Modjo Meat Processing Project Proposal
Modjo Meat Processing Project Proposal
App ,2025
Modjo town Ethiopia
TABLE OF CONTENT
I. EXECUTIVE SUMMARY.................................................................................................................................... 5
1. BACKGROUND INFORMATION........................................................................................................................ 7
1.1. INTRODUCTION...................................................................................................................................................7
1.2. PRODUCT DESCRIPTION.........................................................................................................................................8
1.3. PROJECT LOCATION AND JUSTIFICATION....................................................................................................................8
1.3.1. Location of Modjo town........................................................................................................................8
1.3.2. Demography of Modjo town.................................................................................................................8
1.3.3. Economic activity of Modjo town............................................................................................................9
1.4. MEAT PRODUCTION TRENDS IN ETHIOPIA..............................................................................................................11
1.5. DOMESTIC MEAT CONSUMPTION IN ETHIOPIA........................................................................................................11
1.6. STATUS OF MEAT PROCESSING INDUSTRY IN ETHIOPIA..............................................................................................12
1.7. WHY IS IT BENEFICIAL TO INVEST IN MODJO TOWN?................................................................................................12
1.7.1. The city benefit from the investment...................................................................................................14
2. MARKETING STUDY...................................................................................................................................... 15
3.1. TECHNOLOGY....................................................................................................................................................22
3.1.1. Meat production and preserving process.............................................................................................22
3.1.2. Process flow chart of Cattle meat processing unit...............................................................................23
3.1.3. Environmental and social impact assessment of the project...............................................................24
3.1.4. Production Capacity and Production Program.....................................................................................25
3.2. ENGINEERING...................................................................................................................................................26
3.2.1. Land, buildings and civil works.............................................................................................................26
3.2.2. Machinery and equipment......................................................................................................................29
5. FINANCIAL ANALYSIS.......................................................................................................................................................32
5.1. GENERAL.........................................................................................................................................................................32
LIST OF TABLES
LIST OF FIGURES
8.Employment This project fully employees the local individuals. Except the
Opportunity general manager all other employees are used from the local
area. Hence, this project will create employment
opportunities for 256 individuals from this 156 are skilled and
100are unskilled
9. For The region/ Source of foreign currency, job opportunity for the
country around people, source of revenue for the
government in the form of business tax and etc.
1. Background information
1.1. Introduction
Ethiopia has one of the largest livestock populations in Africa and the tenth in the world. The
country had 59.5 million heads of cattle, 30.70 million heads of sheep, 30.20 million heads of
goats, 56.53 millions of poultry and 1.21 million heads of a camel. Cattle in Ethiopia provide
draught power, income for farming communities, means of savings and investment. It is central to
the Ethiopian economy contributing about 45% to the agricultural GDP, supporting the livelihoods
of 70 % of the population, 18.7% to the national GDP and 16–19% to the total foreign exchange
earning of the country. Meat is the most valuable livestock product and for many people serves as
their first-choice source of animal protein which provides all the essential amino acids and various
micronutrients in proper proportion to the human beings. Meat defined as all animal tissues
suitable as food for human consumption. This includes all processed or manufactured products
prepared from animal tissues. Meat production and consumption is an important in the Ethiopian
economy. The annual contribution of cattle meat production in Ethiopia is accounts for over 70%
of the total red meat production and over 50% of the total meat output in Sub Saharan Africa. The
Country’s export performance reached its peak in 2016/17 by exporting 19,779.20 tons of meat. In
the same period under review, the meat export (chilled shoats, beef carcass and offal) value has
picked up from 1.7 million USD to 92.65 million USD. Among these shoat carcass account 80.35
million dollar (86.72%), beef carcass 6.23 (6.72%) and offal 6.07 (6.55%).
1.2. Product description
Processed meat is considered to be any meat which has been modified in order to either improve
its taste or to extend its shelf life. Methods of meat processing include salting, curing, fermentation
, smoking, and/or the addition of chemical preservatives. Processed meat is usually composed
of pork or beef, but also poultry, while it can also contain offal or meat by-products such as blood.
Processed meat products include bacon, ham, sausages, salami, corned beef, jerky, hot dog, lunch
meat, canned meat and meat-based sauces. Meat processing includes all the processes that change
fresh meat with the exception of simple mechanical processes such as cutting, grinding or mixing.
enterprise based and operating out of Ethiopia. The project entails the
This modern abattoir will have a starting capacity to slaughter and process
200 cattle and 2,000 goats/sheep per working day on a double shift basis. The
plant will have a high level of hygiene which will enable its production to be
exported at a suitable time in the future. Initially, live animals will be bought
from the local markets and the processed meat will all be sold on the domestic
market.
