BEFORE THE HON’BLE REAL ESTATE REGULATORY
AUTHORITY MUMBAI, MAHARASHTRA
COMPLAINT NO. CC005000000461143/2024
IN THE MATTER OF:
PRIYANKA RAJENDRA SHINDE & ANR. …
COMPLAINANT
VERSUS
M/S AVIOR MERLIN VENTURES LLP …
RESPONDENT
INDEX
S. NO. PARTICULARS PAGES
1. REJOINDER ON BEHALF OF THE
COMPLAINANT.
2. AFFIDAVIT
MUMBAI
DATED:
Through
Props Legal
Advocates for the complainant
Office No. 3B, 4th Floor,
Rajendra Place, Pusa Road
New Delhi-110060
Email: - [email protected]
REJOINDER ON BEHALF OF COMPLAINANT
Most respectfully Showeth :-
1. The Complainant submits that the Respondent is not duly
authorized to file the present reply, as no document or evidence has
been annexed to substantiate such authorization. There is no
authority letter, no proof of consent from the partners, and no
documentary evidence establishing that the person filing the reply
is a legally recognized partner of the Respondent firm. In the
absence of such crucial authorizations, the reply has been filed
without any legal standing and is, therefore, non-est in the eyes of
the law.
Further, the said reply has been filed without a proper affidavit,
which is a mandatory requirement for the verification of pleadings.
The absence of a duly sworn affidavit renders the reply procedurally
defective and legally untenable. Moreover, the reply has not been
notarized by a Notary Public or attested by an Oath Commissioner,
which is an essential requirement to establish its authenticity and
legal admissibility. In view of the foregoing defects, the said reply is
liable to be disregarded and cannot be considered as a valid
pleading before this Hon’ble Authority. In support of the above
contentions, complainant relying on below judgments of Hon’ble
courts: -
A. United Bank of India v. Naresh Kumar & Ors., (1996) 6
SCC 660 – The Hon’ble Supreme Court held that in the case of a
partnership firm or corporate entity, a person filing pleadings on
its behalf must demonstrate proper authorization. In the absence
of such authorization, the pleadings are not maintainable.
B. Ramesh Chandra Agrawal v. Regency Hospital Ltd. & Ors.,
(2009) 9 SCC 709 – The Hon’ble Supreme Court emphasized
that affidavits are essential for verification and authentication of
pleadings, and any defect in verification renders the pleading
defective.
C. Church of Christ Charitable Trust & Educational Charitable
Society v. Ponniamman Educational Trust, (2012) 8 SCC
706 – The Hon’ble Court held that if a pleading is not properly
supported by an affidavit, it lacks evidentiary value and cannot
be relied upon.
D. Shree Gajanan Maharaj Sansthan v. State of Maharashtra,
(2002) 2 Mh.L.J. 487 – The Bombay High Court held that
documents requiring attestation must be properly notarized or
sworn before an Oath Commissioner; otherwise, they are not
legally tenable.
In view of the above, the present reply, having been filed without
proper authorization, consent, affidavit, and notarization, is legally
unsustainable and ought to be rejected outright.
2. Without prejudice to all the rights and contentions, the complainant
wishes to maintain and reaffirm each and all averments made in the
complaint. At the very outset, it is submitted that all statements and
contentions made by the respondent in its reply/ written statement
are false, wrong and frivolous and are denied except those, which
have specifically been admitted herein below or traversed
therefrom. Each and every averment contained in the Respondent's
Reply is false, incorrect, and vehemently denied.
3. That the contents of reply/ written statement are wrong and denied
except those, which have specifically been admitted herein below or
traversed therefrom. It is submitted that the contents of the Claim
petition and Preliminary objection shall be read along with the reply
of this para as the same shall not be reiterated here to avoid
repetition. The Complainant reiterates that the Respondent has
failed to provide any updates, information, or intimations regarding
the progress of construction and the status of the project. This
failure is evident from the Respondent’s own Reply/Written
Statement, which is devoid of any documentary evidence, such as
emails, letters, messages, or any other form of communication
establishing that such updates were ever provided to the
Complainant.
4. The complete absence of any supporting documents on record
demonstrates that the Respondent has failed to discharge its
obligation to keep the Complainant informed about the development
of the project, thereby breaching the principles of transparency and
good faith, as mandated under the agreement and applicable laws.
