Sec 177
Sec 177
This section specifies the minimum environmental management obligations relating to the
work to be constructed under this Contract. Additional contract specific requirements may be
included in Section 100.
177.A1 INTRODUCTION
Works under the Contract shall be undertaken so that impacts on the environment are
avoided or minimised. The Contractor shall ensure that the environmental objectives and
measures outlined in the relevant State and Federal legislation are complied with.
The Contractor shall prepare a project specific Environmental Management Plan for the
management of activities that impact on the environment in accordance with this
specification.
##(strikethrough the following paragraph where the project is not identified as containing
high environmental risk – seek advice from Operation Services):Work under the Contract
includes activities which VicRoads has assessed as having potentially high environmental risk.
The Contractor shall ensure a strong focus on environmental management is maintained
whilst executing the work under the Contract, including the provision of staff with appropriate
environmental skills and experience to manage these risks.
177.A2 DEFINITIONS
Ancillary Works Area – an area outside the defined Limit of Works where activities are
undertaken that support the Contractor in the delivery of the project. This may include the
establishment of site compounds, borrow areas, temporary sedimentation basins, and
temporary works.
Contaminated Material – the presence of any chemical substance or waste that exists
above the natural background level of the land or water and represents, or potentially
represents an adverse health or environmental impact.
Cultural Heritage Management Plan (CHMP) – an overview of the heritage values of the
project area and an outline of management processes and initiatives to be implemented to
avoid or minimise impacts on those values during the course of the project.
Environmental Improvement Plan (EIP) – a plan prepared for approval of EPA to address
the use of non-potable water and/or contaminated materials. The plan identifies potential risks
to human and animal health, the environment and surrounding land use areas and details
management options to mitigate the risks.
Environmental Incident – an event which results in or has the potential to result in the
environmental requirements in this Contract being breached and occurs at any location where
works under the Contract are performed.
Noise Sensitive Receptors – uses that may be affected by construction noise. During
daytime hours this may include aged care homes, hospitals, schools, kindergartens, libraries
and other noise sensitive community buildings.
Rain Event – when rainfall results in an off-site discharge, and/or when on-site construction
activities are ceased due to rain, and/or rainfall occurs that requires monitoring as defined in
the Rainfall Intensity Chart attached as Attachment A to this Section 177.
Tree Protection Zone - in accordance with AS 4970-2009 the Tree Protection Zone is the
area enclosed by a radial distance from the centre of the trunk that is 12 times trunk diameter
to a maximum of 15 metres. The trunk diameter is measured at 1.4 metres above ground.
Waterway – includes waterways as defined in the Water Act 1989 and any natural collection
of water (other than water collected and contained in a private dam or a natural depression on
private land) whether or not the flow is continuous, as well as tidal and coastal water and
groundwater.
The Contractor shall be responsible for the preparation, implementation and other
arrangements associated with the Environmental Management Plan (EMP). The EMP shall
include, as a minimum:
(b) a schedule of environmental elements that are expected to be affected by the works
under the Contract including an outline of proposed mitigation treatments and proposed
timeframes;
(c) the identification of work activities and an assessment of their potential impacts and
associated risks to on-site and off-site environmental receptors (e.g. community, land
uses, waterways, flora and fauna, cultural heritage, etc.) including times when the
Contractor is not on site, including but not limited to matters covered in this specification;
An EMP shall be prepared for any works undertaken in an ancillary works area.
HP The Contractor shall submit to the Superintendent for review an EMP not less than
two weeks prior to the commencement of work. The EMP shall be submitted
together with the signed ‘Declaration – Environmental Plan Verification’ in
accordance with Clause 177.L1(a).
Control measures identified in the EMP shall be installed prior to works commencing, or at the
programmed timing for their implementation. Control measures shall be maintained in
working order for the duration of the associated works.
177.A4 TRAINING
(a) Prior to commencement of works on-site, the Contractor shall ensure that all personnel
are informed of the environmental issues and specific risks associated with the project
and the required management and mitigation measures to address these risks.
177.A5 PERMITS
The Contractor shall be responsible for obtaining all necessary permits and approvals from the
relevant authorities, other than those already obtained by VicRoads. Copies of all relevant
documentation relating to permits and approvals obtained by the Contractor shall be provided
to the Superintendent within one week of their receipt and prior to any works relating to the
permit commencing. Copies of all permits and approvals will be kept on site.
The Contractor shall be responsible for implementing any conditions identified in any permits
whether obtained by VicRoads or the Contractor. All permits and associated conditions shall
be identified in the EMP.
