perhaps to look at (say)
organizational governance and risk management across portfolio, programme and project
management, or to limit the scope to one division alone.
The next step, having determined the scope of the assessment is to determine the most
appropriate individual(s) to complete the exercise. The self-assessment may be
undertaken by:
Having decided upon the assessment scope, and determined the approach and who will
contribute to answering the questionnaire, the assessment can be completed, by referring
to the model answers supplied. The most appropriate response from the model answer
specification should be selected that reflects the current process / practices within the
organization. Where a group of individuals have provided their answers, the leader of the
review will need to determine and agree a process for combining the individual scores.
This might be the minimum score, or some form of averaging.
8
The penultimate step is to analyze the results of the assessment in the context of the
organization’s goals or intent. For example, the self-assessment may have been
undertaken to provide a current baseline from which the efficacy of process improvement
can be judged; alternatively it may be used to help justify the case for investment in (say)
programme management methods training.
The final step, having analyzed the results of the self-assessment is to consider and plan
the next steps and perhaps continue to improve portfolio, programme and/or project
management within the organization leading to improved efficiency, quality and successful
delivery of the organization’s initiatives.
9
Decide Approach
Complete Assessment
The descriptions and characteristics of the five Maturity Levels apply equally to each of
the three sub-models – Portfolio, Programme and Project Management. P3M3 recognizes
that organizations may excel at project management without having embraced programme
management, or indeed vice versa. Similarly, an organization may be accomplished in
portfolio management but immature in programme management. P3M3 therefore allows
an organization to asses its effectiveness against any one or more of the sub-models
independently. Although an overall P3M3 maturity rating cannot be given, since each
model is independent from the others, gauging the overall maturity of an organization is
still possible by undertaking assessments under all three sub-models.
The first question relates to the overall organizational maturity levels. The aim in
answering this question is to ascertain which of the five descriptions given below is the
most accurate reflection of the portfolio, programme and/or project management
processes.
a Processes are not usually documented; there are no, or only a few, process
descriptions. Actual practice is determined by events or individual
preferences, and performance is variable.
A key distinction between this and the previous level description is the
scope of standards, process descriptions and procedures. Processes will be
managed more proactively and the standard processes can be tailored to
suit specific circumstances, in accordance with explicit guidelines.
12
Top managers are seen as exemplars, reinforcing the need and potential for
capability and performance improvement.
The knowledge gained by the organization from its process and product
metrics will enable it to understand causes of variation and therefore
optimize its performance. The organization will be able to show that
continuous process improvement is being enabled by quantitative feedback
from its embedded processes and from validating innovative ideas and
technologies. The organization will be able to demonstrate strong
alignment of organizational objectives with business plans, and this will be
cascaded down through scoping, sponsorship, commitment, planning,
resource allocation, risk management and benefits realization.
P3M3 contains seven process perspectives that identify the key characteristics of mature
organizations using portfolio, programme and/or project management to successfully
achieve strategic objectives and priorities. The processes and practices that characterise
a particular level of process capability within each perspective are described.
The following set of questions is intended to examine the process capability associated
with each of the seven perspectives.
13
Management Control
This covers the internal controls of the initiative and how its direction of travel is
maintained throughout its life cycle, with appropriate break points to enable it to be
stopped or redirected by a controlling body if necessary.
Best practice is characterized by clear evidence of leadership and direction, scope, stages,
tranches and review processes during the course of the initiative. There will be regular
checkpoints and clearly defined decision-making processes. There will be full and clear
objectives and descriptions of what the initiative will deliver. Initiatives should have clearly
described outputs, a programme may have a blueprint with defined outcomes, and a
portfolio may have an organizational target operating model.
Internal structures will be aligned to achieve these characteristics and the focus of control
will be on achieving them within the tolerance and boundaries set by the controlling body
and based on the broader organizational requirements. Issues will be identified and
evaluated, and decisions on how to deal with them will be made using a structured
process with appropriate impact assessments.
b There are some pockets of Some general understanding The concepts of project
portfolio discipline within exists of the concepts of management will have been
individual departments, but programme management and grasped by some within the
this is based on key its control mechanisms but organization, and indeed
individuals rather than as part adoption is localized. there may be local experts,
of a comprehensive and such as experienced project
consistent organization-wide managers working on key
approach. projects.
14
Benefits management is the process that ensures that the desired business change
outcomes have been clearly defined are measurable and are ultimately delivered through
a structured approach and with full organizational ownership.
