0% found this document useful (0 votes)
20 views2 pages

20-7-2024 LWR - B, D, E Short Term

Uploaded by

heavenchan.6
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views2 pages

20-7-2024 LWR - B, D, E Short Term

Uploaded by

heavenchan.6
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Programme no.: GW-HCIF-TSPC-LW-BE-001 Rev.

A
Proposed Development AT I.L.9088, Central DATE:20-7-2024
Tentative Short Term Programme
( Lung Wo Road [Link] B~E )

WBS TASK WORKING CALENDAR START FINISH 旬 六月中旬 七月上旬 七月下旬 八月中旬 九月上旬 九月下旬 十月中旬 十一月上 十一月下 十二月中旬
DATE DATE 2/6 9/6 16/6 23/6 30/6 7/7 14/7 21/7 28/7 4/8 11/8 18/8 25/8 1/9 8/9 15/9 22/9 29/9 6/10 3/1 0/1 7/1 3/11 0/1 7/1 4/1 1/12 8/12 5/1 2/1 9/1
1 Lung Wo RD Deck ( Gr. B~E / L1~L2 ) 126 days 1 20 / 5 / 2024 9 / 10 / 2024

1.1 TTM 83 days 1 20 / 5 / 2024 17 / 8 / 2024


1.1.1 Trial Run 1 day 1 20 / 5 / 2024 20 / 5 / 2024 un
1.1.2 Receive Comment From TD ( Working From Monday to Sunday ) 5 days 5 15 / 7 / 2024 19 / 7 / 2024 Receive Comment From TD
1.1.3 TA Application ( With Traffic Survey ) ( Request by TD ) 21 days 24 25 / 7 / 2024 17 / 8 / 2024 TA Application
1.1.4 RA Application 1 day 1 12 / 8 / 2024 12 / 8 / 2024 RA Application
1.2 Temp. Work 93 days 1 11 / 6 / 2024 24 / 9 / 2024
1.2.1 Gr. Line 5 60 days 1 11 / 6 / 2024 15 / 8 / 2024
[Link] P14~22 ( P23 Need Full Core ) 16 days 1 11 / 6 / 2024 27 / 6 / 2024
[Link].1 Hand Over From Vibro 1 day 1 11 / 6 / 2024 11 / 6 / 2024 Hand Over From Vibro
[Link].2 Site Erection 15 days 16 12 / 6 / 2024 27 / 6 / 2024 Site Erection
[Link] P1~P13 32 days 1 10 / 7 / 2024 15 / 8 / 2024
[Link].1 Hand Over From Vibro 1 day 1 10 / 7 / 2024 10 / 7 / 2024 Hand Over From Vibro
[Link].2 Site Erection 25 days 29 11 / 7 / 2024 8 / 8 / 2024 Site Erection
[Link].3 Preparation Work Before Steel Truss Erection 6 days 7 9 / 8 / 2024 15 / 8 / 2024 Preparation Work Before Steel Truss Erection
1.2.2 Gr. Line 10 87 days 1 17 / 6 / 2024 24 / 9 / 2024
[Link] For G.D~E 63 days 1 17 / 6 / 2024 26 / 8 / 2024
[Link].1 Remedial Work for S11D / S11F 9 days 9 25 / 6 / 2024 3 / 7 / 2024 Remedial Work for S11D / S11F
[Link].2 Hand Over From COBC ( Zone 7 - RC Slab )(29/6/2024 Verbal Information ) 17 days 19 4 / 7 / 2024 22 / 7 / 2024 Hand Over From COBC ( Zone 7 - RC Slab )
[Link].3 Design and Calculation Submission 1 day 1 17 / 6 / 2024 17 / 6 / 2024 Design and Calculation Submission
[Link].4 Design and Calculation Approval 17 days 18 18 / 6 / 2024 5 / 7 / 2024 Design and Calculation Approval
