Production Planning & Inventory Control Guide
Production Planning & Inventory Control Guide
4232 4232
ME : Mechanical Engineering
Module 8 : Production Planning and Control, Inventory Control,
Operations Research
INDEX
Operations Research
Introduction 81
Linear Programming 83
Simplex Method 92
Transportation Models 105
Notes Assignment Models 138
Network Theory 145
Queuing Theory 153
List of Formulae 159
LMR (Last Minute Revision) 166
Assignment1 174
Assignments
Assignment2 177
Test Paper1 179
Test Papers
Test Paper2 182
Solutions
Inventory Control
Answer Key 197
Assignments
Model Solutions 198
Answer Key 205
Test Papers
Model Solutions 206
Operations Research
Answer Key 212
Assignments
Model Solutions 213
Answer Key 218
Test Papers
Model Solutions 219
Topic 1 : Production Planning and Control
INTRODUCTION
Products are manufactured by the transformation of raw material (in to finished goods).
This is how production is achieved. Planning looks, anticipates possible difficulties and
decides in advance as to how the production, best, be carried out. The control phase
makes sure that the programmed production is constantly maintained.
A production planning and control system has many functions to perform, some, before
the arrival of raw materials and tools and other while the raw material undergoes
processing. The various functions are as follows.
Forecasting
Tool control
Loading
Scheduling
Corrective action
Replanning
a) Forecasting : Estimation of type, quantity and quality of future work.
b) Order writing : Giving authority to one or more persons to undertake a
particular job.
c) Product design : Collection of information regarding specifications, bill of
materials, drawings etc.
d) Process planning : Finding the most economical process of doing a work
and (then) and routing deciding how and where the
work will be done.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.1
Vidyalankar : GATE – ME
SALES FORECASTING
Basic Elements:
The four basic elements of economic data that should be used are:
1) Trends
2) Cycles
3) Seasonal variation
4) Irregular variation
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.2
Notes on Production Planning and Control
d) Delphi method:
A panel of experts is interrogated by a sequence of questionnaires in which the
response to one questionnaire is used to produce the next questionnaire. Any set of
information available to some experts and not others, is thus passed on to the others,
enabling all the experts to have access to all information and arrive at a reliable
consensus. Delphi method has fair to very good accuracy for short and long term
forecasts.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.3
Vidyalankar : GATE – ME
Consider the historical sales figures in table below, which are to be used to construct a
sales forecast for the next year.
Using the fig. shows that the effect of the moving average is to smooth the sales
pattern and it is therefore of more value in establishing trends.
g) Weighted Moving Average Method for forecasting:
In this, the simple moving average gives equal effect to each component of the
moving average, allows any weights to be placed on each element, providing of
course, that the sum of all weights equal to one.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.4
Notes on Production Planning and Control
wi x i
Moving (Awt) =
wi
xi is the actual data value for time period fi and wi is the weightage given for the time
period fi, then weighted average forecast = fi + 1 = ( wi xi ) / wi
Example :
The demand during the months April, May and June are 50, 70 and 65 and the weights
assigned are 1, 2, 3 for these months, what is the forecast for the months of July?
Solution :
50 1 70 2 65 3
Moving average (Awt) =
1 2 3
= 53.33
Solution :
ft+1 = ft + (xt ft )
actual demand (xt) = 100. predicted value ft = 90, = 0.2
forecast for the next period (ft+1) = 90 + 0.2 (100 90)
= 90 + 0.2 x 10
= 92
The size of should be carefully chosen in the light of the stability or variability of actual
sales and is normally from 0.1 to 0.3. This process is called econometric forecasting.
Here, the analyst tries to notify those factors that best explain the level of sales for a
product. Econometric forecasting utilizes correlation and regression techniques.
i) Correlation Analysis:
Correlation Analysis is frequently used if a relationship can be found between sales
and other economic and noneconomic phenomena, such as the national income,
expenditure, population growth and the weather, such forecasting are generally
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.5
Vidyalankar : GATE – ME
concerned with the sales volume for the entire industry. The forecaster arrives at this
company forecast by estimating the company’s share of total industry demand. It
makes use of cause and effect relationship between sales and some other
phenomena that are related to sales. Correlation and regression techniques are used
in casual model.