Recovery of usable by-products will form an important part of the process and
it is expected that the quality of the by-products like skins/hides, offals, blood,
heart, kidneys will be superior to that obtained from the existing conventional
slaughterhouses.
In order to assure availability of live animals for the meat processing plant, it
is proposed to develop strong links with live animal traders as well as with the
Poultry Paradise Agriculture Animal Product Plc commissioned Bright star and management
Cultanuncy plc. to prepare a feasibility study on the commercial prospects and financial viability of
setting up and operating a modern abattoir in Ethiopia [one of the three major livestock-producing
areas in the country] purposely to produce beef and other beef by-products from the existing livestock
off-take numbers and market them on the domestic market through cold-chain distribution outlets in
Modjo City.
Project Objectives
The proposed abattoir project, which includes commercial and national level interventions to the
Poverty alleviation
Job Creation
Create World Class Facility for the Domestic market and Export
Modernize Agriculture
of 901’48’’N latitude and 38°44′24″E longitudes. This is very near to the geographical center of
the country. It is, therefore, equidistant to the peripheral areas or is equally accessible to almost all
parts of Ethiopia. Modjo town is located on a well-watered plateau surrounded by hills and
mountains. The city is in the highlands on the edge of the Ethiopian rift valley or the eastern slopes
of the Modjo town ranges bordering the Great Rift Valley. The total area of Modjo town is about
The transformation of Modjo town has especially been rapid since 1991. According to the data
from the city’s Bureau of Finance and Economic Development (2006), per capital income of
Modjo town has grown from USD 788.48 in 2010 to USD 1,359 in 2015. The city also achieved a
decline in the poverty index from a high of 29.6 in 2012 to 22.0 in 2014. Moreover, the current
poverty headcount index for Modjo town is estimated at 18.9 while the poverty severity account
for 5 and 1.8 index points respectively. Even though, the poverty status of Modjo town has an
improvement over previous years, there is still much work to be done to curb both the incidence
The major contributor to the economic growth of the city is the implementation of publicly
financed mega urban projects like condominium housing, the Light Rail Transit, the international
airport and industrial zone development (The state of Modjo town, 2017). The existence of
international large and medium-size enterprises in and around Modjo town have also significant
role in creating huge opportunity for employment and technology transfer. Furthermore, there are
strong demand for goods and services following the existence of many embassies and inter-
governmental organizations like the African Union, the United Nations Economic Commission for
Africa.
The manufacturing sector’s contribution to Modjo town’s GDP is high. Despite the fact that 86%
of the industries in the city are micro and small scale (cottage and handicrafts, and small-scale), the
majority of the country’s large and medium scale industries are found in the city. Noticeable
The service sector is both the largest contributor to the city’s economy and the largest employer. It
contributes to 76.4% of the city’s GDP while industry’s share makes up (almost all) the rest. This
sector is dominated by three major sub-sectors: Transport and communication; Real estate, Renting
and Business services; and Trade, Hotel and Restaurants. According to the state of Ethiopian Cities
2015 report, the service sector has also been responsible for more than 50% of the growth in the
estimated annual growth of the city’s GDP. Although 75% of employment in the city is also
generated in the service sector, a large proportion of the employed work in low skill and low
paying jobs as shop salespersons, petty and 'gullit' traders, sales workers in small shops, domestic
Analysis of the economic structure of Modjo town reveals that the services sectors (63%)
dominates with industry (36%) in second place indicating that these sectors account for almost all
Modjo town has a great share in the economy of the country due to its attractiveness to businesses,
companies, individuals and foreign direct investment. Overall primacy index of the city is 24.8
based on urban employment and unemployment survey (CSA 2015). According to the State of
Modjo town 2017 report, the simultaneous high rates of economic growth and urbanization in
Modjo town indicates a likely further rising dominance of the city in Ethiopia’s economy as well
market. The total meat production increase from 578,240 tons in 2004 to 749,430tons in year 2014
and decreased to 596,765 tons in year 2017. Despite the fact that Ethiopia is the tenth largest
livestock population in the world, the production of meat is still low and contributed to about 0.2
percent of the world total meat production, of which most is sheep and goat meat. This ranked
Ethiopia the 55th largest meat producing country in the world. The reasons behind low production
of meat in Ethiopia are due to low off-take rates, most animals slaughtered and exported live were
not produced in commercially oriented manner and sell only in need of cash or when animals get
too old after serving for draft purpose and inability to fulfill minimum standard required in the
international market for processed meat. The trend of meat production in Ethiopia shows it was
general and particularly for beef due to preference for eating meat. Meat consumption is often an indicator
of economic status of a country or an individual. People with a higher social or economic status demand a
greater amount of high-quality meat products. The per capita consumption of meat in developed countries is
much higher than in developing countries. Countries whose population consumes the least amount of meat
are located in Africa and Asia. Developed countries consumed a consistent level of 77 kg of meat per capita
annually, while developing countries struggled to maintain a diet with only 25 kg of meat per capita
annually. With the fast growth of Ethiopian economy and population, the domestic demand for meat is
increasing; however, the country is one of the lowest per capita of meat consumption in the world which is
8 kg, of which about 5.3 kg comes from beef. This is due to low per capita incomes, non-commercial
oriented animal
husbandry practices, high domestic meat prices and the fasting days over 200 days per year by the Orthodox
Christians.
