Estimate
Estimate
VAT 13%
#NAME?
CONTINGENCIES 7% 7%
#NAME?
GRAND TOTAL
#NAME?
ABSTRACT OF COST
Project: Steel Bridge (Dugurne Paani, Mahadev Khola)
Location: Sesmati, Tarkeshwor, Kathmandu
[Link]. Description of Works Unit Quantity Rate(NRs.) Amount (NRs.)
6 8 48.00
Total 48.00 m 5853.00 280944
Providing and laying Dry-stone soling in foundation work, lead
A.4 30m,lift 1.5m with stone size not less than 0.01m3 including levelling
etc. complete.
Total 2 area= 8.22 0.2 3.29 m3 4278.14 14075.0806
Supply and place lean concrete M10 including dewatering, mixing,
A.5
laying,compacting and curing all complete.
Right abutment 1 3.5 1.5 0.15 0.79
Left abutment 1 3.5 1.5 0.15 0.79
Total 1.58 m3 11739.67 18548.6786
Supplying, lying and placing concrete M25 including dewatering,
A.5
mixing, laying,compacting and curing all complete.
Abutment
Abutment Foundation 2 3.500 1.500 0.600 6.30
Abutment stem 2 2.83 0.53 6.00 18.00
Piles
dia = 0.40
6 Area= 0.13 8.00 6.24
Total 30.54 m3 20724.22 632917.6788
A.6 Supplying, Cutting, bending, placing of reinforcement (Fe 500 bars) in
position as shown in the drawings and binding by wires as specified in
the specification.
Abutment and Pile Cap 2 771.000 1542.00
Piles 6 108.000 648.00
Total 1542.00 Kg 100.06 154292.52
1.54 ton
Supply and place form works for substructure and removal after
A.7 completion.
Abutment
Abutment stem 2 perimeter= 6.72 6.00 80.64
Abutment Foundation 2 perimeter= 10.00 0.60 12.19
B Superstructure
B.1 Supply, Fabrication,erection, protection , installation, coating of Mild
Steel Section and Connections all complete as per design and
drawings
Main Girder Nos length (m) kg/m Kg
Web (ISMC100) 2 56.000 9.560 1070.720
Top Cords 2ISMC200 BtoB) 2 13.000 44.6 1159.600
Bottom Cords( 2ISMC200 BtoB)) 2 13.000 44.6 1159.600
Joists (ISMB100) 27 2.100 8.900 504.630
top Joists (ISMB100) 9 2.100 8.900 168.210
longer Joists (2ISMC100 BtoB) 5 3.250 19.120 310.700
Side Struts (2ISMC100 BtoB) 10 1.875 19.120 358.500
Cross Struts (2ISMC100 BtoB) 8 3.900 19.120 596.544
Side Rails (ISNB40M) 6 13.000 3.560 277.680
Total 5606.184 Kg
Connection Plates and Angles 1 15% 840.928 Kg
Anchors and bolts 1 5% 280.309 Kg
Total 6727.421 Kg 164.56 1107064.3998
6.727 MTon
Decking
i 1 2.000 13.000 0.006 0.156
[Link]. 7850.000 kg/m3
Total 1224.600 Kg 164.56 201520.176
1.225 MTon
Approach Slab
Supply and place concrete M25 including dewatering, mixing,
laying,compacting and curing all complete. 2 2.000 3.000 0.150 1.800
Total 1.800 m3 15356.58 27641.844
Supplying, Cutting, bending, placing of reinforcement (Fe500 bars) in
position as shown in the drawings and binding by wires as specified in
the specification. 2 177.000 177.000 Kg 100.06 17710.62
0.177 MTon
Bearings
Providing and installing different types of Bearings including all
necessaary axilliary and incidental works etc. complete as per
drawing and specification. 4 4.000 Nos. 45,627.92 182,511.68
Roadway
Sub Total 3161893.8541
13%VAT for material cost
Item. Description of items Qty Qty/Unit Unit Rate Amount
1 Piling
bentonite 48 12.000 kg 20.000 11520
2 piling rig ( with all accessories) 48 0.500 hr 3000.000 72000
crane 48 0.500 hr 3654.290 87702.96
Bentonite pump 48 0.400 hr 500.000 9600
3 Stone Soling
Stone 3.29 1.20 cum 2577.63 10176.48324
4 PCC M 10
Cement 1.58 4.40 bag 825.00 5735.40
Aggregates ( 20 -40 mm ) 1.58 0.89 cum 3354.45 4717.03
Sand 1.58 0.47 cum 3213.21 2386.13
5 PCC M25
Cement 32.34 0.61 Mt 16500.00 325502.10
Aggregates ( 20 mm ) 32.34 0.64 cum 3354.45 69429.06