The Contractor shall engage a suitably experienced and skilled environmental management
professional to prepare the Environmental Management Plan and manage and monitor all
environmental issues and environmental treatments implemented during construction. The
individual shall be full time on site and shall:
##(choose one of the following options and STRIKETHROUGH the option not required
Option 1 – for use where a project is assessed as containing low, medium or high absolute
environmental risk;
Option 2 – for use where a project has been assessed as containing extreme absolute
environmental risk(s) associated with significant environmental issues.)
:##(Option 1 – delete this author note before finalising document):
• have demonstrated competence and suitable experience in environmental management in
a construction environment; and
• be eligible for membership with the Environment Institute of Australia and New Zealand
(EIANZ), Engineers Australia or other appropriate affiliation;
177.B1 WATER
(a) General
The quality of water in waterways shall not be detrimentally impacted by runoff from the
site.
(b) Monitoring
(i) General
Water quality and rainfall shall be monitored for the parameters identified in
Table 177.B1.01 during all stages of construction to ensure that the water quality in
the receiving waterways:
• does not vary between the upstream and downstream limits of the work site
during the construction period (where upstream results become the background
limits). The allowable variation between results shall be no more than twice the
measurement uncertainty of the instrument; or
• is as agreed between the Contractor, the Superintendent and Environment
Protection Authority Victoria (EPA).
The Contractor shall possess equipment on site that is capable of providing
instantaneous monitoring of parameters as required in Table 177.B1.01. All
equipment associated with monitoring shall be maintained and calibrated in
accordance with the manufacturer’s or equipment supplier’s requirements.
*** Table 177.B1.01 Construction Monitoring
Parameter Method
Litter (definition, including solid inert waste) Visual (prevent litter from entering
waterways and drainage systems)
(ii) Dewatering
Water quality monitoring shall be undertaken when dewatering ponded water to
receiving waterways or drainage infrastructure.
The quality of ponded water to be dewatered to receiving waterways shall not
exceed 30 NTU or shall be equal to or better than the water quality in the receiving
waterways if the turbidity in the receiving waterway is less than 30 NTU.
*** The pH of ponded water to be dewatered shall be within the range of
##(strikethrough the pH range that is not applicable, as defined in EPA
Publication 960 – Section 4.4 Dewatering (Figure 37):##6.4 - 7.7: ##6.5 - 8.3:.
(iii) Bypass Pumping
Water quality monitoring shall be undertaken when bypass pumping water around
works that is being undertaken within a waterway.
(iv) Locations
Monitoring shall be carried out:
• in waterways upstream and downstream of the limits of the site;
• at appropriate locations in waterways within the site including immediately
upstream and downstream of each point source (or flow) entering along the length
of waterways within the project site.
Details of all monitoring locations shall be maintained on the scaled drawings
associated with the EMP. Monitoring sites must be accessible during all on-site
activity and in all weather conditions.
Monitoring for dewatering activities will be undertaken:
• at the ponded water at the pump intake; and
• in the receiving waterways immediately upstream and downstream of the
discharge point (within the mixing zone of the waterway and discharged water); or
• at the pump outlet where dewatering occurs into drainage infrastructure.
Monitoring for bypass pumping activities will be undertaken at locations
immediately upstream and downstream of the pumping activity in the waterway.
(v) Timing
Monitoring shall be undertaken:
• immediately prior to work commencing;
*** • ##(edit as appropriate):daily / weekly / other;
• for each rain event as follows -
- within one hour of commencement of rain event during working hours,
- every four hours for periods of continuous rain during working hours, and
- within 12 hours of a rain event, outside working hours;
• immediately prior to the commencement of and then hourly during dewatering
and bypass pumping activities.
177.B2 GROUNDWATER
(a) General
An assessment of the potential impact of the work under the Contract shall deermine the
beneficial uses to be protected as provided for in State Environmental Planning Policy
(Groundwaters of Victoria) and State Environmental Planning Policy (Waters of Victoria)
when groundwater is:
• expected to be encountered during works under the Contract – as part of the
development of the EMP;
• unexpectedly encountered during works under the Contract – immediately after
identification of the presence of groundwater.
The Contractor shall consider the beneficial uses, quality and quantity of groundwater
when determining the ongoing management of groundwater (i.e. reuse, discharge,
aquifer recharge). Such consideration shall be completed prior to the completion of
related design and prior to commencement/continuation of related construction activities.
Groundwater encountered on site shall be assessed for the opportunity for reuse as a
non-potable water source for the duration of the Contract if no higher fit for purpose use
can be identified.