should be given the resource potential. Currently there are about 15 export slaughter houses
(including 8 under establishment) with installed capacity of 140,702 tons/year while they utilized
23%of their installed capacity and more than 29 abattoirs (with installed capacity 588,123
cattle/year and 317,785 goat/year) serving the local market. Notwithstanding, illegal or informal
killing of animals is highly practiced for domestic consumption at the backyard of practically all
households especially for shoats whereas for cattle killing at village level to share among a group
of neighbors or close families is common which is called” Kircha‟. Municipal level domestic
abattoirs are growing time to time with the growth of urbanization whereas modern slaughter
population share is only 17 percent (as of 2012, World Bank 2015). The city is the only urban area
diversity and depth of skills, innovation, and technology transfers. Thus, investors will be
The capital is the country’s main industrial hub. The city dominates industrial capacity in almost
all the braches of light manufacturing that Ethiopia prioritizes. As a result Modjo town completely
dominates production in various subsectors. This can be taken as the political and social stability
of the city.
Overall, the city has a beautiful environment, favorable location, and strong industrial base. Its
advantage as an economic powerhouse of the country and human resource center are the most
Moreover, investors will be getting a comprehensive set of incentives for priority sectors. These
include:
Customs duty free privilege on capital goods and construction materials, and on spare parts
whose value is not greater than 15% of the imported capital goods’ total value.
Investors have the right to redeem a refund of customs duty paid on inputs (raw materials
and components) when buying capital goods or construction materials from local
manufacturing industries.
Additional 2-4 years income tax exemption for exporting investors located within industrial
Loss Cary forward for half of the tax holiday period. Several export incentives, including
Duty Draw-Back, Voucher, Bonded Factory, and Manufacturing Warehouse, and Export
Employment opportunity
Investment is expected to provide direct and indirect employment. These range from unskilled
Through the use of locally available materials and exporting products, the investment contributes
towards growth of the economy by contributing to the growth of domestic product. These
eventually attract taxes including VAT which will be payable to the government hence
increasing government revenue while the cost of local materials will be payable directly to
the producers. In addition, domestic products save foreign exchange and exports also bring
The current drive and emphasis by the government on the diversification of the industrial base
away from the other sector presents an opportunity for production industry to a valuable
contribution towards achieving goal. Having undertaken a thorough and comprehensive research of
the market we realized that there was a vast opportunity for domestic products. Aware of the fact
operating in such a market is largely dependent on good networking, the promoter intends to
establish networks and strategic relationships with various wholesalers and retailers to ensure a
steady stream of orders. In so doing the owner intend to ensure that the products they produce are
no apparent trend in the growth of import processed meat has continuously been appearing in the
import statistics.
Year Net weight CIF value in CIF value in Total TAX in Total value Unit price
(in Kg) (ETB) USD ETB in ETB per Kg
2012 23,550 23,019 4,474,642 250,461 3,010,368 168,501
2013 13,693 13,562 3,297,673 175,407 2,222,705 118,228
2014 70,819 68,302 6,971,171 346,074 1,603,664 79,612
2015 156,298 134,265 8,694,265 418,356 5,706,053 274,567
2016 48,788 42,093 1,559,541 72,206 993,346 45,991
2017 47,260 45,529 2,662,536 109,945 1,427,669 58,953
2018 17,434 16,454 639,316 - 405,182 20,877
2019 - - - - - -
2020 139,106 119,911 7,640,960 - 1,363,544 -
2021 181,872 151,100 16,191,912 - 4,950,736 -
Source: Ethiopia customs Authority
As it has been shown in table 3 import of processed meat which was 23,019 kg at the beginning of
the period (2012) has increased to 151,100kg by the end of, 2021. A closer observation at the data
set reveals that imported processed meat over the study period has shown varying patterns. Based
on the data obtained from Ethiopia customs Authority, the annual average volume of imported
Table 3 Future forecast of import of processed meat by trend adjusted exponential smoothing method
The demand for meat can be influenced by a number of factors. The size of population and its
growth rate, disposable income prices and culture are few among many variables. With the fast
growth of Ethiopian economy and population, the domestic demand for meat is increasing;
however, the country is one of the lowest per capita of meat consumption in the world which is 8
kg, of which about 5.3 kg comes from beef. This is due to low per capita incomes, non-commercial
oriented animal husbandry practices, high domestic meat prices and the fasting days over 200 days
per year by the Orthodox Christians Nevertheless, for the purpose of this study, attempts have been
made to forecast the likely future demand for meat on the basis of the following assumptions:
iv. According to International Journal of Food Science and Agriculture, 2019 consumption of
As it is indicated above the demand for meat in 2022 is 961,621,432kg. This volume will increase to
Table 6 Future forecast of export of processed meat by trend adjusted exponential smoothing method
When we see the historical supply volume of meat in Ethiopia there is no apparent trend in the
growth. Hence, it is found difficult to objectively forecast the future supply volume. Single
exponential smoothing method was used, for import forecasting purposes. A 2.5% growth rate,
equivalent to population growth of our country, is also assumed for local supply increase, for new
as well as expansion projects for domestic suppliers of the existing slaughters’ house.
