Contractor Evaluation Summary
Contractor Evaluation Summary
WEIGHTED ACTUAL
No. PARTICULARS REMARKS
PERCENTAGE RATINGS
1. WORKMANSHIP
1.1 Contract Documents Verifiaction Checklist 20 10
1.1.1 With Approved Plans 5 5
1.1.2 Contract Administration Documents, PCAB license, etc. 5 5
1.1.3 Approved Reports Submitted (such as SWA & Accomplishment Report, S-Curve,
variation Order, Time Extension, Suspension/Resumption 5 0
No report presented
1.1.4 Materials Test Results (Concrete, RSB, FDT) 5 0
1.2 Project Site Verification Checklist 20 0
1.2.1 Project In-Charge maintaned logbook for daily activitties 4 0
1.2.2 Canal alligned, marked with stationing, correct elevation 4 0
1.2.3 Formworks in Good Condition 4 0 No accomplishment on site
1.2.4 Embankment/Backfill satisfactory (attach picture) 4 0
1.2.5 Concrete works satisfactory including curing pond, molds, samples, RSB 4 0
2. MATERIALS 30 0
2.1 Cement (Portland Type I) 8 0
2.2 Aggregates are clean and well graded 8 0
2.3 Reinforced Steel Bar 8 0 No materials on site
2.4 Water used for concrete mix is clean 3 0
2.5 Suitable material for backfill and embankments 3 0
3. TIME 15 8
3.1 Project accomplishment is based on approved PERT/CPM 7.5 4 Negative slippage of 12% based on
3.2 Project is ahead/delayed 7.5 4 Status of Infra as of March 15, 2023
4. ENVIRONMENTAAL SAFETY AND HEALTH
4.1 Environmental 3 0
4.1.1 Waste material collected, stored and transported to approved dumpsite/disposal 3 0 Not available on site
area.
4.2 Safety and Health 4 0
4.2.1 Approved PPE's (helmets, safety shoes, safety belt, eye protection, dust mask,
face mask) are provided/worn by workers 1 0
Resource Persons/Witness:
Evaluated by:
WEIGHTED ACTUAL
No. PARTICULARS REMARKS
PERCENTAGE RATINGS
1. WORKMANSHIP
1.1 Contract Documents Verifiaction Checklist 20 13
1.1.3 Approved Reports Submitted (such as SWA & Accomplishment Report, S-Curve,
variation Order, Time Extension, Suspension/Resumption 5 3 No updated Variation Order
1.1.4 Materials Test Results (Concrete, RSB, FDT) 5 0 No test result presented
1.2 Project Site Verification Checklist 20 15
1.2.1 Project In-Charge maintaned logbook for daily activitties 4 3 No logbook presented
1.2.2 Canal alligned, marked with stationing, correct elevation 4 4
1.2.3 Formworks in Good Condition 4 4
1.2.4 Embankment/Backfill satisfactory (attach picture) 4 4
1.2.5 Concrete works satisfactory including curing pond, molds, samples, RSB Absence of curing pond and cylindrical
4 0
molder
2. MATERIALS 30 30
2.1 Cement (Portland Type I) 8 8
2.2 Aggregates are clean and well graded 8 8
2.3 Reinforced Steel Bar 8 8
2.4 Water used for concrete mix is clean 3 3
2.5 Suitable material for backfill and embankments 3 3
3. TIME 15 0
3.1 Project accomplishment is based on approved PERT/CPM 7.5 0 Negative slippage of 30.93% based on
3.2 Project is ahead/delayed 7.5 0 Status of Infra as of March 15, 2023
4. ENVIRONMENTAAL SAFETY AND HEALTH
4.1 Environmental 3 3
4.1.1 Waste material collected, stored and transported to approved dumpsite/disposal 3 3
area.