The Hon’ble Supreme Court and various High Courts have
consistently held that a developer is duty-bound to provide
regular updates to homebuyers and failure to do so amounts
to a deficiency in service and unfair trade practice. That in
the matter of Pioneer Urban Land & Infrastructure Ltd. & Anr.
v. Govindan Raghavan (2019) 5 SCC 725 Held that a builder
cannot take advantage of one-sided contractual terms and is liable
for failing to keep the buyer informed about construction progress.
Furthermore, in the case of Bangalore Development Authority
v. Syndicate Bank (2007) 6 SCC 711 Hon’ble Court Emphasized
that non-disclosure of material information and lack of transparency
amounts to unfair trade practice. Furthermore, in the case of
Lucknow Development Authority v. M.K. Gupta (1994) 1 SCC
243 Hon’ble Court Recognized that failure to provide promised
services or updates to the buyer constitutes deficiency in service
under consumer protection laws. Furthermore, in the case of Wing
Commander Arifur Rahman Khan & Ors. v. DLF Southern
Homes Pvt. Ltd. & Ors. (2020) 16 SCC 512 Hon’ble Court
Reinforced that delay and non-communication of project status are
valid grounds for consumer claims against developers.
5. It is abundantly clear from the contents of the Reply filed by the
Respondent that they have blatantly failed to adhere to the terms
and conditions of the Agreement and have wilfully violated the
provisions of the Real Estate (Regulation and Development) Act,
2016 ("RERA"). The Respondent’s failure to upload the stage-wise
progress and status of the construction on the RERA portal, as
mandated under the Act, constitutes a clear violation of statutory
obligations. Furthermore, the Respondent’s failure to provide such
crucial information directly to the Complainant amounts to a
deficiency in service, a breach of contractual obligations, and an
unfair trade practice under the Consumer Protection Act, 2019. The
Hon’ble Supreme Court and various High Courts have categorically
held that developers are under a legal obligation to maintain
transparency and disclose all material information to homebuyers.
The deliberate omission of such disclosures not only prejudices the
rights of the Complainant but also constitutes a violation of the
fundamental objectives of RERA, which is to ensure accountability
and protect the interests of homebuyers. That in the matter of M/s
Imperia Structures Ltd. v. Anil Patni & Ors., (2020) 10 SCC
783 The Hon’ble Supreme Court held that RERA mandates
developers to provide regular construction updates and any failure
to do so constitutes a breach of statutory duty. Further, The Court
emphasized that builders must act in good faith and cannot escape
liability for non-disclosure of vital information related to project
progress. That in the matter of Kolkata West International City
Pvt. Ltd. v. Devasis Rudra, (2019) 18 SCC 692 Held that non-
compliance with contractual and statutory obligations, including
failure to provide construction updates, is a deficiency in service.
6. The claims and contentions of the Respondent regarding alleged
unforeseen challenges and external circumstances beyond their
control are baseless, misconceived, and vehemently denied. It is a
well-established principle that before launching any real estate
project, it is the fundamental duty of the developer to conduct a
proper title search and due diligence concerning the subject
property. However, in the present case, the Respondent has
blatantly failed in its obligation to undertake the requisite due
diligence, thereby demonstrating gross negligence and a clear
disregard for legal compliance. It is pertinent to note that the
Complainant executed the Agreement on 17.09.2020, whereas the
State of Maharashtra had already issued a Gazette
Notification on 21.09.2019, much prior to the execution of the
Agreement. This incontrovertible fact establishes that the
Respondent wilfully ignored the said Gazette Notification dated
21.09.2019 and is now attempting to unjustly shift the
consequences of its own negligence onto the Complainant. The
deliberate omission of such a critical regulatory development from
the Agreement further demonstrates the Respondent’s malafide
intent to misrepresent material facts and extort money from the
Complainant despite having full knowledge of the said Gazette
Notification dated 21.09.2019. The Hon’ble Supreme Court and
various High Courts have consistently held that developers are
duty-bound to conduct comprehensive due diligence before offering
a project for sale and that any failure to disclose material facts
constitutes deficiency in service, misrepresentation, and unfair
trade practice. The Respondent's failure to act in a diligent and
transparent manner renders them liable for serious legal
consequences. The Respondent’s conduct is in clear violation of the
Real Estate (Regulation and Development) Act, 2016 (RERA)
and the Consumer Protection Act, 2019, and appropriate legal
consequences must follow.