Cattle Farmer
Village Middleman
Primary stock
market
Secondary stock
Cattle Trader
market
Local slaughter slab
Local Market
Processor
(Supermarket)
(wholesaler)
Border
3. Technology and engineering
3.1. Technology
cured, canned, and other meat products, and the rendering of inedible and discarded remains into
useful by-products such as lards and oils. Meat is exposed to a series of wide range of processes
viz. curing or preserving processes such as salting, wet pickling, drying, cooking and canning,
sausage manufacture, ham curing. All these processing techniques are aimed at inhibiting the
microbial spoilage and increasing the shelf life of the meat. Major principles involved in meat
processing are use of heat, low temperature, smoking, modified atmosphere packaging and
ionizing radiations. The methods of preservation are mainly grouped in three categories i.e. control
Freezing is an excellent process for preserving the quality of meat for long periods. Freezing is
often used to preserve meats during shipment over long distances or for holding until long times of
storage. Its effectiveness depends on ice crystal formation and rate of lowering of temperature.
When the temperature of storage is below - 18C 2, changes occur at a very slow rate in the muscle
of warm blooded animals. Quality of frozen meat depends on various factors such as rate of
freezing, packaging etc. When muscle tissue is frozen rapidly, small both intra and extra cellular
ice crystals are formed which cause little damage to the meat structure. While large ice crystals are
formed in slow rate of freezing causing compactness of muscle fiber. The process of denaturation
can be accelerated with a resulting decrease in water holding capacity of tissue. Loss of water
holding capacity of the muscle along with mechanical damage to cells by ice crystals is responsible
in large parts of thaw exudates. To protect quality loss due to changes in protein, anti-freezing
compounds
or cry protectants i.e. polydextrose, polyphosphate are added to meat formulations.
Rapid freezing can be obtained by using air blast freezers either on batch or continuous
-40C2 cold air. Large size meat cuts are vacuum packaged to prevent lipid oxidation and
Process Description
The slaughtering and meat processing process has been summarized in the diagram
below:
Ante-mortem
Dirty Process
Slaughtering
and Bleeding
Skinning or
Scaling
Evisceration
Post-mortem
Chilling,
Hanging and
Delivery/Dispatc
3.1.2. Process flow chart of Cattle meat
processing unit
These environmental and social due to development projects occur in different forms. An
Environmental and Social Impact Assessment (ESIA) has to be carried out to study the potential
environmental and social impacts due to the production processed meat. Potential environmental
and social impacts due to the production of meat based products on attributes like air quality,
noise, water quality, soil, flora, socio-economic, etc. have to be assessed as part of the ESIA study.
Appropriate mitigation measures to help minimize/avoid impacts from the development have to be
recommended in the study. The measures include avoidance measures, mitigation measures and
environmental enhancement measures. For the purpose of including environmental costs, the costs
of wastewater treatment plant and solid waste incineration systems are included in the cost of
machinery and equipment. Social responsibility cost estimated to be 1% of fixed investment costs.
3.1.4. Production Capacity and Production Program
The annual production capacity of the plant in full capacity is 500 heads of cattle per day, their
weight is 400kg each. The production capacity is based on projected demand and realistic market
share that could be captured. The production commences three shift and 260 working days a year.
The annual production program for the year 1 to year 4 is indicated in Table 8 below. The plant
initially produces 70 % of its annual rated capacity bound to initial operating problems such as
machine set up and marketing. The production capacity will increase by 10 % and attain its full
successful operation of the processing plant is shown in Table10. A total area ready for the
processing plant is 10,000m2 out of which 1,900m2 is to be covered by building while uncovered
area of 2,100m2 is left open for parking, storage of waste materials and future expansions. In order
to estimate the land lease cost of the project profiles it is assumed that all the project will be
located in different land level from level 1/1 to level 4/3, their current market lease price is from
39,073.31 birr per M 2 to 2,800.71 birr per M 2respectively. Therefore, for the profile a land lease
rate of birr 3,885 per M 2 have been taken, which is between the ranges.