[Link].5 Materials Procurement 7 days 7 6 / 7 / 2024 12 / 7 / 2024 Materials Procurement
[Link].6 Shop Fabrication 8 days 10 13 / 7 / 2024 22 / 7 / 2024 Shop Fabrication
[Link].7 Site Erection ( With Permanent CFT x 3 nos. ) 14 days 16 6 / 8 / 2024 21 / 8 / 2024 Site Erection
[Link].8 Preparation Work Before Steel Truss Erection 4 days 5 22 / 8 / 2024 26 / 8 / 2024 Preparation Work Before Steel Truss Erection
[Link] For Gr.B 18 days 1 3 / 9 / 2024 24 / 9 / 2024
[Link].1 Hand Over From COBC ( Zone 8b - RC Slab )(5/7/2024 COBC Progress ) 1 day 1 3 / 9 / 2024 3 / 9 / 2024 Hand Over From COBC ( Zone 8b - RC Slab )
[Link].2 Site Erection ( With Permanent CFT x 1 no. ) 14 days 17 4 / 9 / 2024 20 / 9 / 2024 Site Erection ( With Permanent CFT x 1 no. )
[Link].3 Preparation Work Before Steel Truss Erection 3 days 4 21 / 9 / 2024 24 / 9 / 2024 Preparation Work Before Steel Truss Erection
1.3 Tower Crane ( TC1 ) 15 days 1 19 / 7 / 2024 5 / 8 / 2024
1.3.1 Revise MS Base on MTR RP Comment 3 days 4 19 / 7 / 2024 22 / 7 / 2024 Revise MS Base on MTR RP Comment
1.3.2 Submit MS and Asking for Advise Approval ( Tentative ) 1 day 1 23 / 7 / 2024 23 / 7 / 2024 Submitt MS and Asking for Advise Approval ( Tentative )
1.3.3 Formal Approval by RP 1 day 1 30 / 7 / 2024 30 / 7 / 2024 Formal Approval by RP
1.3.4 Construct New Soil Location for 500t Crane 7 days 8 24 / 7 / 2024 31 / 7 / 2024 Construct New Soil Location for 500t Crane
1.3.5 Design / Shop Fabrication Steel Protective Barrier for MTR V. Shaft 7 days 8 24 / 7 / 2024 31 / 7 / 2024 Design / Shop Fabrication Steel Protetive Barrier
1.3.6 Site Erection 4 days 1 1 / 8 / 2024 5 / 8 / 2024
[Link] Erect Protective Steel Frame by 500 T Crane 1 day 1 1 / 8 / 2024 1 / 8 / 2024 Curing Time / As Built
[Link] Tower Crane Installation 3 days 4 2 / 8 / 2024 5 / 8 / 2024 Tower Crane
1.4 Pre Work 60 days 1 18 / 6 / 2024 23 / 8 / 2024
1.4.1 Street Light Shortening 1 day 1 18 / 6 / 2024 18 / 6 / 2024 Street Light Shortening
1.4.2 Concrete Footing / Pylon / Working Platform Erection 47 days 1 25 / 6 / 2024 15 / 8 / 2024
[Link] Plate Load Test ( To Verify Extg. Ground Condition ) 11 days 11 25 / 6 / 2024 5 / 7 / 2024 Plate Load Test
[Link] Grouting ( Gap Between Footing / Existing Road )South Side ( 4 nos. of Footing ) 4 days 5 12 / 7 / 2024 16 / 7 / 2024 Grouting
[Link] Pre Load ( 4nos. At South Side / 1no. At North Side ) 28 days 1 15 / 7 / 2024 15 / 8 / 2024