Best practice recommends that Benefits are assessed and approved by the organizational
areas that will deliver them. Benefit dependencies and other requirements are clearly
defined and understanding gained on how the outputs of the initiative will meet those
requirements. There should be evidence of suitable classification of benefits and a holistic
view of the implications being considered. All benefits should be owned, have realization
plans and be actively managed to ensure that they are achieved. There will be a focus on
operational transition, coupled with follow-up activities to ensure that benefits are being
owned and realized by the organization.
a Recognition that initiatives There is recognition of the There may be recognition that
may exist within the concepts of benefits that can the concept of benefits can
organizational and divisional be differentiated from project be differentiated from project
portfolio to enable the outputs. Benefits are being outputs.
achievement of benefits for developed at a project level
the organization. However, with minimal programme
there isn’t a defined benefits control.
realization process.
Finance is an essential resource that should be a key focus for initiating and controlling
initiatives. Financial management ensures that the likely costs of the initiative are captured
and evaluated within a formal business case and that costs are categorized and managed
over the investment life cycle.
b There are some good Financial approvals and cost Business cases are produced
business cases being projections for programmes in various forms and the
produced and some, usually may not be in evidence. better and more formal cases
departmental, structures to There may be a focus on will present the rationale on
oversee investment project finance but the overall which to obtain organizational
decisions. However, business cost of the programme is not commitment to the project.
cases are often appraised fully accounted for.
independently of each other
and real organizational
priorities have not been
established.
d The organization has Programme life cycles are The organization is able to
effective and robust financial being flexed effectively to prioritize investment
control of its investment manage availability of funds. opportunities effectively in
decisions and the approval There is effective decision relation to the availability of
and monitoring of initiatives. making, with consideration of funds and other resources.
There is proactive, evidence- financial evidence. Business cases are evaluated
based management of the and investment decisions
portfolio. ratified by the business.
Project budgets are managed
effectively and project
performance against cost is
monitored and compared.
Cost models are used to
demonstrate the efficacy of
projects.
e Financial control of the Financial control is evident Project financial controls are
portfolio is an integral part of throughout the programme fully integrated with those of
the organization’s financial life cycle and a balanced view the organization. Cost
control regime. of financial risk taking estimation techniques are
underpins programme continually reviewed in terms
governance. of actual versus estimate
comparisons to improve
estimation throughout the
organization.
19
Risk Management
This views the way in which the organization manages threats to, and opportunities
presented by, the initiative. Risk management maintains a balance of focus on threats and
opportunities, with appropriate management actions to reduce or eliminate the likelihood
of any identified risk occurring, and to minimize its impact if it does occur. It will look at a
variety of risk types that affect the initiative, both internal and external, and will focus on
tracking the triggers that create risks.
Mitigation of risk will be innovative and proactive, using a number of options to reduce
likelihood and impact. The review of risk will be embedded within the initiative’s life cycle
and have a supporting process and structures to ensure that the appropriate levels of
rigour are being applied, with evidence of interventions and changes made to manage
risks.
a There may be a growing There is minimal evidence of There may be some evidence
recognition that risks need to risk management being used of risk management being
be managed and that, at least to any beneficial effect. deployed occasionally, but
for key business initiatives There may be evidence of a with minimal beneficial effect.
(e.g. cost saving or major site risk being documented but
developments), they can little evidence of active
threaten success. management.
c Portfolio risks are identified Risk management has a Project risk management is
and quantified, and mitigation clearly defined and centrally based on a centrally defined
plans are developed and managed process that is process that is cognizant of
funded. Risk management followed consistently by all the organization’s policy for
across the portfolio is based programmes. the management of risks.
on a common, centrally The framework is based on
managed process. industry standards and is
supported by a consistent
system used by all
programmes.
Stakeholders are key to the success of any initiative. Best practice suggests that
stakeholders at different levels, both within and outside the organization, are analyzed and
engaged with effectively in order to achieve objectives in terms of support and
engagement. Stakeholder management includes communications planning, the effective
identification and use of different communications channels, and techniques to enable
objectives to be achieved. Stakeholder management should be seen as an ongoing
process across all initiatives and one that is inherently linked to the initiative’s life cycle
and governance controls.
This looks at how the delivery of initiatives is aligned to the strategic direction of the
organization. It considers how start-up and closure controls are applied to initiatives and
how alignment is maintained during an initiative’s life cycle. This differs from management
control, which views how control of initiatives is maintained internally, as this perspective
looks at how external factors that impact on initiatives are controlled (where possible, or
mitigated if not) and used to maximize the final result. Effective sponsorship should enable
this.