The cost of construction of building should be appropriate to the size and expected profitability of
business, costs of building generally differs by the type of construction materials used, the type of
foundation, wall height and location. The current building cost for simple storage and processing
room is from 10,000 Birr per m2 to 25,000 Birr per m2. The total construction cost of buildings and
2
civil works, at a rate of Birr 20,000 per m is estimated at Birr 402.80 million. Therefore, the total
cost of land lease and construction of buildings and civil works is estimated at Birr 597 million.
The proposed plant layout comprises the following buildings and structures.
Table 10 Building costs
SCHRÖDER Maschinenbau
GmbH & Co. KG
Esch 11
33824 Werther, Germany
Tel.: +49 5203 9700 0
Fax.: +49 5203 9700 79
4. Organizational structure for meat processing unit
The selection of structure of the envisaged project is made based on the existing structure of
manufacturing plants operating in the country, the capacity, complexity and technology mix of the
plant. Organizational structure principles such as specialization, coordination, and
departmentalization are also considered for design of structure that best suits the envisaged project
5.1. General
The financial analysis evaluation of the project, under consideration has been carried out for meat
processing cost estimates of the envisaged factory are mainly consisted of capital investment as
well as operating and maintenance costs. The capital investment costs include fixed investment
costs (initial fixed investment and replacement costs) and working capital, while operating and
maintenance costs comprise current expenses related to material inputs, labour, utility, repair and
maintenance costs, spare parts, Overheads, Sales and distribution, interest and depreciation
expenses.
The financial analysis and evaluation has been conducted taking assumptions:
1. It is assumed that about 70% of the total capital investment costs including the working
capital requirement could be covered through development bank loans of short and long-
term credits. The remaining balance 30% will be covered by equity capital contribution of
2. Even though the project might secure loans under different term and conditions as well as
from different financial sources, for the purpose of calculation of debt service scheduling,
the current development bank of Ethiopia credit terms and conditions have been used.
Consequently. It is assumed that the project will secure loan facility on the basis of 11.5 %
3. Even though the estimated project production life is more 10 years, the financial analysis
has been undertaken for a period interval covering the first 10 years only, during which
time
most of the capital assets are assumed to be deprecated, debts recovered and pay-back period
accomplished.
4. It is assumed that the project will be start up production activity at 70 % capacity. During
years 2 & year 3 the projects is anticipated to gradually increase capacity utilization to
reach 100% in year 4. Therefore, starting from year 4 the project will be operational at full
capacity.
5. For the project under reference promotional, sales and distribution expenses have been
6. Maintenance and spare parts costs are 1.5% of the fixed investment costs.
5.2. Initial Fixed investment costs
Table 15 Initial Fixed investment costs
S/No investment type Unit of Quantity Unit price Total Amount Remarks
measurement
1 Square meter 50,000 3,885 194,250,000.00 period of land lease will
be 70 years and
birr/M2 10% of the total
2Buildings and civil works Square meter 5,100 lump sum 402,800,000.00 lease amount
will be paid in
the first
total 597,050,000.00
3Machineries set 2 Lump sum 120,000,000.00
4Transformer set 1 Lump sum 2,000,000.00
5Weighbridge Set 1 Lump sum 4,000,000.00
6 and vehicles Pcs 2 Lump sum 12,000,000.00
7Furniture and Pcs 500,000.00
TOTAL 138,500,000.00
Fixed capital investment 735,550,000.00
costs
8pre-operational expenses 2,000,000.00
Working capital is the financial means required for smooth operation and maintenance of a project
mathematically, it is a difference between current assets and current liabilities. In the particular
case of the project under consideration, the current assets comprise receivables, inventories (local
and imported material inputs, spare parts, work in progress, and products ready for delivery) and
Fixed capital investment costs and working capital requirements are assumed to be financed by
equity capital of the owner and through loans of short and long-term credits.
As stated earlier even though the company obtains loans under different terms and condition as
well as from different sources, for the purpose of calculation of debt service scheduling the current
development bank of Ethiopia credit terms and conditions have been used. Accordingly, it is
assumed that the company will be able to obtain loan 70% of the total investment costs and the
remaining balance that of the total investment costs will be expected to be covered by equity
As it is depicted in Annex Table 21 major categories of the total production costs are assembled
In the project under study the basic material inputs are cattle (Oxen, bulls, and cows), labelled cans and salt.
Therefore, the current prevailing local and international market prices have been used for estimation of
material inputs costs. At full capacity operation the material inputs costs are estimated at Birr 10.05 billion
per annum.