Sources of correlation data
(i) Economic data (ii) Industry data
Survey of current business Trade Journals
Monthly labour review Annual Survey of Manufacturer
Business Magazines Industrial trade association
Correction coefficient is a measure of the extent to which two variables are
associated. Perhaps the most useful coefficient is the Karl Pearson product moment
correlation coefficient, which is calculated as follows:
(x x)(y y)
coefficient (r) for two variables x and y =
(x x)2 (y y)2
where x is the mean value of all the individual x values and y is the mean values of
all the individual y values.
Fig. Correlation
Example :
A comparison of monthly sales of an expensive item, against the total number of visits
made by salesman during the previous months, yields the following data.
Is the correlation of two variables a good indicator of future sales?
sales (x) 1 3 5 7 11
visits made(y) 2 4 8 9 10
Solution :
x (x x ) (x x )2 y (y y ) (y y )2 (x x )(y y )
1 4.4 19.5 2 4.6 19.5 20.0
3 2.4 5.8 4 2.6 6.9 6.25
5 0.4 0.16 8 +1.4 1.95 0.56
7 +1.6 2.6 9 +2.4 5.8 3.85
11 +5.6 31.5 10 +3.4 11.5 19.6
x = 59.56 y = 33 45.65 50.26
27 33
y =
27 5
x=
5 = 6.6
= 5.4
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.6
Notes on Production Planning and Control
(x x) y y 50.26 5
r= 0.093
(x x)2 y y
2 59.56 45.65
n2
The correlation between the number of salesman visits and the number of sales is 0.09,
which is not sufficient to justify its possible use as a method of short term sales
forecasting.
The regression line for y on x is the best line for calculating values y, i.e. the y
values in fig. (a).
The regression line for x on y is the best line for calculating values of x and is
obtained by minimizing the sum of the squares of errors of estimation, i.e. the x
values in fig. (b).
y bx
a=
n
Similarly the general equation for the linear regression of x on y is
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.7
Vidyalankar : GATE – ME
x=a+by
n xy ( x)( y)
b=
n y2 y
2
x by
a= , n = no of observations
n
Example:
Given the data in table below, find the regression line for prediction of growth and
calculate the growth for a weight value of 50.
Let growth be variable y
Let weight be variable x
y = a + bx
Solution:
Weight Growth
x2 xy
(x) (y)
12 5.5 144 66
18 5.9 324 106.2
24 6.5 576 156
30 7.4 900 222
36 8.2 1296 295.2
42 8.9 1764 373.8
48 8.6 2304 412.8
x = 210 y = 51 x2 = 7308 xy = 1632, n = 7
714
= 0.10119
7056
y bx 51 0.10119x 210
a = =
n 7
= 10.32
now, y = a + b x where x = 50
The regression line provides only an estimate of the value y on x. The uncertainty or
accuracy of the estimate can be assessed by calculating the standard error of y on x,
(Syx)
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.8
Notes on Production Planning and Control
(y y1 )2
Syx = where y = actual value
n2
y1 = estimated trend value calculated from regression equation
Similarly the standard error of the estimate of x on y is given by:
(x x1 )2
Sxy =
n2
Syx or Sxy provides a measure of the closeness of the relationship between the two
variables.
AGGREGATE PLANNING
It refers to the preplanning of production, inventory and work force at broadest levels. It
is based on the expected demand, as an out come of forecasting whenever, the
seasonal demands or sales are characterized by fluctuations. The various strategies
which can be used for absorbing these fluctuations have already have discussed. Data
required for the aggregate planning consists of expected demand, production capacity of
the systems, inventory level at the various stages of manufacturing, cost involved due to
change in man power and inventory carrying costs.
Graphic technique:
The graphic technique is simple and shows clearly the fluctuations in production and
demand. However, it simply compares different alternative plans and by itself does not
generate optimum plan. Moreover, it is a static technique.
Production requirement or production demand for the individual months from January to
June and cumulative production demand from January to June in table.
Months Production Demand Cumulative production
(units) demand (unit)
January 240 240
February 340 580
March 380 960
April 240 1200
May 240 1400
June 100 1540
J+F+M
Shows two plans (1 and 2) which may be employed to meet the actual production
requirements.
Plan 1:
It is shown by firm line in fig. It indicates smooth (level) production rate to meet the target
demand of 1540 units in 6 months. Fluctuation demand entails high inventory costs of
under and overstocks.
