Electric Rates
Electric Rates
Electric rates
The electric service rates listed in this
brochure reflect the rates authorized by the
Public Service Commission of Wisconsin
(PSCW) for Wisconsin Electric Power
Company doing business as We Energies.
Rate options
We recommend you review the rate options and prices listed in this
brochure. Your current rate description is listed on your bill. Compare
this rate description to the other rate options described here. You
may also visit www.we-energies.com for pricing information. While
you are the best judge of which rates are right for your situation,
we’ll be glad to help you compare rate options.
Renewable energy rates
Customers have the option to participate in the Company’s Energy
for Tomorrow® renewable energy program. The program gives
customers the option to pay a premium for the Company to obtain
generation fueled by renewable resources. Use of renewable energy
resources has a positive impact on the environment and reduces the
consumption of non-renewable resources.
Time-of-Use rates
Many customers may benefit from our Time-of-Use rate option. With
Time-of-Use, you pay a lower rate when the demand for electricity
is low (weeknights, weekends and holidays) and a higher rate when
demand is high (weekdays on-peak hours).
Each Time-of-Use rate has its own on-peak and off-peak periods.
All time periods as stated are the prevailing time Monday through
Friday, excluding those days designated as the legal holidays for
New Year’s Day, Memorial Day, Independence Day, Labor Day,
Thanksgiving Day and Christmas Day. The off-peak periods consist of
all hours not designated as on-peak.
A Time-of-Use rate is mandatory for residential customers whose
annual consumption exceeds 60,000 kWh. However, residential
customers mandated to the residential Time-of-Use rate have the
option to opt out of that Time-of-Use rate.
Extra meter charges
The Company generally supplies no more than one service drop/
lateral to a premise and not more than one meter. The monthly
charge for each additional meter will either be an additional
facilities charge or an extra meter charge. The determination for
such charge will be in accordance with the Company’s approved
Rules and Regulations, Volume 17, Section 103.1.
Environmental Control Charge
Consistent with an order issued by the PSCW, Environmental Trust
Bonds in the amount of $118,814,000 were issued on May 12, 2021,
by a special purpose entity (SPE) assignee of Wisconsin Electric
Power Company (doing business as We Energies) to securitize a
portion of the remaining undepreciated investment in environmental
control property installed at the retired Pleasant Prairie Power
Plant, plus related upfront financing costs. The issuance of
environmental trust bonds results in savings to customers due to the
lower financing costs associated with the bonds compared to the
company’s average cost of capital.
Your bill includes an Environmental Control Charge (ECC). This charge
is a non-bypassable charge to recover the costs of the environmental
control property secured with the environmental trust bonds and
its related carry and financing costs. The monies collected through
the ECC are the property of the SPE; not We Energies. The ECC will
remain in effect until all costs associated with the environmental
trust bonds have been paid in full and shall be adjusted periodically
as prescribed by PSCW order.
Service charges
• A
ll customers are subject to a late payment charge of 1% per
month on all amounts past due.
• A $15 service fee is charged for all returned checks,
plus additional bank charges that may be incurred.
Residential and Farm (Rg1, Fg1)
Facilities Charge, per day:
Single-phase/Three-phase service. . . . . . . . . . . . . . . . . . . $.52602
Additional meter. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05951
Energy Charge, per kWh. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.13724
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . . . . . . . $.00064
Residential • Time-of-Use (Rg2)
Facilities Charge, per day:
Single-phase/Three-phase service. . . . . . . . . . . . . . . . . . . . $.52602
Additional meter. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05951
Energy Charge, per kWh:
On-peak energy*. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.19625
Off-peak energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.08868
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . . . . . . . . $.00064
*Customers have a choice of four on-peak periods: 7 a.m. to 7 p.m.,
8 a.m. to 8 p.m., 9 a.m. to 9 p.m., or 10 a.m. to 10 p.m.
Time-of-Use rates for farm customers
Time-of-Use Rates are available to farm customers. If both the
residential and commercial portions of the farm customer’s
service are served through one meter the farm customer may take
service under the General Secondary Time-of-Use Rate but not the
Residential Time-of-Use Rate.
Whole-House EV program (WHEV-R)
Available to customers taking service under rate schedule Rg-2
to provide electric vehicle charging equipment to service electric
vehicles. Customers may choose to have the electric vehicle
charging equipment installed and provided by the Company through
its Bundled Service option or customers may choose to pay the
Company for the installed cost of the charging equipment prior
to beginning service through its Pre-Paid Service option. Electric
vehicle charging will be charged with the customer’s home energy
usage which will both be billed under the same rate schedule, plus
the customer will pay the rate below based on the service option the
customer selects.
