Construction Project Updates

The document outlines the pending utility balance work with specific tasks, their progress status, remarks, and target completion dates. Key tasks include primer work, plastering, plumbing, and brick work, with several activities facing manpower issues or dependencies on other work. The target dates for completion range from December 10 to December 20, 2024, with some tasks not yet started.

Uploaded by

Anup
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views1 page

Construction Project Updates

The document outlines the pending utility balance work with specific tasks, their progress status, remarks, and target completion dates. Key tasks include primer work, plastering, plumbing, and brick work, with several activities facing manpower issues or dependencies on other work. The target dates for completion range from December 10 to December 20, 2024, with some tasks not yet started.

Uploaded by

Anup
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

UTILITY BALANCE WORK

Nos PENDING WORK REMARK Target date Manpower status as on 17.12.2024

1 Primer Work and Paint Progress 30.11.2024 Insufficient manpower

2 Kota fixing @ staircase area Progress 30.11.2024 Making started


3 Railing of stair 5.12.2024
4 Outside plaster Progress After Production office work
5 Chajja Plaster Not started
6 Brick work at Rolling shutter west side G.F & F. F 30.11.2024 Work Progress
7 Groove filling 30.11.2024 not started
8 Down take pipe fixing LATER activity
9 Top Dog house slab r sheet 30.11.2024 brick work complete
10 Brickbat Water proofing Material shifting 10.12.2024 Progress
11 Stair case Putty and paint

PVC AREA-1

Nos PENDING WORK REMARK Target date


1 Primer and putty work Progress 5-12-2024 scafolding removing in progress
2 Toilet plumbing and sanitary (RCD) area Progress 20-12-2024
3 Block work & Plaster at Production Office area 18-12-2024 Progress
4 Ramp Out side 10 -12-2024 Subject to soil filling
5 Plinth protection Not started Subject to soil filling
6 Storm line laying Not started Subject to soil filling
7 Trench cover material received 15-12-2024 Progress
8 Polysulphide filling and Baker rod fixing 30-11-2024 Progress
9 Deck slab Concreting 30-11-2024 Waiting for Stair case fixing
10 Grade slab CC
11 Tiles on water cooler area false cealing, louers 20-12-2024
12 Door shifting & stair case fixing
13 Trench slab casting