Table
1. CD/CN
2. If each worker produces ten pieces
Plan 2:
It is shown by dotted line (fig.) above and it matches exactly the actual production
requirement of each month. Such a plan involves high labour turn over costs and other
work force adjustment costs, but the inventory costs move towards zero.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.10
Notes on Production Planning and Control
The two plans discussed above represent two extreme solutions. The desired solution
will steer a path in between the two in such a way that the total cost becomes minimum.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.11
Vidyalankar : GATE – ME
As the first step of the (linear programming) technique aggregate levels are prepared and
then a model is built to develop the plan. The model takes into considerations various
requirements like under time, over time, inventory back order, sub contracting etc. Figure
below shows a distribution matrix for three periods of sale. Row for sub contracting
production can be added if required.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.12
Notes on Production Planning and Control
In order to find optimum solution consider the distribution matrix of the figure.
where capacities and demands have been shown along with the various cost values. The
costs have been calculated by assuming that
C = Rs 5, r = Rs 25, t = Rs 30 and b = Rs2
The solution of matrix by northwest corner method will show the number of units which
should be assigned to regular production and overtime production in three different
periods in order to minimize the total cost.
PROCESS PLANNING
Process planning means the preparation of work detail plan. It determines the most
economical method of performing an operation or activity.
(i) Information required to do process planning:
Quantity of work to be done along with product specification.
Quality of work to be completed.
Availability of equipments, tools and personnel.
Sequence in which operations will be performed on the raw material.
Standard time for each operation.
When the operations will be performed.
(ii) Process planning Procedure:
Different steps involved are:
(1) Selection of process.
(2) Selection of material.
(3) Selection of Jigs, Fixtures and other special attachments.
(4) Selection of cutting tools and Inspection gauges.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.13
Vidyalankar : GATE – ME
C is constant cost per piece (material, direct labour and overheads) and I is inventory
carrying charge rate per year (between 0.1 and 0.25).
Q
Average inventory =
2
Q
Value of average inventory = C
2
Q
Cost of carrying inventory = CI … (1)
2
R
Number of set ups during a year =
Q
R RS
Cost of set ups = S= … (2)
Q Q
The total cost, T is obtained by adding cost equation (1) and (2)
QCI RS
T= +
2 Q
dT
For T to be minimum, we put 0
dQ
dT CI RS
= 2 0
dQ 2 Q
2RS
Q=
CI
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.14
Notes on Production Planning and Control
Example:
Find the economic batch quantity using the data given below
Set up cost = Rs.20 per set up
Annual requirement or yearly consumption of parts
= 1000
Inventory carrying cost = 10% of value / year
Cost per part = Rs.2
Solution:
Given S = Rs.20, R = 1000, C = Rs.2, I = 10% = 0.1
2 1000 20
Using above derived equation, E.B.Q. = 447 parts
2 0.1
The numbers of batches to be made for manufacturing the parts are
1000
2.24
447
1000
Nearest, 2 batches can be made and therefore the modified EQB = 500
2
SCHEDULING
Scheduling means when and in what sequence the work will be done. It involves
deciding as to when the work will start and in certain duration of time how much work will
be finished. Scheduling deals with orders and machines i.e. it determines which order will
be taken up on which machine and in which department by which operator. It is the
document which authorizes the start of an operation on the shop floor. Scheduling
finalizes the planning phase of production planning and control system.
(i) Aims of the scheduling :
1. Effective material utilizations
2. Rapid response to demands
3. Completion of order before prescribe dead lines
4. Completion of work in minimum time
5. Total cost is minimized
(ii) Information required while designing schedule:
1. Routing Decisions
2. Preplanning Decisions
3. Resources capabilities
4. Resources Availability
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.15
Vidyalankar : GATE – ME
first. If the equal values are in the second column (B), select the one with the
lowest entry in column A first.
Step 3: Cross out the Job assigned and continue the process (repeat steps 1 and 2),
placing the Jobs as scheduled. The resulting sequence will minimize T the total
time required.
Example:
A machine operator has to perform two operations, turning and threading, on number of
different Job. Determine the order in which the jobs can be scheduled to minimize the
total time required to turn out all the jobs.
Excluding 6, the smallest values is turning time of 2 minutes for Job 4 in first column.
