Roopa Estimation

The document is a detailed estimate for a residential building project prepared by Praveen L, covering the costs for various construction activities including excavation, masonry, RCC work, and finishing. The total estimated cost for the project is 35,00,000 INR. The estimate includes itemized costs for materials, labor, and additional charges for electrification and sanitary works.

Uploaded by

lokeshkumarm5559
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views3 pages

Roopa Estimation

The document is a detailed estimate for a residential building project prepared by Praveen L, covering the costs for various construction activities including excavation, masonry, RCC work, and finishing. The total estimated cost for the project is 35,00,000 INR. The estimate includes itemized costs for materials, labor, and additional charges for electrification and sanitary works.

Uploaded by

lokeshkumarm5559
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

PRAVEEN . L (B.

E (CIVIL))
REG NO -RMN-LBPAS-LBPAS-REG-10016

DETAILED ESTIMATE FOR GROUND FLOOR,FIRST FLOOR & SECOND FLOOR


, RESEDENTIAL BUILDING AT CITY MUNICIPAL KATHA NO.109/1B/11, SITE
NO. 11, #218B,#T,DYAVARASE GOWDANA DODDI ROAD, BLOCK-4,WARD NO.1,
VADERAHALLI, RAMANAGARA TOWN, RAMANAGARA DISTRICT.

OWNER NAME : Mrs.ROOPA

01. Earth work excavation for foundation in ordinary soil


106.58m3x@Rs 250/- 26,645.00

02. P.C.C-1:4:8 for foundation


58.00 X 0.60 X 0.60 = 20.88 m3
20.88m3x@ Rs.1100/- 22,968.00

03.S.S Masonry in foundation 1:6


38.00 X 0.60 X 0.60 = 20.88 m3
38.00 X 0.60 X 0.60 = 20.88 m3
41.76m3X @Rs 950/- 36,700.00

04. RCC -1.2-4 in plinth concrete


23.12m3 x Rs 5000/- 1,28,500.00

05. Shuttering Roof & Beam


118.00 X 0.60 X 1.0 = 70.88 m3
78.00 X 0.60 X 1.0 = 40.88 m3
110.55-00m2 x@Rs2320/- 1,88,320.00

06.PCC-1:4:8 for flooring


58.00 X 0.60 X 0.60 = 20.88 m3
7.14 x9.19 [email protected]/- 54,000.00

07. 0.23 thick TMB masonry in CM-1:6 in (D-50)


superstructure

1 x140.00x0.23x2.85 =91.88m3

Deductions:-
Doors-4 x0.90 x0.23 x2.10 = -1.47m3
- 1 x1.10 0.23 X2..10 = -0.53m3
Windows - 4x1.50x1.35x0.23 = -1.86m3
2 x1.35 XL 10x0.23 = -1.65 m3
2 x6.46 m3

Net qty =45,88-13-12.92 72.96 m3 x @Rs. 1,750/- 1,22,500.00


PRAVEEN . L (B.E (CIVIL))
REG NO -RMN-LBPAS-LBPAS-REG-10016
08. RCC 1:2:4 for lintels, Beams & Columns

1 x 140.00 x 0.23x0.15 = 4.41m3


1 140.00 0.23 0.23 = 7.22 m3
37.631m3 [email protected]/- 1,38,417.00

09. 75mm thick RCC -1.2:4 chejjas for d/w openings


1 x 33.76 x0.60 -84.52 m3 x @ Rs 1450/- 1,24,250.00

10. Neem wood frames for doors & windows

D1 - 1.05 X2.10 X 2 = 4.20m2


D2 -0.9 X2.10 X4 Nos =6.78 m2
D3 -0.75 x 2.10 4 Nos = 6.15 m2
W -1.50 x1.35 x 14 Nos =28.17 m2
46.17 m2 x 0.05 0.69
10.6 m3 x@Rs 3,214/- 78,600.00

Shutters:Honne wood
D-10 x1.00 x2.00 =20.00
W - 14 x 1.5x 1.30 =26.65
V -4 x0.60 x0.40 = 0.9
48.13m2 x @Rs681/- 48,100.00

11. External wall plastering in CM-1:6 sponge


finish. 18mm thick
140.00 X3.2 = 262.00m2 x @Rs.420/- 45,770.00

12. W/P plastering for top of chejjas


88,730.00
100.00 x 0,60 =600.00 m2 @ Rs.238/-

13. RCC-1:1.5:3 for roof slab & portico.


1x14.14 18.1980.125 14 87m3@Rs 4135/-
1 x 250 x0.12 6.53m3
30.00m3 65,000.00

14. a)Inside wall plastering in lime rendering


in CM 1:3 12mm Thick
9.68+6.96+12.20+4.88+12.00+4.50+12.20
+2.96+3.66-69.22 x 3.00=207.66m2 x 2=415.32m2+420m2

Deductions:
D1-3 X 1.05 X 2.10 = -1.10m2
D2-6 x 0.5 x 0.90 x2.10 = -1.89m2
D3-4 x 0.5 x 3 x 0.75 x 2.10 = -3.15m2
WI-0.5 X 0.75 X 2.10 -1.012
W2-2x0.5x1.5x 1.00 = -1.50m2
PRAVEEN . L (B.E (CIVIL))
REG NO -RMN-LBPAS-LBPAS-REG-10016
V-3 x 0.5x 0.90x 0.60 = -081m2
9.46m2

415.32-15.32 =110.00 m2 x Rs202/- 25,000.00

15. Providing Kitchen granite slab sink anti skid flooring &
Dadoing etc, L/S 2,65,000.00

16. Painting interior &exterior polishing for doors & windows 48,200.00
Glass & fittings L/S

17. Interior works / wood works in gf,ff & sf 7,50,000.00

18.Steel requirement
8.60 x M.T X @ Rs.61,200 5,30,000.00

19. Window grills SS ralings etc.,1400kg x@ Rs.420/- 42,000.00

20.Providing & Constructing RCC stair case L/S 3,30,000.00

21.Electrification charges 7.50% of Estimated cost 2,35,000.00

22.W/S Sanitary charges sump, O.H.T etc, L/S -6% of the Estimated cost 65,000.00

23.Miscellanious & Expenditures. 41,300.00

TOTAL AMOUNT 35,00,000.00

(RUPEES THIRTY FIVE LAKHS ONLY)

ESTIMATE PREPARED BY :