Fire Work Schedule

The document outlines a Work Execution Plan for the New Integrated Passenger Terminal, detailing various fire safety systems and their completion status, with specific target dates for remaining tasks. It includes information on dependencies, manpower requirements, and remarks on pending work. The total length of the systems installed is 30,455 meters, with several tasks scheduled for completion between March and July 2025.

Uploaded by

necpludaipur
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
240 views3 pages

Fire Work Schedule

The document outlines a Work Execution Plan for the New Integrated Passenger Terminal, detailing various fire safety systems and their completion status, with specific target dates for remaining tasks. It includes information on dependencies, manpower requirements, and remarks on pending work. The total length of the systems installed is 30,455 meters, with several tasks scheduled for completion between March and July 2025.

Uploaded by

necpludaipur
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

NEW INTEGRATED PASSENGER TERMINA

Subject: Work Execution Plan


Date: 17-Mar-25
W.O Terget Date
[Link]. Description
Unit Qty Start

Basement-Sprinkler & Internal


1 Hydrant system Mtrs 2,719.00 Done
(Zone- 1 & 2)
Basement-Sprinkler & Internal
2 Hydrant system Mtrs 5,438.00 Done
(Zone- 3,4,5 & 6)

3
Fire Water Curtain system Mtrs 640.00 Done
(Zone- 1 & 2)

4
Fire Water Curtain system Mtrs 1,050.00 Done
(Zone- 3,4 & 6)

5
Non basement Mezzanine floor Mtrs 2,117.00 17-Mar-25
Sprinkler system

6
Arrival Lavel- Sprinkler & Internal Mtrs 6,519.00 11-Mar-25
Hydrant system

7
Departure Level- Sprinkler & Internal Mtrs 9,390.00 15-Apr-25
Hydrant system

8 Terrace Area Mtrs 955.00 1-Jul-25

9 External Hydrant system Mtrs 1,626.00 1-Feb-25

10 Fire Pump Room Lot 1.00 After clerance

30,455.00
NEW INTEGRATED PASSENGER TERMINAL Air Port
Subject: Work Execution Plan
Date: 17-Mar-25
Terget Date Working Dependency by Material
DP Test Hydro test Dependency by Client
Finish No. of Days Pipe Fitting

Done 60.00 Done Done

done 70.00 Done Progress Available Available

Done 30.00 Done

Done 70.00 Available Available

15-Apr-25 33.00 Need to 100 % Work front Available Procurement


clearance

10-May-25 60.00 Need to 100 % Work front Available Procurement


clearance & PT Slab Marking

15-Jun-25 60.00 Need to Work front clearance Procurement Procurement

30-Jul-25 30.00 Need to Work front clearance Procurement Procurement

30-Jun-25 150.00 Need to Work front clearance 50 % available Procurement

After clerance 45.00 Need to Work front clearance Procurement Procurement

608.00

S
Manpower Remarks

Final Painting and Gonge Alarm Valve system erection


pending

Team-1 Final Painting and Gonge Alarm Valve system erection


(Welder,Fitter & Helper)-4 pending

Final Painting and After clerance- Spray Nozzle ffixing


pending

Final Painting and After clerance- Spray Nozzle ffixing


pending

Work already started at Non beasement mezzanine area


and balance Work hold due to work front and Approved
drawing.

Erection- Team-2 11-Mar-25 work front clerance and permition for pipe
(Welder,Fitter & Helper)-10 erection bot PT Slab marking not completed

Branch Fabrication- Team- 3 (Welder, At list 50% work front & floor clerance for esy moving of
Fitter & Helper)- 6 Manlift & secissor lift

Team-4 (Welder,Fitter Work in progress


& Helper)-4