BEFORE THE TAMIL NADU REAL ESTATE APPELLATE TRIBUNAL
(TNREAT)
(Tamil Nadu, Puducherry, Andaman & Nicobar Islands)
(Under the Real Estate Regulation And Development Act 2 0 1 6 )
Reserved o n : 2 1 . 0 7 . 2 0 2 3
Delivered o n : 3 1 . 0 7 . 2 0 2 3
Coram : H o n ' b l e Mr.Justice M.Duraiswamy, Chairperson
Mr.R.Padmanabhan, Judicial Member
Appeal Nos. 1 8 and 1 9 of 2023
A. No. 1 8 of 2023
Vijay Shankar Venugopal
rep. by his P . 0 . A . Holder
S.K.Balasubramanian ... Ap p e ll ant
- Vs
1. M / s . R G E Constructions and Development Pvt. Ltd.,
rep. by its Directors
a) Srin i vasan V a sud e van
b) Pradeep N enumal Lala
c) Jagade esh Babu R amanathan
2. Niranjana R ama k rishnan
A uthor iz ed Si g nator y of M / s . R G E Constructions
and D evelopment Pvt. Ltd . . .. Res p ondents
&
1/9
A . N o . 1 9 of 2023
S . K . Balasubramani an ... Appellant
- Vs -
1. M / s . R G E Constructions and Development Pvt. L t d . ,
Rep. by its Director
a) Srinivasan Vasudevan
b) Pradeep Nenumal Lala
c) Jagadeesh Babu Ramanathan
2. Niranjana Ramakrishnan
Authorized Signatory of M/ s. RGE Constructions
and Development Pvt. Ltd. ... Respondents
Prayer:
Appeals filed under Section 44 of the Real Estate (Regulation and
Development) Act, 2016 against the common order of dismissal of the
complaints in C . C . P . N o s . 6 2 and 63 of 2020 dated 1 3 . 0 2 . 2 0 2 3 on the file
of the Single member, TNRERA and to grant the reliefs sought for in
both the complaints by ordering refund of the advance amount with
interest as prayed for.
For Appellants in both the appeals : Mr. R. Ramasubramaniam Raja
For Respondents in both the appeals: No appearance
COMMON ORDER
The brief facts that are relevant for the disposal of the above
appeals are as follows:
2/9
1. In these two appeals the facts and circumstances are similar to
each other and common questions are involved in these two appeals.
Hence we decided to dispose both the appeals by a common order.
2. The appellant, Vijay Shankar Venugopal in A . N o . 1 8 / 2 0 2 3 is the
son-in-law of the appellant S.K.Balasubramanian in A.No.19/2023. In
the year 2 0 1 2 they booked two separate three bed room apartments,
each one, in their individual name, in the residential project by name
'Embassy Residency' promoted by the 1 respondent/promoter. As per
the construction agreement the respondents agreed to hand over
possession within three years. lnspite of the expiry of seven years as of
2 0 1 9 possession was not handed over to the appellants.
3. It is the case of the appellants that the respondents obtained
partial completion certificate dated 13.04.2017 from the CMDA and
invited the appellants for inspecting the apartments. The appellants
inspected the apartments and found that the construction of
apartments was not completed in full and that the apartments were
not fit for habitation. According to the appellants the quality of
construction was very poor. Expressing their concern over the poor
construction quality the appellants sent various emails to the
respondents. Several hundreds of emails were exchanged between the
parties in this regard from April 2 0 1 7 to April 2 0 1 9 .
4. To give a quietus to the dispute the appellants vide their email
dated 2 7 . 0 4 . 2 0 1 9 expressed their willingness to take possession "Under
Protest". However, the respondents vide their email dated 0 3 . 0 5 . 2 0 1 9
rejected the request of the appellants by stating that handing over of
possession " U n d e r Protest" was against their company's procedure. The
appellants vexed with the adamant attitude of the respondent, decided
3/9
to cancel their booking on the ground of poor quality of construction
and delay in handing over of the apartments. The appellants, vide
registered letter dated 03.12.2019, conveyed their decision to cancel
their booking and demanded refund of the entire amount paid by them
with interest and compensation. For which the respondents sent a
formal reply to the appellants on 11.12.2019 without saying anything
on the demand of refund.
5. Left with no other option, the appellants preferred separate
complaints before the Adjudicating Officer, TNRERA in C . C. P . N o s . 6 2 /
2020 and 63 of 2020 with prayer to refund the amounts paid by them
with interest and for compensation. The said complaints were originally
tried by the Adjudicating Officer and later transferred to the Single
Member of TNRERA in view of the judgment of the Hon'ble Supreme
Court of India i n Newtech Promoters and Developers Pvt. Ltd. Vs State
of U . P . &Ors.