專案: 12-3- 2024 任務 里程碑 專案摘要報告 外部里程碑 期限


日期: 20 / 7 / 2024 分割 摘要 外部任務 進度

Remark : Assume Plate Load Test Result is Positive. 第1頁


Programme no.: GW-HCIF-TSPC-LW-BE-001 Rev.A
Proposed Development AT I.L.9088, Central DATE:20-7-2024
Tentative Short Term Programme
( Lung Wo Road [Link] B~E )

WBS TASK WORKING CALENDAR START FINISH 旬 六月中旬 七月上旬 七月下旬 八月中旬 九月上旬 九月下旬 十月中旬 十一月上 十一月下 十二月中旬
DATE DATE 2/6 9/6 16/6 23/6 30/6 7/7 14/7 21/7 28/7 4/8 11/8 18/8 25/8 1/9 8/9 15/9 22/9 29/9 6/10 3/1 0/1 7/1 3/11 0/1 7/1 4/1 1/12 8/12 5/1 2/1 9/1
[Link].1 South Side ( Footing for TR3 and TR5 ) 4 days 4 15 / 7 / 2024 18 / 7 / 2024 South Side ( Footing for TR3 and TR5 )
[Link].2 North Side ( Footing for TR5 ) 4 days 4 12 / 8 / 2024 15 / 8 / 2024 Nouth Side ( Footing for TR5 )
1.4.3 Erection Working Platform 12 days 13 5 / 8 / 2024 17 / 8 / 2024 Erection Working Platform
1.4.4 Preparation Work Before Steel Truss Erection 11 days 12 12 / 8 / 2024 23 / 8 / 2024 Preparation Work Before Steel Truss Erection
1.5 WSD Flash Water & Salt Water Pipe Diversion ( Tentative ) 32 days 52 6 / 7 / 2024 10 / 8 / 2024
1.5.1 Trial Pit 2 days 2 6 / 7 / 2024 7 / 7 / 2024 Trial Pit
1.5.2 WSD inspection 2 days 2 8 / 7 / 2024 9 / 7 / 2024 WSD inspection
1.5.3 Concrete Plinth 3 days 3 9 / 7 / 2024 11 / 7 / 2024 Concrete Pinth
1.5.4 Pipe Clamp installation 5 days 6 11 / 7 / 2024 16 / 7 / 2024 Pipe Clamp installation
1.5.5 Installation of Water for diversion 12 days 14 13 / 7 / 2024 26 / 7 / 2024 Installation of Water for diversion
1.5.6 Pressure Test for Water Pipe 4 days 5 27 / 7 / 2024 31 / 7 / 2024 Presure Test for Water Pipe
1.5.7 Cleaning of Pipe 1 day 1 1 / 8 / 2024 1 / 8 / 2024 Cleaning of Pipe
1.5.8 Sterilization and take Water Sample 6 days 7 2 / 8 / 2024 8 / 8 / 2024 Sterilization and take Water Sample
1.5.9 Connect by WSD 2 days 2 9 / 8 / 2024 10 / 8 / 2024 Connect by WSD
1.6 Shop Fabrication 90 days 6 / 6 / 2024 14 / 9 / 2024
1.6.1 CFT 33 days 21 3 / 7 / 2024 8 / 8 / 2024
[Link] 3 nos. for Gr. D~E 23 days 25 3 / 7 / 2024 27 / 7 / 2024 CFT Fabrication - 3 nos. for Gr. D~E
[Link] 1no. For Gr. B 22 days 25 15 / 7 / 2024 8 / 8 / 2024 1no. For Gr. B
1.6.2 Steel Truss 90 days 1 6 / 6 / 2024 14 / 9 / 2024
[Link] TR3 / TR4 65 days 1 6 / 6 / 2024 16 / 8 / 2024
[Link].1 Pre- fab. / Fabrication 45 days 49 6 / 6 / 2024 24 / 7 / 2024 TR3 / TR4 - Pre- fab. / Fabrication
[Link].2 Pre assemble 16 days 19 25 / 7 / 2024 12 / 8 / 2024 Pre assemble
[Link].3 Inspection by Relative Party 1 day 1 13 / 8 / 2024 13 / 8 / 2024 Inspection
[Link].4 Dismantle ( Ready for Deliver to Site ) 3 days 3 14 / 8 / 2024 16 / 8 / 2024 Dismantle ( Ready for Deliver to Site )
[Link] TR1 73 days 1 25 / 6 / 2024 14 / 9 / 2024
[Link].1 Fabrication 60 days 67 25 / 6 / 2024 30 / 8 / 2024 TR1 - Fabrication
[Link].2 Pre assemble 12 days 13 2 / 9 / 2024 14 / 9 / 2024 Pre assemble
1.7 Deliver to Site 30 days 1 17 / 8 / 2024 21 / 9 / 2024
1.7.1 By Sea ( Temp. Storage on Tuen Mun ) 30 days 2 17 / 8 / 2024 21 / 9 / 2024
[Link] TR3 / TR4 3 days 4 17 / 8 / 2024 20 / 8 / 2024 Deliver to Site - TR3 / TR4
[Link] TR1 3 days 3 19 / 9 / 2024 21 / 9 / 2024 TR1
1.8 Site Erection ( Detail Schedule Submit Separate ) 36 days 1 27 / 8 / 2024 9 / 10 / 2024
1.8.1 TR3 / TR4 19 days 22 27 / 8 / 2024 17 / 9 / 2024 Site Erection - TR3 / TR4
1.8.2 TR1 12 days 15 25 / 9 / 2024 9 / 10 / 2024

專案: 12-3- 2024 任務 里程碑 專案摘要報告 外部里程碑 期限


日期: 20 / 7 / 2024 分割 摘要 外部任務 進度

Remark : Assume Plate Load Test Result is Positive. 第2頁