Thus we schedule Job 4 first as shown below
4 6
Excluding 4 and 6, two equal minimal values: for job 1 in first column and Job 5 in second
column. According to rules,
4 1 5 6
Excluding column 4, 1, 5 and 6, the smallest value is turning time of 5 minutes for Job 3
in first column.
the schedule Job 3, next to Job 1 and we get the optimal sequence as
4 1 3 2 5 6
We can calculate the elapsed time corresponding to the optimal sequence
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.16
Notes on Production Planning and Control
Thus the minimum elapsed time is 43 minutes. Idle time for turning operation (m/c) is 1
min(from 42nd min or 43 rd minute ) and for threading operation (m/c) is 2 + 4 = 6 minutes
2 from 02 & 4 from 3842 minutes).
To replace the problem by an equivalent problem involving n Jobs and two machines,
these two (fictitious ) machines are denoted by G and H and their corresponding time are
given by
Gi = Ai + Bi, Hi = Bi + Ci
The technique for establishing and maintaining priorities among various jobs of any
project is known as Critical ratio scheduling.
Example:
Determine the order in which the Jobs should be processed in order to minimize the total
time required to turn out all Jobs.
Solution:
Here, min Ai = 2, max Bi = 8, and min Ci = 8. Since min Ci = max Bi, we can solve this
example by the procedure described in above.
The problem can be replaced by the equivalent problem involving 6 jobs and two fictitious
machines G and H
Examining the columns Gi and Hi we find that smallest value is 8 min under operation Gi.
Thus we schedule Job 4 first on machine G.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.17
Vidyalankar : GATE – ME
Excluding job 4, the next smallest value 9 under column Gi for Job 3, hence we schedule
Job 3 as shown.
4 3
Excluding 4 and 3 jobs, there are two equal minimal value processing time 11 minutes
under column G for Job 1 and processing time of 11 minutes under column Hi for Job 5
these are then scheduled as
4 3 1 5
Excluding the above scheduled row, the smallest value 14 is under column H for 6.
Hence we schedule Job 6 next to job 1 and optimal sequence becomes
4 3 1 6 2 5
Thus the minimum elapsed time is 77 minutes. Idle time for turning operation is
77 42 = 35 minutes, for threading operation is 2 + 1 + 11 + 3 + (77 45) = 17 + 32 = 49
minutes and for knurling operation is 8 minutes.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.18
Notes on Production Planning and Control
Table
Machine times for n jobs and K machines
Job A B C … K
1 A1 B1 C1 … K1
2 A2 B2 C2 … K2
3 A3 B3 C3 … K3
: : : : .
i Ai Bi Ci … Ki
: : : : .
n An Bn Cn … Kn
To find the optimum sequence of Jobs which minimizes time, no general solution is
available at present for such a case. However above solution can be applied to cover
the special cases where either one or both of the following condition hold good (it
neither of the conditions holds good, the method fails).
(a) The minimum time on machine A is maximum time on machine B, C, . . . . k
1.
(b) The minimum time on machine k is maximum time on machines B,C, . . . . k
1.
The method is to replace the K machine problem by an equivalent two machine
problem. These two (fictitious) machines are denoted by a and b and their
corresponding processing times are given by ai = Ai + Bi + . . . . . + (K 1)
bi = Bi + Ci + . . . . . + (K 1)i + Ki
The resulting optimal sequence with prescribed order a b is solved by the method of
above, the resulting optimal sequence will also be optimal for the original problem ,
Further, if Bi + Ci + . . . . . + (K 1)i = K
Where K is a fixed positive constant for all Jobs (i = 1, 2, 3, . . . . . , n) then the given
problem can be solved simply as n Job two machine problem.
Example:
Find the total minimum elapsed time if no passing of jobs is permitted
M/ C
A B C D E
Job
1 7 5 2 3 9
2 6 6 4 5 10
3 5 4 5 6 8
4 8 3 3 2 6
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.19
Vidyalankar : GATE – ME
Solution :
Here min Ai = 5, min Ei = 6 and max (Bi, Ci, Di ) = 6, 5, 6 respectively. Since min Ei = max
(Bi, Di) we can also solve this problem by the procedure described in above. The
equivalent problem involving 4 Jobs and 2 fictious machines a and b becomes
1 3 2 4
M/ C
A B C D E
Job
1 07 712 1214 1417 1726
Thus the minimum elapsed times is 51 time units. Machines A, B, C, D and E remain idle
for 25, 33, 37, 35 and 18 units respectively.