The Contractor shall undertake a visual assessment of the site for groundwater daily
during all excavation activities.
(a) General
Non-potable water sources shall be utilised as the primary source of water for all activities
unless the Contractor can demonstrate to the Superintendent’s satisfaction that the use
of non-potable water is not practicable and feasible.
Where non-potable water is used an Environmental Improvement Plan shall be developed
in accordance with VicRoads guidelines (refer Table 177.M1.01) and shall include the
management of all activities related to the sourcing, transport, storage and use of the
non-potable water.
The Contractor shall meet the following requirements, and include appropriate measures
to meet these requirements in the Environmental Improvement Plan:
(i) the transport, storage and use of non-potable water shall be in accordance with the
Environment Improvement Plan prepared for the contract;
(ii) the use of non-potable water shall not result in any off-site discharge, either as run-
off or airborne.
(b) Monitoring
Monitoring shall be undertaken in accordance with the Environmental Improvement Plan.
(a) General
All work under the Contract shall comply with the following requirements:
• emissions of odorous substances or particulates shall not create or be likely to create
objectionable conditions for the public;
• materials of any type shall not be disposed of through burning;
• material that may create a hazard or nuisance dust shall be covered during transport;
and
• dust generated from road construction activities shall not create a hazard or nuisance
to the public, shall not disperse from the site or across roadways, nor interfere with
crops, stock or any other dust-sensitive receptors.
All work under the Contract shall comply with the following requirements:
• emissions of visible smoke to the atmosphere from construction plant and equipment
shall not be for periods greater than 10 consecutive seconds;
• where practicable all heavy duty diesel engines must be fitted with Selective Catalytic
Reduction (SCR) and diesel particulate filters.
(c) Monitoring
(i) General
Monitoring shall comply with the following requirements:
• insoluble solids from any air quality monitoring station, as measured by a dust
deposit gauge in accordance with the requirements of AS 3580.10.1, shall not
exceed 4 g/m²/month or 2 g/m²/month above the background measurement,
whichever is the lesser;
• directional dust gauges that comply with the equipment requirements of
AS 2724.5 shall be installed alongside each air quality monitoring station.
Directional dust gauges shall be orientated such that one of the collecting
cylinders is directed towards the construction activities;
• directional dust shall be measured as insoluble solids in accordance with
AS 3580.10.1 for each of the four collecting cylinders. Directional dust
gravimetric results shall be expressed as the percentage of the total directional
dust gauge catch for each cylinder;
• dust deposition and directional dust monitoring shall be supplemented with
continuous monitoring using a portable laser light scattering instrument, or
equivalent, to allow changes to dust control measures if the PM10 1 hour average
concentration exceeds 120 µg/m³;
*** • no less than ##(edit as appropriate):one/two/three/other portable laser light
scattering instruments shall be operational daily while undertaking construction
activities;
• portable laser light scattering instrument(s) shall provide a visible and logged
alarm and SMS notification if the 1 hour average criterion of 120 µg/m³ is
exceeded;
• the portable light scattering instrument shall be calibrated and maintained in
accordance with manufacturer’s instructions with calibration and maintenance
records retained and made available to the Superintendent upon request. Daily
records shall include checks of instrument zero and flow rate.
(iii) Results
Results of dust deposition and directional dust monitoring shall be submitted to the
Superintendent within 24 hours of receipt from the laboratory.
Daily results of continuous monitoring including the location(s) of the instrument
shall be made available upon request.
A daily visual assessment of the site for airborne dust and vehicle emissions shall be
undertaken at locations where works are being carried out and records maintained
of these inspections.
Hourly wind speed and wind direction data that correlates to the site location shall
be obtained and maintained in the Contractor’s records and made available to the
Superintendent upon request.
(iv) Timing
Sampling frequency for dust deposition and directional dust is based on the risk of
generation of nuisance dust and is season dependent. Dust deposition and
directional dust sampling frequency shall comply with Table 177.C1.01.
Table 177.C1.01
(a) General
All exposed surfaces shall be free of or treated to minimise erosion.