6. The Single Member, TNRERA, after hearing both sides, by his
common order dated 13.02.2023 dismissed both the complaints by
concluding that the appellants already took possession of the
apartments in the year 2 0 1 9 and therefore they are not entitled to ask
for refund of the amount paid by them. Moreover, accepting the case
of the respondents, the Single Member directed the appellant in
A.No.18/2023 namely, Vi jay Shankar Venugopal to pay a sum of
Rs.1,32,139/- towards the balance amount due to the respondents,on
account of improper calculation of interest. Likewise the Single
Member, also directed the respondent to pay a sum of Rs.3,56,327/
due to the appellant in A . N o . 1 9 / 2 0 2 3 namely S . K . B a l a s u b r a m a n i a n , on
account of improper calculation of interest. Further, the Single
4/9
Member, TNRERA gave liberty to the appellants to move the
Adjudicating Officer for compensation on the ground of delay in
handing over of possession. Aggrieved over the common order passed
by the Single Member, TNRERA the appellants have filed these appeals.
7. The notice ordered to Respondents in both the appeals were
duly served on the Respondents through Registered post. As permitted
the private notice sent by the counsel for the appellants was also
served on the respondent. lnpsite of service of notice through both
ways and inspite of sufficient time granted for entering appearance,
the respondents failed to appear either in person or through their
counsels.
8. Heard the counsel for the appellants. Records perused. We
have carefully perused the impugned o r d e r . I n paragraph No. 9(a) of the
impugned order, the Single Member had observed as follows,
"It is very clearly in this two CCPs the date of
delivery as per the construction agreement was
28.02.2015, whereas in both the CCPs the possession
had been handed over on 2 0 1 9 (as admitted by the
complainants in the complaint at page 9 paragraph
16 in both the CCPs)"
We have examined the complaint in this regard. The appellants
nowhere in their complaints have admitted either directly or
indirectly that they have taken possession of the apartments. The
relevant portion in paragraph 16 of the complaint is extracted
below.
"But the respondents have miserably failed to
provide the facilities as mentioned in the
5/9
construction agreement and the respondents are
forcing the applicant to take the possession of the
apartment in the year 2 0 1 9 . "
The Single Member of TNRERA completely misunderstood the above
averments made by the appellants at page 9 paragraph 16 of their
complaint. It is not even the case of the respondents, that they have
handed over possession to the appellants at any point of time. Even in
their reply letter dated 11.12.2019 (ExA8), issued by the respondents to
the cancellation letter d t . 0 3 . 1 2 . 2 0 1 9 (EA7) issued by the appellants, the
respondents have not stated anything about the handing over of
possession. The Single Member, TNRERA omitted to take note of these
two letter correspondences marked as Ex.A7 and Ex.AB on the side of the
complainants in both the cases. Had these two letter correspondences
were brought to the notice of the Single Member, he would have come to
a different conclusion. Therefore the impugned order is liable to be set
aside.
9. Let us now consider afresh, the entitlement of the appellants
for refund of the amount paid by the appellants on various dates, along
with interest from the date of respective dates of payments till date of
actual refund. There is no dispute between the parties with regard to the
execution of sale agreement and construction agreement on 18.04.2012
and subsequent registered sale deed with regard to LIDS share on
13.07.2015. Admittedly the apartments though booked on 18.04.2012,
were not handed over to the allottees even after the lapse of seven years
till January 2020 i . e the month in which the complaints were preferred.
Subsequent to the issuance of partial completion certificate by the CMDA
on 13.04.2017, at the invitation of the respondents, the appellants
6/9
inspected the project premises. After such inspection the allottees have
noticed some important defects to be rectified. In this regard several
hundreds of email communications were exchanged between the parties
from April 2 0 1 7 to April 2019.
10. As there was no progress for two years and with a view to give
a quietus to the dispute, the appellants who are at the receiving end,
came forward to take possession of the apartments "Under Protest. This
was evident from their email dated 27.04.2019. However, the
respondents vide their email dated 03.05.2019 bluntly rejected the
re qu e st of the a pp e ll an t s by stating that handing over of p ossess i on
" U n d e r Protest" was a ga in s t their compan y' s proced u re.