Aggregates ( 10 mm ) 32.34 0.21 cum 3213.21 21822.19
Sand 32.34 0.425 cum 3213.21 44163.96
7 Reinforcement for RCC( Tore steel )
Tor steel 1719 1.05 kg 85 153420.75
Binding wire 1719 0.01 kg 99 1701.81
8 Water proof plywood 93 0.005 cum 50905.250 23670.94125
Nails 93 0.100 Kg 120.000 1116
Strut /Batten 93 0.002 Cum 50905.250 9468.3765
9 Stone Masonary 1:4 C/S
Stone 22 1.1 Cum 2577.63 62378.646
sand 22 0.47 Cum 3213.21 33224.5914
cement 22 2.32 Bag 825.00 42108
10 Iron Angle/I section fabrications 7952 1.000 Kg 87.000 691824
12 Bearing 4.00 1 Nos. 45627.92 182511.68
Sub Total(Material cost) 1866180.1084
13 % VAT 242603.41409
Grand Total 3404497.2682
Page 8 of 23
Rate Analysis
Project: Steel Bridge (Dugurne Paani, Mahadev Khola)
Location: Sesmati, Tarkeshwor, Kathmandu
EXCAVATION IN FOUNDATION
Description of works: Excavation in foundation in all types of soil,all complete including dewatering/diversion/dam/lift and haulage [upto 6m depth] Unit : 1 m3
Spec. cl. No: 903 & 907
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
9.07.01 Unskilled md 4.000 790.00 3160.00 of labour
tools and equipments 3.00% 94.80
cost
Sub total of A = 3160.00 Sub total of B = 0.00 Sub total of C = 94.80
Sub total of A +B + C = 3254.80
Contractors overhead 15% 488.22 It has been assumed that average depth of foundation is 4m and can be used upto 6m depth Unit Rate = 3743.02
9.08 Hw:Df Fine Graded soil Rate
<0 0 3743.02 Note:
0-0.2 7% 4005.03 i)Height of water table/level from the bottom of foundation during working season.
0.2-0.4 14% 4267.04 ii) Df- Depth of the bottom of foundation from the ground.
0.4-0.6 20% 4491.62 iii) This is applicable when depth of water above ground level is less than 0.5m. For greater
0.6:0.8 30% 4865.93 depth of water above ground level,separate norms specific to site condition has to be
0.8:1 40% 5240.23 developed
>1 50% 5614.53
Page 9 of 23
Description of works: Providing and placing machine mixed cement concrete of M25/20 for the founation and footing etc. including compaction,curing,testing and lead 30m
etc all complete as per specification Unit : 1 m3
Spec. cl. No: 2000
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
20.01.v Skilled md 0.500 1080 540.00 cement t 0.38 16500 6187.50 mixer (0.28/ 0.20 m3 ) hr 0.60 654.29 392.574
unskilled md 3.500 790 2765.00 Aggregate 20-40mm m3 0.58 3316.32 1923.47 vibrator hr 0.25 304.29 76.0725
Aggregate 10-20mm m3 0.30 3139.92 941.98
coarse sand m3 0.45 3104.64 1397.09
petrol lit 0.10 104 10.40
diesel lit 3.00 83 249.00
water lit 225.00 0.3 67.50
Sub total of A = 3305.00 Sub total of B = 10776.94 Sub total of C = 468.65
Sub total of A +B + C = 14550.59
2.5% of cost of concrete for mix design and 363.76
quality control=
Total= 14914.35
Contractors overhead 15% 2237.1525 Unit Rate= 17151.50
Page 11 of 23
Description of works: Providing and laying Reinforcement of dia. Above 16mm including cutting,bending,fixing in position and lead [Link]. all complete as per
specification Unit : 1 MT
Spec. cl. No: 2000
Norms No. Labour (A) Material (B) Equipment (C)
[Link] skilled md 9.00 1080 9720.00 Reinforcement t 1.15 91000.00 104650.00
unskilled md 9.00 790 7110.00 Binding Wire kg 9.00 103.00 927.00
Sub total of A = 16830.00 Sub total of B = 105577.00 Sub total of C = 0.00
Sub total of A +B + C = 122407.00
Contractors overhead 15% 18361.05 Unit Rate = 140768.05
BACKFILLING
Description of works: Providing and filling with graded gravel filter material in layers with necessary watering and [Link] 30m,lift 1.5m.