Organizational governance also looks at how a range of other organizational controls are
deployed and standards achieved, including legislative and regulatory frameworks. It also
considers the levels of analysis of stakeholder engagement and how their requirements
are factored into the design and delivery of outputs and outcomes.
d All initiatives are integrated There are clearly aligned Decision-making processes
into an achievable and decision-making processes associated with project
governed portfolio, which is that adopt and integrate with performance are adopted and
aligned to strategic objectives broader organizational integrated into broader
and priorities. The portfolio governance and are organizational performance
contains relevant information transparent to those involved. management, reporting and
on initiatives (e.g. Programme management governance arrangements.
performance measures, responsibilities are embedded
quality attributes and asset within broader role
management data) to support descriptions.
Executive Board decisions.
Resource management covers management of all types of resources required for delivery.
These include human resources, buildings, equipment, supplies, information, tools and
supporting teams. A key element of resource management is the process for acquiring
resources and how supply chains are utilized to maximize effective use of resources.
There will be evidence of capacity planning and prioritization to enable effective resource
management. This will also include performance management and exploitation of
opportunities for greater utilization. Resource capacity considerations will be extended to
the capacity of the operational groups to resource the implications of change.
b The organization has started Resources are being Resources are being
to develop portfolio resource deployed across the deployed across the
management processes and organization but there is little organization but there is little
improve the identification and evidence of a consistent evidence of a consistent
allocation of resources to approach to resource approach to resource
specific initiatives. However, acquisition, planning or acquisition, planning or
this is likely to be reliant on management in support of management in support of
key individuals and does not programmes. projects.
assess the impact of resource
allocation against the
strategic objectives and
priorities.
a Have an Executive Board that Recognize programmes and Recognize projects and run
recognizes programmes and run them differently from them differently from ongoing
projects and maintains an projects. (Programmes may business. (Projects may be
informal list of investments in be running informally with no running informally with no
programmes and projects, standard processes or standard processes or
without perhaps a formal tracking system). tracking system).
tracking mechanism and
documented process.
b Ensure that each programme Ensure that each programme Ensure that each project is
and/or project in its portfolio is is run with its own processes run with its own processes
run with its own processes and procedures to a minimum and procedures to a minimum
and procedures to a minimum specified standard. (There specified standard. (There
specified standard. (There may be limited consistency or may be limited consistency or
may be limited consistency or coordination between coordination between
coordination). programmes). projects).
c Have its own portfolio Have its own centrally Have its own centrally
management process and controlled programme controlled project processes
centrally controlled processes with individual with individual projects being
programme and project programmes being able to able to flex within these
processes with individual flex within these processes to processes to suit the
programmes and projects suit the particular programme. particular project.
being able to flex within these
processes to suit particular
programmes and/or projects.
d Obtain and retain specific Obtain and retain specific Obtain and retain specific
management metrics on its management metrics on its measurements on its project
whole portfolio of programme management management performance
programmes and projects as performance and run a quality and run a quality
a means of predicting future management organization to management organization to
performance. The better predict and control better predict and control
organization assesses its future performance. future performance.
capacity to manage
programmes and projects and
prioritize them accordingly.
The matrix presented below may facilitate in the collation of results for your self-
assessment.
1 Our Maturity
organization
can be best
characterized
as having:
2 Our Portfolio
management
control is best Programme
described by:
Project
Project
Project
Project
7 We deliver Portfolio
organizational
governance Programme
by:
Project
Project
Project
Self-evaluation tips
Question 1 is a general question relating to the level to which the processes have been
defined and established within the organization. Higher levels of process maturity being
demonstrated through the extent to which the processes are quantitatively managed and
whether such management information is used to optimize the processes.
If the overall judgement is that the model answer (a) best characterizes the current
process maturity, then the organization would appear to have immature processes and
only partial awareness of the three Ps. This means, in management terms, that the
organization may occasionally deliver individual initiatives that produce excellent results;
however, managers are likely to be working reactively, focusing on solving immediate
issues, rather than proactively. Schedules and budgets are likely to be exceeded because
of a lack of sound estimating techniques. If deadlines are imposed, the quality of
deliverables is likely to be compromised in order to meet the schedule. For example,
verification and validation activities, including reviews, may be skimped on, if an initiative
falls behind schedule.
If the overall judgement is that the model answer (b), (c), (d) or (e) best characterizes the
current process maturity, then this is indicative of maturing processes, as shown below:
Answers to Questions 2-8 can be collated on the matrix above. The number of answers
will depend upon the scope of the assessment i.e. whether portfolio and/or programme
and/or project management has been included, and also the number of perspectives that
are being considered.
It should be noted that the Level being attained for each Perspective and within each
model (PfM3, PgM3, and PjM3) may be different, as shown in the diagram, below.