7. In Paragraph No. 04 of the Reply, the Respondent has sought to
invoke the doctrine of force majeure under Clause 3.3 of the
Agreement. In response to the same, the Complainant categorically
states that the said benefits are not applicable in the present case
due to the following reasons:
A. Prior Knowledge of Regulatory Restrictions: The Respondent
was fully aware of the State of Maharashtra Gazette
Notification dated 21.09.2019 before launching the project.
Despite having explicit knowledge of the said notification, the
Respondent proceeded with the project, sold the unit to the
Complainant, and deliberately failed to disclose this material fact,
thereby acting in bad faith.
B. Intentional Non-Disclosure and Misrepresentation: The
Respondent intentionally and deliberately omitted any reference to
the Gazette Notification dated 21.09.2019 in the Agreement, with
the clear intent to mislead and misrepresent facts to the
Complainant, demonstrating malafide intent and an attempt to
fraudulently induce the Complainant into the transaction.
C. Non-Compliance with RERA Obligations: The Respondent failed
to fulfil its statutory obligations under the Real Estate (Regulation
and Development) Act, 2016 (RERA) by:
o Failing to upload construction progress updates on the
RERA portal, thereby violating the duty of transparency.
o Failing to disclose ongoing litigation reports on the
RERA portal, depriving homebuyers of crucial information
regarding legal disputes affecting the project.
o Failing to provide any information to the Complainant
regarding these material facts, thereby engaging in an unfair
trade practice.
D. Unjustified Delay in Possession: The Respondent failed to hand
over physical possession of the unit to the Complainant within the
stipulated/agreed timeline mentioned in the Agreement, without any
valid justification. The invocation of force majeure cannot be used
as an afterthought to escape liability for deliberate lapses and
negligent actions on the part of the Respondent.
8. Failure to Exercise Due Diligence: The Stop Work Notice dated
31.12.2020 was issued 15 months after the Gazette Notification
dated 21.09.2019, raising serious doubts about the Respondent’s
due diligence and its reckless approach in dealing with regulatory
issues. The Respondent was grossly negligent in addressing critical
compliance matters and is now seeking to take advantage of its own
wrongful conduct. The Hon’ble Supreme Court and various High
Courts have consistently held that a developer cannot claim force
majeure when delays arise due to their own negligence, lack of
due diligence, and failure to disclose material facts. The
Respondent’s attempt to invoke force majeure is therefore legally
untenable and unsustainable. That it is clearly stated in the
judgment of Pioneer Urban Land & Infrastructure Ltd. v.
Govindan Raghavan, (2019) 5 SCC 725 that a developer cannot
rely on external circumstances to evade liability when it has acted
negligently and failed to disclose material facts. Furthermore,
Hon’ble Court Held that force majeure cannot be claimed if the
developer was aware of regulatory issues before execution of the
agreement and failed to take corrective measures in the case of
Wing Commander Arifur Rahman Khan & Ors. v. DLF
Southern Homes Pvt. Ltd. & Ors., (2020) 16 SCC 512. Given
the above, it is evident that the Respondent is wrongfully seeking to
take advantage of its own negligence to evade liability. The
invocation of force majeure in the present case is legally
unsustainable and must be outrightly rejected.
9. Complainant states that the principle of force majeure is often
invoked by developers as a defense to justify project delays and
escape liability for failing to hand over possession within the
stipulated timelines. While force majeure refers to unforeseeable
events beyond the control of parties, courts have consistently
held that it cannot be misused to shield a developer’s
negligence, lack of due diligence, and failure to disclose
material facts. The doctrine of force majeure finds its roots in
contract law, specifically under Section 56 of the Indian
Contract Act, 1872, which deals with the impossibility of
performance. It is also recognized under Section 6 of the Real
Estate (Regulation and Development) Act, 2016 (RERA),
which allows developers to seek an extension of registration if the
project is delayed due to force majeure events. However, courts
have made it clear that developers cannot take refuge
under force majeure when delays result from their own
wrongful conduct. In support of the contentions,
Complainant relying on the Judgment of M/s Imperia
Structures Ltd. v. Anil Patni & Ors., (2020) 10 SCC 783 where
The Supreme Court ruled that failure to comply with statutory
obligations under RERA, including updating construction
progress and disclosing litigation issues, amounts to
deficiency in service. The developer in this case failed to exercise
due diligence, and its invocation of force majeure was rejected. It is
also reaffirmed that developers cannot claim force majeure when
delays are attributable to their negligence, non-disclosure of
material facts, or lack of due diligence. Hon’ble Court also held that
a developer cannot rely on force majeure when delays arise
due to its own failure to secure necessary approvals,
conduct proper title searches, or disclose regulatory
restrictions. The Court observed that such acts amount to
misrepresentation and unfair trade practice. Further, court also
observed that developers cannot cite force majeure as a
defense when they were aware of regulatory issues before
launching the project and failed to act prudently. That in the
case of Kolkata West International City Pvt. Ltd. v. Devasis
Rudra, (2019) 18 SCC 692 Court ruled that misrepresentation
and non-disclosure of crucial legal restrictions on land
development render an agreement voidable. In this case, the
developer failed to inform homebuyers of legal disputes affecting
the land, and its claim of force majeure was dismissed.