11. U n a bl e to take possession of the apartments , the appellants
have can c e ll ed their b oo k in g a nd demanded refund of the amo u nts paid
by them with i nterest an d compensation, vide their detai l ed letter dated
03.12.2019 (Ex.A7). In this letter the a pp ellants have ju sti fi ed the
cance ll at i on by h i g hl i g h t i n g the inade qu ate ca pacity of water treatment
and sewage treatment p l an and also the im p roper water s upp l y .
Moreover, in the same letter the appellants have expressed their
diss at isf actio n over t h e s tr u ct u ra l stability of the bu il din g and raised their
d ou b t s over the q u al it y of e l ectrica l wirin g, fire - fi g htin g e qu i p ment and
the lifts i nsta ll ed in the b u il d i n g . Even after the receipt of the letter of
c an c e ll ation from the a ppe lla nts , the respondents sent a brief and v agu e
re ply letter on 11.12.2019. Though the re ply letter reads that a detailed
reply w ill be sent wi thin 20 da y s , no such detailed reply letter was iss u ed
by the res p ondents .
12. As no detailed r e pl y was received from the res p ondents , the
a p pe ll a n t s have set the law in motion and preferred separate com p laints
7/9
before the Adjudicating Officer on 29.01.2020 which was later
transferred to the Single Member, TNRERA. In a dispute between an
allottee and the promoter the interest of the allottee is paramount. The
Real Estate (Regulation and Development) Act, 2016 has been enacted
with a view to protect the interest of the consumers in the real estate
sector. As per Section 18 of the Act, 2016 if the promoter fails to
complete or is unable to give possession of an apartment, plot or building
in accordance with the terms and agreements for sale, the promoter shall
be liable on demand to the allottees , in case the allottees wishes to
withdraw from the project, without prejudice to any other remedy
available, to return the amount received by him in respect of the
apartment, plot, building as the case may be with interest at such rate as
may be prescribed in this behalf including compensation in the manner as
provided under the Act, 2 0 1 6 .
13. I n the case on hand the respondents/promoters unable to give
possession as per the construction agreement dated 18.04.2012 even
after the expiry of seven years as of 2019. The failure to hand over
possession for seven years without any reasons by the promoter gave the
appellants/ allottee the right to cancel the booking. Therefore the
appellants are entitled for refund of the amount paid by them with
interest.
14. Coming to the quantum of refund, as per the revised
calculation statement (Ex.A 1 2 ) filed by the appellant in A.No.18/2023
before the TNRERA (Refer Typed set Volume IV page 640 in A.No.18 of
2023) a sum of Rs.1,14,32,198/- inclusive of interest @9% p.a. upto
3 1 . 0 1 . 2 0 2 0 was found due to Vijay Shankar Venugopal, the appellant in
A.No.18/2023. Likewise, as per the revised calculation statement(Ex.A12)
8/9
filed by the appellant in A . N o . 1 9 of 2023 before the TNRERA (Refer Typed
set Volume IV page 626 in A.No.19 of 2023) a sum of Rs.1,18,97,357/
inclusive of interest @9% p.a. upto 31.01.2020 was found due to
S.K.Balasubramanian the appellant in A.No.19/2023. In both cases the
respondents have not filed their statement of calculation or disputed the
correctness of the statements of calculation filed by the appellants.
Therefore, the respondents are liable to refund the amount as per the
statement of calculations filed and marked as Ex.A 1 2 in both cases.
15. I n the result both the appeals are allowed with the following
directions.
Appeal No. 1 8 of 2023
I n so far as the A . N o . 1 8 of 2023 is concerned, we hereby direct the
respondents to pay a sum of R s . 1 , 1 4 , 3 2 , 1 9 8 / - (inclusive of interest at 9%
upto 31.01.2020) to Vijay Shankar Venugopal the appellant in
A. N o . 1 8 / 2 0 2 3 w i t h future interest at 9% to be calculated on the principal
amount from 0 1 . 0 2 . 2 0 2 0 till the date of actual refund.
Appeal No. 1 9 of 2023
In so far as the A.No. 19 of 2023 is concerned, we hereby direct
that the respondents to pay a sum of R s . 1 , 1 8 , 97,357/-(inclusive of
interest at 9% upto 3 1 . 0 1 . 2 0 2 0 ) to S.K.Balasubramanian, the appellant in
A. N o . 1 9 /2023 with future interest at 9% to be calculated on the principal
amount from 0 1 . 0 2 . 2 0 2 0 till the date of actual refund.
Sd./- XXXX
CHAIRPERSON
Sd./- xxxx
JUDICIAL MEMBER
9/9