Project year 1 2 3 4
Materials input Quantity at full Unit
for meat Description Capacity price
processing
1 Cattle Average weight 400kg 500 cattle/day 75,000 6,825,000 7,800,000 8,775,000 9,750,000
2 Can 1000gm, holding capacity 68, 000pcs/day 15 185,640 212,160 238,680 265,200
lubricant, electricity and water consumptions have been taken in to consideration, the rates of which have
been estimated on the basis of the proposed capacity utilization program of the project and at the current
official charging rates. At full capacity operation the project will have the following utility expense per
Start-up Full
Utility”000”Birr Capacity
Capacity utilization 70 % 80 % 90 % 100 %
Project year 1 2 3 4
Item description Unit of measurement
Fuel
Gasoline for service vehicle 50km*260days*37Birr/LIT*8km/Li 29.575 33.80 38.025 42.250
Gasoline for transport truck (200km*300days*37Birr/LIT*5km/Li)*3 655.20 748.80 842.40 936.00
Sub-Total
684.775 782.6 880.425 978.25
Change of oil and lubricant 10% of the fuel consumption
68.48 78.26 88.04 97.83
Sub-Total
753.25 860.86 968.47 1,076.08
Electricity 260days*24 hrs*650kwh* 0.4736Birr/kwh 2,839 3,245 3,650 4,056
In the expenses under this title have been considered cost estimates required for annual repair and
maintenance works including spare parts expenses. These costs include the annual repair expenses
of structures and civil works as well as repair and maintenance expenses of machinery and
equipment including accessory and general service facilities. The repair and maintenance and spare
parts costs have been assumed to be 1.5% of the total fixed costs.
“organization and Management” section of this study. In the estimation of salaries and wages, the
official minimum wage has been taken in to account. At full capacity operation the costs of salaries
In the expenses under this title have been included land and building taxes, buildings, vehicles as
well as machinery and equipment insurance, vehicles annual inspection; postage, telephone and e.
mail, stationery and office supplies; printing and copying; audit fee; cash indemnity etc. The
Insurance
Building and Civil works 0.10% 402.80 402.80 402.80 402.80
Machinery and Equipment 0.20% 240.00 240.00 240.00 240.00
Motor vehicle and Truck 1% 120.00 120.00 120.00 120.00
Vehicles annual inspection and 15,000 Birr per annum per vehicle
registration 45.00 45.00 45.00 45.00
Work cloth Two times per annum per workers at
800 Birr 65.60 65.60 65.60 65.60
Cleaning and sanitation An estimate of 300 Birr/day 78.00 78.00 78.00 78.00
Sub Total
28,701.40 28,701.40 28,701.40 28,701.40
Administration Overhead “000’ Birr
Audit fee 40,000 Birr per annum 40.00 40.00 40.00 40.00
Office cleaning and sanitation 2,000 Birr per month 24.00 24.00 24.00 24.00
Stationery and office supplies 2,000 Birr per month 20.00 20.00 20.00 20.00
Printing and Copy 2,000 Birr per month 24.00 24.00 24.00 24.00
Sub Total 108.00 108.00 108.00 108.00
28,809.40 28,809.40 28,809.40 28,809.40
GRAND TOTAL
Ethiopia credit terms and conditions for newly establishing projects have been used to compute the
financial costs, estimated to be incurred in connection with that of the total investment costs
assumed to be covered through loan financing. The amount of the loan capital to be obtained and
the financial costs to be incurred thereof have been determined depending on the amount of fixed
Depreciation charges should be taken in to account as part of the total production costs in order to
calculate the total production costs, the net working capital and the gross or net-profit. For the
given project under reference, the fixed assets and the pre-production capital expenditures have
been depreciated and amortized respectively on “a straight line” depreciation method basis using
The rationale uses for the estimation of the depreciation and the amortization rates is based on the
expected service life of the assets and repayment capacity of the project under consideration.
Based on the above charging rates and consideration of the above facts, the total annual
depreciation cost at full capacity operation have been estimated at Birr 41.44 million.
Period Start-up
Structure and civil works 402,800,000.00 5% of original value 20,140 20,140 20,140 20,140
Machinery and equipment 120,000,000.00 15 % of original value 18,000 18,000 18,000 18,000
Motor vehicles and trucks 12,000,000.00 15 % of original value 1,800 1,800 1,800 1,800
Office equipment and furniture 500,000.00 20 % of original value 100 100 100 100
annual fixed cost, and divided by Annual sales less Annual variable cost.