ROUTING
Routing lays down the flow of work in the plant. It determines what works is to be done
and where and how it will be done i.e. authorization of work to be performed. Taking from
raw material to the finished product, routing decides the path and sequence of operations
to be performed on the Job from one machine to another. The purpose is to establish the
optimum sequence of operation.
Routing Procedure:
1. Manufacturing type Mass /flow production, Job, Batch production.
2. Availability of Resource like plant, machineries and facilities.
3. Process involved.
4. Characteristics of machineries, plant and facilities.
Route sheet can be made to include many activities like authority to production, materials
requirement, tool orders and move order etc. first two columns of route sheet show the
manufacturing route for given component.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.20
Notes on Production Planning and Control
PROGRESS CONTROL
Progress control means trying to achieve the standard set, i.e. a certain level of efficiency
or a certain volume of production in specified duration. The system of progress control
should be such that it furnishes timely, adequate and accurate information about the
progress made, delays and under or over loading.
Steps involved in progress control
(a) Setting up a system to watch and record the progress of the operating facility.
(b) Transmission of report to
1. Control group for necessary control active and
2. Accounting group for recording material and labour expenditures.
(c) Making a report of the work progress or work accomplishment.
(d) Interpretation of the information contained in the progress report by the control group.
(e) Taking corrective action, if necessary.
System to Record the work Accomplishment:
Progress charts are normally employed for this purpose. They compare the work
progress against a prescribed target and point out the failure to achieve the same.
(1) The Bar chart: consists of number of bars. Each bar has its length proportional to the
activity duration. A bar chart is generally used to point out and analyze interrelated
data which otherwise is difficult to read.
(2) A curve chart: It is a graph between two variable (like, number of days and number of
items produced) marked along x and y axis. As the day pass, the number of items being
produced are marked over the graph such points are joined they indicate the
production trend.
]
Fig. A curve chart
[
(3) The Gnatt chart: developed by Henry L. Gnatt. It is frequently used to keep track of
multiple machine schedules. Gnatt chart is actually a modified bar chart, where in load is
marked against a time scale with one horizontal bar or line. Gnatt chart is useful for
scheduling & control and provides information about production schedule.
Two basic types of Gnatt chart:
(i) Order control chart
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.22
Notes on Production Planning and Control
(4) Mechanical charts: They include wall charts, visible index files and other scheduling
devices like product Tool board, Board master, schedule U Graph etc which are
commercially available. These equipments have added signaling devices likes pages,
strings, clips etc. to focus the attention on the situations needing corrective action.
DISPATCHING
Dispatch function executes planning function. It is concerned with getting the work
started. Dispatch ensures that the plans are properly implemented. Dispatch function
determines by whom the job shall be done and it coordinates production. It is the key
point of a production communication system. It creates a direct link between production
and sales.
Dispatch procedure:
The various steps of dispatch procedure for each operation are listed below in sequence:
(a) Store issue order:
Authorized store (department) to deliver required raw material.
(b) Tool order:
Authorize tool store to release the necessary tools. The tools can be collected by the
tool room attached.
(c) Job order:
Instruct the worker to proceed with the operation.
(d) Time ticket:
It records the beginning and ending time of operation and forms the basis for workers
pay.
(e) Inspection order:
Notify the inspectors to carry out necessary inspections and report the quality of the
component.
(f) Move order:
Authorize the movement of materials and components from one facility (machine) to
another for further operation.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.23
Vidyalankar : GATE – ME
Dispatching rule:
(1) SPT rule:
Shortest processing time (SPT) means that sequencing of jobs in the ascending
order of their processing time. Priority is given to the Job which has shortest
processing time in the machine under consideration.
Properties: (1) Mean flow time minimizes.
(2) In process inventory minimizes.
(3) Mean waiting time minimizes.
(4) It is more superior, most powerful comparatively effective dispatching
rule.
Example :
Five Jobs are processed in a single machine and the data are as follows:
Job (i) 1 2 3 4 5
Processing time (ti) 4 5 7 1 3
Due date (di) 7 20 16 5 6
(a) Determine the sequence of Jobs as per rule
(b) Determine the mean flow time?
(c) Determine (i) Mean lateness (ii) Mean tardiness (iii) in process inventory (iv) No. of
tardy Jobs?
Solution:
Single machine model. Assigning the first Job which has least processing time that is Job
4 and time is 1. Leaving the assigned Job, the next least processing time is Job 5 with
time 3. Similarly assigning the other Job.
