0% found this document useful (0 votes)
606 views7 pages

All Plinth Area Rates (RCE)

Uploaded by

rahimbuxaen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
606 views7 pages

All Plinth Area Rates (RCE)

Uploaded by

rahimbuxaen
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

FORMULATION OF NEW PLINTH AREA RATES ON THE BASIS OF COMPOSITE SCHEDULE OF RATE 2024

CONSTRUCTION OF EDUCATIONAL BUILDING


FRAMED STRUCTURES
Name of Bldgs /
Plinth Area Unit Civil Work W/S & S/F Internal Electtrification Internal Sui Gas Total
S-# Estimates
Rate Amount Rate Amount Rate Amount Rate Amount
1 2 3 4 5 6 7 8 9 10 11 12 13

Main Building
1 Foundation 14,770.90 Sft 1,795.00 26513765.5 - - - - - - 26513765.50

2 Ground Floor 14,770.90 Sft 3,960.00 58492764.00 300.00 4431270.00 480.00 7090032.00 120.00 1,772,508.00 71,786,574.00

Total 98,300,339.50

Services
3 UG Tank 3000 Gln 260 780000.00 780000.00
4 Overhead Tank 1000 Gln 350 350000.00 350000.00

Total 1130000.00

Grand Total 99,430,339.50


6,731.50
Construction Rate Per Sft 6731.5
FORMULATION OF NEW PLINTH AREA RATES ON THE BASIS OF COMPOSITE SCHEDULE OF RATE 2024
CONSTRUCTION OF HOSPITAL BUILDING
FRAMED STRUCTURES
Name of Bldgs /
Plinth Area Unit Civil Work W/S & S/F Internal Electtrification Internal Sui Gas Total
S-# Estimates
Rate Amount Rate Amount Rate Amount Rate Amount
1 2 3 4 5 6 7 8 9 10 11 12 13

Main Building
1 Foundation 13,500.00 Sft 1,795.00 24232500 - - - - - - 24232500.00

2 Ground Floor 13,500.00 Sft 3,960.00 53460000.00 300.00 4050000.00 480.00 6480000.00 120.00 1,620,000.00 65,610,000.00

Total 89,842,500.00

Services
3 UG Tank 3000 Gln 260 780000.00 780000.00
4 Overhead Tank 1000 Gln 350 350000.00 350000.00

Total 1130000.00

Grand Total 90,972,500.00


6,738.70
Construction Rate Per Sft 6,738.70
FORMULATION OF NEW PLINTH AREA RATES ON THE BASIS OF COMPOSITE SCHEDULE OF RATE 2024
CONSTRUCTION OF OFFICE / RESIDENTIAL BUILDINGS
FRAMED STRUCTURES
Name of Bldgs /
Plinth Area Unit Civil Work W/S & S/F Internal Electtrification Internal Sui Gas Total
S-# Estimates
Rate Amount Rate Amount Rate Amount Rate Amount
1 2 3 4 5 6 7 8 9 10 11 12 13

Main Building
1 Foundation 6,600.00 Sft 1,800.00 11880000 - - - - - - 11880000.00

2 Ground Floor 6,600.00 Sft 4,100.00 27060000.00 300.00 1980000.00 480.00 3168000.00 120.00 792,000.00 33,000,000.00

Total 44,880,000.00

Services
3 UG Tank 3000 Gln 260 780000.00 780000.00
4 Overhead Tank 1000 Gln 350 350000.00 350000.00

Total 1130000.00

Grand Total 46,010,000.00


6,971.21
Construction Rate Per Sft 6,971.21
FORMULATION OF NEW PLINTH AREA RATES ON THE BASIS OF COMPOSITE SCHEDULE OF RATE 2024
CONSTRUCTION OF COURT BUILDINGS
FRAMED STRUCTURES
Name of Bldgs /
Plinth Area Unit Civil Work W/S & S/F Internal Electtrification Internal Sui Gas Total
S-# Estimates
Rate Amount Rate Amount Rate Amount Rate Amount
1 2 3 4 5 6 7 8 9 10 11 12 13

