Final Design Report - Dam Report1
Final Design Report - Dam Report1
REPUBLIC OF KENYA
VOLUME I
December, 2014
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-1
Final Design Report
Table of Contents
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-3
Final Design Report
FIGURES
Figure 1-1: Location of possible of water storage structures. ........................................................1-3
Figure 3-1: Spatial distribution of mean annual rainfall .................................................................3-8
Figure 3-2: A plot of the Athi River basin mean rainfall and evaporation ....................................... 3-8
Figure 4-1: 3D Imagery Layout Plan of HERP and VES in Dam Site .......................................... 4-15
Figure 4-2: Geological Profile of Dam.........................................................................................4-16
Figure 4-3: Comparison between degree of jointing (RQD) and rock mass classification obtained
from SPI (SPI with logarithmic scale) for the right bank. ............................................................. 4-21
Figure 4-4: Mean PGA estimated by Midzi et al,......................................................................... 4-27
Figure 5-1: Seismic Zoning Map of Kenya (I. S. Loupekine 1971) .............................................. 5-32
Figure 5-2: Typical rockfill dam with upstream concrete facing ................................................... 5-34
Figure 5-3: Critical Slip Circles for zoned embankment upstream –End of Construction............. 5-37
Figure 5-4: Critical Slip Circles for zoned embankment downstream. ......................................... 5-38
TABLES
Table 3-1: Proposed land sizes per crop ......................................................................................3-6
Table 3-2: Summary of water supply demand, deficit and storage in Mm3 from Galana River ...... 3-7
Table 3-3: Summary of flow flood flows estimated at RGS308 and RGS3F02. ............................. 3-9
Table 4-1: Results of discontinuity system properties ................................................................. 4-14
Table 4-2: Summary of the activities ..........................................................................................4-16
Table 4-3: Summary of SPT values and approximate bearing capacity ...................................... 4-17
Table 4-4: Summary of weak borehole section ........................................................................... 4-18
Table 4-5: Parker test results .....................................................................................................4-19
Table 4-6: Soil Classification ......................................................................................................4-22
Table 4-7: Soil Compaction Test Result .....................................................................................4-22
Table 4-8: Atterberg Limit and Direct Shear Tests Result ........................................................... 4-23
Table 4-9: Point Load Tests Result ............................................................................................4-24
Table 4-10: Density, Water Content, Water Absorption and UCS Tests Result .......................... 4-24
Table 4-11: Permeability classification according to Lugeon and hydraulic conductivity values .. 4-26
Table 4-12:Proposed seismic design parameters ....................................................................... 4-27
Table 5-1: Minimum factor of Safety ...........................................................................................5-30
Table 5-2: Summary of slope stability factor of safety ................................................................ 5-37
Table 5-3: List of instruments .....................................................................................................5-38
Table 5-4: Grouting Specification ...............................................................................................5-40
Table 7-1: Construction cost of the dams at each dam. .............................................................. 7-44
Table 7-2: Unit manpower cost...................................................................................................7-45
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-4
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-5
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-6
Final Design Report
EXECUTIVE SUMMARY
This is the fourth main report on this assignment; the first was the inception report that
confirmed the terms of reference. The second report was the interim report which assessed
the broad components of the assignment. The third report was the feasibility study report
that recommended dam site 2 as the most viable option to proceed to final design.
The main objective of the proposed Galana-Kulalu dam on River Galana is to conserve
water during the rains and release it for irrigation purposes during the dry months of the
season. It shall support 40,000ha (100,000 acres) of irrigation in Galana-Kulalu food
security project ADC Ranch.The current design is for a dam to impound 340 Million m3.
The project area receive between 750mm to 256mm of rainfall per annum with the long
rains (April to May) being the wettest seasons. The short rains season come between
November and December.
From hydrology analysis,the diversion culvert shall be designed to carry 250 m3/s and the
spillway shall be designed to transmit a peak storm flow of 2,671 m3/s after modulation by
the dam.
Geological studies and geotechnical investigation were conducted, give evidence of
availability enough quantity of good quality rock material that can be utilized in the rockfill
dam construction. Further investigation on the source of core material showed that clay
soils were not available.
Based on the water tests, the nature of dam foundation concluded that foundation
treatment will be necessary. Geological studies and geotechnical investigation concluded
that the most feasible dam type was a zoned rockfill dam with central clay core.