Job 4 5 1 2 3
0 1 4 8 13 20
Flow time
(b) SPT sequences: 4 5 1 2 3
Flow time : Fi = Fi 1 + ti
Job lateness Li = Fi di ( due date)
Tardiness : Ti = Li when Li is + ve
= 0 when Li is negative or zero
mean flow time F = ( Fi ) /n = 46/5 = 9.20
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.24
Notes on Production Planning and Control
Properties of EDD:
(a) The maximum tardiness is minimized.
(b) The maximum lateness is minimized
(c) Processing time of the Job is independent
(d) The EDD sequence for single machine model yields only one tardy Job.
Example:
Taking the last problem and sequencing by EDD rule.
Job (i) 1 2 3 4 5
Processing time (ti) 4 5 7 1 3
Due date (di ) 7 20 16 5 6
Solution:
Ascending order of due dates = 5, 6, 7, 16, 20,
EDD sequence : 4 5 1 3 2
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.25
Vidyalankar : GATE – ME
The benefit of MRP is that it enables the firm to overcome uncertainties to eliminate
safety stocks and also reduce carrying the inventory.
The characteristic life cycle of a product consists of 4 periods. The rate of consumption
increases rapidly at the beginning of the maturity period.
LIST OF FORMULAE
WX
Weighted moving average (Awt) = i i
Wi
Xi is the actual data value for time period and Wi is the weightage given for the time
period ti .
The weighted Average forecast = Fi + 1 = ( Wi X i) / Wi
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.26
Notes on Production Planning and Control
x x y y n
Coefficient of correlation , r =
x x y y
2 2
where x is the mean value of all the individual x values and y is the mean values of
all the individual y values.
y b x
a=
n
n = no. of observations.
For x = a + b y,
n xy ( x)( y)
b=
n y2 y 2
x by
a=
n
2
y yi
Standard error Syx = estimates the standard error of y on x, where y =
n2
actual value
yi = estimates the end value calculated from equation of regression
2
x xi
Sxy = determines the standard error of x on y.
n2
Coefficient of determination
Explained variation
=
Total variation
y 2 a y b xy
Standard deviation, SD =
n2
Coefficient of determination
a y b xy ny 2
r2=
y 2 ny 2
(yi y)2 explained variation
=
(y y)2 total variation
Where yi = estimated trend value calculated from regression equation.
Coefficient of correlation, r = r2
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.27
Vidyalankar : GATE – ME
P 1 p
Accuracy = , p = precision
N
Number of random observation
1 p p
N = K2
s.p
2
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.28
Notes on Production Planning and Control
Aggregate Planning refers to the pre planning of production, inventory and work force
at broadest levels.
Linear Regression Analysis: This method is a very useful forecasting technique if
past data appear to fall about a straight line.
Process planning means the preparation of work detail plan. It determines the most
economical method of performing an operation or activity.
Scheduling means when and in what sequence the work will be done. Scheduling
deals with orders and machines.
Earliest Due date (EDD) rule: Priority is given to Jobs which have minimum value of
due date. Job sequencing is in the order of ascending order of due dates from lowest
to highest due dates.
MRP is a method for coordinating multistage production system that involves many
subassemblies, products, components and raw material, so that they are made
available at time schedule.
GATE/ME/SLP/Module_8/Ch.1_Notes /Pg.29
Vidyalankar : GATE – ME
ASSIGNMENT 1
Duration : 45 Min. Max. Marks : 30
Q1 to Q6 carry one mark each
7. The characteristics life cycle of a product consists of four periods. The rate of
consumptions increases rapidly at the beginning of the
(A) incubation period (B) growth period
(C) maturity period (D) decline period
8. The forecast trend of sugar for the month of July is 400 tonnes. The seasonal
indices for the months June, July, August and September are 0.5, 1.5, 0.8 and
0.9 respectively. The forecast for the sugar demand is
(A) 1000 tonnes (B) 600 tonnes
(C) 1600 tonnes (D) 1500 tonnes
GATE/ME/SLP/Module_8/Ch.1_Assign /Pg.30
Assignment on Production Planning and Control
9. Sales data of demand for the months May, June, July and August are 11, 10, 12
and 14 thousand rupees. The forecasted sales for the month of September by
three periods moving average is
(A) Rs. 14000 (B) Rs. 15000
(C) Rs. 16000 (D) Rs. 12000
12. Suppose X is a normal random variable with mean 0 and variance 4. Then the
mean of the absolute value of X is
1 2 2
(A) (B)
2
2 2 2
(C) (D)
13. The data on monthly sales are as 80, 70, 80, 90, 80, 100, 85, 60 and 75
respectively for past nine months. The forecast for the 9th month is taken as
average, what is the forecast for the 10th month by exponential smoothing?