==
Annual sales x Annual fixed
Annual sales−Annual variables = = 8,153,600−7,345,143
costs
BEP (sales) 8,153,600 x 165,510
costs
A. BEP production
To determine BEP production volume, divided BEP sales by the unit selling price (USP)
=
BEP percentage
Annual sales−Annual variables
B.
costs
= 8,153,600−7,345,14
165,510x 100%
= 20.47%
= 41%
= 137%
5.7. Project costs
Project capital investment costs are the sum of fixed capital investment (fixed investment plus pre-
production capital expenses) and net working capital at full capacity, with fixed capital constituting
the resources required for constructions and civil works, importation and installation of production
machinery and equipment and general service facilities, whereas, the working capital
corresponding to the resources needed for operation of the project totally and partially.
As it has been revealed in Annex Table 21 the total annual operating costs excluding depreciation
and interest are estimated to range from 7.3billion Birr in year 1 to 10.45 billion Birr in year 4 and
then after remain constant for the rest of the project life.
The total annual production costs including depreciation and interest increase from 7.46billion Birr
in year 1 to 10.566 billion Birr in year 4 then starts declining until it reaches 10.48 billion Birr in
year 10.
In according to Annex Table 22 requirement for the total working capital has been found to range
from 354 Million Birr to in year 1 to 483 Million Birr in year 4 and then and then after remain
In the assumptions used to compute the working capital, basically care has been taken to cover
costs of consumable materials inventory (material input, spare parts stock, work in progress and
product ready for delivery), delivered products and cash in hand requirement.
5.8. Project benefits
For financial analysis and evaluation of the given project, the current cattle price, and packing
materials buying price and final packed meat price at the project gate has been taken as a basis. As
it has been stated earlier the project is envisaged to reach full capacity operation four years after
commencement of production activities which are assumed to begin with 70% of the estimated
total capacity.
At full capacity operation the project is envisaged to have the following revenue
Project year 1 2 3 4 5
Unit price
Product type
1 Canned meat 600/kg 7,425,600 8,486,400 9,547,200 10,608,000 10,608,000
2 By product like blood, 40% of total 50birr/kg 728,000 832,000 936,000 1,040,000 1,040,000
fatty tissue, skin, weight of the
organs and etc. cattle will be
sold as by
products
TOTAL 8,153,600 9,318,400 10,483,200 11,648,000 11,648,000
Thus, according to the computation in Annex Table 23 and Annex Table 25, the net income and
cash flow statements analysis revealed that at full capacity operation the project will generate a
total income (gross revenue) amounting to 11.64 billion Birr per annum. The corresponding Annex
Table 23 of “Net Income Statement” shows a steady growth of gross profit starting from 692
million Birr in year 1 reaching the peak of 1.1billion Birr in year 10. In its 10 years of
manufacturing activities,
the project is expected to generate a total net profit of 6.68 billion Birr and contribute 3.6billion
According to the current investment Law, machinery and equipment are anticipated to be imported
duty- free. The liquidity position of the project is very strong. The corresponding Annex Table 25
of “Cash Flow Statement” shows the positive cumulative cash balance of Birr 6.2 billion and the
project will not face any cash shortage throughout its production life.
The computation of the pay-back period as depicted in Annex table 30 indicates that the project
will be able to reimburse itself from its net cash-income within one year after commencement of
production activities, the period which is considered to be very good for the project of this nature.
In Annex Table 31 of the Benefit-cost ratio and Net present value (NPV) have been calculated at
17% discount factor (D.F) for 10 years of the project activity. Accordingly, the project has NPV of
3.69billion Birr at 17%D.F. and the benefit-cost ratio of 1.09at 17% D.F. These results are most
appreciable, especially, when related to the external capital borrowing interest rate which ranges
The project under study when implemented will have BEP at about 20.47% operation of the
estimated full capacity. In addition to this, finally, summary of financial efficiency tests have been