Based on the Geological studies and preliminary geotechnical investigation conducted, a
rockfill dam with an impervious concrete facing slab was considered the most appropriate.
The embankment will have 1V:1.4H both on the upstream and downstream slopes.
Hydrology analysis and flood water simulation concluded that an ogee spillway across the
river was the most suitable flood structure and that during construction four number 4 m by
4 m diversion culvert will be sufficient to divert 1:20 year flood flow , during operation two of
the culverts shalll accommodate the drawoff pipes while the other two shall be used to
release compensational flow and flushing.
A sunken flip backet stilling basin has been provided at the spillway toe for energy
dissipation.
A full EIA study will be conducted at the proposed location to identify the positive and
negative effects to the environmental and society caused by the development of this dam.
No major disruption is envisage, Resettlement Action Planning is not a necessity for the
project.
The Construction cost for the dam is estimated to be Ksh16.05 Billion, The recurrent cost
that was identified to cover the personnel cost was estimated to be kshs 413,640.00 per
annum, and operation and maintenance cost of kshs 75,250,000.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-1
Final Design Report
1 INTRODUCTION
1.1 Background
National Irrigation Board (NIB) has a mandate to develop, promote and manage all national
irrigation schemes in the country. In line with this mandate, NIB is currently managing
seven national irrigation schemes and four research stations in various regions of the
country while undertaking the implementation of new irrigation and drainage infrastructural
development projects in other parts of the country.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-2
Final Design Report
This report covers the dam for reservoir storage for option 1B.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-3
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K)ltd.] Page 1-4
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 2-5
Final Design Report
Horticulture 8,000
Total 160,000
At pre-feasibility study stage, it was not possible to determine the cropping pattern, and use
of a simplified method for evaluation of the irrigation water requirement. The following
assumptions were made:
• The crop water requirement crop coefficient K = 1 for all the crops and throughout
the year
• The irrigated area is fully covered throughout the year
• The reference evapotranspiration is taken as the evaporation
• The effective rainfall is deducted from the evaporation
It is estimated that Athi River at Galana Kulalu dam site has the capacity to supply 2.1
Billion m3 of water annually and support irrigation and other enterprises of 160,000 ha.
Table 3.2 gives a summary of water demand, supply and storage requirement.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 3-6
Final Design Report
Table 3-2: Summary of water supply demand, deficit and storage in Mm3 from Galana River
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
supply 93 1181 273 790 430 19 -7 -23 -31 -33 224 253
Demand 317 315 293 75 0 42 95 166 223 123 188 270
deficit -223 -197 -20 715 430 -23 -102 -189 -254 -156 36 -17
storage 216 19 -1 715 1145 1122 1020 831 577 421 457 440
From the table above it is clear that a storage of 1.1 Billion m3 is required. However this can
only be possible in several dams. The current design is for a dam to impound 340 Million
m3. With this volume, the dam is expected to provide water for irrigation of about 40,000 ha.
3.2 Hydrology
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 3-7
Final Design Report
Figure 3-1 shows the distribution of annual mean rainfall across the catchment.
Comparison of month to month variation of both rainfall and evaporation are shown in table
and 3-2 and figure 3-2.
Table 3-2: Athi River Basin Mean Monthly Rainfall and Evaporation (long term mean values)
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Mean(mm) 24 19 61 143 112 34 19 17 16 37 119 77
Mean Evap
(mm) 186 183 191 153 137 127 124 136 168 183 156 167
Figure 3-2: A plot of the Athi River basin mean rainfall and evaporation
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 3-8
Final Design Report
Figure 3-2 shows that there is monthly moisture defict of upto 200mm between July and
October and December to March. During the wet months, moisture difficit is reduced but not
completely covered.
In terms of water quality, the headwaters of this catchments passes through numerous
urban centres including the capital city of Kenya, Nairobi. The quality in terms of heavy
metal contamination cannot be ruled out. However, due to the long stretch of the river and
owing to the river self-purification factors, the water is expected to be good for irrigation at
the point where the proposed irrigation is situated.
The catchment is characterized by high evaporation rates throughout the year. The lower
reaches where the project site is located, evaporation is in excess of 1900 mm per year
against mean annual rainfall input of 500 mm per year.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 3-9
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 3-10
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-11
Final Design Report
fluctuating amounts of sedimentary material derived from the Basement System rocks
further to the west.