Erosion and sediment controls shall include:
• minimising the amount of exposed erodible surfaces during construction including the
staging of works;
• prompt temporary and/or permanent progressive revegetation of the site as work
proceeds;
*** • prompt covering of exposed surfaces (including batters and stockpiles) that would
otherwise remain bare for more than ##28: days. Cover may include mulch, erosion
control mat or seeding with sterile grass;
• installation, stabilisation and maintenance of catch and diversion drains that segregate
water runoff from catchments outside of the construction site from water exposed to the
construction site;
• installation and maintenance of erosion and sedimentation controls, established in
accordance with EPA best practice guidelines for the treatment of sediment laden run-
off resulting from construction activities;
• adequately control and route runoff within the construction site to the appropriate
sedimentation controls; and
• where trees are required to be removed more than two months in advance of any
construction works, remove only that part of the tree that is above ground level and
where possible allow the roots to remain intact beneath the ground surface to assist
with erosion control.
The sizing and modelling of temporary sedimentation basins shall be undertaken using
recognised ‘best practice’ modelling techniques or ‘VicRoads Temporary Sedimentation
Basin Sizing Tool’.
Spillways shall be designed for an event having an Average Recurrence Interval of five
years.
An independent hydraulic consultant who has demonstrated competence and suitable
experience in the design of temporary sedimentation basins shall complete and sign a
declaration in accordance with Attachment C to this Section 177. The declaration shall
accompany submission of the sedimentation basin designs to the Superintendent.
HP The Contractor shall submit to the Superintendent the sedimentation designs
and the associated independent verification declarations not less than two
weeks prior to the commencement of construction of the temporary
sedimentation basin.
Sedimentation basins shall be cleaned out whenever the accumulated sediment has
reduced the capacity of the basin by 30% or more, or whenever the sediment has built up
to a point where it is less than 500 mm below the spillway crest, whichever occurs earlier.
The Contractor shall maintain the capacity of the sedimentation basin and shall ensure
compliance with Clause 177.B1(b)(ii) if dewatering to a waterway.
(d) Stockpiles
Where soil is stockpiled on site, such stockpiles shall be located, where possible, to
provide a clearance of not less than 10 m from waterways. Where it is not possible to
provide a clearance of 10 m, the stockpile shall be above the normal high water level of
the waterways and additional protection shall be provided to prevent the stockpiled
material entering the waterways.
(e) Monitoring
The Contractor shall inspect the whole site for instances of soil erosion or scour and the
effectiveness of erosion and sedimentation controls:
• at intervals not more than seven days;
• within one hour of the commencement of any runoff resulting from rain events during
working hours;
• every four hours during periods of continuous rain during working hours;
• within 12 hours of a rain event outside working hours.
Any defects and/or deficiencies in control measures identified by monitoring undertaken
shall be rectified immediately and these control measures shall be cleaned, repaired and
augmented as required to ensure effective control.
(a) General
All work under the Contract shall comply with the following requirements:
• soils or materials shall not be contaminated as a consequence of work under the
Contract;
• materials imported to the site shall be free from contamination;
• contaminated materials shall only be reused on site following approval from the
Superintendent and EPA;
• contaminated materials to be reused on site as part of the Contract shall be temporarily
stored and managed to minimise any impact on the site or surrounding environment;
• the importing, transport and disposal of contaminated soils or materials off-site shall be
undertaken in accordance with relevant legislation and State Environment Protection
Policies;
• disposal of contaminated materials off-site (where required) shall be undertaken in
accordance with relevant legislation and State Environment Protection Policies.
The discovery of contaminated material on the site during works shall be managed in
accordance with VicRoads and EPA Guidelines. In the event that contaminated material is
encountered on the site, the Contractor shall:
(i) notify the Superintendent and where applicable EPA;
(ii) undertake comprehensive sampling and analysis to determine the type levels and
extent of contamination in accordance with current VicRoads and EPA guidelines;
(iii) investigate the opportunity to reuse the contaminated soil and/or material as a fill
material on site;
(iv) ensure that any proposed reuse and/or disposal methods are acceptable to the
Superintendent and EPA.
The use of contaminated material in the Works shall be subject to the approval of the
Superintendent and EPA. The Contractor shall follow procedures and best practice
containment and management techniques in VicRoads and relevant EPA documentation
when such materials are reused on site.
Prior to the use of any contaminated material on the site, the contractor shall verify that
the proposed use is in accordance with legislative requirements. Where directed an EIP
or other documentation shall be prepared in liaison with EPA and the Superintendent.
Where any contaminated material is used in the works, records shall be kept of the
source, type of contamination, volume of contaminated material incorporated, the
locations placed and all investigations undertaken. The location of contaminated material
incorporated into the site shall be identified in the ‘As Constructed’ drawings. Copies of
all documentation including the EIP are to be forwarded to the Superintendent.
