SCHEDULE OF RATES - 2025
BUILDING, IRRIGATION, ROAD WORKS
AND
MATERIAL TESTING
NORTHERN PROVINCE
Office of the Deputy Chief Secretary
Engineering Services
Northern Province
Jaffna
Office of the Deputy Chief Secretary - Engineering Service, NP Page i
Published by
Office of the Deputy Chief Secretary Engineering Services,
Northern Provincial Council
Provincial Council Complex,
Kandy Road,
Kaithady,
Jaffna
Office of the Deputy Chief Secretary - Engineering Services, NP Page ii
TABLE OF CONTENT
1.Preface ....................................................................................................................................... vii
2.Background ................................................................................................................................. ix
3. The Committee Engaged in Preparation of Schedule of Rates .................................................11
4 General Data ...............................................................................................................................15
4.1. Overhead And Profit Factor For Works..............................................................................15
4.2. Reinforcement: Weights, Specified Spacing’s and Unit Weights ......................................16
4.3. Basic Labour Rates Adopted ..............................................................................................16
5. Rates for Buildings Works ........................................................................................................19
5.1. General Specification for Buildings Works ........................................................................19
5.2. General Data to be Used for Calculations of Quantities .....................................................22
5.3.Demolisher ...........................................................................................................................23
5.4.Excavator .............................................................................................................................25
5.5. Concrete Work ....................................................................................................................28
5.6.Form Work ...........................................................................................................................31
5.7.Reinforcement ......................................................................................................................31
5.8.Ready Mixed Cement Concrete ...........................................................................................32
5.9.Masonry Work .....................................................................................................................32
5.10.Brick Work.........................................................................................................................35
5.11.Paving Work ......................................................................................................................36
5.12.Roof Work .........................................................................................................................43
5.13.Carpentery and Joinery Work ............................................................................................48
5.14.Brass Founder ....................................................................................................................52
5.15.Metal Work ........................................................................................................................53
5.16. Plasterer.............................................................................................................................58
5.17.Water Proofing ...................................................................................................................60
5.18.Painter and Decorator ........................................................................................................61
5.19.Plumbing and Drainage Work ..........................................................................................64
5.20.Electrical Installation .........................................................................................................71
5.21.Miscellaneous ....................................................................................................................78
5.22.Aluminium Work ...............................................................................................................81
Office of the Deputy Chief Secretary - Engineering Service, NP Page iii
6. Rates for Irrigation Works .......................................................................................................105
6.1. General Specifications For Irrigation Works ....................................................................105
6.2 Norms for Clearing And Earth Work.................................................................................106
6.3 Norms for Concrete And Others ........................................................................................110
6.4. Norms for Gates ................................................................................................................112
6.5 Norms for Hume Pipes For L.Ft .......................................................................................112
6.6 Norms for Miscellaneous Works .......................................................................................113
6.7 Norms for Gabion Box.......................................................................................................114
6.8 Norms for Agriculture Wells .............................................................................................115
6.9 Rates for Irrigation Works .................................................................................................116
6.9.1 Clearing Works - Manual ............................................................................................116
6.9.2 Clearing Works - Machinery .......................................................................................117
6.9.3 Earth Work - Manual...................................................................................................118
6.9.4 Earth Work - Machinery..............................................................................................118
6.9.5 Gravel Work ................................................................................................................119
6.9.6 Road Way ....................................................................................................................119
6.9.7 Concrete - Manual .......................................................................................................120
6.9.8 Concrete - Machinery (Mixture) .................................................................................120
6.9.9 Rubble Work ...............................................................................................................121
6.9.10 Reinforcement ...........................................................................................................122
6.9.11 Formwork ..................................................................................................................122
6.9.12 Hume Pipes ...............................................................................................................122
6.9.13 Gates ..........................................................................................................................123
6.9.14 Miscellinious .............................................................................................................124
6.9.15 Gabions......................................................................................................................125
6.9.16 Agriculture Wells ......................................................................................................126
7. Rates for Road Works..............................................................................................................131
7.1 General Specifications For Road Works............................................................................131
7.2 Section I – H.S.R. – Schedule Of Prices ............................................................................131
7.2.1. Hire Charges (Wet Lease Basic - Including Operator) ..............................................131
7.2.2. Construction Material Prices ......................................................................................134
7.2.3. Precast Concrete Items ...............................................................................................136
7.2.4. Blasting Materials (Including Transport Cost)...........................................................137
7.2.5. Paints (Including Transport Cost) ..............................................................................137
Office of the Deputy Chief Secretary - Engineering Services, NP Page iv
7.2.6. Fuel, Oils & Lubricants ..............................................................................................138
7.2.7. Miscellaneous (Including Transport Cost) .................................................................138
7.2.8. Thermoplastic Road Marking Materials Excluding Transport & Vat .......................140
7.3 Section II-Schedule of Rates ..............................................................................................141
7.3.1. Transport Rates ..........................................................................................................141
7.3.2. Roadway and Foundation / Trench Excavation .........................................................145
7.3.3. Aggregate / Rubble Piling Including Loading ...........................................................147
7.3.4. Approved Earth Filling & Compaction ......................................................................149
7.3.5 Rubble Pitching / Paving .............................................................................................151
7.3.6 Aggregate Spreading & Compaction ..........................................................................152
7.3.7 Road Surface Treatment ..............................................................................................154
7.3.8 Road Surface Maintenance ..........................................................................................162
7.3.9 Road Side and Drainage System (Sscm 701.3) ...........................................................164
7.3.10 Bridges, Culverts & Retaining Walls Etc..................................................................165
7.3.11. Kilometer Posts and Guard Stones ...........................................................................178
7.3.12.Notice Boards & Sign Boards ...................................................................................179
7.3.13 Miscellaneous ............................................................................................................181
7.3.14 Surveying, Levelling and Day Works .......................................................................192
8.Rates for Material Testing ........................................................................................................199
8.1. Moisture Content .............................................................................................................199
8.2. Soil Index Properties ........................................................................................................199
8.3. In -Situ Density ................................................................................................................199
8.4. Particle Size Distribution .................................................................................................199
8.5. Bearing Capacity and Soil Profile....................................................................................199
8.6. Concrete ...........................................................................................................................200
8.7. Compressive Strength ......................................................................................................200
8.8. Non-Destructive Test .......................................................................................................200
8.9. Aggregates .......................................................................................................................200
8.10. Asphalt ...........................................................................................................................201
8.11. Soil Sampling ..................................................................................................................201
Office of the Deputy Chief Secretary - Engineering Service, NP Page v
Office of the Deputy Chief Secretary - Engineering Services, NP Page vi
1.PREFACE
It is my great pleasure to release the Schedule of Rates – 2025 for Northern Province.
The objective of this publication is to enhance the transparency and consistency among the
stakeholders of construction industry in Northern Province by publishing a compiled Schedule
of Rates for the year 2025 comprising rates for works related to Buildings, Irrigation and
Roads construction and rates for quality control laboratories for the Northern Province.
In this exercise it is intended to harmonize the rates to the extent possible with the contribution
of three major technical provincial departments namely Buildings Department, Irrigation
Department and Road Development Department by adopting similar approach in deciding
certain basic norms.
I strongly believe that this publication would not only serve as a guideline for non-technical
departments to compare their rates while preparing the estimates, but also would iron-out
certain concerns with regard to difference in rates among the institutions for similar items. In
addition, it would also help the contractors to verify the practicality of their rates to avoid
quoting unduly low rates and struggling to meet the quality requirements during execution.
Therefore, it is anticipated that this publication would contribute to create a win-win situation
between contractors and implementing agencies in assuring quality and value for money and
intern minimize the disputes.
I wish to express my appreciation and gratitude to Deputy Chief Secretary – Engineering
Services, Provincial Directors of Buildings Department, Road Development Department,
Irrigation Department and their subordinates who have timely contributed at different levels
to make this publication as an effective tool for estimation for the construction industry in
Northern Province.
Any suggestions and opinions are appreciated for further improvement and enrichment for the
future publications.
I.Ilaangovan
Chief Secretary
Northern Province.
Office of the Deputy Chief Secretary - Engineering Service, NP Page vii
Office of the Deputy Chief Secretary - Engineering Services, NP Page viii
2.BACKGROUND
In Northern Province there are three technical departments namely Buildings Department,
Irrigation Department and Road Development Department entrusted with the task of
implementing works related to their respective fields in accordance with generally accepted
professional standards and practices and by observing sound management practices, and
employing appropriate technology and safe and effective equipment, machinery, materials and
methods.
One of the key activities of the departments is to prepare unit rates for works items in
accordance with the specification of works, rate analysis and prevailing rates of machinery,
materials and man power.
In order to do so Buildings Department adopts respective buildings related specifications
published by the CIDA and rate analysis (Buildings Schedule Rates (BSR) of Provincial
Buildings Department. Likewise, Irrigation Department adopts respective Irrigation related
specifications published by the CIDA and rate analysis (Irrigation Schedule Rates (ISR) based
on Data for Costing published by the Central Irrigation Department. Similarly, Road
Development Department adopts respective Road related specification published by the CIDA
and rate analysis (Highway Schedule Rates (HSR) published by the Road Development
Authority.
Since it is found to be necessary to adopt respective rates prepared by each department for
their activities in the context of employing appropriate technology and safe and effective
equipment, machinery, materials and methods to suit their respective specifications, it is
justifiable to have independent rates with acceptable variation in similar items.
Even though the departments are permitted to adopt their rates as explained above, it was
strongly felt that similar approach is required in deciding certain basic norms. Hence it has
been decided to involve all three technical departments to work together with the assistance
of Deputy Chief Secretary – Engineering Service to harmonize the rates to the extent possible
and publish a compiled Schedule of Rates comprising rates for Buildings related constructions,
Irrigation related constructions, Road related construction and rates for quality control
laboratories for the Northern Province.
This publication could be used as a guideline by other non-technical departments and
contractors to compare their rates while preparing the estimates. But it is their responsibility
to determine their rates in accordance with the proposed specification and the ground condition
of the work site.
While the Provincial Departments of Buildings, Irrigation, Road Development, Engineering
Services and Northern Provincial Council strives to make the information on this guidebook as
timely and accurate as possible, the departments make no claims, promises, or guarantees about
the accuracy, completeness, or adequacy of the contents of this guidebook, and expressly
disclaims liability for errors and omissions in the contents of this guidebook.
Office of the Deputy Chief Secretary - Engineering Service, NP Page ix
Office of the Deputy Chief Secretary - Engineering Services, NP Page 10
3. THE COMMITTEE ENGAGED IN PREPARATION OF SCHEDULE OF RATES
This guidebook, consisting of Building Schedule Rates, Highway Schedule Rates, Irrigation
Schedule Rates and Material Testing of 2025 were prepared by the committee, comprising
followings members, with the concurrence of Provincial Directors of Engineering
Departments under the guidance of Deputy Chief Secretary Engineering Services, Northern
Province.
Committee Members
1. Eng.V.Jegananthan - Provincial Director (Department of Road Development, NP)
2. Eng.T.Rajagobu - Provincial Director (Department of Irrigation, NP)
3. Eng.C.Saseeharan - Chief Engineer (Department of Buildings, NP)
4. Eng.Mrs.A.Vithyaparan - Director of School Works, (Department of Education, NP)
5. Eng.S.Paraneetharan - Engineer (Department of Local Government, NP)
6. Eng.S.Sulaxana - Engineer (Department of Health, NP)
Other Key Supportive Staffs
1. Eng K. Kowsikan - Chief Engineer (Department of Road Development, NP)
2. Eng.N.Vijeyaravi - Engineer (Department of Irrigation, NP)
3. Eng K Hatheesh - Executive Engineer (Department of Road Development, NP)
4. Mr.N.Lakkunarajh -Technical Officer Special Grade(Department of Buildings, NP)
5. Mrs.K.Niroja -Technical Officer (Department of Buildings, NP)
6. Miss.S.Vatsajini - Draughtsman (Department of Irrigation, NP)
7. Mrs.S.Sivagowri - Work Supervisor (Department of Buildings, NP)
Office of the Deputy Chief Secretary - Engineering Service, NP Page 11
Office of the Deputy Chief Secretary - Engineering Services, NP Page 12
GENERAL DATA
DEPARTMENT OF BUILDINGS,
IRRIGATION AND ROAD DEVELOPMENT
Office of the Deputy Chief Secretary - Engineering Service, NP Page 13
Office of the Deputy Chief Secretary - Engineering Services, NP Page 14
4 GENERAL DATA
4.1. OVERHEAD AND PROFIT FACTOR FOR WORKS
• Overhead and Profit (OH & P) factor is not included in the rates given in the schedule.
• Overhead and Profit factor shall be added to the rates given in this guideline by the entities
that intent to use this guideline.
• Profit factor shall generally be 10% and the Over Head shall be in accordance with the
recommendation of CIDA given by the Chairman CIDA’s letter dated 03.10.2018.
• Provincial Departments shall adopt the Overhead & Profit in the following manner.
Profit 10 %
General Overhead 6%
General Overhead & Profit 16%
• The site overhead shall be included in the Preliminaries as per the recommendation of CIDA
given by the Chairman CIDA’s letter dated 03.10.2018.
• For the CBO contracts, VAT shall be added for cement and reinforcement with the material
cost given in the schedule before the addition of 10% of profit.
• If the departments are responsible for supervision of work, taking measurement and bill
preparation for CBO contracts, the 6% General Overhead shall be reduced.
• Cost for loading, unloading, material wastage and transport is included in the rates.
• For Irrigation & Agriculture roads such as earthen, gravel & concrete, ISR shall be used. For
other type of Irrigation & Agriculture Road, HSR shall be used.
• Round the final abstract rate (with Overhead and Profit) to zero decimal.
• The basic rates do not include any sea transport expenses required to transport the material
to islands, in such case price fixed for sea transport by the District Price Fixing Committee
of Jaffna District shall be taken to account.
• Rates include all taxes other than VAT. VAT to be paid separately.
Office of the Deputy Chief Secretary - Engineering Service, NP Page 15
4.2. REINFORCEMENT: WEIGHTS, SPECIFIED SPACING’S AND UNIT WEIGHTS
Weights of metric (millimeter) bars in kilograms per square meter
Length Spacing of Bars in Millimeters
Weight
Size per
per m
(mm) M.Ton
(kg) 75 100 125 150 175 200 225 250 275 300
(m)
6 0.222 4505 2.96 2.220 1.776 1.480 1.269 1.11 0.987 0.888 0.807 0.74
8 0.395 2532 5.267 3.950 3.16 2.633 2.257 1.975 1.756 1.58 1.436 1.317
10 0.616 1623 8.213 6.160 4.928 4.107 3.52 3.08 2.738 2.464 2.24 2.053
12 0.888 1126 11.84 8.880 7.104 5.920 5.074 4.44 3.947 3.552 3.229 2.96
16 1.579 633 21.05 15.790 12.630 10.530 9.023 7.895 7.018 6.316 5.742 5.263
20 2.466 406 32.88 24.660 19.730 16.440 14.09 12.33 10.96 9.864 8.967 8.22
25 3.854 259 51.39 38.540 30.830 25.690 22.02 19.27 17.13 15.42 14.01 12.85
32 6.313 158 63.130 50.500 42.090 36.07 31.57 28.06 25.25 22.96 21.04
40 9.864 101 78.910 65.760 56.37 49.32 43.84 39.46 35.87 32.88
Basic weight = 0.00785 kg/mm2 per meter
Weight per meter = 0.006165 Ɵ2 kg
Weight per mm2 at spacing s (mm) = 6.165 Ɵ2 /skg
Ɵ = diameter of bar in millimeters
4.3. BASIC LABOUR RATES ADOPTED
Basic Rate (Rs)
Category Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Day
Skilled Grade I 3,200.00 3,000.00 3,000.00 3,100.00 3,200.00
(8hrs)
Day
Skilled Grade II 2,700.00 2,700.00 2,800.00 2,600.00 2,750.00
(8hrs)
Day
Semi-Skilled 2,500.00 2,500.00 2,500.00 2,400.00 2,600.00
(8hrs)
Day
Unskilled 2,400.00 2,300.00 2,300.00 2,300.00 2,500.00
(8hrs)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 16
RATES FOR
BUILDINGS WORKS
Office of the Deputy Chief Secretary - Engineering Services, NP Page 17
Office of the Deputy Chief Secretary - Engineering Services, NP Page 18
Buildings Works Rate 2025
5. RATES FOR BUILDINGS WORKS
5.1. GENERAL SPECIFICATION FOR BUILDINGS WORKS
• Specification for Building Works – Volume I – CIDA Publication No SCA/4/1-Revised
edition – July 2004
• Specification for Building Works – Volume II – Sanitary installations - CIDA Publication
No SCA/4/1-Revised edition – October 2001
• Specification for Water supply, sewerage & Strom water drainage works - CIDA
Publication No SCA/3/2-Revised edition – April 2002
• Specification for Electrical & Mechanical Works associated with building & Civil
Engineering - CIDA Publication No SCA/8 -Revised edition – August 2000
SPECIFICATION AND PRICING PREAMBLES
EXCAVATION AND EARTH WORK
Rates shall include for,
a) Back filling, consolidating and disposal of surplus excavated materials as specified and
as directed.
b) All works under this section are measured net. (Working space not allowed)
c) Keeping trenches free from water and in a clean and dry condition. (Excavation and
construction period)
d) For excavation beyond the depth of 5'-0" an additional unskilled labourer should be
added for every additional depth of 5'-0".
e) Unless otherwise specified in the dewatering for excavation at construction period are
measured separately.
CONCRETE WORKS
Assumptions:
a) Mixing concrete using a concrete mixer 14/10 cuft capacity and manual loading are
the basis on which the norms are worked
b) A gang of one skilled and six unskilled labourers produce 3.00 cubes of concrete per
day using a 14/10 cuft capacity concrete mixer. This is as per accepted practice.
c) The production of concrete is at the mixer site, transporting mixed concrete and placing
same in position is paid for separately.
d) In concrete placing of concrete in column, beams and floors slabs on the ground floor
the labour component allowed is for the placing of concrete between the ground floor
and the top of the 1st floor slab which area is called the ground floor area similarly the
area between the top of the 1st floor slab and the top of the 2nd floor slab is called the
1st floor area etc.
e) Sand Bulking Factor - 1.15
f) Metal Void Ratio - 1.20
g) Water available at site.
h) If water is not available allowance must be made for transport of water.
i) River Sand & Granite metal to be used for all concrete works.
j) For laying 2" thick concrete at depths more than 5'-0", add 1/6-day unskilled
labourer for each additional 5'-0"
k) For laying 3" thick concrete at depths more than 5'-0", add 1/4-day unskilled
labourer for each additional 5'-0”
Office of the Deputy Chief Secretary - Engineering Services, NP Page 19
Buildings Works Rate 2025
Rates shall include for,
a) All concrete shall be made dense with a vibrator, rate shall include for plant mixing,
handling, hoisting, depositing, compacting, curing & making good after removal of form
work.
b) Unless otherwise specified in the respective items, all formwork and reinforcement are
measured separately.
c) R/F in position with tools of cover block in same mix.
d) All costs in connection with the construction of ''kickers''
e) Approved Construction joints to be applied for concrete temporary stop ends as directed.
f) Cement & steel should be S.L.S. certified. (Cement SLS 107, 1247, Steel SLS 375)
g) The quality of the concrete should confirm to the relevant B.S, S.L.S and CIDA
specification for building works.
FORMWORK, REINFORCEMENT & OTHER WORKS
Rates shall include for,
a) All necessary boarding, supports, erecting, framing, cutting, angles, striking, removal
cleaning, wetting etc.
b) Unless otherwise specified in the respective items, all formwork and reinforcement are
measured separately.
c) Form work has been measured in the net contact surface measurement between concrete
& form work.
d) Plywood shuttering to produce to have fair face concrete finish. Mould oil should be
applied to form work surface before using.(steel shuttering for columns included).
e) Reinforcement shall conform to including binding wire, cutting bending, assembling,
supplying fixing position, stools, spacer bar and fabricating steel according to British
standard practice and as shown in structural drawing. All steel to be tor steel
manufactured by SLS certified manufactures.
f) Reinforcement as per B.S 4499 or 4461 having minimum characteristic strength of
500N/mm2 for high yield steel and 250 N/mm2 for mild steel.).
BRICK WORK
Rates shall include for,
Plumbing, angles, straight cutting, forming rebates, reveals and raking out joints for
plastering.
PAVIOR
Rate shall include for,
a) Wall Tiles should be manufactured by Lanka Wall Tile /Rocel ceramic / approved
equivalent
b) All floor tiles shall be Homogenous vitreous porcelain of industrial grade (heavy duty)
Floor tile manufactured by Rocell or approved equivalent.
c) Tile Mortar: Swisstek or equivalent
ROOF WORKS
Rate shall include for,
a. Hoisting & fixing complete with nails, screws clips etc.
b. All straight & square cutting & waste
c. Two coats of wood preservative to roof & flat asbestos ceiling timber frame work
d. All cutting notching, drilling, sinking trimming, framing, jointing splayed in position
complete with all nails spiked screws & priming to joints & ends
e. No application of any description shall be made on any timber is approved by the Eng.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 20
Buildings Works Rate 2025
CARPENTER & JOINER
Rate shall include for,
a) All cutting, notching, drilling, sinking, trimming, framing, jointing, splayed edges & the
like including fixing in position complete with all nails, spikes, joints and ends.
b) No application of any description shall be made on any timber unless and until the timber
is approved by the Engineer.
c) All door frames shall be fixed with spur stones at the foot
d) Hold fast 4Nos for each frame
e) All doors & windows frames shall be fixed to block works with MS hold fast as directed.
f) All doors & windows fittings to be approved before fixing.
ALUMINIUM WORKS
a) Contractor should submit detailed shop drawings and fabricated samples of typical units
of each type illustrating all construction details for prior approval of the Engineer.
b) Frames shall be fixed to the structural openings with appropriate fixing plugs and anchor
bolts.
c) Interface between door / window frames and structural openings shall be properly
caulked and sealed with flexible silicon sealant of a colour to be approved by the
Engineer
d) Corners and joints of frames and sashes shall be miter cut and staked with clears and
mechanically crimped. Where staked joints are not possible. Frames/sashes shall be
miter cut or square cut as required & assembled with stainless screws into appropriate
cleats & integral screw groves within the extrusion. All shall be sealed with approved
joint sealer to prevent leakages. Drainage points shall be provided as required.
e) All openable sashes shall be provided with minimum two layers of Neoprene / EDPM
weather stripping / Gaskets to form a continuous drought proof seal between sashes and
frames.
f) Windows shall be provided with heavy duty stainless steel (304) friction hinges, and
die - cast powder coated aluminium fasteners.
g) All doors / windows shall have stainless steel hinges & screws, locks shall be "Alpha"
locks / approved quality.
ELECTRICAL INSTALLATION
a) Recommended makes of Electrical Accessories,
b) MCCB – Schneider, ABB, Terasaki, Siemens, Orange(sigma) or equivalent
c) MCB'S and RCCB's – Schneider, Siemens, Crabtree, Eaton, Hager, Orange (sigma),
Moeller, Legrand, F & G (Austria) or equivalent.
d) Cable – ACL, Kelani, Sierra or equivalent.
e) Ceiling Fan – KDK, National – Japanese origins or equivalent.
f) Exhaust Fan – KDK, National – Japanese origins or equivalent.
g) Switch and Socket Outlet – Tenby, Clipsal, MK, PDL, Kevilton, Orange or equivalent
h) Fluorescent Lamp – The choke, Starter and Capacitor should be of good quality.
British, French, Australia, German or equivalent and the tube should be preferably
Thorn, Osram, National or equivalent. The fluorescent fittings should be fabricated. In
gauge not smaller than 24 SWG Zinc coated metal, finished with power coating (white
in colour).
i) Distribution Board – Shall be in surface mount metal enclosure fabricated with zinc
coated sheet metal of gauge not less than 1.8mm total enclosed, hinged door with
protective cover plate for terminals, finished with powder coating of approved colour
and components as specified in the BOQ.
j) Energy Saving Bulbs – 4 Star rated
k) LED Lamps – Bright, Green, Kevilton or equivalent
Office of the Deputy Chief Secretary - Engineering Services, NP Page 21
Buildings Works Rate 2025
5.2. GENERAL DATA TO BE USED FOR CALCULATIONS OF QUANTITIES
(a) Multiplication factors for calculation of painting areas of doors and windows
Multiplication
Description
factor
Fully glazed doors / windows / fanlights 1.25
Glazed and paneled doors / windows / fanlights 1.50
Fully paneled doors / windows / fanlights 2.25
Ledge, braced and battened doors / windows / fanlights 2.25
Wooden louvered frames 3.00
Expanded metal or weld mesh with fillets or beadings only 0.75
Expanded metal or weld mesh with frame 1.00
Collapsible gate (open type) 1.50
Collapsible gate (closed type) 2.25
Corrugated asbestos or G.I sheets 1.25
(b) Rate adjustment for upper floors in the building
The rates given in this schedule are applicable only for ground work. Therefore, rates for
upper floors can be calculated by using following multiplication factors and the rates given
in this schedule.
Description First floor Second floor Third floor
Concrete work 3% 5% 7%
Form work 3% 5% 7%
Reinforcement 2.5% 5% 7.5%
Brick work 5% 7% 10%
Calicut tile roof 3% 6% 9%
Asbestos roof 3% 5% 7%
Zink Aluminum roof 3% 5% 7%
Roof plumbing 3% 5% 7%
Ceiling 3% 5% 7%
Plastering 5% 10% 15%
Wall tiling 2% 4% 6%
Floor tiling 2% 4% 6%
Painting 3% 6% 9%
Office of the Deputy Chief Secretary - Engineering Services, NP Page 22
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
5.3.Demolisher
Brick work in cement,
Dem -
demolished brick stacked m3 1,781.00 1,707.00 1,707.00 1,707.00 1,855.00
001
and debris cleared.
Dem - Brick work in lime,
m3 1,336.00 1,280.00 1,280.00 1,280.00 1,391.00
002 demolished brick - do- do
Cadjan roofing or walling
Dem -
dismantled, timber stacked m2 50.00 49.00 50.00 48.00 52.00
003
and debris cleared.
Ceiling, existing, removed
Dem -
materials stacked and debris m2 159.00 155.00 157.00 153.00 164.00
004
cleared.
150 mm thick Cement
Dem -
concrete floor demolished, m2 1,163.00 1,114.00 1,114.00 1,114.00 1,211.00
005
and debris cleared away.
100 mm thick Cement
concrete floor, reinforced,
Dem -
demolished in suspended m2 1,679.00 1,609.00 1,609.00 1,609.00 1,749.00
006
floors, reinforcement
removed and debris cleared.
Corrugated sheets, Iron,
Dem - Asbestos / Aluminium alloy,
m2 192.00 182.00 182.00 185.00 196.00
007 removed from roof or walls
and stacked. [single storey]
Door or window, size up to
Dem - 40 S.ft removed from
No 2,400.00 2,300.00 2,300.00 2,300.00 2,500.00
008 existing walls and stacked
per door or window.
Door or window, size over
Dem - 40 S.ft removed from
No 3,600.00 3,450.00 3,450.00 3,450.00 3,750.00
009 existing walls and stacked
per door or window.
Door or window, sash only
Dem -
010
up to 40 S.ft removed from No 319.00 313.00 319.00 306.00 328.00
existing walls and stacked.
Door or window, sash only
Dem -
011
over 40 S.ft removed from No 478.00 469.00 478.00 459.00 492.00
existing walls and stacked.
Down pipes, 4" to 6" dia. G.I
Dem - old or decayed, removed
012 from existing building and
lm 82.00 79.00 79.00 79.00 85.00
stacked.
Dem - Drains demolished and
013 debris cleared.
lm 205.00 196.00 196.00 196.00 213.00
Fence uprooted, Barbed wire
Dem - rolled up and all materials
014 stacked (length of fencing to
lm 374.00 358.00 358.00 358.00 389.00
measured).
75 mm thick floors brick
Dem -
paved, demolished and m2 145.00 139.00 139.00 139.00 151.00
015
debris cleared away.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 23
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Gate sash removed and
stacked after demolishing
cement concrete blocks or
Dem - removing posts and
016 separating pintles
No 2,400.00 2,300.00 2,300.00 2,300.00 2,500.00
(demolishing brick work
where necessary paid for
separately).
Glass panes in doors and
Dem -
windows and fanlight m2 908.00 908.00 942.00 874.00 925.00
017
removed and stacked.
Gutter, eaves, removed and
Dem - stacked from roof of single
018 storeyed building and
lm 52.00 49.00 49.00 49.00 54.00
stacked.
Gutter, eaves, removed from
Dem -
019
roofs of 2 storeyed building lm 77.00 74.00 74.00 74.00 81.00
and stacked.
Partitions removed and
Dem - stacked at site, including
m2 843.00 822.00 835.00 810.00 870.00
020 making good to walls and
floors.
Dem - Lime plastering chipped and
m2 97.00 93.00 93.00 93.00 101.00
021 debris cleared from site.
Rendering cement, chipped
Dem - from brick walls / floors and
m2 291.00 279.00 279.00 279.00 303.00
022 debris cleared away from
site.
Rendering cement, chipped
Dem - from cement concrete walls /
m2 436.00 418.00 418.00 418.00 454.00
023 floors and debris cleared
away from site.
Roof, removing tiles with
timber frame work, stacking
Dem -
serviceable material and m2 348.00 336.00 339.00 333.00 360.00
024
cleaning debris in single
storied building.
Roof, removing tiles with
timber frame work, stacking
Dem -
serviceable material and m2 483.00 466.00 469.00 463.00 502.00
025
cleaning debris in 2 storied
building.
Rubble masonry in cement,
Dem - demolished, rubble stacked
m3 2,783.00 2,667.00 2,667.00 2,667.00 2,899.00
026 and debris cleared away
from site.
Tiles, glazed demolished
Dem -
and debris cleared away m2 517.00 495.00 495.00 495.00 538.00
027
from site.
Tiles Calicut or half round,
Dem - removed from roof of single
m2 129.00 124.00 124.00 124.00 135.00
028 storeyed buildings and
stacked at site.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 24
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Tiles Calicut or half round,
Dem - removed from roof of 2
m2 203.00 195.00 195.00 195.00 212.00
029 storeyed buildings and
stacked at site.
Waterproof Treatment of hot
Dem - bitumen taken off from flat
m2 517.00 495.00 495.00 495.00 538.00
030 roof and debris cleared
away.
Ceiling Asbestos with
timber frame work removing
Dem - and stacking serviceable
m2 576.00 565.00 576.00 554.00 593.00
031 materials single storeyed
building including debris
cleared away from site.
Ceiling Asbestos with
timber frame work removing
Dem - and stacking serviceable
m2 712.00 695.00 706.00 684.00 735.00
032 materials 2 storeyed building
including debris cleared
away from site.
Valance / Barge board
Dem - removed, materials stacked
033 and debris cleared away in
lm 52.00 49.00 49.00 49.00 54.00
single storeyed building.
Valance / Barge board
Dem - removed, materials stacked
lm 77.00 74.00 74.00 74.00 81.00
034 and debris cleared away in 2
storeyed building.
Cement plastering soffit
Dem -
chipped, and debris cleared m2 381.00 366.00 366.00 366.00 397.00
035
away from site.
Wash Basin / sink / urinal
Dem -
036
with fittings removed and No 2,768.00 2,643.00 2,655.00 2,668.00 2,824.00
walls made good.
Closet pedestal type
disconnecting and plugging
Dem -
037
sewer connection and No 3,175.00 3,025.00 3,025.00 3,075.00 3,225.00
making good all affected
walls and floors.
Closet pedestal type
Dem -
038
disconnecting and plugging No 1,400.00 1,325.00 1,325.00 1,350.00 1,425.00
sewer connection.
5.4.Excavator
Removing top soil to a depth
Exc - not exceeding 6" &
m2 258.00 248.00 248.00 248.00 269.00
001 depositing as directed within
site.
Excavation over site to
reduce level in any material
except rock requiring
Exc -
blasting including m3 1,378.00 1,321.00 1,321.00 1,321.00 1,436.00
002
depositing and leveling as
directed up to a distance not
exceeding 10 m.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 25
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Excavation in trenches for
walls/column pits, in
soft/loose soil from 0 to 5ft
deep, part return fill in and
Exc - ram, and disposing surplus
m3 848.00 813.00 813.00 813.00 883.00
003 excavated material to a
distance not exceeding 10 m.
(Earth work support to be
paid separately where
necessary).
Excavation in trenches for
walls/column pits in
ordinary soil from 0 to 5ft
Exc -
deep, part return fill in and m3 1,908.00 1,829.00 1,829.00 1,829.00 1,988.00
004
ram, and disposing surplus
excavated material to a
distance not exceeding 10 m.
Excavation in trenches for
walls/column pits in
hard/dense soil from 0 to 5ft
Exc -
deep, part return fill in and m3 2,968.00 2,845.00 2,845.00 2,845.00 3,092.00
005
ram, and disposing surplus
excavated material to a
distance not exceeding 10 m.
Excavation in trenches for
walls/column pits in
mud/wet soil from 0 to 5ft
Exc -
deep, part return fill in and m3 2,120.00 2,032.00 2,032.00 2,032.00 2,208.00
006
ram, and disposing surplus
excavated material to a
distance not exceeding 10 m.
Excavation in trenches for
walls/column pits, in soft
disintegrated rock (not
Exc - requiring blasting) up to a
m3 2,544.00 2,438.00 2,438.00 2,438.00 2,650.00
007 depth of 5ft and disposing
surplus excavated material
to a distance not exceeding
10 m.
Benching rock in foundation
Exc -
in 3"-6" steps. (Blasting m2 6,738.00 6,685.00 6,886.00 6,483.00 6,893.00
008
prohibited)
Exc -
Soft rock excavation m3 3,428.00 3,322.00 3,322.00 3,286.00 3,569.00
009
Exc -
Hard rock excavation m3 5,159.00 5,018.00 5,018.00 4,947.00 5,371.00
010
Anti-termite treatment on
excavated foundation and
compacted soil under floors
Exc -
with Bifenthrin chemical m2 560.00 560.00 560.00 560.00 592.00
011
mix (Biflex Manufacturer)
or equivalent as per
manufactures specification.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 26
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Backfilling & compacting
Exc - pits and trenches with
m3 848.00 813.00 813.00 813.00 883.00
012 selected earth available at
site.
Exc - Backfilling & compacting
m3 4,912.00 3,657.00 3,657.00 3,657.00 2,509.00
013 pits and trenches with gravel
Backfilling & compacting
Exc -
pits and trenches with m3 5,521.00 4,673.00 4,470.00 4,673.00 2,915.00
014
granite dust
Backfilling & compacting
Exc -
pits and trenches with lime m3 Not Applicable
015
dust
Backfilling & compacting
Exc -
pits and trenches with red m3 Not Applicable
016
earth
Backfilling & compacting
Exc -
pits and trenches with river m3 8,975.00 6,502.00 6,705.00 7,314.00 7,995.00
017
sand
Filling Under Floors
Filling under floors
including leveling watering
Exc -
and compacting in 6" layers m3 1,696.00 1,625.00 1,625.00 1,625.00 1,767.00
018
with available and selected
earth at site.
Filling under floors
Exc - including leveling watering
m3 5,760.00 4,470.00 4,470.00 4,470.00 3,392.00
019 and compacting in 6" layers
with gravel
Filling under floors
Exc - including leveling watering
m3 6,369.00 5,486.00 5,283.00 5,486.00 3,799.00
020 and compacting in 6" layers
with granite dust
Filling under floors
Exc - including leveling watering
m3 Not Applicable
021 and compacting in 6" layers
with lime dust
Filling under floors
Exc - including leveling watering
m3 Not Applicable
022 and compacting in 6" layers
with red earth
Filling under floors
Exc - including leveling watering
m3 9,823.00 7,314.00 7,518.00 8,127.00 8,878.00
023 and compacting in 6" layers
with river sand.
External earth filling around
Exc -
the building with filling m3 Not Applicable
024
approved earth
External earth filling around
Exc -
the building with filling m3 4,664.00 3,822.00 3,651.00 3,775.00 2,244.00
025
granite dust.
External earth filling around
Exc -
the building with filling lime m3 Not Applicable
026
dust
Office of the Deputy Chief Secretary - Engineering Services, NP Page 27
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
External earth filling around
Exc -
the building with filling red m3 Not Applicable
027
earth
Cutting turf sods loading to
hand carts and transporting
up to 30yards laying and
Exc -
watering for 30 days m2 1,208.00 1,159.00 1,159.00 1,159.00 1,256.00
028
(Royalty for turf, pegging
and transport beyond
30yards paid separately.)
Earthwork Support
Earthwork support (open
planking) in trenches up to a
depth of 5ft 0" . Consider
Exc - trench of length of 15'- 0" ,
m2
029 width 3'- 0"and 5'- 0" depth 1,783.00 1,762.00 1,769.00 1,755.00 1,809.00
open planking to both faces.
[ total area - 2/(15'x 5') =150
sqft.]
Earthwork support (close
planking) in trenches up to
5ft 0" depth. Consider
Exc -
trench of length of 15'-0" , m2
030 2,722.00 2,694.00 2,701.00 2,686.00 2,755.00
width 3'- 0"and 5'- 0" depth
planking to both faces. [ total
area - 2/(15'x 5') =150 sqft.]
Earthwork support (Close
planking ) in deep
excavation in trenches up to
15'- 0" depth.
Exc -
Consider trench length of m2 3,042.00 3,008.00 3,015.00 3,001.00 3,079.00
031
15ft 0" width 5'- 6" at top
and 3'- 6" at bottom. [area
supported 2/(15'x 15')= 450
sqft]
5.5. Concrete Work
Mixing only
Cement concrete 1 : 3 : 6 (1")
Con - hand mixing, up to one cube.
m3 24,534.00 22,122.00 22,092.00 22,035.00 22,114.00
001 (Shuttering paid for
separately)
Con - Cement concrete 1 : 3 : 6 (1")
m3 19,696.00 17,863.00 17,794.00 17,772.00 17,399.00
002 using mixer mix.
Con - Cement concrete 1 : 3 : 6
m3 19,615.00 17,782.00 17,713.00 17,690.00 17,317.00
003 (1½") using mixer mix.
Con - Cement concrete 1 : 2½ : 5
m3 20,636.00 18,669.00 18,616.00 18,634.00 18,316.00
004 (1") using mixer mix.
Con - Cement concrete 1 : 2 : 4
m3 27,491.00 24,994.00 24,971.00 24,935.00 25,212.00
005 (¾") hand mixing.
Con - Cement concrete 1 : 2 : 4
m3 22,353.00 20,612.00 20,545.00 20,514.00 20,316.00
006 (¾") using mixer mix.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 28
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Con - Cement concrete 1 : 1½ : 3
m3 24,428.00 22,899.00 22,828.00 22,764.00 22,567.00
007 (¾") using mixer mix.
Con - Cement concrete 1 : 1 : 2
m3 30,173.00 28,503.00 28,411.00 28,333.00 28,047.00
008 (¾") using mixer mix.
Mixing and Placing
2" thick cement concrete 1:
Con -
3: 6 (1'') screed in foundation m2 1,166.00 1,067.00 1,065.00 1,061.00 1,055.00
009
at depths not exceeding 5'-0"
2" thick cement concrete 1:
Con - 3: 6 (1½'') screed in
m2 1,161.00 1,063.00 1,061.00 1,057.00 1,051.00
010 foundation at depths not
exceeding 5'-0"
3" thick cement concrete 1:
Con -
3: 6 (1'') screed in foundation m2 1,730.00 1,582.00 1,579.00 1,574.00 1,564.00
011
at depths not exceeding 5'-0"
3" thick cement concrete 1:
Con - 3: 6 (1½'') screed in
m2 1,724.00 1,576.00 1,572.00 1,568.00 1,558.00
012 foundation at depths not
exceeding 5'-0"
Con - 3" thick cement concrete in
m2 1,802.00 1,644.00 1,641.00 1,640.00 1,634.00
013 floor 1 : 2½ : 5 (1")
Con - 3" thick cement concrete in
m2 1,932.00 1,792.00 1,788.00 1,783.00 1,786.00
014 floor 1 : 2 : 4 (¾")
Con - 3" thick cement concrete in
m2 2,090.00 1,966.00 1,962.00 1,954.00 1,957.00
015 floor 1 : 1½ : 3 (¾")
6" thick cement concrete
Con - screed in foundation, Mass
m3 23,678.00 21,757.00 21,724.00 21,630.00 21,487.00
016 concrete 1: 3: 6 (1½'') at
depths not exceeding 5'-0"
1:2:4 (¾'') Reinforced
Con -
cement concrete for footing, m3 28,720.00 26,837.00 26,835.00 26,674.00 26,856.00
017
plinth beam and etc.
1 : 1½ : 3 (¾") Reinforced
Con -
cement concrete for footing, m3 30,794.00 29,124.00 29,118.00 28,924.00 29,106.00
018
plinth beam and etc.
Cement concrete 1:2:4 (¾'')
Con -
in 4½"x 6'' column in ground m3 32,825.00 30,727.00 30,751.00 30,619.00 31,031.00
019
floor
Cement concrete 1 : 1½ : 3
Con -
(¾") in 4½"x 6'' column in m3 34,899.00 33,013.00 33,034.00 32,870.00 33,282.00
020
ground floor
Cement concrete 1:2:4 (¾'')
Con -
in 6"x 6'' column in ground m3 32,611.00 30,533.00 30,557.00 30,405.00 30,835.00
021
floor
Cement concrete 1 : 1½ : 3
Con -
(¾") in 6"x 6'' column in m3 34,685.00 32,819.00 32,840.00 32,656.00 33,086.00
022
ground floor
Cement concrete 1:2:4 (¾'')
Con -
in 9"x 9'' column in ground m3 32,352.00 30,289.00 30,314.00 30,146.00 30,591.00
023
floor
Office of the Deputy Chief Secretary - Engineering Services, NP Page 29
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Cement concrete 1 : 1½ : 3
Con -
(¾") in 9"x 9'' column in m3 34,426.00 32,575.00 32,596.00 32,397.00 32,842.00
024
ground floor
Cement concrete 1:2:4 (¾'')
Con -
in 12"x 12'' column in m3 31,317.00 29,300.00 29,316.00 29,147.00 29,541.00
025
ground floor
Cement concrete 1 : 1½ : 3
Con -
(¾") in 12"x 12'' column in m3 33,391.00 31,586.00 31,598.00 31,398.00 31,792.00
026
ground floor
Cement concrete 1:2:4 (¾'')
Con -
in 13½'' x 13½'' column in m3 31,150.00 29,135.00 29,149.00 28,986.00 29,366.00
027
ground floor
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 13½'' x 13½'' column m3 33,224.00 31,421.00 31,431.00 31,237.00 31,617.00
028
in ground floor
Cement concrete 1: 2: 4 (¾'')
Con -
in 6'' x 6'' beam up to first m3 34,604.00 32,491.00 32,516.00 32,319.00 32,948.00
029
floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 6'' x 6'' beam up to m3 36,678.00 34,778.00 34,798.00 34,570.00 35,199.00
030
first floor.