4.2 Safety and Health 4 2.7
4.2.1 Approved PPE's (helmets, safety shoes, safety belt, eye protection, dust mask,
face mask) are provided/worn by workers 1 1
Resource Persons/Witness:
Evaluated by:
WEIGHTED ACTUAL
No. PARTICULARS REMARKS
PERCENTAGE RATINGS
1. WORKMANSHIP
1.1 Contract Documents Verifiaction Checklist 20 13
1.1.1 With Approved Plans 5 5
1.1.2 Contract Administration Documents, PCAB license, etc. 5 5
1.1.3 Approved Reports Submitted (such as SWA & Accomplishment Report, S-Curve,
variation Order, Time Extension, Suspension/Resumption 5 3 No updated Variation Order
1.1.4 Materials Test Results (Concrete, RSB, FDT) 5 0 No test result presented
1.2 Project Site Verification Checklist 20 13
1.2.1 Project In-Charge maintaned logbook for daily activitties 4 3 No logbook presented
1.2.2 Canal alligned, marked with stationing, correct elevation 4 3 Old formworks we're used resulting in
1.2.3 Formworks in Good Condition 4 3 bulging of canal sidings.
1.2.4 Embankment/Backfill satisfactory (attach picture) 4 4
1.2.5 Concrete works satisfactory including curing pond, molds, samples, RSB 4 0 Not available on site
2. MATERIALS 30 30
2.1 Cement (Portland Type I) 8 8
2.2 Aggregates are clean and well graded 8 8
2.3 Reinforced Steel Bar 8 8
2.4 Water used for concrete mix is clean 3 3
2.5 Suitable material for backfill and embankments 3 3
3. TIME 15 0
3.1 Project accomplishment is based on approved PERT/CPM 7.5 0 Negative slippage of 28.17% based on
3.2 Project is ahead/delayed 7.5 0 Status of Infra as of March 15, 2023
4. ENVIRONMENTAAL SAFETY AND HEALTH
4.1 Environmental 3 2
4.1.1 Waste material collected, stored and transported to approved dumpsite/disposal
3 2 Improper disposal of used formworks
area.
4.2 Safety and Health 4 1.7
4.2.1 Approved PPE's (helmets, safety shoes, safety belt, eye protection, dust mask,
face mask) are provided/worn by workers 1 0 No on-going civil work
Resource Persons/Witness:
Evaluated by:
WEIGHTED ACTUAL
No. PARTICULARS REMARKS
PERCENTAGE RATINGS
1. WORKMANSHIP
1.1 Contract Documents Verifiaction Checklist 20 20
1.1.1 With Approved Plans 5 5
1.1.2 Contract Administration Documents, PCAB license, etc. 5 5
1.1.3 Approved Reports Submitted (such as SWA & Accomplishment Report, S-Curve,
variation Order, Time Extension, Suspension/Resumption 5 5
1.1.4 Materials Test Results (Concrete, RSB, FDT) 5 5
1.2 Project Site Verification Checklist 20 17
1.2.1 Project In-Charge maintaned logbook for daily activitties 4 3 No logbook presented
1.2.2 Canal alligned, marked with stationing, correct elevation 4 3 No marked stationing
1.2.3 Formworks in Good Condition 4 4
1.2.4 Embankment/Backfill satisfactory (attach picture) 4 3
1.2.5 Concrete works satisfactory including curing pond, molds, samples, RSB 4 4
2. MATERIALS 30 30
2.1 Cement (Portland Type I) 8 8
2.2 Aggregates are clean and well graded 8 8
2.3 Reinforced Steel Bar 8 8
2.4 Water used for concrete mix is clean 3 3
2.5 Suitable material for backfill and embankments 3 3
3. TIME 15 15
3.1 Project accomplishment is based on approved PERT/CPM 7.5 7.5
3.2 Project is ahead/delayed 7.5 7.5
4. ENVIRONMENTAAL SAFETY AND HEALTH
4.1 Environmental 3 3
4.1.1 Waste material collected, stored and transported to approved dumpsite/disposal 3 3
area.