(e) Monitoring
The Contractor shall undertake a visual assessment of the site for contaminated soils and
materials at the following intervals:
Wherever possible the locations identified above should be avoided. Where this is not
possible, minimising disturbance may involve:
planning to arrange and minimise construction in such a way so that it limits the
amount of excavation of acid sulfate soil required;
locating aspects of the contract on the part of a land where acid sulfate soils are buried
deepest, so the amount of acid sulfate soil removed is reduced;
using construction methods and site management procedures that do not leave acid
sulfate soils exposed to air without treatment; and/or
aligning and designing linear infrastructure in tidal areas so that natural water flows
(both surface and groundwater) are not blocked.
(a) General
The generation of waste materials shall be managed in accordance with the hierarchy, to
avoid, reuse, recycle or dispose of waste material. The Contractor shall be responsible for
the management of any waste produced in performing the work under the Contract.
All work under the Contract shall comply with the following requirements:
• the nature of wastes generated as a consequence of works under the Contract shall be
identified;
• wastes shall be stored prior to reuse or disposal to minimise any impact on the site or
surrounding environment;
• where approval is granted to incorporate recycled materials into the works, the
Contractor shall maintain appropriate records of the type of material and its location;
• vehicles transporting waste shall be covered and appropriately licensed.
Where recycling facilities are available, the materials shall be managed in accordance
with Table 177.F1.01.
Table 177.F1.01 Resource Management Requirements
Material Waste Management Option
Asbestos EPA licensed landfill
Asphalt Recycle or reuse - not to landfill
Concrete and concrete washings Recycle or reuse - not to landfill
Contaminated soil Recycle or reuse on site if opportunity exists
If removed from site, transported by an EPA licensed
contractor and disposed in accordance with EPA regulations
Felled woody vegetation (except Mulched for reuse, or used for habitat logs
fragments of noxious or environmental
weeds capable of regeneration)
Woody weed fragments capable of Burial on site (deeper than 500 mm and not in fill, pavement
regeneration or other critical areas), composting, or disposal to landfill
Formwork Reuse or dispose to landfill
Plastics (Recycle Nos. 1, 2, 3, 4, 5, 6, 7) Recycling facility - not to landfill
Metal Recycle or reuse - not to landfill
Oil containers and lead acid batteries Recycling facility - not to landfill
Packaging materials Recycle where possible or dispose to landfill
Empty paint tins Recycling facility - not to landfill
Petroleum products from spills (absorbed Recycle or reuse with rehabilitation of contaminated soils if
in spill kit material or contaminated soil) opportunity exists
Transported by an EPA licensed contractor and disposed in
accordance with EPA regulations
Timber (untreated) Recycle - not to landfill
Litter Recycle or dispose to landfill
Office waste Recycle where possible or dispose to landfill
Other waste excluding the above wastes Recycle or reuse if opportunity exists
(b) Monitoring
The Contractor shall monitor the whole site for instances of inappropriate waste
management or disposal at intervals of not more than 7 days.
(a) General
Any leakage or spillage of any fuels or chemicals shall not have a detrimental
environmental impact.
The EMP shall include specific procedures to mitigate the effect on the environment from
fuels and chemicals, including herbicides and pesticides. Such procedures shall include:
• nominated fuel and chemical storage areas that comply with Dangerous Goods
(Storage and Handling) Regulations 2012 and EPA Bunding Guidelines
(EPA Publication 347) including the placarding of compounds and bulk storage
containers;
• nominated points for the refuelling and fluid top up of vehicles and plant which shall be
undertaken in a designated area at least 20 m from any drainage point or waterways;
• provision of readily accessible and maintained spill kits for the purpose of cleaning up
chemical, oil and fuel spillages on the site at all times;
• ensuring that personnel trained in the efficient deployment of the spill kits are readily
available in the event of spillages; and
• a contingency plan that shall address the containment, treatment and disposal of any
spill.
(b) Monitoring
Fuel and chemical storages and equipment fill areas shall be monitored for compliance at
intervals of not more than 7 days.
177.H1 NOISE
The mitigation of construction noise shall include:
• hours of work shall be between 7am and 6pm weekdays and Saturday;
• construction vehicles and equipment shall have appropriate measures fitted and be
effectively maintained to minimise engine noise;
• noisy equipment shall be enclosed where possible;
• establishment of temporary noise attenuation barriers where appropriate;
• scheduling noisy work practices (e.g. pile driving) to minimise likelihood of community
annoyance; and
• use of smart movement alarms for vehicles particularly when working in proximity to noise
sensitive receptors or where working outside normal hours.