Note: The rocks of the series are strongly jointed and faulted. Some of the latter throw
down the sedimentary rocks against the gneisses and schists of the Basement System.
4.2.1 Flagstones
Flagstones are the most abundant surface rock towards the end of the right abutment. They
are mainly fine grained varying from light brown to buff in colour and well laminated with the
laminations varying from thin laminations ranging from 6 – 20mm to medium laminations
and rarely wide laminations. The interbedded yellow-white flagstones make up the bulk of
the rock formation within the project area.
4.2.2 Shales
Shale rock material is found mostly on the right abutment of the proposed dam axis. The
rock mass is characterized by thin platy layers resembling the flagstone described above.
On the upstream of the right abutment and towards the end of the axis, the low-lying ridges
are formed of shale material.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-12
Final Design Report
4.2.3 Sandstone
Sandstone is the dominant rock exposure within the project area, covering larger part of the
embankment area and dam basin. Sandstones occur in the area both as fine-grained and
medium to coarse-grained sandstones which are highly laminated and jointed.
4.2.4 Arkose
Arkose is very coarse-grained sandstone belonging to the Duruma series. It is dominantly
found on the right abutment and in some few locations on the left abutment. The lower part
of this group consists of coarse clastic material derived from a rapidly wasting gneiss terrain
that is approximately 750 m away upstream.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-13
Final Design Report
almost completely vertical at the dam axis (N065). The strike of joint set 2 which is the
dominant joint set in the area is almost in parallel with the dam axis. The bedding plane of
the rocks on both abutments were found to be dipping at low angle to the east
(downstream) with an average dip angle of 100. Joint strikes were found to be nearly
vertical to the east of both the abutments.
Table 4-1: Results of discontinuity system properties
Location Discontinuity DIP DIP Dir Strike
Left Abutment Joint set 1 85º 85º 337º
Joint set 1 80º 135º 70º
Bedding Plane 10º 92º 160º
Right Abutment Joint set 2 84º 88º 332º
Joint set 2 79º 134º 66º
Bedding Plane 07º 92º 154º
The quantitative descriptions and statistical distributions of discontinuities of rock units
derived from boreholes and those obtained from the geomechanical mapping through
scanline at the dam site according to ISRM (1981).
• Drilling and core recoveries along the proposed dam axis, reservoir and spillway
locations.
The collected soil samples were for taken to the laboratory for testing.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-14
Final Design Report
In this method electric current is introduced into the ground using current electrodes (A and
B), thus creating an electric field between them and the potential difference in that field is
measured using potential electrodes (M and N). According to Ohm’s Law, the resistance of
rock formations (as the conductor) is obtained by dividing the potential difference (at any
point in that field) by the electric current. The property that determines the conducting nature
of any material is known as resistivity which obtained by multiplying the measured
resistance with a geometric coefficient K. The geometric coefficient is dependent on the
configuration of the electrodes. The Wenner configuration was used for profiling technique
while the Schlumberger configuration was used for vertical electrical soundings (VES) with
the array of electrodes.
