UTILITY BALANCE WORK
Nos PENDING WORK REMARK Target date Manpower status as on 17.12.2024
1 Primer Work and Paint Progress 30.11.2024 Insufficient manpower
2 Kota fixing @ staircase area Progress 30.11.2024 Making started
3 Railing of stair 5.12.2024
4 Outside plaster Progress After Production office work
5 Chajja Plaster Not started
6 Brick work at Rolling shutter west side G.F & F. F 30.11.2024 Work Progress
7 Groove filling 30.11.2024 not started
8 Down take pipe fixing LATER activity
9 Top Dog house slab r sheet 30.11.2024 brick work complete
10 Brickbat Water proofing Material shifting 10.12.2024 Progress
11 Stair case Putty and paint
PVC AREA-1
Nos PENDING WORK REMARK Target date
1 Primer and putty work Progress 5-12-2024 scafolding removing in progress
2 Toilet plumbing and sanitary (RCD) area Progress 20-12-2024
3 Block work & Plaster at Production Office area 18-12-2024 Progress
4 Ramp Out side 10 -12-2024 Subject to soil filling
5 Plinth protection Not started Subject to soil filling
6 Storm line laying Not started Subject to soil filling
7 Trench cover material received 15-12-2024 Progress
8 Polysulphide filling and Baker rod fixing 30-11-2024 Progress
9 Deck slab Concreting 30-11-2024 Waiting for Stair case fixing
10 Grade slab CC
11 Tiles on water cooler area false cealing, louers 20-12-2024
12 Door shifting & stair case fixing
13 Trench slab casting