177.H2 VIBRATION
(a) General
All work under the Contract shall be undertaken utilising construction methodologies that
will minimise vibration disturbance to the community and avoid damage to buildings
and/or structures.
Vibration generated through construction plant and equipment or blasting (Clause 177.H3
– Blasting) shall not de-stabilise the existing ground condition especially if work is carried
out in the vicinity of any natural slopes or embankment.
Construction methodologies shall be utilised to ensure that vibration does not exceed the
peak vibration criteria in Table 177.H2.01 and/or criteria set by a responsible authority for
a specified structure/asset that falls within its responsibility.
(b) Monitoring
Where directed by the Superintendent, vibration monitoring shall be undertaken to
ensure that construction activities do not pose the potential for damage to surrounding
buildings.
Monitoring shall be undertaken to assess the potential vibration impacts on buildings in
accordance with German Standard DIN 4150, part 3 - 1999 (Effects of Vibration on
Structures).
Peak vibration velocities shall not exceed the criteria in Table 177.H1.01
Table 177.H2.01 Vibration Criteria for Assessing Potential for Damage to
Buildings
Peak Vibration Velocity
Type of Structure
at foundation (mm/s)
Reinforced or framed structures. Industrial and heavy
20
commercial buildings
Unreinforced or light framed structure. Residential or
5
light commercial type buildings
Structures that because of their sensitivity to vibration do
not correspond to those listed above and are of great 3
intrinsic value (e.g. heritage listed buildings).
(c) Results
Vibration monitoring results shall be submitted to the Superintendent within 24 hours
being obtained.
177.H3 BLASTING
(a) General
The contractor shall undertake blast monitoring to ensure that blasting activities do not
pose the potential for damage to surrounding buildings or structures and to minimise
disturbance to the community.
The contractor shall ensure that:
• vibration generated by blasting does not exceed the criteria set out in Table 177.H3.01;
and
• blasting overpressure does not exceed 133 dBL.
(b) Monitoring
Monitoring of blasting activities shall be undertaken in accordance with Section J.3.2 of
AS 2187.2-2006 (Explosives - Storage and use - Use of explosives), at locations relevant
to sensitive buildings agreed with the Superintendent.
The peak component particle velocity of predominant pulse shall not exceed the criteria
in Table 177.H3.01.
Table 177.H3.01 Transient Ground Vibration Criteria for Assessing Potential for
Damage to Buildings
(a) General
All work under the Contract shall comply with the following requirements:
• avoid, minimise and offset (where appropriate) the removal of native vegetation during
construction;
• avoid injury to fauna or damage to protected vegetation or habitat; and
• the discovery of significant flora and fauna sites, species or habitat not previously
identified shall be managed to protect flora and fauna.
The permits and/or approvals identified in Table 177.I1.01 have already been obtained, or
are being obtained by VicRoads. Works under the contract shall comply with all permits
and approvals and associated conditions.
Permit/Approval
Site/Species Issuing Authority
Number
Flora
##:
Fauna
##:
##[insert site detail, e.g. State ##E [insert grid reference e.g. 321900]:
significant species]: ##N [insert grid reference e.g. 5828525]:
##or refer to Volume 3 – Drawings or
flora/fauna reports as required:
##: ##:
All sites nominated in Table 177.I1.02 and any additional existing vegetation and native
fauna habitat identified to be retained, shall be identified as ‘No-Go Zones’ and protected
by temporary fencing and signage. All fencing of ‘No-Go Zones’ shall as a minimum be:
• erected a minimum of 1 m beyond the boundary of the habitat to be protected, or at
the tree protection zone;
• constructed of star picket and paraweb with one wire support;
• signage installed on the temporary fencing at intervals no less than 20 m apart stating
‘No-Go Zone – No Unauthorised Access’; and
• retained in place for the duration of construction activities.
The Contractor shall ensure the No-Go Zone includes the full Tree Protection Zone.
Where encroachment within the Tree Protection Zone is unavoidable the contractor shall:
• engage a suitably qualified arborist (with a minimum qualification of Australian
Qualification Framework Level 5, Diploma of Horticulture (Arboriculture) to assess the
potential impact on the trees;
• the arborist assessment shall include the botanical name, diameter at a height of
1.4 metres, useful life expectancy, the tree location and whether the proposed impact
on any Tree Protection Zone will significantly impact the future health of the tree(s).
The assessment shall recommend whether the tree can be retained with mitigation
measures or whether it should be removed.