Figure 4-1: 3D Imagery Layout Plan of HERP and VES in Dam Site
Geophysical investigation was conducted along the dam axis revealing the foundation
condition of the dam site. The figure 4.2 shows the geological profile of dam axis.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-15
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-16
Final Design Report
• Core recovery
Along Dam axis at Left
BH 3 • Sampling 40 m
abutment
• Water test
• Core recovery
Along Dam axis at Right • Sampling
BH 4 50 m
abutment • STP
• Water test
• Core recovery
Along Dam axis at Left
BH 5 • Sampling 60 m
abutment
• Water test
• Core recovery
Along Dam axis at Right
BH 6 • Sampling 60 m
abutment
• Water test
• Core recovery
Along Dam axis at Right
BH 7 • Sampling 60 m
abutment
• Water test
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-17
Final Design Report
• Arkose
• Mudstone
• Greywacke
• Flagstone
The quality of the rock mass is good recording high values of RQD and the joints are tight
and therefore the problem of seepage as a result of the difference in hydraulic head is
minimal except in special cases where a section of borehole depth is faulted like in BH03
where the section between 20 and 33 m is highly sheared. Tables 4-4 give the summary of
the borehole sections that are considered weak and can create a conduit for seepage:
Table 4-4: Summary of weak borehole section
LEFT ABUTMENT
BH01
Depth Range (m) Section RQD (%)
Thickness
From To
1.5 4 2.5 17.0
17.5 21 3.5 29
23.3 24.7 1.4 24.7
31 33 2 16
BH02
Depth Range (m) Section RQD (%)
Thickness
From To
1 2 1 19.0
24 25 1 50.0
29 30.5 1.5 26.0
35.5 36 0.5 23.0
42.5 43.7 1.2 45
43.7 45.2 1.5 38
BH03
Depth Range (m) Section RQD (%)
Thickness
From To
1 7 6 2.4
10.8 12.2 1.4 52.0
20.1 23.5 3.4 20.0
26 27.5 1.5 12.0
30 30.5 0.5 0.0
32.6 33.2 0.6 0.0
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-18
Final Design Report
BH04
Depth Range (m) Section RQD (%)
Thickness
From To
5 6 1 19.0
RIGHT ABUTMENT
BH05
Depth Range (m) Section RQD (%)
Thickness
From To
3 5 2 26.4
26 28.3 2.3 0.0
31.3 32.3 1.0 33.1
51 53.5 2.5 0.0
54 55.5 1.5 0.0
BH06
Depth Range (m) Section RQD (%)
Thickness
From To
1.3 2.9 3.6 22.0
BH07
Depth Range (m) Section RQD (%)
Thickness
From To
1.8 21.5 19.7 3.0
From the Table 4-4, BH03 (left abutment) and BH07 (right abutment) have weak zones
which require sealing. No water flush return achieved between 20 – 33.3 m in BH03 and 2 –
20 m in BH07. These sections of the Borehole will require grouting to seal the crevices.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-19
Final Design Report
Min Max
Depth Lugeon Conductivity Rock discontinuity
Borehole Lugeon Lugeon
value
(meters) value value classification condition
(l/m/min)
(l/m/min) (l/m/min)
BH2 60 0.071 4.769 1.3 Excellent Open closely spaced
or void
BH3 40 0.726 6.089 3.2 Excellent Few partly open
BH4 45 0.181 3.516 1.2 Excellent Needless
RIGHT ABUTMENT
BH5 63.7 0.183 4.479 1.1 Excellent Very tight
BH6 50 0.019 0.933 0.34 Excellent Few partly open
From the results above, dam foundation water transimisity is low to moderate. The results of
these tests indicate that the permeability of the shales, sandstones, greywacke and
mudstone which form the bedrock of the dam site range between, 0.34 and 3.42 Lugeons.
The high Lugeon values were achieved especially in BH01, BH03 and BH07 possibly
because of the shear zone and highly jointed rock masses. High permeability is one of main
geological engineering problems in any dam. Galana-Kulalu dam, whose maximum lugeon
value 9.74, was established is of low permeability.
However there were areas with lugeons values greater than 5 indicating that grouting will be
required to improve water tightness at various locations.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-20
Final Design Report
Figure 4-3: Comparison between degree of jointing (RQD) and rock mass classification obtained from
SPI (SPI with logarithmic scale) for the right bank.
• Hydrometer testing
• Standard Proctor Compaction test: (a) Optimum moisture content and (b) Maximum
dry density
• Unit weight
• Specific Gravity
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-21
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-22
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-23
Final Design Report
4.6.2.2 Density, Water Content, Water Absorption and UCS Test Results
9 UCS tests were carried out for rock samples taken from different depths and rock units
and the laboratory results are presented in Table 4-10. The results show that the UCS
strength of the rock mass selected varies from 15 Mpa to 144 Mpa with an average value of
85 Mpa.
Table 4-10: Density, Water Content, Water Absorption and UCS Tests Result
Based on the laboratory results for the analyses rock specimen, we conclude that the rock
mass material underlying the dam foundation is very strong and competent.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-24
Final Design Report
4.9 Hydrogeological Status and water tightness of the dam foundation along the axis
The study of the hydrogeological conditions of the dam embankment axis side utilized the
water level measurements and the permeability tests in the boreholes, as well as the
observations during drilling. The results of the geophysical investigations were also taken
into account. During the geological mapping, no significant springs were identified, apart
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-25
Final Design Report
from very weak flows after rains from the surface mantle. Classification of the permeability
in the geological formations, in ccordance to lugonis in Table 4-1.