Cement concrete 1: 2: 4 (¾'')
Con -
in 9'' x 6'' beam up to first m3 34,439.00 32,326.00 32,351.00 32,154.00 32,783.00
031
floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 9'' x 6'' beam up to m3 36,513.00 34,613.00 34,634.00 34,405.00 35,034.00
032
first floor.
Cement concrete 1: 2: 4 (¾'')
Con -
in 9'' x 9'' beam up to first m3 34,347.00 32,205.00 32,230.00 32,062.00 32,664.00
033
floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 9'' x 9'' beam up to m3 36,421.00 34,491.00 34,512.00 34,313.00 34,915.00
034
first floor.
Cement concrete 1 : 2 : 4
Con -
(¾'') in 5'' thick floor slab in m3 28,600.00 26,661.00 26,641.00 26,536.00 26,742.00
035
first floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 5'' thick floor slab in m3 30,674.00 28,947.00 28,923.00 28,787.00 28,993.00
036
first floor.
Cement concrete 1 : 2 : 4
Con -
(¾'') in 6'' thick floor slab in m3 28,591.00 26,655.00 26,635.00 26,527.00 26,737.00
037
first floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 6'' thick floor slab in m3 30,665.00 28,942.00 28,918.00 28,778.00 28,987.00
038
first floor.
Cement concrete 1 : 2 : 4
Con -
(¾'') in 4½"x 6'' continuous m3 34,270.00 32,093.00 32,118.00 31,985.00 32,554.00
039
lintel in ground floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 4½"x 6'' continuous m3 36,344.00 34,379.00 34,400.00 34,236.00 34,805.00
040
lintel in ground floor.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 30
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Cement concrete 1 : 2 : 4
Con -
(¾'') in 9"x 9'' continuous m3 34,182.00 32,040.00 32,065.00 31,897.00 32,499.00
041
lintel in ground floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 9"x 9'' continuous m3 36,256.00 34,326.00 34,347.00 34,148.00 34,750.00
042
lintel in ground floor.
Cement concrete 1 : 2 : 4
Con -
(¾'') in 9"x 12'' continuous m3 34,172.00 32,034.00 32,059.00 31,887.00 32,493.00
043
lintel in ground floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 9"x 12'' continuous m3 36,246.00 34,321.00 34,341.00 34,138.00 34,744.00
044
lintel in ground floor.
Cement concrete 1 : 2 : 4
Con -
(¾'') in 12"x 15'' continuous m3 34,142.00 32,017.00 32,041.00 31,857.00 32,474.00
045
lintel in ground floor.
Cement concrete 1 : 1½ : 3
Con -
(¾'') in 12"x 15'' continuous m3 36,217.00 34,303.00 34,324.00 34,108.00 34,725.00
046
lintel in ground floor.
Casting 12"x12", 2" thick
Con -
cement concrete 1:2:4(3/4") No 288.00 277.00 279.00 276.00 281.00
047
cover slab.
5.6.Form Work
Sawn timber formwork to
Con -
9''x 9'' cement concrete m2 3,793.00 3,749.00 3,800.00 3,710.00 3,867.00
048
column in ground floor
Sawn timber formwork for
Con -
concrete beam in ground m2 5,031.00 4,949.00 4,990.00 4,915.00 5,149.00
049
floor
Con - Sawn timber formwork for
m2 3,043.00 3,001.00 3,013.00 2,988.00 3,081.00
050 under side of first floor slab.
Sawn timber formwork for
Con -
column footings, wall and m2 698.00 655.00 658.00 651.00 663.00
051
plinth beam etc.
Con -
Formwork for lintels. m2 948.00 900.00 907.00 892.00 919.00
052
Shuttering for columns up to
4' 00'' height, including
transporting, erecting and
dismantling, using
Con - prefabricated steel shutter
m2 1,070.00 1,057.00 1,065.00 1,102.00 1,086.00
053 halves and necessary fixing
arrangements. The surface
shall be clean and smooth.
The rate shall inclusive of all
props and cleaning moulds.
5.7.Reinforcement
Tor steel reinforcement to
lintels, slab, beam and
Con -
column etc bent to shape laid kg
054 383.00 377.00 377.00 379.00 385.00
in position & tied with GI
wire as directed.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 31
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Mild steel reinforcement to
lintels, slab, beam and
Con -
055
column etc bent to shape laid kg 383.00 377.00 377.00 379.00 385.00
in position & tied with GI
wire as directed.
5.8.Ready Mixed Cement Concrete
Supplying, pumping and
laying ready mixed cement
Con - concrete Grade 20 [Target
m3 36,383.00 40,463.00 42,473.00 45,120.00 36,188.00
056 mean strength 30N/mm2].
Up to 30m3 Transport
included
Supplying, pumping and
laying ready mixed cement
Con - concrete Grade 25 [Target
m3 37,683.00 42,963.00 44,973.00 45,720.00 37,188.00
057 mean strength 35N/mm2].
Up to 30m3 Transport
included
Additional concrete
Con -
pumping truck charges - m3 1,200.00 1,200.00 1,200.00 1,200.00 1,200.00
058
Above 30.00 m3
5.9.Masonry Work
Random rubble masonry in
Mas -
cement mortar 1:5 in m3 20,389.00 18,852.00 18,127.00 18,004.00 17,420.00
001
foundation
Random rubble masonry in
Mas -
cement mortar 1:5 in m3 21,714.00 20,141.00 19,435.00 19,276.00 18,790.00
002
superstructure
Cement concrete block in
Mas -
1:4:5 (¾'') masonry in 1:5 m3 35,292.00 32,224.00 32,452.00 32,101.00 33,152.00
003
cement and sand.
150 mm Block m2 5,294.00 4,834.00 4,868.00 4,815.00 4,973.00
125 mm Block m2 4,412.00 4,028.00 4,057.00 4,013.00 4,144.00
100 mm Block m2 3,529.00 3,222.00 3,245.00 3,210.00 3,315.00
Cement sand block in 1:6
Mas -
mix in masonry in 1:5 m3 25,094.00 22,712.00 23,055.00 23,253.00 24,555.00
004
cement and sand.
150 mm Block m2 3,764.00 3,407.00 3,458.00 3,488.00 3,683.00
125 mm Block m2 3,137.00 2,839.00 2,882.00 2,907.00 3,069.00
100 mm Block m2 2,509.00 2,271.00 2,306.00 2,325.00 2,456.00
Hollow Block Masonry
8" thick Hollow block
Mas - masonry in cement and sand
m2 4,100.00 4,034.00 4,059.00 4,026.00 4,113.00
005 mortar 1:5 with cavities
unfilled.
4" thick Hollow block
Mas - masonry in cement and sand
m2 3,332.00 3,291.00 3,309.00 3,281.00 3,345.00
006 mortar 1:5 with cavities
unfilled.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 32
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Curb in cement concrete
Mas - 1:2:4 (¾") 9" height and 3"
007 thick, cement rendered ½"
lm 2,196.00 2,130.00 2,162.00 2,096.00 2,207.00
thick including excavation.
Pad stones, cement, concrete
Mas - 1:2:4 (¾") precast or in
008 situ.1'-6" x 0'-9" x 0'-6"
no 1,117.00 1,042.00 1,047.00 1,037.00 1,062.00
.(450mmx225mmx150mm)
Slabs over drain, cement
concrete 3" 'thick, 1:2:4 (¾")
Mas - reinforced with expanded
m2 4,320.00 4,031.00 4,054.00 4,019.00 4,123.00
009 metal and ½" cement
rendered 1:2 (R/F paid for
separately).
Spur Stones, cement
Mas -
concrete 1:2:4 (¾") for door No 136.00 133.00 136.00 131.00 139.00
010
posts supplied and fixed.
Drains and Ramps
note: all drains and ramps shall be constructed with lean concrete base and with proper masonry
works. if necessary reinforcement shall be used. in pricing the items, lean concrete, masonry works
and reinforcement shall be measured and paid separately unless they are included in description.
Drains semicircular in
cement concrete 1 : 2½ : 5
(1") 9" wide and 9" average
depth, 3" thick sides and
base with necessary masonry
work and reinforcement,
Mas -
inclusive of ½" cement lm 3,320.00 3,136.00 3,169.00 3,121.00 3,261.00
011
rendering 1:3 with necessary
expansion joints, excavation
and back filling, but without
ramp. (Reinforcement and
masonry work paid
separately)
Drains semicircular in
cement concrete 1: 2½: 5
(1") 9" wide and 9" average
depth, 3" thick sides and
base with necessary masonry
work and reinforcement,
inclusive of ½" cement
Mas -
rendering 1:3 and 750 mm lm 5,490.00 5,147.00 5,188.00 5,129.00 5,312.00
012
wide ramp in 1: 2½: 5 (1"),
3” thick with necessary
expansion joints and
excavation and back filling.
(Reinforcement and
masonry work paid
separately)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 33
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Drains semi circular in
cement concrete 1 : 2 : 4
(¾") 9" wide and 9" average
depth, 3" thick sides and
base with necessary masonry
work and reinforcement,
Mas -
013
inclusive of ½" cement lm 3,397.00 3,225.00 3,257.00 3,206.00 3,344.00
rendering 1:3 with necessary
expansion joints, excavation
and back filling, but without
ramp (Reinforcement and
masonry work paid
separately).
Drains semicircular in
cement concrete 1 : 2 : 4
(¾") 9" wide and 9" average
depth, 3" thick sides and
base with necessary masonry
work and reinforcement,
inclusive of ½" cement
Mas -
rendering 1:3 and 750 mm lm 5,666.00 5,349.00 5,388.00 5,323.00 5,511.00
014
wide ramp in 1 : 2 : 4 (¾"),
3"thick with necessary
expansion joints, excavation
and back filling
(Reinforcement and
masonry work paid
separately).
Ramp in cement concrete 1:
2½: 5 (1"), 3" thick,
inclusive of ½" cement
rendering 1:3 with necessary
Mas - expansion joints,
m2 2,094.00 1,924.00 1,921.00 1,920.00 1,937.00
015 excavation, back filling and
side wall with masonry
work. Masonry work
measured separately. [750
mm wide ramp].
Ramp in cement concrete 1:
2: 4 (¾"), 3" thick, inclusive
of ½" cement rendering 1:3
with necessary expansion
Mas -
joints, excavation and back m2 3,468.00 3,227.00 3,223.00 3,213.00 3,246.00
016
filling [750 mm wide ramp].
Rate include for 3"thick 18"
height side wall with cement
concrete 1: 2: 4 (¾")
Office of the Deputy Chief Secretary - Engineering Services, NP Page 34
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Spreading with 25mm
granite metal ramp with a
width of 150mm including
excavation, 150mm width
and 75mm thick base
concrete in 1:3:6(25mm),
3"thick curb wall concrete in
Mas -
1:2:4(20mm) with 10mm dia m2 6,934.00 6,294.00 6,309.00 6,356.00 6,459.00
017
tor steel at 300mm centers in
vertical , horizontally
225mm spacing with 6mm
dia mild steel, necessary
formwork, earth filling
depth not exceeding 350mm,
rendering, etc.
5.10.Brick Work
Brick work in cement and
Bri -
sand 1:5 in foundation up to m3 26,290.00 22,551.00 23,723.00 25,170.00 21,705.00
001
DPC
Brick work in cement and
Bri -
sand 1:8 in foundation up to m3 25,495.00 21,484.00 22,681.00 24,205.00 20,746.00
002
DPC
Brick work in cement and
Bri -
sand 1:5 in 4 ½" thick wall in m2 3,175.00 2,734.00 2,879.00 3,030.00 2,639.00
003
ground floor
Brick work in cement and
Bri -
sand 1:5 in 9" thick wall in m2 6,097.00 5,223.00 5,498.00 5,823.00 5,034.00
004
ground floor
Brick work in cement and
Bri -
sand 1:5 in 13 ½" thick super m2 9,218.00 7,892.00 8,309.00 8,808.00 7,601.00
005
structure in ground floor
Brick work in cement and
Bri -
sand 1:8 in 9" thick super m2 5,964.00 5,020.00 5,305.00 5,654.00 4,846.00
006
structure in ground floor
Brick work (wire cut) in
Bri -
cement and sand 1:5 in 4 ½" m2 5,526.00 5,157.00 5,775.00 5,153.00 5,233.00
007
thick wall in ground floor
Brick work (wire cut) in
Bri -
cement and sand 1:5 in 9" m2 10,538.00 9,811.00 10,991.00 9,820.00 9,966.00
008
thick wall in ground floor
Brick work (wire cut) in
Bri -
cement and sand 1:5 in 13 m2 16,297.00 15,167.00 16,983.00 15,186.00 15,413.00
009
½" thick in ground floor
3'' thick brick paved floor in
Bri -
lime mortar 2:5 in ground m2 3,017.00 2,693.00 2,787.00 2,891.00 2,682.00
010
floor
Steps 1'- 1 1/2''x 0'- 6''in
brick in cement and sand 1:5
Bri - with ½" thick cement and
lm 2,610.00 2,259.00 2,362.00 2,472.00 2,239.00
011 sand 1:2 rendering including
necessary excavation and
backfilling.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 35
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Brick drains in cement and
sand 1:5, 9" wide and 6"-9"
average depth including 3''
thick 9'' width 1:3:6 (1")
cement concrete base,
Bri -
cement rendering ½" thick lm 4,228.00 3,813.00 3,954.00 4,034.00 3,835.00
012
1:2 to exposed faces with 1'
- 6'' ramp necessary
excavation and back filling.
(Lean concrete paid
separately)
Brick drains in cement and
sand 1:5, 9" wide and 6"-9"
average depth including 3''
thick 9'' width 1:3:6 (1")
cement concrete base,
Bri -
013
cement rendering ½" thick lm 3,590.00 3,254.00 3,366.00 3,428.00 3,290.00
1:2 to exposed faces without
ramp including necessary
excavation and back filling
(Lean concrete paid
separately).
Expansion joints in brick
Bri -
014
floors, filling with bitumen lm 113.00 111.00 113.00 109.00 116.00
and sand.
5.11.Paving Work
Expansion joints in concrete
Pav - floors filling with bitumen
001 and sand (to full depth of
lm 254.00 255.00 261.00 244.00 259.00
concrete and rendering).
Floor tile
200mm x 200mm size, Non-
skid floor tiles bedded in ½"
cement mortar 1:2 and
Pav - pointed with tile grout to
m2 8,137.00 8,048.00 8,072.00 8,048.00 8,169.00
002 match the tiles. (Prime cost
of 200mm x 200mm floor
tile [Lanka tile or
equivalent] 208.00 /=)
200mm x 200mm size, Non-
skid floor tiles on exsisting
bedding and pointed with
Pav -
tile grout to match the tiles. m2 7,048.00 7,008.00 7,019.00 7,008.00 7,073.00
003
(Prime cost of 200mm x
200mm floor tile [Lanka tile
or equivalent] 208.00 /= )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 36
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
300mm x 300mm size, Non-
skid floor tiles bedded in
½"cement mortar 1:2 and
Pav - pointed with tile grout to
m2 6,464.00 6,375.00 6,399.00 6,375.00 6,496.00
004 match the tiles.(Prime cost
of 300mm x 300mm floor
tile [Lanka tile or
equivalent] 320.00/= )
300mm x 300mm size, Non-
skid floor tiles on existing
bedding and pointed with
Pav -
tile grout to match the tiles. m2 5,376.00 5,335.00 5,346.00 5,335.00 5,400.00
005
( Prime cost of 300mm x
300mm floor tile [Lanka tile
or equivalent] 320.00 /= )
400mm x 400mm size, Non-
skid floor tiles bedded in ½"
cement mortar 1:2 and
Pav - pointed with tile grout to
m2 8,388.00 8,323.00 8,299.00 8,420.00
006 match the tiles.(Prime cost 8,299.00
of 400mm x 400mm floor
tile [Lanka tile or
equivalent] 860.00 /= )
400mm x 400mm size, Non-
skid floor tiles on existing
bedding and pointed with
Pav -
tile grout to match the m2 7,299.00 7,259.00 7,270.00 7,259.00 7,324.00
007
tiles.(Prime cost of 400mm x
400mm floor tile [Lanka tile
or equivalent] 860.00 /= )
600mm x 600mm size, Non-
skid floor tiles bedded in ½"
cement mortar 1:2 and
pointed with tile grout to
Pav -
match the tiles. (Prime cost m2 5,984.00 5,895.00 5,919.00 5,895.00 6,016.00
008
of 600mm x 600mm floor
tile [Lanka tile or
equivalent] not less than
1,110.00 /= Excluding vat )
600mm x 600mm size, Non-
skid floor tiles on existing
bedding and pointed with
Pav - tile grout to match the tiles.
m2 4,895.00 4,855.00 4,866.00 4,855.00 4,920.00
009 (Prime cost of 600mm x
600mm floor tile [Lanka tile
or equivalent] not less than
1,110.00 = Excluding vat )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 37
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
300mm x 600mm size,
Homogenous porcelain
Matt floor tile bedded in
Pav - ½"cement mortar 1:2 and
m2 6,390.00 6,302.00 6,326.00 6,302.00 6,423.00
010 pointed with tile grout to
match the tiles.(Prime cost
of Floor tile [Rocell or
equivalent] 627.00/= )
300mm x 600mm size,
Homogenous porcelain
Matt floor tile on existing
Pav - bedding and pointed with
m2 5,302.00 5,262.00 5,273.00 5,262.00 5,326.00
011 tile grout to match the
tiles.(Prime cost of Floor
tile [ Rocell or equivalent]
627.00 /= )
300mm x 600mm size,
Homogenous porcelain
Matt floor tile bedded in ½"
Pav - cement mortar 1:2 and
m2 6,390.00 6,302.00 6,326.00 6,302.00 6,423.00
012 pointed with tile grout to
match the tiles.(Prime cost
of Floor tile [Rocell or
equivalent] 627.00 /= )
300mm x 600mm size,
Homogenous porcelain
Matt floor tile on existing
Pav - bedding and pointed with
m2 5,302.00 5,262.00 5,273.00 5,262.00 5,326.00
013 tile grout to match the
tiles.(Prime cost of Floor
tile [Rocell or equivalent]
627.00 /= )
300mm x 600mm size,
Homogenous porcelain
semi gloss floor tile bedded
Pav - in ½" cement mortar 1:2 and
m2 7,634.00 7,545.00 7,569.00 7,545.00 7,666.00
014 pointed with tile grout to
match the tiles.(Prime cost
of Floor tile [ Rocell or
equivalent] 847.00 /= )
300mm x 600mm size,
Homogenous porcelain
semi gloss floor tile on
Pav - existing bedding and pointed
m2 6,545.00 6,505.00 6,516.00 6,505.00 6,570.00
015 with tile grout to match the
tiles.(Prime cost of Floor
tile [Rocell or equivalent]
847.00/= )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 38
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
400mm x 400mm size,
Homogenous porcelain
Matt floor tile bedded in ½"
Pav - cement mortar 1:2 and
m2 Not Applicable
016 pointed with tile grout to
match the tiles.( Prime cost
of Floor tile [ Rocell or
equivalent] N/A/= )
400mm x 400mm size,
Homogenous porcelain
Matt floor tile on existing
Pav - bedding and pointed with
m2 Not Applicable
017 tile grout to match the
tiles.(Prime cost of Floor
tile [Rocell or equivalent]
N/A/= )
300mm x 300mm size,
Homogenous porcelain
Semi gloss floor tile bedded
Pav - in ½" cement mortar 1:2 and
m2 Not Applicable
018 pointed with tile grout to
match the tiles.( Prime cost
of Floor tile [ Rocell or
equivalent] N/A /= )
300mm x 300mm size,
Homogenous porcelain
Semi gloss floor tile on
Pav - existing bedding and pointed
m2 Not Applicable
019 with tile grout to match the
tiles.( Prime cost of Floor
tile [ Rocell or equivalent]
N/A/= )
300mm x 300mm size,
Homogenous porcelain
Semi gloss floor tile bedded
Pav - in ½" cement mortar 1:2 and
m2 Not Applicable
020 pointed with tile grout to
match the tiles.( Prime cost
of Floor tile [ Rocell or
equivalent] N/A/= )
300mm x 300mm size,
Homogenous porcelain
Semi gloss floor tile on
Pav - existing bedding and pointed
m2 Not Applicable
021 with tile grout to match the
tiles.(Prime cost of Floor
tile [Rocell or equivalent]
N/A /= )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 39
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
400mm x 400mm size,
Homogenous porcelain
Semi gloss floor tile bedded
Pav - in ½" cement mortar 1:2 and
m2 Not Applicable
022 pointed with tile grout to
match the tiles.(Prime cost
of Floor tile [Rocell or
equivalent] N/A /= )
400mm x 400mm size,
Homogenous porcelain
Semi gloss floor tile on
Pav - existing bedding and pointed
m2 Not Applicable
023 with tile grout to match the
tiles.(Prime cost of Floor
tile [Rocell or equivalent]
N/A/= )
400mm x 400mm size,
Homogenous porcelain
Semi gloss floor tile bedded
Pav - in ½" cement mortar 1:2 and
m2 Not Applicable
024 pointed with tile grout to
match the tiles.(Prime cost
of Floor tile [Rocell or
equivalent] N/A /= )
400mm x 400mm size,
Homogenous porcelain
Semi gloss floor tile on
Pav - existing bedding and pointed
m2 Not Applicable
025 with tile grout to match the
tiles.(Prime cost of Floor
tile [Rocell or equivalent]
N/A/= )
600mm x 600mm size,
Homogenous porcelain
Polished floor tile bedded in
½"cement mortar 1:2 and
Pav -
pointed with tile grout to m2 9,942.00 9,853.00 9,878.00 9,853.00 9,974.00
026
match the tiles.(Prime cost
of Floor tile [Rocell or
equivalent] not less than
2,511.00 /= Excluding vat )
600mm x 600mm size,
Homogenous porcelain
Polished floor tile on
existing bedding and pointed
Pav -
with tile grout to match the m2 8,854.00 8,814.00 8,824.00 8,814.00 8,878.00
027
tiles.(Prime cost of Floor
tile [Rocell or equivalent]
not less than 2,511.00 /=
Excluding vat )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 40
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
600mm x 600mm size,
Homogenous porcelain
Semi gloss floor tile bedded
in ½" cement mortar 1:2 and
Pav -
pointed with tile grout to m2 7,552.00 7,463.00 7,487.00 7,463.00 7,584.00
028
match the tiles.( Prime cost
of Floor tile [ Rocell or
equivalent] not less than
1,665.00/= Excluding vat )
600mm x 600mm size,
Homogenous porcelain
Semi gloss floor tile on
existing bedding and pointed
Pav -
with tile grout to match the m2 6,464.00 6,423.00 6,434.00 6,423.00 6,488.00
029
tiles.( Prime cost of Floor
tile [ Rocell or equivalent]
not less than 1,665.00 /=
Excluding vat )
600mm x 600mm size,
Homogenous porcelain
Matt finish floor tile bedded
in ½" cement mortar 1:2 and
Pav -
pointed with tile grout to m2 7,750.00 7,661.00 7,685.00 7,661.00 7,782.00
030
match the tiles.( Prime cost
of Floor tile [ Rocell or
equivalent] not less than
1,735.00 /= Excluding vat )
600mm x 600mm size,
Homogenous porcelain
Matt finish floor tile on
existing bedding and pointed
Pav -
with tile grout to match the m2 6,661.00 6,621.00 6,632.00 6,621.00 6,686.00
031
tiles.( Prime cost of Floor
tile [ Rocell or equivalent]
not less than 1,735.00 /=
Excluding vat )
Tile skirting
100mm hight tiles skirting to
walls including 1:3 cement
sand bed and tile mortar
Pav - grout.( Prime cost of
032 600mm x 600mm floor tile
lm 427.00 424.00 424.00 425.00 428.00
[Lanka tile or equivalent]
not less than 1,110.00/=
Excluding vat )
100mm hight tiles skirting to
walls including 1:3 cement
sand bed and tile mortar
Pav - grout.( Prime cost of
033 600mm x 600mm Polished
lm 847.00 844.00 844.00 845.00 848.00
Floor tile [ Rocell or
equivalent] not less than
2,511.00 /= Excluding vat )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 41
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
100mm hight tiles skirting to
walls including 1:3 cement
sand bed and tile mortar
Pav - grout.(Prime cost of 600mm
034 x 600mm semi gloss Floor
lm 593.00 590.00 590.00 591.00 594.00
tile [Rocell or equivalent]
not less than 1,665.00 /=
Excluding vat )
100mm hight tiles skirting to
walls including 1:3 cement
sand bed and tile mortar
Pav - grout.(Prime cost of 600mm
lm 614.00 611.00 611.00 612.00 615.00
035 x 600mm Matt finish Floor
tile [Rocell or equivalent]
not less than 1,735.00/=
Excluding vat )
Wall tile
300mm x 600mm size,
Glazed tile fixed to walls
including bedding in 1/2"
thick cement mortor 1:2 and
Pav - raking and pointed with tile
m2 5,085.00 4,996.00 5,020.00 4,996.00 5,117.00
036 grout to match the tiles.
(Prime cost of 300mm x
600mm wall tile [Lanka tile
or equivalent] not less than
475.00/= Excluding vat )
300mm x 600mm size,
Glazed tile fixed to walls on
existing rendered wall and
raking and pointed with tile
Pav -
grout to match the tiles. m2 3,997.00 3,956.00 3,967.00 3,956.00 4,021.00
037
(Prime cost of 300mm x
600mm wall tile [Lanka tile
or equivalent] not less than
475.00/= Excluding vat )
300mm x 450mm Glazed
tile fixed to walls including
bedding in 1/2" thick cement
mortor 1:2 and raking and
Pav -
pointed with tile grout to m2 Not Applicable
038
match the tiles. ( Prime cost
of 300mm x 450mm
Ceramic wall tile [ Rocell or
equivalent] N/A /=)
300mm x 450mm Glazed
tile fixed to exsisting
rendered walls raking and
Pav - pointed with tile grout to
m2 Not Applicable
039 match the tiles. ( Prime cost
of 300mm x 450mm
Ceramic wall tile [ Rocell or
equivalent] N/A/= )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 42
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
300mm x 600mm Glazed
tile fixed to walls including
bedding in 1/2" thick cement
mortor 1:2 and raking and
Pav - pointed with tile grout to
m2 6,712.00 6,624.00 6,648.00 6,624.00 6,745.00
040 match the tiles. ( Prime cost
of 300mm x 600mm
Ceramic wall tile [ Rocell or
equivalent] not less than
763.00 /= Excluding vat )
300mm x 600mm Glazed
tile fixed to exsisting
rendered walls and raking
and pointed with tile grout to
Pav -
match the tiles. (Prime cost m2 5,624.00 5,584.00 5,595.00 5,584.00 5,649.00
041
of 300mm x 600mm
Ceramic wall tile [Rocell or
equivalent] not less
than763.00/= Excluding vat)
5.12.Roof Work
If the timber is kempas, the use of imported kempas is only allowed and the rate of imported timber is used
in the analysis.
Roof with calicut pattern
tiles laid on kempas
(imported) / special upper
class timber frame work for
hip roof in single storey
building consisting of wall
plate, beam, ridge plate,
Roo -
rafters, reepers etc. Rate to m2 8,380.00 8,497.00 8,653.00 8,284.00 8,600.00
001
include calicut pattern ridge
tile laid on bedded, cement
and sand 1:5 and pointed
with cement and sand 1:3
coloured to match the colour
of tiles. ( Prime cost of clay
tile 105.00 /= )
Roo - Gable end roof on …do…
m2 7,284.00 7,399.00 7,554.00 7,185.00 7,507.00
002 …do… …do…
Hip Roof covering with
calicut pattern clay tiles in
Roo - single storey building on
m2 2,115.00 2,189.00 2,333.00 2,051.00 2,247.00
003 existing timber frame work.
( Prime cost of clay tile not
less than 105.00 /= )
Roo - Gable end roof on …do…
m2 1,979.00 2,050.00 2,193.00 1,911.00 2,115.00
004 …do… …do…
Roof with corrugated
asbestos sheet fixed on
Roo - kempas (imported) / special
m2 5,616.00 5,588.00 5,599.00 5,578.00 5,628.00
005 upper class timber frame
work in single storeyed
building
Office of the Deputy Chief Secretary - Engineering Services, NP Page 43
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Roof with corrugated asbestos
Roo -sheet (Timber frame work and
m2 2,250.00 2,233.00 2,236.00 2,230.00 2,246.00
006 ridge covering measured
separately )
Asbestos close fittings ridging
Roo -
007
fixed complete with roofing lm 2,341.00 2,315.00 2,321.00 2,309.00 2,330.00
screws or bolts (Hook)
Ridging covering with calicut
Roo -
pattern ridge tiles bedded in lm 1,167.00 1,201.00 1,210.00 1,205.00 1,139.00
008
cement lime mortar 1:1:4.
Tiles, Calicut pattern, flat
supplied and laid up to 5 tiles
Roo -
in single storeyed buildings. No 155.00 158.00 168.00 148.00 167.00
009
(Prime cost of clay tile not less
than 105.00 /= )
Tiles, Calicut pattern, flat
supplied and laid (above 5 and
Roo -up to 25 tiles) in single
No 125.00 129.00 139.00 119.00 136.00
010 storeyed buildings. (Prime cost
of clay tile not less than
105.00 /= )
Tiles, Calicut pattern flat
Roo -supplied and laid in any
m2 1,542.00 1,604.00 1,738.00 1,469.00 1,682.00
011 building. ( Prime cost of clay
tile not less than 105.00 /=)
Tiles, Calicut pattern flat
Roo -supplied and laid in any
m2 129.00 124.00 124.00 124.00 135.00
012 building. (Tiles available at
site)
Roo -Shifting and re - laying calicut
m2 258.00 248.00 248.00 248.00 269.00
013 tiles
¾ ''x 9" high valance board in
Roo -
014
class I fixed with brass screws lm 1,370.00 1,361.00 1,375.00 1,336.00 916.00
to ends of rafters.
24 BWG (1.2mm) galvanized
iron sheet valley gutter 3'-0"
girth over all once bent with
end laps not less than 9" width
Roo -
015
including ¾" tongued and lm 12,421.00 12,342.00 12,370.00 12,330.00 12,473.00
grooved planks in spl upper
class laid to slope and profile
on timber (with wood
preservative ) members.
22 BWG (1.2mm) galvanized
iron sheet valley gutter 3'-0"
girth over all once bent with
end laps not less than 9" width
Roo -
016
including ¾" tongued and lm 13,295.00 13,217.00 13,245.00 13,205.00 13,347.00
grooved planks in spl upper
class laid to slope and profile
on timber (with wood
preservative ) members.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 44
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
24 BWG (1.2mm) galvanized
iron flashing 1' - 6" girth
overall 3 times bent with end
laps not less than 6" lead
Roo -soldered turned and tucked up
lm 3,186.00 3,135.00 3,138.00 3,147.00 3,198.00
017 to not less than 6" into chase
cut in wall and pointed in
cement mortar 1:2 lower end
dressed over roof covering not
less than 1'-0" wide.
Supplying laying sandwich
panel roofing GLAMT G5
A40, 0.47 - 0.35/0.32mm thick
Zn-Al sheet, PU - 50mm panel
density 40kg/m3 with
necessary fittings self-tapping
fasteners etc. On galvanized
Roo -iron 'C' channel purlin as per
m2 12,715.00 12,702.00 12,715.00 12,688.00 12,736.00
018 manufacturer’s specification.
Purlin measured separately.
(Prime cost of 50mm thickness
sandwich panels roof sheet
with transport [Top sheet
0.47mm thick & bottom sheet
0.35mm thick] 1,096.00 /= per
Sqft Excluding vat )
Zinc aluminium Coated
Profiled Steel Sheets shall be
roll -formed from high tensile
steel sheets to AS1397 - G 550
- AZ150 or other approved
international standards,
Minimum yield stress 550 Mpa
and coating mass 150 g/m2.
The sheeting shall have a baked
paint coating of Epoxy primer/
polyester paint of Epoxy
primer / PVF2 paint on the top
surface and Epoxy primer/
polyester paint at the back
Roo -surface. Base steel section shall
m2 5,027.00 5,003.00 4,987.00 5,011.00 5,035.00
019 be not less than 0.42 mm thick
and total coated thickness not
less than 0.47 mm. Type of
profile selected shall be
suitable for the internal and end
support spacing and conform to
the manufacturer's printed
literature. Approved colour laid
on existing frame work and
fixed with self-tapping
fasteners etc. ( Prime cost of
0.47mm Thickness Zinc
Aluminium alloy coated
trimclad roof sheet 380.00 /=
per Sqft Excluding vat )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 45
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Zinc aluminium Coated
Profiled Steel Sheets shall
be roll -formed from high
tensile steel sheets to
AS1397 - G 550 - AZ200
or other approved
international standards,
Minimum yield stress 550
Mpa and coating mass 200
g/m2. The sheeting shall
have a baked paint coating
of Epoxy primer/ polyester
paint of Epoxy primer /
PVF2 paint on the top
surface and Epoxy primer/
polyester paint at the back
surface. Base steel section
Roo - shall be not less than 0.42
m2 6,112.00 6,088.00 6,088.00 6,096.00 6,120.00
020 mm thick and total coated
thickness not less than 0.47
mm. Type of profile
selected shall be suitable
for the internal and end
support spacing and
conform to the
manufacturer's printed
literature. Approved colour
laid on existing frame work
and fixed with self-tapping
fasteners (NO 12-14 x 55
HGS (class 4)) etc. ( Prime
cost of 0.47mm Thickness
Zinc Aluminium alloy
coated trimclad roof sheet
441.00 /= per Sqft
Excluding vat )
Supplying & laying
0.47mm thick coloured Zn-
Roo - Al high tensile ridging with
021
lm 2,372.00 2,355.00 2,333.00 2,361.00 2,377.00
150g/m2 coating mass
fixed with self tapping
fasteners etc.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 46
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying & laying
0.47mm thick coloured Zn-
Roo - Al high tensile ridging with
022 200g/m2 coating mass
lm 3,160.00 3,126.00 3,126.00 3,153.00 3,148.00
fixed with self tapping
fasteners etc.
Supplying & fixing
0.47mm thickness,
Roo - 150g/m2coating mass Zn-
023 Al gutter with 700 mm
lm 2,502.00 3,094.00 3,110.00 2,549.00 2,558.00
girth on valance board with
external brackets.
Supplying & fixing
0.47mm thickness,
Roo - 200g/m2coating mass Zn-
024 Al gutter with 410 mm
lm 4,900.00 4,914.00 4,930.00 4,915.00 4,956.00
girth on valance board with
external brackets.
Supplying & fixing 100 x
100mm square 0.47mm
Roo -
thickness, 150g/m2 coating lm 2,901.00 3,073.00 3,080.00 3,093.00 2,960.00
025
mass Zn-Al down pipe
with necessary fittings.
Supplying & fixing 100 x
100mm square 0.47mm
Roo -
thickness, 200g/m2 coating lm 3,826.00 3,915.00 3,925.00 4,030.00 3,802.00
026
mass Zn-Al down pipe
with necessary fittings.
Supplying & laying 8mm
thick heat installation with
Roo -
75 x 75mm weld mesh m2 1,497.00 1,472.00 1,472.00 1,481.00 1,506.00
027
(gauge 17) under amino
(Zn/Al) sheet roofing.
Supplying & laying 5mm
thick heat installation with
Roo -
75 x 75mm weld mesh m2 1,298.00 1,273.00 1,273.00 1,282.00 1,307.00
028
(gauge 17) under amino
(Zn/Al) sheet roofing.
Supplying & laying 3mm
thick heat installation with
Roo -
75 x 75mm weld mesh m2 1,260.00 1,235.00 1,235.00 1,243.00 1,268.00
029
(gauge 17) under amino
(Zn/Al) sheet roofing.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 47
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
5.13.Carpentery And Joinery Work
Horizontal ceiling lining
using 4'- 0"x 4'- 0" flat
asbestos cement sheets fixed
to timber framework with 2
coats of colourless wood
preservative including
11/2"x 1/2" beading and
Car - 2"x2"cove mouldings on
m2 5,897.00 5,859.00 6,046.00 6,031.00 5,886.00
001 timber frame work.
Comprising of 4'' x 2'' 1200
mm centers joists and 2'' x 2''
bearers 600 mm centers in
kempas timber (imported)
/special upper class timber.
minimum thickness of
sheet is 4mm)
Horizontal ceiling lining
using 4'- 0"x 4'- 0" flat
asbestos free sheets fixed to
timber framework with 2
coats of colourless wood
preservative including
11/2"x1/2"beading and
Car - 2"x2"cove mouldings on
m2 5,559.00 5,499.00 5,607.00 5,471.00 5,601.00
002 timber frame work.
Comprising of 4'' x 2'' 1200
mm centers joists and 2'' x 2''
bearers 600 mm centers in
kempas timber (imported)
special upper class timber.
(minimum thickness of
sheet is 4mm)
Horizontal ceiling lining
using 4'- 0"x 4'- 0" flat
asbestos free sheets fixed to
timber framework with 2
coats of colourless wood
preservative including
aluminium beading 1" wide
both ways with rubber fillets
to aluminium beading on
Car - timber frame work.
m2 5,536.00 5,476.00 5,583.00 5,448.00 5,578.00
003 comprising of 4''x 2'' joists
1200mm centers, 2'' x 2''
bearers 600mm centers and
2"x1" spacer bearers not
exceeding 600mm centres to
from 600 x 600mm paneling
in kempas timber
(imported) / special upper
class timber. (minimum
thickness of sheet is 4mm)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 48
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying and installing non
asbestos/ asbestos free fiber
cement suspended ceiling
system. The frame members
for suspended ceiling are in
a standard kit(approved
type). Main runners (38mm)
are fixed at 1220 centers,
securely suspended using
4mm dia adjustable GI
hanging rod with spring
clips to the structural soffit
Car - or roof structure, using an
m2 3,310.00 3,256.00 3,280.00 3,029.00 3,304.00
004 appropriate suspension at
1220mm centres, cross tees
(27mm) of 1220mm length
to be fixed between the main
runners at 610mm centers
and another cross tees
(27mm) fixed at mid span
between 610mm to form a
grid structure of 610mm x
610mm in size. Wall angles
(24mm) are fixed at wall
edges. (minimum thickness
of sheet is 4mm)
Ceiling asbestos, flat in
eaves fixed with clout
headed nails to 2"x 2" & 2"x
1" bearers & spacers not
exceeding 2'-0" centres both
ways in kempas timber
Car -
(imported) / special upper m2 3,235.00 3,256.00 3,280.00 3,209.00 3,304.00
005
class timber including
11/2"x1/2"beading and
2"x2" cove moulding on
timber frame work. Rate to
include 2 coats of wood
preservative to timbers.
Ceiling asbestos, flat in
eaves fixed with clout
headed nails to 2"x 2" & 2"x
1" bearers & spacers not
exceeding 2'-0" centres both
ways in kempas timber
Car -
(imported) / special upper m2 6,095.00 6,139.00 6,209.00 6,012.00 6,128.00
006
class timber including
aluminium beading 1" wide
with rubber fillets to
aluminium beading. Rate to
include 2 coats of wood
preservative to timbers.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 49
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Cove mouldings Class I
Car - timber 2 "x 2" fixed with
lm 816.00 826.00 866.00 849.00 855.00
007 brass screws & plugs new or
renewed.
Car - Ceiling, upper side cleaned
m2 65.00 62.00 62.00 62.00 67.00
008 and debris cleared away.
Timber in special upper
Car -
class fixed or renewed in m3 289,576.00 289,046.00 290,636.00 287,456.00 290,901.00
009
roof beam and post.
Reapers 2"x 1" in Spl upper
class timber supplied &
Car - fixed new / renewed with
010 iron nails, up to 100 L.ft
lm 296.00 313.00 314.00 294.00 315.00
(shifting of tiles paid for
separately).
Reapers 2"x 1" in Spl upper
class timber supplied &
Car - fixed new / renewed with
lm 285.00 303.00 303.00 284.00 304.00
011 iron nails, over 100 L.ft
(shifting of tiles paid for
separately).
Door single hung with frame
having 1 1/8" to 1¼" thick
glazed / panelled sash 3 ¾"x
Car - 2 ¾" timber frame in Special
m2 27,795.00 27,716.00 28,112.00 27,391.00 27,871.00
012 upper class timber.
Complete with heavy quality
brass fittings. [Lock paid
separately]
Door double hung with
frame having 1 1/8" to 1¼"
thick glazed / panelled sash
Car - 3 ¾"x 2 ¾" timber frame in
m2 27,748.00 27,678.00 28,056.00 27,312.00 27,834.00
013 Special upper class timber.
Complete with heavy quality
brass fittings. [Lock paid
separately]
Plywood door single hung
with frame (Mackply,
Ginthotta or equivalent)
having 1¼" thick sash 3 ¾"x
Car -
2 ¾" timber frame in Special m2 16,083.00 16,548.00 17,175.00 15,992.00 15,967.00
014
upper class timber.
Complete with heavy quality
brass fittings. [Lock paid
separately]
Office of the Deputy Chief Secretary - Engineering Services, NP Page 50
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying and fixing Seal
core wood composite door
Car -
with frame fixed with m2 14,054.00 14,010.00 14,592.00 15,043.00 14,044.00
015
fittings and necessary
locking arrangements.