conducted in Annex table 29, Accordingly, all efficiency ratios indicated positive trends and
consequently, it can be inferred that the project can operate in the frame work of free market
Project Year 1 2 3 4 5 6 7 8 9 10
Cost category
I. Material inputs 7,036,164 8,041,330 9,046,496 10,051,662 10,051,662 10,051,662 10,051,662 10,051,662 10,051,662 10,051,662
II. Labor 7,884 7,884 7,884 7,884 7,884 7,884 7,884 7,884 7,884 7,884
III. Utility 6,251 7,129 8,007 8,886 8,886 8,886 8,886 8,886 8,886 8,886
IV. Repair and Maintenance and spare 8,120 8,120 8,120 8,120 8,120 8,120 8,120 8,120 8,120 8,120
parts (0.5 % of fixed costs)
VI Direct overheads 28,701 28,701 28,701 28,701 28,701 28,701 28,701 28,701 28,701 28,701
A. Direct Production costs 7,087,120 8,093,164 9,099,208 10,105,253 10,105,253 10,105,253 10,105,253 10,105,253 10,105,253 10,105,253
VII. Administration over head 108 108 108 108 108 108 108 108 108 108
VIII. Marketing and Promotional expense
244,608 279,552 314,496 349,440 349,440 349,440 349,440 349,440 349,440 349,440
3 % of sales revenue
B. Operating costs 7,331,836 8,372,824 9,413,812 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801
Interest 87,377 82,747 77,028 70,650 63,539 55,610 46,769 36,911 25,919 13,664
Depreciation 41,440 41,440 41,440 41,440 40,940 40,840 34,009 20,140 20,140 20,140
C. Total production costs 7,460,653 8,497,011 9,532,280 10,566,891 10,559,280 10,551,251 10,535,579 10,511,852 10,500,860 10,488,605
ANNEX IV
CALCULATION OF WORKING CAPITAL REQUIREMENTS
Project year 1 2 3 4 5 6 7 8 9 10
Item description
8,153,600 9,318,400 10,483,200 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000
Product sales revenue
7,460,653 8,497,011 9,532,280 10,566,891 10,559,280 10,551,251 10,535,579 10,511,852 10,500,860 10,488,605
Less total production costs
Gross profit 692,947 821,389 950,920 1,081,109 1,088,720 1,096,749 1,112,421 1,136,148 1,147,140 1,159,395
Tax 242,531 287,486 332,822 378,388 381,052 383,862 389,347 397,652 401,499 405,788
Net profit 450,416 533,903 618,098 702,721 707,668 712,887 723,074 738,496 745,641 753,607
Accumulated 450,416 984,318 1,602,416.40 2,305,137 3,012,805 3,725,692 4,448,766 5,187,262 5,932,903 6,686,510
undistributed profit
ANNEX VII
DEBT SERVICE SCHEDULE AND COMPUTATION
PAYMENT OF EQUAL ANNUAL INSTALLMENTS
Total
A. Debt service
1. First year Loan
a. Interest 87,377 82,747 77,028 70,650 63,539 55,610 46,769 36,911 25,919 13,664
b. Repayment of principal 44,609 49,739 55,459 61,837 68,948 76,877 85,718 95,576 106,567 118,822
ANNEX VIII
CASH-FLOW STATEMENT
FOR
FINANCIAL PLANING
Table 25 Projected Cash flow statement
Item description
A. Cash - inflow 10,653,733 9,562,587 10,727,389 11,892,188 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000
1. Financial resource 2,500,133
(total) 244,187 244,189 244,188
2. Sales revenue 8,153,600 9,318,400 10,483,200 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000 11,648,000
B. Cash – outflow 10,206,486 9,036,983 10,123,310 11,209,864 10,968,340 10,971,150 10,976,635 10,984,940 10,988,786 10,993,075
1. Total assets schedule 2,500,133 244,187 244,189 244,188
including replacement
2. Operating costs 7,331,836 8,372,824 9,413,812 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801 10,454,801
3. Debt service (total)
a. Interest 87,377 82,747 77,028 70,650 63,539 55,610 46,769 36,911 25,919 13,664
b. Repayment 44,609 49,739 55,459 61,837 68,948 76,877 85,718 95,576 106,567 118,822
4. Tax 242,531 287,486 332,822 378,388 381,052 383,862 389,347 397,652 401,499 405,788
C. Surplus (Deficit) 447,247 525,604 604,079 682,324 679,660 676,850 671,365 663,060 659,214 654,925
D. Cumulative cash balance 447,247 972,851 1,576,930 2,259,254 2,938,914 3,615,764 4,287,129 4,950,189 5,609,403 6,264,328
ANNEX XII
TOTAL INVESTMENT COSTS
Table 26 Total investment costs”000”
ANNEX XIII
TOTAL ASSETS
ANNEX XI
SUMMARY OF FINANCIAL EFFECIENCY TESTS
Table 29 Summary of financial efficiency tests
Project year
Project year 1 2 3 4 5 6 7 8 9 10
Capacity utilization 70% 80% 90% 100%
Financial ratio in %
1. Gross profit : Revenue 8% 9% 9% 9% 9% 9% 10% 10% 10% 10%
2. Net profit : Revenue 6% 6% 6% 6% 6% 6% 6% 6% 6% 6%
3. Net profit : initial investment 41% 47% 52% 58% 58% 58% 59% 61% 61% 62%
4. Net profit : Equity 138% 144% 149% 154% 155% 156% 158% 162% 163% 165%
5. Gross profit : Initial investment 63% 72% 81% 89% 89% 90% 91% 93% 94% 95%
6. Operating costs : Revenue 90% 90% 90% 90% 90% 90% 90% 90% 90% 90%
ANNEX XV
CALCULATIONS OF PAYBACK
Table 30 Calculation of payback period”000” PERIOD