Programme no.: GW-HCIF-TSPC-LW-BE-001 Rev.
A
Proposed Development AT I.L.9088, Central DATE:20-7-2024
Tentative Short Term Programme
( Lung Wo Road [Link] B~E )
WBS TASK WORKING CALENDAR START FINISH 旬 六月中旬 七月上旬 七月下旬 八月中旬 九月上旬 九月下旬 十月中旬 十一月上 十一月下 十二月中旬
DATE DATE 2/6 9/6 16/6 23/6 30/6 7/7 14/7 21/7 28/7 4/8 11/8 18/8 25/8 1/9 8/9 15/9 22/9 29/9 6/10 3/1 0/1 7/1 3/11 0/1 7/1 4/1 1/12 8/12 5/1 2/1 9/1
1 Lung Wo RD Deck ( Gr. B~E / L1~L2 ) 126 days 1 20 / 5 / 2024 9 / 10 / 2024
1.1 TTM 83 days 1 20 / 5 / 2024 17 / 8 / 2024
1.1.1 Trial Run 1 day 1 20 / 5 / 2024 20 / 5 / 2024 un
1.1.2 Receive Comment From TD ( Working From Monday to Sunday ) 5 days 5 15 / 7 / 2024 19 / 7 / 2024 Receive Comment From TD
1.1.3 TA Application ( With Traffic Survey ) ( Request by TD ) 21 days 24 25 / 7 / 2024 17 / 8 / 2024 TA Application
1.1.4 RA Application 1 day 1 12 / 8 / 2024 12 / 8 / 2024 RA Application
1.2 Temp. Work 93 days 1 11 / 6 / 2024 24 / 9 / 2024
1.2.1 Gr. Line 5 60 days 1 11 / 6 / 2024 15 / 8 / 2024
[Link] P14~22 ( P23 Need Full Core ) 16 days 1 11 / 6 / 2024 27 / 6 / 2024
[Link].1 Hand Over From Vibro 1 day 1 11 / 6 / 2024 11 / 6 / 2024 Hand Over From Vibro
[Link].2 Site Erection 15 days 16 12 / 6 / 2024 27 / 6 / 2024 Site Erection
[Link] P1~P13 32 days 1 10 / 7 / 2024 15 / 8 / 2024
[Link].1 Hand Over From Vibro 1 day 1 10 / 7 / 2024 10 / 7 / 2024 Hand Over From Vibro
[Link].2 Site Erection 25 days 29 11 / 7 / 2024 8 / 8 / 2024 Site Erection
[Link].3 Preparation Work Before Steel Truss Erection 6 days 7 9 / 8 / 2024 15 / 8 / 2024 Preparation Work Before Steel Truss Erection
1.2.2 Gr. Line 10 87 days 1 17 / 6 / 2024 24 / 9 / 2024
[Link] For G.D~E 63 days 1 17 / 6 / 2024 26 / 8 / 2024
[Link].1 Remedial Work for S11D / S11F 9 days 9 25 / 6 / 2024 3 / 7 / 2024 Remedial Work for S11D / S11F
[Link].2 Hand Over From COBC ( Zone 7 - RC Slab )(29/6/2024 Verbal Information ) 17 days 19 4 / 7 / 2024 22 / 7 / 2024 Hand Over From COBC ( Zone 7 - RC Slab )
[Link].3 Design and Calculation Submission 1 day 1 17 / 6 / 2024 17 / 6 / 2024 Design and Calculation Submission
[Link].4 Design and Calculation Approval 17 days 18 18 / 6 / 2024 5 / 7 / 2024 Design and Calculation Approval
[Link].5 Materials Procurement 7 days 7 6 / 7 / 2024 12 / 7 / 2024 Materials Procurement
[Link].6 Shop Fabrication 8 days 10 13 / 7 / 2024 22 / 7 / 2024 Shop Fabrication
[Link].7 Site Erection ( With Permanent CFT x 3 nos. ) 14 days 16 6 / 8 / 2024 21 / 8 / 2024 Site Erection
[Link].8 Preparation Work Before Steel Truss Erection 4 days 5 22 / 8 / 2024 26 / 8 / 2024 Preparation Work Before Steel Truss Erection
[Link] For Gr.B 18 days 1 3 / 9 / 2024 24 / 9 / 2024