Fixed Service and Administration Charge, per Month: Bundled
Service $14.00 or Pre-Paid Service $5.00
Charger-Only EV program (COEV-R)
Available to customers taking service under rate schedules Rg-1
or Fg-1 to provide electric vehicle charging equipment to service
electric vehicle loads. Customers may choose to have the
electric vehicle charging equipment installed and provided by the
Company through its Bundled Service option or customers may
choose to pay the Company for the installed cost of the charging
equipment prior to beginning service through its Pre-Paid Service
option. Home energy usage will be billed based on rate schedules
Rg-1 or Fg-1 and the electric vehicle charging will be charged
based on the rates below.
Fixed Service and Administration Charge, per Month: Bundled
Service $18.00 or Pre-Paid Service $9.00
Energy Charge, per kWh: June-Sept. Oct.-May
On-peak $0.26357 $0.15140
Intermediate-peak $0.15140 $0.15140
Off-peak $0.06634 $0.06634
Subject to adjustment for cost of fuel consistent with the rate
schedule under which the customer is served for their home
energy usage.
Customers served on COEV-R will have the following on-,
intermediate-, and off-peak periods:
Starting time Ending Time Ending Time
On-peak 12 p.m. 8 p.m. Mon.-Fri.,
excluding holidays
Intermediate-peak 8 a.m. 12 p.m. All days
Intermediate-peak 8 p.m. 12 a.m. All days
Intermediate-peak 12 p.m. 8 p.m. Sat.-Sun.
and holidays
Off-peak 12 a.m. 8 a.m. All days
General Secondary (Cg1)
Less than 329 kWh per day
Facilities Charge, per day:
Single-phase/Three-phase service . . . . . . . . . . . . . . $.52602
Additional meter. . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05951
Energy Charge, per kWh. . . . . . . . . . . . . . . . . . . . . . . . . $.13214
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . . $.00058
General Secondary • Time-of-Use (Cg6)
Less than 329 kWh per day
Facilities Charge, per day:
Single-phase/Three-phase service. . . . . . . . . . . . . $.52602
Additional meter. . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05951
Energy Charge, per kWh:
On-peak energy*. . . . . . . . . . . . . . . . . . . . . . . . . . . . $.19814
Off-peak energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.08954
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . . $.00058
*The on-peak period is 9 a.m. to 9 p.m.
General Secondary • Demand Time-of-Use
(Cg2)
329 kWh per day for the month for any three months in a 12-month
period.
Facilities Charge, per day. . . . . . . . . . . . . . . . . . . . . . . $1.32000
Additional Meter, per day. . . . . . . . . . . . . . . . . . . . . . . $.18542
Energy Charge, per kWh:
On-peak energy*. . . . . . . . . . . . . . . . . . . . . . . . . . $.11152
Off-peak energy . . . . . . . . . . . . . . . . . . . . . . . . . . $.08287
Demand Charge, per kW:
On-peak demand*. . . . . . . . . . . . . . . . . . . . . . . . . $6.860
Customer demand . . . . . . . . . . . . . . . . . . . . . . . . . $2.00
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . $.00058
*The on-peak period is 9 a.m. to 9 p.m.
For monthly on-peak hours of use less than 100, the monthly
demand charge of $6.860 per kW will be reduced by $.04230
times the difference between 100 and the monthly on-peak
hours of use. Monthly on-peak hours of use is the on-peak
energy usage divided by the measured on-peak demand.
Monthly Minimum Charges: The Facilities Charge plus
the Meter Charge plus On-Peak Demand Charge plus the
Customer Demand Charge. For customers who received
an embedded credit, the charge for the minimum on-peak
demand shall be established by contract.
This rate is mandatory after a customer’s energy consumption
is equal to or greater than 329 kWh per day for the month for
any three months out of the past twelve month period. For
Cg1 and Cg6 customers who qualify to be mandated to the
Cg2 rate, if their off-peak energy consumption is on average
80% or greater of their total energy consumption for the most
recent twelve month period, that customer has the option to
be served under either Cg2 or Cg6.
General Secondary • Demand Time-of-Use
(Cg3)
986 kWh per day for the month for any three months in a
12-month period.
