Vedanta Quality Assurance Plan Overview

The Quality Assurance Plan (QAP) outlines the quality checks and standards for the FTP Efficiency Improvement project by Vedanta Limited, managed by Pradhan Associates PVT LTD. It includes detailed descriptions of operations, acceptance criteria, and inspection frequency for various fabrication processes, including dismantling, welding, and painting. The document emphasizes compliance with relevant standards and specifications to ensure quality throughout the project.

Uploaded by

rajan.kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views1 page

Vedanta Quality Assurance Plan Overview

The Quality Assurance Plan (QAP) outlines the quality checks and standards for the FTP Efficiency Improvement project by Vedanta Limited, managed by Pradhan Associates PVT LTD. It includes detailed descriptions of operations, acceptance criteria, and inspection frequency for various fabrication processes, including dismantling, welding, and painting. The document emphasizes compliance with relevant standards and specifications to ensure quality throughout the project.

Uploaded by

rajan.kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

QUALITY ASSURANCE PLAN

CLIENT: Vedanta Limited QAP NO: QAP/PAPL/FTP-1/RVPM001


PO NO: 5600002043 DATE: 14/11/2022 REV: 0
PROJECT: FTP Efficiency improvement
CONTRACTOR Pradhan Associates PVT LTD.
Recording INSPECTION
Sl. Description of operation Characterization of Checks Ref. standards Accetance Frequency/Extend of Remarks
Documents/Form PAPL SGS VAL
1 Dismantling Visual Log Book P RW RW
Fabrication:-
1 Row material

1.1 CHQ plates, Angles , Column, Beam , Dimension & visual Approved Drawing Test Certificate VAL 100% P W/H R
Pipe

Batch Certificate of electrode


1.2 Consumables Compliance to the AWS D 1.1 /ASME SEC II Manufacturers batch Review of batch 100% P W R and paint Barrel to be
specfication/ composition Part - C / Relevant IS code certificate certificate submited prior to weld and
paint job

2 Fabrication
Compliance to the Approved WPS & WPS
2.1 Welding procedure Specification AWS D 1.1 /ASME SEC IX VAL 100% P W R
specfication/ composition ( Review Documents )
Compliance to the
2.2 Welder Qualification Test AWS D 1.1 /ASME SEC IX Approve WQT Tech Specification 100% P W R
specfication & weld visual
IS 7215 or concern AWS As per
2.3 Fit-up Inspection Welding Parameters visual check report 100% P W/H R
Code drawing/VAL
AWS D 1.1 /ASME
2.4 Welding Weld visual and Size AWS D 1.1 /ASME SEC IX Visual and measurment 100% P W R
SEC IX
IS7215 or as per VAL
2.5 Final Dimetional Checks Dimension & weld check Final inspection protocal VAL 100% P W/H R
approval
SSPC SP 2/3 OR any
2.6 Surface Prepration Surface Finish Inspection Inspection Report VAL 100% P W R
Equvalant code
Manual Surface Cleanig prior
SSPC SP 2/3 OR any
2.7 Painting Application /coarse of Inspection Report VAL 100% P W/H R
Equvalant code
application
3 NDE Applicable NDE SEC V Inspection Report VAL 100% P W R

Prepared By:- Verified By :- Approved By:-