Table 4-11: Permeability classification according to Lugeon and hydraulic conductivity values
With no overburden material found on the boreholes, The permeability test was conducted
on rock mass along the dam center line. The primary porosity practically does not exist
within the solid rocks. Intense digenesis and recrystallization have sealed their primary grain
network. Their permeability is controlled by their secondary porosity, which is created by the
network of their hydro-conductive discontinuities. These discontinuities may be their
bedding planes, joints, faults and fractured zones.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-26
Final Design Report
Table 4-12 is a summary of the design seismic input parameters recommended for the
proposed Galana-Kulalu dam:
Table 4-12:Proposed seismic design parameters
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-27
Final Design Report
4.11 Conclusion
• The rocks within the Galana-Kulalu dam site and reservoir area, consist of schists
and gneisses of the Basement System which are overlain by grits, sandstones,
limestones, shales, greywacke and conglomerates ranging in age from Upper
Carboniferous to Triassic and known collectively as the Duruma Sandstones and
Basement System.
• Joints are the most abundant structural features that are observed on the rock
surfaces and their strike rather than their orientation were taken to verify their
dominant trend. The joints are dominant within the flagstone and fine sandstones
across the study area. The area is highly faulted to the west and to the north of the
proposed project site. The exposed metamorphic rocks about 750 m to the west of
the embankment axis have the N.N.W. strike-trend of the Mozambiquian belt and a
westerly foliation dip. There are three major faults sandwiching the proposed
embankment axis.
• Due to the proximity of the Galala Dam to the Kenya rift and the NNW-SSE trending
rifts/shear zones, the maximum PGA for SEE was considered equal to the maximum
PGA that was estimated based on the deterministically-evaluated CMCE scenario,
and, therefore, is considered equal to 0.23g.
• The resistivity survey reveals that the rock mass underlying the proposed dam axis
is not uniform across the embankment axis. The upper part and lower part of the left
abutment has competent rock mass except in two sections of the upper part of the
abutment where two shear zones were identified. The shear zones are deeply
fractured and require special attention. On the right bank, the lower abutment (about
a span of 250 m from the river channel) is very stable and tight. The upper part of
the abutment from BH06 to the end of the axis is highly porous up to an average
depth of 20 m below the ground level. It is interpreted as highly sheared shale and
sandstones texturally with a matrix of clay. This zone also will require special
treatment to improve its stability and structural integrity.
• Based on the packer tests performed in all the seven boreholes. The result shows
that the rock mass within the dam axis is very tight and can be classified as very low
to low permeability. The hydraulic conductivity coefficients recorded within site were
less than 10-5 cm/s with the exception of few cases in specific areas where the value
was higher than 10-5cm/s. This areas include section depth 20m – 32m of BH03 and
section depth 0.3m – 16.5m of BH07, which shall require special treatment.
• The rock head is very shallow and therefore dam foundation will be founded on
competent rock mass.
• The observed faulting and deep weathering in the higher part of the left abutment
may require extensive treatment to provide sound foundations.
4.12 Recommendation
• Geologiccal investigation revealed a stable foundation although faults were identified
however there is a need for more investigations during comstruction to confirm the
design stage parameters adopted.
• More investigation is also recommended to be carried out within the dam reservoir
including some few vertical Electrical Soundings to ascertain the hydrogeological
conditions within the reservoir.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-28
Final Design Report
• From the drilling analysis, the average depth to sound rock head is about 5 m below
the ground level on the left abutment. Therefore, to achieve uniform, stable and
sound foundation, it is recommended a shallow stripping up to a depth of 6 m on the
left abutment to remove the regoliths (fractured and weathered) top rock head.
• A proper curtain grouting up to a depth of 45 m between BH03, BH02 and BH01
respectively is recommended.
• Between BH06 to the end of right side of axis, (500 m long), is deeply sheared,
tectonized and decomposed rocks, on account of this rock mass conditions within
this section. Deep stripping is recommend up to a depth of 10 m, after that, a blanket
grouting be done up to a depth of 16 m deep, followed by three lines of dense
curtain grouting taken down to 22 m.
• Based on the geological and geotechnical studies conducted along the Galana-
Kulalu dam, the ideal dam type recommended is a Rockfill dam with a concrete slab
facing.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 4-29
Final Design Report
5 DAM DESIGN
5.1 Introduction
The major activities during the Feasibility Study was to select a dam location. This was
based on the alternatives that were found to accommodate the relevant amount of water,
assess the river inflows, establish the required storage and dam height, to meet the
projected water demand, assess properties and availability of dam construction materials,
establish the dam foundation condition and establish the design concepts for the design of
proposed dam components and structures.
The Feasibility Study evaluated the topographical, geotechnical and hydraulic factors that
are considered in the dam design. It found out that Dam site 2 was more feasible and was
recommended to proceed to the final design stage. This design stage shall carry further
investigation regarding forms of construction and recommends the dam type that should
proceed to Construction. The criteria and concepts adopted in the design of the dam are
discussed here below.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-30
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-31
Final Design Report
5.2.9 Earthquake
The proposed Galana-Kulalu dam site is in a region which is not seismic active and not
prone to earthquakes. The area’s data on earthquake was analysed and a maximum
credible earthquake for the area was determined. The seismic zoning VI that the dam site
falls (Figure 5-1) refers to the intensity of damage according to the Modified Mercalli scale.
In that scale the intensity in zone VI has low effects.
To ensure the structural stability of the dam, the Kenya earthquake code recommends that
a design basis earthquake (DBE) of 0.12 gal (design earthquakes and accelerations
loading) be applied for earthquake analysis.
A horizontal acceleration of 0.12g was used in the slope stability analysis. Incorporation of
this acceleration in the design process would ensure that in the case of similar vibrations
the dam would not fail.
5.3.1 Permeability
No soil samples obtained for this tests however since the material ranged from Silty sand to
gravel sand permeability is expected in the range of 40 lugeons i.e., 5X10-5m/s which is not
suitable for dam embankment construction particularly the core.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-32
Final Design Report
5.4.3 Sand
Sand for construction purpose is easily and adequately available within close proximity to
the dam site, however, further investigations are recommended to ascertain their quality for
construction and filter purposes.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-33
Final Design Report
• The slopes of spillway and outlet works must be stable under all operational
conditions.
The proposed rockfill dam will have a maximum height of water approximately 38.5 m;
measured from the top water level at EL 172.5 masl down to the lowest point in the natural
riverbed at EL 134 masl. The top of embankment is estimated at 178.5m, as explained in
section 5.5.5 below, on dam freeboard.
The embankment will be rockfill type with impavious upstream concrete facing.
The dam embankment shall contained three zones as described below;
1) Zone A – Upstream Concrete facing
The dam upstream will be covered with a reinforced concrete to provide an
impervious media for the dam.
A well graded sand and gravel base course for the membrane is necessaty to
provide a more flat surface.
2) Zone B – Rockfill shoulder zone with selected processed small rocks
This zone comprise of small selected rocks which allows the concrete membrane
layer to settle uniformy on the dam.
3) Zone C – Rockfill shoulder zone with well graded best quality rock
This zone comprise of the best rock for the embankment.
A typical section of the proposed rockfill dam is presented in the figure below.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-34
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-35
Final Design Report
for a 7.5 free board. Hence to get adequate free free boad of 0.9m the total free board
required is 7.95m. provide an emabankment free board of 6m and a parapet wall 2m high.
Hence, a 8.0m of freeboard is adequate.
5.5.10 Alignment
The alignments were selected based on the contour layout to give the shortest crest length
and allow for the economical location of spillway route and outlet works. In addition to this
Maximum possible storage of the valleys were considered. The crest elevation level of the
dam is at 180 masl and the top water level is at 171.0 masl a crest length of 2610 m
resulted.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-36
Final Design Report
-90.0
-80.0
-70.0
-60.0
-50.0
-40.0
-30.0
-20.0
-10.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
0.0
204.0
194.0
184.0
174.0
164.0
154.0
144.0
134.0
Concrete Fa
Figure 5-3: Critical Slip Circles for zoned embankment upstream –End of Construction
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-37
Final Design Report
-100.0
-90.0
-80.0
-70.0
-60.0
-50.0
-40.0
-30.0
-20.0
-10.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
0.0
204.0
194.0
184.0
174.0
164.0
154.0
144.0
134.0
Concrete Fa
5.5.14 Instrumentation
Instrumentation is included in dam for the purpose of monitoring the conditions and
performance of the embankment and foundation during construction and normal
operations. The most important performance parameters to be monitored will include
seepage, vertical movement (settlement) and horizontal movement. Piezometers and
settlement gauges would be installed in the embankment, piezometers and observation
wells will be installed in the foundation to monitor the pore water pressure. The foundation
shall have seismic measurement device installed either within the embankment foundation
or off the embankment area will be directed to a single chamber where a V-notch shall be
installed. A single observation well will also be required downstream of the embankment.