Facilities Charge, per day . . . . . . . . . . . . . . . . . . . . . $2.00000
Additional Meter, per day. . . . . . . . . . . . . . . . . . . . . . . $.20000
Energy Charge, per kWh:
On-peak energy*. . . . . . . . . . . . . . . . . . . . . . . . . . . . $.07135
Off-peak energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05088
Demand Charge, per kW:
On-peak demand*. . . . . . . . . . . . . . . . . . . . . . . . . . $15.184
Customer demand . . . . . . . . . . . . . . . . . . . . . . . . . . . . $2.55
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . $.00058
*The on-peak period is 9 a.m. to 9 p.m.
On-Peak Demand Adjustment: For monthly on-peak hours of use
less than 100, the monthly on-peak demand charge of $15.184
per kW will be reduced by $.09132 times the difference
between 100 and the monthly on-peak hours of use. Monthly
on-peak hours of use is the on-peak energy usage divided by
the measured on-peak demand.
Monthly Minimum Charges: The Facilities Charge plus the
Meter Charge plus On-Peak Demand Charge plus the Customer
Demand Charge. For customers who received an embedded
credit, the charge for the minimum on-peak demand shall be
established by contract.
This rate is mandatory after a customer’s energy consumption is
equal to or greater than 986 kWh per day for the month for any
three months out of the past 12-month period.
General Secondary • Curtailable (Cg3C)
THIS RATE CLOSED TO NEW ACCOUNTS. Available to customers
who would otherwise qualify for General Secondary Cg3 Time-
of-Use rate with a minimum of 100 kW of curtailable load.
Customers must enter into a contract that specifies a firm
demand level to receive this rate.
Facilities Charge, per day. . . . . . . . . . . . . . . . . . . . . . . . $3.85000
Environmental Control Charge, per kWh . . . . . . . . . . . . . . $.00058
The Additional Meter Charge, On- and Off-Peak Energy Charges,
On-Peak Demand Charge, Customer Demand Charge, Fuel Cost
Adjustment, On-Peak Demand Adjustment and Monthly Minimum
Charges are listed under the General Secondary Demand Time-of-
Use (Cg3) section.
The customer shall receive a curtailable service credit of $.02080
per kWh for on-peak curtailable energy. The curtailable service
credit is determined by the following formula: (A x B) x C
D
A = credit per kWh
B = on-peak curtailable energy
C = on-peak hours in billing period
D = on-peak hours in the billing period minus the actual hours
of capacity curtailment in the billing period
General Secondary Seasonal Curtailable (Cg3S)
THIS RATE CLOSED TO NEW ACCOUNTS. Available to customers
who would otherwise qualify for General Secondary Cg3 Time-
of-Use rate, with a minimum of 100 kW of curtailable demand.
Customers served under this rate must enter into a contract
before the curtailment season begins that specifies a contract
firm demand level.
Facilities Charge, per day . . . . . . . . . . . . . . . . . . . . . . . $3.85000
Environmental Control Charge, per kWh. . . . . . . . . . . . . . . $.00058
The Additional Meter Charge, On- and Off-Peak Energy Charges,
On-Peak Demand Charge, Customer Demand Charge, Fuel Cost
Adjustment, On-Peak Demand Adjustment and Monthly Minimum
Charges are listed under the General Secondary Demand Time-of-
Use (Cg3) section.
Curtailable Service Credits (Available April 1 through Sept. 30)
The customer shall receive a credit of $2.00 per kW for all
curtailable demand during a billing period.
Lighting Rates
Highway Lighting (Ms1)
Rate: The General Secondary Rate (Cg1) applies.
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . . . . . . $.00058
Flashing Lights:
25 watts or less . . . . . . . . . . . . . . . . . . . . . . . . . . $3.06 per flasher
Greater than 25 watts (up to & including 75 watts). . . $3.13 per
flasher
Greater than 75 watts (up to & including 150 watts). . $5.02 per
flasher
Greater than 150 watts. . . . . . . . . . General Secondary Rate Cg1
Standard Area Lighting (Gl1)
THIS RATE CLOSED TO NEW CUSTOMERS AND NEW
INSTALLATIONS.
Monthly charge per lamp
Sodium Sodium Metal halide Metal halide
Lamp size standard flood standard flood
50-watt $9.99** * * *
70-watt $11.57 $13.10** * *
100-watt $13.46 $14.94 * *
150-watt $15.67 $17.19** * *
175-watt * * $25.02 $26.32**
200-watt $18.26 $19.67 * *
250-watt $20.73 $22.06** $26.28 $27.72
400-watt $27.56 $28.73 $30.42 $31.67
1000-watt** * * * $60.34**
*Service not provided.
