NEW INTEGRATED PASSENGER TERMINA
Subject: Work Execution Plan
Date: 17-Mar-25
W.O Terget Date
[Link]. Description
Unit Qty Start
Basement-Sprinkler & Internal
1 Hydrant system Mtrs 2,719.00 Done
(Zone- 1 & 2)
Basement-Sprinkler & Internal
2 Hydrant system Mtrs 5,438.00 Done
(Zone- 3,4,5 & 6)
3
Fire Water Curtain system Mtrs 640.00 Done
(Zone- 1 & 2)
4
Fire Water Curtain system Mtrs 1,050.00 Done
(Zone- 3,4 & 6)
5
Non basement Mezzanine floor Mtrs 2,117.00 17-Mar-25
Sprinkler system
6
Arrival Lavel- Sprinkler & Internal Mtrs 6,519.00 11-Mar-25
Hydrant system
7
Departure Level- Sprinkler & Internal Mtrs 9,390.00 15-Apr-25
Hydrant system
8 Terrace Area Mtrs 955.00 1-Jul-25
9 External Hydrant system Mtrs 1,626.00 1-Feb-25
10 Fire Pump Room Lot 1.00 After clerance
30,455.00
NEW INTEGRATED PASSENGER TERMINAL Air Port
Subject: Work Execution Plan
Date: 17-Mar-25
Terget Date Working Dependency by Material
DP Test Hydro test Dependency by Client
Finish No. of Days Pipe Fitting
Done 60.00 Done Done
done 70.00 Done Progress Available Available
Done 30.00 Done
Done 70.00 Available Available
15-Apr-25 33.00 Need to 100 % Work front Available Procurement
clearance
10-May-25 60.00 Need to 100 % Work front Available Procurement
clearance & PT Slab Marking
15-Jun-25 60.00 Need to Work front clearance Procurement Procurement
30-Jul-25 30.00 Need to Work front clearance Procurement Procurement
30-Jun-25 150.00 Need to Work front clearance 50 % available Procurement
After clerance 45.00 Need to Work front clearance Procurement Procurement
608.00
S
Manpower Remarks
Final Painting and Gonge Alarm Valve system erection
pending
Team-1 Final Painting and Gonge Alarm Valve system erection
(Welder,Fitter & Helper)-4 pending
Final Painting and After clerance- Spray Nozzle ffixing
pending
Final Painting and After clerance- Spray Nozzle ffixing
pending
Work already started at Non beasement mezzanine area
and balance Work hold due to work front and Approved
drawing.
Erection- Team-2 11-Mar-25 work front clerance and permition for pipe
(Welder,Fitter & Helper)-10 erection bot PT Slab marking not completed
Branch Fabrication- Team- 3 (Welder, At list 50% work front & floor clerance for esy moving of
Fitter & Helper)- 6 Manlift & secissor lift
Team-4 (Welder,Fitter Work in progress
& Helper)-4