That in reference to the above judgments, it is clear that
1. Force majeure cannot be invoked for foreseeable regulatory
hurdles: Developers are expected to conduct proper title searches
and due diligence before launching a project.
2. Failure to secure approvals does not constitute force
majeure: If a developer proceeds without obtaining necessary
clearances, delays arising from subsequent legal restrictions cannot
be justified under force majeure.
3. Non-disclosure of material facts invalidates force majeure
claims: Suppression of government notifications, pending litigation,
or other crucial information amounts to misrepresentation.
4. Delays caused by a developer’s negligence do not qualify for
force majeure protection: If delays arise due to lack of planning,
inefficiency, or statutory non-compliance, the developer remains
liable for the consequences.
Complainant also relying on the Recent RERA and Consumer Court
Rulings
Consumer courts and RERA authorities have consistently ruled in favor of
homebuyers where developers attempted to misuse force majeure.
a. The Haryana RERA Authority in 2022 penalized a
builder for citing force majeure despite failing to
secure requisite environmental clearances before
construction.
b. The National Consumer Disputes Redressal
Commission (NCDRC) in 2023 ruled that delays
caused by pending land acquisition disputes are
not force majeure but reflect the developer’s lack
of due diligence.
10. The invocation of force majeure is a legal shield meant for
genuine unforeseen events like natural calamities, war, or
government-imposed restrictions due to pandemics but in the
present case, respondent is trying to take an advantage of these
own wrong doings and negligence. That the Respondent cannot
exploit this doctrine to cover up their own negligence, non-
compliance with legal requirements, or suppression of material
facts. Courts have repeatedly emphasized the duty of transparency,
due diligence, and adherence to contractual obligations. Any failure
on these fronts not only invalidates force majeure claims but also
exposes developers to penalties, compensation claims, and
cancellation of agreements.
11. In Paragraph No. 8 of the reply, the Respondent has
asserted that it has carried out the development and construction of
the project, including the sale of units, with substantial progress and
has obtained the necessary plinth checking certificates from the
Pune Metropolitan Regional Development Authority. In response to
this contention, the Claimant submits that if the Respondent had
indeed made remarkable progress in development and
construction, as claimed, then the invocation of force majeure is
wholly untenable, contradictory, and an attempt to mislead
the Hon’ble Authority. The fact that the Respondent continued to
develop and sell units without disruption clearly establishes that the
alleged impact of COVID-19 was neither unforeseen nor
insurmountable. Hence, the Respondent cannot selectively
invoke force majeure to evade its contractual obligations
under the Agreement.
12. Moreover, the Respondent’s failure to fulfil its obligations
within the stipulated timeframe constitutes a direct
violation of Section 11 and Section 18 of the Real Estate
(Regulation and Development) Act, 2016 (RERA), which
mandate developers to ensure timely possession and accurate
disclosures to homebuyers. The contradictory stance taken by the
Respondent is nothing but an attempt to circumvent liability
and misrepresent material facts before the Hon’ble
Authority.
Negligence, in legal parlance, refers to the failure to exercise the
standard of care that a reasonably prudent person would have
exercised in a similar situation. The law does not excuse negligence,
whether in contractual obligations, statutory compliance, or
professional duties. Courts across jurisdictions have consistently
ruled that negligence, whether wilful or arising out of ignorance,
cannot serve as a defence to evade liability.
Complainant states that it is the duty and responsibility of the
respondent to conduct the proper title search and due diligence.