[Link].1 Hand Over From COBC ( Zone 8b - RC Slab )(5/7/2024 COBC Progress ) 1 day 1 3 / 9 / 2024 3 / 9 / 2024 Hand Over From COBC ( Zone 8b - RC Slab )
[Link].2 Site Erection ( With Permanent CFT x 1 no. ) 14 days 17 4 / 9 / 2024 20 / 9 / 2024 Site Erection ( With Permanent CFT x 1 no. )
[Link].3 Preparation Work Before Steel Truss Erection 3 days 4 21 / 9 / 2024 24 / 9 / 2024 Preparation Work Before Steel Truss Erection
1.3 Tower Crane ( TC1 ) 15 days 1 19 / 7 / 2024 5 / 8 / 2024
1.3.1 Revise MS Base on MTR RP Comment 3 days 4 19 / 7 / 2024 22 / 7 / 2024 Revise MS Base on MTR RP Comment
1.3.2 Submit MS and Asking for Advise Approval ( Tentative ) 1 day 1 23 / 7 / 2024 23 / 7 / 2024 Submitt MS and Asking for Advise Approval ( Tentative )
1.3.3 Formal Approval by RP 1 day 1 30 / 7 / 2024 30 / 7 / 2024 Formal Approval by RP
1.3.4 Construct New Soil Location for 500t Crane 7 days 8 24 / 7 / 2024 31 / 7 / 2024 Construct New Soil Location for 500t Crane
1.3.5 Design / Shop Fabrication Steel Protective Barrier for MTR V. Shaft 7 days 8 24 / 7 / 2024 31 / 7 / 2024 Design / Shop Fabrication Steel Protetive Barrier
1.3.6 Site Erection 4 days 1 1 / 8 / 2024 5 / 8 / 2024
[Link] Erect Protective Steel Frame by 500 T Crane 1 day 1 1 / 8 / 2024 1 / 8 / 2024 Curing Time / As Built
[Link] Tower Crane Installation 3 days 4 2 / 8 / 2024 5 / 8 / 2024 Tower Crane
1.4 Pre Work 60 days 1 18 / 6 / 2024 23 / 8 / 2024
1.4.1 Street Light Shortening 1 day 1 18 / 6 / 2024 18 / 6 / 2024 Street Light Shortening
1.4.2 Concrete Footing / Pylon / Working Platform Erection 47 days 1 25 / 6 / 2024 15 / 8 / 2024
[Link] Plate Load Test ( To Verify Extg. Ground Condition ) 11 days 11 25 / 6 / 2024 5 / 7 / 2024 Plate Load Test
[Link] Grouting ( Gap Between Footing / Existing Road )South Side ( 4 nos. of Footing ) 4 days 5 12 / 7 / 2024 16 / 7 / 2024 Grouting
[Link] Pre Load ( 4nos. At South Side / 1no. At North Side ) 28 days 1 15 / 7 / 2024 15 / 8 / 2024
專案: 12-3- 2024 任務 里程碑 專案摘要報告 外部里程碑 期限
日期: 20 / 7 / 2024 分割 摘要 外部任務 進度
Remark : Assume Plate Load Test Result is Positive. 第1頁
Programme no.: GW-HCIF-TSPC-LW-BE-001 Rev.A
Proposed Development AT I.L.9088, Central DATE:20-7-2024
Tentative Short Term Programme
( Lung Wo Road [Link] B~E )
WBS TASK WORKING CALENDAR START FINISH 旬 六月中旬 七月上旬 七月下旬 八月中旬 九月上旬 九月下旬 十月中旬 十一月上 十一月下 十二月中旬
DATE DATE 2/6 9/6 16/6 23/6 30/6 7/7 14/7 21/7 28/7 4/8 11/8 18/8 25/8 1/9 8/9 15/9 22/9 29/9 6/10 3/1 0/1 7/1 3/11 0/1 7/1 4/1 1/12 8/12 5/1 2/1 9/1
[Link].1 South Side ( Footing for TR3 and TR5 ) 4 days 4 15 / 7 / 2024 18 / 7 / 2024 South Side ( Footing for TR3 and TR5 )
[Link].2 North Side ( Footing for TR5 ) 4 days 4 12 / 8 / 2024 15 / 8 / 2024 Nouth Side ( Footing for TR5 )