**This rate is closed to new installations.
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . . . . . . . $.00040
There is an additional monthly charge of $2.80 for each additional
pole and $2.73 for each additional span of circuit installed to serve
a lighting unit.
The Company will no longer install new or additional poles under
this rate. Installations which require new poles shall be served
under the Ms4 rate.
Standard Sodium and Metal Halide Street
Lighting (Ms3)
THIS RATE CLOSED TO NEW CUSTOMERS AND NEW
INSTALLATIONS.
Lamp size Monthly charge per lamp
50-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sodium $10.00
70-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sodium $11.58
100-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sodium $13.46
150-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sodium $15.69
175-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . Metal halide $25.04
200-watt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sodium $18.27
250-watt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sodium $20.74
250-watt . . . . . . . . . . . . . . . . . . . . . . . . . . . Metal halide $26.30
400-watt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Sodium $27.58
400-watt . . . . . . . . . . . . . . . . . . . . . . . . . . . Metal halide $30.44
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . . . . . $.00040
Non-Standard Street and Area Lighting (Ms4)
THIS RATE CLOSED TO NEW CUSTOMERS AND NEW
INSTALLATIONS.
Lamp size Monthly charge per lamp
50-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .$2.28
70-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $3.36
100-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $5.21
150-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $7.38
175-watt. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $8.37
200-watt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $9.77
250-watt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $12.16
400-watt . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $18.79
1000-watt** . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $43.76
**This rate closed to new installations
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . . . . . $.00040
These rates do not include the facilities charge. The facilities
charge can be paid in one of two ways:
Option A: A monthly payment of 1.9% of the estimated
installed cost of the lighting and related facilities.
Option B: A one-time charge equal to the estimated installed
cost of the lighting and related facilities, payable
prior to installation of facilities, plus a monthly
charge equal to 0.5% of the estimated installed cost
of the facilities.
Alley Lighting (AL1)
THIS RATE CLOSED TO NEW CUSTOMERS.
Lamp size and type: Monthly charge per lamp
0-10 watt LED. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
$2.27
>10-20 watt LED. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $2.60
>20-30 watt LED. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $3.00
>30-40 watt LED. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $3.41
>40-50 watt LED. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $3.81
>50-60 watt LED. . . . . . . . . . . . . . . . . . . . . . . . . . . . . $4.20
50-watt HPS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $4.20
70-watt HPS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $5.38
100-watt HPS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $7.10
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . $.00040
Incandescent Street Lighting (Ms2)
Energy Charge, per kWh. . . . . . . . . . . . . . . . . . . . . . . . $.12714
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . $.00040
The annual minimum charge is $150.
Time-of-Use Street Lighting (Cg6)
The Facilities Charge, Energy Charges, Fuel Cost Adjustment and
Environmental Control Charge are listed in the General Secondary
Time-of-Use (Cg6) section.
General Secondary Optional Time-of-Use Street
Lighting (St1)
Facilities Charge, per day:
Single-phase/Three-phase. . . . . . . . . . . . . . . . . . . . $.52602
Additional meter. . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05951
Energy Charge, per kWh:
On-peak energy* . . . . . . . . . . . . . . . . . . . . . . . . . . . $.29104
Off-peak energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05099
Fuel Cost Adjustment, per kWh . . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . $.00040
*The on-peak period is 7 a.m. to 9 p.m.
General Secondary Optional 12-Hour Time-of-
Use Street Lighting (St2)
Facilities Charge, per day:
Single-phase/Three-phase. . . . . . . . . . . . . . . . . . . . $.52602
Additional meter. . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05951
Energy Charge, per kWh:
On-peak energy* . . . . . . . . . . . . . . . . . . . . . . . . . . . $.30055
Off-peak energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . $.05375
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . $.00764
Environmental Control Charge, per kWh. . . . . . . . . . . $.00040
*The on-peak period is 6 a.m. to 6 p.m.
LED Standard and Non-Standard Lighting
Service (LED)
This rate is available to all customers contracting for Standard
or Non-Standard Light Emitting Diode (LED) street or area
lighting service by means of existing 120 volt Company-owned
and maintained Standard or Non-Standard lighting facilities.