Plant, equipment, material or debris shall not be driven, dragged, placed or stored within
the No-Go Zones. Vegetation management activities required to protect vegetation
quality may be undertaken in No-Go Zones.
(g) Monitoring
The Contractor shall undertake monitoring of the condition of flora and fauna habitat sites
and protective measures at the sites at the following intervals:
##: ##:
(a) General
Declared noxious weeds, pests and diseases (also referred to as pathogens) shall not be
introduced to the site, spread through the site, or removed from the site (if present) as a
consequence of work under the Contract.
The Contractor shall prevent the spread of declared noxious weeds, pests and diseases
within the site and off-site through the implementation of controls that shall include the:
• treatment of declared noxious weeds prior to the commencement of any ground
disturbing activities and in response to their identification through monitoring of the
site;
• management of noxious weeds and soil pathogens potential within imported materials;
• provisions for cleaning plant and equipment at the following times -
prior to arrival on site,
prior to departure from site, and
prior to movement within the site from infested to non-infested areas;
• location of cleaning areas;
• use of a vehicle and machinery hygiene log book.
(b) Cinnamon Fungus ##(this clause only applies to projects that are to be undertaken in
high risk infested zone / area - strikethrough all of (b) if this is not relevant):
Plant involved in the initial earthworks shall be cleaned and then disinfected with a
suitable disinfectant applied with a high pressure pump spray prior to leaving the site.
(c) Phylloxera ##(this clause only applies to projects that are to be undertaken in Phylloxera
Infected Zones as identified by the Phylloxera and Grape Industry Board of South
Australia website mapping - strikethrough all of (c) if this is not relevant):
Contractors shall contact the Department of Environment and Primary Industries (DEPI) to
discuss and develop an agreed procedure for the movement and protocol requirements of
plant and equipment within the Phylloxera Infected Zone.
(d) Monitoring
*** The site shall be monitored for the presence of weeds and pests at intervals of not more
than ##(edit as appropriate):weekly/fortnightly/other.
(a) General
Cultural heritage sites and areas of cultural significance shall not be damaged, disturbed
or otherwise adversely impacted unless an appropriate authorisation has been obtained.
*** A Cultural Heritage Management Plan has not been prepared for the works under this
Contract. Works shall comply with any cultural heritage management procedures or
initiatives outlined in an Aboriginal cultural heritage agreement or Aboriginal cultural
heritage permit listed in Table 177.J1.01.
The work under the Contract shall be undertaken to comply with any Historical
Archaeological Heritage permit or consent relevant to the project. Historical
Archaeological Heritage shall be protected from unauthorised disturbance during site
establishment and construction.
The permits and/or approvals identified in Table 177.J1.01 have already been obtained, or
are being obtained by VicRoads. The Contractor shall comply with the terms and
conditions of these permits and approvals.
*** Table 177.J1.01 Heritage Permits and Approvals Obtained by VicRoads
(including Cultural Heritage Management Plans)
Permit/Approval
Site Issuing Authority
Number
##:
##:
Chainage/
Reference
Site AMG grid reference/
Number
location
• the Contractor shall engage a cultural heritage advisor to evaluate the nature, extent
and significance of the cultural heritage;
• the Contractor shall consult with the Superintendent, relevant approval authorities and
the Contractor’s cultural heritage advisor to determine the process to be followed to
manage the discovered cultural heritage and how to proceed with the works. The
Superintendent’s agreement shall be obtained for the proposed process for
management of the discovered cultural heritage prior to implementation;
• the Contractor shall obtain the relevant cultural heritage approvals prior to any
disturbance of cultural heritage discovered during construction and shall comply with
all conditions of any such approvals. Removal of any cultural heritage from the site
shall be undertaken in accordance with statutory requirements and relevant cultural
heritage approval conditions;
• works may recommence in the relevant area if:
the conditions of the cultural heritage approval have been met, or
works can resume without risk to the discovered cultural heritage.
(g) Monitoring
The Contractor shall undertake a visual assessment of the site for cultural heritage during
ground disturbing activities.
The condition of heritage sites and protective measures at the sites shall be monitored at
the following intervals:
PART K - REPORTING
177.K1 REPORTING
(a) General
All environmental monitoring results and all non-conformance reports relating to
environmental performance and current status shall be submitted to the Superintendent
monthly or as agreed by the Superintendent.
The Contractor shall submit to the Superintendent copies of the data/information listed in
Table 177.K1.01. This data/information shall include both the data for the latest reporting
period and a summary of use to date in the Contract.