Answers that are mainly (a) for a particular Perspective represent Level 1, through to
mainly (e) representing Level 5. Level 1 is the lowest level of process capability and this
basic awareness of the importance of a particular perspective is built upon in an
incremental fashion as depicted in the P3M3 model answer specification.
In interpreting the results, it is recommended that the detailed Attributes within the P3M3
model for a particular Level and Perspective are reviewed to verify the accuracy of the
self-assessment. If the organization wants to use the self-assessment results as the basis
of an improvement initiative, then the assessment provides a valuable snapshot of where
the organization stands currently.
The next step is to consider where the organization wishes to be positioned in future. It
should be recognized that the optimal level may not be Level 5 across all Perspectives or
all three models, and business needs in terms of the optimal level of performance, the
business case for any process improvement initiative and what the organization feels able
to achieve and sustain needs to be considered.
Office of Government Commerce, 1 Horse Guards Road, London SW1A 2HQ This is a Crown copyright value added product, reuse of
which requires a Click-use licence for value added material
Service Desk: 0845 000 4999 E: [email protected] W: www.ogc.gov.uk issued by OPSI.
P3M3 acknowledges that organizations may differ in maturity across its three sub-models – portfolio, programme, and project management. It uses a five-level maturity framework that allows organizations to assess their effectiveness for each sub-model independently . This variance is recognized in the model design, as an organization might excel in project management but not in programme management, enabling targeted assessments and improvements .
P3M3 fosters balance between flexibility and control by providing structured yet adaptable frameworks for portfolio, program, and project management. Processes are defined and documented centrally but allow for customization to fit specific project requirements, ensuring consistency without stifling innovation . This balance is achieved by empowering project teams with standard methods while encouraging adaptive techniques to respond to dynamic project demands and align with strategic imperatives .
The P3M3 Process Perspectives provide a comprehensive framework to evaluate key practices across portfolio, programme, and project management. These seven perspectives include Management Control, Benefits Management, Financial Management, Stakeholder Management, Risk Management, Organizational Governance, and Resource Management . They enable organizations to assess specific areas of capability in detail, thus facilitating targeted improvements and providing a clear understanding of organizational strengths and weaknesses .
The key objectives of conducting a P3M3 self-assessment include gauging an organization's current level of maturity in portfolio, programme, and project management; providing a baseline for improvement initiatives; and identifying embedded practices needed for enhanced capability . It serves as an introduction to the core P3M3 concepts such as Maturity Levels and Process Perspectives, allowing organizations to consider subsequent steps like training or consultancy . However, it is important to note that self-assessments can introduce optimism bias, which may be mitigated by a third-party facilitated assessment .
P3M3 incorporates financial controls by ensuring financial management practices are embedded throughout the project and program life cycles. This includes maintaining a balanced view of financial risks, integrating project financial controls with organizational financial systems, and continually reviewing cost estimation techniques for accuracy . This integration supports strategic alignment and efficient management of financial resources, crucial for successful program delivery .
The P3M3 model supports continuous improvement by encouraging organizations to use the self-assessment as a starting point towards understanding current maturity and planning subsequent improvement initiatives . Moving beyond the questionnaire is essential to avoid optimism bias inherent in self-assessments and to develop a detailed, evidence-based improvement plan . The questionnaire provides initial insights, but the actual model attributes should guide sustained process refinement and maturity development .
The P3M3 approach to Risk Management involves identifying, quantifying, and actively managing risks across portfolios, programs, and projects. It emphasizes a balanced focus on threats and opportunities and uses proactive management actions to minimize risks . This comprehensive approach is crucial for managing uncertainties and enhancing the likelihood of achieving strategic objectives safely and efficiently, ensuring organizational initiatives remain on track .
P3M3’s Resource Management perspective ensures that resources, including human, equipment, and information, are managed efficiently to support strategic objectives. It involves capacity planning, resource profiling, and prioritization, ensuring resources are allocated effectively to align with organizational goals . The model encourages systematic management of resources within and across portfolios, thereby helping organizations dynamically respond to strategic changes and priorities .
A well-defined Organizational Governance process in P3M3 ensures that management controls and decision-making structures are aligned with strategic objectives and priorities at all levels of portfolio, program, and project management . This alignment facilitates effective oversight, accountability, and transparency, helping organizations achieve strategic goals and improve overall performance through consistent governance practices .
Benefits Management in P3M3 ensures that business change outcomes are clearly defined, measurable, and delivered with organizational ownership. It involves assessing and approving benefits by relevant areas and managing dependencies to align outputs with organizational needs . This structured approach aids in delivering program goals effectively by embedding benefits realization plans and continuously managing them within the organizational context .