Main Building
1 Foundation 9,900.00 Sft 2,200.00 21780000 - - - - - - 21780000.00

2 Ground Floor 9,900.00 Sft 4,300.00 42570000.00 300.00 2970000.00 480.00 4752000.00 120.00 1,188,000.00 51,480,000.00
(Court Height 16' including stage and wooden railing)
Total 73,260,000.00

Services
3 UG Tank 3000 Gln 260 780000.00 780000.00
4 Overhead Tank 1000 Gln 350 350000.00 350000.00

1130000.00

Grand Total 74,390,000.00


7,514.14
Construction Rate Per Sft 7,514.14
FORMULATION OF NEW PLINTH AREA RATES ON THE BASIS OF COMPOSITE SCHEDULE OF RATE 2024
CONSTRUCTION OF OFFICE / RESIDENTIAL BUILDINGS
LOAD BEARING STRUCTURES
Name of Bldgs /
Plinth Area Unit Civil Work W/S & S/F Internal Electtrification Internal Sui Gas Total
S-# Estimates
Rate Amount Rate Amount Rate Amount Rate Amount
1 2 3 4 5 6 7 8 9 10 11 12 13

Main Building
1 Foundation 6,600.00 Sft 996.00 6573600 - - - - - - 6573600.00

2 Ground Floor 6,600.00 Sft 4,100.00 27060000.00 300.00 1980000.00 480.00 3168000.00 120.00 792,000.00 33,000,000.00

Total 39,573,600.00

Services
3 UG Tank 3000 Gln 260 780000.00 780000.00
4 Overhead Tank 1000 Gln 350 350000.00 350000.00

Total 1130000.00

Grand Total 40,703,600.00


6,167.21
Construction Rate Per Sft 6,167.21
FORMULATION OF NEW PLINTH AREA RATES ON THE BASIS OF COMPOSITE SCHEDULE OF RATE 2024
CONSTRUCTION OF HOSPITAL BUILDING
LOAD BEARING STRUCTURES
Name of Bldgs /
Plinth Area Unit Civil Work W/S & S/F Internal Electtrification Internal Sui Gas Total
S-# Estimates
Rate Amount Rate Amount Rate Amount Rate Amount
1 2 3 4 5 6 7 8 9 10 11 12 13

Main Building
1 Foundation 13,500.00 Sft 1,644.00 22194000 - - - - - - 22194000.00

2 Ground Floor 13,500.00 Sft 3,960.00 53460000.00 300.00 4050000.00 480.00 6480000.00 120.00 1,620,000.00 65,610,000.00

Total 87,804,000.00

Services
3 UG Tank 3000 Gln 260 780000.00 780000.00
4 Overhead Tank 1000 Gln 350 350000.00 350000.00

Total 1130000.00

Grand Total 88,934,000.00


6,587.70
Construction Rate Per Sft 6,587.70
FORMULATION OF NEW PLINTH AREA RATES ON THE BASIS OF COMPOSITE SCHEDULE OF RATE 2024
CONSTRUCTION OF EDUCATIONAL BUILDING
LOAD BEARING STRUCTURES
Name of Bldgs /
Plinth Area Unit Civil Work W/S & S/F Internal Electtrification Internal Sui Gas Total
S-# Estimates
Rate Amount Rate Amount Rate Amount Rate Amount
1 2 3 4 5 6 7 8 9 10 11 12 13

Main Building
1 Foundation 14,770.00 Sft 840.00 12406800 - - - - - - 12406800.00

2 Ground Floor 14,770.00 Sft 3,960.00 58489200.00 300.00 4431000.00 480.00 7089600.00 120.00 1,772,400.00 71,782,200.00

Total 84,189,000.00

Services
3 UG Tank 3000 Gln 260 780000.00 780000.00
4 Overhead Tank 1000 Gln 350 350000.00 350000.00

Total 1130000.00

Grand Total 85,319,000.00


5,776.15
Construction Rate Per Sft 5,776.15