Table 177.K1.01
Data/Information Frequency
Statutory documents obtained by the Contractor as part of Within one week of receipt by
the project (e.g. permits) the Contractor.
In the event that an environmental incident occurs in relation to the work under the Contract,
the Contractor shall:
• take immediate action to avoid continuance of the incident (which may include cessation of
work), and to minimise the effect of the incident on the environment, as outlined in any
Environmental Management or Environmental Improvement Plans;
• immediately notify the Superintendent and EPA Pollution Watch (Tel. 1300EPAVIC) and
other responsible authorities of the incident (or by 9am the next working day if the incident
occurs outside working hours); and
• submit to the Superintendent for review an incident report within 7 days of the incident.
The incident report shall include photographs where available and cover details of the
incident and the proposed corrective action to avoid a re-occurrence.
PART L - AUDITS
PART M - REFERENCES
177.M1 REFERENCES
Environment protection shall be implemented in accordance with, but not limited to, the
references listed in Table 177.M1.01. The reference shall be the edition or version current at
the time of closing of tenders.
Australian and New Zealand Environment and Conservation Council - Australian Water
Quality Guidelines for Fresh and Marine Waters
Environment Protection Authority Publication 275 – Construction Techniques for Sediment
Pollution Control
Environment Protection Authority Publication 347 – Bunding Guidelines
Environment Protection Authority Publication 441 – A Guide to the Sampling and Analysis of
Waters, Wastewaters, Soils and Wastes
Environment Protection Authority Publication 448 – Classifications of Wastes
Environment Protection Authority Publication 480 – Environmental Guidelines for Major
Construction Sites
Environment Protection Authority Publication 464.2 – Use of Reclaimed Water
Environment Protection Authority Publication 669 – Groundwater Sampling Guidelines
Environment Protection Authority Publication 960 – Doing It Right On Subdivisions
Environment Protection Authority Publication 1178 – Off-site Management and Acceptance
to Landfill
Environment Protection Authority Publicaiton 1254 – Noise Control Guidelines
Environment Protection Authority Publication 1436 to 1442 - Industrial Waste Fact Sheet
Series
State Environment Protection Policy (Air Quality Management)
State Environment Protection Policy (Groundwaters of Victoria)
State Environment Protection Policy (Prevention and Management of Contaminated Land)
State Environment Protection Policy (Waters of Victoria) and schedules
Department of Environment and Primary Industries – Permitted clearing of native
vegetation Biodiversity assessment guidelines
Department of Environment and Primary Industries – Native vegetation gain scoring manual
VICROADS DOCUMENTS
AUSTRALIAN STANDARDS
Austroads Guide to Road Design - Part 6B: Roadside Environment and VicRoads Supplement
to AGRD Part 6B
Best Practice Erosion and Sediment Control – International Erosion Control Association
Engineers Australia - Australian Runoff Quality
Melbourne Water (2005) WSUD Engineering Procedures: Stormwater
VicRoads Carbon Gauge Calculator
VicRoads Temporary Sedimentation Basin Sizing Tool
VicRoads Project Environment Protection Strategy ##(insert name, date and version):
German Standard DIN 4150, part 3 – 1999 Effects of Vibration on Structures
##(insert report names relating to Flora and Fauna studies):
##(insert report names relating to Cultural Heritage studies):
##(insert report names of other relevant pre-construction investigations):
##(insert any other relevant references):
DECLARATION
ENVIRONMENTAL PLAN VERIFICATION
Environmental Plan(s):......................................................................................................................
......................................................................................................................(Document Reference)
I .........................................................................................................................................................
of .......................................................................................................................................................
Signed
On behalf of (Company)
Date
VicRoads
DECLARATION
TEMPORARY SEDIMENTATION BASIN VERIFICATION
...........................................................................................................................................................
...........................................................................................................................................................
...........................................................................................................................................................
...........................................................................................................................................................
I .........................................................................................................................................................
of .......................................................................................................................................................
(a) I have reviewed and assessed the above document(s) for the control of water runoff from
the site associated with a 1:2 ARI (39.35% AEP) over a 6 hour duration and verify that the
proposed temporary sedimentation basin(s) has/have been designed as a
containment/treatment pond (strikethrough as appropriate) and -
(i) will address the requirements of the works (and the catchment) to provide
environmental protection for the catchment, and
(ii) are modelled in accordance with industry recognised ‘best practice’ methodology
for design of sedimentation basins;
(b) in signing this declaration I endorse the above document(s) as adequate and fit for
purpose.
Signed
On behalf of (Company)
Date