Form No3

The document provides workwise details of the contractor B.K Nakrani for the Gutter line Works at Amba Gram Panchayat, with an estimated cost of Rs.2,75,000 and a tender cost of Rs.2,50,000. The work commenced on 18/03/2022 and was completed ahead of schedule on 15/07/2022, with an amount of work done totaling Rs.2,40,000. It includes sections for verifying the correctness of the details and the quality of work completed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
73 views2 pages

Form No3

The document provides workwise details of the contractor B.K Nakrani for the Gutter line Works at Amba Gram Panchayat, with an estimated cost of Rs.2,75,000 and a tender cost of Rs.2,50,000. The work commenced on 18/03/2022 and was completed ahead of schedule on 15/07/2022, with an amount of work done totaling Rs.2,40,000. It includes sections for verifying the correctness of the details and the quality of work completed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd

FORM NO.

3(А)

[Referred to in Rule no. 5.b.(ii)]

Workwise Details of Work Completed or in Progress by The Contractor

1. Name of Contractor : B.K Nakrani

2. Name of Work : Cont of Gutter line Works

At amba Gram Panchayat Ta mandvi Dist surat

3. Agreement No. : 2021-2022

4. Estimate cost of Work put to tender : Rs.2,75,000

5. Tender cost : Rs.2,50,000

6. Date Of Starting the Work :Date:-18/03/2022

7. Date of Complete of Work : Date:-20/07/2022

(As per contract agreement)

8. Actual Date of Completion of Work : 15/07/2022

Date:14 Month: 06 Year: 2022

9. Amount of Work done up to :Rs.2,40,000

Signature of Contractor

10. State Whether the details above :

given by the contractor are correct

if not, State as to what is correct

information

11. State whether the contractor has :

executed the work in progress

satisfactorily as per specification/has

completed the work satisfactorily as

per specification if not given the

correct position of the work.

12. Any other remarks :

Signature of Authorised