The number and types of the instrumentation will largely depend on the embankment and
foundation soils. The proposed dam instruments are summarised in the Table 5-3.
Table 5-3: List of instruments
Instruments Sets Quantity
Survey Monument 40
Vibrating wire piezometer 80
Earth pressure cell 80
Concrete face starin meter 80
In place Inclinometer and settlement cells gauges 20
Seepage measuring device (Vee notch) 2
Stand pipe piezometer 20
Extensometer 20
Complete Weather station 1
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-38
Final Design Report
The accuracy and specific details of the proposed instrumentation will be provided during
construction.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-39
Final Design Report
Layout of grout
holes
Change of grout
mix
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-40
Final Design Report
It should also be noted that the above proposed grouting will be subject to changes depending on site conditions observed before or
during the construction period. In addition to this, contractors with good experience in this field would be required. The Resident Engineer
must ensure all the works are done to his/her satisfaction and all changes required are done to ensure minimum seepage.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 5-41
Final Design Report
6.1 Introduction
The environmental and social scooping exercise was conducted and used the
recommended Integrated Participatory
A project report has been prepared for submission to NEMA. The project report to be
presented separately is summarised herein.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 6-42
Final Design Report
• Water quality
• Waste management
• Terrestrial & Aquatic Ecology
• Cultural
An elaborate Environmental & Social Mitigation and management Plan ESMMP will be
prepared.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 6-43
Final Design Report
7 COST ESTIMATED
• Soliciting quotations from reputable suppliers of various materials for civil works
construction mechanical and electrical equipment and building into this
quotations a reasonable profit and overhead factor
The investment costs are broken down into their main components and summarised in
the Table 7-1. The detailed cost estimates are to be submitted as confidential draft cost
estimates.
The table below gives the estimated cost each dam broken down to their major
components.
Table 7-1: Construction cost of the dams at each dam.
GRAND SUMMARY
ITEM
DESCRIPTION Total AMOUNT (KSh)
NO.
2 Geotechnical 1,366,980,000.00
4 Earthworks 6,119,302,092.50
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 7-44
Final Design Report
Assuming 3 labourers, the total annual manpower cost will be 413,640 Kenyan shillings.
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 7-45
Final Design Report
8 PROGRAMME OF WORKS
The proposed construction period for Galana - Kulalu dam is approximate three and a half years (3.5 years)
Foundation treatment
Fill Embankment
Transmision pipeline
Post Construction
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 8-1
Final Design Report
APPENDIX 1 – REFERENCES
1. Design of small dams, United States Bureau of Reclamation (USBR).
2. Practice Manual for small dams and pans and other water conservation structures in
Kenya, Ministry of Water and Irrigation, 2015.
3. Practice Manual for Water Supply Services in Kenya, Ministry of Water and Irrigation,
2005.
4. US Army Corps of Engineers, Engineering Manuals April 2000.
5. Bureau of Reclamation – US Department of Commerce –1991
6. Characteristics of Problems of Dispersive Soils – US
7. Department of Interior – Bureau of Reclamation 1991.
8. Soil Mechanics R.F Craig ELBS 1990.
9. Guidelines for Predicting and Minimizing Sedimentation in Small Dams (Wallingford, H.
R. 2004).
10. Kenya Vision 2030, October 2007.
11. National Water Harvesting and Storage Management Policy, Ministry of Water and
Irrigation, May 2010.
12. National Water Quality Management Strategy (NWQMS) 2012 – 2016, Ministry of
Water and Irrigation.
13. Irrigation and Drainage Master Plan, Ministry of Water and Irrigation, June 2009.
14. Water Resource Technical Publication, Engineering Monograph No. 25, Hydraulic
Design of Stilling Basins and Energy Dissipators, United States Bureau of Reclamation
(USBR).
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 8-1
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 8-2
Final Design Report
[Agrigreen in Association with Enviroplan and Management Consultants(K) and Amiran (K) ltd.] Page 8-3