Unit : 1 m3
Spec. cl. No: 2404 & 3110
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Unskilled md 0.80 790 632.00 Graded filter material m 3
1.10 1166 1282.60
24.11
Description of works: Providing and laying RRM in cement mortar (1:4) including scaffolding, curing, preparation of mortar etc., all complete as per drawings and
Unit : 1 m3
Spec. cl. No: 2602,2603,260technical specifications
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
26.03 Skilled md 1.40 1080 1512.00 cement t 0.124 16500.00 2046.00 mixer (0.28/ 0.20 m3 ) hr 0.15 654.29 98.14
Unskilled md 2.80 790 2212.00 Sand m3 0.348 3104.64 1080.41
3724.00 Stone m3 1.150 3316.32 3813.77
3% of total labour cost for T&P 111.72 Diesel lit 1.000 83.00 83.00
Water lit 100.000 0.30 30.00
Sub total of A = 3835.72 Sub total of B = 7053.18 Sub total of C = 98.14
1.5% of cost
Sub total of A +B + C = 10987.04 Mix Design and Quality Control= 164.8056
of concrete
Total= 11151.85
Contractors overhead 15%= 1672.7775 Unit Rate= 12824.63
Page 15 of 23
PILLING WORKS
Description of works: Providing, Boring and installing bored cast-in-situ RCC Pile excluding Reinforcement and Concrete in all types of soil including Bentonite and other
consumable and removal of excavated earth with necessary lifts and lead all complete as per Drawing and Technical Specifications. [dia 400] Unit :5 Rm
Spec. cl. No: 1612
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
piling rig ( with all
16.01.B skilled md 1.000 1080.00 1080.00 bentonite kg 60 20.00 1200 hr 2.50 3000.00 7500.00
790.00 5530.00 accessories)
unskilled md 7.000 crane hr 2.50 3654.29 9135.73
Bentonite pump hr 2.00 500.00 1000.00
Sub total of A = 6610.00 Sub total of B = 1200.00 Sub total of C = 17635.73
Sub total of A +B + C = 25445.73
Contractors overhead 15% 3816.86 Unit Rate= 5852.52
pile depth is assumed to be greater than 15m
Page 16 of 23
Description of works: Providing and laying Dry-stone soling in foundation work, lead 30m,lift 1.5m with stone size not less than 0.01m3 including levelling etc. complete.
Unit : 1 m3
Spec. cl. No: 2406(2,5)
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
24.03.01 Skilled md 0.60 1080 648.00 Stone m3 1.100 3316.32 3647.95
Unskilled md 2.00 790 1580.00
Mild Steel
Description of works: Fabricating and Providing structural steel components / elements including nut, bolt, gusset plate, shop drawings, facilities for inspection & testing
and trial assembling for built-up-beams,plate girders etc including corrosion protection works all complete. Unit : 1 Ton
Spec. cl. No: 2203
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Cutting,drilling ,grinding,wel l.s. 5% of the
Engineer md 0.50 1155.00 577.50 Steel t 1.05 89000.00 93450.00 ding machine etc. cost of 4672.50
22.01.02.a steel
Technician md 1.00 970.00 970.00 Nuts & bolts/ Rivetts no 0.00
Consumables(gas,elect l.s. 5% of
skilled md 3.0 1080.00 3240.00 rodes,drill bits etc.) cost of 4672.50
steel
Semi-skilled md 4.5 890.00 4005.00 Galvanization t 1.0 42000.00 42000.00
Unskilled md 4.5 790.00 3555.00
Description of works: Assembling and erecting fabricated structural steel components / elements in place including tying down bolts, nuts, rivets etc. complete as per
drawing. (False work not included) Unit : 1 Ton
Spec. cl. No: 2208
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
22.02.02 Engineer md 0.50 1155.00 577.50 Diesel lit 15.0 83.00 1245.00 20t-cap crane hr 1.5 3654.29 5481.44
Technician md 1.00 970.00 970.00
skilled md 3.0 1080.00 3240.00
Semi-skilled md 6.0 890.00 5340.00
Unskilled md 6.0 790.00 4740.00
(Please note that only the rates relevent to us in this project have been adjusted)
1) Labour 4) Material
9 Loader hr. 1200.00 154.29 1354.29 11 GI Pipe 50mm medium class rm 537.00 537.00
15 Pneumatic Tyred Roller hr. 1200.00 154.29 1354.29 17 bentonite kg 20.00 20.00
16 mixer hr. 500.00 154.29 654.29 18 Planks 38mm thick. m3 300000.00 300000.00
17 Vibrator hr. 150.00 154.29 304.29 19 struts, ballies, etc. m3 300000.00 300000.00
Measurement
[Link]. Description of works Nos Quantity Unit
L(m) B(m) H(m) Rate Amount Remarks
Earthwork in excavation by mechanical means of Foundation
of structures, including construction of shorring and bracing,
1 removal of stumps and other deleterious matter and backfilling
with aproved materials as per drawing and technical
specification.