(A) 80 (B) 85
(C) 79 (D) 70
14. In a time series forecasting model, the demand for five time periods was 10, 13,
15, 18 and 22. A linear regression fit resulted in an equation F = 6.9 + 2.9 t where
F is the forecast for period t. The sum of absolute deviations for the five data is
(A) 2.2 (B) .2
(C) -1.2 (D) 24.3
15. For a product, the forecast and the actual sales for December 2002 were 25 and
20 respectively. If the exponential smoothing constant () is taken as 0.2, the
forecast sales for January 2003 would be
(A) 21 (B) 23
(C) 24 (D) 27
16. A component can be produced by any of the four processes I, II, III and IV.
Process I has a fixed cost of Rs. 20 and variable cost of Rs.3 per piece. Process
II has a fixed cost of Rs.50 and variable cost of Re.1 per piece. Process III has a
fixed cost of Rs.40 and variable cost of Rs.2 per piece. Process IV has a fixed
cost of Rs.10 and variable cost of Rs.4 per piece. If the company wishes to
produce 100 pieces of the component, from economic point of view it should
choose
(A) Process I (B) Process II
(C) Process III (D) Process IV
GATE/ME/SLP/Module_8/Ch.1_Assign /Pg.31
Vidyalankar : GATE – ME
17. A washing machine firm has been using a 12 month moving average of monthly
demand. The March month forecast made was 950 units, but the actual
demand is found to be 1000 units. Hence they want to convert to exponential
smoothing model for the forecast for April. What would be their forecast for April?
(A) 957.50 (B) 958.68
(C) 957.00 (D) 960.00
18. A firm has developed a seasonal index for the various months in a year, for their
product. The seasonal index for August and September is as 1.08 and 1.20
respectively. The old forecast sales are for an average of 500 units per month. The
firm uses exponential smoothing for forecast with = 0.1. If the actual sales for
August is 450 units, what is the forecast for September?
(A) 600.0 (B) 650.00
(C) 590.00 (D) 550.00
GATE/ME/SLP/Module_8/Ch.1_Assign /Pg.32
Vidyalankar : GATE – ME
TEST PAPER 1
GATE/ME/SLP/Module_8/Ch.1_Test /Pg.36
Test on Production Planning and Control
7. If one state occurred four times in hundred observations while using the work
sampling technique, then precision of the study using as 95% confidence level
will be
(A) 90% (B) 95%
(C) 92% (D) 98%
8. Match list I (methods) with list II (problems) and select the correct answer
using the codes given below the lists:
11. In a study to estimate the idle time of a machine out of 100 random observations,
the machine is found idle on 40 observations. The total random observations
required for 95% confidence level and 5 % accuracy are
(A) 384 (B) 600
(C) 12000 (D) 9600
12. Match List I and II and select the correct answer using the codes given below the
lists
a. Decision making under complete 1. Delphi approach
certainty
b. Decision making under risk 2. Maxi max criterion
c. Decision making under complete 3. Transportation model
uncertainty.
d. Decision making based on expert 4. Decision free
opinion.
GATE/ME/SLP/Module_8/Ch.1_Test /Pg.37
Vidyalankar : GATE – ME
Code a b c d
(A) 3 4 1 2
(B) 4 3 2 1
(C) 3 4 2 1
(D) 4 3 1 2
13. XYZ firm uses exponential smoothing with = 0.1 to forecast, the demand of
their products. The forecast for January was 500 units whereas actual demand
turned out to be 450 units, if the trend forecast for February with smoothing
constant for trend is = 0.2. What is trend adjusted forecast for March?
(A) 504.8 (B) 550.8
(C) 514.8 (D) 510.8
14(b). For above problem, if the actual demand for February turned out to be 505 units,
what would be the forecast for March?
(A) 500 (B) 560
(C) 496 (D) 450
GATE/ME/SLP/Module_8/Ch.1_Test /Pg.38