Contracting for the illumination of public roadways is limited
to municipalities or other governmental units.
Rate
Each light fixture requires payment of a one-time Installation
Charge, plus monthly Facilities, Source and Energy Charges
which continue until facilities are permanently removed:
Installation and Facilities Charge - Standard Lighting
Fixture
Facilities charge
(per light fixture,
per month) Early removal
charge
Light Installed cost per Installation During After (x months
fixture light fixture range charge per initial initial remaining in
class From To light fixture term* term* initial term)
A $1 $249 $100 $7.73 $3.65 $5.61
B $250 $349 $125 $8.84 $4.22 $6.37
C $350 $449 $150 $10.14 $4.87 $7.28
D $450 $549 $175 $11.43 $5.52 $8.19
E $550 $649 $200 $12.74 $6.17 $9.10
F $650 $749 $225 $14.04 $6.82 $10.00
G $750 $849 $250 $15.34 $7.47 $10.91
H $850 $949 $275 $16.64 $8.12 $11.82
I $950 $1,049 $300 $17.94 $8.77 $12.73
Installation and Facilities Charge - Non-Standard Lighting
Fixture
Facilities charge
(per light fixture, Early
per month) removal
charge
Light Installed cost per Installation During After (x months
fixture light fixture range charge per initial Iinitial remaining in
class From To light fixture term* term* initial term)
A $1 $249 ** $5.17 $3.62 $2.58
B $250 $349 ** $5.65 $4.19 $2.58
C $350 $449 ** $6.19 $4.84 $2.58
D $450 $549 ** $6.74 $5.49 $2.58
E $550 $649 ** $7.28 $6.14 $2.58
F $650 $749 ** $7.82 $6.79 $2.58
G $750 $849 ** $8.36 $7.44 $2.58
H $850 $949 ** $8.91 $8.09 $2.58
I $950 $1,049 ** $9.45 $8.74 $2.58
J $1,050 $1,149 ** $9.99 $9.39 $2.58
K $1,150 $1,249 ** $10.53 $10.04 $2.58
L $1,250 $1,349 ** $11.08 $10.69 $2.58
M $1,350 $1,449 ** $11.62 $11.34 $2.58
N $1,450 $1,549 ** $12.16 $11.99 $2.58
O $1,550 $1,649 ** $12.70 $12.64 $2.58
P $1,650 $1,749 ** $13.25 $13.29 $2.58
Q $1,750 $1,849 ** $13.79 $13.94 $2.58
R $1,850 $1,949 ** $14.33 $14.59 $2.58
S $1,950 $2,049 ** $14.87 $15.24 $2.58
T $2,050 $2,149 ** $15.42 $15.89 $2.58
*Initial term under this rate is 84 billed months.
**Prior to installation of facilities, the customer shall pay the total
estimated installed cost of all Non-Standard lighting related facilities.
Miscellaneous Rates
Electric Vehicle Pilot program (EV-C)
Available to customers served under rate schedules Cg1, Cg2,
Cg3, Cg3S, Cg3C, Cg-6, Cp1, Cp3, Cp3S, CpFN, and Cp4 subject
to availability criteria and subscription limits specified in the EV-C
rate schedule.
Rate: Customer will be charged in accordance with their otherwise
applicable rate schedule for all usage.
Optional Charger Service: Charging equipment may be supplied
and installed either by the customer or by the Company through an
Optional Charger service. Optional Charger service by the Company
is available as a Bundled service option that includes a monthly
charge for the installed cost of charging equipment or as a Pre-Paid
service option to customers electing to pay the Company for the
installed cost of charging equipment:
Service Charger per Month per Port Group A Group B Group C
Bundled option – Single port $27.00 $28.00 $28.00
Bundled option – Dual port $26.00 $26.00 $27.00
Pre-pay option – Single port $4.00 $4.00 $4.00
Pre-pay option – Dual port $2.00 $2.00 $2.00
For more details, please contact us or visit our website.
Municipal Defense Siren (Mg1)
For unmetered siren service only: $3.00 per year or any part of
the year for each 2 horsepower or fraction thereof for each siren
installed. For metered sirens and associated equipment: the
General Secondary Rate schedule (Cg1) excluding the facilities
charge applies.
Fuel Cost Adjustment, per kWh. . . . . . . . . . . . . . . . . . . . . . $.00000
Environmental Control Charge, per kWh. . . . . . . . . . . . . . . . . $.00058
WE-220037-04-JN-GH-1MM