1.4.3 Erection Working Platform 12 days 13 5 / 8 / 2024 17 / 8 / 2024 Erection Working Platform
1.4.4 Preparation Work Before Steel Truss Erection 11 days 12 12 / 8 / 2024 23 / 8 / 2024 Preparation Work Before Steel Truss Erection
1.5 WSD Flash Water & Salt Water Pipe Diversion ( Tentative ) 32 days 52 6 / 7 / 2024 10 / 8 / 2024
1.5.1 Trial Pit 2 days 2 6 / 7 / 2024 7 / 7 / 2024 Trial Pit
1.5.2 WSD inspection 2 days 2 8 / 7 / 2024 9 / 7 / 2024 WSD inspection
1.5.3 Concrete Plinth 3 days 3 9 / 7 / 2024 11 / 7 / 2024 Concrete Pinth
1.5.4 Pipe Clamp installation 5 days 6 11 / 7 / 2024 16 / 7 / 2024 Pipe Clamp installation
1.5.5 Installation of Water for diversion 12 days 14 13 / 7 / 2024 26 / 7 / 2024 Installation of Water for diversion
1.5.6 Pressure Test for Water Pipe 4 days 5 27 / 7 / 2024 31 / 7 / 2024 Presure Test for Water Pipe
1.5.7 Cleaning of Pipe 1 day 1 1 / 8 / 2024 1 / 8 / 2024 Cleaning of Pipe
1.5.8 Sterilization and take Water Sample 6 days 7 2 / 8 / 2024 8 / 8 / 2024 Sterilization and take Water Sample
1.5.9 Connect by WSD 2 days 2 9 / 8 / 2024 10 / 8 / 2024 Connect by WSD
1.6 Shop Fabrication 90 days 6 / 6 / 2024 14 / 9 / 2024
1.6.1 CFT 33 days 21 3 / 7 / 2024 8 / 8 / 2024
[Link] 3 nos. for Gr. D~E 23 days 25 3 / 7 / 2024 27 / 7 / 2024 CFT Fabrication - 3 nos. for Gr. D~E
[Link] 1no. For Gr. B 22 days 25 15 / 7 / 2024 8 / 8 / 2024 1no. For Gr. B
1.6.2 Steel Truss 90 days 1 6 / 6 / 2024 14 / 9 / 2024
[Link] TR3 / TR4 65 days 1 6 / 6 / 2024 16 / 8 / 2024
[Link].1 Pre- fab. / Fabrication 45 days 49 6 / 6 / 2024 24 / 7 / 2024 TR3 / TR4 - Pre- fab. / Fabrication
[Link].2 Pre assemble 16 days 19 25 / 7 / 2024 12 / 8 / 2024 Pre assemble
[Link].3 Inspection by Relative Party 1 day 1 13 / 8 / 2024 13 / 8 / 2024 Inspection
[Link].4 Dismantle ( Ready for Deliver to Site ) 3 days 3 14 / 8 / 2024 16 / 8 / 2024 Dismantle ( Ready for Deliver to Site )
[Link] TR1 73 days 1 25 / 6 / 2024 14 / 9 / 2024
[Link].1 Fabrication 60 days 67 25 / 6 / 2024 30 / 8 / 2024 TR1 - Fabrication
[Link].2 Pre assemble 12 days 13 2 / 9 / 2024 14 / 9 / 2024 Pre assemble
1.7 Deliver to Site 30 days 1 17 / 8 / 2024 21 / 9 / 2024
1.7.1 By Sea ( Temp. Storage on Tuen Mun ) 30 days 2 17 / 8 / 2024 21 / 9 / 2024
[Link] TR3 / TR4 3 days 4 17 / 8 / 2024 20 / 8 / 2024 Deliver to Site - TR3 / TR4
[Link] TR1 3 days 3 19 / 9 / 2024 21 / 9 / 2024 TR1
1.8 Site Erection ( Detail Schedule Submit Separate ) 36 days 1 27 / 8 / 2024 9 / 10 / 2024
1.8.1 TR3 / TR4 19 days 22 27 / 8 / 2024 17 / 9 / 2024 Site Erection - TR3 / TR4
1.8.2 TR1 12 days 15 25 / 9 / 2024 9 / 10 / 2024
專案: 12-3- 2024 任務 里程碑 專案摘要報告 外部里程碑 期限
日期: 20 / 7 / 2024 分割 摘要 外部任務 進度
Remark : Assume Plate Load Test Result is Positive. 第2頁