Complainant herein refere the legal maxim "ignorantia juris non
excusat" (ignorance of the law is no excuse) applies broadly to all
legal and contractual obligations. In commercial transactions, real
estate dealings, professional conduct, and administrative duties,
Respondent are expected to act with due diligence. Any failure to
adhere to these responsibilities, resulting in harm or contractual
breach, constitutes negligence, for which the law provides strict
liability. In support of the contentions, complainant relying on the
Wing Commander Arifur Rahman Khan v. DLF Southern
Homes Pvt. Ltd. (2020) 16 SCC 512 where The Supreme Court
held that developers who fail to conduct due diligence before
launching projects cannot later claim ignorance of legal hurdles. The
Court directed compensation for homebuyers, ruling that negligence
in verifying land titles and obtaining approvals cannot be excused.
The principle that negligence has no excuse under the law is a
cornerstone of legal jurisprudence. Whether in contractual
obligations, statutory compliance, or professional responsibilities,
courts have consistently rejected negligence as a defense. Judicial
precedents reinforce that every individual and entity must act with
due diligence, failing which they face legal consequences.
Therefore, diligence, awareness, and adherence to legal
duties remain the only safeguard against liability.
13. In Paragraph No. 14 of the reply, the Respondent has
contended that the first and second notifications were published
without its knowledge or consultation and that no intimation
was provided to the Respondent, including the Pune Metropolitan
Region Development Authority (PMRDA). The Complainant
categorically denies these contentions as being false,
misleading, and legally untenable. The Respondent was fully
aware of the notifications prior to launching the project and
commencing sales. Despite this knowledge, the Respondent
proceeded with the project in blatant disregard of
regulatory requirements, thereby attempting to unjustly benefit
from its own negligence and wrongful actions. It is a settled
principle of law that a party cannot take advantage of its
own wrongs (ex turpi causa non oritur actio).
Furthermore, if the Respondent now claims to have been unaware of
such notifications, it raises serious concerns regarding the due
diligence, statutory compliance, and regulatory approvals
obtained prior to the launch of the project. The failure to
conduct proper due diligence or obtain necessary regulatory
clearances before initiating the project amounts to gross
negligence and wilful omission, which cannot be excused under
the law.
The Respondent has further failed to discharge its burden of
proof by not producing any documentary evidence before the
Hon’ble Authority to substantiate its claim that the notifications
were unknown to it. This omission not only discredits the
Respondent’s claim but also demonstrates its attempt to evade
legal responsibility by misleading the Hon’ble Authority.
The Respondent’s claim of ignorance regarding the notifications is
nothing but an afterthought and a deliberate attempt to
evade accountability. The failure to conduct proper due
diligence before launching the project constitutes gross
negligence, which is not excusable under the law. The
Respondent’s omission of material facts amounts to
misrepresentation, violation of statutory obligations, and an
attempt to mislead both the Complainant and the Hon’ble
Authority.
14. In Paragraph No. 16 of the reply, the Respondent has falsely
contended that it had addressed a letter to the PMRDA objecting to
the stop-work notice on numerous grounds. This assertion is entirely
baseless and misleading, as the Complainant was never informed or
updated regarding any such communication. The Respondent has
failed to produce any documentary evidence on record to
substantiate this claim, thereby establishing that no such update
was ever shared with the Complainant. This deliberate omission was
clearly intended to mislead and deceive the Complainant with a
fraudulent ulterior motive.
Furthermore, regarding the Respondent's reference to Writ Petition
No. 2404/2021, the Complainant categorically relies on the contents
of the Hon’ble High Court's order dated 03.07.2021. The order
explicitly states that the Municipal Commissioner had directed the
petitioners to send their representative with documentary evidence
for a hearing scheduled at 1:00 PM on 07.01.2021. However, no
such hearing took place as the petitioners belatedly responded to
the show cause notice only on 04.02.2021—nearly four weeks after
the scheduled hearing date.
This unequivocally establishes that the Respondent is solely
responsible for its own default by failing to appear before the
Municipal Commissioner on the stipulated date and subsequently
filing a delayed reply. The resultant delay is entirely attributable to
the Respondent’s inaction. Accordingly, the Hon’ble High Court did
not grant any substantive relief to the Respondent but merely
provided an opportunity for a hearing.
Pursuant to the Hon’ble High Court's order, the hearing was
conducted, and the developer was expressly directed to halt
construction until the finalization of the alignment of the ring road
as proposed by MSRDC. It is imperative to highlight that the
Respondent, in blatant disregard of its obligations, failed to
communicate, intimate, or disclose this crucial development on the
RERA Portal. Additionally, the Respondent deliberately withheld this
material information from the Complainant, thereby breaching its
fiduciary duty and acting in bad faith.
15. That Writ Petition No. 8218/2021 has remained at the pre-
admission stage since 2021, and the Respondent has willfully failed
to pursue the matter, demonstrating a clear lack of diligence. The
Complainant further reiterates that the Respondent has deliberately
withheld these crucial details from the RERA portal, which
constitutes a blatant and gross violation of the RERA Rules and
Regulations. Additionally, the Respondent has failed to apprise the
Complainant of these developments in any manner, thereby
intentionally keeping the Complainant in the dark with a fraudulent
ulterior motive to mislead and deceive.
16. That Writ Petition No. 29853 of 2024 has not filed properly
and the same is under objection as per the order dated 22.11.2024
which states that “The aforesaid writ petition was notified on 23 and
24th October 2024 for removal of office objections as provided under
Rule 3 sub rule (ii) of the chapter XVII of the Bombay High Court
Appellate Side rules, 1960. The Ld. Advocate and the Petitioner have
failed to remove office objections – finally 2 weeks’ time granted to
the Petitioner to remove the objections and otherwise appropriate
order will passed”. It is noteworthy to mention herein that the said
writ petition is still under the objections and the Respondent has
wilfully failed to pursue the matter, demonstrating a clear lack of
diligence. The Complainant further reiterates that the Respondent
has deliberately withheld these crucial details from the RERA portal,
which constitutes a blatant and gross violation of the RERA Rules
and Regulations. Additionally, the Respondent has failed to apprise
the Complainant of these developments in any manner, thereby
intentionally keeping the Complainant in the dark with a fraudulent
ulterior motive to mislead and deceive.
17. That in response to Para no 17 to 20, complainant states that the
Respondent’s blatant failure to adhere to statutory obligations under the
Real Estate (Regulation and Development) Act, 2016 (“RERA”), along with
gross negligence, misrepresentation, and willful suppression of material
facts, thereby causing grave prejudice to the Complainant. The
Respondent has not only defaulted on its contractual obligations but has
also attempted to mislead the Hon’ble Authority by raising frivolous
contentions, which are legally untenable.
At the very outset, the Complainant categorically denies all
allegations and contentions made by the Respondent in its
Reply/Written Statement, except those expressly admitted herein.
The Respondent’s claims are not only devoid of merit but are also
unsubstantiated, as they fail to provide any documentary evidence
supporting their assertions. The Respondent has deliberately
withheld critical information from the Complainant and has failed to
provide regular updates on the progress of the project, thereby
violating the fundamental principles of transparency and good faith.
It is pertinent to note that Writ Petition No. 8218/2021 has remained
at the pre-admission stage since 2021, with the Respondent failing
to pursue the matter, reflecting a lack of due diligence.
Furthermore, Writ Petition No. 29853/2024 has not been properly
filed and remains under objection as per the Hon’ble Court’s order
dated 22.11.2024. This demonstrates the Respondent’s deliberate
inaction and failure to act in a responsible and legally compliant
manner.
The Respondent’s reliance on the doctrine of force majeure is
completely misconceived, as it had prior knowledge of regulatory
restrictions, including the Gazette Notification dated 21.09.2019,
which was issued well before the execution of the Agreement with
the Complainant. Despite such prior knowledge, the Respondent
failed to disclose this material fact, thereby engaging in an unfair
trade practice. Established judicial precedents, including Pioneer
Urban Land & Infrastructure Ltd. v. Govindan Raghavan (2019) 5
SCC 725, have categorically held that a developer cannot escape
liability by invoking one-sided contractual terms or by suppressing
material information from homebuyers.
Further, the Respondent has violated its statutory obligations under
RERA by failing to upload construction progress updates on the
RERA portal and withholding critical litigation details from
homebuyers. Such omissions constitute a direct breach of Sections
11 and 18 of RERA and have been recognized as deficiency in
service by the Hon’ble Supreme Court in M/s Imperia Structures Ltd.
v. Anil Patni & Ors. (2020) 10 SCC 783. Additionally, the Hon’ble
Courts have consistently held that non-disclosure of material facts
and lack of transparency amount to unfair trade practices under
consumer protection laws, as reaffirmed in Lucknow Development
Authority v. M.K. Gupta (1994) 1 SCC 243.
The Complainant further submits that the Respondent has
attempted to mislead the Hon’ble Authority by falsely claiming that
it had objected to the stop-work notice issued by PMRDA. However,
no documentary evidence, such as letters, emails, or any official
communication, has been placed on record to substantiate this
claim. Moreover, the Respondent’s delay in responding to the show
cause notice in Writ Petition No. 2404/2021—by filing a reply four
weeks after the scheduled hearing—demonstrates a clear lack of
diligence on their part. Consequently, the Hon’ble High Court did not
grant any relief to the Respondent except an opportunity to be
heard. The subsequent hearing resulted in a direction to halt
construction until the finalization of the alignment of the ring road
as proposed by MSRDC, a crucial development that the Respondent
failed to disclose to the Complainant.
The Respondent’s conduct, including suppression of material
information, failure to upload crucial updates on the RERA portal,
and non-disclosure of pending litigation, clearly violates statutory
provisions and established legal principles. The invocation of force
majeure is legally untenable as it is being used as a shield to cover
up the Respondent’s own wrongful actions and regulatory non-
compliance. The Hon’ble Supreme Court in Wing Commander Arifur
Rahman Khan & Ors. v. DLF Southern Homes Pvt. Ltd. & Ors. (2020)
16 SCC 512 has categorically held that delays and non-
communication of project status are valid grounds for consumer
claims against developers.
That the Respondent’s malafide conduct, lack of due diligence, and
failure to comply with legal obligations render it liable for
appropriate legal consequences under RERA, the Consumer
Protection Act, 2019, and relevant contractual provisions. The
Complainant, therefore, seeks strict action against the Respondent
for its failure to act in good faith and discharge its obligations in
accordance with law.
PRAYER: -
In light of the foregoing facts and circumstances, the Complainant
most respectfully prays that this Hon’ble Authority may be pleased
to:
a. Admit the present complaint and take cognizance of the
Respondent’s acts of misrepresentation, breach of contractual and
statutory obligations, and deficiency in service.
b. Direct the Respondent to refund the entire amount paid by the
Complainant towards the said unit, along with interest at an
appropriate rate, from the date of payment till the date of actual
realization, in accordance with the provisions of the Real Estate
(Regulation and Development) Act, 2016 and the Consumer
Protection Act, 2019.
c. Award compensation to the Complainant for the mental agony,
financial hardship, and harassment caused due to the wrongful
conduct of the Respondent.
d. Impose appropriate penalty on the Respondent for its deliberate
non-compliance with statutory obligations under RERA and its failure
to uphold transparency and good faith in its dealings with the
Complainant.
e. Pass any other relief(s) and orders as this Hon’ble Authority
may deem just, fit, and proper in the interest of justice, equity, and
good conscience.
BEFORE THE HON’BLE REAL ESTATE REGULATORY
AUTHORITY MUMBAI, MAHARASHTRA
COMPLAINT NO. CC005000000461143 /2024
IN THE MATTER OF:
PRIYANKA RAJENDRA SHINDE & ANR. …
COMPLAINANT
VERSUS
M/S AVIOR MERLIN VENTURES LLP …
RESPONDENT
AFFIDAVIT
I, GAURAV MOHAN BARU, R/O A-47, ROOM NO.2, HIMALAYA APERTMENT,
SECTOR NO. 15, AIROLI, NAVI MUMBAI-400708. do herby solemnly affirm
the state as under:
1. That I am the complainant in the above-mentioned matter and as such I am
well conversant with the facts and circumstances of the case hence, I am
competent to swear this affidavit.
2. That the accompanying Rejoinder has been drafted by my counsel under my
instructions and the contents of the same may kindly be read as part and
parcel of this affidavit as the same has not been produced herein for the sake
of brevity.
3. That the contents of the accompanying Complaint are true and correct to the
best of my knowledge, information and belief, no part of it is false and no
material has been concealed therefrom.
DEPONENT
VERIFICATION
Verified at Delhi on this the.......day of ……………..............that the contents of
the aforesaid affidavit are true and correct to the best of my knowledge and
belief, no part of it is false and no material has been concealed there from.
DEPONENT