Door / window ledged
braced and battened single
hung with frame having ¾"
to 7/8" thick tongued and
grooved planks in Special
Car -
upper class timber and 3 m2 28,097.00 27,953.00 28,256.00 27,756.00 27,910.00
016
¾"x 2 ¾" timber frame in
Special upper class timber.
Complete with heavy
quality brass fittings. [Lock
paid separately]
Window glazed 1¼" thick
openable sashes with 3 ¾"x
2 ¾" timber frame and
Car -
mullions in Special upper m2 26,544.00 26,454.00 26,862.00 26,163.00 26,880.00
017
class timber. Complete
with heavy quality brass
fittings.
1/8'' glass panes exceeding
1'- 00'' but not exceeding 4
Car -
square feet cut and fixed m2 5,523.00 5,464.00 5,523.00 5,404.00 5,613.00
018
with timber beadings to
doors and windows.
Car - Door or window, removing
019 easing and re-fixing.
sash 956.00 938.00 956.00 919.00 984.00
Car - Door or window, easing
020 only.
sash 338.00 338.00 350.00 325.00 344.00
Door or window frames
Car - renewed in short lengths
m3 371,687.00 371,687.00 377,208.00 366,166.00 374,448.00
021 within special upper class
timber.
Door or window sashes
Car -
022
available fixed in position sash 1,913.00 1,875.00 1,913.00 1,838.00 1,969.00
(fittings paid separately)
Door sashes swing,
Car -
removed and re-fixed in sash 1,275.00 1,250.00 1,275.00 1,225.00 1,313.00
023
new position.
Door frame 4"x 3" in
Car - special upper class timber
m2 10,708.00 10,634.00 10,735.00 10,573.00 10,455.00
024 supplied and fixed in
position.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 51
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying and Installing non
asbestos mineral fiber
suspended ceiling system.
The frame members for
suspended ceiling are in a
standard kit(approved type).
Main runners (38mm) are
fixed at 1220 centers,
securely suspended using
4mm dia adjustable GI
hanging rod with spring
clips to the structural soffit
Car - or roof structure, using an
m2 6,775.00 6,721.00 6,745.00 6,673.00 6,769.00
024 appropriate suspension at
1220mm centres, cross tees
(27mm) of 1220mm length
to be fixed between the main
runners at 610mm centers
and another cross tees
(27mm) fixed at mid span
between 610mm to form a
grid structure of 610mm x
610mm in size. Wall angles
(24mm) are fixed at wall
edges. (minimum thickness
of sheet is 10mm)
5.14.Brass Founder
Bolts barrel, brass, polished,
Bra -
001
4" heavy quality supplied No 949.00 943.00 949.00 936.00 974.00
and fixed with brass screws.
Bolts barrel, brass, polished,
Bra -
6" heavy quality supplied No 1,059.00 1,053.00 1,059.00 1,046.00 1,084.00
002
and fixed with brass screws.
Skelton bolt, brass, polished,
Bra -
003
12" heavy quality supplied No 2,969.00 2,913.00 2,969.00 2,956.00 2,998.00
and fixed with brass screws.
Casement fastener brass
Bra - with motice plate, polished
004 heavy quality supplied and
No 1,295.00 1,287.00 1,295.00 1,278.00 1,316.00
fixed with brass screws.
Casement stays, polished
Bra -
005
10" heavy quality supplied No 689.00 693.00 719.00 706.00 736.00
and fixed.
Fanlight catches brass heavy
Bra -
quality with brass screws No 815.00 807.00 815.00 798.00 766.00
006
fixed complete.
Hinges brass 4" x 3" heavy
Bra -
007
quality supplied & fixed No 2,129.00 2,110.00 2,138.00 2,104.00 2,158.00
with brass screws complete.
Hinges center pivot
(consisting of 2 pieces) brass
Bra -
polished heavy quality set 1,297.00 1,285.00 1,303.00 1,280.00 1,316.00
008
supplied and fixed with
brass screws complete.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 52
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Draw Rings, brass 1 ¾" to
Bra - 1½" supplied and fixed to
009 doors & windows with brass
No 316.00 294.00 316.00 312.00 323.00
screws.
Rim lock with chromium
plated handle. ( Prime cost
Bra -
of Rim lock with screws & No 6,475.00 6,450.00 6,475.00 6,425.00 6,513.00
010
handle not less than 5,200.00
/= Per No )
Mortice lock [Single lever]
with handle. ( Prime cost of
Bra -
Mortice lock with screws & No 5,300.00 5,250.00 5,300.00 4,950.00 4,625.00
011
handle not less than 2,750.00
/= Per No )
Mortice lock [Single lever]
with handle. ( Prime cost of
Bra -
Mortice lock with screws & No 8,550.00 8,500.00 8,550.00 8,450.00 11,125.00
012
handle not less than 6,000.00
/= Per No )
5.15.Metal Work
Supplying and fixing
100mm x 50mm x (12-
20)mm size, 2mm thick G.I
"C" purlin fixed to wall or
cleats at not exceeding
Met - 900mm centres and joints
lm 2,434.00 2,427.00 2,430.00 2,431.00 2,436.00
001 should be bolted with 2 Nos
12mm dia bolts and nuts
other side welding with
cleats minimum length
450mm. As per
manufacturer's specification.
Supplying and fixing
100mm x 50mm x (12-
20)mm size, 2mm thick G.I
Zinc Coated and Chromate
Passivated "C" purlin fixed
to wall or cleats at not
Met - exceeding 900mm centers
002 and joints should be bolted
lm 2,921.00 2,914.00 2,917.00 2,918.00 2,923.00
with 2 Nos 12mm dia bolts
and nuts other side welding
with cleats minimum length
450mm (AZ-200 roofing).
As per manufacturer's
specification.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 53
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying and fixing
150mm x 65mm x (14-
20)mm size, 2mm thick G.I
"C" purlin fixed to wall or
cleats at not exceeding
Met - 900mm centres and joints
003 should be bolted with 2 Nos
lm 3,325.00 3,318.00 3,321.00 3,322.00 3,327.00
12mm dia bolts and nuts
other side welding with
cleats minimum length
450mm. As per
manufacturer's specification.
Supplying and fixing
150mm x 65mm x (14-
20)mm size, 2mm thick G.I
Zinc Coated and Chromate
Passivated "C" purlin fixed
to wall or cleats at not
Met - exceeding 900mm centres
lm 3,884.00 3,877.00 3,880.00 3,881.00 3,886.00
004 and joints should be bolted
with 2 Nos 12mm dia bolts
and nuts other side welding
with cleats minimum length
450mm (AZ-200 roofing).
As per manufacturer's
specification.
Supplying and fixing 50mm
x 50mm x 6mm thick Angle
iron purlin fixed to wall with
necessary steel anchoring
and concrete or cleats at not
exceeding 900mm centres
and joints should be bolted
Met -
with 2 Nos 12mm dia bolts lm 1,600.00 1,584.00 1,585.00 1,589.00 1,602.00
005
and nuts other side welding
with cleats minimum length
225mm in next reduced
angle iron including two
coats of Anticorrosive paint
and 2 coats of enamel paint
as directed.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 54
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying and fixing 63mm
x 63mm x 6mm thick Angle
iron purlin fixed to wall with
necessary steel anchoring
and concrete or cleats at not
exceeding 900mm centers
and joints should be bolted
Met -
006
with 2 Nos 12mm dia bolts lm 1,973.00 1,953.00 1,955.00 1,960.00 1,974.00
and nuts other side welding
with cleats minimum length
225mm in next reduced
angle iron including two
coats of Anticorrosive paint
and 2 coats of enamel paint
as directed.
End Truss - 2/50mm x
50mm x 6mm including
1:2:4(20mm) concreting 2
Met -
007
Nos 12mm dia 225mm long lm 4,118.00 4,054.00 4,078.00 4,056.00 4,108.00
welded to end truss with 2
coats of anticorrosive paint
and 2 coats of enamel paint.
End Truss - 2/63mm x
63mm x 6mm including
1:2:4(20mm) concreting 2
Met -
008
Nos 12mm dia 225mm long lm 4,706.00 4,643.00 4,666.00 4,644.00 4,697.00
welded to end truss with 2
coats of anticorrosive paint
and 2 coats of enamel paint.
25mm x 6mm, Flat iron 1' -
0" long weld to end purlin as
bracket to fix valance board
Met -
with two coats of No 146.00 143.00 144.00 143.00 145.00
009
anticorrosive paint and 2
coats of enamel paint and
bolt & nut.
50mm x 6mm, Flat iron 1' -
0" long weld to end purlin as
bracket to fix valance board
Met -
with two coats of No 251.00 248.00 249.00 248.00 250.00
010
anticorrosive paint and 2
coats of enamel paint and
bolt & nut.
M.S Bar 5/8" dia (16mm)
supplied & fixed in window
Met -
frame at 4" crs. & Painted lm 618.00 611.00 613.00 611.00 622.00
011
with 1 coat red lead & 2
coats of enamel paint.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 55
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Iron grill supplied & fixed
to safety of window with
16mm x 5.5mm flat iron
& 12mm x 5.5mm flat
Met - iron uprights welded at
m2 10,362.00 10,244.00 10,272.00 10,310.00 10,440.00
012 75mm c/c & horizontally
welded at 150mm c/c.
Rates including for 2 coats
coat of anticorrosive paint
& 2 coats of enamel paint.
B.R.C Weld mesh gauge
10, fixed to existing
Met -
frames with staples (fillets m2 2,195.00 2,150.00 2,161.00 2,150.00 2,223.00
013
and beading paid for
separately).
B.R.C Weld mesh gauge
10 supplied & fixed to
window frames with 2"x
½" Spl upper class timber
beading & painting weld
mesh with 1coat
Met - anticorrosive paint & 2
m2 6,838.00 6,802.00 6,860.00 6,629.00 6,957.00
014 coats enamel paint &
beading with primer,
undercoat & 2 coats of
enamel paint to approved
tint, Rate to include for
making openings for
bolts, casement stays etc.
B.R.C ½'' x ½'' Chicken
mesh supplied & fixed to
window frames with 2"x
½" Spl upper class timber
beading & painting mesh
with 1 anticorrosive paint
Met -
& 2 coats enamel paint & m2 6,722.00 6,685.00 6,743.00 6,513.00 6,840.00
015
beading with primer,
undercoat & 2 coats oil
paint to approved tint,
Rate to include for making
openings for bolts,
casement stays etc.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 56
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Mild steel roof truss 9.00m
span centre to centre for Zn-
Al roof and eaves extended
both side upto 1050mm,
Consisting of 2Nos.
63mmx63mmx6mm thick
angles as top and bottom
chords, 2Nos.
50mmx50mmx6mm thick
angles as struts, 1No.
50mmx50mmx6mm thick
angles as ties, 10mm thick
Met - gusset plates, base plates &
no 204,051.00 201,506.00 202,026.00 201,976.00 204,176.00
016 sole plates, mild steel rag
bolt, cleats not less than the
size of purlin etc. & all
details as per the drawing
(Project no S1363/J Sheet
No 01/06). Rate include for
fabricating and application
of two coats of and
anticorrosive paint and two
coats of enamel paint as
directed (matt finish),
transporting, hoisting and
fixing in position.
Mild steel roof truss 7.50m
span centre to centre for Zn-
Al sheet and eaves extended
both side upto 1050mm,
Consisting of 2Nos.
50mmx50mmx6mm thick
angles as top and bottom
chords, 1No.
50mmx50mmx6mm thick
angles as struts & ties,
10mm thick gusset plates,
base plates & sole plates,
Met -
mild steel rag bolt, cleats not no 127,920.00 126,205.00 126,725.00 126,347.00 127,870.00
017
less than the size of purlin
etc. & all details as per the
drawing (Project no
S1363/J Sheet No 02/06).
Rate include for fabricating
and application of two coats
of and anticorrosive paint
and two coats of enamel
paint as directed (matt
finish), transporting,
hoisting and fixing in
position.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 57
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Mild steel roof truss 7.50m
span centre to centre for
calicut tile roof, Consisting
of 2Nos.
50mmx50mmx6mm thick
angles as top and bottom
chords, 1No.
50mmx50mmx6mm thick
angles as struts & ties,
10mm thick gusset plates,
base plates & sole plates,
Met - mild steel rag bolt, cleats not
no 126,952.00 126,191.00 126,776.00 125,685.00 126,949.00
018 lessthan the size of purlin
etc. & all details as per the
drawing (Project no
S1363/J Sheet No 03/06).
Rate include for fabricating
and application of two coats
of and anticorrosive paint
and two coats of enamel
paint as directed (matt
finish), transporting,
hoisting and fixing in
position.
Supplying & fixing safety
grill for window area in
position with dowels with
1/31mm x 31mm x 5.5mm
angle iron frame work for
horizontal & vertical &
2/31mm x 31mm x 5.5mm
double angle iron uprights
Met - welded at 900mm c/c &
m2 18,056.00 18,259.00 18,291.00 18,366.00 18,842.00
019 6mm dia. MS rod welded
diagonally shape at 75mm
c/c to fill internal space of
frame. Rates including for
single coat of anticorrosive
paint & 2 coats of enamel
paint. All complete as per
detail drawing (Project no
S1363/J Sheet No 06/06).
5.16. Plasterer
¾" thick DPC in cement
Pla - sand 1:2 finished with 2
m2 1,813.00 1,730.00 1,763.00 1,711.00 1,802.00
001 coats hot tar and blinded
with sand.
5/8" thick plastering to wall
Pla - in lime and sand 2:5
m2 1,611.00 1,547.00 1,565.00 1,549.00 1,614.00
002 including floating with lime
putty.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 58
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
5/8" thick plastering to wall
Pla - in cement and sand 1:3
m2 1,074.00 1,019.00 1,036.00 1,019.00 1,077.00
003 including neat cement
floating.
3/8" thick plastering to soffit
Pla - of slab in cement and sand
m2 1,755.00 1,696.00 1,736.00 1,669.00 1,771.00
004 1:3 including floating with
lime putty.
3/8" thick plastering to soffit
Pla -
of slab in cement and sand m2 1,669.00 1,610.00 1,650.00 1,583.00 1,685.00
005
1:3 finished smooth.
3/8" thick plastering to side
and soffit of beams in
Pla -
cement and sand 1:3 m2 1,481.00 1,427.00 1,462.00 1,405.00 1,489.00
006
including floating with lime
putty.
3/8" thick plastering to side
Pla - and soffit of beams in
m2 1,395.00 1,341.00 1,376.00 1,319.00 1,403.00
007 cement and sand 1:3 finished
smooth .
5/8" thick plastering to wall
Pla - in lime, cement and sand
m2 1,140.00 1,081.00 1,098.00 1,083.00 1,137.00
008 1:1:5 finished semi rough
with wooden float.
5/8" thick plastering to wall
Pla - in lime, cement and sand
m2 1,463.00 1,402.00 1,425.00 1,396.00 1,464.00
009 1:1:5 finished smooth with
lime putty floating.
5/8" thick plastering to wall
Pla -
in cement and sand 1:4 m2 963.00 908.00 923.00 909.00 963.00
010
finished smooth.
5/8" thick plastering to wall
Pla -
in cement and sand 1:3 to m2 1,019.00 965.00 980.00 965.00 1,019.00
011
internal and external wall.
½" thick rendering in cement
Pla - and sand 1:3 finished
m2 1,048.00 997.00 1,010.00 997.00 1,059.00
012 smooth with neat cement
floating.
½" thick rendering in cement
Pla - and sand 1:2 in floors
m2 1,153.00 1,102.00 1,115.00 1,102.00 1,164.00
013 finished smooth with neat
cement floating.
½" thick rendering in cement
and sand 1:2 in coloured
Pla -
cement floors finished m2 1,379.00 1,328.00 1,341.00 1,328.00 1,390.00
014
smooth with coloured
cement floating.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 59
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
¾" thick rendering in cement
Pla - and sand 1:3 in floors
m2 1,435.00 1,359.00 1,377.00 1,363.00 1,445.00
015 finished smooth with neat
cement floating.
¾" thick rendering in cement
Pla - and sand 1:2 in floors
m2 1,524.00 1,448.00 1,466.00 1,452.00 1,533.00
016 finished smooth with neat
cement floating.
¾" thick rendering in cement
and sand 1:2 in coloured
Pla -
cement floors finished m2 1,750.00 1,674.00 1,692.00 1,678.00 1,759.00
017
smooth with coloured
cement floating.
½" x 6" skirting in cement &
sand 1:3 projected or flush to
Pla -
walls finished smooth with lm 686.00 670.00 683.00 660.00 700.00
018
coloured cement floating
including forming groove.
½" x 4" skirting in cement &
sand 1:3 projected or flush to
Pla -
019
walls finished smooth with lm 394.00 386.00 395.00 379.00 401.00
coloured cement floating
including forming groove.
½" x 4" skirting in cement &
sand 1:3 projected or flush to
Pla -
020
walls finished smooth with lm 371.00 363.00 371.00 356.00 377.00
neat cement floating
including forming groove.
Plaster bands laid over tiles
Pla - 4'' to 6'' wide on roof in
lm 356.00 340.00 344.00 340.00 359.00
021 cement, sand and lime
mortar 1:1:4.
Reveal plastering wide in
Pla -
1:3, 5/8" thick not lm 268.00 258.00 263.00 256.00 272.00
022
exceeding 6" wide.
Cover moulding 2 ½" x 2 ½"
Pla -
in cement mortar 1:2 built in lm 497.00 483.00 492.00 477.00 507.00
023
existing wall.
¾" thick rendering in cement
Pla -
and sand 1:2 with pudlo m2 1,552.00 1,488.00 1,509.00 1,544.00 1,575.00
024
cement.
5.17.Water Proofing
Supplying and laying 1000
Wat -
gauge polythene on m2 143.00 140.00 140.00 140.00 146.00
001
compacted earth area.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 60
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying and applying 2
coats of Masterseal 540
water proofing system
strictly according to
manufacturer's
specifications. Reinforced
all vertical / horizontal
Wat - intersections with Glasscoat
m2 5,257.00 5,122.00 5,149.00 5,133.00 5,289.00
002 60 in a strip 200mm wide,
cure the application for 2day
and check for water
tightness. Rate including
cement and sand rendering /
plastering 1:3 in two times
for brick/ cement sand block
wall.
Prepare the concrete surface
and applying 2 coats of
Masterseal 540 water
proofing membrane
according to the
manufacturers’
specifications. Reinforced
Wat - all vertical / horizontal
m2 4,709.00 4,628.00 4,652.00 4,628.00 4,733.00
003 intersections with Glascoat
60 in a strip 200 mm wide ,
cure the application for 2
days and check for water
tightness. Rate to include for
12 mm thick cement sand
rendering 1:2 for toilet floor
and sunshade.
5.18.Painter And Decorator
The paint shall be approved by the engineer before the commencement of work. the paint shall comply
with the cida specification for building works (sca/4/i) and shall be the superior quality of relevant
manufacturer
Prepare and apply of
preservative (oil type) to
Pai -
structural timber including m2 670.00 648.00 648.00 657.00 675.00
001
touching up cut ends etc.
after fixing.
Prepare surface of steel truss
Pai -
and apply two coats of m2 1,230.00 1,181.00 1,181.00 1,197.00 1,246.00
002
anticorrosive primer.
Apply one coat of
anticorrosive primer and two
Pai -
coats of enamel paint on m2 1,532.00 1,467.00 1,467.00 1,494.00 1,543.00
003
already shop primed and
erected steel roof truss.
Prepare and apply two coats
Pai - of primer and finishing coat
m2 1,411.00 1,373.00 1,373.00 1,384.00 1,427.00
004 of enamel paint to mild steel
[Angle / flat] gate.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 61
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Painting steel on new work
Pai -
with 2 coats of anticorrosive m2 473.00 449.00 449.00 461.00 473.00
005
paint.
Painting steel work, 1 coat,
with anticorrosive paint
Pai -
including removing scares m2 311.00 297.00 297.00 304.00 311.00
006
and wire brushing. (Old
work)
Painting new timber work
Pai -
with 2 coats of wood m2 405.00 394.00 394.00 400.00 405.00
007
preservative.
Preparing and painting wood
Pai -
work with primer and 2 coats m2 1,052.00 1,012.00 1,038.00 1,155.00 1,057.00
008
of enamel paint.
Painting new wood work
Pai -
with approved wood primer m2 323.00 310.00 334.00 442.00 323.00
009
1 coat.
Painting, enamel paint
including washing cleaning
Pai -
& smoothing down with m2 357.00 343.00 343.00 350.00 357.00
010
sandpaper, 1 coat. ( Old
work)
Painting, enamel paint
including washing cleaning
Pai -
& smoothing down with m2 667.00 643.00 643.00 655.00 667.00
011
sandpaper, 2 coats. ( Old
work)
White or colour washing
two coats of in single
Pai -
storeyed buildings, m2 112.00 109.00 112.00 96.00 68.00
012
including patching and
preparing surface.
Painting walls with internal
Pai -
primer to internal walls. m2 229.00 221.00 224.00 223.00 227.00
013
(one coat)
Painting walls with external
Pai -
primer to external walls. m2 255.00 247.00 250.00 249.00 253.00
014
(one coat)
Prepare and apply one coat
Pai - of internal primer and two
m2 732.00 702.00 707.00 715.00 729.00
015 coats of emulsion paint to
walls.
Prepare and apply one coat
Pai - of internal primer and two
m2 809.00 777.00 779.00 790.00 806.00
016 coats of emulsion paint to
soffit of slab.
Painting walls with emulsion
Pai - paint, 2coats including
m2 453.00 437.00 439.00 443.00 451.00
017 preparing surface of old
work.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 62
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Painting walls with emulsion
Pai - paint, 1coat including
m2 240.00 232.00 234.00 234.00 238.00
018 preparing surface of old
work.
Prepare and apply one coat
of external primer and two
Pai -
coats of whether shield m2 799.00 773.00 778.00 784.00 796.00
019
emulsion paint to external
walls.
Painting walls with weather
Pai - shield emulsion paint, 2coats
m2 537.00 521.00 523.00 527.00 535.00
020 including preparing surface
of old work.
Painting walls with weather
Pai - shield emulsion paint, 1coat
m2 286.00 277.00 279.00 279.00 284.00
021 including preparing surface
of old work.
Cement washing to walls of
Pai -
single storeyed buildings m2 137.00 130.00 131.00 132.00 138.00
022
2coats
Varnishing 2 coats with
Pai -
copal varnish after sand m2 514.00 498.00 498.00 503.00 520.00
023
papering .
Pai - Preparing and applying floor
m2 401.00 389.00 389.00 395.00 401.00
024 polish.
Painting, epoxy floor paint
Pai -
including washing cleaning m2 383.00 371.00 371.00 377.00 383.00
025
& smoothing down 1 coat.
Painting, epoxy floor paint
Pai -
including washing cleaning m2 747.00 723.00 723.00 735.00 747.00
026
& smoothing down 2 coats.
Ceiling painting, 2 coats of
Pai -
emulsion painting for m2 630.00 607.00 610.00 612.00 635.00
027
ceiling.
Ceiling painting, 1 coat of
Pai -
emulsion painting for m2 351.00 339.00 342.00 340.00 353.00
028
ceiling.
Prepare and apply 2 coats of
Pai - skim putty for internal walls
m2 409.00 391.00 393.00 398.00 414.00
029 including finished smooth as
directed.
Pai - Painting walls with internal
m2 184.00 176.00 178.00 177.00 181.00
030 wall filler to internal walls.
Pai - Painting walls with external
m2 205.000 197.00 200.00 198.00 202.00
031 wall filler to external walls.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 63
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Prepare and apply 2 coats of
Pai -
wall putty including finished m2 544.00 525.00 527.00 533.00 540.00
032
smooth as directed.
Prepare and apply one coat
Pai - of internal wall filler and two
m2 686.00 657.00 662.00 670.00 683.00
033 coats of emulsion paint to
walls.
Prepare and apply one coat
Pai - of internal wall filler and two
m2 763.00 731.00 734.00 745.00 761.00
034 coats of emulsion paint to
soffit of slab.
Prepare and apply one coat
of external wall filler and
Pai -
two coats of whether shield m2 749.00 722.00 724.00 734.00 746.00
035
emulsion paint to external
walls.
5.19.Plumbing And Drainage Work
Wash Basin with pedestal
575mm x 450mm size,
chromium plated pillar tap,
1
waste plug and " angle
2
Plu - valve supplied & fixed
complete.( Prime cost not No 34,102.00 33,852.00 33,877.00 33,902.00 34,215.00
001
less than for Wash basin
with pedestal 21,566.00 /= &
Chromium plated pillar tap
6,500.00 /= Excluding vat ).
Angle valve paid separately.
Wash Basin with pedestal
575mm x 450mm size,
chromium plated pillar tap,
1
waste plug and 2 " angle
valve supplied & fixed
Plu - complete.(Prime cost not No
002
34,190.00 33,940.00 33,965.00 33,990.00 34,303.00
less than for Wash basin
with pedestal 21,652.00 /= &
Chromium plated pillar tap
2" 6,500.00 /= Excluding
vat). Angle valve paid
separately.
Closet, pedestal approved
type with low level glazed,
earthenware flushing cistern,
flush pipe, double plastic
seat cover, ½'' angle valve,
Plu - trap etc. Supplied & fixed
003 complete. (Prime cost not
No 48,983.00 48,683.00 48,708.00 48,758.00 49,096.00
less than for Low level
closet, tank & seat cover
40,871.00 /= Excluding
vat). Angle valve paid
separately.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 64
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Closet, pedestal approved
type with low level glazed,
earthenware flushing cistern,
flush pipe, double plastic
seat cover, ½'' angle valve,
Plu - trap etc. Supplied & fixed
No 56,966.00 56,666.00 56,691.00 56,741.00 57,078.00
004 complete. (Prime cost not
less than for Low level
closet, tank & seat cover
48,697.00 /= Excluding
vat). Angle valve paid
separately.
Sink, glazed, earthenware
24''x 15"x 7" supplied
approved quality and fixed
with waste plug complete
Plu - with ½'' angle valve . (Prime
005 cost not less than for
No 33,752.00 33,602.00 33,602.00 33,652.00 33,802.00
ceramic lab sink with waste
plug and chain 30,345.00 /=
Excluding vat). Angle valve
paid separately
Closet squatting type, large
with trap supplied & fixed.
Plu - (Prime cost not less than for
No 15,828.00 15,528.00 15,528.00 15,628.00 15,928.00
006 Squatting pan [large] with
foot rest & trap 9,217.00 /=
Excluding vat)
Vitreous bidet suite fixed
complete to working order.
Plu -
007
(Prime cost of Bidet not less No 25,490.00 25,190.00 25,190.00 25,290.00 25,590.00
than 19,500.00 /= Excluding
vat)
1 No. Bowl type Urinal with
flush valve & bottle trap
complete to working orders.
Plu -
(Prime cost not less than for No 54,375.00 54,077.00 54,105.00 54,129.00 54,483.00
008
Urinal bowls 34,522.00 /=
Flush valve 10,870.00 /=
Excluding vat)
Bowl type urinal with trap.
Plu - (Prime cost of Urinal bowl
009 not less than 34,522.00 /=
No 37,552.00 37,515.00 37,515.00 37,527.00 37,565.00
Excluding vat)
Supplied and fixed Ceramic
urinal separator (Prime cost
Plu -
of urinal separator not less No 26,322.00 26,288.00 26,293.00 26,265.00 26,329.00
010
than 25,400.00 /= per No
Excluding vat)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 65
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplied and fixed single
board stainless steel kitchen
sink with chromium plated
swan neck tap and bottle
trap, ½'' angle valve. (Prime
Plu -
cost not less than for No 19,780.00 19,625.00 19,625.00 19,675.00 19,825.00
011
Stainless steel kitchen sink
20,957.00 /= & Chromium
plated swan neck tap
6,750.00 /= Excluding vat).
Angle valve paid separately
Flushing cistern, low level,
Plu -
plastic supplied and fixed No 10,756.00 10,606.00 10,606.00 10,656.00 10,806.00
012
complete.
Flushing cistern, high level,
Plu -
plastic supplied and fixed No 13,510.00 13,360.00 13,360.00 13,410.00 13,560.00
013
complete.
Supplying and fixing
Disable person toilet fittings
imported. All complete as
directed. (Prime cost not
less than for Disable person
closet, cistern & seat cover
190,678.00/=, wash basin
58,898.00 / =, Elbow action
basin tap 13,983.00/=,
Plu -
½''dia Bidet shower No 353,566.00 352,254.00 352,658.00 352,605.00 353,559.00
014
1,950.00 /=, Stainless steel
powder coated grab rail
23,305.00 /=, Stainless steel
powder coated ''L'' shape rail
23,305.00 /=, Stainless steel
powder coated straight rail
6,992.00 /=, paper holder
7,585.00 /= & 1¼'' dia Waste
1,450.00 /= Excluding vat)
Mirror, bathroom type,
supplied & fixed to wall with
Plu - rawl plugs. ( Prime cost of
015 Mirror with fittings - Flat
No 4,280.00 4,268.00 4,268.00 4,274.00 6,320.00
model not less than 4,000.00
/= Excluding vat)
Towel rail 600mm long ¾"
dia chromium plated. (Prime
Plu - cost of 600mm Long
No 12,552.00 12,527.00 12,527.00 12,540.00 12,552.00
016 Chromium plated towel rail
not less than 11,914.00 /=
Excluding vat)
Soap tray, plastic, supplied
Plu -
017
& fixed to wall with rawl No 910.00 732.00 732.00 1,000.00 910.00
plugs.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 66
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Tooth brush holder,
Plu - chromium plated supplied &
018 fixed to wall with rawl
No 6,112.00 6,087.00 6,087.00 6,100.00 6,112.00
plugs.
Supply and fixing 3'' size
adjustable Shower rose,
Plu - chromium plated (Prime cost
No 2,215.00 2,206.00 2,206.00 2,209.00 2,218.00
019 of Chromium plated jet
shower rose not less than
2,000.00 /= Excluding vat)
Supply and fixing 8'' square
head adjustable rain shower,
Plu - chromium plated (Prime cost
020 of Chromium plated rain
No 12,150.00 12,140.00 12,140.00 12,144.00 12,153.00
shower not less than
11,740.00/= Excluding vat)
Supplied and fixed plastic
Bidet Shower. (Prime cost of
Plu -
021
plastic bidet shower not less No 2,113.00 1,849.00 1,900.00 2,005.00 2,218.00
than 1,900.00/= Excluding
vat)
Plu - Brass Bib Tap ½'' [ English
022 ] Pegler
No 3,701.00 3,689.00 3,689.00 3,693.00 3,706.00
Plu - Brass Bib Tap ¾" [ English
023 ] Pegler
No 4,211.00 4,199.00 4,199.00 4,203.00 4,216.00
Chromium plated [plumber]
tap ¾" supplied & fixed.
Plu - (Prime cost of ¾" dia
No 4,743.00 4,730.00 4,730.00 4,734.00 4,747.00
024 Chromium plated bib tap not
less than 4,421.00 /=
Excluding vat)
Plu - Plastic tap ¾" supplied &
025 fixed.
No 1,151.00 1,139.00 1,139.00 1,143.00 1,156.00
Plu - Ball Cocks, plastic ½’’
026 supplied & fixed.
No 823.00 805.00 805.00 811.00 830.00
Plu - Ball Cocks, plastic ¾”
No 1,117.00 1,098.00 1,098.00 1,258.00 1,072.00
027 supplied & fixed.
Plu - Ball Cocks, plastic 1”
No 1,301.00 1,282.00 1,282.00 1,288.00 1,286.00
028 supplied & fixed.
Plu - Ball Cocks, plastic 1 ¼”
No 1,827.00 1,808.00 1,808.00 1,814.00 1,833.00
029 supplied & fixed.
Plu - Ball Cocks, plastic 1 ½’’
030 supplied & fixed.
No 2,115.00 2,116.00 2,116.00 2,123.00 2,141.00
Plu - Ball Cocks, plastic 2’’
031 supplied & fixed.
No 3,020.00 3,002.00 3,002.00 3,008.00 3,027.00
Brass Gate Valve 1 ¼"
supplied and fixed [English
Plu - type]. ( Prime cost of 1¼"dia
032 Brass gate valve not less
No 10,992.00 10,969.00 10,969.00 10,977.00 11,000.00
than 10,000.00/= Excluding
vat)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 67
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Brass Gate Valve 2"
supplied and fixed [English
Plu - type]. ( Prime cost of 2" dia
033 Brass gate valve not less
No 17,898.00 17,874.00 17,874.00 17,882.00 17,906.00
than 16,500.00/= Excluding
vat)
Pipes pvc ½'' dia. supplied &
Plu -
fixed.(20mm dia) Type lm 232.00 229.00 229.00 230.00 232.00
034
PNT14
Pipes pvc ¾'' dia. supplied &
Plu -
035
fixed. (25mm dia) Type lm 413.00 411.00 411.00 412.00 414.00
PNT11
Pipes pvc 1'' dia. supplied &
Plu -
fixed. (32mm dia) Type lm 563.00 559.00 559.00 560.00 564.00
036
PNT11
Pipes pvc 1¼'' dia. supplied
Plu - & fixed Type PNT11 with
lm 1,050.00 1,038.00 1,038.00 1,039.00 1,059.00
037 excavation & back filling.
[40mm]
Pipes pvc 1¼'' dia. supplied
Plu - & fixed PNT9 with
lm 902.00 890.00 890.00 891.00 911.00
038 excavation & back filling.
[40mm]
Pipes pvc 1¼'' dia. supplied
Plu -
039
& fixed Type PNT11 lm 873.00 868.00 868.00 869.00 874.00
without excavation. [40mm]
Pipes pvc 1¼'' dia. supplied
Plu -
040
& fixed Type PNT9 without lm 725.00 720.00 720.00 722.00 727.00
excavation. [40mm]
Pipes pvc 1½'' dia. supplied
Plu - & fixed Type PNT11 with
041 excavation & back filling.
lm 1,485.00 1,472.00 1,472.00 1,474.00 1,494.00
[50mm]
Pipes pvc 1½'' dia. supplied
Plu - & fixed Type PNT9 with
042 excavation & back filling.
lm 1,261.00 1,249.00 1,249.00 1,250.00 1,270.00
[50mm]
Pipes pvc 1½'' dia. supplied
Plu -
043
& fixed Type PNT11 lm 1,308.00 1,303.00 1,303.00 1,304.00 1,309.00
without excavation. [50mm]
Pipes pvc 1½'' dia. supplied
Plu -
044
& fixed Type PNT9 without lm 1,084.00 1,079.00 1,079.00 1,081.00 1,085.00
excavation. [50mm]
Pipes pvc 2'' dia. supplied &
Plu - fixed Type PNT11 with
045 excavation & back filling.
lm 2,196.00 2,182.00 2,182.00 2,184.00 2,205.00
[63mm]
Office of the Deputy Chief Secretary - Engineering Services, NP Page 68
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Pipes pvc 2'' dia. supplied &
Plu - fixed Type PNT9 with
046 excavation & back filling.
lm 1,820.00 1,806.00 1,806.00 1,808.00 1,829.00
[63mm]
Pipes pvc 2'' dia. supplied &
Plu -
fixed Type PNT11 without lm 2,019.00 2,012.00 2,012.00 2,014.00 2,021.00
047
excavation. [63mm]
Pipes pvc 2'' dia. supplied &
Plu -
048
fixed Type PNT9 without lm 1,643.00 1,637.00 1,637.00 1,639.00 1,645.00
excavation. [63mm]
Supply and fix approved
manufactures fibre glass
PE+or equivalent 500 liter
Plu - water tank approved type by
049 Engineer [double layer].
No 8,510.00 8,448.00 8,448.00 8,460.00 8,548.00
(Prime cost of 500 lit water
tank not less than 7,000.00
/= Excluding vat)
Supply and fix approved
manufactures fibre glass
PE+ or equivalent 1000 liter
Plu - water tank approved type by
No 16,853.00 16,791.00 16,791.00 16,803.00 16,891.00
050 Engineer (double layer).
(Prime cost of 1000 lit water
tank not less than 15,100.00
/= Excluding vat)
Supply and fix approved
manufactures fibre glass
PE+ or equivalent 2000 liter
Plu - water tank approved type by
051 Engineer (double layer).
No 33,333.00 33,271.00 33,271.00 33,283.00 33,371.00
(Prime cost of 2000 lit water
tank not less than 31,100.00
/= Excluding vat)
Supply and fix approved
manufactures fibre glass
PE+or equivalent 550 liter
Plu - water tank approved type by
052 Engineer [Triple layer].
No 10,931.00 10,868.00 10,868.00 10,881.00 10,968.00
(Prime cost of 550 lit water
tank not less than 9,350.00
/= Excluding vat)
Supply and fix approved
manufactures fibre glass
PE+ or equivalent 1000 liter
Plu - water tank approved type by
053 Engineer (Triple layer).
No 20,973.00 20,911.00 20,911.00 20,923.00 21,011.00
(Prime cost of 1000 lit water
tank not less than 19,100.00
/= Excluding vat)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 69
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supply and fix approved
manufactures fibre glass
PE+ or equivalent 2000 liter
Plu - water tank approved type by
054 Engineer (Triple layer).
No 40,687.00 40,625.00 40,625.00 40,637.00 40,725.00
(Prime cost of 2000 lit water
tank not less than 38,240.00
/= Excluding vat)
Eaves gutters 4" square type
Plu -
pvc fixed with aluminium lm 1,392.00 1,376.00 1,395.00 1,374.00 1,399.00
055
brackets.
Down pipe 3½" (88mm) Pvc
Plu -
fixed with wooden plugs to lm 1,206.00 1,191.00 1,204.00 1,184.00 1,210.00
056
wall etc.
Drains, pvc type PNT7 4"
laid on cement concrete 6"
Plu - thick up to 2'-0" depth of
057 invert including excavation
lm 4,533.00 4,359.00 4,354.00 4,354.00 4,408.00
& cement concrete hunching
(1:3:6 - 1" metal).
Plu - Drains, pvc type PNT9 4"
lm 2,643.00 2,638.00 2,638.00 2,639.00 2,644.00
058 supplied and fixed
Plu - Drains, pvc type PNT7 4"
lm 2,197.00 2,192.00 2,192.00 2,193.00 2,198.00
059 supplied and fixed
Plu - Gulley pvc 6" supplied &
No 4,688.00 4,469.00 4,487.00 4,449.00 4,503.00
060 fixed including gulley box.
Plu - Wire Dome 2" Supplied &
061 fixed
No 650.00 644.00 644.00 647.00 650.00
Manhole 2' x 2' & up to 2'-0"
deep, 5" thick block in
cement sand 1:3 walls &
Plu - cement rendered ½" (1:2)
062 with 6" cement
No 20,607.00 19,146.00 19,303.00 19,167.00 19,984.00
conc.foundation 1:3:6 (1"
metal) including forming
channels but without cover.
Manhole 3'- 6'' x 2'- 3'' & 2'-
0" to 4'-00'' deep, 5" thick
block in cement sand 1:3
Plu - walls & cement rendered ½"
063 (1:2) with 6" cement
No 35,307.00 32,704.00 32,963.00 32,756.00 34,121.00
conc.foundation 1:3:6 (1"
metal) including forming
channels but without cover.
Manhole cover reinforced
concrete 3" thick 2'- 00''x 2'-
Plu - 00" approx. supplied & fixed
m2 7,320.00 7,085.00 7,145.00 7,034.00 7,239.00
064 reinforced with 1/4" dia
M.S.rods at 3" centres both
ways.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 70
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Chamber 9" x 9" & up to 9"
deep, 3" thick 1:3:6 (1")
Plu - cement conc walls & cement
065 rendered ½" (1:2) with 3"
No 4,833.00 4,497.00 4,528.00 4,467.00 4,542.00
cement conc. foundation in
1:3:6 (1") with cover.
Chamber 1'- 00'' x 1'- 00'' &
up to 1'- 00'' deep, 3" thick
1:3:6 (1") cement conc walls
Plu -
& cement rendered ½" (1:2) No 5,133.00 4,684.00 4,723.00 4,642.00 4,725.00
066
with 3" cement conc.
foundation in 1:3:6 (1") with
cover.
Plu - Angle valve, chromium
067 plated ½’’ supplied & fixed.
No 2,506.00 2,488.00 2,488.00 2,494.00 2,513.00
5.20.Electrical Installation
MCCB 40 Amp 4 pole, with
metal enclosure , etc. (Prime
Ele -
001
cost of MCCB 40 Amp 4 No 30,750.00 30,450.00 30,450.00 30,550.00 30,850.00
pole [Orange, Schnieder or
equivalent] 18,700.00 /= )
MCCB 60 Amp 4 pole, with
metal enclosure , etc. ( Prime
Ele -
cost of MCCB 60 Amp 4 No 35,450.00 35,150.00 35,150.00 35,250.00 35,550.00
002
pole [Orange, Schnieder or
equivalent] 23,400.00 /= ).
Earth electrode copper rod,
12mm dia, 1500mm long,
Ele -
etc. ( Prime cost of Earth No 5,500.00 5,388.00 5,388.00 5,425.00 5,538.00
003
copper rod 12mm dia,
1500mm long 3,400.00 /=)
Exhaust fan ( 8 inch ) with
13A Socket outlet [Standard
Ele -
or equivalent, Wall mounted No 21,859.00 21,672.00 21,672.00 21,734.00 21,922.00
004
type ventilating fan prime
cost 8,800.00 /=)
13 Amp switched socket
outlet with neon indicator
with 2.5mm2 wire, 2.5mm2
Ele - earth wire, sunk box, screws,
No 11,559.00 11,447.00 11,447.00 11,484.00 11,597.00
005 conduit etc. ( Prime cost of
13 Amp plug with switch
[Keviltonl, Orange, ACL, or
equivalent] 1,130.00/= )
Wall mounted fan (16
Ele - inch)with 13 Amp Socket
006 outlet (Bajaj or equivalent)
No 24,459.00 24,310.00 24,310.00 24,359.00 24,510.00
12,000.00/= )
Light point with 1.0mm2
wiring, flexible wire, round
Ele -
plug, ceiling rose, switch, No 4,062.00 3,987.00 3,987.00 4,012.00 4,087.00
007
sunk box, holder, conduit,
screws, clips, pins, etc.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 71
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
20W LED lamp or angle
battern lamp with 1.0mm2
wiring, flexible wire, round
plug, ceiling rose, switch,
sunk box, holder, 20 W LED
Ele -
008
light with one year warranty, No 6,262.00 6,150.00 6,150.00 6,187.00 6,300.00
conduit, screws, clips, pins,
etc.(Prime cost of 20 W LED
lamp or angle battern lamp
[Orange or equivalent]
1,500.00 /=)
Water tight lamp with 12 W
LED set 1.0mm2 wiring,
flexible wire, switch, sunk
box, LED light with one year
Ele -
009
warranty, shade conduit, No 7,403.00 7,291.00 7,291.00 7,328.00 7,441.00
screws, clips, pins, etc.
(Prime cost of 12W Water
tight LED lamp set [Orange
or equivalent] 3,450.00 /=)
1200 x 600mm size,
reflector model 2 x 36 W
fluorescent lamp with
1.0mm2 wiring, flexible
wire, switch, sunk box,
Ele - holder, conduit, screws,
010 clips, pins, etc. ( Prime cost
No Not Applicable
of 1200mm x 600mm Size,
reflector model 2 x 36W
fluorescent lamp [Orange,
Kevilton or equivalent] N/A
/=)
600 x 600mm size, reflector
model 3 x 18w fluorescent
lamp with 1.0mm2 wiring,
flexible wire, switch, sunk
box, conduit, screws, clips,
Ele -
pins, etc. (Prime cost of No Not Applicable
011
600mm x 600mm Size,
reflector model 3 x 18W
fluorescent lamp [DLS,
Yamadha or
equivalent]N/A/= )
1200mm fluorescent lamp
set with 1.0mm2 wiring,
flexible wire, round plug,
ceiling rose, switch, sunk
Ele - box, holder, adapter.
No 6,412.00 6,300.00 6,300.00 6,337.00 6,450.00
012 conduit, screws, clips, pins,
etc. ( Prime cost of 1200 mm
Long fluorescent lamp
[Orange, Kevilton or
equivalent ]1,650.00/=)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 72
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
600mm fluorescent lamp set
with 1.0mm2 wiring,
flexible wire, round plug,
ceiling rose, switch, sunk
Ele - box, holder, adapter.
No
013 conduit, screws, clips, pins, 6,062.00 5,950.00 5,950.00 5,987.00 6,100.00
etc. ( Prime cost of 600 mm
Long fluorescent lamp
[Orange, Kevilton or
equivalent ] 1,300.00/= )
Hood lamp set with 12W
LED lamp 1.0mm2 wiring,
switch, sunk box, conduit,
screws, clips, pins, etc.
Ele - (Prime cost of Hood lamp set
No
014 with 12W LED lamp 7,314.00 7,202.00 7,202.00 7,239.00 7,352.00
[Orange, Bright or
equivalent 3,450.00 /=)
(Switch shall be Orange
ACL or equivalent)
Wall bracket with 12W LED
lamp set with 1.0mm2
wiring, switch, sunk box,
Ele - conduit, screws, clips, pins,
No
015 etc. ( Prime cost of Wall 6,864.00 6,752.00 6,752.00 6,789.00 6,902.00
bracket with 12W LED lamp
[Orange, Bright or
equivalent ] 3,000.00/=)
Ceiling fan (KDK, N56 RG
Modal) 1400mm sweep, 225
CMM air delivery, 5 speed
regulator with 1.0mm2
wiring, 2.5mm2 earth wire,
Ele - flexible wire, round plug,
No
016 switch, sunk box, fan hook, 31,912.00 31,762.00 31,762.00 31,812.00 31,962.00
conduit, screws, clips, pins,
1.5mm2 Earth wiring etc.
(Prime cost of Ceiling fan
[KDK, N56 RG Model or
equivalent ] 24,800.00 /= )
Ceiling fan (Bajaj) 1400mm
sweep, 205 CMM air
delivery, 5 speed regulator
with 1.0mm2 wiring,
2.5mm2 earth wire, flexible
Ele -
wire, round plug, switch, No
017 21,012.00 20,862.00 20,862.00 20,912.00 21,062.00
sunk box, fan hook, conduit,
screws, clips, pins, 1.5mm2
Earth wiring etc. (Prime cost
of Ceiling fan [ Bajaj or
equivalent ] 13,900.00 /= )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 73
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
LED light point 1mm2 wire,
Ele -
sunk box, switch, conduit, No 3,154.00 3,079.00 3,079.00 3,104.00 3,179.00
018
etc.
12W LED light fitting with
1mm2 wiring, sunk box,
Ele - switch conduit etc. ( Prime
019 cost of 12W LED bulb
No 6,554.00 6,442.00 6,442.00 6,479.00 6,592.00
[Bright, Kevilton or
equivalent ] 2,700.00 /=)
18W LED light fitting with
1mm2 wiring, sunk box,
Ele - switch conduit etc. (Prime
No 7,554.00 7,442.00 7,442.00 7,479.00 7,592.00
020 cost of 18W LED bulb
[Bright, Kevilton or
equivalent ] 3,000.00 /=)
24W LED light fitting with
1mm2 wiring, sunk box,
Ele - switch conduit etc. (Prime
021 cost of 24W LED bulb
No 6,034.00 5,922.00 5,922.00 5,959.00 6,072.00
[Bright, Kevilton or
equivalent ] 3,700.00 /= )
Calling bell with 1.0mm2
wiring, round plug, bell
bush, sunk box, conduit,
Ele -
screws, clips, pins, etc. No 6,854.00 6,742.00 6,742.00 6,779.00 6,892.00
022
(Prime cost of Calling bell
[Polychrome or equivalent]
1,450.00 /= )
Single phase Distribution
board 10 Way ABC box with
conduit, 6 Amp or 10 Amp
Ele - or 16 Amp or 20 Amp
023 necessary circuit breakers, No 19,148.00 18,923.00 18,923.00 18,998.00 19,223.00
40Amp isolated main switch
& 40Amp trip switch with
indicator bulb etc.
Single phase Distribution
board 12 Way ABC Box
with conduit, 6 Amp or 10
Ele - Amp or 16 Amp or 20 Amp
024 necessary circuit breakers, No 21,350.00 21,125.00 21,125.00 21,200.00 21,425.00
40Amp isolated main switch
& 40Amp trip switch with
indicator bulb etc.
Single phase Distribution
board 16 Way ABC Box
with conduit, 6 Amp or 10
Ele - Amp or 16 Amp or 20 Amp
025 necessary circuit breakers, No 25,070.00 24,845.00 24,845.00 24,920.00 25,145.00
40Amp isolated main switch
& 40Amp trip switch with
indicator bulb etc.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 74
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
RCCB single phase 40 amp,
2P screws etc. ( Prime cost
Ele -
026
of RCCB single phase - 40 No Not Applicable
amp [ Orange, Schnieder or
equivalent ] 5,500.00 /= )
40 Amp isolator main single
phase. (Prime cost of
Ele -
027
Isolator - 40 amp [Orange, No Not Applicable
Schnieder or equivalent]
2,300.00/=)
Service bracket 1500mm
long, 50x50x6mm angle iron
Ele - bend to shape fix to wall or
No
028 timber with bolt & nut, 5,655.00 5,505.00 5,505.00 5,555.00 5,705.00
conduit, making holes,
painting, etc.
Supplying and installing
Ele -
6.0mm2 twin wire with lm
029 1,084.00 1,079.00 1,079.00 1,080.00 1,085.00
conduit etc.
Telephone socket outlet with
two pair wire, multy
connector, sunk box, screws,
Ele -
conduit etc. ( Prime cost of No
030 5,149.00 5,074.00 5,074.00 5,099.00 5,174.00
Telephone socket outlet
[Kryton, 3M or equivalent ]
1,125.00 /=)
TV socket outlet with TV
antena wire, multy
connector, sunk box, screws,
Ele -
conduit etc. (Prime cost of No
031 5,149.00 5,074.00 5,074.00 5,099.00 5,174.00
TV socket outlet [Kryton,
3M or equivalent] 1,125.00
/= )
Supplying and installing
Ele -
6.0mm2 earth wire with lm
032 442.00 437.00 437.00 438.00 443.00
conduit etc.
Supplying and installing
Ele - 10.0mm2 (Cu/PVC/PVC)
033 unarmoured 4 core wire with
lm
4,571.00 4,561.00 4,561.00 4,564.00 4,574.00
conduit etc.
Supplying and installing
Ele - 16.0mm2 (Cu/ PVC/ PVC)
lm
034 4 core unarmoured wire with 6,834.00 6,824.00 6,824.00 6,827.00 6,837.00
conduit etc.
Supplying and installing
Ele -
10.0mm2 earth wire with lm
035 684.00 679.00 679.00 680.00 685.00
conduit etc.
Supplying and installing
Ele -
16.0mm2 earth wire with lm
036 1,018.00 1,013.00 1,013.00 1,014.00 1,019.00
conduit etc.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 75
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying and installing
Ele - 10.0mm2 (Cu/PVC/PVC) 4
037 core unarmoured cable and
lm 5,251.00 5,236.00 5,236.00 5,241.00 5,256.00
10.0mm2 earth wire.
Supplying and installing
Ele - 16.0mm2 (Cu/PVC/PVC) 4
lm 7,848.00 7,833.00 7,833.00 7,838.00 7,853.00
038 core unarmoured cable and
16.0mm2 earth wire.
25mm2 (CU /XLPE /SWA /
PVC) 4 core armoured cable
Ele -
laying with necessary lm 12,362.00 12,065.00 12,091.00 12,140.00 12,274.00
039
accessories and materials to
working order.
35mm2 (CU /XLPE /SWA /
PVC) 4 core armoured cable
Ele -
laying with necessary lm 16,042.00 15,745.00 15,771.00 15,820.00 15,953.00
040
accessories and materials to
working order.
Supplying and fixing
Electric pump with motor
single phase 1.5 Hp with
starter, on cement concrete
bed 2'- 00''x 1'- 6''x 0''- 6'' in
1:2:4 (20mm) mix with 4
Nos 3/8''x 6'' rag bolt and
nuts, rendered cement
Ele - mortar 1:2 including foot
No
041 valve, starter switch. All 154,700.00 154,300.00 154,300.00 154,450.00 154,800.00
completed to working order
with necessary connecting
accessories. ( Prime cost of
Centrifugal electric Water
pump 1.5 Hp [ Jinesena ]
132,000.00 /=, Starter
[Schnieder, Orange or
equivalent] 12,500.00 /= )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 76
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying and fixing
Electric pump with motor
single phase 1.0 Hp with
starter, on cement concrete
bed 2'- 00''x 1'- 6''x 0''- 6'' in
1:2:4 (20mm) mix with 4
Nos 3/8''x 6'' rag bolt and
nuts,rendered cement
mortar 1:2 including foot
Ele -
valve, starter switch. All No
042 87,300.00 87,700.00 87,300.00 87,450.00 87,800.00
completed to working order
with necessary connecting
accessories. ( Prime cost of
Centrifugal electric Water
pump 1.0 Hp [Solex
65,000.00 /= Excluding
vat], Starter [Schnieder,
Orange or equivalent]
12,500.00 /=)
Supplying and fixing
Electric pump with motor
single phase 1.0 Hp with
starter, on cement concrete
bed 2'- 00''x 1'- 6''x 0''- 6'' in
1:2:4 (20mm) mix with 4
Nos 3/8''x 6'' rag bolt and
nuts,rendered cement
mortar 1:2 including foot
Ele -
valve, starter switch. All No 70,300.00 70,700.00 70,300.00 70,450.00 70,800.00
043
completed to working order
with necessary connecting
accessories. ( Prime cost of
Centrifugal Electric Water
pump 1.0 Hp [Singer
48,000.00 /= Excluding vat
], Starter [Schnieder,
Orange or equivalent]
12,500.00 /=)
Ceiling fan (Havells
CREW Modal) 1400mm
sweep, 225 CMM air
delivery, 5 speed regulator
with 1.0mm2 wiring,
Ele -
flexible wire, round plug, No 18,012.00 17,862.00 17,862.00 17,912.00 18,062.00
044
switch, sunk box, fan hook,
conduit, screws, clips, pins,
etc. ( Prime cost of Ceiling
fan [Havells CREW
model] 13,000.00 /= )
Office of the Deputy Chief Secretary - Engineering Services, NP Page 77
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
5.21.Miscellaneous
Fence barbed wire pvc
coated (12 gauge), 4 points,
Mis -
3" aparts, supplied and lm 85.00 78.00 79.00 75.00 76.00
001
fixed in existing concrete
posts with G.I staples.
Fence barbed wire GI, 14
gauge, 4 points, 3" aparts,
Mis -
supplied and fixed in lm 85.00 78.00 79.00 75.00 76.00
002
existing concrete posts with
G.I staples.
Intermediate fence posts ,
cement conc 1 : 1½ : 3 (¾")
reinforced with 4 Nos. 8
mm dia Tor steel wound
round with No 14 BWG
Mis -
wire to form a strriup at 175 post
003 6,623.00 6,455.00 6,523.00 6,439.00 6,639.00
mm C-C, 2100 mm high
square section 100" to 150"
fixed complete as per
project No S1362, sheet No
01/04.
Intermediate fence post,
cement conc 1 : 1½ : 3 (¾")
reinforced with 4 Nos. 10
mm dia. Tor Steel with 5.5
Mis - mm dia strriups at 200 C-C,
post
004 2400 mm high square 9,094.00 8,857.00 8,918.00 8,797.00 8,994.00
section 100 mm to 150mm
fixed complete as per
project No S1362, sheet No
03/04.
End post 2325 mm high,
with 2 Nos struts for Type
Mis - barbed wire fence fixed
post
005 complete in cement 33,638.00 32,214.00 32,409.00 32,085.00 32,515.00
concrete as per project No
S1362, sheet No 02/04.
End post 2400 mm high,
with 2 Nos struts for Type
Mis - barbed wire fence fixed
post
006 complete in cement 36,968.00 36,124.00 36,368.00 35,890.00 36,652.00
concrete as per project No
S1362, sheet No 04/04.
String Bolts 1/2" dia made
Mis -
and fixed 18" long No
007 1,623.00 1,553.00 1,565.00 1,626.00 1,721.00
(Approx).
Office of the Deputy Chief Secretary - Engineering Services, NP Page 78
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Fence barbed wire pvc
coated, 7 strands 12 B.W.G
with 4 points at 75 mm
centres & R.C.C posts 1 : 1½
: 3 (¾") metal reinforced
with 4 Nos. 8 mm dia Tor
Steel with 14 B.W.G
stirrups at 175 mm C-C. post
to be fixed at 8'- 0" C-C.
including excavation,
cement conc foundation
Mis -
1:3:6 (1" ) metal to corner lm 4,792.00 4,612.00 4,653.00 4,580.00 4,698.00
008
posts & structs & string
bolts,all as per type plan
S1362, Sheet No 1/4 & 2/4
structs to be reinforced with
4Nos. 10mm Tor seel &
corner posts with 4 Nos. 12
mm Tor steel. Rate to
include for additional post
and struts for more than
100'-0" and 2 coats of white
washing to all concrete post.
Fence barbed wire GI, 7
strands 12 B.W.G with 4
points at 75 mm centres &
R.C.C posts 1: 1½: 3 (¾")
metal reinforced with 4 Nos.
8 mm dia, with 14 B.W.G
stirrups at 175 mm C-C. Post
to be fixed at 8'- 0" C-C.
Including excavation,
cement conc foundation
Mis - 1:3:6 (1”) metal to corner
009 posts & structs & string
lm 4,792.00 4,612.00 4,653.00 4,580.00 4,698.00
bolts,all as per type plan
S1362, Sheet No 1/4 & 2/4
structs to be reinforced with
4Nos. 10mm Tor seel &
corner posts with 4 Nos. 12
mm Tor Steel. Rate to
include for additional post
and struts for more than
100'-0" and 2 coats of white
washing to all concrete post.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 79
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Fence barbed wire pvc
coated, 10 strands 12 B.W.G
with 4 points at 75 mm
centres & R.C.C posts 1 : 1½
: 3 (¾") metal reinforced
with 4 Nos. 10 mm tor steel
with 5.5 mm stirrups at 200
mm C-C. post to be fixed at
8'- 0" C-C. including
excavation, cement concrete
foundation 1:3:6 (1" ) metal
Mis -
to intermediate posts, corner lm 6,067.00 5,859.00 5,898.00 5,797.00 5,924.00
010
posts & structs & string
bolts,all as per type plan
S1362, Sheet No 3/4 & 4/4
structs to be reinforced with
4Nos. 10mm Tor seel &
corner posts with 4 Nos. 12
mm tor steel. Rate to include
for additional post and struts
for more than 100'-0" and 2
coats of white washing to all
concrete post.
Fence barbed wire GI, 7
strands 14 B.W.G with 4
points at 75 mm centres &
R.C.C posts 1 : 1½ : 3 (¾")
metal reinforced with 4 Nos.
10 mm tor steel with 5.5 mm
stirrups at 200 mm C-C. post
to be fixed at 8'- 0" C-C.
including excavation,
cement conc foundation
1:3:6 (1" ) metal to
Mis -
intermediate posts, corner lm 5,899.00 5,711.00 5,751.00 5,659.00 5,787.00
011
posts & structs & string
bolts,all as per type plan
S1362, Sheet No 3/4 & 4/4
structs to be reinforced with
4Nos. 10mm Tor seel &
corner posts with 4 Nos. 12
mm tor steel. Rate to include
for additional post and struts
for more than 100'-0" and 2
coats of white washing to all
concrete post.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 80
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
5.22.Aluminium Work
Supplying & fixing 100 mm
Door 1.6mm thick single
sash Aluminium door
(Aluminium composite
panel & glazed ) consisting
5mm thick glass panes on
top, 4 mm thick aluminium
composite panel at bottom,
door lock, stainless steel
Alu -
hinges, one pair stainless m2 36,477.00 36,580.00 36,657.00 36,452.00 36,631.00
001
steel handle, 1No door
closer, rubber, wool felt,
screws, reverts & any other
necessary fittings. All
complete as per detail
drawing. [Door closer paid
separately] (Project No:
S.1363/J, DRG- Door &
Window)
Supplying & fixing 100 mm
Door 1.6mm thick double
sash Aluminium door
(Aluminium composite
panel & glazed ) consisting
5mm thick glass panes on
top, 4 mm thick aluminium
composite panel at bottom,
door lock, stainless steel
Alu -
hinges, two pair stainless m2 34,921.00 34,982.00 35,074.00 34,905.00 35,044.00
002
steel handle, 2No Door
closer, rubber, wool felt,
screws, reverts & any other
necessary fittings. All
complete as per detail
drawing. [Door closer paid
separately] (Project No:
S.1363/J, DRG- Door &
Window)
Supplying & fixing 70 mm,
1.5mm thick Aluminium
glazed casement window
consisting 5mm thick glass
panes, casement lock,
Alu - stainless steel bar hinges,
m2 35,987.00 35,987.00 35,987.00 35,987.00 35,987.00
003 rubber, screws, reverts &
any other necessary fittings.
All complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 81
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying & fixing 70 mm,
1.3mm thick Aluminium
glazed sliding window
consisting 5mm thick glass
panes, sliding lock, roller,
Alu -
rubber, screws, reverts & m2 21,272.00 21,272.00 21,272.00 21,171.00 21,171.00
004
any other necessary fittings.
All complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Supplying & fixing 80 mm,
1.5mm thick Aluminium
glazed sliding window
consisting 5mm thick glass
panes, sliding lock, roller,
Alu -
rubber, screws, reverts & m2 30,278.00 30,278.00 30,278.00 30,177.00 30,177.00
005
any other necessary fittings.
All complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Supplying & fixing 70 mm,
1.2mm thick Aluminium
glazed top hung fanlight
consisting 5mm thick glass
panes, lock, rubber, screws,
Alu -
reverts & any other m2 41,768.00 41,768.00 41,768.00 41,768.00 41,768.00
006
necessary fittings. All
complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Supplying & fixing 70 mm,
1.2mm thick Aluminium
Alu - louver panel. All complete
m2 56,794.00 56,794.00 56,794.00 56,794.00 56,794.00
007 as per detail drawing.
(Project No: S.1363/J, DRG-
Door & Window)
Supplying & fixing
Alu -
008
hydraulic door closer. [ VVP no 4,786.00 4,965.00 4,965.00 4,978.00 5,143.00
or equivalent]
Supplying & affixing sand
blast sticker as per
Alu -
instructions. (Shall be m2 772.00 766.00 766.00 768.00 775.00
009
measured to the clear area of
glass in between frames).
Office of the Deputy Chief Secretary - Engineering Services, NP Page 82
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying & fixing 100mm
Aluminium shop front
partition (2.0mm thick)
(Aluminium composite
panel & glazed) consisting
5mm thick glass panes in top
and 4 mm thick aluminium
composite panel in bottom
Alu -
with all necessary
010 m2 25,398.00 25,398.00 25,398.00 25,398.00 25,398.00
accessories including,
gasket, rubber, self-trapping
screws, pop reverts, wall
plugs, silicon & any other.
All complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Supplying & fixing 100mm
Aluminium shop front
partition (2.0mm thick)
(Aluminium composite panel
& glazed) consisting 5mm
thick glass panes in middle
and 4 mm thick aluminium
composite panel in top &
Alu -
bottom of glass with all
011 m2 26,527.00 26,527.00 26,527.00 26,527.00 26,527.00
necessary accessories
including, gasket, rubber,
self-trapping screws, pop
reverts, wall plugs, silicon &
any other. All complete as
per detail drawing. (Project
No: S.1363/J, DRG- Door &
Window)
Supplying & fixing 100mm
Aluminium shop front
partition (2.0mm thick)
(Plywood panel & glazed)
consisting 5mm thick glass
panes in top and 3 mm thick
plywood panel in bottom with
all necessary accessories
Alu - including, gasket, rubber,
012 self-trapping screws, pop m2 20,548.00 20,528.00 20,541.00 20,601.00 20,551.00
reverts, wall plugs, silicon &
any other. The rate shall
inclusive of one coat of wood
primer and two coats of
enamel paint. All complete as
per detail drawing. (Project
No: S.1363/J, DRG- Door &
Window)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 83
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying & fixing 100mm
Aluminium shop front
partition (2.0mm thick)
(Plywood panel & glazed)
consisting 5mm thick glass
panes in middle and 3 mm
thick plywood panel in top
and bottom of glass panes
with all necessary accessories
Alu -
including, gasket, rubber,
013 m2 21,558.00 21,531.00 21,549.00 21,627.00 21,561.00
self-trapping screws, pop
reverts, wall plugs, silicon &
any other. The rate shall
inclusive of one coat of wood
primer and two coats of
enamel paint. All complete as
per detail drawing. (Project
No: S.1363/J, DRG- Door &
Window)
Supplying & fixing 76mm
Aluminium shop front
partition (1.2mm thick)
(Aluminium composite
panel & glazed) consisting
5mm thick glass panes in top
and 4 mm thick aluminium
composite panel in bottom
Alu -
with all necessary
014 m2 12,500.00 12,500.00 12,500.00 12,500.00 12,500.00
accessories including,
gasket, rubber, self-trapping
screws, pop reverts, wall
plugs, silicon & any other.
All complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Supplying & fixing 76mm
Aluminium shop front
partition (1.2mm thick)
(Aluminium composite
panel & glazed) consisting
5mm thick glass panes in
middle and 4 mm thick
aluminium composite panel
Alu - in top & bottom of glass
015 with all necessary m2 13,234.00 13,234.00 13,234.00 13,234.00 13,234.00
accessories including,
gasket, rubber, self-trapping
screws, pop reverts, wall
plugs, silicon & any other.
All complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 84
Buildings Works Rate 2025
Item Basic Rate (Rs.)
Code
Description Unit
Jaffna Kilinochchi Mullaitivu Mannar Vavuniya
Supplying & fixing 76mm
Aluminium shop front
partition (3mm thick)
(Plywood panel & glazed)
consisting 5mm thick glass
panes in top and 3 mm thick
plywood panel in bottom
with all necessary
accessories including,
Alu -
gasket, rubber, self-trapping
016 m2 11,152.00 11,131.00 11,145.00 11,205.00 11,154.00
screws, pop reverts, wall
plugs, silicon & any other.
The rate shall inclusive of
one coat of wood primer and
two coats of enamel paint.
All complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Supplying & fixing 76mm
Aluminium shop front
partition (1.2mm thick)
(Plywood panel & glazed)
consisting 5mm thick glass
panes in middle and 3 mm
thick plywood panel in top
and bottom of glass panes
with all necessary
Alu - accessories including,
017 gasket, rubber, self-trapping m2 21,558.00 21,531.00 21,549.00 21,627.00 21,561.00
screws, pop reverts, wall
plugs, silicon & any other.
The rate shall inclusive of
one coat of wood primer and
two coats of enamel paint.
All complete as per detail
drawing. (Project No:
S.1363/J, DRG- Door &
Window)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 85
Buildings Works Rate 2025
Project No :S.1362/J
DRG No :A1362
Sheet No :01/04
Not to Scale
Fencing with Reinforced Concrete Fence Post 2100mm Height
Office of the Deputy Chief Secretary - Engineering Services, NP Page 86
Buildings Works Rate 2025
Project No :S.13621/J
DRG No :A1362
Sheet No :02/04
Not to Scale
Fencing with Reinforced Concrete Fence Post 2100mm Height
Office of the Deputy Chief Secretary - Engineering Services, NP Page 87
Buildings Works Rate 2025
Project No :S.13622/J
DRG No :A1362
Sheet No :03/04
Not to Scale
Fencing with Reinforced Concrete Fence Post
2400mm Height
Office of the Deputy Chief Secretary - Engineering Services, NP Page 88
Buildings Works Rate 2025
Project No :S.13622/J
DRG No :A1362
Sheet No :04/04
Not to Scale
Fencing with Reinforced Concrete Fence Post
2400mm Height
Office of the Deputy Chief Secretary - Engineering Services, NP Page 89
Buildings Works Rate 2025
01/06
Office of the Deputy Chief Secretary - Engineering Services, NP Page 90
Buildings Works Rate 2025
02/06
Office of the Deputy Chief Secretary - Engineering Services, NP Page 91
Buildings Works Rate 2025
03/06
Office of the Deputy Chief Secretary - Engineering Services, NP Page 92
Buildings Works Rate 2025
04/06
Office of the Deputy Chief Secretary - Engineering Services, NP Page 93
Buildings Works Rate 2025
05/06
Office of the Deputy Chief Secretary - Engineering Services, NP Page 94
Buildings Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 95
Buildings Works Rate 2025
01/06
Office of the Deputy Chief Secretary - Engineering Services, NP Page 96
Buildings Works Rate 2025
02/06
Office of the Deputy Chief Secretary - Engineering Services, NP Page 97
Buildings Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 98
Buildings Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 99
Buildings Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 100
Buildings Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 101
Buildings Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 102
Irrigation Works Rate 2025
RATES FOR
IRRIGATION WORKS
Office of the Deputy Chief Secretary - Engineering Services, NP Page 103
Office of the Deputy Chief Secretary - Engineering Services, NP Page 104
Irrigation Works Rate 2025
6. RATES FOR IRRIGATION WORKS
6.1. GENERAL SPECIFICATIONS FOR IRRIGATION WORKS
• Specification for Irrigation & Land Drainage – Published on January 2017
CIDA Publication No: CIDA/SP/102
• Specification for Building Works (Volume I) – [3rd Edition (Revised) – July 2004]
ICTAD Publication No: SCA/4/1
• Specification for Electrical & Mechanical Works - [2nd Edition (Revised) – August 2000]
ICTAD Publication No: SCA/8
• Data for Costing of civil works Published by Irrigation Department third revision 1st January
1980.
• Rates included all taxes other than VAT. VAT to be paid separately.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 105
Irrigation Works Rate 2025
6.2 NORMS FOR CLEARING AND EARTH WORK
No Description Unit Qty
CLEARING - MANUAL
1 Clearing and grubbing light jungle clearing L.Day / Ha 74
2 Shrub & thorny jungle clearing L.Day / Ha 49
3 Secondary growth jungle clearing L.Day / Ha 37
2
4 Weeding L.Day / m 0.004
3
5 Stripping top soil L.Day / m 0.785
2
6 Scarifying top soil L.Day / m 0.02
CLEARING - MACHINERY
7 Clearing and grubbing light jungle Ha / Day 1.619
Burning to asses L.Day / Ha 2
8 Shrub & thorny jungle clearing Ha / Day 2.429
Burning to asses L.Day / Ha 2
9 Medium jungle clearing Ha / Day 1.214
Burning to asses L.Day / Ha 2
10 Common jungle clearing Ha / Day 1.416
Burning to asses L.Day / Ha 2
11 Heavy jungle clearing Ha / Day 1.335
Burning to asses L.Day / Ha 2
Stripping top soil along the upstream slope, downstream slope and top of the bund
12 to a thickness of 0.075 meters in order to receive new earth by machinery and spoils
to be disposed outside the reservation as directed
Stripping by Dozer m3/day 1,471.6
Loading by Back-hoe m3/day 1,279.16
EARTH WORK - MANUAL
Earth Excavation in foundation and back filling / spoil
13 L.Day / m3 1.04
to waste / dump including watering and compaction
Borrowing earth from identified borrow areas including transport and placing in
14
tank bund to the design profile in 225 mm layers including watering and compacting
Borrow Earth cut and lift 5' haul 200' L.Day / m3 0.883
Placing and compaction in tank bund including
L.Day / m3 0.213
picking roots and spreading
Watering on tank bund for compaction L.Day / m3 0.01
3
Less haul 200ft (0.196 L.day per 100 ft) L.Day / m 0.392
Earth Excavation from borrow and forming canal bund including watering and
15
compacting
Borrow Earth cut and lift 5' haul 200' L.Day / m3 0.883
Placing and compaction in canal bund including
L.Day / m3 0.213
picking roots and spreading
Watering on canal bund for compaction L.Day / m3 0.01
Less haul 200ft (0.196 L.day per 100 ft) L.Day / m3 0.392
Office of the Deputy Chief Secretary - Engineering Services, NP Page 106
Irrigation Works Rate 2025
No Description Unit Qty
16 Earth Cutting in canal and forming canal bund including watering and compacting
Borrow Earth cut and lift 5' haul 200' L.Day / m3 0.883
Placing and compaction in canal bund L.Day / m3 0.213
Watering on canal bund for compaction L.Day / m3 0.01
Less haul 100ft L.Day / m3 0.196
17 Desilting in canal and spoil to waste as directed
Desilt manual m3 /Day 1.415
EARTH WORK - MACHINERY
Borrowing earth from identified borrow areas including transport, benching, placing
in layers average thickness not more than 225mm as earth filling in existing bund
18
embankment and picking roots, watering as directed, compacting by vibrating
compactor
Borrow Earth - Dozing by Dozer m3 /Day 633.92
Loading by Back-hoe m3 /Day 289.23
Spreading by dozer - 100 ft m3 /Day 3,090.36
Picking roots by manual L.Day / m3 0.024
Watering on tank bund for compaction by Bowser m3 /Day 142
Compaction in tank bund by Sheep Foot roller m3 /Day 1,881.4
Earth Excavation from borrow and forming Canal bund including Compaction by
19
Machinery and shaping by manual
Borrow Earth by Excavator m3 /Day 289.23
Shaping by manual m3 /Day 100
Compacting by Back - hoe m3 /Day 300
Earth Cutting in canal or canal reservation and forming Canal bund including
20
Compaction by Machinery and shaping by manual
Earth cutting by Back - hoe m3 /Day 289.23
Shaping by manual m3 /Day 100
Compacting by Back - hoe m3 /Day 300
21 Earth cutting in canal and spoil to waste as directed
Earth cutting by Excavator m3 /Day 289.23
22 Earth deduction along spill tail canal and spoil to deposit
Earth - Dozing by Dozer m3 /Day 633.92
Loading by Back-hoe m3 /Day 289.23
23 Earth deduction along spill tail canal and level / heap
Earth - Dozing by Dozer m3 /Day 633.92
Office of the Deputy Chief Secretary - Engineering Services, NP Page 107
Irrigation Works Rate 2025
No Description Unit Qty
Earth Excavation from borrow and forming canal bund by manual Transport by
24
tractor (Earth cutting by machinery)
Earth cutting by Excavator m3 /Day 289.23
Placing and compaction in tank bund by manual L.Day / m3 0.213
Watering on tank bund for compaction by manual L.Day / m3 0.01
25 Cut open the bund and Spoil to waste by machinery
Cut open by Excavator m3 /Day 289.23
26 Cut open the bund by Machinery and filling by manual
Cut open by Excavator m3 /Day 289.23
Refilling haul manual 100' L.Day / m3 0.196
Placing and compaction in tank bund manual L.Day / m3 0.213
Watering on tank bund for compaction manual L.Day / m3 0.01
27 Cut open the bund and refilling including watering and compaction by machinery
Cut open by Excavator m3 /Day 289.23
Refilling by Back-hoe m3 /Day 904
Spreading manual L.Day / m3 0.09
Watering on tank bund for compaction by bowser m3 /Day 142
Compaction in tank bund by sheep foot roller m3 /Day 141.5
GRAVEL WORK
Furnishing, transporting, placing and spreading of gravel on the bund including
28
watering and compaction by manual
Gravel cut and lift 5' haul 200' L.Day / m3 1.04
Placing and compaction in tank bund including
L.Day / m3 0.213
picking roots and spreading
Watering on tank bund for compaction L.Day / m3 0.01
Less haul 50' L.Day / m3 0.196
Furnishing, transporting, placing and spreading of gravel on the bund including
29
watering and compaction by machinery
Gravel Cutting by Back-hoe m3 /Day 245.36
Spreading by dozer - 100' m3 /Day 2,988.5
Watering on tank bund for compaction by bowser m3 /Day 142
Compaction in tank bund by Sheep Foot Roller m3 /Day 1,881.4
Furnishing and placing 0.15m thick gravel bedding for placement of Rip rap as
30
directed
Spreading by dozer - 100 ' m3 /Day 2,988.5
Compaction in tank bund by Dozer m3 /Day 664.107
Office of the Deputy Chief Secretary - Engineering Services, NP Page 108
Irrigation Works Rate 2025
No Description Unit Qty
ROAD WAY
31 Trimming and comparing road way by machinery
Data for 1025 sq.m. for a 200mm thick layer
Volume of soil in the area cu.m(VankVol) 205
Grader blade efficiency % 85
Time for 4 passes in 1025 sq.m area Hours 1.5
Hire charges 120 - 140 hp motor grader Hours 1.5
Cost of banks men s/sk Hours 1.5
32 Earth Excavation from borrow and forming Road way
Borrow Earth Dozing by Dozer m3 /Day 633.92
3
Loading by Back-hoe m /Day 289.23
Spreading by Dozer - 100' m3 /Day 2,988.5
Picking roots Manual L.Day / m3 0.024
3
Watering on tank bund for compaction by Bowser m /Day 142
Compaction in road way by Vibrating roller m3 /Day 2,822.1
Furnishing, transporting, placing and spreading of gravel on the road way including
33
watering and compaction
Gravel Cutting by Back-hoe m3 /Day 245.36
Spreading by Dozer - 100' m3 /Day 1,992.32
3
Watering on tank bund for compaction m /Day 142
Compaction in road way by Vibrating roller m3 /Day 1,881.4
Supplying turf sods to site, preparation and dressing of surface, firmly placing and
34 full turfing to new fill and watering and kept moist till grass root up as directed by
the Engineer.
Cutting and planting turf in slopes L.Day / m2 0.072
L.days for watering L.Day / m2 0.0011
Water for turf l 12.474
2
Loading / unloading L.Day / m 0.0269
Office of the Deputy Chief Secretary - Engineering Services, NP Page 109
Irrigation Works Rate 2025
6.3 NORMS FOR CONCRETE AND OTHERS
No Description Unit Quantity
1 Reinforcement
Material including 25% for waste & lap of unit rate for 1kg
Tor steel reinforcement kg 1.25
2% Cost of Tor steel for bindings wire
1% Cost of Tor Steel for cover blocks
Skilled Labour L.Day 0.01
Unskilled Labour L.Day 0.03
2 Formwork in Timber
Plywood Sq 1.15
25 % cost of Planks for struts and battens
Assorted wire nails kg 7
5 % cost of Planks for deboning materials
Skilled for making for 6 uses L.Day 0.5
Unskilled for making for 6 uses L.Day 0.5
Unskilled for fixing and removing L.Day 1
3 6"-9" Random Rubble Masonry
Cement bags 2
Rubble m3 1.37
Sand m3 0.34
Water lit 58.83
Mason L.Day 0.26
Labourer L.Day 1.77
4 6"-9" Random Rubble Pitching - Thickness 9"
Cement bags 0.45
Rubble m3 0.33
Sand m3 0.08
Water lit 14.24
Mason L.Day 0.054
Labourer L.Day 0.38
5 300-450mm Removing Rip Rap
Labourer Removing existing rip rap L.Day 0.21
6 300-450mm Removing and Repacking Rip Rap
Labourer Removing existing rip rap L.Day 0.21
Labourer Repacking rip rap L.Day 0.21
7 Supplying & Dumping Rip Rap 300 - 450mm
Rubble 300 - 450mm m3 1.05
8 Placing & Packing Rip rap (Manual)
Labourer for placing & packing rip rap L.Day 0.23
Office of the Deputy Chief Secretary - Engineering Services, NP Page 110
Irrigation Works Rate 2025
No Description Unit Qty
9 Rubble Packing (Manual)
Rubble 150mm-225mm m3 1.05
Back Hoe M.Hrs 0.028
Internal Transport m3 1
Placing & packing day 0.2
Machinery Manual
No. Description Unit
1:3:6 1:2:4 1:11/2:3 1:3:6 1:2:4 1:11/2:3
10.0 Cement bags 4.54 6.40 8.10 4.54 6.40 8.10
11.0 Metal m3 0.92 0.88 0.82 0.92 0.88 0.82
12.0 Sand m3 0.46 0.44 0.41 0.46 0.44 0.41
13.0 Water lit 158.90 160.00 182.25 158.90 160.00 182.25
14.0 Skilled Labour day 0.35 0.35 0.35 0.35 0.35 0.35
Unskilled
15.0 day 1.06 1.06 1.06 2.74 2.74 2.74
Labour
16.0 Mixture hrs 0.71 0.71 0.71
17.0 Vibrator hrs 0.35 0.35 0.35
Tools &
18.0 L.Cost 0.03 0.03 0.03 0.03 0.03 0.03
Equipment
Office of the Deputy Chief Secretary - Engineering Services, NP Page 111
Irrigation Works Rate 2025
6.4. NORMS FOR GATES
For fixing gate Loading Unloading
(by team of 2 (by team of 2
No. Size of gate Skilled Unskilled unskilled unskilled
Labour Labour workmen per workmen per
hour) hour)
1 6" dia 150mm dia 0.4 1.4 8 8
2 9" dia 225mm dia 0.4 1.4 8 8
3 12" dia 300mm dia 0.5 1.5 4 4
4 15" dia 380mm dia 0.5 1.5 4 4
5 18" dia 450mm dia 0.75 2.75 4 4
6 24" dia 600mm dia 1 5 2 2
7 30" dia 750mm dia 1.5 7 2 2
8 36" dia 900mm dia 1.5 7 1 1
6.5 NORMS FOR HUME PIPES FOR L.FT
For Laying & Unloading
Loading
Jointing (by team
(by team of 2
of 2 Joint
No. Size of Hume pipe unskilled
Skilled Unskilled unskilled materials
workmen per
Labour Labour workmen
hour)
per hour)
1 4" dia 100mm dia 0.5/60 2/60 36ft 36ft
2 6" dia 150mm dia 0.5/60 2/60 36ft 36ft
3 9" dia 225mm dia 0.5/42 2/42 36ft 36ft
4 12" dia 300mm dia 0.5/24 2/24 36ft 36ft
5 15" dia 380mm dia 0.5/24 2/24 36ft 36ft 11/2 %
cost of
6 18" dia 450mm dia 1/30 4/30 16ft 16ft pipe
7 24" dia 600mm dia 1/24 4/24 16ft 16ft
8 30" dia 750mm dia 1/18 4/18 8ft 8ft
9 36" dia 900mm dia 1/18 6/18 8ft 8ft
10 48" dia 1200mm dia 1/12 6/12 4ft 4ft
Office of the Deputy Chief Secretary - Engineering Services, NP Page 112
Irrigation Works Rate 2025
6.6 NORMS FOR MISCELLANEOUS WORKS
No Description Unit Quantity
1 Supplying and fixing of 12mm Ø 0.45m long Mild steel Dowel
Weight of Steel kg 0.4
Skilled Labour L.Day 0.1
Unskilled Labour L.Day 0.1
2 Supplying and Fixing of 16mm Ø 0.45m long Mild steel Dowel
Weight of Steel kg 0.71
Skilled Labour L.Day 0.125
Unskilled Labour L.Day 0.125
Furnishing and fixing 50 x 100mm R.C.C. hand rails with 2 Nos. 10mm Ø
3
reinforcement including form work
1:2:4 (20 mm) ct. concrete per L/m m3 0.005
2
Formwork m 0.3
Fixing Skilled Labour L.Day 0.166
Fixing Unskilled Labour L.Day 0.166
Reinforcement kg 1.234
4 Guard Stones
12 mm Tor steel kg 3.2
1:2:4(20mm) ct. con m3 0.026
Form work m2 0.393
5 Forming of Sand in Pohora Bags.
Unskilled Labour L.Day 0.033
6 Stitching of Sand Bags.
Unskilled Labour L.Day 0.005
7 Laying of Sand Bags.
Unskilled Labour L.Day 0.025
8 Removing of Sand Bags.
Unskilled Labour L.Day 0.025
Rate Analysis for fabricating and installation of 1350mm x 750m size steel paneled
9
gate
50mm x50mm x6mm L angle m 7.05
6mm thick steel plate m² 1.013
37.5mm Dia spindle bar m 2.25
Thread cutting charges ft 3.445
37.5mm Dia GI housing, base plate & locking
No 1
arrangement with full set
Brass nut No 1
150mm x75mm size channel iron m 1.65
Rag bolt 3/4" x 9" Nos 2
Operating handle No 1
Office of the Deputy Chief Secretary - Engineering Services, NP Page 113
Irrigation Works Rate 2025
No Description Unit Quantity
10 Water Level Measuring Gauge
Supplying and fixing 0.15m x 13.72m Stainless steel plat in
approved colour printing of water level measuring gauge
16 gauge stainless steel plat (including wastage) m2 2.97
2
Colour print m 2.97
Stainless scrow Nos 64
Skill labour L.day 2
Painter L.day 2
Welder L.day 2
Labour L.day 6
11 Furnishing, & Packing 225 x 150 mm random rubble in to Gabion boxes
Rubble Cube 1.44
Unskilled Labour L.Day 4.25
Skilled L.Day 0.85
12 Furnishing, & Laying Polyfelt Geosynthetics sheet 1.5mmthk. for gabion boxes
Unskilled Labour L.Day 0.05
13 Furnishing, & Laying Polyfelt Geosynthetics 2.5mmthk. sheet for gabion boxes
Unskilled Labour L.Day 0.05
14 Expansion joints in concrete
Bitumen Lit 22.5
River sand Cube 5
Skill Labour L.day 0.125
Unskill Labour L.day 0.125
6.7 NORMS FOR GABION BOX
Lacing & Placing or
No Size
1 No Gabion Box/ L Day
1 1.0 x 0.5 x 0.5 0.167
2 1.0 x 1.0 x 1.0 0.292
3 1.5 x 1.0 x 1.0 0.313
4 2.0 x 1.0 x 1.0 0.333
5 2.0 x 1.0 x 0.5 0.250
6 3.0 x 1.0 x 1.0 0.375
7 3.0 x 1.0 x 0.5 0.292
Office of the Deputy Chief Secretary - Engineering Services, NP Page 114
Irrigation Works Rate 2025
6.8 NORMS FOR AGRICULTURE WELLS
Rate adjustment for Agriculture Wells
Depth in ft Plastering Block Work Rubble Masonary
0 - 05 add 0.25 L.Days add 0.25 L.Days add 0.25 L.Days
05 -10 add 0.5 L.Days add 0.5 L.Days add 0.5 L.Days
10 - 15 add 0.75 L.Days add 0.75 L.Days add 0.75 L.Days
15 - 20 add 1 L.Days add 1 L.Days add 1 L.Days
Earth Excavation
Production of 8 hrs Excavator in Shaping Spreading
Lift in ft m3 by manual by dozer - 100 ft
Cutting Lifting (m3 per day) (m3 per day)
0-5 144.613 289.23
5 - 10 141.783 283.57
100 2988.48
10 - 15 138.387 276.77
15 - 20 135.274 270.55
No Description Unit Quantity
16mm thick cement and sand 1:3 Plastering
Cement Cube 1.47
River sand Cube 0.06
Skill Labour L.day 0.75
Unskill Labour L.day 1.50
Cement Concrete block in 1:4:5(20mm) Masonry 1:5 Cement and Sand
Block Casting: Cement Cwt 11.25
River Sand Cube 0.60
¾” Metal Cube 1.00
Skill Labour L.day 4.5
Unskill Labour L.day 9.00
Basket 0.66
Masonry work: Cement Cwt 2.5
River Sand Cube 0.25
Skill Labour L.day 2.50
Unskill Labour L.day 4.00
Basket 0.33
* Rate to be added for every 5’depth as 5%, 7%, 10%, 13%, 16%.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 115
Irrigation Works Rate 2025
6.9 RATES FOR IRRIGATION WORKS
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
6.9.1 CLEARING WORKS - MANUAL
Light jungle clearing along
the tank bund / Canal /
Spill tail canal / road way
and reservations including
1 177,600.00 170,200.00 170,200.00 185,000.00 170,200.00
uprooting stumps Ha
removing outside and
burning to ashes as
directed.
Shrub and thorny jungle
clearing along the Tank
bund / Canal / Spill tail
canal / road way and
2 reservations including 117,600.00 112,700.00 112,700.00 122,500.00 112,700.00
Ha
uprooting stumps
removing outside and
burning to ashes where
ever necessary as directed.
Secondary growth jungle
clearing along the tank
bund / Canal / Spill tail
canal / road way and
3 88,800.00 85,100.00 85,100.00 92,500.00 85,100.00
reservations including Ha
uprooting and removing
outside and burning to
ashes as directed.
Weeding and clearing
along the tank bund /
4 Canal / Spill tail canal /
m2 10.00 9.00 9.00 10.00 9.00
road way and reservations
as directed.
Stripping top soil along the
upstream slope,
downstream slope and top
of the bund to a thickness
5 of 0.075 meters in order to
m3 1,884.00 1,806.00 1,806.00 1,962.00 1,805.00
receive new earth and
spoils to be disposed
outside the reservation as
directed
Scarifying top soil along
the upstream slope,
downstream slope and top
of the bund / canal bund to
6 a thickness of 0.025 meters
m2 48.00 46.00 46.00 50.00 46.00
in order to receive new
earth and spoils to be
disposed outside the
reservation as directed
Office of the Deputy Chief Secretary - Engineering Services, NP Page 116
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
6.9.2 CLEARING WORKS - MACHINERY
Light jungle clearing along
the tank bund / Canal /
Spill tail canal / road way
and reservations including
7 49,907.00 62,137.00 49,784.00 62,384.00 57,195.00
uprooting stumps Ha
removing outside and
burning to ashes as
directed.
Shrub and thorny jungle
clearing along the Tank
bund / Canal / Spill tail
canal / road way and
8 reservations including 33,272.00 41,425.00 33,189.00 41,589.00 38,130.00
Ha
uprooting stumps
removing outside and
burning to ashes where
ever necessary as directed.
Medium jungle clearing
along the tank bund /
Canal / Spill tail canal /
road way and reservations
9 66,557.00 82,867.00 66,392.00 83,196.00 76,276.00
including uprooting Ha
stumps removing outside
and burning to ashes as
directed.
Common jungle clearing
along the tank bund /
Canal / Spill tail canal /
road way and reservations
10 71,186.00 93,644.00 93,644.00 88,276.00 71,045.00
including uprooting Ha
stumps removing outside
and burning to ashes as
directed.
Heavy jungle clearing
along the tank bund /
Canal / Spill tail canal /
road way and reservations
11
including uprooting Ha 75,506.00 99,326.00 99,326.00 93,632.00 75,355.00
stumps removing outside
and burning to ashes as
directed.
Stripping top soil along the
upstream slope,
downstream slope and top
of the bund to a thickness
12 of 0.075 meters in order to
m3 215.00 236.00 214.00 217.00 224.00
receive new earth and
spoils to be disposed
outside the reservation as
directed
Office of the Deputy Chief Secretary - Engineering Services, NP Page 117
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
6.9.3 EARTH WORK - MANUAL
Earth Excavation in
foundation and back filling
13 / spoil to waste / dump
m3 2,496.00 2,392.00 2,392.00 2,600.00 2,392.00
including watering and
compaction
Borrowing earth from
identified borrow areas
including transport and
14 placing in tank bund to the
design profile in 225 mm m3 1,916.00 1,845.00 1,844.00 1,976.00 1,796.00
layers including watering
and compacting
Earth Excavation from
borrow and forming canal
15
bund including watering m3 1,868.00 1,797.00 1,796.00 1,930.00 1,796.00
and compacting
Earth Cutting in canal and
forming canal bund
16
including watering and m3 2,184.00 2,093.00 2,093.00 2,275.00 2,093.00
compacting
Desilting in canal and
17
spoil to waste as directed m3 1,696.00 1,625.00 1,625.00 1,766.00 1,625.00
6.9.4 EARTH WORK - MACHINERY
Borrowing earth from
identified borrow areas
including transport,
benching & Spreading(by
dozer - 100ft), placing in
layers average thickness
18
not more than 225mm as m3 691.00 793.00 693.00 732.00 709.00
earth filling in existing
bund embankment and
picking roots, watering as
directed, compacting by
vibrating compactor
Earth Excavation from
borrow and forming Canal
19 bund including
m3 616.00 697.00 614.00 580.00 641.00
Compaction by Machinery
and shaping by manual
Earth Cutting in canal or
canal reservation and
forming Canal bund
20
including Compaction by m3 461.00 542.00 460.00 435.00 487.00
Machinery and shaping by
manual
Earth cutting in canal and
21
spoil to waste as directed m3 343.00 385.00 378.00 355.00 392.00
Office of the Deputy Chief Secretary - Engineering Services, NP Page 118
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Earth deduction along spill
22 tail canal and spoil to
m3 467.00 541.00 502.00 511.00 535.00
deposit
Earth deduction along spill
23 m3 124.00 156.00 124.00 156.00 143.00
tail canal and level / heap
Earth Excavation from
borrow and forming canal
24 bund by manual Tpt by
m3 878.00 898.00 891.00 913.00 904.00
tractor (Earth cutting by
machinery)
Cut open the bund and
25 Spoil to waste by
m3 343.00 385.00 378.00 355.00 392.00
machinery
Cut open the bund by
26 Machinery and filling by
m3 1,230.00 1,230.00 1,188.00 1,257.00 1,201.00
manual
Cut open the bund and
refilling including
27
watering and compaction m3 865.00 1,320.00 1,220.00 1,263.00 1,190.00
by machinery
6.9.5 GRAVEL WORK
Furnishing, transporting,
placing and spreading of
28 gravel on the bund
m3 7,841.00 6,769.00 5,953.00 4,727.00 5,901.00
including watering and
compaction by manual
Furnishing, transporting,
placing and spreading of
29 gravel on the bund
m3 5,676.00 4,790.00 3,899.00 2,562.00 3,945.00
including watering and
compaction by machinery
Furnishing and placing
0.15m thick gravel bedding
30
for placement of Rip rap as m3 4,836.00 4,016.00 3,342.00 2,094.00 3,364.00
directed
6.9.6 ROAD WAY
Trimming and comparing
31
road way by machinery m2 17.00 17.00 13.00 15.00 14.00
Earth Excavation from
32 borrow and forming Road
m3 693.00 775.00 671.00 714.00 689.00
way
Furnishing, transporting,
placing and spreading of
33 gravel on the road way
m3 5,694.00 4,794.00 3,895.00 2,471.00 3,897.00
including watering and
compaction
Office of the Deputy Chief Secretary - Engineering Services, NP Page 119
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Supplying turf sods to site,
preparation and dressing of
surface, firmly placing and
34 full turfing to new fill and
m2 288.00 258.00 251.00 270.00 276.00
watering and kept moist till
grass root up as directed by
the Engineer.
6.9.7 CONCRETE - MANUAL
1:3:6(40) Ct. sand concrete
compacting with porker
35
viberator including curing m3 24,861.00 23,215.00 22,160.00 22,846.00 22,487.00
without form work
1:3:6(40) Ct. sand concrete
compacting with porker
36
viberator including curing m3 27,112.00 25,619.00 24,525.00 25,223.00 24,758.00
with form work
1:2:4(20) Ct. sand concrete
compacting with porker
37
viberator including curing m3 27,875.00 26,296.00 25,241.00 26,111.00 25,566.00
without form work
1:2:4(20) Ct. sand concrete
compacting with porker
38
viberator including curing m3 30,879.00 29,506.00 28,398.00 29,285.00 28,598.00
with form work
1:1 1/2:3(20) Ct. sand
concrete compacting with
39
porker viberator including m3 30,240.00 28,718.00 27,675.00 28,560.00 28,040.00
curing without form work
1:1 1/2:3(20) Ct. sand
concrete compacting with
40
porker viberator including m3 32,091.00 30,695.00 29,620.00 30,515.00 29,907.00
curing with form work
6.9.8 CONCRETE - MACHINERY (MIXTURE)
1:3:6(40) Ct. sand concrete
using concrete mixer and
41 compacting with porker
m3 21,870.00 19,923.00 19,000.00 19,495.00 19,327.00
viberator including curing
without form work
1:3:6(40) Ct. sand concrete
using concrete mixer and
42 compacting with porker
m3 24,121.00 22,326.00 21,365.00 21,872.00 21,598.00
viberator including curing
with form work
1:2:4(20) Ct. sand concrete
using concrete mixer and
43 compacting with porker
m3 24,883.00 23,003.00 22,080.00 22,758.00 22,404.00
viberator including curing
without form work
Office of the Deputy Chief Secretary - Engineering Services, NP Page 120
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
1:2:4(20) Ct. sand concrete
using concrete mixer and
44 compacting with porker
m3 27,888.00 26,213.00 25,237.00 25,931.00 25,436.00
viberator including curing
with form work
1:1 1/2:3(20) Ct. sand
concrete using concrete
45 mixer and compacting with
m3 27,248.00 25,425.00 24,514.00 25,207.00 24,877.00
porker viberator including
curing without form work
1:1 1/2:3(20) Ct. sand
concrete using concrete
46 mixer and compacting with
m3 29,122.00 27,426.00 26,483.00 27,185.00 26,768.00
porker viberator including
curing with form work
6.9.9 RUBBLE WORK
Supplying and placing 9"
random rubble masonry
47 work using 150-225mm
m3 18,121.00 17,011.00 15,024.00 14,988.00 15,269.00
thickness rubble with 1:5
ct.sand motor
Supplying and placing 9"
random rubble Pitching
48 work using 150-225mm
m2 4,154.00 3,891.00 3,417.00 3,401.00 3,478.00
thickness rubble with 1:5
ct.sand motor
Supplying and heaping 300
49
- 450 mm rubble for rip rap m3 5,406.00 5,211.00 3,835.00 3,140.00 3,834.00
Placing Rip-Rap from the
dumped rubble an average
thickness of 300/450 mm
on upstream slope of bund
50
as directed by the m3 552.00 529.00 529.00 575.00 529.00
Engineer.(Rate includes
the necessary internal
transport and loading)
Removing existing
collapsed rip -rap and
51
heaping the rubble as m3 504.00 483.00 483.00 525.00 483.00
directed by the Engineer.
Removing and re packing
52 rip rap as directed by the
m3 1,008.00 966.00 966.00 1,050.00 966.00
Engineer.
Supplying and placing
53 150-225mm rubble
m3 6,226.00 6,053.00 4,634.00 3,959.00 4,648.00
packing
Office of the Deputy Chief Secretary - Engineering Services, NP Page 121
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
6.9.10 REINFORCEMENT
Supplying bending and 417.00 414.00 415.00 420.00 413.00
kg
54 placing QT Rib bar as
reinforcement
6.9.11 FORMWORK
Furnishing and making of
form work made out 20mm
thick plywood with
55
necessary frame and m2 1,143.00 1,220.00 1,200.00 1,206.00 1,152.00
supports including fixing
and removing as directed
6.9.12 HUME PIPES
Supplying , laying and
56 jointing 100 mm dia Hume L.m 4,083.00 4,013.00 4,076.00 3,543.00 4,208.00
pipe in position
Supplying , laying and
57 jointing 150 mm dia hume L.m 4,665.00 4,304.00 4,659.00 4,126.00 4,790.00
pipe in position
Supplying , laying and
58 jointing 225 mm dia hume L.m 5,746.00 5,110.00 5,736.00 5,212.00 5,865.00
pipe in position
Supplying , laying and
59 jointing 300 mm dia hume L.m 7,043.00 6,499.00 7,024.00 6,522.00 7,147.00
pipe in position
Supplying , laying and
60 jointing 375 mm dia hume L.m 7,542.00 7,373.00 7,524.00 7,021.00 7,647.00
pipe in position
Supplying , laying and
61 jointing 450 mm dia hume L.m 10,090.00 9,676.00 10,063.00 8,734.00 10,391.00
pipe in position
Supplying , laying and
62 jointing 600 mm dia hume L.m 13,965.00 12,728.00 13,929.00 12,621.00 14,251.00
pipe in position
Supplying , laying and
63 jointing 900 mm dia hume L.m 22,815.00 22,584.00 22,733.00 20,360.00 23,337.00
pipe in position
Supplying , laying and
64 jointing 1200 mm dia L.m 44,697.00 45,538.00 44,578.00 39,727.00 45,805.00
hume pipe in position
Office of the Deputy Chief Secretary - Engineering Services, NP Page 122
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
6.9.13 GATES
Supplying and fixing
150mm Dia C.I Gate with
complete set including
65 spindle 25mm diameter, 56,590.00 56,443.00 56,600.00 56,807.00 56,547.00
Nr
2m long ,base plate, Brass
nut, Rag Bolts,ect in
position
Supplying and fixing
225mm Dia C.I Gate with
complete set including
66 spindle 25mm diameter, 79,590.00 75,944.00 79,600.00 79,807.00 79,547.00
Nr
2m long, base plate, Brass
nut, Rag Bolts,ect in
position
Supplying and fixing
300mm Dia C.I Gate with
complete set including
67 spindle 25mm diameter,
Nr 85,250.00 85,588.00 85,371.00 85,539.00 85,325.00
2m long, base plate, Brass
nut, Rag Bolts,ect in
position
Supplying and fixing
375mm Dia C.I Gate with
complete set including
68 spindle 37mm diameter, Nr 110,250.00 114,088.00 110,371.00 110,539.00 110,325.00
2m long, base plate, Brass
nut, Rag Bolts,ect in
position
Supplying and fixing
450mm Dia C.I Gate with
complete set including
69 spindle 37mm diameter, Nr 138,925.00 126,638.00 138,946.00 139,351.00 138,850.00
2m long, base plate, Brass
nut, Rag Bolts,ect in
position
Supplying and fixing
600mm Dia C.I Gate with
complete set including
70 spindle 50mm diameter, Nr 205,300.00 199,775.00 205,321.00 206,069.00 205,224.00
2m long, base plate, Brass
nut, Rag Bolts, ect in
position
Supplying and fixing
750mm Dia C.I Gate with
complete set including
71 spindle 50mm diameter, Nr 251,450.00 260,725.00 251,321.00 252,444.00 251,124.00
2m long, base plate, Brass
nut, Rag Bolts, ect in
position
Office of the Deputy Chief Secretary - Engineering Services, NP Page 123
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Supplying and fixing
900mm Dia C.I Gate with
complete set including
72 spindle 50mm diameter, Nr 382,800.00 381,750.00 382,363.00 373,817.00 382,655.00
2m long, base plate, Brass
nut, Rag Bolts, ect in
position
Supplying fabricating and
73 installation of 1350mm x Nr 97,270.00 105,606.00 108,043.00 105,766.00 122,819.00
750m size steel paneled
gate
6.9.14 MISCELLINIOUS
Supplying and fixing of
74 12mm dia. 0.45 m long Nr 610.00 600.00 610.00 625.00 590.00
mild steel dowels
Supplying and fixing of
75 16mm dia. 0.45 m long Nr 815.00 803.00 815.00 833.00 790.00
mild steel dowels
76 Chemical Anchoring Nr
without Reinforcement 449.00 409.00 438.00 453.00 442.00
Furnishing and fixing
50*100mm R.C.C. hand
77 rails with 2 Nos. 10mm dia. m
1,847.00 1,842.00 1,848.00 1,886.00 1,800.00
Reinforcement including
formwork
Providing guard stones as
78 per type NP/IRR/GS/Type Nr 5,507.00 5,325.00 5,177.00 5,295.00 5,201.00
No 01
Providing of 50 x 100 weep
79 holes as per type Nr 3,859.00 2,715.00 2,788.00 3,002.00 3,012.00
NP/IRR/WH/Type No 01
225.00 750.00 475.00 1,000.00 500.00
80 Water Pumps 50 mm (2") Hr.
338.00 875.00 581.00 1,125.00 562.00
81 Water Pumps 75 mm (3") Hr.
Supplying of empty C.I.C.
82 pohora bags ( 50kg size of Nr 70.00 70.00 52.00 52.00 70.00
fertilizer)
Forming of sand in pohora
83 Nr 80.00 77.00 77.00 83.00 76.00
bags.
84 Stitching of sand bags. Nr 12.00
12.00
11.00 12.00 11.00
85 Laying of sand bags. Nr 60.00 58.00 58.00 62.00 57.00
86 Removing of sand bags. Nr 60.00 58.00 58.00 62.00 57.00
Water level measuring
87 m2 62,060.00 55,422.00 51,660.00 52,534.00 51,878.00
gauge
Office of the Deputy Chief Secretary - Engineering Services, NP Page 124
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Expansion joints in
concrete floors filling with
88 bitumen and sand (to full L.m 892.00 844.00 849.00 873.00 844.00
depth of concrete and
rendering) ( 1/2" thick and
40" deep)
6.9.15 GABIONS
Furnishing, Lacing &
89 Placing of PVC Coated 1 x Nr 4,625.00 4,608.00 4,608.00 4,641.00 4,433.00
0.5 x 0.5 m Gabions boxes
Furnishing, Lacing &
Placing of PVC Coated 1.0
90 Nr 10,450.00 10,420.00 10,420.00 10,479.00 10,420.00
x 1.0 x 1.0 m Gabions
boxes
Furnishing, Lacing &
Placing of PVC Coated 1.5
91 Nr 13,100.00 13,068.00 13,068.00 13,131.00 13,068.00
x 1.0 x 1.0 m Gabions
boxes
Furnishing, Lacing &
Placing of PVC Coated 2.0
92 Nr 17,440.00 17,406.00 17,406.00 17,473.00 17,406.00
x 1.0 x 1.0 m Gabions
boxes
Furnishing, Lacing &
Placing of PVC Coated 2.0
93 Nr 12,430.00 12,404.00 12,404.00 12,455.00 12,404.00
x 1.0 x 0.5 m Gabions
boxes
Furnishing, Lacing &
Placing of PVC Coated 3.0
94 Nr 24,170.00 24,132.00 24,132.00 24,207.00 24,132.00
x 1.0 x 1.0 m Gabions
boxes
Furnishing, Lacing &
Placing of PVC Coated 3.0
95 Nr 19,160.00 19,130.00 19,130.00 19,189.00 19,130.00
x 1.0 x 0.5 m Gabions
boxes
Furnishing, & Laying
96 Polyfelt Geosynthetics m2 453.00 665.00 540.00 455.00 445.00
1.5mmthk. sheet for gabion
boxes
Furnishing, & Laying
97 Polyfelt Geosynthetics m2 783.00 797.00 777.00 675.00 665.00
2.5mmthk. sheet for gabion
boxes
Furnishing, & Packing 225
98 x 150 mm random rubble m3 11,285.00 10,361.00 9,383.00 8,142.00 9,323.00
in to Gabion boxes
Office of the Deputy Chief Secretary - Engineering Services, NP Page 125
Irrigation Works Rate 2025
Rate (Rs) without profit and overhead
No Description Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
6.9.16 AGRICULTURE WELLS
Earth Excavation in
foundation 0-5 ft. lift up to
99 5ft. Spread with in 100ft. m3 717.00 848.00 716.00 683.00 761.00
by Machinery and shaping
by manual
Earth Excavation in
foundation 5-10 ft. lift up
100 to 10ft. Spread with in m3 725.00 857.00 724.00 691.00 770.00
100ft. by Machinery and
shaping by manual
Earth Excavation in
foundation 10-15 ft. lift up
101 to 15ft. Spread with in m3 749.00 886.00 748.00 713.00 795.00
100ft. by Machinery and
shaping by manual
Earth Excavation in
foundation 15-20 ft. lift up
102 to 20ft. Spread with in m3 765.00 905.00 764.00 728.00 812.00
100ft. by Machinery and
shaping by manual
Soft Rock Excavation in
foundation 0-5 ft. lift up to
103 m3 1,197.00 1,418.00 1,196.00 1,133.00 1,271.00
20ft. Spread with in 100ft.
by Machinery and shaping
16mm thick cement and
104 m2 745.00 745.00 745.00 1,000.00 946.00
sand 1:3 plastering
100mm Cement concrete
block in 1:4:5[20mm]
105 m2 4,001.00 3,650.00 3,647.00 3,797.00 3,701.00
masonry in 1:5 cement and
sand.
125mm Cement concrete
block in 1:4:5[20mm]
106 m2 5,001.00 4,562.00 4,559.00 4,747.00 4,626.00
masonry in 1:5 cement and
sand.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 126
Irrigation Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 127
Irrigation Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 128
Road Works Rate 2025
RATES FOR
ROAD WORKS
Office of the Deputy Chief Secretary - Engineering Services, NP Page 129
Road Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 130
Road Works Rate 2025
7. RATES FOR ROAD WORKS
7.1 GENERAL SPECIFICATIONS FOR ROAD WORKS
• Standard Specification for Construction and Maintenance of Roads and Bridges (SSCM).
ICTAD publication No. SCA/5 second edition June 2009
7.2 Section I – H.S.R. – Schedule of Prices
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
7.2.1. Hire Charges (Wet lease basic - including operator)
Tar Boiler (Heating with
Day
B0-101 Firewood) (Less Operator) 90.00 90.00 90.00 90.00 90.00
(6hrs)
*
Concrete / Asphalt Mixer Day
B0-102 (400 Ltrs) 7,650.00 7,650.00 7,650.00 7,650.00 7,650.00
(6hrs)
Bitumen Sprayer (Less Day
B0-103 Operator) * 100.00 100.00 100.00 100.00 100.00
(6hrs)
Water Tank + 50 mm. Day
B0-104 Pumb (Less Operator) * 3,320.00 3,320.00 3,320.00 3,320.00 3,320.00
(6hrs)
Welding Plant Engine Day
B0-105 14,100.00 14,100.00 14,100.00 14,100.00 14,100.00
Driven: With Welder (6hrs)
Porker Vibrater (Less Day
B0-106 1,980.00 1,980.00 1,980.00 1,980.00 1,980.00
Operator) * (6hrs)
Plate Compactor (90 Kg) Day
B0-107 (Less Operator) * 3,750.00 3,750.00 3,750.00 3,750.00 3,750.00
(6hrs)
Vibrating Rammer (60 Day
B0-108 Kg) (Less Operator) * 3,600.00 3,600.00 3,600.00 3,600.00 3,600.00
(6hrs)
Vibrating Roller (1/2 - 1 Day
B0-109 Ton) 8,120.00 8,120.00 8,120.00 8,120.00 8,120.00
(6hrs)
Vibrating Roller (Smooth Day
B0-110 39,450.00 39,450.00 39,450.00 39,450.00 39,450.00
- 10 Tons) (6hrs)
Smooth / Road Roller (8 - Day
B0-111 20,580.00 20,580.00 20,580.00 20,580.00 20,580.00
10 Tons: Static) (6hrs)
Pneumatic Road Roller (8
B0-112 Hour 7,350.00 7,350.00 7,350.00 7,350.00 7,350.00
- 10 Tons)
B0- Vibrating Roller (0.75 -
Day 10,074.00 10,074.00 10,074.00 10,074.00 10,074.00
112-A 1.25 Ton)
Day
B0-113 Motor Grader (65 Hp) 29,860.00 29,860.00 29,860.00 29,860.00 29,860.00
(6hrs)
Motor Grader (120 - 140 Day
B0-114 47,160.00 47,160.00 47,160.00 47,160.00 47,160.00
Hp) (6hrs)
Day
B0-115 Backhoe Loader (Jcb ) 30,800.00 30,800.00 30,800.00 30,800.00 30,800.00
(6hrs)
Day
B0-116 Whell Loader (1.4 Cu.M) 31,880.00 31,880.00 31,880.00 31,880.00 31,880.00
(6hrs)
B0- Day
Wheel loader (1.7 Cu.m) 32,970.00 32,970.00 32,970.00 32,970.00 32,970.00
116a (6hrs)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 131
Road Works Rate 2025
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Day
B0-117 Tractor & Trailer (3 ton:) 9,540.00 9,540.00 9,540.00 9,540.00 9,540.00
(6hrs)
Lorry / Tipper / Dt km/
B0-118 32.50 32.50 32.50 32.50 32.50
(Exceeding 10 km) Cu.m
-Do - (For less than 10 km. km/
B0-119 35.00 35.00 35.00 35.00 35.00
distances) Cu.m
B0-119 -Do - (For less than 03 km. km/
37.50 37.50 37.50 37.50 37.50
-1 distances) Cu.m
km/
Transport of premix by
B0-120 M.To 27.50 27.50 27.50 27.50 27.50
dump truck **
nne
km/1
B0- Transport of emulsion per
00 4.00 4.00 4.00 4.00 4.00
120a 100 liters
Ltrs
Sand / Chip spreader - Day
B0-121 40,180.00 40,180.00 40,180.00 40,180.00 40,180.00
propelled (6hrs)
B0- Day
Sand / Chip spreader - towed 2,600.00 2,600.00 2,600.00 2,600.00 2,600.00
121a (6hrs)
Day
B0-122 Farm tractor & broom 11,150.00 11,150.00 11,150.00 11,150.00 11,150.00
(6hrs)
Emulsion sprayer self-prop. Day
B0-123 25,920.00 25,920.00 25,920.00 25,920.00 25,920.00
(4000 liters) (6hrs)
Wheel loader (2.7 - 3.1 Day
B0-124 44,850.00 44,850.00 44,850.00 44,850.00 44,850.00
Cu.m) (6hrs)
B0- Wheel loader (2.0 - 2.3 Day
36,200.00 36,200.00 36,200.00 36,200.00 36,200.00
124a Cu.m) (6hrs)
B0-125 Lorry 3 Ton (2.5 Cu.m) km 72.00 72.00 72.00 72.00 72.00
B0-126 Lorry 5 Ton (3.5 Cu.m) km 85.00 85.00 85.00 85.00 85.00
B0-127 Lorry 7 Ton (4.5 Cu.m) km 105.00 105.00 105.00 105.00 105.00
Day
B0-128 Water bowser (6000 liters) 20,580.00 20,580.00 20,580.00 20,580.00 20,580.00
(6hrs)
B0-129 Asphalt paver (Crawler) Hour 11,120.00 11,120.00 11,120.00 11,120.00 11,120.00
B0-
Asphalt paver (Wheel) Hour 11,320.00 11,320.00 11,320.00 11,320.00 11,320.00
129a
B0-130 Tanker only (20,000 liters) Hour 215.00 215.00 215.00 215.00 215.00
Prime mover old (For
B0-131 Hour 8,950.00 8,950.00 8,950.00 8,950.00 8,950.00
20,000 L Tanker)
B0- Prime mover new (For 30 T
Hour 8,950.00 8,950.00 8,950.00 8,950.00 8,950.00
131a Trailer)
Baby dumper .75 Cu.m
B0-132 Hour 1,750.00 1,750.00 1,750.00 1,750.00 1,750.00
(Less operator)
Water pump 4'' (With
B0-133 Hour 1,670.00 1,670.00 1,670.00 1,670.00 1,670.00
operator)
B0- Water pump 2'' (Less
Hour 790.00 790.00 790.00 790.00 790.00
133a operator)
Sludge pump 4'' (With
B0-134 Hour 2,270.00 2,270.00 2,270.00 2,270.00 2,270.00
operator)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 132
Road Works Rate 2025
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Vibrating roller (6 - 7 Tons)
B0-135 Hour 3,400.00 3,400.00 3,400.00 3,400.00 3,400.00
tandem
Concrete mixer with load Day
B0-136 11,720.00 11,720.00 11,720.00 11,720.00 11,720.00
cell weighs batcher 14/10 (6hrs)
Trolley emulsion (Less
B0-137 Hour 95.00 95.00 95.00 95.00 95.00
operator)
B0-138 Sprayer emulsion hand cart Hour 1,150.00 1,150.00 1,150.00 1,150.00 1,150.00
Road marker hand cart gas
B0-139 Hour 3,200.00 3,200.00 3,200.00 3,200.00 3,200.00
heater
Bitumen distributor 750
B0-140 Hour 2,160.00 2,160.00 2,160.00 2,160.00 2,160.00
liters
Tank truck bitumen 10,000
B0-141 Hour 5,360.00 5,360.00 5,360.00 5,360.00 5,360.00
ltr
B0-142 Stone crusher 40 t/h Hour 17,500.00 17,500.00 17,500.00 17,500.00 17,500.00
B0-143 Track drill crawler Hour 2,250.00 2,250.00 2,250.00 2,250.00 2,250.00
B0-144 Compressor air 750 cfm Hour 9,910.00 9,910.00 9,910.00 9,910.00 9,910.00
B0-145 Slurry sealing machine Hour 16,270.00 16,270.00 16,270.00 16,270.00 16,270.00
Day
B0-146 Mobile crane 25 ton 10,080.00 10,080.00 10,080.00 10,080.00 10,080.00
(8hrs)
B0-146 Day
Mobile crane 30 ton - wet 13,310.00 13,310.00 13,310.00 13,310.00 13,310.00
a (8hrs)
B0-147 Asphalt plant 60t/h hot mix Hour 27,640.00 27,640.00 27,640.00 27,640.00 27,640.00
Cold mix plant 15t/h
B0-148 Hour - - - - -
ITEM DELETED
Pickup truck 2wd
B0-149 km - - - - -
ITEM DELETED
Farm tractor with water
B0-150 Hour 1,780.00 1,780.00 1,780.00 1,780.00 1,780.00
bowser
Lorry 17 ton self-loading
B0-151 km 260.00 260.00 260.00 260.00 260.00
(Wet)
Tractor with emulsion
B0-152 Hour 1,590.00 1,590.00 1,590.00 1,590.00 1,590.00
bowser
Emulsion tank truck (8000
B0-153 km 220.00 220.00 220.00 220.00 220.00
liters)
Dozer (Crawler tractor) D-
B0-154 Hour 6,900.00 6,900.00 6,900.00 6,900.00 6,900.00
4, D-41(80 - 100 HP)
B0-155 Excavator mobile Hour 10,200.00 10,200.00 10,200.00 10,200.00 10,200.00
B0-156 Air compressor 250 cfm Hour 6,620.00 6,620.00 6,620.00 6,620.00 6,620.00
Hand held breaker
B0-157 Day 605.00 605.00 605.00 605.00 605.00
(Demolisher) less operator
Rock drill hand held (less
B0-158 Hour 440.00 440.00 440.00 440.00 440.00
drill steel)
Supply of soil from borrow pits including loading and transport. (For quantities more than 300
Cu.m.)
Approved soil type I & II
B0-201 Cu.m 3,534.00 2,473.00 2,473.00 1,413.00 2,473.00
for bases & shoulders
Approved soil type I & II
B0-202 Cu.m 3,357.00 2,297.00 2,297.00 1,237.00 2,297.00
for embankments
Office of the Deputy Chief Secretary - Engineering Services, NP Page 133
Road Works Rate 2025
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
7.2.2. Construction Material Prices
Aggregate & Rubble
Note * Unit rates are scheduled to the main town of each district (No transport will be added to
10km from that town)
(150mm - 225mm) Rubble
B0-301
- (Vehicle measurement, Cu.m 4,770.00 4,240.00 3,534.00 2,473.00 3,534.00
Excluding piling)
(150mm - 225mm)
B0-302 Cu.m 5,222.00 4,692.00 3,986.00 2,943.00 3,969.00
Rubble piled
Manual Production
B0-303 (100mm) Aggregate Cu.m 5,300.00 4,594.00 4,417.00 3,357.00 4,240.00
Plant Production
B0-308a (19mm) Aggregate Cu.m 5,830.00 5,124.00 4,947.00 4,064.00 4,770.00
B0-309 (12.5mm) Aggregate Cu.m 5,124.00 4,594.00 4,417.00 3,180.00 4,594.00
(37.5mm) - Do -,
B0-310 (S.S.C.M. Tb: 1701-1 / Cu.m 5,565.00 4,859.00 4,682.00 3,622.00 4,505.00
1701-4)
(50mm) - Do -, (S.S.C.M.
B0-311 Cu.m 5,477.00 4,770.00 4,594.00 3,534.00 4,417.00
Tb: 1701-4)
Crusher Fines (6.3mm.
B0-312 Cu.m 4,417.00 3,710.00 3,534.00 2,120.00 3,710.00
Down wards)
(37.5mm) Graded (Table
B0-313 Cu.m 5,654.00 4,417.00 4,240.00 3,357.00 4,240.00
1701.5 for ABC)
Aggregate for seal coat treatments
(Grading as per SSCM table 1701-8)
B0-314 Aggregate 19mm Cu.m 6,030.00 5,324.00 5,147.00 4,264.00 4,970.00
B0-315 Aggregate 12.5mm Cu.m 5,324.00 4,794.00 4,617.00 3,380.00 4,794.00
B0-316 Aggregate 9.5mm Cu.m 5,324.00 4,794.00 4,617.00 3,380.00 4,794.00
Sand (Unit rates are scheduled to the main town of each district)
(No transport will be added to 10km from that town)
River sand for road
B0-331 surface applications Cu.m 7,067.00 4,947.00 5,124.00 6,184.00 5,654.00
(SSCM table 1701-9)
River sand for concrete
B0-332 and masonry work Cu.m 6,360.00 4,947.00 4,947.00 6,184.00 5,654.00
(SSCM table 1701-2)
Bitumen & Emulsion
Bitumen 80/100[200 ltr
B0-351 l 170.00 170.00 170.00 170.00 170.00
Drums]
Bitumen 60/70 [140 ltr
B0-351a l 170.00 170.00 170.00 170.00 170.00
drums] (Ex-Stockist)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 134
Road Works Rate 2025
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
B0-352 Emulsion - C.S.S. 1 l 150.00 150.00 150.00 150.00 150.00
B0-353 Emulsion - C.R.S. 1 l 150.00 150.00 150.00 150.00 150.00
B0-354 Emulsion - C.R.S. 2 l 155.00 155.00 155.00 155.00 155.00
Bo- 356 Mc 30 l 260.00 260.00 260.00 260.00 260.00
Premixed Bituminous Materials (Transport Cost from Plant to the Laying Site to be Paid
Separately)
Asphalt concrete:
B0-361 surfacing material - M.Ton 16,000.00 16,000.00 16,000.00 16,000.00 16,000.00
BINDER 60/70 BITUMEN @
4.7% OF MIX
Timber & Firewood (Including transport cost)
Sawn timber class 1 Cu.Dec
B0-391 255.00 255.00 255.00 255.00 255.00
(Local) i.m
Sawn timber class 2 Cu.Dec
B0-392 115.00 115.00 115.00 115.00 115.00
(Local) i.m
Timber round jungle -
B0-393
100mm minimum and m 130.00 130.00 130.00 130.00 130.00
150mm average diameter
Timber round jungle -
B0-394
150mm minimum and m 125.00 125.00 125.00 125.00 125.00
200mm average diameter
B0-395 Firewood Cu.m 2,790.00 2,790.00 2,790.00 2,790.00 2,790.00
Plywood (MR) for
B0-396 Sq.m 1,920.00 1,920.00 1,920.00 1,920.00 1,920.00
formwork - 15mm thick
Bamboo tree length
B0-397 No. 550.00 550.00 550.00 550.00 550.00
greater than 8 meters
Cement (Including transport cost)
Portland cement (for all Bag
B0-401 1,650.00 1,650.00 1,650.00 1,650.00 1,650.00
work) (50 kg)
Steel and steel items (Including transport cost)
B0-411 Mild steel kg 250.00 250.00 250.00 250.00 250.00
B0-411a Tor steel kg 250.00 250.00 250.00 250.00 250.00
B0-431 Binding wire kg 330.00 330.00 330.00 330.00 330.00
Wire nails, M.S. bolts &
B0-432 kg 340.00 340.00 340.00 340.00 340.00
nuts
Stainless steel 20mm dia.
B0-433 m 1,950.00 1,950.00 1,950.00 1,950.00 1,950.00
(for dowels)
GI Pipes,50mm diameter:
B0-434 m 3,420.00 3,420.00 3,420.00 3,420.00 3,420.00
heavy duty type
B0-435 M.S sheet,2mm thick Sq.m 5,730.00 5,730.00 5,730.00 5,730.00 5,730.00
Office of the Deputy Chief Secretary - Engineering Services, NP Page 135
Road Works Rate 2025
7.2.3. Precast Concrete Items
Minimum Price –Transport to be added from the Casting Place
Reinforced Concrete Pipes & Collars- Jaffna
Pipe Collar
Diameter - mm Length - mm Unit
A B
B0-441 153 (6") 2438 (8') 01 No. 7,000.00 1,200.00
B0-442 229 (9") 2438 (8') 01 No. 9,000.00 1,450.00
B0-443 305 (12") 2438 (8') 01 No. 11,000.00 2,000.00
B0-444 450 (1' 6") 2438 (8') 01 No. 14,000.00 2,750.00
B0-445 610 (2' 0") 2438 (8') 01 No. 22,000.00 3,150.00
B0-446 914 (3' 0") 1219 (4') 01 No. 17,500.00 4,275.00
B0-447 1219 (4' 0") 1219 (4') 01 No. 35,000.00 5,300.00
Reinforced Concrete Pipes & Collars- Kilinochchi
Pipe Collar
Diameter - mm Length - mm Unit
A B
B0-441 153 (6") 2438 (8') 01 No. 7,000.00 1,200.00
B0-442 229 (9") 2438 (8') 01 No. 9,000.00 1,450.00
B0-443 305 (12") 2438 (8') 01 No. 11,000.00 2,000.00
B0-444 450 (1' 6") 2438 (8') 01 No. 14,000.00 2,750.00
B0-445 610 (2' 0") 2438 (8') 01 No. 22,000.00 3,150.00
B0-446 914 (3' 0") 1219 (4') 01 No. 17,500.00 4,275.00
B0-447 1219 (4' 0") 1219 (4') 01 No. 35,000.00 5,300.00
Reinforced Concrete Pipes & Collars- Mullaitivu
Pipe Collar
Diameter - mm Length - mm Unit
A B
B0-441 153 (6") 2438 (8') 01 No. 7,000.00 1,200.00
B0-442 229 (9") 2438 (8') 01 No. 9,000.00 1,450.00
B0-443 305 (12") 2438 (8') 01 No. 11,000.00 2,000.00
B0-444 450 (1' 6") 2438 (8') 01 No. 14,000.00 2,750.00
B0-445 610 (2' 0") 2438 (8') 01 No. 22,000.00 3,150.00
B0-446 914 (3' 0") 1219 (4') 01 No. 17,500.00 4,275.00
B0-447 1219 (4' 0") 1219 (4') 01 No. 35,000.00 5,300.00
Reinforced Concrete Pipes & Collars- Vavuniya
Pipe Collar
Diameter - mm Length - mm Unit
A B
B0-441 153 (6") 2438 (8') 01 No. 7,000.00 1,200.00
B0-442 229 (9") 2438 (8') 01 No. 9,000.00 1,450.00
B0-443 305 (12") 2438 (8') 01 No. 11,000.00 2,000.00
B0-444 450 (1' 6") 2438 (8') 01 No. 14,000.00 2,750.00
B0-445 610 (2' 0") 2438 (8') 01 No. 22,000.00 3,150.00
B0-446 914 (3' 0") 1219 (4') 01 No. 17,500.00 4,275.00
B0-447 1219 (4' 0") 1219 (4') 01 No. 35,000.00 5,300.00
Reinforced Concrete Pipes & Collars- Mannar
Pipe Collar
Diameter - mm Length - mm Unit
A B
B0-441 153 (6") 2438 (8') 01 No. 7,000.00 1,200.00
B0-442 229 (9") 2438 (8') 01 No. 9,000.00 1,450.00
B0-443 305 (12") 2438 (8') 01 No. 11,000.00 2,000.00
B0-444 450 (1' 6") 2438 (8') 01 No. 14,000.00 2,750.00
B0-445 610 (2' 0") 2438 (8') 01 No. 22,000.00 3,150.00
B0-446 914 (3' 0") 1219 (4') 01 No. 17,500.00 4,275.00
B0-447 1219 (4' 0") 1219 (4') 01 No. 35,000.00 5,300.00
Office of the Deputy Chief Secretary - Engineering Services, NP Page 136
Road Works Rate 2025
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Precast concrete items Transport to be added from the Casting Place
Std road kerb 125 X 250 X
B0-448 1 No. 1,750.00 1,750.00 1,750.00 1,750.00 1,750.00
900 G25 concrete
Paving slab 450 X 450 X
B0-449 1 No. 975.00 975.00 975.00 975.00 975.00
50 mm G20 concrete
B0-450 Bridge kerb 915 1 No. 3,475.00 3,475.00 3,475.00 3,475.00 3,475.00
Std. uprights for bridges
B0-451 1 No. 4,100.00 4,100.00 4,100.00 4,100.00 4,100.00
(New design)
Std. hand rails for bridges
B0-452 1 No. 3,900.00 3,900.00 3,900.00 3,900.00 3,900.00
(New design)
Couping pairs for hand
B0-453 1 Pair 1,700.00 1,700.00 1,700.00 1,700.00 1,700.00
rails
Rain water channels
B0-454 1 No. 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00
609mm long
Cement sand hollow block
B0-455 1 No. 65.00 65.00 65.00 65.00 65.00
16" X 8" X 4"
Interlocking concrete
B0-456a blocks (210x110x60mm) 1 No. 57.50 57.50 57.50 57.50 57.50
(15n/mm2)
Interlocking concrete
B0-456b blocks (210x110x80mm) 1 No. 66.50 66.50 66.50 66.50 66.50
2
(40n/mm )
Interlocking concrete
B0-456c blocks (210x110x80mm) 1 No. 62.50 62.50 62.50 62.50 62.50
(30n/mm2)
7.2.4. Blasting Materials (Including transport cost)
B0-501 Blasting powder kg 2,050.00 2,050.00 2,050.00 2,050.00 2,050.00
B0-502 Fuse wire m 830.00 830.00 830.00 830.00 830.00
B0-503 Steel, Jumper kg 700.00 700.00 700.00 700.00 700.00
B0-504 Electric detonators No 165.00 165.00 165.00 165.00 165.00
B0-505 Dyna cord m 77.00 77.00 77.00 77.00 77.00
B0-506 Gelignite kg 3,720.00 3,720.00 3,720.00 3,720.00 3,720.00
B0-507 Ammonium nitrate kg 1,400.00 1,400.00 1,400.00 1,400.00 1,400.00
B0-508 Ordinary detonator No 12.00 12.00 12.00 12.00 12.00
7.2.5. Paints (Including transport cost)
Bituminous emulsion pain
B0-531 l 155.00 155.00 155.00 155.00 155.00
(Crs-2)
B0-534 Glue kg 615.00 615.00 615.00 615.00 615.00
B0-537 Lime - Boiled kg 35.00 35.00 35.00 35.00 35.00
B0-541 Enamel paint l 1,460.00 1,460.00 1,460.00 1,460.00 1,460.00
B0-542 Paint - Anti corrosive l 1,370.00 1,370.00 1,370.00 1,370.00 1,370.00
B0-544 Paint - Emulsion l 870.00 870.00 870.00 870.00 870.00
B0-545 Rust remover l 3,400.00 3,400.00 3,400.00 3,400.00 3,400.00
Emulsion for exterior use
B0-546 l 980.00 980.00 980.00 980.00 980.00
(Weather shield)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 137
Road Works Rate 2025
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Road marking paint
B0-547 l 1,900.00 1,900.00 1,900.00 1,900.00 1,900.00
(Yellow)
Road marking paint
B0-548 l 1,900.00 1,900.00 1,900.00 1,900.00 1,900.00
(White)
7.2.6. Fuel, Oils & Lubricants
Industrial kerosene oil
B0-601 l 188.00 188.00 188.00 188.00 188.00
(Colombo)
Mould Oil (Including
B0-602 l 160.00 160.00 160.00 160.00 160.00
transport)
B0-611 Lubricant (Oil) l 1,520.00 1,520.00 1,520.00 1,520.00 1,520.00
B0-612 Auto diesel l 286.00 286.00 286.00 286.00 286.00
B0-613 Petrol l 309.00 309.00 309.00 309.00 309.00
B0-614 Furnace oil for burners l 135.00 135.00 135.00 135.00 135.00
B0-615 Gas kg 365.00 365.00 365.00 365.00 365.00
B0-616 Lubricant (Grease) kg 3,270.00 3,270.00 3,270.00 3,270.00 3,270.00
7.2.7. Miscellaneous (Including transport cost)
B0-631 Baskets 1 No. 300.00 300.00 300.00 300.00 300.00
B0-632 Gunny bags new (Large) 1 No. 102.00 102.00 102.00 102.00 102.00
B0-632a Poly sacs (65kg capacity) 1 No. 70.00 70.00 70.00 70.00 70.00
B0-633 Cotton waste kg 135.00 135.00 135.00 135.00 135.00
B0-634 Salt kg 75.00 75.00 75.00 75.00 75.00
Empty tar barrels (140
B0-635 No 91.00 91.00 91.00 91.00 91.00
Ltrs)
P.V.C. pipe 110 mm dia
B0-636 m 1,060.00 1,060.00 1,060.00 1,060.00 1,060.00
type 250 Pe (With trans.)
P.V.C. pipe 110 mm dia
B0-636b m 1,610.00 1,610.00 1,610.00 1,610.00 1,610.00
type 400 Pe (With trans.)
P.V.C. pipe 50 mm dia
B0-637 m 330.00 330.00 330.00 330.00 330.00
type 400 (With trans.)
Hard rubber 12mm thick X
B0-638 m 2,695.00 2,695.00 2,695.00 2,695.00 2,695.00
75mm wide (With trans.)
Polythene 325mm dia
gauge 300 (approx. 13.5
B0-639 meters/ kg) kg 700.00 700.00 700.00 700.00 700.00
(tubular flat width app.505
mm, with trans.)
B0-640 Aluminum sheet 24 Swg Sq.m 2,360.00 2,360.00 2,360.00 2,360.00 2,360.00
B0-641 Angle iron 50x50x6 mm m 1,290.00 1,290.00 1,290.00 1,290.00 1,290.00
B0-642 M.S. Plate 12mm thick Sq.m 33,300.00 33,300.00 33,300.00 33,300.00 33,300.00
B0-643 Adhesive 250gm tin No 1,310.00 1,310.00 1,310.00 1,310.00 1,310.00
B0-644 Emulsifier -css/ crs Kg 2,560.00 2,560.00 2,560.00 2,560.00 2,560.00
Early strength ad mixer
B0-645 (usage:300 ml per 50kg l 495.00 495.00 495.00 495.00 495.00
cement bag)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 138
Road Works Rate 2025
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
B0-646 Traffic cones No 3,130.00 3,130.00 3,130.00 3,130.00 3,130.00
B0-647 75mm x 8mm dia nuts and No
35.00 35.00 35.00 35.00 35.00
bolts
B0-648 Saw dust (loose) Cu.m 130.00 130.00 130.00 130.00 130.00
B0-649 Drill steel M 150.00 150.00 150.00 150.00 150.00
Piece rates & allowances allow for:
Barricading (small work
B0-704 Item 1,100.00 1,100.00 1,100.00 1,100.00 1,100.00
items)
Barricading, Lighting,
B0-705
Signaling etc for 100 m Day 2,750.00 2,750.00 2,750.00 2,750.00 2,750.00
(stationary operations)
Cement, Sand & Water for
B0-711 jointing - Hume pipe Joint 110.00 110.00 110.00 110.00 110.00
152mm diameter
- Do - 229 to 610mm
B0-712 Joint 220.00 220.00 220.00 220.00 220.00
diameter
B0-713 - Do - 915mm diameter Joint 440.00 440.00 440.00 440.00 440.00
B0-714 - Do - 1220mm diameter Joint 770.00 770.00 770.00 770.00 770.00
Coir rope (for scaffolding
B0-715 Item 550.00 550.00 550.00 550.00 550.00
93 Sq.m area)
Coir string for cutting side
B0-716 Item 80.00 80.00 80.00 80.00 80.00
drains (per 2.83 Cu.m)
- Do - Fixing scaffolding
B0-717 Item 440.00 440.00 440.00 440.00 440.00
(per 93 Sq.m)
Minor repairs of parapets
B0-718
with cement, sand & water Item 550.00 550.00 550.00 550.00 550.00
(per 9.29 Sq.m)
Fuel *(for loosening road
B0-720 surface in manual
Item 110.00 110.00 110.00 110.00 110.00
breaking 50 mm depth X
307 Sq.m) *
Fuel, forge etc. (per 2.83
B0-723 Item 220.00 220.00 220.00 220.00 220.00
Cu.m blasting)
B0-732 Ladders (per 93 Sq.m) Item 550.00 550.00 550.00 550.00 550.00
Paint (for lettering &
B0-741 Item 220.00 220.00 220.00 220.00 220.00
numbering items)
Pegs (for turfing in 19
B0-746 Item 550.00 550.00 550.00 550.00 550.00
Sq.m area)
Sand paper & cott.waste
B0-751 Item 330.00 330.00 330.00 330.00 330.00
(per 9.29 Sq.m )
Sharp. scarifier tynes (for
B0-752 Item 110.00 110.00 110.00 110.00 110.00
307 Sq.m)
Timber planks & bamboos
B0-761 Item 1,430.00 1,430.00 1,430.00 1,430.00 1,430.00
(for 93 Sq.m)
Timber post, horizontal
B0-762 etc.(for barricading work Item 2,200.00 2,200.00 2,200.00 2,200.00 2,200.00
in 4l.m)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 139
Road Works Rate 2025
New Basic Rate (Rs)
Description of Item Unit
Code Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Water for concreting
Allow for water for
B0-781 Cu.m 55.00 55.00 55.00 55.00 55.00
mixing by machine per
Allow for water for
B0-782 Cu.m 55.00 55.00 55.00 55.00 55.00
mixing manually per
Water for compaction & general use
Allow for gravel
B0-784 Cu.m 28.00 28.00 28.00 28.00 28.00
compaction per
Allow for aggregate
B0-785 Cu.m 30.00 30.00 30.00 30.00 30.00
compaction per
Allow for moistening road
B0-786 Item 110.00 110.00 110.00 110.00 110.00
surface
Allow for water bucket &
B0-787 Item 110.00 110.00 110.00 110.00 110.00
coir rope
B0-788 Water for general purpose l 28.00 28.00 28.00 28.00 28.00
White washing for barricading
White washing empty
B0-791 01 No. 250.00 250.00 250.00 250.00 250.00
barrels (Pen. Grade)
White washing timber
B0-792
posts, horizontals, etc. (In 01 Item 95.00 95.00 95.00 95.00 95.00
4 l.m barricading)
7.2.8. Thermoplastic road marking materials excluding transport & VAT
Following material prices are for estimation only *(Payments should be based on approved tender
prices)
Thermo plastic road
B0-800 marking materials kg 320.00 320.00 320.00 320.00 320.00
(White)*
Thermo plastic road - Do-
B0-801 kg 260.00 260.00 260.00 260.00 260.00
(Yellow)*
B0-802 Glass beads* kg 300.00 300.00 300.00 300.00 300.00
Gabion Mesh* (Galvanized) Excluding Transport & VAT Gabion Size M
1x1x1 in clu. coated tie
Per
B0-850 (Binding) wire @ 5% of 8,950.00 8,950.00 8,950.00 8,950.00 8,950.00
Box
gabion weight
2x1x.5 inclu. coated tie
Per
B0-851 (Binding) wire @ 5% of 11,200.00 11,200.00 11,200.00 11,200.00 11,200.00
Box
gabion weight
1.5x1x1 inclu. coated tie
Per
B0-852 (Binding) wire @ 5% of 12,000.00 12,000.00 12,000.00 12,000.00 12,000.00
Box
gabion weight
2x1x1 inclu. coated tie
Per
B0-853 (Binding) wire @ 5% of 16,400.00 16,400.00 16,400.00 16,400.00 16,400.00
Box
gabion weight
Geotextiles * Excluding transport & VAT
Geotextiles (Nonwoven
polypropylene polymer
B0-860 Per
tear resistant > 400n and 360.00 360.00 360.00 360.00 360.00
Sq.m
apparent pore size < 200
nm)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 140
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
7.3 Section II-Schedule of Rates
7.3.1. Transport Rates
*See Section I of general notes of HSR published by RDA for selection of mode of transport
Transport of soil 25m to
T1- 100m by any means
Cu.m 676.00 648.00 648.00 704.00 648.00
001 (including loading and
unloading):
Transport 100m to 0.5km by
T1-
any means (excluding Cu.m 381.00 381.00 381.00 381.00 381.00
002
loading):
Transport 0.5km to 1.0km by
T1-
any means (excluding Cu.m 408.00 408.00 408.00 408.00 408.00
003
loading):
Transport of each
T1-
subsequent 1km from 1.0 -
003 Cu.m 63.00 63.00 63.00 63.00 63.00
8.0 km by any means
A
(excluding loading):
Transport of each
T1-
subsequent 1km beyond 8.0
003 Cu.m 42.00 42.00 42.00 42.00 42.00
km by any means (excluding
B
loading):
* T1--004, T1-005 - codes changed as T1-003a and T1-003b
Transport of material in bulk
T1- excluding loading (for
Cu.m 112.00 112.00 112.00 112.00 112.00
006 distance less than or equal 3
kilo meters)
Transport of material in bulk
T1- excluding loading (from 3
Cu.m 35.00 35.00 35.00 35.00 35.00
007 km up to 10 kilo meters
distance)
T1- Transport of material in bulk
007 excluding loading (for Cu.m 32.00 32.00 32.00 32.00 32.00
A distance more than 10km)
* T1-008 : Code amended as T1-007A
Transport of premix in bulk
T1-
excluding loading other than mt/km 27.00 27.00 27.00 27.00 27.00
009
at mixing plant
Transport of barrels of
T1- bitumen for first 1.0 km of
No 59.00 59.00 59.00 60.00 59.00
010 transport (excluding loading
and unload) :
Transport of barrels of
T1- bitumen for each subsequent
010 1.0 km, from 1.0 - 8.0 km No 14.00 14.00 14.00 14.00 14.00
A (excluding loading and
unload):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 141
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Transport of barrels of
T1- bitumen for each subsequent
010 1.0 km beyond 8.0 km No 10.00 9.00 9.00 10.00 9.00
B (excluding loading and
unload):
T1-011 & T1-012 code changed
Loading barrels of bitumen
T1-
inclusive of rolling up to No 42.00 40.00 40.00 43.00 40.00
013
25m:
Unloading barrels of
T1-
bitumen inclusive of rolling No 18.00 17.00 17.00 18.00 17.00
014
and stacking:
Transport of Hume pipes
T1- 152mm dia. For 1st 1.0 km
lm 45.00 44.00 44.00 45.00 44.00
015 of transport (excluding
loading and unload):
Transport of Hume pipes
152mm dia. For each
T1-
subsequent 1.0 km, from 1.0
015 lm 12.00 11.00 11.00 12.00 11.00
- 8.0 km of transport
A
(excluding loading and
unload):
Transport of Hume pipes
152mm dia. For each
T1-
subsequent 1.0 km beyond
015 lm 8.00 8.00 8.00 8.00 8.00
8.0 km of transport
B
(excluding loading and
unload):
* T1-016 & T1-017 code changed
Transport of Hume pipes
T1- 229mm dia. For 1st 1.0 km
lm 50.00 50.00 50.00 51.00 50.00
018 of transport (excluding
loading and unload):
Transport of Hume pipes
152mm dia. For each
T1-
subsequent 1.0 km, from 1.0
018 lm 13.00 13.00 13.00 13.00 13.00
- 8.0 km of transport
A
(excluding loading and
unload):
Transport of Hume pipes
152mm dia. For each
T1-
subsequent 1.0 km beyond
018 lm 9.00 9.00 9.00 9.00 9.00
8.0 km of transport
B
(excluding loading and
unload):
* T1-019 & T1-020: code change
Office of the Deputy Chief Secretary - Engineering Services, NP Page 142
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Transport of Hume pipes
T1- 305mm dia. For 1st 1.0 km
lm 67.00 67.00 67.00 68.00 67.00
021 of transport (excluding
loading and unload):
Transport of Hume pipes
305mm dia. For each
T1-
subsequent 1.0 km, from 1.0
021 lm 18.00 17.00 17.00 18.00 17.00
- 8.0 km of transport
A
(excluding loading and
unload):
Transport of Hume pipes
305mm dia. For each
T1-
subsequent 1.0 km beyond
021 lm 13.00 12.00 12.00 13.00 12.00
8.0 km of transport
B
(excluding loading and
unload):
* T1-022 & T1-023: code changed
Transport of Hume pipes
T1- 457mm dia. For 1st 1.0 km
lm 101.00 100.00 100.00 102.00 100.00
024 of transport (excluding
loading and unload):
Transport of Hume pipes
457mm dia. For each
T1-
subsequent 1.0 km, from 1.0
024 lm 27.00 26.00 26.00 27.00 26.00
- 8.0 km of transport
A
(excluding loading and
unload):
Transport of Hume pipes
457mm dia. For each
T1-
subsequent 1.0 km beyond
024 lm 19.00 19.00 19.00 19.00 19.00
8.0 km of transport
B
(excluding loading and
unload):
* T1-025 & T1-026: code changed
Transport of Hume pipes
T1- 610mm dia. For 1st 1.0 km
lm 135.00 134.00 134.00 136.00 134.00
027 of transport (excluding
loading and unload):
Transport of Hume pipes
610mm dia. For each
T1-
subsequent 1.0 km, from 1.0
027 lm 36.00 35.00 35.00 37.00 35.00
- 8.0 km of transport
A
(excluding loading and
unload):
Transport of Hume pipes
610mm dia. For each
T1-
subsequent 1.0 km beyond
027 lm 26.00 25.00 25.00 26.00 25.00
8.0 km of transport
B
(excluding loading and
unload):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 143
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
* T1-028 & T1-029: code changed
Transport of Hume pipes
T1- 915mm dia. For 1st 1.0 km
lm 202.00 201.00 201.00 204.00 201.00
030 of transport (excluding
loading and unload):
Transport of Hume pipes
915mm dia. For each
T1-
subsequent 1.0 km, from 1.0
030 lm 54.00 53.00 53.00 55.00 53.00
- 8.0 km of transport
A
(excluding loading and
unload):
Transport of Hume pipes
915mm dia. For each
T1-
subsequent 1.0 km beyond
030 lm 39.00 38.00 38.00 39.00 38.00
8.0 km of transport
B
(excluding loading and
unload):
* T1-031 & T1-032: code changed
Transport of Hume pipes
T1- 1220mm dia. For 1st 1.0 km
lm 460.00 455.00 455.00 464.00 455.00
033 of transport (excluding
loading and unload):
Transport of Hume pipes
1220mm dia. For each
T1-
subsequent 1.0 km, from 1.0
033 lm 162.00 158.00 158.00 167.00 158.00
- 8.0 km of transport
A
(excluding loading and
unload):
Transport of Hume pipes
915mm dia. For each
T1-
subsequent 1.0 km beyond
033 lm 118.00 114.00 114.00 121.00 114.00
8.0 km of transport
B
(excluding loading and
unload):
* T1-034 & T1-035: code changed
Loading and unloading
T1-
152mm dia. 2.44m long No 129.00 124.00 124.00 135.00 124.00
036
Hume pipes:
Loading and unloading
T1-
229mm dia. 2.44m long No 151.00 144.00 144.00 157.00 144.00
037
Hume pipes:
Loading and unloading
T1-
305mm dia. 2.44m long No 300.00 287.00 287.00 312.00 287.00
038
Hume pipes:
Loading and unloading
T1-
457mm dia. 2.44m long No 499.00 478.00 478.00 520.00 478.00
039
Hume pipes:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 144
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Loading and unloading
T1-
610mm dia. 2.44m long No 650.00 623.00 623.00 677.00 623.00
040
Hume pipes:
Loading and unloading
T1-
915mm dia. 1.22.44m long No 1,200.00 1,150.00 1,150.00 1,250.00 1,150.00
041
Hume pipes:
Loading and unloading
T1-
1220mm dia. 1.22m long No 2,400.00 2,300.00 2,300.00 2,500.00 2,300.00
042
Hume pipes:
Transport of precast kerb
T1- stones (all types) for road
lm/km 2.00 2.00 2.00 2.00 2.00
043 works, including loading
and unloading:
Transport of precast kerb
T1- stones for bridge works,
lm/km 3.00 3.00 3.00 3.00 3.00
044 including loading and
unloading:
Transport of precast
concrete hand rails up-rights
T1-
and joints for bridge works, lm/km 5.00 5.00 5.00 5.00 5.00
045
including loading and
unloading:
Transport of precast
concrete slabs 450 x 450 x
T1- Sq.m/
50 mm for foot walks, 6.00 6.00 6.00 6.00 6.00
046 km
including loading and
unloading:
Transport of precast
T1-
standard boundary markers No/km 3.00 3.00 3.00 3.00 3.00
047
including unloading only*:
* Supply rate include loading at yard.
T1- 100 l /
Transport of emulsion: 2.00 2.00 2.00 2.00 2.00
048 km
T1-
049 Transport of Gabion mesh
No/km 1.00 1.00 1.00 1.00 1.00
(NE 4x1x1 m size:
W)
7.3.2. Roadway and foundation / trench excavation
(Including loading, unloading and transporting within 25 meters distance unless otherwise specified)
Note: For roadway excavations involving more than 300 cu.m, machine rates should be adopted
Note: Transportation to be included for sand related works
E1- Excavation in loose
Cu.m 904.00 868.00 868.00 940.00 868.00
001 soil(dry)[SSCM 301.2(iv)]:
Excavation in loose soil
E1-
(wed) in slips [SSCM Cu.m 1,121.00 1,076.00 1,076.00 1,167.00 1,076.00
002
301.3(0)] :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 145
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Excavation in ordinary soil
E1-
(cutting measurement) Cu.m 1,339.00 1,284.00 1,284.00 1,393.00 1,284.00
003
[SSCM 301.2(v)]:
Excavation in ordinary soil
E1-
(vehicle measurement) Cu.m 1,205.00 1,156.00 1,156.00 1,254.00 1,156.00
004
[SSCM 301.2(v)]:
Excavation in medium soil
E1-
(cutting measurement) Cu.m 1,773.00 1,701.00 1,701.00 1,846.00 1,701.00
005
[SSCM 301.2(iv)]:
Excavation in medium soil
E1-
(vehicle measurement) Cu.m 1,507.00 1,446.00 1,446.00 1,569.00 1,446.00
006
[SSCM 301.2(v)]:
Excavation in hard soil
E1-
(cutting measurement) Cu.m 2,643.00 2,534.00 2,534.00 2,751.00 2,534.00
007
[SSCM 301.2(vII)]:
Excavation in hard soil
E1-
(vehicle measurement) Cu.m 3,039.00 2,914.00 2,914.00 3,164.00 2,914.00
008
[SSCM 301.2(vII)]:
Excavation in unclassified
E1-
soil (cutting measurement) Cu.m 1,918.00 1,840.00 1,840.00 1,997.00 1,840.00
009
[SSCM 301.2a(I)]:
See item nos. From E1-027 on page 27 of HSR published by RDA for roadway excavation
Note
using machinery.
Excavation in soft rock
E1-
(cutting measurement) Cu.m 2,860.00 2,742.00 2,742.00 2,978.00 2,742.00
010
[SSCM 301.2(vII)]:
Excavation in mud/marshy
E1-
material (cutting
010 Cu.m 2,208.00 2,117.00 2,117.00 2,299.00 2,117.00
measurement) [SSCM
A
301.2(vII)]:
Excavation pit/trench for
foundation in ordinary soil
not exceeding 1.5 m. Deep
including levelling and
ramming bottom, excavation
E1-
material deposited at site Cu.m 1,773.00 1,701.00 1,701.00 1,846.00 1,701.00
011
within 25 m or as directed. *
(shoring, dewatering, if
necessary, shall be paid
separately) [SSCM 302.1-
302.3]:
* See general notes 24(2) of HSR published by RDA for details regarding additional excavation
required for working space.
E1- Ditto - medium soil, -do - do
Cu.m 2,208.00 2,117.00 2,117.00 2,299.00 2,117.00
012 -:
E1-
Ditto - hard soil, -do - do -: Cu.m 3,077.00 2,950.00 2,950.00 3,204.00 2,950.00
013
E1- Ditto - in unclassified soil, -
Cu.m 2,353.00 2,256.00 2,256.00 2,449.00 2,256.00
014 do - do -:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 146
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
E1- Ditto - mud/marshy
Cu.m 2,643.00 2,534.00 2,534.00 2,751.00 2,534.00
015 material, -do - do -:
* Item nos. E1-016 to E1-018 deleted
Excavating soft rock, not
E1-
exceeding 1.5m depth Cu.m 3,512.00 3,367.00 3,367.00 3,657.00 3,367.00
019
[SSCM 301.2 (II) ]:
* Note: excavating rock for foundation to be paid on S.S.R.
* Item no. E1-020 deleted
E1-
Piling available soil: Cu.m 217.00 208.00 208.00 226.00 208.00
021
E1- Loading available soil to a
Cu.m 286.00 274.00 274.00 298.00 274.00
022 tractor or equivalent:
Excavating rock, requiring
E1-
blasting, for roadway for
023
boulders (excluding dozing Cu.m 3,369.00 3,368.00 3,369.00 3,370.00 3,367.00
(ame
away [ SSCM 301.2 (IIi) &
nd.)
306.1 - 306.4 ] :
E1- Boulders sledging, piling,
Cu.m 4,038.00 3,929.00 3,965.00 4,183.00 3,875.00
024 etc..
E1-
Rock requiring blasting: Cu.m 4,444.00 4,372.00 4,444.00 4,480.00 4,336.00
025
E1-
026 Rock requiring blasting and
Cu.m 5,712.00 5,585.00 5,639.00 5,811.00 5,549.00
(ame piling:
nd)
Roadway excavation in
unclassified soil using
E1-
machinery excluding Cu.m 321.00 321.00 321.00 322.00 321.00
027
loading and piling. (Cutting
measurement)
Loading material by
E1- machinery in roadway
Cu.m 197.00 197.00 197.00 198.00 197.00
028 excavation (cutting
measurement ) :
Trimming / cambering by
E1-
motor grader (cutting Cu.m 45.00 45.00 45.00 45.00 45.00
029
measurement) :
E1- Trimming / cambering by
029 motor grader (cutting Sq.m 9.00 9.00 9.00 9.00 9.00
A measurement) :
7.3.3. Aggregate / rubble piling including loading
Sledding available rock 150-
A1-
225 mm rubble including Cu.m 3,187.00 3,132.00 3,169.00 3,295.00 3,060.00
001
piling & loading :
Blasting etc. & piling 150-
A1-
225 mm rubble excluding Cu.m 5,676.00 5,549.00 5,585.00 5,784.00 5,513.00
002
loading :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 147
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
A1- Blasting sledging etc. &
002 piling 150-225mm rubble
A using compressor & hand- Cu.m N/A N/A N/A N/A N/A
(NE held drills excluding loading
W) :
Blasting etc. & piling
A1-
100mm aggregate, Cu.m N/A N/A N/A N/A N/A
003
excluding loading :
Blasting etc. & piling 75 mm
A1-
aggregate, excluding loading Cu.m N/A N/A N/A N/A N/A
004
:
Blasting etc. & piling 50 mm
A1-
aggregate, excluding loading Cu.m N/A N/A N/A N/A N/A
005
:
Blasting etc. & piling 37.5
A1-
mm aggregate, excluding Cu.m N/A N/A N/A N/A N/A
006
loading :
Blasting etc. & piling 25 mm
A1-
aggregate, excluding loading Cu.m N/A N/A N/A N/A N/A
007
:
Blasting etc. & piling 19 mm
A1-
aggregate, excluding loading Cu.m N/A N/A N/A N/A N/A
008
:*
* Prior approval of the p.dd should be obtained for the use of 19 mm hand broken aggregate.
50 mm aggregate, single size
crusher production
A1-
excluding piling and loading Cu.m 5,477.00 4,770.00 4,594.00 3,534.00 4,417.00
009
[SSCM404.1-406.1: table
1701-4]:
37.5 mm aggregate, single
size crusher production
A1-
excluding piling and loading Cu.m 5,565.00 4,859.00 4,682.00 3,622.00 4,505.00
010
[SSCM404.1-406.1: table
1701-4]:
19 mm aggregate, single size
crusher production
A1-
excluding piling and loading Cu.m 5,830.00 5,124.00 4,947.00 4,064.00 4,770.00
011
[SSCM404.1-406.1]: table
1701-4]:
12.5 mm aggregate, single
size crusher production
A1-
excluding piling and loading Cu.m 5,124.00 4,594.00 4,417.00 3,180.00 4,594.00
012
[SSCM404.1-406.1: table
1701-4]:
Plant production aggregate for dense graded aggregate base course
Aggregate 37.5 mm,
A1- downgraded (SSCM - table
Cu.m 5,654.00 4,417.00 4,240.00 3,357.00 4,240.00
013 1701.5) excluding piling &
loading:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 148
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Crusher fines 6.3 mm down,
A1-
excluding piling & loading Cu.m 4,417.00 3,710.00 3,534.00 2,120.00 3,710.00
014
for 1.0 cu.m :
Aggregate 19 mm for seal
A1- coat treatments as per SSCM
Cu.m 6,030.00 5,324.00 5,147.00 4,264.00 4,970.00
015 table 1701-8, including - do
-
Aggregate 12.5 mm for seal
A1- coat treatments as per SSCM
016 table 1701-8, including - do Cu.m 5,324.00 4,794.00 4,617.00 3,380.00 4,794.00
-
Blended aggregate for
rectification overlay, with
37.5 mm single size
aggregate and 19 mm & 12.5
A1-
mm crusher aggregate mixed Cu.m 5,482.00 4,761.00 4,576.00 3,461.00 4,453.00
017
in the volume ratio of 7:2:1
including mixing and
loading.(piling to pay
separately):*
Prior approval of the p.dd should be obtained for the use of blended aggregate in rectification overlay
construction work.
A1-
Piling available aggregate: Cu.m 226.00 226.00 226.00 235.00 217.00
018
A1-
Piling available rubble: Cu.m 452.00 452.00 452.00 470.00 434.00
019
A1- Loading available aggregate
Cu.m 434.00 416.00 416.00 452.00 416.00
020 /rubble:
7.3.4. Approved earth filling & compaction
Rates for borrow earth supply given under item codes EW1-001 & EW1-011 n this schedule is
based on manual excavation and intended for small works involving less than 300 Cu.m. in the
Note case of borrow earth supply exceeds 300 Cu.m(for the whole project), rates based on machine
excavation as per B0-201, B0-202, EW1-013 or EW1-014 shall be adopted. For any deviations
the procurement procedure given in "general notes" of HSR published by RDA, shall be followed.
Approved soil (type I & II
materials) excavation for
EW bases & shoulder
1- construction including Cu.m 2,078.00 1,994.00 1,994.00 2,163.00 1,994.00
001 loading and piling. (loose
volume) [SSCM 601.1 to
601.4] :
EW
Spreading piled approved
1- Cu.m 301.00 290.00 290.00 312.00 290.00
soil (loose volume):
002
Office of the Deputy Chief Secretary - Engineering Services, NP Page 149
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Approved soil spread &
EW rolled including roller hire
1- charges, fuel & watering Cu.m 620.00 608.00 608.00 631.00 608.00
003 (loose volume)* [SSCM
601.1 to 4]:
* See general notes section 26.4 of HSR published by RDA for rate on compacted volume.
The items EW1-003 or EW1-004 on manual spreading should be adopted on approval by pd/ce
Not
for small works only. When machinery is used for spreading and compaction, ew1-003a shall be
e
adopted.
EW Approved soil spread &
1- rolled using machinery
003 including motor grader &
Cu.m 309.00 309.00 309.00 309.00 309.00
A roller hire charges, fuel &
(NE watering (loose volume)*
W) [SSCM 601.1 to 4]:
* See general notes section 26.4 of HSR published by RDA for rate on compacted volume.
Approved soil spread &
rolled in strips where
average width is less than 1.2
EW
meters for road widening,
1- Cu.m 765.00 754.00 754.00 776.00 754.00
including roller hire charges,
004
fuel & watering (loose
volume)* [SSCM 601.1 to
4]:
* See general notes section 26.4 of HSR published by RDA for rate on compacted volume. Assuming
50 cu.m compaction per day
EW
1- Deleted
005
Approved soil spread &
compacted in places behind
abutments and structures,
EW
shoulders above sub base
1- Cu.m 701.00 686.00 686.00 716.00 686.00
level and in service line
006
trenches, using 1/2-to-1-ton
vibrating roller including
watering (loose volume) :
* See general notes section 26.4 of HSR published by RDA for rate on compacted volume.
Approved soil spread &
EW compacted in 150 to 225 mm
1- thick layers using machine Cu.m 664.00 650.00 650.00 679.00 650.00
007 rammer at narrow places
(loose volume) :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 150
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Spreading, leveling and
compacting manually using
EW
standard cast iron stamper or
1- Cu.m 977.00 937.00 937.00 1,018.00 937.00
equivalent and filling in 150
008
- 225 mm thick layer (loose
volume) :
Trimming, leveling and
EW compaction of original
1- ground/subgrade to 100% Sq.m 100.00 100.00 100.00 100.00 100.00
009 std. Density. [SSCM 304.3
c] :
Trimming, leveling and
EW
compaction of original
1- Sq.m 91.00 91.00 91.00 91.00 91.00
ground/subgrade to 95% std.
010
Density. [SSCM 304.3 c] :
Approved soil excavation
EW for embankment filling
1- including loading and piling Cu.m 1,812.00 1,739.00 1,739.00 1,886.00 1,739.00
011 (loose volume) [SSCM
601.1 to 601.4] :
EW
1- Deleted
012
Note Type 1 soil, Type II soil royalty included
Approved soil (type I & II
materials) excavation using
EW machinery for bases &
1- shoulder construction Cu.m 3,751.00 2,681.00 2,681.00 1,639.00 2,681.00
013 including loading, transport
and piling (loose volume)
[SSCM 601.1 to 601.4] :
Approved soil (type I & II)
excavation using machinery
EW
for embankment filling
1- Cu.m 3,574.00 2,505.00 2,505.00 1,463.00 2,505.00
including loading, transport
014
and piling (loose volume)
[SSCM 601.1 to 601.4] :
EW
Grading and spreading by
1- Cu.m 112.00 112.00 112.00 112.00 112.00
motor grader:
015
Data for output in 6 hours spreading & compaction
7.3.5 Rubble pitching / paving
(Rubble to be paid separately)
P1- Pitched paving 225 mm
Sq.m 551.00 551.00 551.00 573.00 529.00
001 thick :
P1- Pitched paving 150 mm
Sq.m 413.00 413.00 413.00 430.00 397.00
002 thick :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 151
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
P1-
Flat paving 225 mm thick : Sq.m 366.00 366.00 366.00 381.00 352.00
003
P1-
Flat paving 150 mm thick : Sq.m 275.00 275.00 275.00 286.00 264.00
004
7.3.6 Aggregate spreading & compaction
Cost of watering to be deducted from rate if not carried out under the relevant items.
Spreading, Watering &
Rolling 100 mm Aggregate
M1-
including Hire Charges Of Cu.m 1,411.00 1,411.00 1,411.00 1,434.00 1,389.00
001
Roller. (Loose Volume)
[SSCM 304.3(D),(E)] :
Breaking Road Surface To
M1- 50 mm Depth By Hand,
Sq.m 159.00 153.00 153.00 165.00 152.00
002 Screen & Replace Old
Aggregate :
Scarifying Road Surface To
M1- 50 mm Depth By Roller,
Sq.m 126.00 124.00 124.00 129.00 123.00
003 Screen & Replace Old
Aggregate :
Spreading & Compacting 50-
19 mm New Aggregate By
M1-
Roller including Watering Cu.m 2,152.00 2,138.00 2,138.00 2,196.00 2,108.00
004
Hire, Etc. (Loose
Volume)[SSCM 403.3(C)]
Breaking 50 mm Additional
M1-
Depth By Hand Screening & Sq.m 94.00 91.00 91.00 98.00 91.00
005
Replacing Old Aggregate:
Scarifying 50 mm Additional
M1-
Depth With Roller, Screening Sq.m 102.00 101.00 101.00 104.00 100.00
006
& Replacing Old Aggregate :
Spreading Watering &
Compacting 50-19 mm
M1- Aggregate in Edge
Cu.m 2,756.00 2,756.00 2,756.00 2,785.00 2,726.00
007 Correction Using Roller
including Hire, Etc. (Loose
Volume)[SSCM 1103.3] :
Spreading Watering &
Compacting 50-19 mm
M1- Aggregate in Edge
Cu.m 2,226.00 2,226.00 2,226.00 2,256.00 2,196.00
008 Correction Using Roller
including Hire, Etc. (Loose
Volume)[SSCM 1103.3] :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 152
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Spreading & Compacting 50-
19 mm Aggregate By 8-10
M1- Ton Roller After Applying
Cu.m 1,992.00 1,992.00 1,992.00 2,022.00 1,962.00
009 Tack Coat in Overlay (Loose
Volume)(Tack Coat Paid
Separately):
Water Bound Macadam -
Spreading Watering &
Compacting 50-25 mm
Aggregate And Filling The
Voids To Refusal With
M1- Crusher Fines By Watering
Cu.m 9,320.00 8,530.00 8,333.00 7,161.00 8,122.00
010 And Rolling To Form A
Water Bound Macadam Base
Excluding Transport For
Aggregates And Fines.
(Loose Volume)[SSCM
404.1] :
Dry Bound Macadam -
Spreading Watering &
Compacting 50-25 mm
Aggregate And Filling The
Voids To Refusal With
M1- Crusher Fines By Rolling
Cu.m 8,942.00 8,151.00 7,955.00 6,783.00 7,744.00
011 With Vibration Roller To
Form A Dry Bound
Macadam Base Excluding
Transport For Aggregates
And Fines. (Loose
Volume)[SSCM 404.1] :
* M1-012 : Deleted
Dense Graded Aggregate
Base [Aggregate Base
Course] including Piling,
Spreading Watering &
M1- Compacting Graded 37.5
012 mm Aggregate To Form A
A Dense Aggregate Base Cu.m 6,223.00 4,986.00 4,809.00 3,928.00 4,808.00
(NE Using Machinery including
W) Motor Grader & Roller Hire
Charges Transport Of
Aggregates To Be Paid
Separately (Loose
Volume)[SSCM 404.1] :
*For the rate on compacted volume, increase loose volume rate by 42%. if measurement is on end
product, piling cost of aggregate as per A1-018 Shall Be Deducted.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 153
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Dense Graded Aggregate
Base [Aggregate Base
Course] including Piling,
Spreading Watering &
Compacting Graded 37.5
mm Aggregate To Form A
M1-
Dense Aggregate Base in Cu.m 7,860.00 6,623.00 6,446.00 5,594.00 6,414.00
013
Strips, Average Width Not
Exceeding 1.2 Meters, For
Road Widening. Excluding
Transport Of Aggregates
(Loose Volume)* [SSCM
405.1 To 4] :
For the rate on compacted volume, increase loose volume rate by 42%. If measurement is on end
product, piling cost of aggregate as per A1-018 shall be deducted.
The item m1-013 on manual labour should be adopted on approval by pd / ce for small works
NO
only. When machinery is used for spreading and compaction, M1-012A / M1-013a shall be
TE
adopted depending on site situation.
Graded 37.5 Aggregate Base
Course Material including
Piling, Spread & Rolled in
M1-
Strips, Average Width Not
013
Exceeding 1.2 Meter Using
A Cu.m 6,298.00 5,060.00 4,883.00 4,004.00 4,881.00
Machinery including Motor
(NE
Grader & Roller Hire
W)
Charges, Fuel & Watering
(Loose Volume)* [SSCM
405.1 To 4]:
For the rate on compacted volume, increase loose volume rate by 42%. If measurement is on end
product, piling cost of aggregate As Per A1-018 shall be deducted.
7.3.7 Road Surface Treatment
Transport of Emulsion / Bitumen to be Paid Separately)
Not
Transportation to be included for sand related works
e
Bitumen Surfacing First
Coat Using 2 Ltr/Sq.m
including Blinding With
S1-
Sand At The Rate Of 125 Sq.m 125.00 108.00 109.00 120.00 111.00
001
Sq.m/Cu.M [SSCM 503.1]:
(Excluding Cost Of
Bitumen) :
Bitumen Surfacing First
Coat Using 2 Ltr/Sq.m
including Blinding With
S1-
Gravel Where Sand Is Not Sq.m 107.00 105.00 105.00 111.00 102.00
002
Available Within 16km:
(Excluding Cost of Bitumen)
:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 154
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Double Bituminous Surface
Treatment With Hot
Bitumen (Manual) including
S1-
internal Transport (Binder Sq.m 180.00 178.00 178.00 184.00 176.00
003
And Aggregate Paid
Separately) [SSCM 505.1 -
505.5 & Table 505-1] :
Single Bituminous Surface
Treatment With Hot
Bitumen (Manual) including
S1-
internal Transport (Binder Sq.m 98.00 97.00 97.00 100.00 96.00
004
And Aggregate Paid
Separately) [SSCM 505.1 -
505.5 & Table 505-1] :
Double Bituminous Surface
Treatment With Emulsion
S1- (Crs-1) (Manual) including
Sq.m 175.00 173.00 173.00 179.00 171.00
005 internal Transport (Binder
And Aggregate Paid
Separately) :
Single Bituminous Surface
Treatment With Emulsion
S1- (Crs-1) (Manual) including
Sq.m 112.00 111.00 111.00 114.00 110.00
006 internal Transport (Binder
And Aggregate Paid
Separately) :
Bitumen surfacing
subsequent coat using 0.75
ltr/Sq.m including blinding
S1-
with sand @ 125 Sq.m/Cu.m Sq.m 100.00 83.00 84.00 94.00 87.00
007
[SSCM 503.1(B)]:
(Excluding cost of bitumen)
:
Bitumen surfacing
2nd/Subsequent coat using
1.0 ltr/Sq.m including
S1-
blinding at the rate of 125 Sq.m 100.00 83.00 84.00 94.00 87.00
008
Sq.m/Cu,m (new works)
[SSCM 503.1(B)]:
(excluding cost of bitumen)
Bitumen surfacing facing
subsequent coat using 0.75
ltr/Sq.m including blinding
S1- with gravel free of clay
Sq.m 82.00 80.00 80.00 85.00 78.00
009 where sand is not available
within 16 km [SSCM
503.2(B)]: (Excluding cost
of bitumen) :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 155
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Bitumen surfacing
2nd/subsequent coat using
1.0ltr/Sq.m including
blinding with gravel free of
S1-
clay where sand is not Sq.m. 82.00 80.00 80.00 85.00 78.00
010
available within 16km (new
works) [SSCM 503.4(C)]:
(Excluding cost of Bitumen)
:
Emulsion / Cold Bitumen
(Crs-1) Surface Treatment
1st Coat With 3.5 Ltr/Sq.m
S1-
including Blinding With Sq.m 94.00 77.00 78.00 89.00 81.00
011
Sand, @ 125 Sq.m/Cu.m
(Manual): (Excluding Cost
Of Emulsion) :
Emulsion / Cold Bitumen
(Crs-1) Surface Treatment
1st Coat With 3.5 Ltr/Sq.m
S1- (Using Trolley, Emulsion),
Sq.m 73.00 56.00 58.00 67.00 61.00
012 including Blinding With
Sand, @ 125 Sq.m/Cu.m :
(Excluding Cost Of
Emulsion):
Emulsion / Cold Bitumen
(Crs-1) Surface Treatment
Subsequent Coat Using 3.5
S1- Ltr/Sq.m including Blinding
Sq.m 73.00 56.00 58.00 67.00 61.00
013 With Sand, @ 125
Sq.m/Cu.M (Manual):
(Excluding Cost Of
Emulsion) :
Emulsion / Cold Bitumen
(Crs-1) Surface Treatment
Subsequent Coat With 0.75
S1- Ltr/Sq.m (Using Trolley,
Sq.m 65.00 48.00 50.00 59.00 54.00
014 Emulsion), including
Blinding With Sand, @ 125
Sq.m/Cu.m : (Excluding
Cost Of Emulsion) :
Tack Coat Using Emulsion
(Css-1) @ The Rate Of 0.5
Ltr/Sq.m inclusive Of
S1-
Brushing, Cleaning Road Sq.m 21.00 21.00 21.00 22.00 20.00
015
Surface (Manual) [SSCM
502.3]: (Excluding Cost Of
Emulsion) :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 156
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Tack Coat Using Emulsion
(Css-1) @ The Rate Of 0.75
Ltr/Sq.m inclusive of
S1-
Brushing, Cleaning Road l 43.00 42.00 42.00 45.00 41.00
016
Surface (Manual) [SSCM
502.3]:(Excluding Cost of
Emulsion) :
Tack Coat Using Emulsion
(Css-1) @ The Rate Of 0.75
Ltr/Sq.m inclusive of
S1-
Brushing, Cleaning Road Sq.m 21.00 21.00 21.00 22.00 20.00
017
Surface (Manual) [SSCM
502.1-502.3]: (Excluding
Cost of Emulsion) :
Tack Coat With 30% Cut
Back Bitumen Using 0.5
Ltr/Sq.m including Brushing
S1-
and Cleaning Road Surface Sq.m 72.00 72.00 72.00 74.00 71.00
018
(Manual): [SSCM 502.1-
502.3]: (Excluding Cost of
Bitumen) :
Tack Coat With 30% Cut
Back Bitumen Using 0.5
S1- Ltr/Sq.m including Brushing
l 145.00 145.00 145.00 149.00 142.00
019 And Cleaning Road Surface
(Manual) (Excluding Cost
Of Bitumen) :
Tack coat with 30% cut back
bitumen using 0.75 Ltr/Sq.m
including brushing and
S1-
cleaning road surface Sq.m 87.00 87.00 87.00 89.00 85.00
020
(MANUAL) [SSCM
503.4(D)]: (Excluding cost
of bitumen)
Rolling over blinding
material spread over
S1- subsequent bitumen
Sq.m 18.00 18.00 18.00 18.00 18.00
021 surfacing using diesel roller
(8-10 Tons) [SSCM
503.4(D)]:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 157
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Prime Coat With
Emulsion/Cold
Bitumen(Css-1) Using 1
Ltr/Sq.m including Blinding
S1- With Sand At The Rate Of
Sq.m 54.00 45.00 45.00 51.00 47.00
022 250 Sq.m/Cu.m And
Brushing Cleaning And
Moistening Road Surface :
(Excluding Cost Of
Emulsion) :
Prime Coat With
Emulsion/Cold
Bitumen(Css-1) Using 1
S1- Ltr/Sq.m Without Blinding,
Sq.m 22.00 21.00 21.00 23.00 21.00
023 But inclusive Of Brushing,
Cleaning And Moistening
Road Surface : (Excluding
Cost Of Emulsion) :
Prime Coat With 30% Cut
Back Bitumen Using 1
Ltr/Sq.m including Blinding
With Sand At The Rate Of
S1-
250 Sq.m/Cu.M And Sq.m 136.00 127.00 128.00 134.00 128.00
024
Brushing, Cleaning And
Moistening Road Surface :
(Excluding Cost Of
Bitumen) :
Prime Coat With 30% Cut
Back Bitumen Using 1
Ltr/Sq.m Without Blinding
S1-
But inclusive Of Brushing, Sq.m. 103.00 102.00 102.00 104.00 101.00
025
Cleaning And Moistening
Road Surface : (Excluding
Cost Of Bitumen) :
S1- Sweeping Over Tarred
Sq.m. 6.00 6.00 6.00 7.00 6.00
026 Surface to Arrest Bleeding:
Application Of Asphalt
Emulsion For Surface
S1- Treatment Using Crs - 1
l 12.00 12.00 12.00 12.00 12.00
027 (Using Plant) "Rate Per
Liter" (Excluding Cost Of
Emulsion) :
Blinding The Bitumen
Surface With Sand At The
S1-
Rate Of 125 Sq.m Per 1 Sq.m 65.00 48.00 49.00 58.00 53.00
028
Cu.m Using Material From
Stock Pile :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 158
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Single Bituminous Surface
Treatment With Emulsion
(Crs-1) Using Plant. (Binder
S1- And Aggregate Paid
Sq.m 89.00 89.00 89.00 89.00 88.00
029 Separately) (Rate To include
Transport Cost Of
Aggregate Up To 16 Kms)
[SSCM 505.5(B)]
Double Bituminous Surface
Treatment With Emulsion
(Crs-1) Using Plant. (Binder
S1- And Aggregate Paid
Sq.m 179.00 178.00 178.00 179.00 178.00
030 Separately) (Rate To include
Transport Cost Of
Aggregate Up To 16 Kms)
[SSCM 505.5(E)]
Supply, Lay and Compact
Asphalt Premix Concrete
(19 mm, Binder (80/100) 5%
Mix) -Dense (Plant Made) in
Wearing Surface Of Small
S1- Works Such As Bridge
mt. 19,645.00 19,604.00 19,604.00 19,707.00 19,574.00
031 Decking, Reinstatement Of
Trenches Etc. (Transport Of
Aggregate* For Premix And
Transport Of Premix To Be
Paid Separately.) [SSCM -
506] :
(For Other Binder Contents See General Notes - Clause 29.8 of HSR published by RDA) :
Average 0.6270 Cu.m Of Aggregate Required For 1.0 Metric Ton Of Premix (All Types)
Supply, Lay And Compact
Asphalt Bound Premix (37.5
mm, Binder(80/100) 3.53%
Mix) -Dense Base Material
(Plant Made) in Of Small
S1- Works Such As Bridge
mt 3,645.00 3,604.00 3,604.00 3,707.00 3,574.00
032 Decking, Reinstatement Of
Trenches Etc. (Transport Of
Aggregate* For Premix And
Transport Of Premix To Be
Paid Separately.) [SSCM -
506] :
(For Other Binder Contents See General Notes - Clause 29.8 of HSR published by RDA)
Average 0.6270 Cu.m of Aggregate Required For 1.0 Metric Ton of Premix (All Types)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 159
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Supply, Lay And Compact
Asphalt Concrete Cold Mix
(19 mm, 20% Cut Back With
Binder(80/100) 5.5% Mix) -
Dense (Plant Made) in Small
S1- Works Such As Bridge
mt 3,645.00 3,604.00 3,604.00 3,707.00 3,574.00
033 Decking, Reinstatement Of
Trenches Etc. (Transport Of
Aggregate* For Premix and
Transport of Premix To Be
Paid Separately.) [SSCM -
506] :
(For Other Binder Contents See General Notes - Clause 29.8 of HSR published by RDA)
* Average 0.6270 Cu.m Of Aggregate Required For 1.0 Metric Ton of Premix (All Types)
Supply, Lay and Compact
Asphalt Concrete Cold Mix
with Emulsion Css-1(6.67%
By Wgt of Agg. 19 mm) -
Dense (Plant Made) in Small
S1-
Works Such as Bridge
033 mt 3,645.00 3,604.00 3,604.00 3,707.00 3,574.00
Decking, Reinstatement of
A
Trenches Etc. (Transport Of
Aggregate* For Premix and
Transport of Premix to Be
Paid Separately.) [SSCM -
506]:
(For Other Binder Contents See General Notes - Clause 29.8 of HSR published by RDA)
Lay And Compact Asphalt
Premix Using Paver (Cost of
S1- Premix, Aggregate
mt. 2,123.00 2,111.00 2,113.00 2,139.00 2,105.00
034 Transport* And Premix
Transport to Be Paid
Separately.) :
* Average 0.6270 Cu.m of Aggregate Required For 1.0 Metric Ton of Premix (All Types)
Bitumen Surfacing (Sand
Sealing - Manual) Using
Emulsion (Crs-1) At the
Rate Of 1ltr. /Sq.m.
S1- including Preparing Surface,
035 Blinding with Sand at The
(A Rate Of 4 Cu.M/500 Sq.m
Sq.m 80.00 63.00 64.00 73.00 68.00
me And Pressing with
nde Improvised Hand Rallers:
d) (Patching Pot Holes If
Necessary & External
Transport to Pay Separately)
(Excluding Cost of
Emulsion):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 160
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
S1- Patching Minor Pot Holes
035 Using Sand Emulsion Mix
A 1:8 Where Necessary, Prior Sq.m. 24.00 23.00 23.00 24.00 23.00
(NE To Sand Sealing. (Excluding
W) Cost of Emulsion):
Sand Sealing with Emulsion
Crs-1 At the Rate Of 1
Ltr/Sq.m Using Plant,
including Brushing,
S1-
Cleaning, Blinding with
036
Sand @ Of 125 Sq.m/Cu.M,
*
And Rolling with Pneumatic
(A Sq.m. 84.00 66.00 68.00 77.00 72.00
Roller and Internal
ME
Transport [SSCM 504]:
ND
(Excluding Cost of
ED)
Emulsion) (Patching Pot
Holes If Necessary &
External Transport to Pay
Separately)
*NO The above rate is applicable only if chip spreader and pneumatic roller are used for the
TE: construction. otherwise, Approved SSR should be adopted.
Reconstruct base with
penetration macadam using
nominal size 50 mm
aggregate and 19 mm key
aggregate from stock piles, to
S1-
a compacted thickness of 75 Sq.m. 239.00 237.00 237.00 244.00 234.00
037
mm, on existing pavements.
[SSCM 406] (cost of binder,
and aggregate including
transport to be paid
separately):
Reconstruct Base with
Penetration Macadam Using
Nominal Size 37.5 mm
Aggregate And 12.5 mm Key
Aggregate from Stock Piles,
S1- To A Compacted Thickness
Sq.m 168.00 166.00 166.00 171.00 164.00
038 Of 55 mm, On Existing
Pavements. [SSCM 406]
(Cost of Binder, And
Aggregate including
Transport to Be Paid
Separately):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 161
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Correction Of Corrugations,
Depression and Cambering
Road Surfaces Using Asphalt
Concrete Compacted by
S1- Vibrating Roller including
mt. 3,004.00 2,936.00 2,936.00 3,072.00 2,927.00
039 internal Transport.
(Application Of Tack Coat
and Supply of Asphalt
Concrete to Be Paid
Separately):
Sand Sealing with Emulsion
Crs-2 At the Rate of 0.8
S1- Ltr/Sq.m Using Plant, And
040 Blinding with Sand at The
* Rate Of 125 Sq.m/Cu.M on
(A D.B.S.T./S.B.S.T. (Triple Sq.m. 84.00 66.00 68.00 77.00 72.00
ME Seal) including internal
ND Transport [SSCM 504]:
ED) (Binder Transport to Site to
Pay Separately) (Excluding
Cost of Emulsion):
This item should be used only for sand sealing on road surface after DBST / SBST work and use
Not
of pneumatic roller is essential. if emulsion and / or the rate of application or the method of sand
e
spreading to be changed, S.S.R. shall be prepared and approved.
7.3.8 Road Surface Maintenance
Internal transport of hot bitumen up to 16 km
Not Transportation to be included for sand related works
e
Patching With Hot Bitumen
MN Using 14 Litters Per 1/2 km
1- (SSCM 1102.1 - 1102.3) 1/2 km 2,676.00 2,437.00 2,456.00 2,644.00 2,453.00
001 (Excluding Cost of
Bitumen):
Patching With Hot Bitumen
MN
Using 21 Litters Per 1/2 km
1- 1/2 km 4,014.00 3,655.00 3,685.00 3,966.00 3,680.00
(Excluding Cost of
002
Bitumen):
Patching With Hot Bitumen
MN
Using 28 Liters Per 1/2 km
1- 1/2 km 5,352.00 4,874.00 4,913.00 5,289.00 4,907.00
(Excluding Cost of
003
Bitumen):
Patching With Hot Bitumen
MN
Using 35 Liters Per 1/2 km
1- 1/2 km 6,691.00 6,093.00 6,142.00 6,611.00 6,133.00
(Excluding Cost of
004
Bitumen):
MN Patching with hot bitumen
1- using 42 liters per 1/2 km 1/2 km 8,029.00 7,311.00 7,370.00 7,933.00 7,360.00
005 (excluding cost of bitumen)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 162
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Patching With Hot Bitumen
MN
Using 49 Liters Per 1/2 km
1- 1/2 km 9,367.00 8,530.00 8,598.00 9,255.00 8,587.00
(Excluding Cost of
006
Bitumen):
Patching With Hot Bitumen
MN
Using 56 Liters Per 1/2 km
1- 1/2 km 10,705.00 9,748.00 9,827.00 10,578.00 9,814.00
(Excluding Cost of
007
Bitumen):
Extensive Patching for
MN
Every Additional 7 Ltrs. Hot
1- 1/2 km 1,338.00 1,218.00 1,228.00 1,322.00 1,226.00
Bitumen: (Excluding Cost of
008
Hot Bitumen):
Patching With Cold Bitumen
MN
(Crs-1) Using 14 Liters Per
1- 1/2 km 1,670.00 1,431.00 1,451.00 1,601.00 1,486.00
1/2 km: (Excluding Cost of
009
Cold Bitumen):
Patching With Cold Bitumen
MN
(Crs-1) Using 21 Liters Per
1- 1/2 km 2,506.00 2,147.00 2,177.00 2,401.00 2,229.00
1/2 km: (Excluding Cost of
010
Cold Bitumen):
Patching With Cold Bitumen
MN
(Crs-1) Using 28 Liters Per
1- 1/2 km 3,341.00 2,863.00 2,902.00 3,202.00 2,972.00
1/2 km: (Excluding Cost of
011
Cold Bitumen):
Patching With Cold Bitumen
MN
(Crs-1) Using 35 Liters Per
1- 1/2 km 4,177.00 3,579.00 3,628.00 4,002.00 3,715.00
1/2 km: (Excluding Cost of
012
Cold Bitumen):
Patching With Cold Bitumen
MN
(Crs-1) Using 42 Liters Per
1- 1/2 km 5,012.00 4,295.00 4,354.00 4,803.00 4,458.00
1/2 km: (Excluding Cost of
013
Cold Bitumen):
Patching With Cold Bitumen
MN
(Crs-1) Using 49 Liters Per
1- 1/2 km 5,848.00 5,011.00 5,080.00 5,603.00 5,201.00
1/2Km: (Excluding Cost of
014
Cold Bitumen):
Patching With Cold Bitumen
MN
(Crs-1) Using 56 Liters Per
1- 1/2 km 6,683.00 5,727.00 5,805.00 6,404.00 5,944.00
1/2 km: (Excluding Cost of
015
Cold Bitumen):
Extensive Patching for
MN Every Additional 7 Ltrs.
1- Cold Bitumen Crs-1: 1/2 km 835.00 715.00 725.00 800.00 743.00
016 (Excluding Cost of Cold
Bitumen):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 163
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
MN
50 mm - 19 mm Aggregate
1- Cu.m 6,389.00 6,317.00 6,317.00 6,534.00 6,245.00
Roller Patching:
017
MN
50 mm - 19 mm Aggregate
1- Cu.m 7,201.00 7,128.00 7,128.00 7,489.00 6,912.00
Stamped Patching:
018
7.3.9 Road side and drainage system (SSCM 701.3)
(*Rate to include spreading the resulting materials suitably in the vicinity unless otherwise directed)
DR
Cutting New Side Drains in
1- Cu.m 1,186.00 1,176.00 1,176.00 1,231.00 1,140.00
Ord. Soil: *
001
DR
Cutting New Side Drains in
1- Cu.m 1,638.00 1,629.00 1,629.00 1,702.00 1,575.00
Med. Soil: *
002
DR
Cutting New Side Drains in
1- Cu.m 2,091.00 2,082.00 2,082.00 2,173.00 2,010.00
Hard Soil: *
003
DR
Cutting New Side Drains in
1- Cu.m 2,317.00 2,308.00 2,308.00 2,408.00 2,227.00
Soft Rock: *
004
DR
Cutting New Side Drains in
1- Cu.m 1,638.00 1,629.00 1,629.00 1,702.00 1,575.00
Unclassified Soil: *
005
Cutting Side Drains of Std.
DR Dimensions in Unclassified
1- Soil Using Machine (Back
Cu.m 777.00 774.00 774.00 795.00 758.00
005 Hoe J.C.B.) including
A Shaping, Trimming and
Levelling Bottom Manually.
DR
Cutting New Side Drains in
1- Cu.m 5,617.00 5,536.00 5,608.00 5,735.00 5,463.00
Rock: *
006
Turfing (Excluding royalty,
DR
transport and watering &
1- Sq.m 290.00 279.00 279.00 301.00 279.00
maintenance) [SSCM
007
802.3a]:
Watering & Maintaining
DR
Ture for Three Months
1- Sq.m 360.00 352.00 352.00 369.00 352.00
including Transport of
008
Water:
DR
Levelling & Trimming
1- Sq.m 34.00 33.00 33.00 35.00 33.00
Earth: *
009
DR Clearing Silt Ect. From
1- Kerbs & Channels [SSCM m 20.00 20.00 20.00 21.00 20.00
010 1205.3]: *
Office of the Deputy Chief Secretary - Engineering Services, NP Page 164
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Cutting Scupper Drains on
Any Soil Other Than Rock
DR
to An Average Width Of
1- m 145.00 145.00 145.00 150.00 139.00
0.75m With Proper Gradient
011
and Ave. Depth Of 100 mm
[SSCM 1304.3]: *
DR
Clearing & Desilting of
1- No. 426.00 409.00 409.00 443.00 409.00
Culverts [SSCM 1303.3]: *
012
DR Levelling Chocked Culverts
1- (With Head Room > 1 M**): Cu.m. 1,773.00 1,701.00 1,701.00 1,845.00 1,701.00
013 *
** If the culvert head room is less than 1 m, work shall be carried out on day works basis.
Cleaning Desilting Existing
Side Drains and Lead Up
DR
Drains to Proper Shape and
1- m 52.00 50.00 50.00 54.00 50.00
Gradient and Transport of
014
Excavated Materials from
Road Side Up To 100m: *
DR
Clearing inlets & Outlets of
1- No. 384.00 368.00 368.00 399.00 368.00
Culverts: *
015
7.3.10 Bridges, Culverts & Retaining Walls Etc.
Not Transportation to be included for sand related works
e
ST1 Demolishing Dry Coursed
- Masonry including Stacking Cu.m 5,251.00 5,070.00 5,070.00 5,469.00 5,034.00
001 or Loading. [SSCM 202.2]:
Demolishing Coursed
ST1
Masonry in Cement Mortar
- Cu.m 6,121.00 5,903.00 5,903.00 6,374.00 5,867.00
including Stacking or
002
Loading. :
Demolishing Random
ST1
Rubble Masonry in Cement
- Cu.m 2,680.00 2,643.00 2,643.00 2,788.00 2,571.00
Mortar including Stacking or
003
Loading. :
Random Rubble Masonry,
150-225 mm Rubble in
ST1
Approved Cements & Sand
- Cu.m 19,347.00 18,200.00 17,533.00 17,024.00 17,382.00
Mortar 1:6 (Excluding
004
Transport of Rubble &
Piling) [SSCM 1006.3]:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 165
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Random Rubble Masonry,
150-225 mm Rubble in
ST1
Approved Cements & Sand
- Cu.m 19,985.00 18,838.00 18,171.00 17,662.00 18,020.00
Mortar 1:5 (Excluding
005
Transport of Rubble &
Piling) [SSCM 1006.3]:
Random Rubble Masonry, in
ST1
Approved Cements & Sand
- Cu.m 14,106.00 13,542.00 13,650.00 14,307.00 13,498.00
Mortar 1:6 With Available
006
Rubble 150-225 mm:
Random Rubble Masonry, in
ST1
Approved Cements & Sand
- Cu.m 14,743.00 14,179.00 14,288.00 14,945.00 14,136.00
Mortar 1:6 With Available
007
Rubble 150-225 mm:
ST1 Dry Masonry with Available
- Heavy Rubble or Boulders Cu.m 7,424.00 7,243.00 7,243.00 7,606.00 7,153.00
008 [SSCM 1006.3(B)]:
Dry Random Masonry with
ST1
Rubble 150-225 mm
- Cu.m 10,709.00 10,034.00 9,328.00 8,556.00 9,256.00
Excluding Transport of
009 Rubble & Piling):
ST1 Dry Random Masonry with
- Available Rubble 150-225 Cu.m 5,939.00 5,795.00 5,795.00 6,084.00 5,722.00
010 mm:
ST1 Packing Available Rubble
- and Aggregate Filter Layers Cu.m 1,556.00 1,493.00 1,493.00 1,619.00 1,493.00
011 Behind Masonry Walls:
Clay Puddled & Laid Behind
ST1
Masonry Walls (Excl.
- Cu.m 3,944.00 3,782.00 3,782.00 4,105.00 3,782.00
Transport of Clay) [SSCM
012 705.3]:
Grouting Coursed Stone
ST1 Masonry Joints with
- Approved Cement & Sand Sq.m 659.00 638.00 638.00 669.00 638.00
013 Mortar 1:3 [SSCM 804.2
(C)]:
Grouting Rubble Paving
ST1 with Concrete Class C,
- 1:2:4(19 mm) (Excl. Cu.m 3,265.00 3,091.00 3,075.00 3,139.00 3,074.00
014 Transport of Aggr. For
Concrete & Piling):
ST1 Grouting Rubble Paving
- with Approved Cement & Sq.m 1,098.00 1,061.00 1,061.00 1,111.00 1,063.00
015 Sand Mortar (1:3):
Forming Weep Holes on
ST1- Masonry Construction
No. 546.00 512.00 512.00 546.00 529.00
016 (Labour Only) [SSCM
706.3]:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 166
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Forming Weep Holes Using
P.V.C Pipes of Int. Dia. Not
ST1
Less Than 100 mm.
- m 1,421.00 1,417.00 1,425.00 1,428.00 1,409.00
Complete with Drip ledge
017
And Surround Finish
Smooth:
ST1 Shoring With 37.5 mm
- Thick Class II Timber Sq.m 1,382.00 1,354.00 1,354.00 1,399.00 1,360.00
018 Planks Up To 3 m Depth:
ST1 Supplying & Fixing Class II
Cu.dec
- Timber Struts Etc. For 112.00 107.00 107.00 114.00 108.00
im
019 Shoring Up 3 m Depth:
Supplying & Fixing Class II
ST1
Timber in Shoring Up To 3
- Sq.m 1,661.00 1,621.00 1,621.00 1,684.00 1,630.00
m Depth (Rate Per Area
020
Basis):
ST1
Lifting Soil for Every 1.5m Cu.m /
- 869.00 833.00 833.00 905.00 833.00
Beyond The initial 1.5m: lift
021
ST1 Lifting Wedge Stones Every
Cu.m./
- 1.5 m Beyond The initial 1.5 2,607.00 2,499.00 2,499.00 2,716.00 2,499.00
lift
022 m:
ST1 Lifting Rubble or Concrete
Cu.m./
- 1.5 m Beyond The initial 1.5 1,303.00 1,249.00 1,249.00 1,358.00 1,249.00
lift
023 m:
ST1 Lowering Wedged Stones
Cu.m./
- Every 1.5 m Beyond The 1,738.00 1,666.00 1,666.00 1,810.00 1,666.00
lower
024 initial 1.5m:
ST1 Lowering Rubble or
Cu.m/
- Concrete for Every 1.5 m 869.00 833.00 833.00 905.00 833.00
lower
025 Beyond The initial 1.5 m:
ST1 Rendering 12.5 mm Thick in
- Cement Sand Motar 1:2 Mix Sq.m 1,116.00 1,081.00 1,081.00 1,130.00 1,082.00
026 (Rough):
ST1 Rendering 12.5 mm Thick in
- Cement Sand Motar 1:2 Mix Sq.m 1,306.00 1,265.00 1,265.00 1,320.00 1,269.00
027 (Smooth Finish):
ST1 Rendering 19mm Thick in
- Cement Sand Motar 1:2 Mix Sq.m 1,574.00 1,523.00 1,523.00 1,592.00 1,526.00
028 (Rough):
ST1 Rendering 19 mm Thick in
- Cement Sand Motar 1:2 Mix Sq.m. 1,764.00 1,708.00 1,708.00 1,782.00 1,714.00
029 (Smooth Finish):
ST1 Rendering 12.5 mm Thick in
- Cement Sand Motar 1:3 Mix Sq.m. 1,060.00 1,021.00 1,021.00 1,074.00 1,024.00
030 (Rough):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 167
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
ST1 Rendering 12.5 mm Thick in
- Cement Sand Motar 1:3 Mix Sq.m 1,266.00 1,221.00 1,221.00 1,280.00 1,227.00
031 (Smooth Finish):
ST1 Rendering 19 mm Thick in
- Cement Sand Motar 1:3 Mix Sq.m 1,473.00 1,417.00 1,417.00 1,491.00 1,423.00
032 (Rough):
ST1 Rendering 19 mm Thick in
- Cement Sand Motar 1:2 Mix Sq.m 1,684.00 1,623.00 1,623.00 1,702.00 1,631.00
033 (Smooth Finish):
Grade 10 1:4:8 (50mm)
(Volume Batching) Using
ST1
Crusher Run Aggregate
- Cu.m 20,746.00 19,136.00 18,960.00 18,905.00 19,026.00
(Excl. Transport of
034
Aggregate & Piling)
(Manual) [SSCM 1001.4]:
Grade 10 1:4:8 (50mm)
(Volume Batching) Using
ST1 Crusher Run Aggregate
- (Excl. Transport of Cu.m 20,277.00 18,626.00 18,450.00 18,388.00 18,610.00
035 Aggregate & Piling) (Using
Concrete Mixer) [SSCM
1001.8-1001.9]:
Grade 10 1:4:8 (50mm) With
20% Plums (Volume
ST1
Batching) Using Crusher
- Cu.m 19,705.00 18,264.00 17,981.00 17,852.00 17,997.00
Run Aggregate (Excl.
036
Transport of Aggregate &
Piling) (Manual)
Grade 10 (50mm) With 20%
Plums (Volume Batching)
ST1
Using Crusher Run
- Cu.m 18,384.00 16,935.00 16,653.00 16,447.00 16,763.00
Aggregate (Excl. Transport
037
of Aggregate & Piling):
(Using Concrete Mixer)
NO When hand broken aggregate (50 mm or 37.5 mm) is used, in place of crusher run aggregate, on
TE: approval by Pd/Ce S.S.R.R to be prepared based on the same norms.
Grade 15 (37.5 mm) With
20% Plums (Volume
ST1
Batching) Using Crusher
- Cu.m 20,825.00 19,384.00 19,101.00 18,972.00 19,117.00
Run Aggregate (Excl.
038
Transport of Aggregate &
Piling) (Manual)
Grade 15 (37.5 mm) With
20% Plums (Volume
ST1 Batching) Using Crusher
- Run Aggregate (Excl. Cu.m 19,482.00 18,037.00 17,754.00 17,547.00 17,863.00
039 Transport of Aggregate &
Piling) :(Using Concrete
Mixer)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 168
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Grade 15 (37.5mm)
(Volume Batching) Using
ST1
Crusher Run Aggregate
- Cu.m 23,685.00 22,040.00 21,863.00 21,881.00 21,930.00
(Excl. Transport of
040
Aggregate & Piling) [SSCM
1001.4]: (Manual)
Grade 15 (37.5 mm)
(Volume Batching) Using
ST1
Crusher Run Aggregate
- Cu.m 22,351.00 20,701.00 20,524.00 20,462.00 20,683.00
(Excl. Transport of
041
Aggregate & Piling): (Using
Concrete Mixer)
Grade 15 (19 mm) (Volume
ST1 Batching) Using crusher
- Run Aggregate (Excl. Cu.m 23,597.00 22,014.00 21,852.00 22,126.00 21,934.00
042 Transport of Aggregate &
Piling): (Manual)
Grade 15 (19 mm) (Volume
ST1 Batching) Using Crushed
- Aggregate (Excl. Transport Cu.m 22,115.00 20,528.00 20,366.00 20,562.00 20,541.00
043 of Aggregate & Piling):
(Using Concrete Mixer)
Grade 20 (37.5 mm)
(Volume Batching) Using
ST1
crusher Run Aggregate
- Cu.m 25,784.00 24,139.00 23,962.00 23,980.00 24,029.00
(Excl. Transport of
044
Aggregate & Piling):
(Manual)
Grade 20 (37.5 mm)
(Volume Batching) Using
ST1
crusher Run Aggregate
- Cu.m. 24,674.00 23,024.00 22,847.00 22,786.00 23,007.00
(Excl. Transport of
045
Aggregate & Piling): (Using
Concrete Mixer)
Grade 20 (19 mm) (Volume
ST1 Batching) Using crusher
- Run Aggregate (Excl. Cu.m 25,495.00 23,919.00 23,760.00 24,043.00 23,843.00
046 Transport of Aggregate &
Piling): (Manual)
Grade 20 (19 mm) (Volume
Batching) Using crusher
ST1
Run Aggregate (Excl.
- Cu.m 24,365.00 22,788.00 22,629.00 22,833.00 22,805.00
Transport of Aggregate &
047
Piling): (Using Concrete
Mixer)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 169
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Mixing & Laying Using
Concrete Mixer
(W/Batching), Cement
ST1 Concrete for Grade
- 25(19mm) Using crusher Cu.m 26,009.00 24,431.00 24,272.00 24,476.00 24,448.00
048 Run Aggregate in
Foundations and Floors.
(Excl. Transport of
Aggregate & Piling): *
* See General Notes: Clause 33.7 of HSR published by RDA
Mixing & Laying Using
Concrete Mixer
ST1 (W/Batching), Cement
- Concrete for Grade 25 (70%
Cu.m. 24,386.00 22,893.00 22,755.00 22,970.00 22,951.00
048 37.5+30%19) Using crusher
A Run Aggregates. (Excl.
Transport of Aggregate &
Piling): *
* See General Notes: Clause 33.7 of HSR published by RDA
Mixing & Laying Using
Concrete Mixer
(W/Batching), Cement
ST1
Concrete for Grade
- Cu.m 28,960.00 27,378.00 27,217.00 27,415.00 27,392.00
30(19mm), With crusher
049
Run Aggregate. (Excl.
Transport of Aggregate &
Piling): *
*See General Notes: Clause 33.7 of HSR published by RDA
Mixing & Laying Using
Concrete Mixer
(W/Batching), Cement
ST1
Concrete for Grade
- Cu.m 31,886.00 30,299.00 30,138.00 30,333.00 30,313.00
40(19mm), With Crusher
050
Run Aggregate (Excl.
Transport of Aggregate &
Piling): *
*See General Notes: Clause 33.7 of HSR published by RDA
ST1- Mixing & Laying Cement
Cu.m 7,297.00 7,206.00 7,206.00 7,550.00 7,016.00
051 Concrete by Hand:
ST1 Mixing & Laying Cement
- Concrete by Power Driven Cu.m 5,969.00 5,873.00 5,873.00 6,138.00 5,776.00
052 Concrete Mixer V/Batching
ST1 Curing Of Concrete Decks,
Sq.m/
- Slabs, Beams, Walls Etc. 63.00 57.00 57.00 61.00 59.00
day
053 [SSCM 1011.11]:
ST1 Fabricate & lay tor steel as
- reinforcement (incl. kg 418.00 414.00 414.00 420.00 414.00
055 Transport):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 170
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Cutting & laying
ST1
reinforcement fabric
- Sq.m 317.00 306.00 306.00 323.00 306.00
(excluding cost of
056
reinforcement fabric):
Suppling & Fixing 25mm
ST1 Thick planks of class II
- timber as shuttering, Sq.m. 1,707.00 1,674.00 1,674.00 1,718.00 1,685.00
057 including removing [SSCM
1008.3 (b)]:
Supplying & fixing class II
ST1 timber bearers, joists, etc.
Cu.deci
- including dismantling in 86.00 82.00 82.00 87.00 83.00
m
058 shuttering [SSCM 1008.3
(a)]:
ST1 100 - 150 mm dia. round
- jungle timber supplied & m 146.00 139.00 139.00 148.00 141.00
059 fixed as props. :
ST1 150 - 200 mm dia. round
- jungle timber supplied & m 145.00 138.00 138.00 147.00 140.00
060 fixed as props. :
Formwork smooth finish
with class II timber for
ST1
bridge beams, bridge deck
- Sq.m. 4,120.00 4,092.00 4,113.00 4,166.00 4,050.00
under sides and sides
061
including dismantling.
[SSCM 1008.3(b)]:
Consider a beam section 300x450 mm and 6100 mm long.
Formwork smooth finish
ST1 with class II timber for
- bridge column shafts Sq.m. 3,788.00 3,765.00 3,788.00 3,836.00 3,717.00
062 including dismantling.
[SSCM 1008.3(b)]:
Formwork smooth finish,
using plywood (shutter 15
ST1
mm) and class II timber
- Sq.m. 4,012.00 3,911.00 3,936.00 4,076.00 3,910.00
bearers, joists and jungle
063
timber props for bridge
abutments, wingwalls etc.:
Consider 2 no. Panels of 1m x 1m
Supplying & fixing 25 mm
thick planks and struts of
ST1
class II timber as formwork
- Sq.m. 1,888.00 1,833.00 1,833.00 1,906.00 1,851.00
rough finish, in foundation
064
etc. including removing.
[SSCM 1008.3(b)]:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 171
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Formwork smooth finish for
general purposes, using 25
ST1 mm thick planks & struts of
- class II timber and round Sq.m. 2,581.00 2,521.00 2,521.00 2,604.00 2,530.00
065 jungle timber props 100-
150mm dia., including
dismantling:
Laying & jointing 152 mm
ST1 dia. Concrete pipes
- (transport and bedding m 4,206.00 4,169.00 4,169.00 4,234.00 4,169.00
066 material paid separately)
[SSCM 707.3(c) - 707.4]:
Laying & jointing 229 mm
ST1 dia. Concrete pipes
- (transport and bedding m 5,160.00 5,117.00 5,117.00 5,188.00 5,121.00
067 material paid separately)
[SSCM 707.3(c) - 707.4]:
Laying & jointing 305 mm
ST1 dia. Concrete pipes
- (transport and bedding m 6,217.00 6,175.00 6,175.00 6,248.00 6,175.00
068 material paid separately)
[SSCM 707.3(c) - 707.4]:
Laying & jointing 457 mm
ST1 dia. Concrete pipes
- (transport and bedding m 7,651.00 7,609.00 7,609.00 7,683.00 7,609.00
069 material paid separately)
[SSCM 707.3(c) - 707.4]:
Laying & jointing 610 mm
ST1 dia. Concrete pipes
- (transport and bedding m 12,142.00 12,058.00 12,058.00 12,205.00 12,058.00
070 material paid separately)
[SSCM 707.3(c) - 707.4]:
Laying & jointing 915 mm
ST1 dia. Concrete pipes
- (transport and bedding m 21,146.00 21,006.00 21,006.00 21,261.00 21,006.00
071 material paid separately)
[SSCM 707.3(c) - 707.4]:
Laying & jointing 1220 mm
ST1 dia. Concrete pipes
- (transport and bedding m 37,854.00 37,658.00 37,658.00 38,015.00 37,658.00
072 material paid separately)
[SSCM 707.3(c) - 707.4]:
ST1 Laying & jointing 152 mm
- dia. Available concrete pipes m 1,010.00 972.00 972.00 1,038.00 972.00
073 and collars:
ST1 Laying & jointing 229 mm
- dia. Available concrete pipes m 1,075.00 1,033.00 1,033.00 1,103.00 1,036.00
074 and collars:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 172
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
ST1 Laying & jointing 305 mm
- dia. Available concrete pipes m 1,162.00 1,120.00 1,120.00 1,194.00 1,120.00
075 and collars:
ST1 Laying & jointing 610 mm
- dia. Available concrete pipes m 2,265.00 2,181.00 2,181.00 2,328.00 2,181.00
076 and collars:
ST1 Laying & jointing 915 mm
- dia. Available concrete pipes m 3,881.00 3,741.00 3,741.00 3,997.00 3,741.00
077 and collars:
ST1 Laying & jointing 1220 mm
- dia. Available concrete pipes m 5,545.00 5,349.00 5,349.00 5,706.00 5,349.00
078 and collars:
Fixing new bridge new bride
ST1
planks runners and stacking
- No 1,366.00 1,298.00 1,298.00 1,400.00 1,315.00
old planks (available)
079
[SSCM 1402.2(a)]:
ST1
Removing & re-setting old
- No. 854.00 811.00 811.00 875.00 822.00
bride planks:
080
ST1 Supplying & fixing new
Cu.dec
- bride planks of class I 279.00 278.00 278.00 280.00 278.00
im
081 timber:
ST1 Supplying & fixing 31 mm
- thick deck planks of class I Sq.m. 10,456.00 10,319.00 10,319.00 10,501.00 10,365.00
082 timber:
Fixing new chequered or
ST1
m.s. plates on timber -
- m 2,016.00 1,915.00 1,915.00 2,066.00 1,940.00
decked bridge. [SSCM
083
1402.2(d)]:
ST1 Removing & refixing new
- chequered m.s. plates on m 2,688.00 2,554.00 2,554.00 2,755.00 2,587.00
084 timber - decked bridge. :
ST1
Tightening bolts & nuts of
- m 470.00 445.00 445.00 478.00 453.00
chequered or m.s. plates:
085
ST1- Removing & refixing 'u'
No 287.00 271.00 271.00 292.00 276.00
086 clips. [SSCM 1402.2(b)]:
ST1 Cleaning, wire brushing &
- painting steel work, one coat Sq.m 385.00 377.00 377.00 396.00 374.00
087 enamel paint. :
ST1 Cleaning, wire brushing &
- applying tar on steel work, Sq.m 286.00 278.00 278.00 297.00 275.00
088 one coat:
ST1 Cleaning with cotton waste
- & painting steel work with Sq.m 231.00 229.00 231.00 234.00 226.00
089 enamel paint, one coat. :
ST1 Chipping to bare metal etc.
- & painting with Sq.m. 1,249.00 1,241.00 1,245.00 1,293.00 1,204.00
090 anticorrosive paint, one coat.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 173
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Painting with one coat of
ST1 enamel paint after cleaning,
- derusting & application of Sq.m. 890.00 882.00 889.00 913.00 864.00
091 one coat anticorrosive paint.
[SSCM 1401.3(c)]:
Painting with two coat of
ST1 enamel paint after cleaning,
- derusting & application of Sq.m. 1,102.00 1,091.00 1,100.00 1,129.00 1,071.00
092 one coat anticorrosive paint.
:
ST1 Oiling steel cables on
- suspension bridges [SSCM Sq.m. 1,656.00 1,656.00 1,656.00 1,678.00 1,634.00
093 1405.3]:
Cleaning booms of steel
ST1
bridges including
- m 112.00 112.00 112.00 116.00 109.00
scaffolding where necessary
094
[SSCM 1405.3]:
Demolishing unreinforced
cement concrete including
cleaning of debris in
ST1
foundation and
- Cu.m 4,560.00 4,416.00 4,452.00 4,723.00 4,379.00
superstructure in dry
095
condition excluding under
water structures. [SSCM
202.2]:
ST1
Demolishing reinforced
- Cu.m 6,408.00 6,227.00 6,299.00 6,625.00 6,154.00
concrete and debris cleared
096
Demolishing unreinforced
concrete in very heavy
ST1 structures buildup of grade
- 30 above concrete in work Cu.m 23,848.00 23,775.00 23,881.00 23,973.00 23,669.00
097 such as bridge beams & deck
slabs, including collecting &
removing:
Supplying & fixing m/s.
dowels, spliced and dove
ST1
tailed with wedge at one end,
- No. 1,076.00 1,076.00 1,101.00 1,089.00 1,051.00
16 mm dia and 1 m long,
098
boring holes t0 0.3 m depth
in fixing:
Supplying & fixing m/s.
dowels, spliced and dove
ST1
tailed with wedge at one end,
- No 1,383.00 1,383.00 1,411.00 1,397.00 1,355.00
20 mm dia and 1 m long,
099
boring holes t0 0.3 m depth
in fixing:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 174
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Supplying & fixing m/s.
dowels, spliced and dove
ST1
tailed with wedge at one end,
- No 1,896.00 1,896.00 1,930.00 1,913.00 1,863.00
25 mm dia and 1 m long,
100
boring holes t0 0.3 m depth
in fixing:
Laying & standard type road
kerbs (125 mm wide x 900
mm long), set on 19 mm
thick 1:3 cement mortar
layer on 150 mm x 275 mm
wide 1:2:4 (19) concrete
ST1
foundation with ave. 157
- m 3,594.00 3,427.00 3,421.00 3,546.00 3,426.00
mm x 150 mm wide backing
101
with same concrete
including excavation and
shuttering. (cost of kerb
stones including transport
and aggregate * transport, to
pay separately):
Lay standard precast bridge
ST1
kerbs (cost of precast kerbs
- lm 759.00 725.00 725.00 782.00 730.00
including transport to be
102
paid separately):
Constructing 150 x 150 mm
thick insitu lower kerb in
ST1
grade 20 (14 mm) concrete
- lm 407.00 386.00 385.00 395.00 392.00
for bridge: (aggregate
103
transport to be paid
separately)
Laying 450 x 450 x 50 mm
precast concrete slabs on
ST1 foot walks including ave. 40
- mm thick 1:3 cement mortar Sq.m 2,493.00 2,356.00 2,356.00 2,530.00 2,401.00
104 bedding. (cost of precast
slabs and transport, to be pay
separately):
Laying 450 x 450 x 50 mm
precast concrete slabs on
ST1 foot walks including ave. 40
- mm thick sand bedding. Sq.m 1,607.00 1,489.00 1,489.00 1,641.00 1,528.00
105 (cost of precast slabs and
transport, to be pay
separately):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 175
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Fixing precast hand railing
and uprights using grade
25(19) concrete including
ST1
form work for pockets. (Cost
- lm 2,129.00 2,028.00 2,025.00 2,135.00 2,048.00
of the precast items
106
including transport and
aggregate* transport, to pay
separately.)
*Quantity of aggregate required for concreting in 1 m length is equal to: 0.017 cu.m.
Construction of R.C.C.
ST1 grade 25(19 mm) end
- pilaster, type I. (aggr. No. 68,637.00 66,135.00 65,954.00 67,185.00 66,260.00
107 Transport and iron piling to
be paid separately)
Construction of R.C.C.
ST1 grade 25(19 mm) end
- pilaster, type II. (aggr. No 76,555.00 73,571.00 73,349.00 74,765.00 73,721.00
108 Transport and iron piling to
be paid separately)
Construction of R.C.C.
grade 25(19 mm) end
ST1
pilaster, type IIi. (aggr.
- No. 44,263.00 42,612.00 42,489.00 43,241.00 42,698.00
Transport and built-up
109
rubble foundation to be paid
separately)
Construction of R.C.C.
ST1
grade 25(19 mm) end
- No. 47,542.00 45,855.00 45,731.00 46,536.00 45,941.00
pilaster, type iv. (aggr.
110
Transport to be separately)
Laying of grade 20 concrete
precast pin kerbs in grade
ST1
20(19) concrete foundation
- lm 1,203.00 1,151.00 1,147.00 1,181.00 1,141.00
as ending: (aggregate
111
transport to be paid
separately):
*Aggregate required per 1 m for pin kerb - 0.01 cu.m & for foundation - 0.02 cu.m.
Supplying & fixing 25 mm
thick tougne & grooved
ST1
planks with 50x50 mm struts
- Sq.m 2,095.00 2,069.00 2,069.00 2,122.00 2,055.00
of class I timber in panels as
112
smooth shuttering for
concrete drains:
Supply and packing 50 - 200
ST1 mm dry stone lining behind
- abutments and wing walls: Cu.m 7,160.00 6,443.00 5,993.00 5,015.00 5,887.00
113 (aggregate transport to pay
separately):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 176
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
ST1 Laying geotextile on
- prepared surface supply and Sq.m 87.00 85.00 86.00 90.00 84.00
114 transport to pay separately:
Construction of gabion wall
using 4x1x1m mesh
ST1
including lacing wire on
- Cu.m 11,336.00 10,533.00 9,700.00 8,656.00 9,574.00
prepared ground. (supply
115
and transport of gabion mesh
to be paid separately):
Construction of gabion wall
using 4x1x0.5m mesh
ST1
including lacing wire on
- Cu.m 11,985.00 11,158.00 10,325.00 9,333.00 10,197.00
prepared ground. (supply
116
and transport of gabion mesh
to be paid separately):
ST1- Construction of kerb inlet
117 with cover slabs, aggregate No. 16,965.00 16,257.00 16,207.00 16,590.00 16,303.00
(new) transport to pay separately:
NO
Earth excavation to consider by engineer as per site condition and add separately if required
TE
Items reserved for bridge works only
The rates in the following items from ST1-118 to ST1-120 should be added to the concrete rate
selected from items ST1-038 TO ST1-050, depending on the structural location
ST1
Additional labour for
-
pouring, compacting and
118 Cu.m 1,233.00 1,208.00 1,208.00 1,266.00 1,187.00
levelling concrete in screed
(NE
under foundation slab:
W)
Additional labour for
ST1
pouring & compacting
-
concrete in abutment,
119 Cu.m. 376.00 352.00 352.00 376.00 364.00
wingwalls, capping beams
(NE
including screed of bridge
W)
decks.:
Additional labour for
ST1
pouring, compacting and
-
levelling infiler concrete
120 Cu.m 1,848.00 1,749.00 1,749.00 1,881.00 1,782.00
between bridge beams
(NE
including screed of bridge
W)
decks. :
ST1
Laying ready mixed grade
-
concrete including vibration.
121 Cu.m 2,487.00 2,415.00 2,415.00 2,548.00 2,403.00
* (supply of concrete to be
(NE
paid separately):
W)
*Additional labour to be considered depending on the location of concretion.
Office of the Deputy Chief Secretary - Engineering Services, NP Page 177
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Supplying and laying
ST1
- approved hard rubber
122 bearing pads 75mm x 12mm m 2,841.00 2,833.00 2,833.00 2,844.00 2,836.00
(NE over capping beams and
W) under the approach slabs:
Bituminous sealing material
ST1 supplied and laid under
- beam ends to prevent grout
123 leak on to capping beam m 213.00 205.00 205.00 217.00 204.00
(NE transport of emulsion
W) including: (excluding cost of
emulsion):
230 mm dia. Polythene
ST1
displaces supplied and filled
-
with saw dust or similar light
124 m 117.00 114.00 114.00 119.00 114.00
material in deck. Transport
(NE
of saw dust to be pay
W)
separately:
325 mm dia. Plythene
ST1
displaces supplied and filled
-
with saw dust or similar light
125 m 179.00 175.00 175.00 183.00 175.00
material in deck. Transport
(NE
of saw dust to be pay
W)
separately:
ST1
-
PCC beams (10.55 to 13.5m)
126 m 14,950.00 14,873.00 14,873.00 15,001.00 14,885.00
launched into position:
(NE
W)
ST1
-
M.s. angle iron and hard
127 m 11,861.00 11,621.00 11,621.00 11,998.00 11,662.00
rubber expansion joints
(ne
w)
7.3.11. Kilometer posts and guard stones
RF1
White washing, two coats to
- No. 99.00 97.00 97.00 103.00 95.00
guide/guard stone:
001
RF1 White washing, two coats
- k.m.stones inc. Numbering No. 1,044.00 1,024.00 1,024.00 1,085.00 1,003.00
002 & tar skirting :
RF1 Painting white back ground
- on parapets etc. & stenciling No. 395.00 388.00 388.00 409.00 381.00
003 nos.:
RF1
Fixing guard stones in any
- No. 307.00 294.00 294.00 320.00 294.00
soil:
004
Office of the Deputy Chief Secretary - Engineering Services, NP Page 178
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Casting std. K.m. stones
RF1 with R.C.C. [1:2:4 (19 mm)
- & cement 282.5 kg/cu.m], No. 9,013.00 8,625.00 8,605.00 8,966.00 8,631.00
005 including curing, for "a" and
"b" class roads:
Casting std. K.m. stones
RF1 with R.C.C. [1:2:4 (19 mm)
- & cement 282.5 kg/cu.m], No. 5,991.00 5,759.00 5,749.00 6,002.00 5,764.00
006 including curing, for "c" and
"d" class roads:
RF1
Fixing standard type k.m.
- No. 2,275.00 2,194.00 2,194.00 2,369.00 2,181.00
stone in any soil:
007
Fixing new or refixing type
guard stone cement concrete
RF1
[1:3:6 (37.5 mm) and cement
- No. 1,254.00 1,176.00 1,169.00 1,195.00 1,171.00
219 kg/cu.m] with min.
008
Cover 75mm x 300mm
depth:
Casting standard type guard
RF1
stones in concrete [1:2:4(19
- No. 3,110.00 2,954.00 2,945.00 3,070.00 2,961.00
mm) & cement 282.5
009
kg/cu.m:
RF1
Casting standard type guard
-
stones in concrete g25(19), No. 4,518.00 4,365.00 4,356.00 4,474.00 4,372.00
009
for bridges & culverts:
A
RF1
Route numbering with
- No. 881.00 830.00 830.00 881.00 855.00
reflective paint on 2 sides
010
Casting standard boundary
markers in reinforced
concrete [1:2:4(19 mm)]
RF1
with admixtures, including
- No. 3,153.00 3,027.00 3,020.00 3,114.00 3,039.00
14 days curing and loading
011
to vehicles at yard
(aggregate transport to pay
separately):
Note 19 mm aggregate per boundary marker Cu.m
7.3.12.Notice boards & sign boards
[ SSCM 810.2 and 1501.3]
(All paints should conform to the requirements of S.L.S. as given in SSCM 1707)
Notice & traffic sign boards
RS1 etc. Fixed in concrete
- [1:3:6(35.7 mm) and cement No. 2,278.00 2,139.00 2,129.00 2,203.00 2,143.00
001 219 kg/cu.m), (excluding
transport of aggregate):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 179
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
RS1 Cleaning white washing 2
- coat town name boards (inc. No. 558.00 549.00 549.00 575.00 540.00
002 Tar skirt):
Cleaning, painting one coat
RS1
& erlettering etc. town
- No. 3,094.00 2,941.00 2,941.00 3,146.00 2,992.00
traffic sign boards inc. Paint
003
post in b/w:
RS1- Cleaning and painting one
Sq.m. 465.00 465.00 465.00 479.00 452.00
004 coat on notice board:
RS1- Lettering & numbering
No. 72.00 68.00 68.00 72.00 70.00
005 below 50 mm:
RS1- Lettering & numbering 50
No. 87.00 82.00 82.00 87.00 84.00
006 mm - 75 mm
RS1- Lettering & numbering 75
No. 109.00 102.00 102.00 109.00 106.00
007 mm - 150 mm:
RS1- Lettering & numbering 150
No. 145.00 137.00 137.00 145.00 141.00
008 mm - 225 mm:
Painting 2 coats continuous
RS1-
centre line, 100 mm wide m 195.00 187.00 187.00 197.00 190.00
009
with enamel paint:
Painting 1 coat continuous
RS1- centre line, 100 mm wide
m 208.00 199.00 199.00 210.00 202.00
010 with road marking paint
(white):
Painting 2 coats broken
RS1-
centre line, 100 mm wide m 183.00 175.00 175.00 186.00 178.00
0011
with enamel paint:
Painting 1 coat broken centre
line, without reflective
RS1-
studs), 100 mm wide, at 3 m 193.00 185.00 185.00 196.00 188.00
012
metre intervals with road
marking paint (white):
Barricading with empty (hot
RS1- tar) barrels including white
No. 543.00 533.00 533.00 552.00 533.00
013 washing, transporting and
cost of barrels:
Revetment to banks etc.
With empty barrels in
RS1-
horizontal tiers with vertical No. 868.00 836.00 836.00 894.00 839.00
014
batter (1:8), including
transport of barrels:
RS1- Road marking continuous
015 centre line 100 mm width,
(AM using thermoplastic Sq.m. 510.00 500.00 500.00 514.00 503.00
END paint(white), inclusive
ED) barricading:
(Paint material and reflective glass beads to pay separately)
NOTE 1 kg of thermoplastic paint covers 0.28 Sq.m area at 1.5 mm thickness
Office of the Deputy Chief Secretary - Engineering Services, NP Page 180
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
25 kg of glass beads is sufficient for 100 Sq.m of centre line.
RS1-
Road marking, standard
016
pedestrian crossing, using
(AME m 1,111.00 1,095.00 1,095.00 1,118.00 1,100.00
thermoplastic paint(white),
NDE
inclusive barricading:
D)
(Paint material and reflective glass beads to pay separately)
NOTE 1 kg of thermoplastic paint covers 0.28 Sq.m area at 1.5 mm thickness
6 kg of glass beads is sufficient for 15-metre-long standard crossing.
Supplying and paving inter
locking 210 X 110 X 60mm
RS1 (15N/mm2) blocks in
- 1:2:4(12.5mm) cement
Sq.m 3,961.00 3,764.00 3,777.00 3,908.00 3,829.00
017 concrete blocks (Excluding
A block transport (Transport
schedule to main town of
each district)
Supplying and paving inter
locking 210 x 110 x 80mm
RS1 (40n/mm2 )blocks in
- 1:2:4(12.5mm) cement
Sq.m 4,349.00 4,152.00 4,165.00 4,296.00 4,218.00
017 concrete blocks (excluding
B blocks transport) (transport
scheduled to main town of
each district)
Supplying and paving inter
locking 210 x 110 x 80mm
RS1 (30n/mm2) blocks in
- 1:2:4(12.5mm) cement
Sq.m 4,177.00 3,979.00 3,993.00 4,123.00 4,045.00
017 concrete blocks (excluding
C blocks transport) (transport
scheduled to main town of
each district)
7.3.13 Miscellaneous
Preparing, stock piling
MS premix using pen. Grade
1- bitumen (excl. Transport of Cu.m. 16,112.00 14,859.00 14,822.00 14,742.00 14,911.00
001 aggregate) (site made):
(excluding cost of bitumen)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 181
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Patching shallow holes,
depth less than 20mm using
hot bitumen 1.2 ltr/Sq.m and
12.5 mm chips single size at
MS
the rate of 13.75 cu.deci
1- Sq.m. 218.00 210.00 208.00 196.00 207.00
m/Sq.m including hand
002
tamping (rate excludes cost
of bitumen and includes cost
of materials)(excl. Transport
of aggregate & bitumen) :
Patching shallow holes,
depth less than 20 mm using
10% - 20% cut back bitumen
1.2 ltr/Sq.m and 12.5 mm
MS chips single size at the rate of
1- 13.75 cu.deci m/Sq.m Sq.m. 214.00 206.00 204.00 192.00 203.00
003 including hand tamping (rate
excludes cost of bitumen and
includes cost of materials)
(excl. Transport of aggregate
& bitumen) :
Patching shallow pot holes,
depth less than 20 mm using
emulsion(crs 1) at the rate of
1.2 ltr/Sq.m and 12.5 mm
chips single size at the rate of
MS
13.75 cu.deci m/Sq.m
1- Sq.m. 214.00 206.00 204.00 192.00 203.00
including hand tamping,
004
transport emulsion to site
etc. (rate excludes cost of
bitumen and includes cost of
materials)( excl. Transport
of aggregate ) :
Patching pot holes of
medium depth of 20-75 mm
with premix material (site
made) using cut back
bitumen 10-20% at the rate
of 83.5 cu.m of 19 mm and
down gauge stone aggregate
MS including preparation of
1- surface, tack coat with 30% Sq.m. 1,742.00 1,635.00 1,633.00 1,683.00 1,627.00
005 cut back bitumen at .75
ltr/Sq.m, trimming sides,
laying premix, tamping etc.
Complete. (rate inclusive of
premix made at site & tack
coat) (excl. Transport of
aggregate ) : (excluding cost
of bitumen) :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 182
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Patching pot holes using
plant made premix bound
including sealing the
MS patching with emulsion (crs-
1- 1) painting @ 7.3 ltr/mton, Mt. 5,894.00 5,530.00 5,551.00 5,990.00 5,514.00
006 cover with sand
(transport of premix paid
separately) :(excluding cost
of emulsion) :
Patching pot holes of
medium depth of 20-75 mm
using graded aggregate 19-
12.5 mm using hot bitumen
1.75 ltr/Sq.m covered with
blotton material at the rate of
1 cu.m/125 Sq.m, including
MS preparation of surface tack
1- coat with 30% cut back Sq.m. 1,379.00 1,292.00 1,282.00 1,290.00 1,261.00
007 bitumen at .75 ltr/Sq.m,
trimming sides, laying
aggregate, tamping etc.
Complete (rate inclusive of
aggregate but excl.
Transport of aggregate &
bitumen) : (excluding cost of
bitumen) :
Patching deep pot holes
deeper than 75 mm with c/b
premix material (site made)
to a depth of 37.5 mm (over
the already prepared surface
with aggregate and gravel
paid separately) using 10-
20% cut back bitumen at the
rate of 83.5 ltr/cu.m of 19
MS
mm and downgraded
1- Sq.m. 1,018.00 966.00 964.00 995.00 956.00
aggregate incl. Preparation
008
of surface, tack coat with
30% cut back bitumen at .75
ltr/Sq.m, trimming sides,
laying premix, tamping etc.
Complete (rate inclusive of
premix made at site and tacl
coat) (excl. Transport of
aggregate & bitumen)
:(excluding cost of bitumen)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 183
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Patching pot holes more than
75 mm deep with water
bound gravel material using
50 mm or 12.5 mm single
size aggregate along with
MS useable old aggregate
1- obtained from picking and Sq.m. 81.00 80.00 80.00 85.00 78.00
009 preparation of surface inc.
Laying, watering, spreading
gravel of approved quality
and tamping as directed.
(aggregate and gravel would
be paid separately) :
Patching ruts and
depressions up to 75 mm
depth using site made cold
mix (cut back) material with
the surface and edge
MS
prepared as per
1- Sq.m. 1,499.00 1,402.00 1,400.00 1,431.00 1,395.00
specifications and
010
application of tack coat with
30% cut back bitumen at .75
ltr/Sq.m, (excl. Transport of
aggregate) : (excluding cost
of bitumen) :
Patching ruts and
depressions up to 75 mm
depth using plant made cold
mix (cut back) material with
the surface and edge
MS prepared as per
1- specifications and Sq.m. 621.00 608.00 608.00 644.00 597.00
011 application of tack coat with
30% cut back bitumen at .75
ltr/Sq.m, (cold mix transport
will be paid separately):
(excluding cost of bitumen)
:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 184
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Patching ruts and
depressions deeper than 75
mm the surface and edge
prepared as per
specifications tack coat with
30% cut back bitumen at .75
ltr/Sq.m, trimming sides 50
MS
mm down gauge aggregated
1- Sq.m. 1,470.00 1,416.00 1,415.00 1,465.00 1,390.00
laid and compacted and the
012
top 40 mm laid and
compacted with cold mix
(cut back) material
(aggregate 50 mm down
gauge and transport will be
paid separately) :(excluding
cost of bitumen):
Patching ruts and
depressions up to 75 mm
depth the surface and edges
prepared as per
specifications and
application of tack coat with
30% cut back bitumen at .75
MS
ltr/Sq.m, 50 mm down gauge
1- Sq.m. 1,114.00 1,084.00 1,085.00 1,147.00 1,061.00
aggregated laid and
013
compacted using hot
bitumen (1.75 ltr/Sq.m
covered with blotten
material (sand) at the rate of
1 cu.m/125 Sq.m (aggregate
will be paid separately):
(excluding cost of bitumen):
Patching ruts and
depressions deeper than 75
mm depth the surface and
edges prepared as per
specifications and
application of tack coat with
30% cut back bitumen at .75
MS
ltr/Sq.m, 50 mm down gauge
1- Sq.m. 1,295.00 1,265.00 1,266.00 1,335.00 1,235.00
aggregated laid and
014
compacted using hot
bitumen (1.75 ltr/Sq.m
covered with blotten
material (sand) at the rate of
1 cu.m/125 Sq.m (aggregate
will be paid separately):
(excluding cost of bitumen):
Office of the Deputy Chief Secretary - Engineering Services, NP Page 185
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Correcting & strengthening
the edges of road by cold
mix 40 mm thick prepared
using cut back bitumen 10-
20% at the rate of 83.5
ltr/cu.m of 19 mm and down
gauge aggregate over a tack
MS
coat using with 30% cut
1-
back bitumen at .75 ltr/Sq.m, Sq.m. 1,872.00 1,813.00 1,812.00 1,883.00 1,777.00
015
laid over 50 mm and
M
compacted including earth
work excavation to a width
of 225 mm and depth of 125
mm. (cost of aggregate and
transport to be paid
separately) :(excluding cost
of bitumen) :
Correcting & strengthening
the edges of road by cold
mix 40 mm thick prepared
using cut back bitumen 10-
20% at the rate of 83.5
ltr/cu.m of 19 mm and down
gauge aggregate over a tack
coat using with 30% cut
back bitumen at .75 ltr/Sq.m,
laid over 50 mm and down
MS
gauge aggregate laid, on
1- Sq.m. 2,238.00 2,173.00 2,172.00 2,263.00 2,128.00
position watered and
016
compacted with a bottom
layer of 100 mm aggregate
closely pact, including earth
work excavation to a width
of 225 mm and depth of 225
mm. (aggregate 100mm,
50mm down gauge and
transport will be paid
separately) :(excluding cost
of bitumen) :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 186
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Patching sealing with
emulsion painting the
surface by spray of crs-1 at
MS the rate of 0.75 ltr/Sq.m
1- squeezing the emulsion and Sq.m. 106.00 88.00 90.00 100.00 92.00
017 spreading the blotton
material (sand) at the rate of
1 cu.m/125 Sq.m: (excluding
cost of emulsion)
Patching sealing with hot
bitumen painting the surface
by using 0.75 ltr/Sq.m
MS squeezing the bitumen and
1- spreading the blotton Sq.m. 108.00 91.00 92.00 103.00 95.00
018 material (sand) at the rate of
1 cu.m/125 Sq.m (transport
of bitumen paid separately):
(excluding cost of bitumen):
Patch sealing of pitted
surface using hot sand
bitumen mix 104 ltr/cu.m of
MS sand spead and hand tamped
1- including brushing and Sq.m. 277.00 240.00 243.00 270.00 249.00
019 cleaning the surface before
application (excluding
transport of bitumen):
(excluding cost of bitumen):
Patch sealing of pitted
surface with a emulsion sand
slurry using crs 1 or 2 at the
rate of 136.5 ltr/cu.m of sand
MS
mix properly laid, levelled &
1- Sq.m. 244.00 211.00 214.00 236.00 218.00
squeeged including brushing
020
and cleaning the surface
before application :
(excluding cost of emulsion)
:
General upkeep of road sides
including maintaining the
right of way in a neat
MS
condition by trimming,
1- Sq.m. 41.00 40.00 40.00 43.00 40.00
weeding & clearing of the
021
road sides, drains, drainage
structures, scupper drains
and cleaning minor slips :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 187
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Cleaning ordinary jungle
including removing high
growing plants and trees of
girth less than 300 mm other
MS1-
022
than those designated to Sq.m. 5.00 4.00 4.00 5.00 4.00
remain, by uprooting or by
cutting and then uprooting the
stumps or by cutting only as
directed (SSCM 1203.2) :
Cleaning medium jungle
including remaining all high
growing plants and trees of
girth less than 300 mm other
MS1-
than those designated to Sq.m. 7.00 6.00 6.00 7.00 6.00
023
remain, by uprooting or by
cutting and then uprooting the
stumps or by cutting only as
directed :
Cleaning heavy jungle
including removing all high
growing plants and trees of
girth less than 300 mm other
MS1-
024
than those designated to Sq.m. 9.00 8.00 8.00 9.00 8.00
remain, by uprooting or by
cutting and then uprooting the
stumps or by cutting only as
directed :
Repairs to damage of
shoulders verges and
embankments slopes
including making good
depressions, ruts, holes and
MS1- erosion path with approved
Cu.m 815.00 797.00 797.00 834.00 797.00
025 gravelly soil and compacting
the same with roller (8-10 ton)
as directed (gravelly soil be
paid separately if brought
from outside) [SSCM 1201.3]
:
Re grading and re gravelling
of shoulders with gravel of
approved quality, duly
compacted with roller (8-10
tons) as directed for repairing
MS1- high sides caused by
Cu.m 419.00 419.00 419.00 419.00 419.00
026 heavying’s deposits and
construction debris, to
required levels by using a
grader (120-140 hp) (gravel
be paid for separately) [scm
1201.3(b)] :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 188
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Re grading and re gravelling
of shoulders with gravel of
approved quality, duly
compacted with roller (8-10
MS tons) as directed for repairing
1- high sides caused by Cu.m 902.00 881.00 881.00 922.00 881.00
027 heavying’s deposits and
construction debris, to
required levels by manually
((gravel (loose volume) paid
separately) [scm 1201.3(b)] :
Replacing the damage
cracked concrete slabs in the
foot walks with precast/cast
insity cement concrete 1:2:4
(19mm) using 19 mm & down
MS
gaige stone aggregate to a
1- Sq.m. 3,355.00 3,210.00 3,202.00 3,351.00 3,196.00
minimum thickness of 50 mm
028 including fixing / laying in
position with cement mortar
1:3 joints over a compacted
bed etc. (excluding transport
of aggregate) [scm 1204.3] :
Cutting and removing fallen
trees upto 600mm girth
including cutting into
MS
required number of pieces
1- No. 1,076.00 1,031.00 1,031.00 1,121.00 1,031.00
including disposal as directed.
029 Minimum piece shall not be
less than 2.5 m in length
[SSCM 1203.2] :
Cutting and removing fallen
trees upto 600 - 900 mm girth
MS including cutting into
1- required number of pieces No. 1,537.00 1,473.00 1,473.00 1,601.00 1,473.00
030 including disposal as directed.
Minimum piece shall not be
less than 2 m. [SSCM 1203.2]
Weeding masonry culverts
MS1-
031
small bridges and retaining No. 366.00 366.00 366.00 376.00 356.00
walls [SSCM 1303.3] :
Masonry random rubble with
MS1-
boulders including collect Cu.m 1,988.00 1,916.00 1,916.00 2,037.00 1,916.00
032
[SSCM 1006.3(b)] :
Fixing cats eyes in tar
MS1- macadam including breaking
No. 556.00 540.00 545.00 576.00 534.00
033 road surface, barricade etc.
[SSCM 810.3(c)] :
Reducing high sides in
MS1-
ordinary soil [SSCM Cu.m 922.00 886.00 886.00 958.00 886.00
034
301.3/1201.3(c)] :
Office of the Deputy Chief Secretary - Engineering Services, NP Page 189
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
MS1- Reducing high sides in
Cu.m 1,356.00 1,302.00 1,302.00 1,411.00 1,302.00
035 medium soil :
MS1- Reducing high sides in hard
036
Cu.m 1,791.00 1,719.00 1,719.00 1,863.00 1,719.00
soil :
MS1- Reducing high sides in soft
Cu.m 2,226.00 2,135.00 2,135.00 2,316.00 2,135.00
037 rock :
MS1- Reducing high sides in rock
038
Cu.m 5,063.00 4,963.00 5,013.00 5,189.00 4,912.00
requiring blasting :
White washing 1 coat to
MS1-
039
parapets of bridges and Sq.m. 67.00 66.00 66.00 69.00 65.00
culverts. [SSCM 1403.3(e)]
White washing 2 coats to
MS1-
parapets of bridges and Sq.m. 113.00 111.00 111.00 117.00 109.00
040
culverts :
White washing 1 coat to
MS1- parapets of bridges and
Sq.m. 128.00 127.00 128.00 130.00 126.00
041 culverts after cleaning
attending to minor repairs :
White washing 2 coats to
MS1- parapets of bridges and
Sq.m. 176.00 174.00 176.00 179.00 172.00
042 culverts after cleaning
attending to minor repairs :
Painting with emulsion 1 coat
to parapets of bridges and
MS1- culverts, guard stones and
Sq.m. 296.00 296.00 300.00 298.00 291.00
043 k.m. posts after cleaning
attending to minor repairs
[SSCM 1501.3(a)-(v)] :
Painting with enamel 1 coat to
parapets of bridges and
MS1- culverts, guard stones and
Sq.m. 346.00 346.00 351.00 349.00 341.00
044 k.m. posts after cleaning
attending to minor repairs
[SSCM 1501.3(a)-(v)] :
Painting with enamel 2 coats
to parapets of bridges and
MS
culverts, guard stones and
1- Sq.m. 546.00 546.00 555.00 550.00 537.00
k.m. posts after cleaning
045 attending to minor repairs
[SSCM 1501.3(a)-(v)] :
Painting with emulsion 2
MS coats to parapets of bridges
1- and culverts, guard stones and Sq.m. 470.00 470.00 479.00 474.00 461.00
046 k.m. posts after cleaning
attending to minor repairs :
Painting 1 coat emulsion paint
to parapets of bridges and
MS
culverts, guard stones and
1- Sq.m. 236.00 236.00 241.00 239.00 231.00
k.m. posts including
047 preparing surface of old work.
[SSCM 1501.3(b)(v)]:
Office of the Deputy Chief Secretary - Engineering Services, NP Page 190
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Painting sub coat emulsion
paint to parapets of bridges
MS
and culverts, guard stones
1- Sq.m. 209.00 209.00 213.00 211.00 205.00
and k.m. posts including
048
preparing surface [SSCM
1501.3(b)] :
Painting 1 coat emulsion
paint to parapets of bridges
MS
and culverts, guard stones
1- Sq.m. 218.00 218.00 223.00 221.00 214.00
and k.m. posts including
049
preparing surface of new
work. [SSCM 1501.3(b)(v)]:
Cleaning & painting 100 mm
MS
wide stripe for skirting to
1- lm 124.00 122.00 122.00 129.00 119.00
guard stones. [SSCM
050
1501.3(b)(v)] :
Painting 2 coats standard
MS
pedestrian crossing for
1- lm 3,103.00 2,987.00 2,987.00 3,141.00 3,026.00
carriageway. [SSCM
051
810.2(c)] :
Painting 1 coat standard
MS pedestrian crossing for
1- carriageway using road lm 3,431.00 3,305.00 3,305.00 3,473.00 3,347.00
052 marking paint. [SSCM
810.2(c)] :
Erecting, barricading in
jungle timber 75 - 100 mm
MS
dia. Vertical posts at .9 m
1- lm 912.00 898.00 898.00 926.00 898.00
centres and 1.2 m above
053
ground including white
washing. [SSCM 1709] :
Temporary scaffolding for
painting or tarring bridges
MS
and for weeding on bridges
1- Sq.m. 191.00 191.00 191.00 197.00 184.00
or retaining wall including
054
dismantling after work
[SSCM 1008.3(a)] :
Roughening existing smooth
tarred metaled carriageway
MS
by hand for bonding,
1- Sq.m. 27.00 27.00 27.00 28.00 26.00
collecting disposal of all
055
loose materials. [SSCM
403.3(b)]:
MS Supply of diesel for
1- machineries: (ex-filling l 286.00 286.00 286.00 286.00 286.00
056 station)
Office of the Deputy Chief Secretary - Engineering Services, NP Page 191
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
Patching road with premix
(loose volume) after prep.
Surface with emulsion (css-
1) at .75 ltr/Sq.m as tack
MS coat, including internal
1- transport and hand stamping. Cu.m 9,089.00 8,962.00 8,962.00 9,343.00 8,836.00
057 (supply of premix (loose
vol.) Paid separately)
[SSCM 1102.3(b)(i)]
:(excluding cost of
emulsion) :
Patching road with premix
after preparing surface with
emulsion (css-1) at .75
ltr/Sq.m as tack coat,
MS
including internal transport
1- mt. 8,801.00 8,611.00 8,625.00 9,014.00 8,568.00
and hand stamping. (supply
058
of premix (loose vol.) Paid
separately) [SSCM
1102.3(b)(i)] : (excluding
cost of emulsion) :
MS Painting two coats enamel
1- paint on kerbs, after cleaning Sq.m. 544.00 540.00 549.00 552.00 531.00
059 and preparing surfacing. :
Preparing and stock piling
premix at site using 12.5 mm
MS
aggregate and emulsion css-
1- Cu.m 25,383.00 23,985.00 23,948.00 23,940.00 24,254.00
1 (excluding transport of
060
aggregate) : (excluding cost
of emulsion) :
MS
1- Breaking manually asphalt
061 layer 2" - 3" thick on the m 674.00 672.00 672.00 700.00 648.00
(NE carriageway for kerb laying:
W)
7.3.14 Surveying, levelling and day works
SV
1- Supply of unskilled labour : day 2,400.00 2,300.00 2,300.00 2,500.00 2,300.00
001
SV
1- Supply of semiskilled labour day 2,500.00 2,500.00 2,500.00 2,600.00 2,400.00
002
SV
Supply of skilled 'a' grade
1- day 3,200.00 3,000.00 3,000.00 3,200.00 3,100.00
labour :
003
SV
Supply of skilled 'b' grade
1- day 2,700.00 2,700.00 2,800.00 2,750.00 2,600.00
labour :
004
Office of the Deputy Chief Secretary - Engineering Services, NP Page 192
Road Works Rate 2025
Basic Rate
Code Description of Items Unit
Jaffna Kilinochchi Mullaitivu Vavuniya Mannar
SV Clearing jungle (light) to a
1- width of 1.22 m for survey km 9,167.00 8,785.00 8,785.00 9,549.00 8,785.00
005 work :
SV Clearing jungle (medium) to
1- a width of 1.22 m for survey km 12,223.00 11,714.00 11,714.00 12,732.00 11,714.00
006 work :
SV Clearing jungle (heavy) to a
1- width of 1.22 m for survey km 18,335.00 17,571.00 17,571.00 19,099.00 17,571.00
007 work :
SV Supply of labour for
1- cleaning and cutting pegs km 2,387.00 2,387.00 2,387.00 2,482.00 2,291.00
008 and pegging :
Levelling chaining and
SV pegging and establishing
1- bench marks on concrete km 4,774.00 4,774.00 4,774.00 4,965.00 4,583.00
009 rock or pegs and checking
back levels :
SV
Surveying including fixing
1- km 4,774.00 4,774.00 4,774.00 4,965.00 4,583.00
pickets & taking angles :
010
SV
Changing traverse lines and
1- km 6,366.00 6,366.00 6,366.00 6,621.00 6,111.00
taking off-sets :
011
Office of the Deputy Chief Secretary - Engineering Services, NP Page 193
Road Works Rate 2025
Office of the Deputy Chief Secretary - Engineering Services, NP Page 194
RATES FOR
MATERIAL TESTING
Material Testing Rate 2025
PROVINCIAL ENGINEERING LABORATORY, NORTHERN PROVINCE
GENERAL NOTES
1. This Test Rates becomes operative from 01.01.2025.
2. The test rates are applicable only for the samples which are delivered to the laboratory
3. When test is carried out in the field, Transport charges, overtimes and travelling
allowances for the staff will be added separately
Office of the Deputy Chief Secretary - Engineering Services, NP Page 198
Material Testing Rate 2025
.PROVINCIAL ENGINEERING LABORATORY, NORTHERN PROVINCE
8.RATES FOR MATERIAL TESTING
Test Standard/
No Instruments Test Rate (Rs)
Method
8.1. MOISTURE CONTENT
Moisture BS EN ISO
Oven Method 1000.00
1 Content 17892-1:2014
Speedy
For reliable moisture measurement in BS EN ISO 1,000.00 +
2 Moisture
field 17892-1:2014 Travelling
Test
For direct digital reading of moisture BS EN ISO 1,100.00 +
3 Moisture Meter
measurement 17892-1:2014 Travelling
8.2. SOIL INDEX PROPERTIES
Casagrande To determine the Liquid limit ,Plastic BS 1377 Part
4 3,200.00
Apparatus limit, Plastic index 2:1990
Cone To define plastic limit ,Plastic limit, TRL DCP (RN
5 3,200.00
Penetrometer Plastic index 31)
8.3. IN -SITU DENSITY
Sand cone
To determine the dry density of in – situ BS 1377 Part 2000.00 +
6 apparatus
soil 2:1990 Travelling
Replacement
Core cutter 2000.00 +
7 To determine the density of in situ soil ASTM D5361
Apparatus Travelling
8.4. PARTICLE SIZE DISTRIBUTION
1. Fine Aggregate:200BS/ISO s/S
BS 812-
4.75pp-200 Bs/ISO s/s 75 2,100.00
103.1:1985
UMWW
8 Test sieve 2. Coarse Aggregate: 300BS/ISO 75.0 BS 812-
2,100.00
pp-300 BS/ISO 4.00 pp 103.1:1985
3. Soil Hydrometer: Practical (beyond the ASTM D7928 2,000.00
clay size) Distribution by wet sieving
BS 1377 Part
1. Standard Protector Compaction Test 3,900.00
Compaction 4:1990
9
Test BS 1377 Part
2. Modified Protector Compaction Test 4,100.00
4:1990
BS 1377 Part
10 CBR California Bearing Ratio 4,400.00
4:1990
8.5. BEARING CAPACITY AND SOIL PROFILE
Plate Bearing
Determination of bearing capacity of the ASTM D1194 - 3,500.00 +
11 Test
soil in in-situ 94 Travelling
Equipment
Field testing of CBR, Co relate the
Proving Ring 1,500.00 +
12 bearing capacity with CBR testing ASTM D2937
Penetrometer Travelling
method ( Including Transport)
6,000.00 +
13 SPT Standard Penetration Test (Per Point) ASTM D1586
Travelling
Office of the Deputy Chief Secretary - Engineering Services, NP Page 199
Material Testing Rate 2025
Test Standard/
No Instruments Test Rate (Rs)
Method
8.6. CONCRETE
To measure the workability of fresh BS 1881-
14 Slump Test 750.00
cement 102:1983
Require that specimens are casted in
Cube casting number of standard sizes
15
3 Nos convenient of compression and flexural BS EN – 1,000.00
test determinations 12390 2:2019
8.7. COMPRESSIVE STRENGTH
1. Cubes of 150*150 mm,100*100 BS EN – 12390
mm,200*200 3:2019 750.00
2. Compression testing for cylinders
(with or without 1,000.00
capping)
3. Compression testing for concrete SLS :855 Part1 700.00
Blocks
- Water Absorption SLS :855 Part1 500.00
- Drying Shrinkage and SLS :855 Part1 650.00
ADR 1500 Wetting Expansion
16
Compression - Density of the Block SLS :855 Part1 650.00
- Moisture Content SLS :855 Part1 750.00
4. Compression testing for Paving Blocks SLS 1425 Part 750.00
2:2011
5. Compression testing for Clay Bricks ASTM C62 – 750.00
13a(41)
-Water Absorption 400.00
-Dimension 100.00
100KN Flexural Flexural and transverse strength of BS EN – 12390
17 (Beams) concrete and Determine the internal 5:2019 5,000.00
stresses of the concrete
8.8. NON-DESTRUCTIVE TEST
Digital Schmitt To calibrate the surface hardening of the BS 1881 – 202 3,000.00+
18 Hammer surface by using vibration reaction (Per 1986 Travelling
point with 9 shots)
To determine the cover blocks thickness 3,000.00+
19 Rebar Locator and spacing of the reinforcement which Travelling
are buried on the concrete (per Sq. meter)
8.9. AGGREGATES
The degree of flakiness and elongation to
Flakiness Gauge determine to avoid the low workability of BS 812 – 1,600.00
20 concrete mix and long-term durability 105.1:1989
barriers
Measure the ratio of length to width of BS 812 –
21 Length Gauge individual particles as described in 105.2:1989 1,600.00
EN 933-4
AIV impact value is to determine various
AIV mechanical characteristic that need to be BS 812 – 3,150.00
22 known in order to select the most suitable 112.1:1990
economic type of aggregate
Office of the Deputy Chief Secretary - Engineering Services, NP Page 200
Material Testing Rate 2025
Test
No Instruments Test Standard/ Rate (Rs)
Method
8.10. ASPHALT
To the determination of road asphalt,
Bitumen liquid asphalt emulsified asphalt
23 Penetrometer distillation or evaporation residue ASTM D5 2,700.00
penetration
Mot Edge To measure irregularities on road 2,700.00
24 pavement, floors, concrete pavements
Coating Gauge Find out the coating thickness of 700.00
25 Aluminium partition (Per Sample)
8.11. SOIL SAMPLING
SO - 1 Hand Augering, 0.0 - 1.5m BS 1377 Part 2,850.00+
26 2:1990 Travelling
SO - 2 Hand Augering, 1.5 - 3.0m BS 1377 Part 3,200.00+
27 2:1990 Travelling
SO - 3 Hand Augering,3.0 - 4.5m BS 1377 3,550.00+
28 Part2:1990 Travelling
SO - 4 Collecting a disturbed sample BS 1377 Part 200.00 +
29 2:1990 Travelling
SO - 8 Collecting a undisturbed sample BS 1377 Part 3,500.00+
30 2:1990 Travelling
Office of the Deputy Chief Secretary - Engineering Services, NP Page 201