4.2 Safety and Health 4 4
4.2.1 Approved PPE's (helmets, safety shoes, safety belt, eye protection, dust mask,
face mask) are provided/worn by workers 1 1
Resource Persons/Witness:
Evaluated by:
WEIGHTED ACTUAL
No. PARTICULARS REMARKS
PERCENTAGE RATINGS
1. WORKMANSHIP
1.1 Contract Documents Verifiaction Checklist 20 18
No approved plans when project
1.1.1 With Approved Plans 5 3
commenced
1.1.2 Contract Administration Documents, PCAB license, etc. 5 5
1.1.3 Approved Reports Submitted (such as SWA & Accomplishment Report, S-Curve,
variation Order, Time Extension, Suspension/Resumption 5 5
1.1.4 Materials Test Results (Concrete, RSB, FDT) 5 5
1.2 Project Site Verification Checklist 20 19
1.2.1 Project In-Charge maintaned logbook for daily activitties 4 3 No logbook presented
1.2.2 Canal alligned, marked with stationing, correct elevation 4 4
1.2.3 Formworks in Good Condition 4 4
1.2.4 Embankment/Backfill satisfactory (attach picture) 4 4
1.2.5 Concrete works satisfactory including curing pond, molds, samples, RSB 4 4
2. MATERIALS 30 30
2.1 Cement (Portland Type I) 8 8
2.2 Aggregates are clean and well graded 8 8
2.3 Reinforced Steel Bar 8 8
2.4 Water used for concrete mix is clean 3 3
2.5 Suitable material for backfill and embankments 3 3
3. TIME 15 15
3.1 Project accomplishment is based on approved PERT/CPM 7.5 7.5
3.2 Project is ahead/delayed 7.5 7.5
4. ENVIRONMENTAAL SAFETY AND HEALTH
4.1 Environmental 3 3
4.1.1 Waste material collected, stored and transported to approved dumpsite/disposal 3 3
area.
4.2 Safety and Health 4 4
4.2.1 Approved PPE's (helmets, safety shoes, safety belt, eye protection, dust mask,
face mask) are provided/worn by workers 1 1
Resource Persons/Witness:
Evaluated by:
WEIGHTED ACTUAL
No. PARTICULARS REMARKS
PERCENTAGE RATINGS
1. WORKMANSHIP
1.1 Contract Documents Verifiaction Checklist 20 16
1.1.1 With Approved Plans 5 3 No updated plans as per variation order
1.1.2 Contract Administration Documents, PCAB license, etc. 5 5
1.1.3 Approved Reports Submitted (such as SWA & Accomplishment Report, S-Curve,
variation Order, Time Extension, Suspension/Resumption 5 3 Reports presented are not updated
1.1.4 Materials Test Results (Concrete, RSB, FDT) 5 5
1.2 Project Site Verification Checklist 20 16
1.2.1 Project In-Charge maintaned logbook for daily activitties 4 4
No stationing and sudden drop in
1.2.2 Canal alligned, marked with stationing, correct elevation 4 2
elevations
Honeycombs are present in some
1.2.3 Formworks in Good Condition 4 2
portion of the canal lining
1.2.4 Embankment/Backfill satisfactory (attach picture) 4 4
1.2.5 Concrete works satisfactory including curing pond, molds, samples, RSB 4 4
2. MATERIALS 30 30
2.1 Cement (Portland Type I) 8 8
2.2 Aggregates are clean and well graded 8 8
2.3 Reinforced Steel Bar 8 8
2.4 Water used for concrete mix is clean 3 3
2.5 Suitable material for backfill and embankments 3 3
3. TIME 15 12.5
3.1 Project accomplishment is based on approved PERT/CPM 7.5 7.5
3.2 Project is ahead/delayed 7.5 5 With liquidated damages
4. ENVIRONMENTAAL SAFETY AND HEALTH
4.1 Environmental 3 3
4.1.1 Waste material collected, stored and transported to approved dumpsite/disposal 3 3
area.
4.2 Safety and Health 4 4
4.2.1 Approved PPE's (helmets, safety shoes, safety belt, eye protection, dust mask,
face mask) are provided/worn by workers 1 1
Resource Persons/Witness:
WEIGHTED ACTUAL
No. PARTICULARS REMARKS
PERCENTAGE RATINGS
1. WORKMANSHIP
1.1 Contract Documents Verifiaction Checklist 20
1.1.1 With Approved Plans 5
1.1.2 Contract Administration Documents, PCAB license, etc. 5
1.1.3 Approved Reports Submitted (such as SWA & Accomplishment Report, S-Curve,
variation Order, Time Extension, Suspension/Resumption 5
Resource Persons/Witness:
Contractor's Representative
Evaluated by: