11605748
11605748
NATIONAL MUSEUM
SUB-PROJECT
TABLE OF CONTENTS
Volume 3IT
• INSTRUCTIONS TO TENTERERS
- INSTRUCTIONS TO TENDERERS
- APPENDIXES
- ENCLOSURES
- FORM OF TENDER
*** MPWH Letter head
Dear Sir,
THE HASHEMITE KINGDOM OF JORDAN has received an ODA Loan from JAPAN BANK
FOR INTERNATIONAL COOPERATION (hereinafter referred to as JBIC) toward the cost of
TOURISM SECTOR DEVELOPMENT PROJECT, NATIONAL MUSEUM SUB-PROJECT and
intended to apply the proceeds of the loan to payment under the contract. Disbursement of ODA
Loan by JBIC will be subject, in all respects, to the terms and conditions of the Loan Agreement,
including the disbursement procedures and the “ Guidelines for Procurement under JBIC ODA
Loans” . No Party other than THE HASHEMITE KINGDOM OF JORDAN shall derive any rights
from the Loan Agreement or have any claim to loan proceeds. The above Loan Agreement will
cover a part of the project cost. As for the remaining portion, THE HASHEMITE KINGDOM OF
JORDAN will take appropriate measures for finance.
JBIC requires that Tenderers and Contractors, as well as THE HASHEMITE KINGDOM OF
JORDAN, under the Contracts funded with JBIC ODA Loans and other Japanese ODA, observe the
highest standard of ethics during the procurement and execution of such contracts. In pursuance of
this policy, JIBC;
(a) will reject a proposal for award if it determines that the tenderer recommended for award has
engaged in corrupt or fraudulent practices in competing for the contract in question;
(b) will recognize a contractor as ineligible, for a period determined by JBIC, to be awarded a
contract funded with JBIC ODA Loans if it at any times determines that the contractor has
engaged in corrupt or fraudulent practices in competing for, or in executing, another contract
funded with JBIC ODA Loans or other Japanese ODA.
THE MINISTRY OF PUBLIC WORKS AND HOUSING (hereinafter referred to as “ MPWH” )
invites sealed tenders from prequalified eligible Tenderers for construction and completion of the
NATIONAL MUSEUM SUB-PROJECT (hereinafter referred to as “ the Works” ) in accordance
with the following documents:
VOLUME I - Instructions to Tenderers
n Appendixes
n Enclosure
VOLUME II - Specifications
VOLUME III - Bill of Quantities
VOLUME IV - Drawings
VOLUME V - Conditions of Contract
A Tender is required for the Construction of the NATIONAL MUSEUM SUB-PROJECT and its
associated works for the Tourism Sector Development Project as described in the Tender Documents
and to be submitted under sealed cover in accordance with the Instruction to Tenderers.
3. Clarification Meeting
If the Tenderer has any questions regarding the Tender Documents and/or other detail conditions,
the Tenderer must submit written questions to the MPWH GOVERNMENT
th
TENDERS DIRECTORATE by ---- ----------- 2000.
The Clarification Meeting will be held on ---th ---------- 2000, time 09:00, at the MPWH
GOVERNMENT TENDERS DIRECTORATE.
4. Tender Submission and Tender Opening
The completed Tender should be submitted to the MPWH GOVERNMENT TENDERS
DIRECTORATE at the following address between the hours of 09:00 - 11:00 on the ----th -------
2000.
The Tender will be opened on same day of Tender submission at --------- hours.
5. Tenderers will be informed in due course of the result of the Tender Review.
6. All other necessary requirements for the preparation and submission of Tenders are given in the
INSTRUCTIONS TO TENDERERS.
Nasir Madadha
THE GOVERNMENT OF
THE HASHEMITE KINGDOM OF JORDAN
THE MINISTRY OF TOURISM & ANTIQUITIES
THE MINISTRY OF PLANNING
(JO – P11)
OF
VOLUME I
INSTRUCTIONS TO TENDERERS
September - 2000
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
TABLE OF CONTENTS
1. GENERAL -------------------------------------------------------------------------- 1
4. QUALIFICATION OF TENDERER--------------------------------------------- 4
1
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
INSTRUCTIONS TO TENDERERS
1. GENERAL
a. THE MINISTRY OF PUBLIC WORKS AND HOUSING (hereinafter referred to as “MPWH”),
PROJECT MANAGEMENT UNIT (MPWH) of THE HASHEMITE KINGDOM OF JORDAN
has received a loan from JAPAN BANK FOR INTERNATIONAL COOPERATION (hereinafter
referred to as the “JBIC”) for the Tourism Sector Development Project, National Museum
Sub-Project. The MPWH shall apply the loan towards the cost of the project and intends to apply
the proceeds of the loan to eligible payments under this contract for which this invitation to tender
is issued (hereinafter called "the Contract"). Disbursement of loan by the JBIC will be made only at
the request of the MPWH and upon approval by the JBIC in accordance with the terms and
conditions of the Loan Agreement No. JO-P11, dated 2nd December 1999 including “Guidelines for
Procurement under JBIC ODA Loans” and will be subject in all respects to the terms and
conditions of the said agreement. No party other than MPWH shall derive any rights from the Loan
Agreement or have any claim to loan proceeds.
b. Fund for the both foreign and local currency portions of the Project covered under this Contract is
financed under the said Loan Agreement, and it is intended that proceeds of this loan will be
applied to payment for the foreign and local currency portions under the Contract except Taxes and
Duties which will be borne by the Government of the Hashemite Kingdom of Jordan (hereinafter
referred to as the “Government”).
c. The proceeds of the loan are required to be used with due attention to considerations of economy,
efficiency and non-discrimination among countries which are eligible for procurement of goods
and services (such countries are hereinafter called "The eligible source countries").
The list of Eligible Source Countries is included in the Appendix “M“
d. Only those contractors who have been pre-qualified by the MPWH will be eligible to participate in
this Tendering. The MPWH is required to submit to the JBIC a complete statement of the source
and origin of the plant, materials and services furnished under the Contract. To assist the MPWH in
this matter, the Tenderer shall submit a complete breakdown of the source or origin of all plant,
materials and services furnished under the Contract.
e. The Tenderer shall familiarize himself with the forgoing requirements and, in submitting a
Tender. The Tenderer shall be deemed to have taken account of and complied with the
Government laws, regulations, agreement, procurement procedure and other qualifying
requirements.
ITT/1
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
a. Site Location: Ali Bin Abi Taleb Street, Ras Al-Ein, Amman
See the Location Map Drawing
b. Development Site Area :15,600m2
- Building area in total : 4,090m2
- Car parking area : 1,400m2
- Entrance plaza : 1,560m2
- Outdoor exhibition space : 700m2
- Others (landscaping areas) : 7,850m2
c. Building and associated facilities
(a) Total floor area : 9,230m2
- Main building : 8,150m2
Basement floor : 2,910m2
Ground floor : 2,510m2
st
1 floor (Mezzanine) : 590m2
2nd floor : 2,140m2
- Annex-building : 940m2
Ground floor : 940m2
- Bridge : 140m2
(b) Exhibition Galleries
- Permanent Gallery : 3,030m2
- Temporary Gallery : 350m2
- Outdoor Space : 700m2
(c) Number of stories
- Main building : 3 stories and 1 basement floor
- Annex building : 1 story
(d) Type of structure: Reinforced concrete
(e) Foundation type: Mat slab foundation
(f) Other provisions
- Exhibition equipment and materials
- Utility services
- Landscaping and car parking
ITT/2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
3. TENDER DOCUMENTS
a. The Tender Documents consist of the followings:
ITT/3
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
b. The Tenderer, whether or not submits a tender proposal, shall treat all the Tender Documents as
private and confidential. The Tenderer shall not use them other than for the preparation of his
tender proposal and shall not in part or in whole reproduce or release them to any third party
without prior written consent of the MPWH. The Tenderer, however, may transmit to a third
party such part of the Tender Documents as necessary for the purpose of preparing his tender
proposal provided that such third party undertakes to keep confidential.
The MPWH may deem any violation of this secrecy obligation by such third party as the same
by the Tenderer.
4. QUALIFICATION OF TENDERER
a. Only those Tenderers who have been pre-qualified by the MPWH will be eligible to participate
in this tendering.
b. If a Tenderer has been pre-qualified in association with other companies as a joint venture,
consortium and/or with one or more major subcontractors (a subcontractor responsible for more
than Thirty percent (30%) of the total value of the work) this group must be jointly maintained
in tendering and contracting, except that subcontractors, other than major subcontractors, can be
included, excluded or substituted at any time subject to the approval of MPWH.
c. Any pre-qualified Tenderer may not change his original joint operation partner(s) who has
(have) been proposed at the stage of Prequalification and approved by the MPWH.
e. During the Tender period, the Tenderer is obliged to attend all events announced officially by
the MPWH.
ITT/4
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
Should the Tenderer required further visit and inspection of the site, the Tenderer may visit and
inspect the site, on his own responsibility and at his own expense, to obtain all information that
may be necessary for the purpose of preparing his Tender and entering into a Contract.
b. The Site investigation report is included in the Appendix “J” as a guide only for preparing his
Tender, but without assurance as their accuracy or applicability and without prejudice to the
Tenderer’s liability.
c. The Tenderer shall be responsible for the examination and understanding of all parts of the
Tender Documents furnished.
d. All divisions or amendments to the Tender Documents shall be made through the formal
addenda duly issued by the MPWH.
e Any neglect or failure on the part of the Tenderer to obtain reliable information and physical
conditions on the spot or elsewhere, or any other matters affecting the execution, completion
and maintenance of the Works, the Tender Price and the Contract shall not relive the Tenderer
whose tender proposal is accepted, of the responsibility for completing and handing over the
Works as defined in the Contract.
b. The meeting will be held for the purpose of clarifying any elements of the proposed work and
ITT/5
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
also for answering all written questions received from the prospective Tenderers before the time
of the pre-Tender meeting and questions which may arise during the meeting.
c. Should the Tenderer have any query on any matter concerning the Tender Documents, such
query shall be sent to the MPWH in writing in the form provided in Appendix “K” not later
than twenty-one (21) days prior to the Tender Opening Date. Each addendum to answer such
query and/or to notify modifications will be issued by the MPWH Government Tenders
Directorate not later than fourteen (14) days prior to the Tender Opening Date. Each Addendum
will be distributed to all those who have been issued the Tender Documents and who shall
acknowledge receipt of each Addendum by signing and returning the attached Receipt Form.
All Addendum issued will become part of the Tender Documents.
b. All taxes and duties, including custom duties and import taxes, levies in accordance with laws
and regulations of the Hashemite Kingdom of Jordan in connection with the performance of the
Works to be paid by the Contractor, (those taxes and duties shall be bone by the Government in
accordance with the Sub-Clause 1, b of the Instructions to Tenderers), shall be deemed to be
included in the Tender Price.
c. Attention of the Tenderer shall be drawn to the fact that local regulations require special
formalities to be complied with in connection with the ordering, purchasing and importing of
materials and plant.
10. SIGNING
a. A Tender by corporation shall be executed in the official corporate name followed by the
signature and designation of the president, secretary or person(s) legally authorized to bind the
corporation. A Power of Attorney granting the person to sign the Tender Proposal shall be
enclosed with the tender proposal.
b. A Tender by joint operation shall be executed and designated by one of the partners or by an
authorized representative as specified hereinbefore.
c. A power of Attorney giving authorization to sign as the representative of the corporation or the
joint operation shall be attached to the Tender.
ITT/6
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
investigations, the preparation and submission of his Tender including all accompanying
documents, Tender Security, authentication and other incidental cost shall be borne by the
Tenderer.
12. WITHDRAWAL
The Tender, once submitted, shall not be withdrawn by the Tenderer, for any reasons whatsoever.
If the Tenderer withdraws before expiration of the Tender Validity, the amount of his Tender
Security shall be forfeited to the MPWH by virtue of this Clause.
Tender shall comprise the following documents which are categorized into two packages.
PACKAGE –I DOCUMENTS shall contain all documents as encountered below with all the
information except the value of the Tender. All prices, rates and totals comprising the Tender shall
be entirely confined to the PACKAGE - II DOCUMENTS.
In case there is discrepancy between the original set and the copies of the Tender, the original shall
govern.
b. Certification of submission of Tender Security certifying the Tender Security has included in
Package- II Documents (marked as Enclosure No.2)
ITT/7
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
f. Detailed monthly Cash Flow of Anticipated Contractor Payments. (marked as Enclosure No.
14)
ITT/8
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
b. Individual schedule rates and item prices, whether quoted on unit price basis or on a
lump-sum basis in the Bill of Quantities, will be only used for purposes of tender evaluation
and comparison, interim payments calculation, and, in some cases, of price basis for issuance
of variation order as prescribed in the Conditions of Contract.
c. The Bill of Quantities has an entry for each item on which payment shall be made and no
other allowance of any kind shall be made unless specifically provided for in the Tender
Documents. In the appropriate spaces provided for in the Bill of Quantities, opposite each
Tender item, the Tenderer shall specify the unit rate or lump sum for the work and/or services
included under the item. If the rate of an item is not filled in, the cost of that item shall be
deemed to be included in the unit rate for other items.
d. In case of discrepancy between the “Unit Rate” and the corresponding “Total Amount”
entered for any item in the Bill of Quantities, the “Unit Rate” shall govern.
The foreign currency (international traded currency) percentage quoted by the Tenderer in his Tender
shall be on the basis of the justification made by the price analysis submitted by him as described below,
giving the breakdown of the foreign and local components of the pay items specified in the Bill of
Quantities.
The foreign currency component shall be calculated according to the following principles:
a. Expenditures estimated to be incurred in Jordan for goods and services obtainable locally shall be
classified as local component for all Tenderers
b. A Tenderer from a foreign country should classify all expenditures to be incurred in other eligible
source countries of the Japan Bank for International Cooperation (JBIC) for materials and plant
(C.I.F. port of entry, Jordan) produced in and/or services supplied from such countries including
salaries and wages of foreign personnel as well as the Contractor’s profits and his office overhead as
foreign component expressed in the currencies of such countries and converted into Jordanian Dinar.
A Tenderer from a foreign country shall, when so requested by the MPWH, produce letters of credit
covering expenditures for material and plant.
c. A Tenderer from Jordan shall classify only such expenditures estimated to be incurred in other
eligible member countries of the JBIC for materials and plant (C.I.F. port of entry, Jordan) produced
in and/or services supplied from such countries as foreign component expressed in Jordanian Dinar.
A Tenderer from Jordan shall, when so requested by the MPWH, produce letters of credit covering
such expenditures.
ITT/9
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
d. The foreign exchange component in respect of construction equipment shall be limited to the value of
depreciation of such equipment during the period of construction.
e. On the basis of the price analysis made according to the above principles, each Tenderer shall enter
in the Foreign Exchange Form included as Appendix “E”, in the Tender Documents, the required
percentage of foreign currency in relation to the total amount of the Tendered Sum.
Should the Contractor fail to submit his detailed price analysis with his Tender, the required
percentage of foreign currency shall be considered to be nil irrespective of percentage of foreign
currency stated by the Tenderer in Appendix “E”, Foreign Exchange.
f. The foreign exchange rates that should be applied in the calculation of the unit rates and /or
lump-sum prices of the Foreign Currency Component are to be entered in Appendix “E”, Foreign
Exchange. The rate shall be the T/T Buying Rate for the Jordanian Dinar, available from the Central
Bank of Jordan, prevailing twenty-eight (28) days prior to the date of the opening of the Tenders.”
The Currency Exchange Rate stated in the Appendix “E”, Foreign Exchange, is fixed duration of
the Contract Period.
b. In exceptional circumstances, prior to expiry of the original Tender validity period, the
MPWH may request the Tenderer for an extension of the period of Validity. The request and
responses thereto shall be made in writing.
c. The Tenderer will be required to extend, at his own expense, the validity of his Tender
correspondingly. The provision of Clause 17 regarding discharge and forfeiture of Tender
Security shall be continue to apply during extended period of Tender validity.
b. The Tender Security shall be valid for thirty (30) days beyond the validity of the Tender.
c. Where the Tenderer is a single company, the Security shall be in the same name of that
company. Where the Tenderer is a joint venture/consortium, the Security shall be in the name
of joint venture/consortium as expressed in the Tender.
ITT/10
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
e. The Tender Security of the successful Tenderers will be discharged when the successful
Tenderer has signed the Contact Agreement and furnished the required Performance Security.
b. The original and copies of the Tender shall be typed in indelible ink. The Tender, Appendix to
Tender, Enclosure No. 1 to 14, together with all Summary, Final Summary and Overall
Summary pages of the Bill of Quantities shall be signed by a person (or persons) duly
authorized to bind the Tender. Proof of authorization shall be furnished in the form of written
Power of Attorney which shall accompany the Tender. All pages of the Tender, where
necessary, entries or amendments have been made in line with addenda (Notice to Tenderer)
shall be signed by the person (persons) signing the Tender.
c. The complete Tender shall be without alteration or erasures, except those to accord with
written Notice to Tenderers issued by the MPWH or as necessary to correct errors made by
the Tenderer, in which case such corrections shall be initialed by the person (or persons)
signing the Tender.
d. All pages of the Tender, except those referenced in Clause 18-1,b above, shall be initialed by
the person (or persons) signing the Tender.
ITT/11
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
b. Package –I and Package –II Documents shall be submitted in separate envelope or container
in the same manner specified in Sub-clause 18-2, a, above.
c. Each complete set of Tender Documents shall be in envelope or container and shall consist of:
PACKAGE – I DOCUMENTS
Contained in a sealed envelope or container bearing the following identification:
PACKAGE – II DOCUMENTS
Contained in a sealed envelope or container bearing the following identification:
ITT/12
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
18-3. Submission
a. The envelop or container shall be personally delivered by the Tenderer or his duly authorized
representative to the address stated Sub-clause 18-2, f. above, and shall be received by the
MPWH only during the submission time and date announced in the Letter of Invitation to
Tenderer. The Tender sent by cable, telex or facsimile will not be accepted.
It is to be fully understood that any risk accompanied by the submission of his Tender
Proposal until its physical receipt by the MPWH shall solely rest with the Tenderer.
b. Each envelope or container will be time/date-stamped by the MPWH as it is received and will
be maintained, sealed and safeguarded in the place with routine security and confidentiality.
c. Any Tender that has been submitted in the period other than specified by the MPWH shall be
rejected, for any reasons whatsoever.
e. The Tenderer shall inform the MPWH, within seven (7) days of receipt of Tender Documents,
as to whether he intends to submit the Tender or not by filling the form of Request for Tender
Acknowledgement Appendix “L”.
b. The MPWH may, at their discretion, extend the closing date for submission of Tenders by
issuing addendum in accordance with the Clause 8, (Interpretation of Tender Documents
/Pre-tender meeting), in which case all rights and obligations of the MPWH and the Tenderers
previously subject to the original submitting date shall thereafter be subject to the new
submitting date as extended.
c. Any Tender submitted to the MPWH other than during the time and date specified for
submission of Tenders shall be returned un-open to the Tenderer.
b. The Tenderer’s authorized representatives who are present shall sign a register as evidence of
attendance.
c. Any Tender for which acceptable Notice of Withdrawal have been submitted shall not be
opened.
ITT/13
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
d. The MPWH will announce the Tenderer’s names, withdrawals (if any) and the names of
Tenderers who have not submitted their Tenders.
e. The MPWH shall prepare, for their own records, minutes of the Tender Opening, including the
information disclosed to those present in accordance with Sub-Clause 19, b, above.
f. The MPWH will open Package -I Documents to examine the Tender to determine whether they
are complete, whether the documents have been properly signed, and whether the documents
are generally in order in accordance with Sub-Clause 18 of the Tender Documents.
g. Should the Package -I Documents of the Tender be determined by the MPWH to be not in
compliance with the requirements of the Tender Documents, then such Tender shall be rejected
and returned to the Tenderer.
h. Deviations and omissions will be recorded. Incomplete Package –I Documents will be returned
to the Tenderer and results in termination of the Tender to participate in the subsequent phase of
the Tender.
c. The MPWH reserve the right to accept or reject any or all Tenders and is not bound to accept the
lowest Tender. The MPWH shall not be liable for any claim regarding the procedure of the
evaluation of the Tendering and shall not be bound to give any reasons for his decision to any
Tenderer.
b. The weighting system will be utilized for technical evaluation. The Tender scoring more than
the predetermined level of each evaluation item will be deemed to be technically qualified.
ITT/14
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
8) Outline Construction Plan and Temporary work plan (Enclosure No. 8).
The Construction plan including, layout plan for temporary works, method statement,
description of sequence, and quality and safety control procedures.
A Construction Plan and Proposed Layout Plan for Temporary Works of project sites
showing the Tenderer’s proposed temporary roads, construction plan, temporary facilities,
ITT/15
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
such as, camps, offices, workshops, storage, etc.. The designated location and area for
the Temporary facilities is included in the Appendix “I”.
10) The list of major materials and plants (Enclosure No. 10).
A List of Major Materials and Plant to be incorporated into the Works as called for in the
Specifications together with necessary catalogues, brochures and technical supporting
details submitted by the Tenderer will be evaluated.
d. If Package - I Documents of the Tender are found not contractually and technically qualified,
then the corresponding Package - II Documents of the Tender will not be opened and will be
returned to the Tenderer.
b. The contractually and technically qualified Tenderer’s authorized representatives who are
present shall sign a register as evidence of attendance.
c. The MPWH shall prepare, for their own records, minutes of the Tender Opening, including
the information disclosed to those present.
d. The MPWH will open the Package - II Documents to examine Tender to determine whether
they are complete, whether the documents have been properly signed, and whether the
ITT/16
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
e. Should the Package - II Documents of the Tender be determined by the MPWH to be not in
compliance with the requirements of the Tender Documents, then such Tender shall be
rejected and returned to the Tenderer.
f. At this opening, the Tenderers satisfying the requirements of Package - II Documents will have
their names and Tender Prices announced.
g. The Tenders that have passed the contractual and technical evaluation and the foregoing
requirements will then be checked arithmetically and evaluated financially.
h. Any arithmetic errors in computation and summation will be corrected by the MPWH as
follows:
1) Where there is a discrepancy between amount quoted in figures and quoted in words, the
amount in words will govern and
2) Where there is a discrepancy between the unit rate and the total amount derived from the
multiplication of the unit rate and the quantity, the unit rate as quoted will govern, unless
in the opinion of the MPWH there is an obviously gross misplacement of the decimal
point on the unit rate, in which event the total amount as quoted will govern and the unit
rate will be corrected.
i. The amount stated in the Tender will be adjusted by the MPWH in accordance with the above
procedures for the correction of errors with the concurrence of the Tenderer, and it shall be
considered as binding upon the Tenderer. If the Tenderer will not accept the corrected amount
of the Tender, his Tender will be rejected and his Tender Security will be forfeited.
j. The Tender Prices and Breakdown of Major Rates will be evaluated in comparison with the
estimated cost of the Project, which has been authorized by the MPWH.
Where there is a gross discrepancy between the prices of the Work in the Tender and in the
MPWH estimation, the Tenderer may be asked for further clarification of his Tender.
ITT/17
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
b. The decision of the MPWH with respect to acceptance of Tender shall be final and no
correspondence or communication on the matter will be entered into.
c. The MPWH reserves the right to reject any or all Tenders, to waive any required formality in
the Tenders received, and to disregard any Tender which is obviously unbalanced, particularly
on the major items. The right is also reserved to reject the Tender of any Tenderer who has
previously failed to satisfactorily perform or complete any construction contract undertaken
by him.
b. After receipt of the Letter of Acceptance, the successful Tenderer shall submit a Performance
Security within fourteen (14) days as specified in the Conditions of Contract and sign the
Contract in the form attached within the time specified in the said notice. In return for submission
of the Performance Security, the Tender Security shall be released to the successful Tenderer.
c. The awarded Tenderer shall dispatch a duly authorized person(s) at his cost to the place where
the MPWH designates for negotiating and entering into a Contract Agreement.
d. The MPWH will issue the Notice to Proceed the Work within fourteen (14) days after receipt
of the performance Security submitted by the Contractor. The commencement of the Contract
will start within twenty-eight (28) days from the issuing date of the written Notice to Proceed
the Work, when the Contractor commence the work as defined as the Date of Commencement
of the Works.
ITT/18
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX
APPENDIX A
Amount of performance Security 10.1 Ten percent (10%) of the respective currency component of the
total contract Sum stated in the Contract Agreement
Submission of Performance Security 10.2 within fourteen (14) days from after receipt of Letter of Acceptance
Period for submission of Insurance 25.1 Within twenty-eight (28) day of the commencement date
Time for Completion of the Works 43.1 Twety- four (24) months after Commencement date
Period for commencement from the ITT 23, d Twenty-eight (28) days
Employer's Notice to Proceed
Delay damages for the Works 47.1 a 1/1,000 (0.1%) of the final Contract Sum per day, in the
currencies and proportions in which the Contract Sum is payable.
Maximum amount of liquidated damages 47.1 a Five percent (5 %) of the final Contract Sum
Plant and Materials for payment when 60.3 Eighty percent (80%) of plant and materials rate
delivered to the Site
Percentage of Retention 60.5 Five percent (5%) of the Accepted Contract Sum
Limit of retention Money 60.5 Five percent (5%) of the Accepted Contract Sum
Payment of Retention Money 60.6 Fifty percent (50%) upon issuance of Taking-Over Certificate
Fifty percent (50%) upon expiration pf Defect Liability Period
Total Advance Payment 60.7, a) Fifteen percent (15%) of the Accepted Contract Sum
Repayment amortization of Advance Payment 60.7, a) Twenty percent (20%) from progress payments
Completion of repayment of Advance Payment 60.7, b) Prior to eighty percent (80%) of Contract Sum certified
Period of Interim Payment 60.8 Within fifty-six (56) days from receipt of Contractor's monthly statement
Time for Payment 60.11 Forty-five (45) days after delivery of payment certificate the Employer
APPENDIX B
FORM OF AGREEMENT
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX B
FORM OF AGREEMENT
FOR
FORM OF AGREEMENT
FOR
CONSTRUCTION
OF
TOURISM SECTOR DEVELOPMENT PROJECT
NATIONAL MUSEUM SUB-PROJECT
BY AND BETWEEN
The MINISTRY OF PUBLIC WORKS AND HOUSING (MPWH) of THE HASHEMITE KINGDOM
OF JORDAN, Mr. Nasir Madadha, the General Director of Government Tenders directorate, with
address at Eighth Circle, Albiader Street, Amman, The Hashemite Kingdom of Jordan, hereinafter
referred to as the “EMPLOYER”.
AND
Organized and existing under the law of the ------------------------, for this purpose represented by
Mr.----------------------------------- duly authorized to negotiate and sign this Contract Agreement by
virtue of Power of Attorney dated ---------------------------------------,
Having its office in ---------------------------------------------------------------------------------------------,
Hereinafter referred to as the “CONTRACTOR”.
FOA-1
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX B
WITNESSTH
WHEREAS the EMPLOYER is desirous that the execution and completion of the Works included in the
Contract Agreement;
1. In this Contract Agreement words and expression shall have the same meaning as are respectively
assigned to them in the Contract Documents hereinafter referred to.
2. The following documents (hereinafter referred to as the “Contract Documents”) shall be deemed to
form and be read and as an integral part of this Contract Agreement, namely;
4. The EMPLOYER hereby covenants to pay the CONTRACTOR in consideration of the execution
and completion of the Works the Contract Sum at the times and in the manner prescribed in the
Contract Documents.
FOA-2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX B
5. The Contract Sum to be paid by the EMPLOYER to the CONTRACTOR subject to the
requirements of this Contract is:
(J.D. )
(US$, )
6. The payment to the CONTRACTOR shall be made in Jordanian Dinar and Unites States Dollar.
The amount of Jordanian Dinar and Foreign Currencies certified by the Ministry of Public Works
and Housing shall be paid by bank check issued by the Ministry of Public Works and Housing in
favor of the CONTRACTOR.
7. Advance Payment being fifteen percent (15%) of the respective currencies, equal to;
(J.D. )
(US$, )
shall be made by the EMPLOYER to the CONTRACTOR, against an invoice from the
CONTRACTOR and submission of Bank Guarantee for Advance Payment acceptable to the
EMPLOYER, for the amounts received.
FOA-3
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX B
8. The Time for Completion of the Works shall be within Twenty-four (24) months from the
Commencement Day.
The Defect Liability Period shall be Three hundred thirty-five (365) days calculated according to
Sub-Clause 49.1 of the Conditions of Contract.
9. This Contact Agreement shall become effective upon the date the latest of the following conditions
have been satisfied;
IN WITNESS WHEREFORE, the parties have caused this Contract Agreement to be executed by their
respective duly authorized and empowered officers, on the day and year first above written.
Witness: Witness:
FOA-4
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX C
TENDER SECURITY
1. ,
2. In submitting his Tender, the Tenderer agrees to furnish a TENDER SECURITY through the
above named BANK in the sums of;
(J.D.
3. We agree to be the GUARANTOR to the EMPLOYER for the TENDER SECURITY in the
above sum.
FTS-1
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX C
4. In the Tenderer, who has submitted the Tender, does not abide by the TENDER or any related
conditions contained in the Tender Documents, we agree to pay above sums to the
EMPLOYER within fourteen (14) days after receiving written notification from the
EMPLOYER of the default of the TENDERER.
6. Notification to pay shall be issued by the EMPLOYER not later than thirty (30) days after the
expiry date of the TENDER SECURITY.
a. The TENDERER has accomplished his works in accordance with the Tender Documents
even if the expiry date is not due yet.
b. No notification to pay is issued by the EMPLOYER after thirty (30) days from the expiry
date of the TENDER SECURITY and is no longer effective.
FTS-2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX C
8. The TENDER SECURITY shall be returned to us after the Security has been fulfilled or
becomes ineffective.
Signature:
Name of Signatory:
Position:
FTS-3
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX D
PERFORMANCE SECURITY
1. WHEREAS the Ministry of Public Works and Housing of the Hashemite Kingdom of Jordan,
(hereinafter referred to as the “EMPLOYER”) has awarded a Contract for the TOURISM
SECTOR DEVELOPMENT PROJECT, NATIONAL MUSEUM SUB-PROJECT to
, (hereinafter referred to as the “CONTRACTOR”) in the
sums of :
(J.D. )
(US$. )
2. WHEREAS the CONTRACTOR is bound by the said Contract to submit to the EMPLOYER a
PERFORMANCE SECURITY for the amount of :
FPS-1
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX D
(hereinafter referred to as the “GUARANTOR”) and fully authorized to sign and to incur
obligation in the name of the GUARANTOR, hereby declare that the GUARANTOR shall
guarantee the EMPLOYER the full amount as set forth Clause 2 above.
4. After the CONTRACTOR has signed the Contract Agreement with the EMPLOYER, the
GUARANTOR shall be liable to pay the full amount as aforesaid upon first written demand
from the EMPLOYER if the CONTRACTOR fails to comply with the terms and conditions of
the Contract.
Provided always that no alteration in terms and conditions of the Contract Agreement between
the EMPLOYER and the CONTRACTOR or in the nature of the Works to be constructed,
completed and maintained thereunder and no allowance of time by the EMPLOYER under the
Contract nor any forbearance or forgiveness in or respect of any matter concerning the Contract
on the part of the EMPLOYER shall in any way release the GUARANTOR from any liability
under this SECURITY.
The GUARANTOR shall deliver the said amount to the EMPLOYER immediately without
delay against your receipt accompanied by your written statement certifying that the
CONTRACTOR failed to comply with the Contract terms and conditions and without it being
necessary to give any reason.
5. The GUARANTOR shall be valid for the whole of the Time for Completion and any extension
thereof, the Defect Liability Period and for the period thereafter until the receipt by the
CONTRACTOR of a Defect Liability Certificate issued in accordance with Conditions of
Contract Sub-Clause 62.1.
FPS-2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX D
6. If at any during the validity period of the SECURITY, the EMPLOYER grants an extension of
time to the CONTRACTOR, or the Contract, the GUARANTOR shall extend this SECURITY
under the same conditions for the required time.
7. Until the EMPLOYER shall issue an instruction to the GUARANTOR to the effect that this
SECURITY may be released, the GUARANTOR undertakes, notwithstanding the validity
period as stated in Clause 5 herein, to extend the validity under the same conditions for
successive period at a time and to forward the appropriate extension to the EMPLOYER.
8. As a declaration of good faith, the legal representative of the GUARANTOR hereby signs, seals
and delivers this SECURITY on the date , , 2000.
Signature:
Name of Signatory:
Position:
FPS-3
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX E
APPENDIX E
Note:
*-1: Column (1) must the same amount stated in the General Summary page of the Bill of Quantities.
Column (3) shall be the United States Doller equivalent the amount of J.D. stated in the Foreign Portion columns of the Bill of Quantities.
*-2: Column (4) shall be the T/T buying rate published by the Central Bank on the 28 days prior to the Tender Submission.
The Rate(s) in column (4) shall be fixed duration of Contract Period in accordance with the Clause 72.1 of the Conditions of Contract.
*-3: Price in Column (2) and (3) shall be carried to the Form of Tender
APPENDIX F
1. WHEREAS the Ministry of Public Works and Housing of the Hashemite Kingdom of Jordan,
(hereinafter referred to as the “EMPLOYER”) has signed a Contract Agreement with :
(hereinafter referred to as the “CONTRACTOR”) for the TOURISM SECTOR
DEVELOPMENT PROJECT, NATIONAL MUSEUM SUB-PROJECT on
, 2000,
2. WHEREAS according to the Contract, an Advance Payment consisting of fifteen percent (15%)
of the respective currencies component of the Contract Price (hereinafter referred to as the
“ADVANCE PAYMENT”) shall be paid by the EMPLOYER to the CONTRACTOR.
(J.D. )
(US$. )
FAP-1
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX F
4. If the CONTRACTOR, after receiving the ADVANCE PAYMENT, should fail to commence or
continue the Works or refuse to repay or default in the repayments of the ADVANCE
PAYMENT, whatever the reason, the GUARATOR shall forthwith return to the EMPLOYER
the whole, or the remaining ADVANCE PAYMENT after deduction of any of the ADVANCE
PAYMENT received by the EMPLOYER. The GUARANTOR shall deliver the money owed to
the EMPLOYER upon the EMPLOYER’s first demand, without delay and without the necessity
of a previous notice, or judicial procedure and without it being necessary to prove to the
GUARANTOR the shortcoming of the CONTRACTOR.
5. We understand that the total amount of this Security may be successively reduced but only after
each payment by the CONTRACTOR has been made in accordance with the requirements of the
Contract and then only after we have received a written official notification from the
EMPLOYER of the amount of reduction that shall be applied.
6. This Security shall remain valid until the EMPLOYER shall issue a written instruction to us to
the effect that the CONTRACTOR has completely discharged his payment obligation under the
aforementioned Contract excluding fourteen day (14) days claim period.
7. The GUARANTOR hereby waives the priority right to claim for attachment and disposal of the
property of Debtor for the settlement of the obligation of Debtor prior to the payment of the
Guaranteed amount.
FAP-2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX F
8. This Security is hereby execute by seal and hand by the responsible representative of the
GUARANTOR this day of , 2000.
Signature:
Name of Signatory:
Position:
FAP-3
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX G
DRAWING LIST
The Tourism Sector Development Project
National Museum Sub-Project
Architecture Drawings
DRAWING
NO. DRAWING TITLE SCALE
NO.
1 Cover
Page 1
The Tourism Sector Development Project
National Museum Sub-Project
Architecture Drawings
DRAWING
NO. DRAWING TITLE SCALE
NO.
24 A-256 Wall Section (6) 1/50
Page 2
The Tourism Sector Development Project
National Museum Sub-Project
Architecture Drawings
DRAWING
NO. DRAWING TITLE SCALE
NO.
48 A-416 Seminar Room (4) 1/2,5
Page 3
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX H
1 Preparation
2 Excavation
3 Foundation
4 Basement Structure
5 Ground F. Structure
6 1st F. Structure
7 2nd F. Structure
8 Basement Finishing
9 Ground F. Finishing
10 1st F. Finishing
11 2nd F. Finishing
12 Roof Finishing
14 M & E
15 Landscaping
16 Miscellaneous
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX I
APPENDIX J
APPENDIX K
QUERY FORM
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
QUERY FORM
APPENDIX K
Query No.:
Date:
Name of Document Page No. Clause or Section No. Question
INSTRUCTIONS TO TENDERERS
FOR
ENCLOSURES
ENCLOSURE NO. 10 : LIST OF MAJOR MATERIALS AND PLANT FOR THE WORKS
-(i)-
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
INSTRUCTIONS TO TENDERERS
Notes :
1) Enclosures shall each be read in conjunction with the Tender Documents.
2) Enclosures shall be signed and returned with the Tender in strict accordance with the
requirements of appropriate Clause of Instructions of Tenderers.
- ( ii ) -
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 1
POWER OF ATTORNEY
Name :
Position :
Name of Company:
Business Address :
Telephone :
Facsimile :
Date prepared :
Name of Tenderer :
Signature of Tenderer :
Official Stamp :
ENC-1
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 2
WHEREAS we have prepared a Tender Security in accordance with the Tender Documents for the
Tourism Sector Development Project, NATIONAL MUSEUM Sub-project, and it is a condition of the
aforesaid Tender Documents that the Tenderer shall furnish a Tender Security in the amounts of
J.D.--------------.
We hereby certify that a Tender Security complying with the above and in the form as prescribed in the
Tender Documents has been prepared and completed by the Guarantor
(Name of Bank)
ENC-2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 3
The Tenderer shall submit with his Tender a Joint Operation Agreement in accordance with the Sub-
Clause 20-1, c, 3) of the Instructions to Tenderers, clearly labeled as Enclosure No. 3.
ENC-3
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 4
LETTER OF ASSOCIATION
The Tenderer shall submit with his Tender a Letter of Association in accordance with the Sub-Clause
20-1, c, 4) of the Instructions to Tenderers, clearly labeled as Enclosure No. 4.
ENC-4
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 5
2 We have also:
3. I further certify that we are satisfied with the description of the Works and the written explanation
given by the MPWH and that we understand perfectly the scope of works to be executed.
Signature of Tenderer :
Name of Tenderer :
Date prepared :
Official Stamp :
ENC-5
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 6
The Tenderer shall submit with his Tender a “ Basic Program of the Works” clearly labeled as Enclosure
No.6. The program shall indicate the timing, proposed sequence and order of execution of the Works,
and take full account of the stipulated completion period.
The Program shall be submitted in Bar Chart form with plotted time/percentage completion together
with a Critical Path Network detailing activities.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-6
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 7
The Tenderer shall submit with his Tender a detailed organization chart clearly labeled as Enclosure
No.7. The organization chart shall include an illustration of the Contractor’ s proposed management
structure for the Works:
Principal personnel including Project management, administrative, technical and supervisory staff,
foreign and local, shall each be named or referenced in the Organization Chart and, in addition, the
Tenderer shall submit:
(1) An assignment schedule for each personnel in the form of bar chart, indicating whether full
or part time and the proposed period of assignment;
(2) Comprehensive Curriculum Vitae for personnel, describing names, position, qualifications,
age and relevant experience, company name if the Tenderer has been pre-qualified in
association with other companies as a Joint venture/Consortium and their authorities
(3) Monthly manpower requirement chart for the total Contract Period and categorized into
management, supervision, engineering, administrative and labor for both foreign and local.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-7
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 8
The Tenderer shall submit the following with his Tender, clearly labeled as Enclosure No. 8.
(1) An Outline Construction Plan; and
(2) A proposed Layout Plan for Temporary Works.
The proposed layout plan for Temporary Works shall be accompanied by drawings indicating the layout
and Engineers Office, temporary roads, workshop, control of soil erosion and sedimentation, storage
areas, hard standings, offices, fences, Site lighting, power and water supplies etc. and all protection
works.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-8
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 9
The Tenderer shall submit with his Tender a List of Contractor’ s and Sub-contractor’ s Equipment to be
used on the Works in the format of the enclosed page, clearly labeled as Enclosure No.9.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-9
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
The Tenderer shall submit with his Tender a List of Major Materials and Plant for the Works, clearly
labeled as Enclosure No.10.
A. The materials to be incorporated in the Works shall comply with the Specifications in the Tender
Documents.
B. The list must be complete in all respects including materials and plant and the Tenderer must
submit with his Tender. All manufacturers’ catalogues and enclosures, and performance
specifications including drawings as necessary, pertaining to the materials.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-10
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
LIST OF MAJOR MATERIALS AND PLANT FOR THE WORKS
ENCLOSURE NO. 10
DESCRIPTION SEC. AND CLAUSE NO. OF MANUFACTURER / SUPPLIER STANDARD / MODEL COUNTRY OF ORIGIN
VOLUME-II, SPECIFICATIONS
A Site, Civil, Architectural Works
1. Ready Mixed Concrete
2. Cement
3. Fine Aggregates
4. Coarse Aggregates
5. Reinforcing Bars (diameter 9mm or less)
6. Reinforcing Bars (all others)
7. RC Pipe 400 - 800 mm Dia.
8 Asphaltic Conctrete
9 Pre-cast Cponcrete Pile
10 Waterstop
11 Sesmic isolation pad
12 Cement Roofing Tiles
13 Concrete Block
14 Paint
15 Steel Doors
16 Wooden Doors
17 Aluminium Windows
18 Rolling Shutters
19 Glass
20 Sanitary Fixtures
B Mechanical Works
1 Valves
2 Galvanized Steel Pipes
3 Cast Iron Pipes
4 PVC Pipes
5 Piping Acessories: joint, bend, tee etc.
6 Pumps
7 Flow meters
8 Air Conditioner
9 Ventilation Fans
ENC-10/2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 10
DESCRIPTION SEC. AND CLAUSE NO. OF MANUFACTURER / SUPPLIER STANDARD / MODEL COUNTRY OF ORIGIN
VOLUME-II, SPECIFICATIONS
C Electrical Works
1 Circuit Breakers
2 Meters
3 Switch Boards
4 Tranformers
5 Busbars
6 Cables
7 Intermediate Metalic Conduits
8 Cable ladders
9 Computer
10 Lighting Fixtures
11 Switches and Receptacles
12 Heat and Smoke Detectors
D Landscape
E Exhibition
LIST OF SUB-CONTRACTORS/SUPPLIERS
The Tenderer shall submit a list of Sub-contractors/Suppliers he proposes to use with his Tender in the
format of the enclosed page, clearly labeled as Enclosure No.11. The Tenderer shall also enter a
Statement of Similar works previously executed by the proposed sub-contractor including description,
location and address of the Employer/Engineer. Notwithstanding such information, the Tenderer, if
awarded the Contract, shall remain entirely and solely responsible for the satisfactory completion of the
Works.
Reference and/or copy of regal documents for proposed Sub-contractors/Suppliers shall be enclosed.
Extension to this schedule in the same format should be used to provide complete information.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-11
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
LIST OF SUB-CONTRACTORS/SUPPLIERS
ENCLOSURE NO. 11
TARD OR NAME OF ADDRESS OF NAME OF SIMILAR WORKS NAME OF EMPLOYER/ DESCRIPTION OF WORK
MATERIALS SUB-CONTRACTOR/ SUB-CONTRACTOR/ PREVIOUSLY EXECUTED EMPLOYER OF WORKS
SUPPLIER SUPPLIER PREVIOUSLY EXECUTED
The Tenderer shall submit with his Tender a List of Intended Import Materials and Plant, clearly labeled
as Enclosure No. 12.
Such list shall include estimated Taxies/duties and other all necessary charges and specify the source
countries.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-12
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project LIST OF INTENDED IMPORT MATERIAL AND PLANT
ENCLOSURE NO. 12
ITEM DESCRIPTION UNIT QUANTITY MATERIAL / SOURCE OF AMOUNT DUTIES OTHER TOTAL
PLANT RATE COUNTRIES (FOB) CHARGE
ENC-12/2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 13
The Tenderer shall submit with his Tender a Breakdown of Major Rates, clearly labeled as Enclosure
No. 13.
Such breakdowns shall at all times be subject to the approval of the Engineer. The Engineer reserves the
right to request such further breakdown as he may consider necessary.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-13
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
BREAKDOWN OF MAJOR RATES
ENCLOSURE NO. 13
ITEM DESCRIPTION UNIT QUANTITY LOCAL CURRENCY (JD) FOREIGN CURRENCY (----) TOTAL
RATE AMOUNT RATE AMOUNT (J.D.)
A SITE, CIVIL AND BUILDING WORKS
1
2
3
4
5
6
7
8
9
10
11
12
13
B MECHANICAL WORKS
B-1 Plumbing Works
1
2
3
4
5
6
7
8
9
10
11
12
13
B-2 Air-conditioning and Ventilation Works
1
2
3
4
5
6
7
8
ENC-13/2
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
ENCLOSURE NO. 13
ITEM DESCRIPTION UNIT QUANTITY LOCAL CURRENCY (JD) FOREIGN CURRENCY (----) TOTAL
RATE AMOUNT RATE AMOUNT (J.D.)
C ELECTRICAL WORKS
C-1
1
2
3
4
5
6
7
8
9
10
C-2
1
2
3
4
5
6
D LANDSCAPE
E EXHIBITION
The Tenderer shall submit with his Tender a Detailed Monthly Cash Flow of Anticipated Contract
Payment to indicate all payments anticipated to be received under the Contract in relation to the
program thereof (cash flow shall be with tabular and graphical form). Appropriate allowance shall be
made for payment and repayment of advance payments under the Contract, clearly labeled as Enclosure
No.14.
ALL PAGES OF THIS ENCLOSURE AS SUBMITTED SHALL BE SIGNED BY THE TENDERER AND
ENDORSED WITH THE TENDERER’ S COMPANY STAMP.
ENC-14
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX L
TENDER ACKNOWLEDGEMENT
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
Appendix L
TENDER ACKNOWLEGEMENT
2. We further declare that we shall submit our Tender Proposal in strict accordance with
requirements of the Instructions to Tenderer.
Signature of Tenderer :
Name of Tenderer :
Date prepared :
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
APPENDIX M
All Countries
The Tourism Sector Development Project Instructions to Tenderers
National Museum Sub-Project
THE GOVERNMENT OF
THE HASHEMITE KINGDOM OF JORDAN
THE MINISTRY OF TOURISM & ANTIQUITIES
THE MINISTRY OF PLANNING
FORM OF TENDER
OF
TENDER
FOR
CONSTRUCTION
OF
1. Having examined the Tender Documents comprising the Instructions to Tenderers, Conditions of
Contract, the Specifications, the Bill of Quantities, the Drawings and Addendums for the
above-named works. We, undersigned, offer to undertake the work complete in conformity with the
above mentioned documents for the sum of;
( J.D. )
and
(US$ )
FOT-1
2. We undertake, if our Tender is accepted, to commence the Works within twenty-eight (28) days
after receipt of the Employer’s Letter of Acceptance, this period to be utilized for mobilization
works, and to complete and deliver the while works comprised in the contract within Twenty-four
(24) months from the last date of the aforesaid period in which the Works are to be commenced.
3. If our Tender is acceptable, we will submit a Performance Security in the form of Bank Guarantee
to jointly and severally bound us in the sum equal to ten percent (10%) of the total Contract Prices
in above mentioned currencies for the faithful and satisfactory performance of the contract.
4. We agree to abide by this Tender for a period of ninety (90) calendar days from the date set for the
opening of Tender and it shall remain binding upon us and may be accepted at any time before the
expiration of this period. The Tender Security shall remain valid for one hundred twenty (120)
calendar days after the date of opening of Tender.
5. Unless and until the Contract Agreement is prepared and executed, this Tender, together with your
Letter of Acceptance, shall constitute a binding Contract between us. We agree that our receipt of
your Letter of Acceptance will bind us to enter into the Contract Agreement with you, until the
submission by us of an acceptable Performance Security within the required period.
FOT-2
8. We understand that you are not bound to accept the lowest or any Tender you may receive.
Signed :
(Printed Name)
Designation :
(Witness) (Witness)
(Witness) (Witness)
FOT-3